You are on page 1of 1

Construction of 4/6 laning Pavement from km

132.375 to km 153.058 (length 20.683km) on


Daboka Dimapur section (Dimapur Bypass) on NH-
36 & NH-39 on EPC basis under Phase -A of
SARDP-NE in the State of Nagaland

EPC CONTRACTOR Consultant Client

National Highways & Infrastructure


M/S Simplex Infrastructures Limited
Development Corporation Limited

FREE SWELL INDEX OF SOIL


(As per IS : 2720 Part - 40)

Sample No. : Date of Sampling :

Location of Sampling : Sampled By :

Source Of Material : Date of Testing :

Dry Wt. of Soil : Tested By :

OBSERVATION TABLE

Determination No. 1 2 Remarks

Volume of Soil in Water after Specified Period of


Submergence=Vd

Volume of Soil in Kerosene = Vk

Free Swell Index, ((Vd-Vk)/ VK) x 100

Average

EPC Representative Engineer Representative