You are on page 1of 16

Project :- Four-laning of Ambala - Kaithal Section of NH-65 from Km 0.000 (Ambala) to Km 50.

860 (Pehowa) with paved shoulder


(length 50.860 km) in the State of Haryana under NHDP Phase-III on EPC Basis.

ANNEXURE -"B"

LIST OF LAB EQUIPMENTS

Sl.No Sub. NO. Description Quantity Due Date of Remark


Calibration

1 (A) FOR SOIL

(i) Liquid limit device with casagrande and ASTM grooving tools as per IS :2720 (Part-5) 1 Set 1-Aug-17

(ii) Liquid limit device ( cone penetrometer ) and plastic limit device as per IS :2720 (Part-5) 1 Set 1-Aug-17

Compaction Apparatus ( Proctor Mould ) 100mm int. dia as per IS:2720 (Part-7) complete with collar, base plate
(iii) and hammer (2.6kg 2 Set 1-Aug-17

Modified (Heavy) Compaction Apparatus ( Proctor Mould ) 150mm int. dia 127.3mm ht. as per IS:2720 (Part-8)
(iv) complete with collar, base plate and hammer (4.89X457mm fall) 2 Set 1-Aug-17

100mm dia Sand Pouring Cylinder with conical funnel and tap and complete as per IS 2720 (Part-28) 1980
(v) including modified equipment 2 Set 1-Feb-17

150mm dia Sand Pouring Cylinder with conical funnel and tap and complete as per IS 2720 (Part-28) 1980
(vi) including modified equipment 2 Set 1-Feb-17

200mm dia Sand Pouring Cylinder with conical funnel and tap and complete as per IS 2720 (Part-28) 1980
(vii) including modified equipment 2 Set 1-Feb-17

(viii) Speedy Moisture Meter complete with chemicals 4 Set 1-Aug-17

Lab CBR testing equipment for cunducting CBR testing load frame with 5 ton capacity, electrically operated with
(ix) speed control as per IS 2720 (Part-16) with all accessories. 1 Set 2-Aug-17

(a) CBR mould 150mm Dia - 175 ht. 45 Nos 2-Aug-17

(b) Tripod stand for holding dial gauge holder 3 Nos 2-Aug-17

(c) CBR plunger with settlement dial gauge holder 1 Nos 2-Aug-17

(d) Surcharge weight 147mm dia 2.5 kg wt 45 Nos 2-Aug-17

(e) Perforated Plate (Brass) 45 Nos 2-Aug-17

(f) Moisture Container (Small) 100 Nos

(f) Moisture Container (Big) 100 Nos

(g) Proving Ring - 50KN 2 Nos 18-Jul-17

(g) Proving Ring - 50KN 2 Nos 18-Jul-17

(g) Proving Ring - 50KN 1 Nos 18-Jul-17

(g) Dial Indicator - 25mm*0.01 1 Nos 18-Jul-17

2 (B) For Aggregate

(i) Aggregate Impact Value Test Appratus as per IS 2386 (Part-4) 1963 1 Set 2-Aug-17

(ii) Loss Abrasion Test Appratus as per IS 2386 (Part-4) 1963 1 Set 2-Aug-17

EPC Contractor Representative Authority's Engineer Representative


Project :- Four-laning of Ambala - Kaithal Section of NH-65 from Km 0.000 (Ambala) to Km 50.860 (Pehowa) with paved shoulder
(length 50.860 km) in the State of Haryana under NHDP Phase-III on EPC Basis.

ANNEXURE -"B"

LIST OF LAB EQUIPMENTS

Sl.No Sub. NO. Description Quantity Due Date of Remark


Calibration

(iii) 3 ltr, 15 ltr, 30 ltr capacity cylinder for checking bulk density of aggregate with tamping rod 1 Set 2-Feb-17

(iv) Flakiness and Elongation Gauge 2 Set 1-Aug-17

(v) Riffle Box as per ASTM C-136 1 Set 2-Aug-17

(vi) Wire Basket for bulk density test 1 Set 2-Feb-17

(vii) Sand Equivalent Appratus 1 Set 1-Aug-17

3 (C) For Bitumen and Bituminous Mixes

Constant Temperature Bath for accmodating bitumen test specimen electrically operated and thermostatically
(i) controlled 50 ltr capacity temp. range ambient 80 ͦC 1 Set 2-Aug-17

Oven-Electrically Operated thermostically controlled


(ii) ( from 0 ͦC to 220 ͦC ) 1 Nos 18-Jul-17

(iii) Penetrometer automatic type, adjustable weight arrangement and needles as per IS 1203-1978 1 Set 2-Aug-17

Electrically operated solvent extraction or centrifuge type apparatus complete (AASHTO T-164) with extraction
(iv) thimbles with stocks of solvent and filter paper. 2 Set 2-Aug-17

(v) Marshal Stability test apparatus complete with all accessories. 1 Set 2-Aug-17

(vi) Acclerated Curing water bath 1 Nos 2-Aug-17

(vii) Ring and Ball Apparatus as per 1205-1978 1 Set 2-Aug-17

(viii) Core Cutting Machine with 100mm & 150mm dia. Diamond Cutting Edge Bit 1 Set 2-Aug-17

(ix) Standard tar viscometer 1 Set 2-Aug-17

(x) Saybolt Viscometer 1 Set 2-Aug-17

(xi) Vaccum Pump and 2ltr. Capacity Glass flask 1 Set 2-Aug-17

(xii) Hot Plate 3 Nos 2-Aug-17

(xiii) Asphalt Mixer 1 Nos

4 (D) For Cement, Concrete and Materials

(i) Vicat Needle Apparatus for Setting time with plunger as per IS 269-1967 1 Nos 2-Aug-17

(ii) Soundness testing apparatus for cement, Le Chatlier moulds 2 Set 2-Aug-17

(iii) High Frequency mortor cube vibrator for cement testing 1 Set 2-Aug-17

(iv) Slump Cone with Rod 6 Set 2-Feb-17

EPC Contractor Representative Authority's Engineer Representative


Project :- Four-laning of Ambala - Kaithal Section of NH-65 from Km 0.000 (Ambala) to Km 50.860 (Pehowa) with paved shoulder
(length 50.860 km) in the State of Haryana under NHDP Phase-III on EPC Basis.

ANNEXURE -"B"

LIST OF LAB EQUIPMENTS

Sl.No Sub. NO. Description Quantity Due Date of Remark


Calibration

(v) Vibrating (DLC) Hammer (AIMIL TYPE) 1 Set 2-Feb-17

(vi) Compression Testing Machine 2000KN capacity 1 Nos 1-Aug-17

(vii) Concrete Cubes Moulds (150X150X150)mm 150 Nos 2-Feb-17

(viii) Concrete Cubes Moulds (100X100X100)mm 15 Nos 2-Feb-17

(ix) Concrete Cubes Moulds (70.6X70.6X70.6)mm 12 Nos 2-Feb-17

(x) Concrete Cubes Moulds (50X50X50)mm 12 Nos 2-Feb-17

(xi) Concrete Beam Moulds (150X150X700)mm 30 Nos 2-Feb-17

(xii) Flexural Testing Machine 1 Set 1-Aug-17

5 (E) General

1 Rain Gauge with rain measuring cylinder 1 Nos 2-Aug-17

2 Weight Balance

(i) 50kg capacity semi-self indicating Electronic Balance - Accuracy 5.0 gm 3 Nos 18-Jul-17

(ii) 30kg capacity semi-self indicating Electronic Balance - Accuracy 1.0 gm 3 Nos 18-Jul-17

(iii) 5kg capacity semi-self indicating Electronic Balance - Accuracy 0.1 gm 2 Nos 18-Jul-17

(iv) 600gm capacity semi-self indicating Electronic Balance - Accuracy 0.01 gm 1 Nos 18-Jul-17

(v) Platform Balance 250 kg Capacity 1 Nos 2-Aug-17

(vi) Dial gauge of 0.25mm 4 Nos 2-Aug-17

(vii) Spacer Disc 2 Nos 2-Feb-17

3 Enamel Trays

(i) 240mm X 180mm X 50mm 6 Nos 2-Feb-17

(ii) 180mm X 120mm X 40mm 6 Nos 2-Feb-17

(iii) 120mm X 100mm X 40mm 6 Nos 2-Feb-17

(iv) Circular plates of 250mm dia 15 Nos 2-Feb-17

4 Sieve as per IS-460-1962

EPC Contractor Representative Authority's Engineer Representative


Project :- Four-laning of Ambala - Kaithal Section of NH-65 from Km 0.000 (Ambala) to Km 50.860 (Pehowa) with paved shoulder
(length 50.860 km) in the State of Haryana under NHDP Phase-III on EPC Basis.

ANNEXURE -"B"

LIST OF LAB EQUIPMENTS

Sl.No Sub. NO. Description Quantity Due Date of Remark


Calibration

Set of IS Sieves 450mm internal dia. 75mm, 63mm, 50mm, 45mm, 40mm, 37.5mm, 31.5mm, 26.5mm, 25mm,
(i) 22.4mm, 20mm, 19mm, 16mm, 13.2mm, 12.5mm, 11.2mm, 10mm, 9.5mm, 6.3mm, 5.6mm, 4.75mm, 2.36mm 1 Set 2-Aug-17
complete with lid and pan

Set of IS Sieves 200mm internal dia. (brass frame and steel or brass wire cloth mesh) 4.75mm, 2.8mm, 2.36mm,
(ii) 2.0mm, 1.40mm, 1.0mm, 1.18mm, 900micron, 850micron, 710micron, 600micron, 425micron, 355micron, 1 Set 18-Jul-17
300micron, 180micron, 150micron, 90micron, 75micron, 45micron complete with lid and pan

5 Thermometer

(i) Glass Thermometer range 0 to 300 ͦC 3 Nos 2-Feb-17

(ii) Digital Thermometer range -50 to +300 ͦC 3 Nos 2-Feb-17

(iii) Digital Hygrometer range -50 ͦC to +100 ͦC (for Max. & Min. Temprature & Humidity Recording) 2 Nos 2-Feb-17

6 (F) Glasswares

(i) Glass Beaker 250ml capacity, Borosil 4 Nos 2-Aug-17

(ii) Glass Beaker 500ml capacity, Borosil 2 Nos 2-Aug-17

(iii) Glass Beaker 1000ml capacity, Borosil 1 Nos 2-Aug-17

(iv) Glass Measuring Cylinder, 100ml Capacity Borosil 40 Nos 2-Aug-17

(v) Glass Measuring Cylinder, 250ml Capacity Borosil 6 Nos 2-Aug-17

(vi) Glass Measuring Cylinder, 500ml Capacity Borosil 4 Nos 2-Aug-17

(vii) Glass Measuring Cylinder, 1000ml Capacity Borosil 2 Nos 2-Aug-17

(viii) Glass Pycknometer 1000ml. Capacity Borosil 3 Nos 2-Aug-17

(ix) Glass Pycknometer 500ml. Capacity Borosil 3 Nos 2-Aug-17

(x) Sp. Gravity Bottle 50ml capacity Borosil 1 Nos 2-Aug-17

(xi) Gmm Flask 2000ml Capacity Borosil 1 Nos 2-Aug-17

(xii) Sampling Pipettes fitted with pressure and suction inlets, 10ml capacity 2 Nos 2-Aug-17

(xiii) Grain Size Analysis Pipette Method, 10ml capacity complete with sedimentation tube and stand 1 Nos 2-Aug-17

EPC Contractor Representative Authority's Engineer Representative


ANNEXURE - "C" -MPR FOR QUALITY CONTROL

QUALITY ASSURANCE & QUALITY CONTROL TEST REPORT WITNESSED BY AUTHORITY'S ENGINEER FOR UP TO THE MONTH OF 11 JANUARY 2016
TESTS CONDUCTED DURING CURRENT TOTAL TESTS CONDUCTED BY AE TOTAL TESTS CONDUCTED BY AE UP
NO. OF TEST TOTAL TEST UPTO PREVIOUS MONTH MONTH TOTAL TESTS UPTO THIS MONTH DURING CURRENT MONTH TO THIS MONTH
Sl. No. DESCRIPTION FREQUENCY OF TEST REQUIRED IN REMARK
CURRENT MONTH
TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED

1.0 TESTS ON BORROW AREAS FOR EMBANKMENT AND SUBGRADE/FLY ASH

1.1 FSI 1 test / 1500 mᶟ 234 234 0 0 0 0 234 234 0 0 0 0 234 234 0

1.2 GSA 1 test / 1500 mᶟ 234 234 0 0 0 0 234 234 0 0 0 0 234 234 0

1.3 LL / PL / PI 1 test / 1500 mᶟ 375 375 0 0 0 0 375 375 0 0 0 0 375 375 0

1.4 MDD / OMC 1 test / 1500 mᶟ 375 375 0 0 0 0 375 375 0 0 0 0 375 375 0

1.5 CBR Test 1 test / 3000 mᶟ 181 181 0 0 0 0 181 181 0 0 0 0 181 181 0

1.6 FDD (Emb. Layer) 1 set / 3000 m² 4805 4782 23 2430 2424 6 7235 7206 29 2430 2424 6 7235 7206 29

1.7 FDD (Sub. Layer) 1 test / 2000 m² 3044 3027 17 2180 2174 6 5224 5201 23 2180 2174 6 5224 5201 23

2.0 TESTS ON OGL SAMPLES (MCW&SR)

2.1 FSI 1 test / 250m 208 208 0 0 0 0 208 208 0 0 0 0 208 208 0

2.2 GSA 1 test / 250m 208 208 0 0 0 0 208 208 0 0 0 0 208 208 0

2.3 LL / PL / PI 1 test / 250m 206 206 0 0 0 0 206 206 0 0 0 0 206 206 0

2.4 MDD / OMC 1 test / 250m 206 206 0 0 0 0 206 206 0 0 0 0 206 206 0

2.5 CBR Test As Required 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

2.6 FDD (OGL) Min. 6 Pit 742 726 16 72 72 0 814 798 16 72 72 0 814 798 16

3.0 TESTS ON EXCAVATED SOIL

3.1 FSI 1 test / 1500 mᶟ 14 14 0 0 0 0 14 14 0 0 0 0 14 14 0

3.2 GSA 1 test / 1500 mᶟ 14 14 0 0 0 0 14 14 0 0 0 0 14 14 0

3.3 LL / PL / PI 1 test / 1500 mᶟ 14 14 0 0 0 0 14 14 0 0 0 0 14 14 0

3.4 MDD / OMC 1 test / 1500 mᶟ 14 14 0 0 0 0 14 14 0 0 0 0 14 14 0

3.5 CBR Test As Required 7 7 0 0 0 0 7 7 0 0 0 0 7 7 0

4.0 TEST ON GRANULAR SUB BASE COURSE (GSB)

4.1 GRADATION 1 test / 400 mᶟ 170 170 0 114 114 0 284 284 0 114 114 0 284 284 0

4.2 LL / PL / PI 1 test / 400 mᶟ 170 170 0 114 114 0 284 284 0 114 114 0 284 284 0

4.3 MDD / OMC 1 tset / source 12 12 0 0 0 0 12 12 0 0 0 0 12 12 0

4.4 CBR Test 1 tset / source 12 12 0 0 0 0 12 12 0 0 0 0 12 12 0

4.5 AIV As Required 15 15 0 0 0 0 15 15 0 0 0 0 15 15 0

4.6 FDD (GSB) 1 test / 1000 m² 396 396 0 312 312 0 708 708 0 312 312 0 708 708 0

5.0 TEST ON AGGREGATE BASE COURSE (WMM)

5.1 Mix Aggregate Gradation 1 test / 200 mᶟ 170 170 0 104 104 0 274 274 0 104 104 0 274 274 0

5.2 Plasticity Index 1 test / 200 mᶟ 144 144 0 104 104 0 248 248 0 104 104 0 248 248 0

5.3 AIV 1 test / 1000 mᶟ 45 45 0 35 35 0 80 80 0 35 35 0 80 80 0

5.4 MDD / OMC 1 tset / source 6 6 0 0 0 0 6 6 0 0 0 0 6 6 0

5.5 Water Absorption 1 tset / source 6 6 0 0 0 0 6 6 0 0 0 0 6 6 0

5.6 FI & EI 1 test / 500 mᶟ 77 77 0 58 58 0 135 135 0 58 58 0 135 135 0

EPC Contractor Representative Authority's Engineer Representative


ANNEXURE - "C" -MPR FOR QUALITY CONTROL

QUALITY ASSURANCE & QUALITY CONTROL TEST REPORT WITNESSED BY AUTHORITY'S ENGINEER FOR UP TO THE MONTH OF 11 JANUARY 2016
TESTS CONDUCTED DURING CURRENT TOTAL TESTS CONDUCTED BY AE TOTAL TESTS CONDUCTED BY AE UP
NO. OF TEST TOTAL TEST UPTO PREVIOUS MONTH MONTH TOTAL TESTS UPTO THIS MONTH DURING CURRENT MONTH TO THIS MONTH
Sl. No. DESCRIPTION FREQUENCY OF TEST REQUIRED IN REMARK
CURRENT MONTH
TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED

5.7 FDD (WMM) 1 test of 3 test / 1000 mᶟ 678 670 8 548 548 0 1226 1218 8 548 548 0 1226 1218 8

5.8 FDD (DLC) 1 test of 3 test / 2000 mᶟ 310 310 0 310 310 0 620 620 0 310 310 0 620 620 0

5.9 FDD (SHOULDER) 1 test / 2000 m² 234 234 0 234 234 0 468 468 0 234 234 0 468 468 0

5.10 FDD (MEDIAN) 1 test / 2000 m² 151 151 0 151 151 0 302 302 0 151 151 0 302 302 0

5.11 FDD (BACKFILLING) MIn. 3 Pit 24 24 0 24 24 0 48 48 0 24 24 0 48 48 0

6.0 FINE AGGREGATE (SAND FOR CONCRETE)

6.1 Sieve Analysis / Gradation On Daily Basis 0 0 0 32 32 0 0 0 0 32 32 0 39 39 0

6.2 Specific Gravity (SSD) As Required 0 0 0 0 0 0 0 0 0 0 0 0 34 34 0

6.3 Water Absorption / Moisture Content On Daily Basis 0 0 0 32 32 0 0 0 0 32 32 0 34 34 0

6.4 Silt Content Once in a week 0 0 0 32 32 0 0 0 0 32 32 0 24 24 0

7.0 COARSE AGGREGATE (FOR CONCRETE)

7.1 Sieve Analysis / Gradation of 10mm On Daily Basis 189 187 2 32 32 0 221 219 2 32 32 0 221 219 2

7.2 Sieve Analysis / Gradation of 20mm On Daily Basis 185 183 2 32 32 0 217 215 2 32 32 0 217 215 2

7.3 Sieve Analysis / Gradation of All in Aggregate On Daily Basis 71 71 0 32 32 0 103 103 0 32 32 0 103 103 0

7.4 Specific Gravity (3test = 1 set) As Required 34 34 0 0 0 0 34 34 0 0 0 0 34 34 0

7.5 AIV 3 test / week 79 79 0 15 15 0 94 94 0 15 15 0 94 94 0

7.6 FI & EI 3 test / week 64 64 0 15 15 0 79 79 0 15 15 0 79 79 0

7.7 Water Absorption / Moisture Content On Daily Basis 86 86 0 32 32 0 118 118 0 32 32 0 118 118 0

8.0 CEMENT

Physical Tests
8.1 Standard Consistency Test 1 test per lot 10 10 0 4 4 0 14 14 0 4 4 0 14 14 0

8.2 Soundness Test 1 test per lot 10 10 0 4 4 0 14 14 0 4 4 0 14 14 0

8.3 Intial & Final Setting Time Test 1 test per lot 10 10 0 4 4 0 14 14 0 4 4 0 14 14 0

8.4 Compressive Strength Test 1 test per lot


(i) 3 Days (Set) 18 18 0 12 12 0 30 30 0 12 12 0 30 30 0

(ii) 7 Days (Set) 18 18 0 12 12 0 30 30 0 12 12 0 30 30 0

(iii) 28 Days (Set) 18 18 0 12 12 0 30 30 0 12 12 0 30 30 0

9.0 PRIME COAT / TACK COAT

9.1 Rate of Spray (Prime Coat) 1 test / lot 36 36 0 36 36 0 72 72 0 36 36 0 72 72 0

9.2 Rate of Spray (Tack Coat) 3 test / Day 36 36 0 36 36 0 72 72 0 36 36 0 72 72 0

10.0 DENSE BITUMEN MACADAM (DBM)


10.1 Sieve Analysis 1 test for each 34 34 0 34 34 0 68 68 0 34 34 0 68 68 0

400 ton of mix & Min. 2


10.2 Bitumen Extraction & Gradation Test test / day
48 48 0 48 48 0 96 96 0 48 48 0 96 96 0

10.3 Aggregate Impact Value 1 test / 350 mᶟ 28 28 0 28 28 0 56 56 0 28 28 0 56 56 0

10.4 Comb. Flakiness & Elongation Index 1 test / 350 mᶟ 28 28 0 28 28 0 56 56 0 28 28 0 56 56 0

EPC Contractor Representative Authority's Engineer Representative


ANNEXURE - "C" -MPR FOR QUALITY CONTROL

QUALITY ASSURANCE & QUALITY CONTROL TEST REPORT WITNESSED BY AUTHORITY'S ENGINEER FOR UP TO THE MONTH OF 11 JANUARY 2016
TESTS CONDUCTED DURING CURRENT TOTAL TESTS CONDUCTED BY AE TOTAL TESTS CONDUCTED BY AE UP
NO. OF TEST TOTAL TEST UPTO PREVIOUS MONTH MONTH TOTAL TESTS UPTO THIS MONTH DURING CURRENT MONTH TO THIS MONTH
Sl. No. DESCRIPTION FREQUENCY OF TEST REQUIRED IN REMARK
CURRENT MONTH
TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED

10.5 GMM 1 test / day 14 14 0 14 14 0 28 28 0 14 14 0 28 28 0

10.6 Marshall Stability, Flow, VMA, VFB, & Air Voids 1set / 3mould 144 144 0 144 144 0 288 288 0 144 144 0 288 288 0

10.7 Drilled Core Density 1test / 700 m² 89 89 0 89 89 0 178 178 0 89 89 0 178 178 0

10.8 Sp. Gravity & Water Absorption As Required 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11.0 BITUMINOUS CONCRETE (BC)


11.1 Sieve Analysis 1 test for each 400 MT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

400 ton of mix & Min. 2


11.2 Bitumen Extraction & Gradation Test test / day
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11.3 Aggregate Impact Value 1 test / 50 mᶟ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11.4 Comb. Flakiness & Elongation Index 1 test / 50 mᶟ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11.5 Stripping Value Test 1 test / source 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11.6 Marshall Stability, Flow, VMA, VFB, & Air Voids 1set / 3mould 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11.7 Drilled Core Density 1test / 250 m² 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

11.8 Sp. Gravity & Water Absorption As Required 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

12.0 BITUMEN VG-30


12.1 Penetration Grade at 25 Degree 1 test / lot 33 33 0 33 33 0 66 66 0 33 33 0 66 66 0

12.2 Softening Point 1 test / lot 33 33 0 33 33 0 66 66 0 33 33 0 66 66 0

12.3 Dutility at 27 Degree 1 test / lot 33 33 0 33 33 0 66 66 0 33 33 0 66 66 0

12.4 Viscosity 1 test / lot 33 33 0 33 33 0 66 66 0 33 33 0 66 66 0

12.5 Specific Gravity 1 test / lot 33 33 0 33 33 0 66 66 0 33 33 0 66 66 0

13.0 CONCRETE CUBE TESTING (SITE)

13.1 7 Days
(i) M-15 PCC (SET) MORT&H - Section 1700 48 48 0 16 16 0 64 64 0 16 16 0 64 64 0

(ii) M-20 PCC (SET) MORT&H - Section 1700 82 82 0 17 17 0 99 99 0 17 17 0 99 99 0

(iii) M-25 RCC (SET) MORT&H - Section 1700 7 7 0 1 1 0 8 8 0 1 1 0 8 8 0

(iv) M-30 RCC (SET) MORT&H - Section 1700 67 67 0 67 67 0 134 134 0 67 67 0 134 134 0

(v) M-35 RCC (SET) MORT&H - Section 1700 7 7 0 7 7 0 14 14 0 7 7 0 14 14 0

(vi) M-35 PILE (SET) MORT&H - Section 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(vii) M-40 RCC (SET) MORT&H - Section 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(viii) M-45 RCC (SET) MORT&H - Section 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(ix) M-20 KERB (SET) MORT&H - Section 1700 10 10 0 10 10 0 20 20 0 10 10 0 20 20 0

(x) DLC MORT&H - Section 600 104 104 0 104 104 0 208 208 0 104 104 0 208 208 0

(xI) PQC MORT&H - Section 600 198 198 0 198 198 0 396 396 0 198 198 0 396 396 0

13.2 28 Days

(i) M-15 PCC (SET) MORT&H - Section 1700 24 24 0 22 22 0 46 46 0 22 22 0 46 46 0

EPC Contractor Representative Authority's Engineer Representative


ANNEXURE - "C" -MPR FOR QUALITY CONTROL

QUALITY ASSURANCE & QUALITY CONTROL TEST REPORT WITNESSED BY AUTHORITY'S ENGINEER FOR UP TO THE MONTH OF 11 JANUARY 2016
TESTS CONDUCTED DURING CURRENT TOTAL TESTS CONDUCTED BY AE TOTAL TESTS CONDUCTED BY AE UP
NO. OF TEST TOTAL TEST UPTO PREVIOUS MONTH MONTH TOTAL TESTS UPTO THIS MONTH DURING CURRENT MONTH TO THIS MONTH
Sl. No. DESCRIPTION FREQUENCY OF TEST REQUIRED IN REMARK
CURRENT MONTH
TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED

(ii) M-20 PCC (SET) MORT&H - Section 1700 30 30 0 26 26 0 56 56 0 26 26 0 56 56 0

(iii) M-25 RCC (SET) MORT&H - Section 1700 2 2 0 2 2 0 4 4 0 2 2 0 4 4 0

(iv) M-30 RCC (SET) MORT&H - Section 1700 100 100 0 100 100 0 200 200 0 100 100 0 200 200 0

(v) M-35 RCC (SET) MORT&H - Section 1700 10 10 0 10 10 0 20 20 0 10 10 0 20 20 0

(vi) M-35 PILE (SET) MORT&H - Section 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(vii) M-40 RCC (SET) MORT&H - Section 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(viii) M-45 RCC (SET) MORT&H - Section 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(ix) M-20 KERB (SET) MORT&H - Section 1700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(x) PQC MORT&H - Section 600 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

14.0 CONCRETE CUBE/BEAM TESTING (MIX DESIGN TRIALS)

14.1 7 Days
(i) M-15 PCC (SET) MORT&H - Section 1700 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

(ii) M-20 PCC (SET) MORT&H - Section 1700 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

(iii) M-25 RCC (SET) MORT&H - Section 1700 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

(iv) M-30 RCC (SET) MORT&H - Section 1700 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

(v) M-35 RCC (SET) MORT&H - Section 1700 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

(vi) M-35 PILE (SET) MORT&H - Section 1700 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

(vii) M-40 RCC (SET) MORT&H - Section 1700 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

(viii) M-45 RCC (SET) MORT&H - Section 1700 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

(ix) DLC MORT&H - Section 600 6 6 0 0 0 0 6 6 0 0 0 0 6 6 0

(x) PQC MORT&H - Section 600 6 6 0 0 0 0 6 6 0 0 0 0 6 6 0

14.2 28 Days

(i) M-15 PCC (SET) MORT&H - Section 1700 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(ii) M-20 PCC (SET) MORT&H - Section 1700 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(iii) M-25 RCC (SET) MORT&H - Section 1700 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(iv) M-30 RCC (SET) MORT&H - Section 1700 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(v) M-35 RCC (SET) MORT&H - Section 1700 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(vi) M-35 PILE (SET) MORT&H - Section 1700 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(vii) M-40 RCC (SET) MORT&H - Section 1700 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(viii) M-45 RCC (SET) MORT&H - Section 1700 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

15.0 THIRD PARTY TESTING

12.1 Soil Testing

(i) FSI As Required 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(ii) GSA (Silt & Clay) As Required 6 6 0 0 0 0 6 6 0 0 0 0 6 6 0

(iii) LL / PL / PI As Required 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

EPC Contractor Representative Authority's Engineer Representative


ANNEXURE - "C" -MPR FOR QUALITY CONTROL

QUALITY ASSURANCE & QUALITY CONTROL TEST REPORT WITNESSED BY AUTHORITY'S ENGINEER FOR UP TO THE MONTH OF 11 JANUARY 2016
TESTS CONDUCTED DURING CURRENT TOTAL TESTS CONDUCTED BY AE TOTAL TESTS CONDUCTED BY AE UP
NO. OF TEST TOTAL TEST UPTO PREVIOUS MONTH MONTH TOTAL TESTS UPTO THIS MONTH DURING CURRENT MONTH TO THIS MONTH
Sl. No. DESCRIPTION FREQUENCY OF TEST REQUIRED IN REMARK
CURRENT MONTH
TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED TESTED PASSED FAILED

(iv) MDD / OMC As Required 12 12 0 6 6 0 18 18 0 6 6 0 18 18 0

(v) CBR Test As Required 12 12 0 6 6 0 18 18 0 6 6 0 18 18 0

(vi) Shrinkage Limit As Required 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(vii) Soluble Sulphate Test As Required 8 8 0 0 0 0 8 8 0 0 0 0 8 8 0

(viii) Soil Bearing Capacity (Plate Load Test) As Required 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15.2 Steel

(i) 8mm (3pc = 1 set) 1 test / lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(ii) 10mm (3pc = 1 set) 1 test / lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(iii) 12mm (3pc = 1 set) 1 test / lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(iv) 16mm (3pc = 1 set) 1 test / lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(v) 20mm (3pc = 1 set) 1 test / lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(vi) 25mm (3pc = 1 set) 1 test / lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(vii) 32mm (3pc = 1 set) 1 test / lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15.3 Aggregate
(i) Fine Aggregate As Required 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(ii) Coarse Aggregate (10mm) As Required 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(iii) Coarse Aggregate (20mm) As Required 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(iv) Coarse Aggregate (40mm) As Required 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

(v) GSB As Required 2 2 0 0 0 0 2 2 0 0 0 0 2 2 0

15.4 Cement
(i) Ultratech (OPC-43) 1 test / 500 MT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

(ii) Shree (OPC-43) 1 test / 500 MT 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

15.5 Water As Required


15.6 Hume pipe Testing(1200mm dia) As Required 8 8 0 0 0 0 8 8 0 0 0 0 8 8 0

15.7 Hume pipe Testing(600mm dia) As Required 8 8 0 0 0 0 8 8 0 0 0 0 8 8 0

15.8 Admixture As Required 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

16.0 CALIBRATION IN-HOUSE

16.1 Batching Plant CP-30 6 Month 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

16.2 Batching Plant CP-2.50 6 Month 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

16.3 Hot Mix Plant 6 Month 1 1 0 0 0 0 1 1 0 0 0 0 1 1 0

EPC Contractor Representative Authority's Engineer Representative


Project :- Four-laning of Ambala - Kaithal Section of NH-65 from Km 0.000 (Ambala) to Km 50.860 (Pehowa) with paved shoulder (length 50.860 km) in the State of Haryana under NHDP Phase-III on EPC
Basis.
ANNEXURE -"D"

BORROW AREA SUMMARY


FREE GSA ATTERBERGS LIMITS PROCTOR TEST
SWELL CBR AT
INDEX MDD 97 % OF
GRAVEL SAND SILT & LL PL PI OMC MDD
Sl.No BA NO. VILLAGE LOCATION SIDE CLAY USED FOR APPROVED BY AE

(%) (%) (%) (%) (%) (%) (%) (gm/cc) (%) (%)

BA No. 01 MSV/ PRJ/ 168/ NHAI/A-K /2OL6/154 Dated


1 Fujalpur 19+250 LHS 11.98 2.15 53.45 44.4 23.09 N.P. N.P. 1.997 9.99 12.75 EMBANKMENT & SUB GRADE on 04.10.2016
( Part Quan.I )

BA No. 01 MSV/ PRJ/ 168/ NHAI/A-K /2OL6/170 Dated


2 Fujalpur 19+250 LHS 12.75 2.15 53.12 44.74 23.88 N.P. N.P. 1.998 10.28 12.95 EMBANKMENT & SUB GRADE on 20.10.2016
( Part Quan.II )

BA No. 01 MSV/ PRJ/ 168/ NHAI/A-K /2OL6/197 Dated


3 Fujalpur 19+250 LHS 13.62 1.12 42.45 56.43 29.10 N.P. N.P. 1.932 11.14 13.15 EMBANKMENT & SUB GRADE
( Part Quan.III ) on 21.11.2016

4 BA No. 08 Baroli 23+200 LHS 14.15 0.13 48.07 51.80 23.43 N.P. N.P. 1.947 10.43 13.73 EMBANKMENT & SUB GRADE MSV/ PRJ/ 168/ NHAI/A-K /2OL6/199 Dated
on 22.11.2016

MSV/ PRJ/ 168/ NHAI/A-K /2OL6/200 Dated


5 BA No. 09 Untsar (PB) 06+000 RHS 12.55 0.56 39.63 59.81 32.63 22.78 9.84 1.811 11.90 12.50 EMBANKMENT & SUB GRADE on 22.11.2016

MSV/ PRJ/ 168/ NHAI/A-K /2OL6/202 Dated


6 BA No. 10 Baroli 23+200 LHS 5.82 0.00 84.78 15.22 35.97 N.P. N.P. 1.675 13.32 EMBANKMENT on 23.11.2016

BA No. 11 MSV/ PRJ/ 168/ NHAI/A-K /2OL6/188 Dated


7 Jhansa (Thol) 30+600 LHS 13.12 10.82 39.58 49.60 31.53 22.69 8.83 1.966 10.74 EMBANKMENT & SUB GRADE on 09.11.2016
( Part Quan.I )

BA No. 11 MSV/ PRJ/ 168/ NHAI/A-K /2OL6/201 Dated


8 Jhansa (Thol) 30+600 LHS 13.19 10.33 38.66 51.01 31.43 22.37 9.06 1.962 10.70 EMBANKMENT & SUB GRADE on 22.11.2016
( Part Quan.II )

9 BA No. 12 Naise 39+600 RHS 12.48 0.72 20.92 78.36 33.64 21.47 12.18 1.884 11.39 12.5 EMBANKMENT & SUB GRADE MSV/ PRJ/ 168/ NHAI/A-K /2OL6/204 Dated
on 28.11.2016

MSV/ PRJ/ 168/ NHAI/A-K /2OL6/203 Dated


10 BA No. 13 Jalberha 43+000 LHS 13.99 0.64 29.22 70.14 33.24 23.08 10.16 1.906 11.65 9.98 EMBANKMENT & SUB GRADE on 24.11.2016

BA No. 16 MSV/ PRJ/ 168/ NHAI/A-K /2OL6/205 Dated


11 Untsar (PB) 06+000 RHS 22.54 0.00 15.22 84.78 36.80 20.74 16.07 1.861 12.26 9.90 EMBANKMENT & SUB GRADE on 28.11.2016
( Part Quan.II )

EPC Contractor Representative Authority's Engineer Representative


NATIONAL HIGHWAYS AUTHORITY OF INDIA

Four-laning of Ambala - Kaithal Section of NH-65 from Km 0.000 (Ambala) to Km 50.860 (Pehowa) with paved shoulder (length 50.860 km) in the State of Haryana under NHDP Phase-III on EPC
Basis.
ANNEXURE -"E"
:
CLIENT NATIONAL HIGHWAYS AUTHORITY OF INDIA
:
AUTHORITY'S ENGINEER MSV INTERNATIONAL INC.
M/s DILIP BUILDCON LIMITED
: M/s VARAHA INFRA LIMITED (JV)
EPC CONTRACTOR

SUMMARY OF CONCRETE MIX DESIGN


Source of Coarse Aggregate :- DBL Stock (Handesra/Narayangarh) Brand of Cement :- Shree / Ultratech

Source of Fine Aggregate :- DBL Stock (Handesra/Narayangarh) Grade of Cement :- OPC-43

Source of Water :- Borewell No.1 @ Base Camp Brand of Admixture :- KUNAL Kunacon 37SS

Compressive Strength
SSD WT. kg/m³ SLUMP (mm) (N/mm²)
Sl. Date of Grade of CA : CA CA : FA Water Admixture Cement Fly-Ash Water
No. Casting Concrete
(20mm : 10mm)
% Cement (kg) (kg) (kg) (kg) Remarks
% Ratio 20mm Aggragate 10mm Aggregate Fine Aggregate
(kg) (kg) (kg) Initial 30 min. 60 min. 90 min. 7 Days 28 Days

1 1/9/2016 M:15 PCC 60:40 62:38 0.50 2.28 285 0 142.5 723 482 753 120 100 80 65 16.09 27.09 Approved

2 20/09/2016 M:20 PCC 60:40 60:40 0.50 1.95 300 0 150.0 712 474 742 120 95 80 60 21.5 33.05 Approved

3 1/9/2016 M:25 RCC 60:40 57:43 0.44 1.63 340 0 149.0 643 429 827 Collaps 190 160 100 26.06 40.00 Approved

4 15/09/2016 M:30 RCC 60:40 58:42 0.39 2.04 370 0 144.3 651 434 802 Collaps 200 170 110 30.25 43.1 Approved

5 16/09/2016 M:35 RCC 60:40 57:43 0.38 2.09 380 0 144.4 637 425 817 Collaps 200 180 120 35.5 48.2 Approved

6 17/09/2016 M:35 PILE 60:40 57:43 0.38 2.60 400 0 152.0 624 416 800 Collaps Collaps 200 160 34.09 47.21 Approved

7 13/12/2016 M:35 RE 65:35 65:35 0.40 2.66 380 0 152.0 675 547 660 Collaps 150 100 80 34.07 Approved
PANNEL

8 15/10/2016 M:40 RCC 60:40 60:40 0.36 2.48 400 0 144.0 665 443 754 180 150 120 100 40.95 53.25 Approved

9 15/10/2016 M:45 RCC 60:40 60:40 0.34 2.55 425 0 144.5 657 438 745 Collaps 180 150 120 40.6 60.12 Approved

10 20/12/2016 M:20 KERB 60:40 55:45 0.45 1.55 310 0 139.5 545 543 875 30 20 15 10 24.37 Approved

11 16/10/2016 DLC 60:40 - - - 120 30 132.0 456 788 846 - - - - 13.07 - Approved

12 16/10/2016 PQC 60:40 60:40 0.34 320 80 136.0 555 552 751 50 35 25 20 31.67 44.12 Approved

EPC Contractor Representative Authority's Engineer Representative


EPC Contractor Representative Authority's Engineer Representative
NATIONAL HIGHWAYS AUTHORITY OF INDIA
Four-laning of Ambala - Kaithal Section of NH-65 from Km 0.000 (Ambala) to Km 50.860 (Pehowa) with paved shoulder (length
50.860 km) in the State of Haryana under NHDP Phase-III on EPC Basis.

ANNEXURE -"F"

CLIENT : NATIONAL HIGHWAYS AUTHORITY OF INDIA


AUTHORITY'S ENGINEER : MSV INTERNATIONAL INC.
EPC CONTRACTOR : M/s DILIP BUILDCON LIMITED
M/s VARAHA INFRA LIMITED (JV)

DAILY WEATHER REPORT


Month : DECEMBER Year : 2016

Location of Weather Station: DBL Base Camp

TEMPARATURE HUMIDITY RAINFALL


DATE STATUS REMARK
Max. ͦC Min. ͦC Max. Min. 24hrs (mm)
1-Dec-2016 23.9 14.6 95 63 - CL S = Sunny
2-Dec-2016 24.7 15.5 86 54 - CL CL = Cloudily
3-Dec-2016 22.7 12.5 94 61 - CL R = Rainy
4-Dec-2016 22.5 11.9 90 49 - CL
5-Dec-2016 23.0 11.3 89 53 - S/CL
6-Dec-2016 21.8 11.2 90 70 - S/CL
7-Dec-2016 20.0 11.0 90 75 - S/CL
8-Dec-2016 20.0 11.1 92 77 - S/CL
9-Dec-2016 20.3 12.1 92 73 - S/CL
10-Dec-2016 20.5 13.5 90 76 - S/CL
11-Dec-2016 23.4 15.1 92 71 - CL
12-Dec-2016 22.7 14.1 92 72 - CL
13-Dec-2016 19.9 14.0 87 74 - CL
14-Dec-2016 20.0 12.8 89 68 - CL
15-Dec-2016 20.9 10.3 87 50 - CL
16-Dec-2016 20.5 10.8 89 58 - CL
17-Dec-2016 21.8 10.5 90 50 - CL
18-Dec-2016 21.6 12.1 88 44 - S/CL
19-Dec-2016 22.1 12.2 82 54 - S/CL
20-Dec-2016 22.7 10.2 85 42 - S/CL
21-Dec-2016 22.4 8.1 83 47 - S/CL
22-Dec-2016 21.2 9.8 89 63 - S/CL
23-Dec-2016 22.8 10.4 90 60 - CL
24-Dec-2016 21.9 12.2 89 65 - CL
25-Dec-2016 19.9 11.4 82 62 - S/CL
26-Dec-2016 21.1 10.2 86 52 - CL
27-Dec-2016 21.5 10.7 84 50 - S/CL
28-Dec-2016 21.9 12.7 85 55 - CL
29-Dec-2016 20.1 13.5 85 69 - S/CL
30-Dec-2016 21.4 13.1 81 59 CL
31-Dec-2016 21.2 17.7 85 61 - CL
Summary (Rain Fall In mm)
Till Previous Month (mm) During the Month (mm) Commulative (mm)
191 0 62.00
EPC Contractor's Representative Authority Engineer Representative.
NATIONAL HIGHWAYS AUTHORITY OF INDIA
Four-laning of Ambala - Kaithal Section of NH-65 from Km 0.000 (Ambala) to Km 50.860 (Pehowa) with paved shoulder (length
50.860 km) in the State of Haryana under NHDP Phase-III on EPC Basis.

ANNEXURE -"F"

CLIENT : NATIONAL HIGHWAYS AUTHORITY OF INDIA


AUTHORITY'S ENGINEER : MSV INTERNATIONAL INC.
EPC CONTRACTOR : M/s DILIP BUILDCON LIMITED
M/s VARAHA INFRA LIMITED (JV)

DAILY WEATHER REPORT


Month : JANUARY Year : 2017

Location of Weather Station: DBL Base Camp

TEMPARATURE HUMIDITY RAINFALL


DATE STATUS REMARK
Max. ͦC Min. ͦC Max. Min. 24hrs (mm)
1-Jan-2017 22.9 11.4 89 56 - CL S = Sunny
2-Jan-2017 23.1 10.9 82 51 - CL CL = Cloudily
3-Jan-2017 23.1 10.8 81 50 - CL R = Rainy
4-Jan-2017 23.3 11.1 85 59 - CL
5-Jan-2017 23.2 11.0 84 59 - S/CL
6-Jan-2017 20.5 13.5 84 71 - S/CL
7-Jan-2017 16.0 10.0 90 74 - S/CL
8-Jan-2017 19.8 10.1 90 65 - S/CL
9-Jan-2017 19.5 7.9 83 60 - S/CL
10-Jan-2017 17.4 6.7 79 47 - S/CL
11-Jan-2017 17.4 7.0 77 49 - CL
12-Jan-2017 18.1 6.8 77 52 - CL
13-Jan-2017 18.2 7.5 80 50 - CL
14-Jan-2017 18.5 7.6 81 54 - CL
15-Jan-2017 18.7 8.0 80 57 - CL
16-Jan-2017 18.2 9.0 83 64 - CL
17-Jan-2017 14.5 7.9 90 72 - CL
18-Jan-2017 17.2 7.0 85 67 - S/CL
19-Jan-2017 18.6 7.5 86 62 - S/CL
20-Jan-2017 17.9 8.0 82 66 - S/CL
21-Jan-2017 17.8 10.5 85 72 - S/CL
22-Jan-2017 21.8 11.2 83 68 - S/CL
23-Jan-2017 21.9 10.9 87 56 - CL
24-Jan-2017 20.0 12.5 86 68 - CL
25-Jan-2017 20.8 15.5 84 68 - S/CL
26-Jan-2017 16.8 13.5 88 79 - CL
27-Jan-2017 20.8 12.6 90 82 - S/CL
28-Jan-2017 18.8 12.8 88 76 - CL
29-Jan-2017 - S/CL
30-Jan-2017 CL
31-Jan-2017 - CL
Summary (Rain Fall In mm)
Till Previous Month (mm) During the Month (mm) Commulative (mm)
191 0 62.00
EPC Contractor's Representative Authority Engineer Representative.

You might also like