DEMAND NO.

16
Assets-Acquisitions, Construction and Replacement
B- New Works
Railway Southern Railway Plan Head : 36 - Other Electrical

WP NO. Particulars of Work Cost


(thousands Rs.)
0 PGT Division: Shifting of Neutral sections for running of 12/16 car MEMU rake & 24372
Conversion of existing IOL type Neutral section to PTFE type at MNY/SP.

Allocation Cost Outlay Department Cost


(In Rs. Thousands) (In Rs. Thousands) (In Rs. Thousands)
RRSK 24372 0 Electrical (TRD) 24372

TOTAL : 24372 0 TOTAL : 24372

Division Palghat State Kerala,Tamil Nadu Station/Section MDKI-UAA

Gauge : Route Class Quantity


Rail Type Sleeper Type Priority Rank

Justification
JUSTIFICATION

As per RDSO’s final speed certificate for running of 8/12/16 car MEMU stock, CESE/MAS has circulated draft
JSC no. ELEC/MEMU/01/1 dl. 15.07.19 for running of 8/12/16 car MEMU on all the BG sections of Southern
Railway and requested OHE compliance certificate for processing sanction.
In connection with same CEDE/SR has advised division to initiate proposal for necessary OHE modification work
since the current OHE arrangement as per ACTM Vol.II, Part-lI, Appendix-I, para 16.5., PTFE type short neutral
section is only having a clearance of 400 m after the stop signal and 200 m before the stop signal. This 200 m
distance is adequate for running up to 9 car EMU/MEMU rakes only where the total length of 9 car MEMU is
191m. 12/16 car MEMUs are having total length of 266/355 m and hence minimum distance between neutral
sections and next stop signal should be 266/355 m for running 12/16 car MEMU. To enable running 12/16 car
MEMU, 6 neutral sections out of 30 in the electrified sections of Palakkad division are proposed to shift to get an
adequate clearance from nearest stop signal.

As per extant Railway board policy, the OHE to be made fit for running the trains at 160 Kmph in main lines. In
this connection, all the IOL type Neutral Sections are to be converted into PTFE type short neutral sections. In
PGT division, only one IOL type Neutral Section is available, which is located at MNY/SP. As a part of Railway
board policy as mentioned above, the said Neutral Section is now proposed to be converted as Short Neutral
Section by providing PTFE type Neutral Section Assembly.

As such, this proposal for " PGT Division: Shifting of Neutral sections for running of 12/16 car MEMU rake &
Conversion of existing IOL type Neutral section to PTFE type at MNY/SP " has been framed at a cost of Rs. 2.44
crores for consideration in the LAW sanction for the year 2020-21.

FA & CAO's Comments

Railway's Comments
Break Up Cost: (Figures in Rs.)

Store
Quantity
Dept. Desription Unit Rate Cash Total
Purchase Stock

Electrical Preparation of Designs & Drawings 10 TKM 23500 0 0 0 235000


(TRD)

Electrical Foundation Concrete for OHE 120 cum 10000 0 0 0 1200000


(TRD) structure.

Electrical Supply & Erection of OHE structures 16 Tonne 138000 0 0 0 2208000


(TRD) incuding SPS

Electrical Provision of Guy Rod arrangements 24 Each 16200 0 0 0 388800


(TRD)

Electrical Supply & Erection of single bracket 40 Each 36000 0 0 0 1440000


(TRD) assembly for Conventional type OHE.

Electrical Supply of PTFE type Neutral Section 8 Each 954030 0 0 0 7632240


(TRD) Assembly

Electrical Erection of PTFE type Neutral Section 8 Each 25000 0 0 0 200000


(TRD) Assembly

Electrical Supply of 107 Sq.mm Hard Drawn 2 MT 665000 0 0 0 1330000


(TRD) Copper Contact wire.

Electrical Supply of 65 sqmm cadmium copper 2 MT 546300 0 0 0 1092600


(TRD) catenary wire

Electrical Supply and erection of OHE (excluding 2 Km 109800 0 0 0 219600


(TRD) supply of copper contact wire &
catenary wire)
Electrical Supply and erection of 25kV feeder 1 Km 1478285.5 0 0 0 1478285.5
(TRD)

Electrical Provision of regulating equipment for 18 Each 111200 0 0 0 2001600


(TRD) conventional type OHE

Electrical OHE termination arrangements for 24 Each 11400 0 0 0 273600


(TRD) conventional OHE

Electrical Provision for Traction bonding 3 TKM 90000 0 0 0 270000


(TRD) arrangements

Electrical Provision for Earthing Arrangements 8 Each 6600 0 0 0 52800


(TRD)

Electrical Dismantlement of OHE mast / 25 Each 3000 0 0 0 75000


(TRD) structure by cutting

Electrical Tools & Plants @ 5% 1 LS 1004876 0 0 0 1004876


(TRD)

Electrical Environmental Charges@1% 1 LS 211024 0 0 0 211024


(TRD)

Electrical Security related works @ 0.25% 1 LS 52756 0 0 0 52756


(TRD)

Electrical Provision for Sports @ 0.5% 1 LS 105512 0 0 0 105512


(TRD)

TOTAL: 21471693.5

Additional Charges Amount


Contingency 422048.03 Rs. 24371796.54
Grand Total :
D&G Charges 2478055.01
24372 (In thousands of
TOTAL: 2900103.04