You are on page 1of 10

The New Texas U-Beam

Bridges: An Aesthetic and


Economical Design Solution
Mary Lou Ralls, P.E. A new precast, prestressed concrete beam
Supervising Design Engineer
Division of Bridges and Structures was recently developed by the Texas
Texas Department of Department of Transportation. Aesthetics and
Transportation economy were primary design considerations
Austin, Texas
for this open-top trapezoidal beam. Two
U-beam bridge projects are currently under
contract, with production of the U-beams due
to begin in the fall of 1993. This paper dis-
cusses the development of the U-beam, in-
cluding design, production and construction
aspects. Cost comparisons with other bridge
systems are also given together with antici-
pated usage of the U-beam.
Luis Ybanez, P.E.
Director of Bridges
Division of Bridges and Structures
Texas Department of uring the 1920s and 1930s, aesthetics was a major
Transportation
Austin , Texas
D design consideration in the construction of bridges in
Texas. This was expressed primarily through railing
treatments and substructure shapes. Many of the ornate
and/or unusual bridges constructed during that period have
been given historical status during recent years.
After World War II, the more basic concerns of economy
and durability, however, took the forefront with the intro-
duction of prestressed concrete in North America. In 1950,
the Walnut Lane Memorial Bridge in Philadelphia, Pennsyl-
vania, was the first major prestressed concrete bridge built
in the United States. The entry of Texas into prestressed
concrete bridge construction occurred in 1952, when two
John J. Panak, P.E. 30 ft (9.1 m) standard slab-and-girder spans were post-ten-
Bridge Design Engineer
sioned together to make a 60ft (18.3 m) prestressed span.
Division of Bridges and Structures
Texas Department of The Federal Aid Highway Act began the interstate high~
Transportation way network in 1956, escalating highway construction and,
Austin, Texas concomitantly, the need for economical and durable pre-

20 PCI JOURNAL
stressed concrete bridges and other
structures. That same year, the first
significant prestressed concrete beam
bridge in Texas was constructed over I
the Corpus Christi Harbor; the 2000 ft ,
I

(610 m) bridge was composed of 40


and 60 ft (12.2 and 18.3 m) specially
shaped beams that were precast at the
jobsite and post-tensioned in place.
During this same period, Texas was
developing standard beam shapes that
, ,' •
''
were suitable for pretensioning or post-
, ,, ''•
tensioning applications. I
I
, _------- ...........----------A.A.- - ------,
THE CHALLENGE
Fig. 1. Comparison of 1-shaped beams with U-shaped beams.
Although the driving forces behind
innovation in bridge design at the
Texas Department of Transportation tion with their substantial economy, shape was developed. The number of
(TxDOT) have remained economy, moved this type of construction to the beams and the number of visual break-
durability, function and safety, today forefront in the early 1960s. lines have been reduced by replacing
aesthetics is again being considered, Extremely good performance has the !-shaped beams with more widely-
albeit with caution since aesthetic de- been obtained from prestressed con- spaced beams having smoother lines,
signs are typically more costly. The crete beams produced in Texas pre- as compared in Fig. 1. The result is the
renewed emphasis toward aesthetics in casting plants. The most common and U-beam, a trapezoidal open-top sec-
bridge design has come from within cost-effective bridge span continues to tion with sloping webs.
the department and from the public. consist of simply supported prestressed
The basic philosophy at the TxDOT (pretensioned) concrete !-shaped Metrication
now is to develop aesthetically pleas- beams, such as the AASHTO Type IV
As shown in Fig. 2, the U-beam was
ing alternatives for the more visible beam [spans to about 120ft (36.6 m)]
developed in metric dimensions, in an-
bridges, but to do so at costs that are and the Texas Type C beam [spans to
ticipation of the FHWA mandate that
competitive with standard designs. · about 90 ft (27.4 m)]. The current av-
all federally funded construction plans
The state system has 33,300 bridges, erage total cost of cast-in-place slab
be specified in metric (SI) units after
and the city and county system has and prestressed concrete !-shaped
September 1996. Depths were main-
14,500 bridges, for a total of 47,800 beam bridges in Texas is $31.67 per sq
tained approximately the same as ex-
bridges in Texas. Of these, almost ft, including substructure. This com-
isting beams, primarily to facilitate
14,400 are "structurally deficient" or pares to an average cost of $41.21 per
widening of existing structures.
"functionally obsolete," and require sq ft for steel bridges.
rehabilitation or replacement at an es- Although the prestressed concrete
timated cost of $5 .3 billion. Such !-shaped beam bridge is both durable Cooperati ve
enormous needs, within limited bud- and economical, the beams are spaced Development Process
gets, require increasingly innovative relatively close together with numer- The development of the U-beam in-
thinking and state-of-the-art engineer- ous visual breaklines along the side volved many people. The original con-
ing practice in the planning, design face of the bridge. To some observers, cept of a Texas open-top trapezoidal
and construction of bridges. this is considered to be unattractive. shape was conceived in the late 1980s
Through the years, the TxDOT has This perception of being unattractive by Robert L. Reed, who retired as
used various types of bridge construc- may be due, in part, to the large num- head of bridge design at the Division
tion: simple pan-form and slab-span ber of prestressed concrete beam of Bridges and Structures in 1985. He
structures , complex post-tensioned bridges in Texas; something common was instrumental in the early develop-
gull wing railroad structures, post-ten- may eventually be considered un- mental stage, and gave the beam its
sioned slabs, segmental, simple and attractive even though still functional. name, the "U-beam." The Division of
continuous trusses, steel curved gird- Bridges and Structures also has a
ers, strutted girders and box girders. highly motivated and innovative group
DEVELOPMENT OF
Over the past couple of years, an aver- of engineers and engineering techni-
age of 500 structures per year have THE U-BEAM cians in-house, and several persons
been let to contract. The serviceability To achieve the desired aesthetics, have contributed significantly to the
and long-term maintenance advan- yet maintain the economy of precast, development of the U-beam.
tages of precast, prestressed (preten- prestressed beams manufactured under In addition, the TxDOT is fortunate
sioned) concrete beams, in combina- controlled plant conditions, a new to hilve an excellent working rela-

September-October 1993 21
2440 (8 . 0 ftl

400 820

44

0
Ill

641

..
I
I
I

Type U5-4A ! Type U5-4B


• •
I
I

220 300 1400

Fig. 2. Cross section of Type U54 beam.

tionshi p with the Precast Concrete to actually see the details and modify Likewise, the Type U40 beam is 1016
Manufacturers Association of Texas them as needed, within design con- mm (40.00 in.) deep and is an aestheti-
(PCMA T), which has members from straints, to simplify the production cally pleasing alternative to the 40 in.
most of the precasting plants in the process. (1016 mm) Texas Type C beam. The
state. Meetings between the TxDOT In addition to the major contribu- AASHTO Type IV beam and, to a
and the PCMAT are usually held tions provided by the PCMAT, good lesser degree, the Texas Type C beam
twice a year, with the agenda consist- input was also received from other constitute most of the prestressed con-
ing of many topics of mutual concern, states, precasters and consultants, and crete beams used in Texas.
all related to getting the best and most from engineers at the TxDOT district The U-beam is larger than any pre-
trouble-free and constructable bridge offices. The Louisiana Department of cast, prestressed concrete beam pro-
at a fair price to both precast produc- Transportation contributed its own duced in Texas, having a bottom
ers and the TxDOT. open-top trapezoidal beam experience, flange width of 1400 mm (4.59 ft), two
Shortly after preliminary details of and this information was invaluable top flange widths of 400 mm (15.75
the U-beam were distributed to the during the developmental stage. in.) each, and web widths of 126 mm
precast producers at one PCMA T (4.96 in.). Sections with two standard
meeting , one of the participating depths have been developed, the U54
Cross Section beam at 1372 mm (54.02 in.) and the
plants took the initiative, at their cost,
to construct a full-scale mock-up of The Type U54 beam shown in U40 beam at 1016 mm (40.00 in.).
the end region reinforcement prior to Fig. 2 is 1372 mm (54.02 in.) deep and Note that the suffix A refers to a
any contract being advertised. This en- is an aesthetic alternative to the 54 in. section with a maximum of two layers
abled the engineers and the precaster (1372 mm) AASHTO Type IV beam. of prestressed strands in a 158 mm

22 PCI JOURNAL
58.00 ft

ft ~I

I
3.00 ft 7 I-shaped beams at 8.67 ft

6. 75 ft 4 U-shoped beams at 14.83 ft

Fig. 3. Comparison of 56 f1 (16.6 m) roadway cross section with AASHTO Type IV beams and U54 beams. Note: 1 f1 = 0.3048 m.

(6.22 in.) bottom flange, and the suffix approximately 115 ft (35 .1 m) may Russell. 3 In essence, the efficiency
B refers to a section with three layers require 28-day concrete strengths factor can be expressed as the ratio of
of prestressed strands in a 208 mm higher than the maximum of 8000 psi the moment of inertia of the section
(8.19 in.) bottom flange. (55 MPa) typically used in Texas. divided by the product of the area and
The overall top flange width of the Longer span lengths may also require the distances from the centroid of the
U54 beam is 2440 mm (8.01 ft). The closer beam spacings, and this could section to the top and bottom fibers.
1372 mm (54.02 in.) depth was se- result in a loss in the aesthetic quality Mathematically, the equation takes the
lected to allow the use of the U54 of the overall structure. form:
beam on widenings and retrofits of ex- Beam spacings in the 13 to 16 ft
isting bridges with 54 in. (1372 mm) (3.96 to 4.88 m) range are preferred.
beams. A comparison of two struc- The maximum span length for the
tures can be seen in Fig . 3, which 54 in. (1372 mm) U-beam is, there-
shows AASHTO Type IV beams and fore, comparable to the 120ft (36.6 m) where
U54 beams for a 56ft (17.1 m) wide preferred maximum length of the 54 in.
roadway . (1372 mm) AASHTO Type IV beam,
p = efficiency factor of section
I = moment of inertia of section
With an emphasis on economics in and the maximum span length of the
A = area of cross section
the development of the U-beam, every 40 in. (1016 m) U-beam is comparable
Yb = distance from centroid of sec-
phase of beam design , beam produc- to the 90ft (27.4 m) preferred maxi-
tion to bottom fiber
tion and bridge construction was ex- mum length of the 40 in. (1016 m)
y 1 = distance from centroid of sec-
amined to develop processes that are Texas Type C beam. The se span
tion to top fiber
simple, yet as similar as possible to lengths are based on designs using
r = radius of gyration of section
existing methods. HS20 loading.
A prime consideration in the devel- = -JTTA
opment of the U-beam was the struc- The higher the efficiency factor, the
Design tural efficiency of the section. Several more efficient the section becomes. A
Although the 54 in. (1372 mm) sim- methods can be used to evaluate the theoretical maximum efficiency factor
ple-span prestressed (pretensioned) section efficiency. The TxDOT de- of one results with thin top and bottom
concrete U-beam has been designed to cided to use the method developed by flanges and webs of negligible thick-
a maximum span length approaching Guyon, ' which has been discussed by ness. As indicated in Table 1, both the
130 ft (39.6 m), lengths greater than Podolny and Muller2 and Rabbat and U54A and the U54B are more effi-

September-October 1993 23
Table 1. Comparison of efficiency and
weight of 1-shaped and U-shaped Type U54A 1 Type U54B
beams (see text and Refs. 1, 2 and 3).
Efficiency Weight
80
+ ..
Beam type factor (kips per linear ft)

AASHTO
Type IV
0.456
~ 0.82

U54A 0.516 ~ 1.07


U54B 0.509 ·~ 1.17
Texas 0.426
·~ 0.52
TypeC ~
U40A 0.505 0.92
U40B 0.485 1.02
Note: l kip per ft = 0.00148 kg!m.

0 0
0.1.()
til
cient than the AASHTO Type IV 0
+-
0
beam. Likewise, both the U40A and
the U40B are more efficient than the
Texas Type C beam.
Beam weight was also a consider-
ation. As shown in Table 1, the !- 50 26 Spa. at 50
shaped beams have lighter sections,
but because they are more closely Fig. 4. Prestressed strand patterns. Note: Dimensions in millimeters;
spaced than U-beams, 1.7 to 2.0 times 1 mm = 0.0394 in.
as many !-shaped beams are typically
required per span. Therefore, the total
weight of a U-beam span is usually quired. Depressed strand arrangements Live Load Distribution
less because the reduced number of for the web strands are not anticipa-
U-beams more than offsets the addi- ted until possibly later in production Highway bridges in Texas are cur-
tional beam weight, particularly with development. rently designed for HS 20 live loads.
the 54 in. (1372 rnm) beams. As indicated in Fig. 4, an optional A significant design concern with the
A secondary benefit of the reduced strand pattern with four or six strands U-beam was appropriate lateral distri-
superstructure dead weight is a reduc- in the top flanges may be used. Use of bution of these load s. Spread box
tion in substructure, with fewer and/or this option allows debonding in the beams are governed by Article 3.28,
smaller columns required. The founda- end region to be minimized and re- "Distribution of Load s for Bending
tion requirements for the total struc- quired only in the top layer of bottom- Moment in Spread Box Girders," in
ture are likewise reduced. In addition flange strands . Strands in the top the 1992 AASHTO Standard Specifi-
to these economic advantages, the flanges may be debonded in the mid- cations for Highway Bridges! Several
cleaner visual lines enhance the ap- dle quarter to a third of the span and of the specification limits were ex-
pearance of the total structure. then cut at midspan so that no force ceeded in the designs for interior U-
Maximum concrete strengths in is applied in the debonded midspan beams. Many designs required fewer
U-beam designs are usually the same region. than four beams or more than 10
as those for !-shaped beams and box The U-beams are typically designed beams, a beam spacing of greater than
beams. These strengths are approxi- to the same debonding criteria as used 11 ft (3.35 m) and/or roadway widths
mately 6000 psi (41 MPa) at release in standard Texas box-beam designs . of less than 32 ft (9.75 m) or greater
and 8000 psi (55 MPa) at 28 days. The The criteria are a minimum of six than 66 ft (20.1 m).
U-beam is stressed with standard bonded strands in the bottom row, a To resolve the concern about ade-
0.5 in. (12 .7 mm) diameter 270 ksi maximum of 75 percent debonded quacy of existing specification guide~
(1862 MPa) low-relaxation strands on strands per row and per section, and a lines; a procedure was developed for
a 50 rnm (1.97 in.) grid, as shown in maximum debonding length of 20 per- the determination of the live load dis-
Fig. 4. cent of the span, not to exceed 15 ft tribution that included evaluation of
A maximum of 74 strands in the (4.57 m). These values are currently five cases:
U54A and U40A beams and 99 being evaluated based on recently • Case 1 used the current AASHTO
strands in the U54B and U40B beams completed research on debonding that distribution for interior beams.
may be placed in the lower flange and was conducted at The University of • Case 2 was the same as Case 1 ex-
webs. Strands are straight and are Texas at Austin by Ned H . Burns, cept that the assumed roadway
debonded in the end regions as re- Ph.D., and others. width was limited to 66 ft (20.1 m),

24 PCI JOURNAL
with a corresponding decrease in producers in Texas generally prefer
number of beams.
• Case 3 was a lower bound limit of
this method, in which the concrete is
initially poured down one web and vi- t
90 percent of the distribution for brated across the bottom flange; the
conventional beams at the same concrete is then poured down the other
spacing. web and across the top flange.
• Case 4 was taken from the Load and Problems occur because buoyancy
Resistance Factor Design (LRFD) forces resulting from the concrete
specifications for prestressed con- under vibration often displace the
crete spread box beams, which is void form upward and sometimes lat-
based on NCHRP Report 12-26/1, erally. In addition, if the mix is not
"Distribution of Wheel Loads on well designed, or if casting proce- Fig. 5. Method for removing form .
Highway Bridges."5 dures are not followed exactly, con-
• Case 5 results from assuming hinges solidation problems may occur in the
the concrete in the bottom flange, with
at interior flanges, and is calculated bottom flange concrete below the void
relatively equal web pouring. Proper
for exterior beams in accordance form. This is of particular concern
consolidation of concrete can thus be
with AASHTO, and for interior since the bottom flange cannot be vi-
assured.
beams with beam spacings greater sually inspected, and, therefore, no re-
than 11.5 ft (3.5 m), in accordance liable means is available for determin-
with the NCHRP report cited. ing whether unintentional voids have THE U-BEAM BRIDGE
The largest live load distribution formed at locations along the length
As shown in Fig. 6, the outside
from these five cases is used in the of the beam.
edge of the exterior U- beam top
design of the U-beams. For interior Although one precast producer uses
flange is embedded in the deck over-
beams, Case 4 (LRFD, spread box) the two-stage monolithic casting
hang, creating a smooth line from
controls most frequently, followed by method for box beams, precasters in
edge of deck to web of beam. Also
Case 1 (AASHTO, spread box). For Texas typically prefer the one-stage
note that, for the 26ft (7.92 m) road-
exterior beams, Case 4 again typically method for beams with internal voids.
way, the number of U-beams per span
controls, followed by Case 5. Case 2 The two-stage method requires casting
is reduced to half the number of
occasionally controls interior beams, the bottom flange, securing the void
!-shaped beams required.
whereas Case 3 does not typically form, placing the top flange reinforce-
control. In general, the new LRFD dis- ment, then vibrating the web concrete
tribution will give the most conserva- into the already-cast bottom flange Precast Concrete Panels
tive distribution for the subject types while the bottom flange concrete is Precast, prestressed concrete panels
of beams. still plastic. In Texas, especially in the were introduced in 1963 as part of the
The procedure for calculating distri- hot summer months, this can be a real composite deck for Texas bridge con-
bution using the previously described challenge! struction. The panel provides approxi-
five cases may appear cumbersome. The inherent problems associated mately half the deck thickness. Texas
The method is believed to be appropri- with the internal voids in closed-top has invested significant time and
ate, however, until more specific box beams were largely responsible money in research on this highly suc-
spread-box studies are performed with for the decision to develop a trape- cessful deck construction method.
higher-level computer models for zoidal beam with an open top, thus In 1976, the bid item "Reinforced
various parameters, including span eliminating the possibility of such Concrete Slab" was introduced, which
lengths, roadway widths , number of problems. Significant effort was made changed the traditional measurement
beams and beam spacings. in the development of the U-beam to from cubic yards of concrete to square
streamline the anticipated production feet of bridge deck. The contractor has
process. Chamfers at the top of the the option of using conventional
Production bottom flange, as shown in Fig. 2, are forms, stay-in-place metal deck forms,
The closed-top box beam, while used to allow a more efficient flow of or precast, prestressed concrete panels.
quite efficient, has historically been concrete, which is especially impor- Precast, prestressed concrete panels
more costly and difficult to consis- tant for the one-stage monolithic cast- are the preferred method in Texas for
tently manufacture than !-shaped ing method. constructing decks on most pre-
prestressed concrete beams, mainly Drafts are provided on all form sur- stressed concrete beam bridges and
due to problems in placing concrete faces except the bottom to facilitate some steel beam bridges, with the pan-
around internal void forms. In the one- form removal. This allows the interior els quickly providing a convenient and
stage monolithic casting method, the form to be lifted up and the side forms safe working surface for the remaining
void form is tied into position prior to moved out, similar to all 1-shaped sec- cast-in-place deck construction.
concrete placement, and is typically of tions. The interior form can be one Although no exact data on precast
polystyrene at a cost similar to an unit or split, as shown in Fig. 5. The concrete panel usage exist, a check
equivalent volume of concrete. Precast split form allows direct vibration of with the largest precast beam produc-

September-October 1993 25
28.0 ft
I, 0 ft 26.0 ft roadway

Nominal face of ral I

Prestressed
concrete
panels

2. 75 ft Type U54 beams


6. 75 ft 14.50 ft

Fig. 6. Typical transverse section of 26ft (7.92 m) roadway. Note: 1 ft = 0.3048 m; 1 in. = 25.4 mm.

concrete panels as the deck-forming


method, with permanent metal deck
forms allowed as an option.

Construction
One goal for U-beam construction
was to minimize changes to usual con-
struction methods. As shown in Fig. 3,
precast concrete panels span between
1-shaped beams, and also between and
over the U-beams. The same applies to
permanent metal deck forms , should
the contractor select that deck-forming
method. There is no difference in deck
construction between a prestressed
concrete 1-shaped beam span and aU-
beam span except for the forming of
the sloping overhang. Even for the
overhang detail, the brackets required
are similar to those required for con-
ventional construction.
To further simplify construction, a
constant minimum composite deck
thickness of 8 in. (203 mm) is used,
with 60 ksi ( 414 MPa) reinforcing
steel. The strength of the deck con-
Fig. 7. Isometric of a typical26 ft (7.92 m) roadway superstructure and preliminary crete has been changed from 3600 to
single-column bent. 4000 psi (25 to 28 MPa) in the re-
cently released TxDOT 1993 Standard
Specifications for Construction of
ers and consultants who prepare shop with these panels. It is anticipated that Highways, Streets and Bridges. 6
drawings indicate that approximately precast concrete panels will continue Neoprene pads provide the bearing
75 percent of all prestressed concrete to be preferred, and, therefore, the at supports. One large pad at one end
beam bridges in Texas are constructed U-beam span details show precast and two smaller pads at the other end

26 PCI JOURNAL
to the first U-beam project, which was
let in March 1993, an estimate of beam
cost was made. Fig. 10 presents beam
cross-sectional area vs. average bid
price for various prestressed concrete
beams; this has been found to be a rea-
sonable method for cost comparison.
After precast producers have amor-
tized the U-beam formwork and pre-
cast bed modifications, it is believed
that the price will approach $60 to $70
per linear foot. Although the price per
foot of U-beams is expected to remain
higher than for 1-shaped beams, bridges
constructed with U-beams should be
competitive with bridges constructed
with 1-shaped beams due to the lower
number of U-beams per span and the
typically reduced superstructure and
Fig. 8. Perspective of a typical 38 ft {11.58 m) roadway superstructure and substructure dead weights.
preliminary two-column bent. The low bid on the first U-beam
project was $40.27 per sq ft, including
substructure. Seven contractors bid on
are used to eliminate the tendency shown in these two figures are in the the project, with U-beam prices rang-
of the beam to rock when placed on initial developmental stage. ing from $86.00 to $132.60 per linear
supports. foot; the low bid went to the contrac-
tor with aU-beam price of $120.00
FINITE-ELEMENT per linear foot. The beams for this pro-
STANDARDS ANALYSES ject are expected to be cast in the fall
To minimize the time required for During the U-beam development of 1993.
design of various U-beam structures process, simplified finite-element The low bid on the second U-beam
and to facilitate uniformity and, there- models of the beam were evaluated project, let in June 1993, was $30.50
fore, economy of bridge construction, under various loads. One typical per sq ft, including substructure. Six
a number of U-beam standard details model is shown in Fig. 9 . Both a contractors bid on the project, with
have been developed. These standards square-end model and a skewed-end U-beam prices ranging from $110.00
are added to the contract plans, there- model were evaluated. Also, a three- to $140 .00 per linear foot ; the low
by also reducing the number of details support model and a four-support bid went to the contractor with a
required on the abutment , bent and model were studied to allow evalua- weighted-average U-beam price of
span drawings for uniquely designed tion of the three-pad design. Hauling $115.15. This project resulted in a
bridges. effects were also evaluated, although second precasting plant's entry into
In addition to detail s specific to the currently no specifications govern U-beam production.
U-beam itself, other standard details the transportation of beams; the only While the first two contracts have
include: (1) bearing build-ups and requirement is that the beams be U-beam prices per linear foot higher
bearing pads, (2) de.ck reinforcement erected with no visible cracking. than estimated, it is believed that, with
at interior bents and in thickened deck Results from the finite-element an- competition and production efficien-
at ends of units, (3) precast concrete alyses showed no unusual behavior. cies, the prices will eventually be
panels and (4) permanent metal deck Even during an assumed severe haul- within the range shown in Fig. 10. The
forms. ing twist, the analyses showed stresses U-beam transportation cost could be a
In conjunction with the U-beam to be comparable to those of typical somewhat higher percentage of the
standards developed to reduce the !-shaped beams. Therefore, construc- total cost per foot than for !-shaped
number of details required on bridge tion methods for U-beam bridges will beams because special transport
drawings, superstructure and substruc- follow those used for standard pre- equipment may be required. 1-shaped
ture standards are being developed for stressed 1-shaped beam bridges. beams can usually be transported with
specific roadway widths and span 5- to 7-axle pole-type rigs, while the
lengths. Fig. 7 is an isometric render- heavier U-beams may require 8- to 10-
ing of the 26ft (7.92 m) roadway at a COST COMPARISONS axle rigs - which may possibly in-
single-column bent, while Fig. 8 is a U-beam bridges are anticipated to be clude additional jeep or dolly units.
perspective of the 38 ft (11.6 m) road- competitive in cost with prestressed The cost per square foot of total
way at a two-column bent. The bents concrete 1-shaped beam bridges. Prior structure, as indicated by the low bids

September-October 1993 27
Fig. 9. Finite-element model used to analyze U-beam .

of $40 .27 for the fir st project and


U TYPES BOX TYPES $30.50 for the second project, can be
<3 forms> - - --.. <2 forms + vo r dl fa vorably compared to conventional
!-Shaped TYPES prestressed concrete !-shaped beam
<2 forms> - --.. bridge construction costs averaging
Estimated $31.67 per sq ft of total structure. The
Eventual
Price Range higher cost on the first project may
for U- Beams ----t-~· ___.___ be the result of difficulty in allocat-
1200 .----.-----.~~;-----+-~L,-----,----,
ing costs for the U-beam spans rela-
U54 (I> tive to the costs of the numerous steel
USO< I> trapezoidal box beam units on that
N 1000 project. The second project had no
c steel beams, and the cost per square
foot of total structure was approxi-
~ 800 r---~~~~r+-~~~~~-r---r--~ mately the same as for conventional
L
oCt prestressed concrete !-shaped beam
(!)
+- bridge construction.
(!)
L
0
c o June '93
0
u ANTICIPATED USAGE
400 1--- - - lf-----+t -- - + - - - + - - e. March ' 93
B < r 5> • Jon '91 - In the past year, construction of pre-
I Jon ' 92
A ( 10) cast, pretensioned concrete !-shaped
beam bridges totaled over 3 million
20 40 60 80 140
sq ft (278700 m2) of bridge deck, rep-
Average Bid Price, Dol Iars per LF resenting approximately 65 percent of
all bridge construction in Texas. It is
Fig. 10. Cost comparison between U-beam types, 1-beams and box girders. anticipated that the majority of Texas

28 PCI JOURNAL
bridge construction will continue with These parameters may become the 2. Podolny, Walter Jr., and Muller, Jean,
this mainstay and that U-beam bridges standard, or they may be expanded in Construction and Design of Prestressed
will be constructed at the more visible years to come. It is anticipated that the Concrete Segm ental Bridges , John
and/or urban locations where aesthetic future may also see post-tensioned ap- Wiley & Sons, Inc. , New York, NY,
1982, p. 159.
structures are appropriate. Local pub- plications with deeper, horizontally
lic input for structure type selections is curved U-beam segments. 3. Rabbat, Basile G., and Russell, Henry
emphasized. The responsibility of the TxDOT is G., "Optimized Sections for Precast
to continually strive for more durable, Prestressed Bridge Girders ," PCI
JOURNAL, V. 27, No. 4, July-August
economical and aesthetic structures,
FUTURE DIRECTIONS 1982, pp. 88-104.
incorporating wherever possible the
use of state-of-the-art design, produc- 4. AASHTO, Standard Specifications for
When production of U-beams be- Highway Bridges, Fifteenth Edition ,
gins in the fall of 1993, some details tion, construction techniques and ma-
American Association of State High-
may be modified due to streamlining terials. The development and imple-
way and Transportation Officials,
of the manufacturing process. In addi- mentation of the Texas U-beam bridge
Washington, D.C., 1992.
tion, variations to the basic design, in- is considered to be a major step to-
ward that goal! 5. Zokaie, Toorak, Osterkamp, Tim A .,
cluding the use of depressed strands, and Irnbsen, Roy A. , " Di stribution of
may be expected with time. Wheel Loads on Highway Bridges,"
The TxDOT is now coordinating a NCHRP Report 12-26/1 , Transporta-
FHW A-sponsored research project REFERENCES tion Research Board, Washington,
with The University of Texas at I. Guyon, Y., Prestressed Concrete, V. 1, D.C., 1991.
Austin; two bridges will be construc- jointly published by Contractors 6. TxDOT, Standard Specifications for
ted with U-beam concrete strengths in Record Ltd., London, Great Britain, Construction of Highways, Streets and
the 12,000 psi (83 MPa) range and and John Wiley & Sons, Inc., New Bridges, Texas Department of Trans-
with 0.6 in. (15 mm) diameter strands. York, NY, 1953, p. 239. portation, Austin, TX, 1993.

September-October 1993 29

You might also like