PLATE 2 Description of Activities
PLATE 2 Description of Activities
PLATE NO. 2
DESCRIPTION OF ACTIVITIES
structures, which will be used during erection of the building. This includes
bunkhouses, fences and temporary work areas for storing machines and
materials.
wooden frames, on the property line to indicate the desired levels and also
foundation. This also includes the laying-out of the floor plan by fastening
strings on the batter board based on the distance indicated on the plan. The
batter boards will provide a stable surface for the attachment of the lay-out
lines. An important part of the installation of the batter board is making sure
the steel reinforcement of the slab, column, footing, wall footing, and tie
beams.
batter board based on the distances indicated by the plan. The locations
where the strings intersect are locations of the columns and footings.
on the footings and columns. This includes the cutting of rebars based on
of the prepared steel bars on the excavated area. A spacer block is first
placed on the ground to make sure that there is at least 75mm clear cover
before the steel bars are placed. Steel bars are installed following the
of the reinforcement bars for the columns right above the reinforcement bars
of the footing. Column ties are also placed. Spacing of column ties are
the location of the columns to hold the reinforcement bars from collapsing.
cement and gravel on the prepared excavated hole for the footing.
15. COMPACTION is the process of making sure that there are none or few
voids on the soil, which was backfilled around the foundation. Compacting it
by layer would result to a more dense soil and is a good support to the slab-
reinforcement for the different structural members. This includes the cutting
of the rebars based on the specified length and then installed on the
the monolithic pouring of concrete on the wall footing and slab-on grade.
mixture of sand, cement and gravel, on the form of the column until it
reaches a height of 0.40 to 0.60 meters below the supposed end of the T-
beam.
preparation of where the plumbing and electrical wirings and pipes will pass
through in the slabs and beams before the concrete pouring to prevent
25. ROOFING is the installation of galvanized iron sheets as roofing. This also
28. CHB WALLING is the process of setting concrete hollow blocks as divisions
of different rooms.
29. DOORS AND WINDOWS is the installation of doors and windows all
33. PAINTING involves the putting of the anti-rust paint for the railings, and
setting aside all materials used in the construction for the removal during