Bill of Quantities for the Construction of Foundations Annexed to the Main Design for

Pešter Development Centre in Sjenica

No. DESCRIPTION Unit No. of Unit Price Total


Units
1 PREPARATORY WORKS
1.01 Mark structure, clear the terrain including removing
hummus and making a 20 cm layer of gravel on the
terrain around the structure and taking excess ground
and debris to the landfill. Calculation by m2 as per
description.
m2
1.02 Machine excavation of ground for continuous footings,
category III wide excavation in wet soil and terrain
levelling according to design. Calculation by m3 of
excavated natural ground. Take measurements on site.

m3
1.03 Backfill and compact soil in 20 cm layer, including
wetting around the foundations and across the terrain,
using vibro compactors, to achieve the necessary
compactness. Calculation by m3 of loose ground
(+20%). Take measurements on site.
m3
1.04 Load, transport and unload excess ground to landfill up
to 10 km away. Calculation by m3 of transported loose
ground (+20%). Take measurements on site.

1.05 Procure, transport, fill and spread tampon layers of


gravel (natural gravel) under the floor slab and
continuous footings. Calculation by m3 of gravel
purchased, filled and spread to necessary
compressibility MS40.
m3
1.06 Make continuous footings using reinforced concrete
MB 30, reinforced using static calculations and
reinforcement details. Calculation by m3 of set with
plating.
m3
1.07 Make reinforced concrete monolith floor slab MB 30 -
ground slab, according to static calculations,
reinforcement details and regulations for reinforcement
concrete works. Calculation by m2 of slab made
according to description with plating.
d=10cm m2
1.08 Make reinforced concrete foundation walls - using
reinforced concrete MB 30 with smooth plating,
according to static calculations, reinforcement details
and regulations for reinforcement concrete works .
Calculation by m2 of wall with plating. m2

1.09 Make hydro insulation type Condor. Calculation by m2


of insulation in the base, according to description and
details given by the designer.
m2
PREPARATORY WORKS TOTAL 1: