Professional Documents
Culture Documents
Ammonia Storage Decommissioning PDF
Ammonia Storage Decommissioning PDF
One ammonia tank was decommissioned in 2004 for internal inspection as well as replacement of
insulation blocks. The decommissioning, inspection and recommissioning project duration was 5
months. Based on this experience, the 2nd tank was successfully decommissioned and inspected in the
year 2006 in just 4 months.
This paper describes the methodology followed for the inspection project of the tanks along with
details of decommissioning and recommissioning.
Yusuf Abdulla
Gulf Petrochemical Industries Co.
Kingdom of Bahrain
Yoga Narasimha
Gulf Petrochemical Industries Co.
Kingdom of Bahrain
G
ulf Petrochemical Industries Co. (GPIC)
was formed on 5th December 1979 as an production level of 1,200 MT per day each. In
equal partnership between the 1998, GPIC diversified into the manufacture of
governments of Bahrain, Saudi Arabia and fertilizer with the commissioning of a 1,700 MT
Kuwait with the primary objective of utilising per day single stream Granular Urea plant with
Bahrain’s natural gas for the production of associated Offsite facilities.
petrochemicals.
2.0 Description of the NH3 tanks
GPIC’s first project was its grassroot
petrochemical complex at Sitra Island on the The GPIC complex has two ammonia storage
north-east coast of Bahrain. A site of 60 hectare tanks (T-7101A and B) each of 20,000 MT
was successfully reclaimed from the sea to capacity for storage of liquid ammonia at near
construct the ammonia and methanol plants atmospheric pressure. Basic engineering for the
(with an original capacity of 1000 MT per day ammonia tanks was done by UHDE GmbH and
BA SEINSULATION
BASE IN SULA TION D ETAFOR
DETAIL IL FOR A MMONI
AMMONIA TANKA TA NK
DDETAIL
ETA I AL-
A
N OTES:
NOTES -
AAS
SPEPER
R SN ASNAMPROGETTI’
MPROG ETTI
'S SPECI
FI STI
CA SPECS.
ONS
The ammonia storage facility has three screw of the storage tanks and the refrigeration system
type compressors for maintaining the tank has been satisfactory due to the stable operation
pressure. Three high capacity ammonia pumps of the tanks between 40 and 50 mbarg pressure.
are available for export to ships. A separate The base heaters of the tanks have been
vapour return line has been provided to handle operational throughout and an effective
vapours from the liquid loading line as well as preventive maintenance schedule has been in
from ships. A common flare system is provided force.
for both the tanks. In 1995, both the tanks showed signs of
deterioration of the roof and shell vapour seals.
3.0 Operation and Maintenance The insulation was found saturated with water at
History some locations on T-7101B. Complete renewal
of the vapour sealing was carried out for both
the tanks T-7101A and B. Again in 2002, the
The ammonia storage tanks have been in
vapour sealing system for both the tanks showed
operation since the year 1985. The performance
deterioration and was renewed.
Roof thickness 5 mm
Bottom insulation 50 mm sand screed layer + 2 layers of foamed glass 100 mm and 200 mm insulation blocks
Base heating elements 46 elements divided into two zones (2 thermocouples in each zone for measurement)
The stairway platform supports on the top for A similar icing phenomenon was observed in
both the tanks were found to be corroded and tank T-7101A. To determine the failure
these were renewed. To ascertain the condition mechanism of the concrete insulation blocks in
of the tank foundations, the concrete based the foundations of tanks T-7101A and B,
insulation blocks below tank T-7101B were specialists from UHDE and Motherwell Bridge
inspected in September 2002. This inspection were invited to site for inspection.
revealed severe icing and varying degrees of The icing and deterioration phenomenon were
deterioration on the outer concrete insulation reviewed. Core samples were collected from a
blocks (refer to Fig. 2). depth of approximately 400 mm from the
insulation blocks of T-7101B for analysis and
compared to design specifications. The
laboratory results of the core sample are shown
in Table-2.
4.0 The Reasons for the Tank The complete list of activities was sequenced in
Inspection line with the decommissioning and
recommissioning operations. Following
Based on analysis of the insulation block core maximum reduction of the ammonia level in the
samples and site inspection findings and tank, three options were considered for removal
recommendations, replacement of the damaged of the liquefied ammonia below the pump
bottom insulation blocks was planned. suction.
Ø Review and finalise proposals for the 5.2 Project Team Formation:
replacement of insulation blocks.
Ø Firm up inspection scope based on A dedicated project team was formed in year
EFMA guidelines. 2003. The procedures for decommissioning and
Ø Finalise decommissioning and recommissioning were prepared and reviewed
recommissioning procedures for review by UHDE. P&I diagrams for both
by UHDE. decommissioning and recommissioning
20
10
-20
-30
-40
Time
During heating of the tank, the pressure was After completing the heating operation, purging
maintained at 60 mbarg and vapours were was started by admitting nitrogen at tank floor
routed to the refrigeration system. The heating level at a rate of flow of 600 Nm3/hr. The tank
took 240 hours (refer to Chart 1). pressure was maintained at 60 mbarg. Nitrogen
N2 Purging
NH3 Concentration (%)
100
90
80
70
60
NH3 analysis
50
40
30
20
10
0
9-May-04 11-May-04 13-May-04 15-May-04 17-May-04 19-May-04 21-May-04
Because of high inert levels, it was decided to confirming the purge gas analysis, nitrogen was
divert the vapours to the flare. Steam to the closed and the tank was depressurised. The
nitrogen jacket heater was isolated when the mercury content in the vapour was found to be
tank base temperature reached 20 oC. This was 20 micro gram/m3.
necessary in order to prevent the tank
temperature exceeding ambient temperature. 7.5 Air purging:
However, the temperatures stabilised at 40 oC
which is a typical ambient temperature likely to After depressurising the tank, blinds were
prevail in the Arabian Gulf during the summer installed at all tank flanges. The blinds were
months. fabricated of stainless steel material and
thickness was chosen to withstand the design
The vapours were analysed for ammonia content line pressure. Stainless steel material was
at several points and after 9 days of purging, the preferred as it was considered suitable to
concentration at the top of the tank was 1.58 % withstand against cold ammonia which is likely
ammonia. One of the tank’s safety valves was to be present should any tank side valves pass.
removed and a temporary vent pipe was The 24”(600mm) liquid line was removed and
installed to facilitate local venting. After an air-driven reaction fan was fitted in the
Figure-9 : Cold Cutting the Diaphragm Plate After removing the oil, the surface still had a lot
of oil residue, puddles as well as an oil coating
The ammonia content in the annular space was over the wall plates at the bottom remained. It
12 ppm and mercury was 5 micro gram/m3 was decided to clean the floor plates including
maximum. The inner tank manway cover was the tank wall surfaces up to the first course weld
opened using full Personal Protective joint using a high pressure hydrojet. While
Equipment (PPE). The same cold cutting hydrojet cleaning, the oily water was removed
technique was adopted for removing inner tank continuously using the vacuum truck (refer to
manway diaphragm plate. Figure-11).
Roof External:
General: 100% leak test
Nozzles 29 No. (roof & 100% Vacuum Box test
shell) 100%NDT Random UT Thickness
Metallurgical Replication Scan
/ hardness etc. –Need (4-6 points / plate)
basis Internal*:
* Rope Access Annular Rings Welding* 100% NDT of nozzle
random NDT of welds welds & shell to roof
joint
8.2 Preparations for inspection: of the annular space. A fixed scaffolding tower
was installed covering the required EFMA
Mobile scaffolding was erected for the internal scope of 10% T joints up to the top of the inner
tank shell inspection of the first and second tank (refer to Figure-12).
course weld joints. For the annular shell first
course weld joints, a small wooden structure Rope access methods were planned for the
was suitably arranged in line with the curvature internal roof surface and annular space between
3) Outer Tank:
Top PI
O2 concentration %
4 Top vent
Outer shell
0
6-Aug-04 11-Aug-04 16-Aug-04 21-Aug-04 26-Aug-04 31-Aug-04
9.3 Water addition to the tank: was connected to the suction of the refrigeration
compressors and arrangements were made to
Based on UHDE’s recommendation, water was start cooling down operations.
added to avoid direct impingement of liquefied
ammonia droplets on the bottom plate during 9.5 Tank cooling down:
the cooling down period. These may create
localised stress and possible cracks. The pool of To facilitate cooling down, liquid ammonia was
water on the bottom plate ensured a uniform introduced from the top of the tank. It was
cooling effect over the entire bottom plate. In envisaged to utilise the loading line as liquid
accordance with the dimensional calculations a buffer from where the liquid ammonia was
volume of 20 m3 of demineralised water was introduced to the central distributor at the top of
introduced to the tank for this purpose. the tank, using the cool down line. The total
expected cooling down time was 54 hours,
9.4 Ammonia-Nitrogen exchange: based on a 1 oC/hr cooling rate, however for
safety reasons the cooling period was doubled
It was planned to add ammonia vapour to the using a cooling rate of 0.5 oC/hr. Cooling was
top of the tank and to withdraw the ammonia- closely monitored using the bottom plate and
nitrogen vapours from the bottom, followed by shell skin temperatures. The tank bottom plate
flaring. This exchange operation was completed temperature reached -31 oC after 7 days (refer to
in 5 days. Subsequently the tank vapour outlet Chart-4).
35
30
TE-71116
25
TE-71117
20 TE-71118
TE-71119
15 TE-71120
TE-71121
10 TE-71122
TE-71123
5 TE-71124
TE-71125
0
TE-71126
8-Sep 9-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep 15-Sep
TE-71127
-5
0 HRS 10 HRS 34 HRS 58 HRS 82 HRS 106 HRS 134 HRS TE-71129
HRS TE-71130
-10
TE-71131
-15
-20
-25
-30
-35
TEMP. DEG. C
2) Decommissioning method Dry method with hot vapour addition. Dry method with hot vapour addition.
3) Jobs carried out - Outer row insulation blocks replacement. - Outer row insulation blocks replacement.
- Roof insulation renewal. - 6”& 24”liquid O/L bellows change.
- 6”& 24”liquid O/L bellows change. - Enraf level monitor modifications.
- Enraf level monitor modifications.
(e) Metallurgical Study - Linear indications of shell cleat areas revealed - All linear indications were due to fabrication
defects due to Hydrogen crack/lack of fusion. defects and no evidence of cracks due to
- Fabrication defects (removed by grinding). fatigue or SCC.
(e) N2 purging 15 15
(g) Inspection 20 15
(h) Recommissioning 45 30
12.0 Improvements