Pilot Project
Location: Malaysia Power Plant
Date: 12th March 2020
1
Project Background
2
Pilot Site
3
Installation NTG System – PM System
4
Installation NTG PG System – PS-HW Series
Install
location of SW
& DW
PS System
5
Results for the PAP -1
Summary PAP Results for Heat Transfer Efficiency of the Plate
Heat Exchanger Unit A.
Baseline
58.6 NA
(9 Jan to 24 Jan 2020)
70% 69.5%
68.2%
60%
58.6%
Heat Transfer
53.1%
50% Efficiency
Week 1 53.1%
40%
HTE continue to decrease After PG system starts to take effect
Week 2 68.2%
HTE starts to ramp up in a very short time
30%
Week 3 69.5%
20%
10%
0%
Baseline (Jan 9 to Jan 24,
2020)
PAP during 1 week (Jan 25 PAP during 2 week (Feb 3 to PAP during 3 week (Feb 12
to Feb 2, 2020) Feb 11, 2020) to Feb 18, 2020)
7
Results for the PAP – visual inspection
8
Improvement & Benefit
10