Professional Documents
Culture Documents
Plate 4
Plate 4
No. of footings
indicated on
Fabrication and
plan;
10 Installation of 3600 /ftng 23 ftng 82800.00 100 kg/day
56.844kg/ftng;
rebar for footings
200kg/day/cre
w
Footing
dimensions
indicated on
8 Concreting plan with 6779.24 /cum 4.9374 cum 33471.82 64 cum/day
Footing dimensions:
1.7x1.7,
2.8x2.8 and
2.5x2.5
Fabrication of
10 20.84kg/lm 1313 /lm 73.79 lm 96886.27 200 kg/day
rebar for columns
Installation of
10 20.84kg/lm 1313 /lm 241.5 lm 317089.50 200 kg/day
rebar for columns
Formwork
8 Fabrication of areas = total 525 /col 23 col 12075.00 2 col/day
formworks surface area of
columns
Formwork
Installation of
areas = total
12 formwork for 283 /col 23 col 6509.00 2 col/day
surface area of
columns
columns
Column
13 Concrete pouring dimensions 6779.24 /cum 10.584 cum 71751.48 64 cum/day
for columns indicated on
plan.
Formwork
Stripping of
areas = total
14 formworks for 63.7 /sqm 120.96 sqm 7705.15 14.88 sqm/day
surface area of
columns
columns
Fabrication of
17 formworks for tie 35000 /flr 1 flr 35000.00 0.34 flr/day
beams
Installation of
18 formwork for tie 13608 /flr 1 flr 13608.00 0.34 flr/day
beams
Volume
computed by:
19 Concrete pouring cross-sectional 6779.24 /cum 29.025 cum 196767.44 64 cum/day
for tie beams
area x total
linear meters
Formwork
Stripping of
areas = total
20 formwork for tie 63.7 /sqm 256.55 sqm 16342.24 14.88 sqm/day
surface area of
beams
tie beams
Fabrication of
3.9kg/lm of
21 rebar for wall 122.85 /lm 0 lm 0.00 200 kg/day
wall footing
footings
Installation of
22 rebar for wall 3.9kg/lm of 122.85 /lm 0 lm 0.00 335 kg/day
footings and wall footing
vertical bars
Volume
computed by:
23 Concrete pouring cross-sectional 6779.24 /cum 0 cum 0.00 64 cum/day
for wall footings
area x total
linear meters
Backfill and Backfill=Vol.
compact the soil excavated-
24 excavated from volumes of tie 457.8 /cum 224.29 cum 102679.96 1 cum/day
footings and tie beams and
beams footings
Earthfill for slab
Floor area x
25 on grade 1017 /cum 34.2 cum 34781.40 1 cum/day
thickness
foundation
Base course for
Floor area x
26 slab on grade 2697.8 /cum 34.2 cum 92264.76 1 cum/day
thickness
foundation
Installation of
28 plumbing Cost/CR 6000 /CR 2 CRs 12000.00 2 CR/day
roughing-ins
Installation of
29 electrical Cost/sqm 300 /sqm 342 sqm 102600.00 32 sqm/day
roughing-ins
30 Concrete pouring Volume = floor 6779.24 /cum 34.2 cum 231850.01 64 cum/day
for slab on grade area x 0.1 m
24bf/sqm of
Installation of
6 floor area; 35 /bf 10453 bf 365855.00 40 bf/day
scaffolddings
35/bf costing
Fabrication and
34 Installation of 9.24kg/sqm 582 /sqm 342 sqm 199044.00 335 kg/day
rebar for slab
Fabrication of
formwork for floor
15 beams and slab 35000 /flr 1 flr 35000.00 0.34 flr/day
at the second
floor
Installation of
formwork for floor
36 beams and slab 13608 /flr 1 flr 13608.00 0.34 flr/day
at the second
floor
Installation of
14 plumbing Cost/CR 6000 /CR 4 CRs 24000.00 2 CR/day
roughing-ins
Installation of
14 electrical Cost/sqm 300 /sqm 1039.08 sqm 311724.00 32 sqm/day
roughing-ins
Volume
Concrete pouring
computed by:
39 for floor beam cross-sectional 6779.24 /cum 28.125 cum 190666.13 64 cum/day
and slabs at the
area x total
second floor
linear meters
Stripping of
40 formwork of floor 63.7 /sqm 256.55 sqm 16342.24 14.88 sqm/day
beams
41 Fabricate rebar 7886 /stair 4 stairs 31544.00 2 stairs/day
for stairs
42 Installation rebar 1600 /flr 2 flr 3200.00 2 flr/day
for stairs
Fabrication of
43 formwork for 6300 /stair 4 stairs 25200.00 1 stairs/day
stairs
Installation of
44 formwork for 800 /stair 4 stairs 3200.00 1 stairs/day
stairs
45 Concrete pouring 6779.24 /cum 5.19 cum 35184.26 64 cum/day
for stairs
Stripping of
46 formworks for 800 /stair 4 stairs 3200.00 1 stairs/day
stairs
Fabrication of
47 rebar for columns 20.84kg/lm 1313 /lm 126.9 lm 166619.70 200 kg/day
in 2nd floor
Installation of
48 rebar for columns 20.84kg/lm 1313 /lm 126.9 lm 166619.70 200 kg/day
in 2nd floor
Fabrication of
49 formwork for 525 /col 27 col 14175.00 2 col/day
columns at the
second floor
Installation of
50 formwork for 283 /col 27 col 7641.00 2 col/day
columns at the
second floor
Volume
computed by:
51 Concrete pouring cross-sectional 6779.24 /cum 17.02 cum 115382.66 64 cum/day
for columns
area x total
linear meters
Formwork
Stripping
areas = total
52 formwork for 63.7 /sqm 186.12 sqm 11855.84 14.88 sqm/day
surface area of
columns
tie beams
Installation of
53 scaffoldings for 35 /bf 10453 bf 365855.00 40 bf/day
3rd floor
Fabrication of
56 formwork for 3rd 35000 /flr 1 flr 35000.00 0.34 flr/day
floor beams and
slab
Installation of
57 formwork for 3rd 13608 /flr 1 flr 13608.00 0.34 flr/day
floor beams and
slab
Installation of
58 plumbing Cost/CR 6000 /CR 0 CRs 0.00 2 CR/day
roughing-ins
Installation of
59 electrical Cost/sqm 300 /sqm 342 sqm 102600.00 32 sqm/day
roughing-ins
Volume
Concrete pouring computed by:
60 for 3rd floor cross-sectional 6779.24 /cum 56.199 cum 380986.51 64 cum/day
beams and slab area x total
linear meters
Formwork
61 Stripping of areas = total 13608 /flr 1 flr 13608.00 0.34 flr/day
formworks surface area of
tie beams
Fabrication of
62 rebar for columns 20.84kg/lm 1313 /lm 126.9 lm 166619.70 200 kg/day
in 3rd floor
Installation of
63 rebar for columns 20.84kg/lm 1313 /lm 126.9 lm 166619.70 200 kg/day
in 3rd floor
Fabrication of
64 formwork for 525 /col 27 col 14175.00 2 col/day
columns at the
3rd floor
Installation of
65 formwork for 283 /col 27 col 7641.00 2 col/day
columns at the
3rd floor
Volume
Concrete pouring computed by:
66 for 3rd floor cross-sectional 6779.24 /cum 17.02 cum 115382.66 64 cum/day
columns area x total
linear meters
Formwork
Stripping
67 formwork for 3rd areas = total 63.7 /sqm 120.96 sqm 7705.15 14.88 sqm/day
surface area of
floor columns
tie beams
24bf/sqm of
Installation of
70 floor area; 35 /bf 10453 bf 365855.00 40 bf/day
scaffoldings
35/bf costing
Fabrication of
71 formworks for roof 35000 /flr 1 flr 35000.00 0.34 flr/day
beam
Installation of
72 formworks for roof 13608 /flr 1 flr 13608.00 0.34 flr/day
beam
Volume
computed by:
73 Concrete pouring cross-sectional 6779.24 /cum 16.74 cum 113484.48 64 cum/day
of roof beams
area x total
linear meters
Formwork
Stripping of
74 formworks for roof areas = total 63.7 /sqm 206.1 sqm 13128.57 14.88 sqm/day
surface area of
beams
tie beams
7850kg/cum x
Fabrication and
75 Installation of roof cross-sectional 81.09 /kg 7494.07 kg 607694.14 335 kg/day
area x total
truss members
length
Setting of CHB for
76 interior and 794 /sqm 1276.9 sqm 1013858.60 6 sqm/day
exterior walls
Trusses and
77 struts painted with 300 /sqm 43.57 sqm 13071.00 8 sqm/day
red lead
Installation of
78 Ceiling area 193 /sqm 342 sqm 66006.00 43.2 sqm/day
purlins
Installation of Diagonal area
79 metal sheet of roof 358.68 /sqm 556.2 sqm 199497.82 17.71 sqm/day
roofing considered
Ceiling areas
80 Installation of including 226.11 /sqm 1046.52 sqm 236628.64 43.2 sqm/day
ceiling overhangs and
eaves
Plastering wall
Plastering of
area deducted
exterior and
by openings
84 interior walls, 333.44 /sqm 6129.12 sqm 2043693.77 6 sqm/day
such as
columns and
windows and
beams
doors
Fabricate angle
85 bar for casement 81.09 /kg 0 kg 0.00 335 kg/day
windows
Fabrication and
86 Installation of 1200 /lm 108 lm 129600.00 3 lm/day
steel railings for
stairs
Installation of
87 Cost/CR 10000 /CR 5 CRs 50000.00 1 CR/day
plumbing fixtures
Installation of
88 Cost per unit 1880 /set 42 sets 78960.00 2 set/day
window jambs
Installation of
89 Cost per panel 400 /panel 168 panels 67200.00 4 panel/day
windows
Installation of
90 Cost per unit 1010 /set 45 sets 45450.00 4 set/day
doors jambs
Cost per unit
considered
Installation of
multiplied with
91 doors (finish 4673.9 /door 45 doors 210325.50 2 doors/day
total number
painted)
as indicated in
plan
Painting of
Painting wall
exterior and
area =
92 interior walls, 300 /sqm 6129.12 sqm 1838736.00 8 sqm/day
plastering wall
columns and
area
beams
Installation of
97 black board for 5066 /board 9 boards 45594.00 1 board/day
every room
98 Site cleaning 60 /sqm 6000 sqm 360000.00 1500 sqm/day
Similar with
99 Demobilization 50000 /lot 1 lot 50000.00
mobilization
TOTAL COST 14740711.06
Work Duration Manpower
Survey Team
Electrician
Carpenter
Steelman
Plumber
Painter
Mason
Driver
No. of Units No. of Duration Equipment
personnel/teams (days)
Dumptruck,
One-bagger
2 concrete 2 1
mixer,
backhoe
4 6
135 lm 5 2 5 5
7 2 2 1
2 4 4
72 cum 2 1 2 Vibrator 8 2 4
2644.596 kg 2 7 2 2
23 col 4 3 4 4
23 col 4 3 4 4
120.96 sqm 15 1 30 30
4720 kg 10 5 10 10
1 flr 1 3 2 2
1 flr 1 3 8 8
256.55 sqm 15 2 30 30
34.2 cum 10 4 5
2 CRs 1 1 1 1
342 sqm 4 3 4 4
10453 bf 50 6 30 30
1 flr 2 2 2 2
1 flr 2 2 2 2
2 CRs 1 1 1 1
1039.08 sqm 4 9 4 4
256.55 sqm 20 1 10 10
4 stairs 2 2 2 2
4 stairs 2 2 2 2
4 stairs 2 2 2 2
27 col 4 4 4 4
27 col 4 4 4 4
186.12 sqm 2 7 2 2
10453 bf 50 6 30 30
1 flr 3 1 2 2
1 flr 3 1 8 8
5 CRs 1 3 1 1
342 sqm 4 3 4 4
1 flr 1 3 8 8
27 col 4 4 4 4
27 col 4 4 4 4
17.02 cum 1 1 1 Vibrator 1 4 1 1
120.96 sqm 10 1 10 10
10453 bf 50 6 30 30
1 flr 1 3 2 2
1 flr 1 3 8 8
206.1 sqm 30 1 30 30
7494.07 kg 5 5 5 5
1276.9 sqm 30 8 30 20
43.57 sqm 1 6 2 2
342 sqm 2 4 2 2
556.2 sqm 10 4 5 5
1046.52 sqm 10 3 5 5
124.25 lm 5 3 5 5
72 lm 2 3 2 2
513 sqm 3 4 3 3
3064.56 sqm 30 18 40 15
108 lm 20 2 10 10
5 CRs 2 3 2 2
42 sets 10 3 10 10
167 panels 20 3 10 10
45 sets 10 2 10 10
45 doors 10 3 10 10
3064.56 sqm 20 20 20 20
1 unit 1 10 2 1
17 units 1 9 1 1
63 sqm 20 1 10 10
1026 sqm 10 3 3 3
9 boards 3 3 1 1
6000 sqm 1 4 6
2 Dumptruck 2 1
50000
20520
67200
150000
20000
37311.1
97200
33471.82
96886.27
166619.7
14175
7641
71751.48
7705.15
242726.4
297360
350000
13608
196767.44
16342.24
102679.96
34781.4
92264.76
199044
12000
102600
231850.01
365855
242726.4
242726.4
199044
35000
13608
12000
102600
190666.13
16342.24
31544
3200
252000
3200
35184.26
3200
166619.7
166619.7
14175
7641
115382.66
11855.84
365855
174938.4
174938.4
35000
13608
102600
380986.51
13608
166619.7
166619.7
14175
7641
115382.66
7705.145
195048
195048
365855
35000
13608
113484.48
13128.57
607694.14
1013858.6
13071
66006
199497.82
236628.64
21122.5
28800
23940
2043693.77
129600
50000
78960
67200
45450
210325.5
1838736
35000
13600
50400
71820
45594
360000
50000
14935543.595
Activity Duration Cost
1 Mobilization 2 50000
2 Construction of 3
temporary fence 67200
Construction of
9 catch basins and 9 13600
grease trap
10 Construction of 10 35000
septic tank
Concrete pouring
11 1 33471.82
for footings
Fabrication of
12 formworks for 4 14175
columns
Installation of rebar
13 7 166619.7
for columns
Fabrication of rebar
14 4 242726.4
for tie beams
Installation of
15 formworks for 4 7641
columns
Installation of rebar
16 5 297360
for tie beam
Concrete pouring
17 for columns at 1 71751.48
ground floor
Fabrication of
18 formworks for tie 3 35000
beams
Installation of
20 formworks for tie 3 13608
beams
Fabrication and
21 installation of rebar 4 199044
for slab on grade
Concrete pouring
22 1 196767.44
for tie beams
Installation of
23 plumbing roughing 1 12000
inns
Installation of
24 electrical roughing 3 102600
inns
Fabrication of rebar
26 for floor beam at 4 242726.4
the second floor
Concrete pouring
27 1 231850.01
for slab on grade
Installation of
28 scaffoldings for 2nd 6 365855
floor
Fabrication of
formwork for floor
30 2 35000
beams and slab at
the second floor
Installation of
formwork for floor
31 2 13608
beams and slab at
the second floor
Fabrication of
32 2 25200
formwork for stairs
Stripping of
formworks for
33 1 7705.15
columns at the
ground floor
Stripping of
34 formworks for tie 2 16342.24
beams
Installation of rebar
35 for floor beam at 2 242726.4
the second floor
Fabrication and
installation of rebar
36 for slab at the 1 199044
second floor
37 Installation of 2 3200
formwork for stairs
Fabrication of rebars
38 2 31544
for stairs
Installation of
39 electrical roughing 3 102600
inns
Fabrication of
formwork for
40 columns at the 4 14175
second floor
Installation of rebar
41 1 3200
for stairs
Fabrication of rebar
42 for columns in 2nd 3 166619.7
floor
Concrete pouring
for floor beam and
43 slabs at the second 1 190666.13
floor
Concrete pouring
44 1 35184.26
for stairs
Concrete pouring
45 for columns in the 1 115382.66
2nd floor
Installation of
formworks for
46 4 7641
columns at the
secod floor
Installation of
47 scaffoldings for 3rd 6 365855
floor
Installation of rebar
48 for columns in 2nd 3 166619.7
floor
Fabrication of
49 formwork for 3rd 1 35000
floor beams and slab
Installation of
50 formwork for 3rd 1 13608
floor beams and slab
Installation of
51 electrical roughing 3 102600
inns
Installation of rebar
52 for 3rd floor beams 3 174938.4
and slab
Fabrication of rebar
53 for 3rd floor beams 2 174938.4
and slab
Concrete pouring
54 for 3rd floor beams 1 380986.51
and slab
Fabrication of
formwork for
55 columns at the 3rd 4 14175
floor
Fabrication of rebar
56 for columns in 3rd 7 166619.7
floor
Stripping of
57 formwork of floor 1 16342.24
beams
Installation of
58 formwork for 4 7641
columns at the 3rd
floor
Stripping of
59 2 3200
formworks for stairs
Installation of rebar
60 for columns in 3rd 7 166619.7
floor
Fabrication of
61 formworks for roof 3 35000
beam
Installation of
62 scaffoldings in the 6 365855
3rd floor
Installation of
63 formworks for roof 3 13608
beam
Fabrication of roof
64 beams rebars 4 195048
Concrete pouring
65 for 3rd floor 1 115382.66
columns
Stripping formwork
66 for columnns at the 7 11855.84
2nd floor
Insrallation of roof
67 4 195048
beam rebars
Stripping of
68 formworks of beam 3 13608
and slab in 3rd floor
Installation of
69 wiring, panel board, 4 23940
etc.
Fabrication and
70 installation of roof 5 607694.14
truss members
Concrete pouring of
71 1 113484.48
roof beams
Setting of CHB for
72 interior and exterior 8 1013858.6
walls
73 Installation of 4 66006
purlins
Trusses and sruts
74 painted with red 6 13071
lead
Installation of metal
75 4 199497.82
sheet roofing
Fabrication and
76 installation of steel 2 129600
railings for stairs
Plastering of
exterior and interior
77 18 2043693.77
walls, columns and
beams
Painting of exterior
78 and interior walls, 20 1838736
columns and beams
Installation of
compact fluorescent
81 3 71820
lamps and ceiling
fans
Installtion of
82 3 50000
plumbing fixtures
Installation of
83 3 21122.5
downspout
Stripping formwork
84 for 3rd floor 1 7705.15
columns
Stripping of
85 formworks for roof 1 13128.57
beams
86 Tile setting 1 50400
Installation of
87 3 78960
window jambs
Installation of doors
90 3 210325.5
(finish painted)
Installation of black
91 board for every 3 45594
room
92 Site clearing 4 360000
93 Demobilization 2 50000
14381743.6
NAME: DUASO, CHRYSLER G.
PROJECT TITLE: AS BUILT PLAN STANDARD THREE STOREY NINE(9) CLASSROOM SCHOOL BUILDING
DON VICENTE RAMA MEMORIAL ELEMENTARY SCHOOL, CEBU CITY
51 55 56 1 1 0 1 1 1 102680
41 41 45 4 4 0 4 4 4 34781.4
45 45 49 4 4 0 4 4 4 92264.76
42 46 46 0 0 0 CA 0 0 0 199044
48 42 49 7 1 6 7 7 7 12000
46 44 49 5 3 2 5 5 5 102600
49 47 50 3 3 0 3 3 3 231850
50 56 56 0 0 0 CA 0 0 0 365855
46 50 50 0 0 0 CA 0 0 0 242726.4
56 58 58 0 0 0 CA 0 0 0 242726.4
81 57 82 25 1 24 25 25 25 199044
58 52 60 8 0 8 8 8 8 35000
60 54 62 8 0 8 8 8 8 13608
82 61 85 24 0 24 24 24 24 102600
85 62 86 24 0 24 24 24 24 190666.1
82 74 83 9 0 9 9 9 9 16342.24
58 60 60 0 0 0 CA 0 0 0 31544
60 61 61 0 0 0 CA 0 0 0 3200
62 56 64 8 0 8 8 8 8 252000
64 58 66 8 0 8 8 8 8 3200
86 63 87 24 4 20 24 24 24 35184.26
83 76 85 9 0 9 9 9 9 3200
61 64 64 0 0 0 CA 0 0 0 166619.7
64 67 67 0 0 0 CA 0 0 0 166619.7
66 62 70 8 0 8 8 8 8 14175
71 66 75 9 0 8 9 9 9 7641
87 68 88 20 0 20 20 20 20 115382.7
91 90 98 8 0 8 8 8 8 11855.84
70 68 76 8 0 8 8 8 8 365855
67 69 69 0 0 0 CA 0 0 0 174938.4
69 71 71 0 0 0 CA 0 0 0 174938.4
75 67 76 9 1 8 9 9 9 35000
76 69 77 8 0 8 8 8 8 13608
88 71 91 20 0 20 20 20 20 102600
91 72 92 20 13 7 20 20 20 380986.5
99 93 102 9 9 0 9 9 9 13608
71 78 78 0 0 0 CA 0 0 0 166619.7
78 85 85 0 0 0 CA 0 0 0 166619.7
77 73 81 8 0 8 8 8 8 14175
81 77 85 8 0 8 8 8 8 7641
92 86 93 7 7 0 7 7 7 115382.7
129 124 130 6 0 6 6 6 6 7705.145
85 89 89 0 0 0 CA 0 0 0 195048
89 93 93 0 0 0 CA 0 0 0 195048
85 82 91 9 1 8 9 9 9 365855
85 80 88 8 0 8 8 8 8 35000
88 83 91 8 0 8 8 8 8 13608
93 94 94 0 0 0 CA 0 0 0 113484.5
130 125 131 6 0 6 6 6 6 13128.57
94 98 99 1 0 1 1 1 1 607694.1
94 102 102 0 0 0 CA 0 0 0 1013859
99 104 105 1 0 1 1 1 1 13071
105 108 109 1 0 1 1 1 1 66006
109 112 113 1 0 1 1 1 1 199497.8
123 123 123 3 0 3 3 0 3 236628.6
123 126 126 0 0 0 CA 0 0 0 21122.5
120 123 123 0 0 0 CA 0 0 0 28800
98 94 102 8 4 4 8 8 8 23940
102 120 120 0 0 0 CA 0 0 0 2043694
113 114 115 1 0 1 1 1 1 129600
123 126 126 0 0 0 CA 0 0 0 50000
126 129 129 0 0 0 CA 0 0 0 78960
129 132 132 0 0 0 CA 0 0 0 67200
127 128 129 1 0 1 1 1 1 45450
129 131 132 1 1 0 1 1 1 210325.5
115 134 135 1 1 0 1 1 1 1838736
13 23 23 0 0 0 CA 0 0 0 35000
14 22 23 1 1 0 1 1 1 13600
131 126 132 6 6 0 6 6 6 50400
126 123 129 6 0 6 6 6 6 71820
132 135 135 0 0 0 CA 0 0 0 45594
135 139 139 0 0 0 CA 0 0 0 360000
139 141 141 0 0 0 CA 0 0 0 50000
0 1 2 3 4 5 6 7 8 9 10 11 12
Cash flow
Expenditure 25000 25000 37530 37530 27530 5130 58087.17 58087.17 58087.17 45650.14 21428.57 21428.57
Cumulative Expenditure 25000 50000 87530 125060 152590 157720 215807.17 273894.34 331981.51 377631.65 399060.22 420488.79
Percentage Accomplishment 0.17581567806 0.17581567806 0.26393449591 0.26393449591 0.19360822468 0.03607737714 0.40850540721 0.40850540721 0.40850540721 0.32104041271 0.15069914258 0.15069914258
Cumulative Percentage Accomplishment 0.17581567806 0.35163135612 0.61556585203 0.87950034793 1.07310857261 1.10918594975 1.51769135696 1.92619676417 2.33470217138 2.65574258409 2.80644172666 2.95714086924
Manpower Capability
Carpenter 9 9 5 2 2 2 2 2 2
Laborer, Helper 2 2 15 15 11 6 7 7 7 4 2 2
Steelman 2 2 2 2
Operator(Backhoe, Vibrator) 1 1 3 3 3
Driver 1 1
Plumber
Electrician
Painter
Survey Team 1 1 1 1 1 1
Mason
100
90
80
70
60
50
40
30
20
10
60
50
40
30
20
10
0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79 81 83 85 87 89 91
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Concrete
pouring for
4 5 footings
Construction of Septic Tank
13 13 23 23
21428.57 24451.11 24451.11 24451.11 24451.11 24451.11 5011.11 5011.11 5011.11 5011.11 3500 60818.38 27346.56 27346.56 27346.56
441917.36 466368.47 490819.58 515270.69 539721.8 564172.91 569184.02 574195.13 579206.24 584217.35 587717.35 648535.73 675882.29 703228.85 730575.41
0.15069914258 0.17195553936 0.17195553936 0.17195553936 0.17195553936 0.17195553936 0.0352412681 0.0352412681 0.0352412681 0.0352412681 0.02461419493 0.42771298873 0.19231815956 0.19231815956 0.19231815956
3.10784001182 3.27979555118 3.45175109054 3.6237066299 3.79566216926 3.96761770862 4.00285897672 4.03810024482 4.07334151292 4.10858278102 4.13319697594 4.56090996468 4.75322812424 4.9455462838 5.13786444336
2 4 4 4 4
2 8 8 8 8 8 3 3 3 3 2 14 6 6 6
5 5 5 5 5 2 2 2 2
2
1
2 2 2 2 2 2 2 2 2 1 4
1 1 1 1 1
2
85 87 89 91 93 95 97 99 1 3 5 7 9 1 3 5 7 9 1 3 5 7 9 1 3 5 7 9 1
10 10 10 10 10 11 11 11 11 11 12 12 12 12 12 13 13 13 13 13 14
28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
Fabrication of rebar for tie beams 7 Installation of rebar for tie beams
34 34
Concrete
pouring for
columns at Concre
ground floor pouring fo
beams
Installation of formwork for columns Installation of formwork for tie beams
6 9 11 12
30 30 34 36 39 39 42 42
Base course f
23802.81 23802.81 23802.81 62591.85 62591.85 62591.85 62591.85 142890.15 71138.67 71138.67 68167.35 68167.35 13231.35 13231.35 73802.19
754378.22 778181.03 801983.84 864575.69 927167.54 989759.39 1052351.24 1195241.39 1266380.06 1337518.73 1405686.08 1473853.43 1487084.78 1500316.13 1574118.32
0.1673962872 0.1673962872 0.1673962872 0.44018514195 0.44018514195 0.44018514195 0.44018514195 1.00489314442 0.5002917401 0.5002917401 0.47939555448 0.47939555448 0.09305115088 0.09305115088 0.51902328309
5.30526073056 5.47265701775 5.64005330495 6.0802384469 6.52042358886 6.96060873081 7.40079387277 8.40568701719 8.90597875729 9.40627049738 9.88566605186 10.3650616063 10.4581127572 10.5511639081 11.0701871912
4 4 4 4 3 2 2 8 8 8
2 2 2 9 9 9 9 16 12 12 15 15 13 13 10
2 2 2 5 5 5 5 10 10 10 10 10
1
1
4
1 1 1 1
1 1 1 1
43 44 45 46 47 48 49 50 51 52 53 54 55 56 57
46 46
Fabrication
and
Installation of
Concrete
Concrete rebar for slab
pouring for
pouring for tie at the second
slab on grade
beams floor
Backfill and compact the soil excavated from footings and tie beams
Installation of
Base course for slab on grade foundation Fabrication of formwork Fabrication of
formwork for floor Installation of
for floor beams and slab beams and slab at the formwork for formwork for
at the second floor second floor stairs stairs
18 20 25
52 60 54 62 56 64
Stripping of formworks
for columns at ground Stripping of
floor formwork for tie
26 beams
Installation of electrical roughing-ins
55 64
303794.59 107027.19 72827.19 49761 292531.6 60681.6 60681.6 60681.6 99011.82 99011.82 88315.82 88315.82 101816.97 81746.95 330178.32
1877912.91 1984940.1 2057767.29 2107528.29 2400059.89 2460741.49 2521423.09 2582104.69 2681116.51 2780128.33 2868444.15 2956759.97 3058576.94 3140323.89 3470502.21
2.13647407329 0.75268231923 0.51216647165 0.34995055824 2.05726566433 0.42675106599 0.42675106599 0.42675106599 0.69631321078 0.69631321078 0.62109223107 0.62109223107 0.71604078475 0.57489581775 2.32202100848
13.2066612645 13.9593435837 14.4715100553 14.8214606136 16.8787262779 17.3054773439 17.7322284099 18.1589794759 18.8552926867 19.5516058974 20.1726981285 20.7937903596 21.5098311443 22.0847269621 24.4067479706
1 1 32 32 32 32 62 62 32
17 12 9 5 5 5 62 62 62 62 92 62 44
3 3 3 3 5 5 5 5 12
1
4 4
1 1 1 1 1 1 1 1
1
1 1 1 1
58 59 60 61 62 63 64 65 66 67 68 69 70 71 72
Installation
lation of rebar for Fabricate rebar for Fabrication of rebar Installation of rebar
oor beam at the rebar for stairs Fabrication of rebar for Installation of rebar for for 3rd floor beams for 3rd floor beams
second floor stairs columns in 2nd floor and slab and slab
19 22 23 columns in 2nd floor 29 32 34 38
58 58 60 60 61 61 64 64 67 67 69 69 71 71
Concrete
pouring for Concrete Concrete
floor beam pouring for pouring for 3rd
and slabs at Concrete columns in floor beams
the second pouring for the 2nd floor and slab
floor stairs Installation of electrical
Installation of electrical roughing-ins
21 roughing-ins 24 28 33 35 39
58 82 61 85 62 86 67 87 68 88 71 91
Fabrication of Installation of
formwork for formwork for
3rd floor 3rd floor
beams and beams and
Installation of slab
formwork for Installation of formwork for slab Fabrication of formwork for
Fabrication of formwork for
stairs 27 columns at the second floor 30 columns at the second floor 31 36 37 columns at the 3rd floor
58 66 62 70 66 75 68 76 69 77
122963.2 53515.75 53515.75 40943.75 249749.75 101614.09 66429.83 118425.98 118425.98 151515.73 263827.73 135277.2 96056.55 96056.55 408333.06
3593465.41 3646981.16 3700496.91 3741440.66 3991190.41 4092804.5 4159234.33 4277660.31 4396086.29 4547602.02 4811429.75 4946706.95 5042763.5 5138820.05 5547153.11
0.86475433538 0.37635631493 0.37635631493 0.28794212674 1.75639686568 0.71461400536 0.4671762242 0.83284575895 0.83284575895 1.06555363228 1.85540204965 0.95135410577 0.67552989882 0.67552989882 2.87165415275
25.271502306 25.6478586209 26.0242149358 26.3121570626 28.0685539282 28.7831679336 29.2503441578 30.0831899167 30.9160356757 31.981589308 33.8369913576 34.7883454634 35.4638753622 36.139405261 39.0110594138
2 4 4 4 5 35 34 34 34 32 31 8 4 4 5
2 9 9 9 10 14 10 10 10 8 13 17 13 13 10
10 1 1 1 2 2 2 2 2 2 5 5 5 5 2
1 1 1
4 4 4 4 4 4
1 1 1
1 1 1 1 1 1 1 1 1
1 1 1
73 74 75 76 77 78 79 80 81 82 83 84 85 86 87
Fabrication of rebar for columns in 3rd floor 40 Installation of rebar for columns in 3rd floor 42 Fabrication of roof beam reb
78 78 85 85
Concrete
pouring for 3rd
floor columns
45
85 92
Stripping of
formwork of
floor beams
Stripping of formworks
43 for stairs 47 Installation of scaffoldings in the 3rd floor
74 83 76 85
27346.56 42055.3 27313.06 27313.06 86688.89 96445.31 96445.31 96445.31 89314.64 89314.64 28338.81 25496.5 25496.5 165838.39 50455.69
5574499.67 5616554.97 5643868.03 5671181.09 5757869.98 5854315.29 5950760.6 6047205.91 6136520.55 6225835.19 6254174 6279670.5 6305167 6471005.39 6521461.08
0.19231815956 0.29575924342 0.19208256655 0.19208256655 0.60965063903 0.67826390294 0.67826390294 0.67826390294 0.6281165597 0.6281165597 0.19929628382 0.17930737743 0.17930737743 1.16627955946 0.35483605398
39.2033775733 39.4991368168 39.6912193833 39.8833019499 40.4929525889 41.1712164918 41.8494803948 42.5277442977 43.1558608574 43.7839774171 43.9832737009 44.1625810783 44.3418884558 45.5081680152 45.8630040692
4 14 6 6 30 32 32 32 38 38 8 2 2 3 2
6 16 8 8 36 34 34 34 40 40 10 4 4 11 7
2 2 2 2 2 2 2 2 2 2 2 2 2 5 5
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
88 89 90 91 92 93 94 95 96 97 98 99 100 101 102
Concrete
pouring of roof
beams
51 54 55
Setting of CHB for interior and exterior walls
93 93 94 94 102 102
Stripping of formworks of
columns at the second floor 53 beam and slab in 3rd floor
90 98
50455.69 50455.69 50455.69 59283 59283 59283 241008.3 248271.1 248271.1 248271.1 248271.1 128910.8 128910.8 128910.8 128910.8
6571916.77 6622372.46 6672828.15 6732111.15 6791394.15 6850677.15 7091685.45 7339956.55 7588227.65 7836498.75 8084769.85 8213680.65 8342591.45 8471502.25 8600413.05
0.35483605398 0.35483605398 0.35483605398 0.4169152337 0.4169152337 0.4169152337 1.69492150732 1.74599807158 1.74599807158 1.74599807158 1.74599807158 0.90658158846 0.90658158846 0.90658158846 0.90658158846
46.2178401232 46.5726761772 46.9275122311 47.3444274648 47.7613426985 48.1782579322 49.8731794396 51.6191775111 53.3651755827 55.1111736543 56.8571717259 57.7637533143 58.6703349028 59.5769164912 60.4834980797
2 2 2 8 8 8 1
7 7 7 16 16 16 12 35 35 35 35 32 32 32 32
5 5 5 5 5 5 5 5 5 5 5
3 3 3 3
2 2 2 2
20 20 20 20 20 20 20 20
1 1 1 1 1 1 1 1 1 1 1
103 104 105 106 107 108 109 110 111 112 113 114 115 116 117
115717 115717 130040 130040 130040 130040 163412.96 163412.96 163412.96 163412.96 178338.5 178338.5 205475.3 205475.3 205475.3
8716130.05 8831847.05 8961887.05 9091927.05 9221967.05 9352007.05 9515420.01 9678832.97 9842245.93 10005658.89 10183997.39 10362335.89 10567811.19 10773286.49 10978761.79
0.81379451273 0.81379451273 0.914522831 0.914522831 0.914522831 0.914522831 1.14922241466 1.14922241466 1.14922241466 1.14922241466 1.25418817208 1.25418817208 1.44503116777 1.44503116777 1.44503116777
61.2972925924 62.1110871052 63.0256099362 63.9401327672 64.8546555982 65.7691784292 66.9184008438 68.0676232585 69.2168456731 70.3660680878 71.6202562599 72.874444432 74.3194755997 75.7645067675 77.2095379353
2 2 2 2 5 5 5 5
42 42 42 42 42 42 45 45 45 45 50 50 60 60 60
10 10
2 2 20 20 20
15 15 15 15 15 15 15 15 15 15 15 15 15 15 15
118 119 120 121 122 123 124 125 126 127 128 129 130 131 132
Installation of doors
Installation of gutter 61 Installation of downspout 63 jambs 69 Installation of doors (finish painted)
205475.3 205475.3 205475.3 204353.01 204353.01 204353.01 123349.45 128772.87 166044.3 140981.8 140981.8 188365.3 184445.3 184445.3 114336.8
11184237.09 11389712.39 11595187.69 11799540.7 12003893.71 12208246.72 12331596.17 12460369.04 12626413.34 12767395.14 12908376.94 13096742.24 13281187.54 13465632.84 13579969.64
1.44503116777 1.44503116777 1.44503116777 1.43713852068 1.43713852068 1.43713852068 0.86747068761 0.9056115782 1.16772764771 0.99147243045 0.99147243045 1.32470291771 1.29713501939 1.29713501939 0.80408808077
78.654569103 80.0996002708 81.5446314386 82.9817699593 84.41890848 85.8560470006 86.7235176882 87.6291292664 88.7968569141 89.7883293446 90.7798017751 92.1045046928 93.4016397121 94.6987747315 95.5028628123
7 7 7 15 15 5 20 20 20 20 20 10
60 60 60 30 30 30 37 37 37 40 40 40 40 40 20
3 3 3
20 20 20 20 20 20 20 20 20 20 20 20 20 20 20
15 15 15 10
133 134 135 136 137 138 139 140 141
21 21 1 6 6 6 6 2 2
1 1
20 20
1 1
100
90
80
70
60
50
40
30
20
10
0
NO. Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
1 Mobilization
5 Construction of bunkhouse
73 Installation of purlins
79 Installation of ceiling
80 Installtion of gutter
83 Installation of downspout
86 Tile setting
89 Installation of windows
92 Site clearing
93 Demobilization
41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89
90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138
139 140 141