I. Daftar Harga Satuan Upah: No. Pekerja SAT Harga Upah Total Harga Upah (RP) 32,473,208.79
I. Daftar Harga Satuan Upah: No. Pekerja SAT Harga Upah Total Harga Upah (RP) 32,473,208.79
69,230.05
286,069.08
388,087.31
79,022.13
586,413.45
27,506.64
37,316.09
24,699.60
56,385.91
36,355.32
5,516.03
120,000.00
III. TABEL ANALISA HARGA SATUAN
HARGA
HARGA UPAH HARGA BAHAN JUM HARGA
No. SAT URAIAN SAT KOEF SATUAN VOL
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 4 5 6 7 8 9
A PEKERJAAN PERSIAPAN AWAL
3 1M3 Pek. Galian tanah biasa untuk basement 119,250.00 119,250.00 50.40
Tukang Gali 0.9 125000.00 112,500.00 112,500.00 45.36
Mandor 0.045 150000.00 6,750.00 6,750.00 2.27
4 1M3 Pek. Urugan tanah kembali untuk pondasi 57,500.00 57,500.00 0.00
HARGA
HARGA UPAH HARGA BAHAN JUM HARGA
No. SAT URAIAN SAT KOEF SATUAN VOL
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 4 5 6 7 8 9
Pekerja 0.5 100000.00 50,000.00 50,000.00 0.00
Mandor 0.05 150000.00 7,500.00 7,500.00 0.00
5 1M3 Pek. Urugan tanah (Imported soil) 31,500.00 48,000.00 79,500.00 0.00
Tanah Urug 1.2 40000.00 48,000.00 48,000.00 0.00
Pekerja 0.3 100000.00 30,000.00 30,000.00 0.00
Mandor 0.01 150000.00 1,500.00 1,500.00 0.00
6 1M3 Pek. Pas Bata merah tebal 1/2 bata (1:4) 46,050.00 57,200.00 103,250.00 3.35
Bata merah Kelas I bh 70 450.00 31,500.00 31,500.00 234.36
Semen Gresik 50 kg Zak 0.23 65000.00 14,950.00 14,950.00 0.77
Pasir Pasang M3 0.043 250000.00 10,750.00 10,750.00 0.14
Tukang Batu O/H 0.1 125000.00 12,500.00 12,500.00 0.33
Kepala Tukang Batu O/H 0.01 130000.00 1,300.00 1,300.00 0.03
Pekerja O/H 0.3 100000.00 30,000.00 30,000.00 1.00
Mandor O/H 0.015 150000.00 2,250.00 2,250.00 0.05
D PEK. BETON
4 1 M' Pek. Pas. Plint Kramik 10/30 19,050.00 7,765.00 26,815.00 0.00
Plint Keramik 10 / 30 3.5 1500.00 5,250.00 5,250.00 0.00
HARGA
HARGA UPAH HARGA BAHAN JUM HARGA
No. SAT URAIAN SAT KOEF SATUAN VOL
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 4 5 6 7 8 9
Semen Gresik 50 kg 0.031 65000.00 2,015.00 2,015.00 0.00
Pasir Pasang 0.002 250000.00 500.00 500.00 0.00
Tukang Batu 0.05 125000.00 6,250.00 6,250.00 0.00
Kepala Tukang Batu 0.01 130000.00 1,300.00 1,300.00 0.00
Pekerja 0.1 100000.00 10,000.00 10,000.00 0.00
Mandor 0.01 150000.00 1,500.00 1,500.00 0.00
7 1 M' Pek. Pas. Plint PC Polos 15/20 19,050.00 4,265.00 23,315.00 0.00
Tegel Plin PC Polos 15 x 20 3.5 500.00 1,750.00 1,750.00 0.00
Semen Gresik 50 kg 0.031 65000.00 2,015.00 2,015.00 0.00
Pasir Pasang 0.002 250000.00 500.00 500.00 0.00
Tukang Batu 0.05 125000.00 6,250.00 6,250.00 0.00
Kepala Tukang Batu 0.01 130000.00 1,300.00 1,300.00 0.00
Pekerja 0.1 100000.00 10,000.00 10,000.00 0.00
Mandor 0.01 150000.00 1,500.00 1,500.00 0.00
HARGA
HARGA UPAH HARGA BAHAN JUM HARGA
No. SAT URAIAN SAT KOEF SATUAN VOL
(Rp) (Rp) (Rp) (Rp)
1 2 3 4 4 5 6 7 8 9
J PEK. BORONGAN
JUMLAH 8,521,397.93
DIBULATKAN 8,521,000.00
JUMLAH HARGA (BORONGAN)
(Rp.)
200,000.00
400,000.00
5,000,000.00
12,000,000.00
1,000,000.00
(Exclude)
18,600,000.00
18,600,000.00