WALL FOOTING
T
L = LENGTH
W
FORMULA: VOLUME = L * W * T
CLASS A CONCRETE MIX
Enter Length LT (M) 14.00 M
Enter Width W (M) 0.40 M
Enter Thickness T (M) 0.25 M
TOTAL VOLUME OF CONCRETE: 1.40 CU.M.
# OF CEMENT BAGS 13.00 BAGS
VOL. OF SAND CU.M. 0.70 CU.M.
LT = TOTAL LENGTH/PERIMETER VOL. OF 3/4" GRAVEL CU.M. 1.40 CU.M.
W2
FORMULA: VOLUME = H * W1 * W2
H CLASS A CONCRETE MIX
Enter Height L (M) 5.20 M
VOLUME OF CONCRETE FOR EACH COLUME: 0.64 CU.M.
Number of Columns Units 3.00 Units
TOTAL VOLUME OF CONCRETE: 1.91 CU.M.
# OF CEMENT BAGS 18.00 BAGS
VOL. OF SAND CU.M. 1.00 CU.M.
VOL. OF 3/4" GRAVEL CU.M. 2.00 CU.M.
CONCRETE BEAMS
FORMULA: VOLUME = LT * W * D
CLASS A CONCRETE MIX
EnterTotal Length LT (M) 24.00 M
LT Enter Width W (M) 0.30 M
BEAM DIMENSIONS: Enter Depth D (M) 0.40 M
D TOTAL VOLUME OF CONCRETE: 2.88 CU.M.
# OF CEMENT BAGS 26.00 BAGS
VOL. OF SAND CU.M. 1.50 CU.M.
VOL. OF 3/4" GRAVEL CU.M. 2.90 CU.M.
W
CONCRETE STAIRS