Professional Documents
Culture Documents
Maintenance of Distribution
network, under DHBVN
MAINTENANCE PROCEDURES
Proper maintenance of electrical systems helps in minimizing/preventing unwarranted breakdowns
of Equipment / lines improving the reliability and generating revenue. Periodical or preventive
maintenance is normally followed to keep the equipment continuously in service for desired output.
Condition based maintenance is the most accepted and adopted concept in maintenance now a day’s
which helps in providing advance information about the health of the equipment to take corrective
action in advance.
As the system is growing, it is getting more and more complex. Due to stringent regulations the
utility cannot afford to have breakdowns in the system resulting in interruption of power supply to
the consumer. On the other hand equipment are getting older and are more prone to failure.
Equipment overhaul and major maintenance are also expensive and need to be planned based on the
condition of the equipment rather than on a periodic basis as a routine.
1. POWER TRANSFORMERS
A transformer is an electrical device that transfers electrical energy between two or more circuits
through electromagnetic induction. Electromagnetic induction produces an electromotive force
within a conductor which is exposed to time varying magnetic. It constitutes the single most
expensive item in a substation.
In order to provide long and trouble free service, it is important that a careful and regular
supervision and maintenance of the transformer and its components is carried out. The frequency
and extent of such a supervision and maintenance is dependent on the experience, climatic
conditions, environment, service conditions, loading pattern etc. All work done on transformers
should be recorded in maintenance register / checklist.
Alarms & Trippings provided for Power Transformers being used in Sub Stations under
DHBVN
2. CIRCUIT BREAKERS:
A circuit breaker is an automatically-operated electrical switch designed to protect an electrical
circuit from damage caused by faults. Circuit breaker can be reset (either manually or
automatically) to resume normal operation.
OPERATING PRINCIPLE
Under fault conditions, current intensity increases multiple times the normal current flow. This
current senses by relay and energized tripping coil of breaker to isolate the system. Circuit breaker
also used to isolate the section manually
Type of circuit breakers used in DHBVN
At 33 KV level
1. Oil circuit Breakers
2. Vacuum circuit breaker
At 11 KV level
1. Vacuum circuit breakers
CIRCUIT BREAKER RATING:The breaking capacity of a circuit breaker depends on
(i) Symmetrical breaking capacity
(ii) Asymmetrical breaking capacity
Symmetrical breaking capacity
It is the rms. Value of the ac component of the fault current that the circuit breaker is capable of
breaking under specified conditions of recovery voltage.
Asymmetrical breaking capacity
It is the rms value of the total current comprising of both ac and dc components of the fault current
that the circuit breaker can break under specified conditions of recovery voltage.
Making Capacity of circuit breakers
The rated making current is defined as the peak value of the current (including the dc component) in
the first cycle at which a circuit breaker can be closed onto a short circuit.
Testing of circuit breakers
BREAKER TIMING
CONTACT RESISTANCE MEASUREMENT
Testing Procedure:
De- energize, discharge the equipment which is to be tested as a safety precaution. .
Check whether Timer leads and associated clips that are to be connected to the breaker
poles are good & tight.
Make the test connections on the lines of circuit diagram
Switch on the power supply to the timer and issue Close command from the timer. Note
down the close timing displayed on the timer
After recommended time interval (3 seconds), issue Open command from the timer.
Note down the open timing displayed on the timer.
Now issue Close-Open (CO) command from the timer. Note down the CO timing
displayed on the timer.
Confirmation of Test:
Breaker opening time should be less than the closing time of the breaker, it should
come in the range of 30-45 ms. while closing time should be 40-60 ms.
CO- time breaker should at the middle of the closing and opening time.
Opening time < closing -Opening time < closing time
Please refer GTP Details of the Breaker for confirmation of the Timing Results.
Inference/Recommendation:
If the specimen breaker satisfies the respective condition then the respective breaker is considered
to be satisfactory. If any deviation is observed from above mentioned condition then corrective
action should be taken with the help of the manufacturer /OEM.
3. CURRENT TRANSFORMERS:
A current transformer (CT) is a type of instrument transformer designed to provide a current in
its secondary winding proportional to the alternating current flowing in its primary. They are
commonly used in metering and protection circuits
Principle
The current transformer works on the principle of variable flux. In the "ideal" current transformer,
secondary current would be exactly equal (when multiplied by the turn’s ratio) and opposite of the
primary current
4. POTENTIAL TRANSFORMERS
Voltage transformers (VT) or potential transformers (PT) are another type of instrument
transformer, used for metering and protection in high-voltage circuits. Typically the secondary of a
voltage transformer is rated for 110 V at rated primary voltage, to match the input ratings of
protective relays.
Ratio test is a routine test of potential transformer, ratio test is recommended during overhaul and
maintenance to check the expected ratio of potential transformer. Limit level of the tests is +- 3 %.
5. LIGHTNING (SURGE) ARRESTERS:
Lightning is one of the most serious causes of over voltage. A lightning rod provides a cone of
protection, which has a ground radius approximately, equal to its height above the ground. The
typical lightning arrester also known as surge arrester has a high voltage terminal and a ground
terminal.
LA voltage rating Corresponding to the system voltage
ARRESTER RATING IN KV
RATED SYSTEM VOLTAGE HIGHEST SYSTEM VOLTAGE
FOR EFFECTIVE EARTHED
(KV) (KV)
SYSTEM
11 12 9
33 36 30
66 72.5 60
132 145 120/132
220 245 198/216
400 420 336
Surge Arrestors installed in the substation are intended to divert surges to earth and thus protect
costly switchyard equipment. Proper insulation coordination is necessary for enhancing life span of
costly substation equipment.
Disconnectors have main current carrying arms and operating mechanism for connection and
disconnection. Being off-line devices, they are normally air break type. Normally horizontal double
break, Horizontal center break, Pantograph, Vertical break Disconnectors are in use in EHV
substations.
The alignment of Disconnectors is very important for smooth operation. The limit switches, the
healthiness of auxiliary contacts needs to be checked periodically. The main contacts are to be
inspected and made smooth if any pitting marks seen. All moving parts are to be lubricated for
smooth operation. The gear mechanism and motor normally do not require any maintenance and
manufacturer's' recommendation should be referred for maintenance of gears.
Earth Switches: The earth switch is a safety device and smooth operation is to be ensured by
proper alignment. The earth blade contacts are to be cleaned properly for proper contact and contact
resistance to be measured to ensure healthiness. The earth connection from blade to earth is to be
carefully checked. All the joints should be tightened. Flexible copper braid connections are
provided and healthiness ensured. All moving parts should be lubricated for smooth operation.
7. BATTERY AND BATTERY CHARGERS:
In substation DC supply has equal importance. All protection & indication circuits enable with DC
supply only. Substations generally use Lead Acid batteries / Nickel-Cadmium batteries for DC
supply. Now a days valve regulated lead acid batteries (maintenance free batteries) are also in use
for substation applications.
Battery Chargers: Battery charger is to be maintained for keeping the battery always charged and
also to supply normal DC load for operation.
Rating of Battery bank along with VA capacity used
EARTH MAT:
It is formed by steel 75/8 flats laid horizontally at a depth of 0.5 m below surface of ground to form
a mesh of rectangular formation & are welded together. The spacing of earth rods is determined by
required touch & step potential. In addition to earth mat, earth electrodes are used these are also
connected to the mesh. Solid bar risers are welded to mesh and brought up near the equipment
foundations.
BASIS FOR DESIGN OF GROUNDING SYSTEM
Magnitude of fault current
Transient Over voltage
Lightning Protection
Application of Protective devices for selective ground fault protection
Type of load served viz. Motor, Generator etc.
GENERAL GUIDELINES FOR EARTHING
An effective grounding system must satisfy the following conditions:
Provide a low impedance path to ground for personnel and equipment safety.
Withstand and dissipate repeated faults and surge currents
Provide ample corrosion allowance to various chemicals to ensure continuous service during
life of the equipment being protected.
Provide rugged mechanical properties for easy driving of earth electrodes with minimum
difficulty.
All non-current carrying metal parts associated with installation shall be effectively earthed
to a grounding system or mat which will limit the touch and step potential to tolerable
values.
BASIC REQUIREMENT FOR EARTHING:
The current carrying path of earthing system should have enough capacity to carry
maximum fault current.
The resistance of earth & current path should be low enough so as to prevent voltage rise
between N & E.
Step & Touch potential should be within the safe limits.
Systematic survey of earth resistivity should be carried out.
The earth electrodes should be driven in the ground to a sufficient depth.
To obtain sufficient low earth resistance ,
The area of earth mesh is increased.
The spacing of buried rods is reduced.
Soil is kept wet.
The number of earth electrodes are increased.
Earth resistance is reduced by means of Nacl (Common salt), CaCl2 (Calcium chloride),
Na2CO4 (sodium carbonate), CuSO4 (Copper Sulphate), charcoal, soft coal etc.
Method of improving Grounds:
11 KV LEVEL
DISTRIBUTION TRANSFORMER
Scope:
This operational guideline is intended to carry out the fundamental checks on Transformer for its
maintenance and while taking it into service. This requires that the concerned SDO should prepare
the action plan and ensure the availability of necessary tools and tackles to carry out this activity.
Prerequisites:
Ensure that necessary permit has been taken. Feeding Sub-station is responsible for providing
outage and PTW. The working party is responsible for ensuring isolation. Ensure that the
transformer is de-energized, isolated & grounded.
Working party should ensure the availability of proper tools and accessories, safety apparels, spares
and consumables required for carrying out the work.
UNDERGROUND CABLES: the underground cable network of any electricity distribution utility
is a vital component of the LV/HV network of the system. It has a several unique benefits over
overhead networks. In particular, they have:
1. Flash over due to Phase to phase & Phase Ensure sufficient clearance
to earth clearance at cable termination
(Refer table4)
Ensure proper Tightening/crimping of
2. Insulation degradation due to Hot spot at
joints & Terminations Lugs & Ferrules
External damage Insulation Damaged by external agency Ensure Patrolling of cable routes
Leakage current through the cable insulation/ Ensure Lug seal to be intact at outdoor
Water ingress cable failure, Corrosion in cable conductor
&Armour due ingress of water termination.
S. No Test UG Cable
Phase toGround and Phase to Phase to be tested with 2.5/5.0 KV
1 Meggar meggar for one minute or till reading stabilized. Minimum IR value
should be 50 M ohms.
Each phase to be tested @ 6.5 KV DC for 5 minute with respect to
2 Hi pot ground with other two phases grounded. The cable must with stand
the test voltage & leakage current should not exceed 2mA
Depth of the cable (Table-3)
Voltage Level Depth of cable
LT cable (1.1kv) 0.6 m
HV cable (11kv) 0.9 m
EHV cable (33kv) 1.2 m
EHV cable (66kv) 1.5 m
Current Rating (Table4)- 11 KV XLPE UG Cable
Nominal Size of Cable Current Carrying Capacity (Amps)
S. No. (Sqmm)
In Ground at 30˚C In Duct at 30˚C In Air at 30˚C
for 11 kV level
1 3x95 190 165 230
2 3x120 220 190 260
3 3x150 245 210 295
4 3x185 275 240 335
5 3x240 315 275 395
6 3x300 355 310 450
Nominal Size of Cable Current Carrying Capacity (Amps)
S. No. (Sqmm)
In Ground at 30˚C In Duct at 30˚C In Air at 30˚C
for 11 kV level
7 1x630 560 480 840
8 1x1000 680 580 1070
HT OVERHEAD LINES
Introduction:
Overhead lines are the most cost effective and frequently used carriers for electric energy. Exposure
to environment accelerates deterioration; if this not detected and repaired quickly, some of it will
degenerate into serious problems with time. To increase line loading and increase quality of power
supply, frequent inspection programs is required to locate and repair any significant failure at the
earliest possible stage.
Frequent failure in the Overhead lines can cause extensive damage to the insulator and other
electrical & earth joints which not only interrupts electricity supply but also results in large revenue
losses. Poor/inadequate maintenance in the areas of pole, span length, non-tension electrical joints,
conductor spacing, line stay leads to the instability in the electrical and mechanical parameter which
reduce the life of the line. With appropriate on site actions, like proper maintenance procedure, the
useful life of the overhead lines can be extended.
Scope:
This operational guideline is intended to carry out the fundamental Line Survey / Checks for its
maintenance and while taking it into service. This requires that the concerned engineer should
prepare the action plan and ensure the availability of required materials, tools and tackles to carry
out this activity.
Prerequisites:
Ensure that necessary permit has been taken from feeding sub-station officer who is responsible for
providing outage and PTW.
The Operating personnel is responsible for ensuring de-energization, isolation and properly
grounding the network where the activity has to be carried out.
Properly Grounding means
All conductor of the isolated working zones, should be shorted with earth by shorting
links at both ends.
The end of the shorting links which are to be connected with conductor & earth terminal
should be fitted with crocodile clip. (Presently all conductor are shorted with safety
chain without earth.A thin layer of Aluminium oxide form on conductor as it expose in
air which behaves like insulator. Due to small surface contact area by the safety chain
&conductor may cause high resistance at the chain contact point causing unusual
behavior. Shorting links should Better performance than safety chain)
If there be any branch line within the working zones, should be isolated/all conductor to
be shorted in similar manner.
If there be any DT within the working zones, the G.O (Gang Operated Switch) of all
DT’s should be OFF to avoid any back feeding from downstream.
During fixing the crocodile clip of shorting links to the conductor, it should be careful :
Before connection the shorting clip to the conductor, the earthing terminal of
the shorting clip should be earth.
Before connecting the shorting clip to a conductor, it (conductor) should be
earth by earth stick & holding the earth stick on the said conductor, the
crocodile clip of shorting links should be fastened with the conductor by
wearing safety gloves & then the earth stick to be removed. Repetition of the
same process of other too conductors must also be ensured.
The Working personnel should ensure the availability of proper tools and accessories, safety
apparels, spares and consumables required for carrying out the work.
Clearance
LV 11 KV
Minimum clearances from any accessible point
The vertical clearance from the highest point 2.5 m 3.7 m
The horizontal clearance from the nearest point 1.2 m 1.2 m
Minimum Ground Clearance
Across the street 5.8 m 6.1 m
Along the street 5.5 m 5.8 m
Line erected elsewhere 4.6m 4.6m
Line with Insulated Conductor 4m 4m
Line crossing 11 KV & LT line 2.4 m
1 35 106
2 50 150
3 70 190
4 95 230
5 120 265
6 150 300
7 185 345
Cable jointing Process
Power cables
Cablesare used for the transmission/distribution of electrical power and consist of three major
components:
Conductors
Insulation
Protective jacket
For cables operating at or above 6,000 volts between conductors, a conductive shield surrounds
each insulated conductor to equalize the electrical stress on the cable insulation. The construction
and requirements are specified in standards such as IS7098 and IEC 60502, IEC6084.
The important steps in the cable jointing of medium voltage XLPE insulated screened
armoured cable
a. Strip the jointing ends of both the cables to be done i.e. stripping of outer sheath, armour, inner
sheath, insulation screen, core insulation and conductor screen. Longer end will be 1050mm and
other end 750mm for 33Kv XLPE 3*400 sq. mm cable. Park the tubes 1000mm and 500mm then
1000mm at the longest side of the cable.
b. All the conductor cores shall be joint with the help of jointing ferrule/mechanical connector and
its crimping by suitable crimping tool.
c. Fill up the space between the ferrule and the core insulation and the crimped portion in ferrule
with semi conducting clay, so that it forms a smooth and round profile with 2 mm.
d. Measure a distance of 20 mm on both sides of the semi-conducting tape. Apply stress grading pad
of 30mm width over the core covering 10mm of the semi conducting tape.
e. Keeping conducting layer of core, wrap the self-amalgamating insulating tape so that the required
insulation thickness is built up. Ensure a tapered profile of the tape towards the semi conducting
layer of the insulation, the self-amalgamating tape should be stretched to 2/3rds of its original width
while applying.
f. Fill up the gap 5mm between self-amalgamating insulating tape and semi conducting layer of core
by stress grading pad of 30mm width.
g. Apply semi conducting tape one layer half over lapped about 10mm on one side of metallic
shielding to the other end in the same manner.
h. Wrap 2 layers of self-amalgamating insulating tape, each half overlapped to cover the semi
conducting tape. Stretch the tape 2/3rds of width while applying as shown in figure given below.
i. Wrap one layer of copper wire mesh on the core to connect the copper tape from end to another
over the tapes.
j. Place the black stress control tube centrally over the joint. Starting at the centre shrink the tube
towards one end and then towards the other end until fully shrunk. Apply heat evenly throughout
the process. When completed adhesive will flow from the ends, wipe off excess.
Role of Earthing in Power Distribution
Earthing In Electrical System
Earthing means making an electrical connection to general mass of earth.
Earth forms an intrinsic part of electricity System.
Earthing of electrical installation is primarily concerned with ensuring safety.
Soil conductivity is an important consideration. Lower the resistivity, easier to get good
earth.
The ground is more effective conductor than copper wire used in electrical circuit.
Earth provides the shortest path for fault current to travel.
Short circuits allows electrical current to by-pass its normal route. Under short circuit,
current follows the least resistance fault to ground.
Reason for Poor Earthing Practices:
Inadequate understanding about technical requirement of earthing & Standards.
Earthing has no role to play during normal conditions.
Lack of compatibility between earthing requirement of electronic equipments & power
system.
Lack of motivation & importance to engineers for keeping earthing & connections in
proper state.
Why Earthing Important?
Earthing in a substation is extremely important for the safety of operating personnel as well as for
proper system operation.
It provides safe passage to earth fault current to flow. E/F current flow through the earth
and may readily cause operation of fuse or E/F relay.
It provides low resistance path to fault current to ensure prompt & consistent operation
of protective devices under fault current.
It protects the equipment other than live parts from attaining potential. Under fault
conditions, frames & enclosures etc may attain high potential w.r.t ground. So these
non-current carrying parts should be connected to ground for the safety of the operating
personal & other human beings for discharging electrical energy to earth.
It protects the equipment from over voltages, HV surges resulting from lightning &
other causes.
It ensures safety of life from electric shocks by grounding all metallic structures and also
avoid hazardous voltage gradients by suitably designing the grounding system. The
potential of earthed body does not reach to dangerously high values during fault.
It ensure that ground potential rise does not have any dangerous effect on
communication system.
It plays an important role in increasing the reliability & continuity of supply service and
stabilizing the voltage conditions.
It has means of discharging feeders & equipments to ground before proceeding with
maintenance.
Attributes Of Good Earth Connection
Lowest soil resistivity.
Low electrical resistance to earth.
Good corrosion resistance.
Ability to carry high current repeatedly.
A reliable life of at least 30 years.
Low loop impedance path of earthing.
Limits of Earthing Resistance
Following are values of earth resistance considered appropriate for different electrical
installation
FUSES
A switchingd)device,
Largewhich
HV and
by EHV s/stnsof one or- more 0.5
the fusion ohms
of its specially designed and proportioned
components open the circuit, in which it is inserted and breaks the current, when the same exceeds a
e) Industrial and Distribution s/stns - 2.0 ohms
LT UNDERGROUND CABLES
The underground cable network of any electricity distribution utility is a vital component of the
LV/HV network of the system. The reliability of the underground distribution network directly
affects the reliability of the overall system and ultimately the overall customer satisfaction.
Scope:
The operational guidelines involved in Testing & Repairing of Cable faults being carrying out for
maintenance of electricity distribution system.
Prerequisites:
Ensure that necessary permit should be taken. Site In-charge is responsible for ensuring
isolation of the faulty cable for both ends & providing the PTW. Ensure that the cable is
de-energized, isolated & grounded.
The workman should ensure the availability of proper tools and accessories, safety
apparels, spares and consumables required for carrying out the work.
Minimum permissible Bending radius
PILC PVC XLPE
Type of Core 1C 3C 1C 3C 1C 3C
Upto 1.1 KV 20D 15D 15D 12D 15D 12D
‘D’ Diameter of the cable
Tests on Cables during fault localization, after repairs or when network modification is done
Test 230/440 V
Megger Test Phase to ground and phase to phase to be tested with 1KV Megger
for 1 Minute/or till reading stabilizes. Minimum IR values should be
50M Ohms.
Depth of the cable
LT cable (1.1kv) 0.6 m
LT OVERHEAD LINES
Overhead lines are the most cost effective and frequently used carriers for electric energy. Exposure
to environment accelerates deterioration; if the fault is not detected and repaired quickly, some of it
will degenerate into serious problems with time. To increase line loading and quality of power
supply, frequent inspection program is required, to locate and repair any significant failure at the
earliest possible stage.
Frequent failure in the Overhead lines can cause extensive damage to the insulator and other
electrical & earth joints which not only interrupts electricity supply but also results in large revenue
losses. Poor/inadequate maintenance in the areas of pole, span length, non-tension electrical joints,
conductor spacing, pole stay leads to the instability in the electrical and mechanical parameter
which reduce the life of the line. With appropriate on site actions, like proper maintenance
procedure, the useful life of the overhead lines can be extended.
Scope
This operational guideline is intended to carry out the fundamental Line Survey / Checks for its
maintenance and while taking it into service. This requires that the concerned engineer should
prepare the action plan and ensure the availability of required materials, tools and tackles to carry
out this activity.
Prerequisites:
Ensure that necessary permit has been taken from SDO/JUNIOR ENGINEER who is
responsible for providing outage and PTW.
The PTW has to transfer to Working personnel after ensuring de-energization, isolation
and properly grounding the network where the activity has to carry out.
The Working personnel should ensure the availability of proper tools and accessories,
safety apparels, spares and consumables required for carrying out the work.
Clearance
Check visually, the condition of Pole base & alignment of pole. If the pole is tilted,
should be straighten & rammed the pole base with brick bats after digging the earth
around the pole base. If any bend occurred at the mid of the pole, should be changed &
new pole to be erected.
Check visually the condition of existing stay
Check the Condition & size of GI wire. It should be 7/10 SWG.
Check the Condition of Guy/Egg Insulator-if any damage observed or is missing, it
should be fixed/replaced.
Check the Condition of tension screw-if any damage observed, it has to be changed.
Tighten the turn buckle if required.
Check the condition of anchor hook.
Check visually the Line Hardware
Condition of Shackle Insulator-if there is any crack, flash mark on the surface of the
insulator, it should be changed.
Condition of Pin insulator spindle- if any damage or bend happened, it needs to be
changed. Check the tightness of the fixing nuts.
Condition of Top hamper- if any tilt observed at top hamper or any damage occurred to
the metal part, it has to be change. Check the tightness of fixing nuts bolts.
Condition of the Double line X-arm. if any damage occurred on X-arm or on the fixing
clamp, it has to be changed. Check the tightness of the fixing Nuts, bolts
All metal parts to be painted by Primer &Aluminium paint for increasing the durability
& life span of the same.
Visual inspection of bare conductor -if any damage occurred on the conductor, it to be
replaced with the same conductor through sleeve joint & the nos. of joint is limited to
maximum 2 per span.
Use of Line Spacer to avoid fall of snapped conductor to ground & also maintaining
equal conductor spacing.
Span length should be maximum 40 m. If the length longer than it, a mid span pole
should be provided.
Line should be sectioned at every 4/5 span, if more, it should be reduced to 4/5 span.
Visual inspection of Earthing should be carried out. If any damage occurred on GI wire,
it has to be replaced with a new complete earth electrode. If there is any joint observed
at earth wire, either the wire or the complete earth electrode has to be changed. Also,
tighten all joints on earth set. Resistance value of earth shall be measured &It’s value
would be < 1 Ohm.
Visual inspection of Earth wire- if any damage/broken happened, it would be re-drawn
by 4 SWG GI wire.
Inspection of Joints – Jumpering should be done by same conductor & will be jointed by
suitable C-wedge connector. Mid span joint has to be done by Suitable Sleeves & the
joint is limited to 2 no per span.
Cable mounting on OH feeder-The cable should be mounted on pole structure through
GI pipe and must be mounted with clamps/STP. Cable be taken upto top of line and
jumper at cable end be through properly crimped lugs and fitted with C-wedge
connector with line.
Service line should be limited to 8 nos.perpole,if the above exceeds the latest instruction
followed by DHBVNsalescircular.
During connection of service cable with the distribution box, the cable/conductor surface
(after opening the insulation) should be cleaned properly and should apply anti corrosive
grease before termination on distribution box.
Configuration of line
LT ARIAL BUNCHED CABLE (ABC)
The AB cable network of any electricity distribution utility is a vital component of the LV network
of the system. The reliability of the AB cable distribution network directly affects the reliability of
the overall system and ultimately the overall customer satisfaction.
Laying of AB Cables
It may be ensure that AB cable should not be dragged on roads/ footpaths etc. It must be laid by use
of rollers & pulleys. In case the AB cable is laid through trees/ vegetation area, branches may be
trimmed to avoid abrasion on AB cables. OH distribution box (3-Φ /1-Φ) should be mounted on
pole for giving service connection. Incoming cable of suitable size for Distribution box should be
jointed with ABC by Mini wedge connector/IPC.
LT ABC (Values as per IS : 6474 – 71 & IS : 7098(1) 88 )
Clearly checking the phase of cable 1 line for R phase, 2 line for Y phase and 3 for B phase.
S. No LT AB Cable Size Current Rating @ 40 deg C
1 3x150+1x120 Sqmm 273A
2 3x95+1x95 Sqmm 235A
3 3x70 +1x70 Sqmm 190A
4 3x50 +1x35 Sqmm 149A
5 3x25 +1x25 Sqmm 99A
6 3x16 +1x25 Sqmm 60A
LT FUSE BOARD
LT fuse board shall be installed on One Pole for Plinth/Pole Mounted DT/H-Pole of the ratings
required at site. Insulated cable from LV side of DTs shall be connected to one side of fuse board
through proper size lug/thimble.
RECOMMENDATIONS
1. Regular Trainings/Seminars shall be organized for field staffs as a part of policy for
improving the capabilities for maintenance of distribution network.
2. Frequently breakdown of feeders shall be thoroughly checked for analyzing the reason of
fault and action shall be taken for minimizing the breakdown.
3. JE/SDO should maintain the Log Book of breakdowns in his area and all the details of
breakdowns must be recorded.
4. Phase balancing of feeders shall be regularly carried out as the balanced distribution
network have less interruptions, no heating of any one conductor and ageing/breaking of
conductors shall be minimized. A balanced network has less technical losses than an un-
balanced network.
5. Analysis of weak and strong area of every sub-division on the basis of data recorded in Log
Book, shall be carried out. After ascertaining the reason of weak area, action should be
taken to make it a strong area.
6. Reasons should be identified for frequent breakdowns of following equipments and
immediate action should be taken: -
Distribution Transformers
Line conductors
U/G cables
Jumpers
Insulators
Overloading of any feeder
7. Tree trimming shall be done on regular basis and the same should be taken as a preventive
maintenance.
Various Faults / Point of concern with Probable Causes and Remedial Actions
Probable Cause of Fault /
S. No. Fault / Point of Concern Remedial Action
Point of Concern
1. Plan for Flashed /Punctured
or broken insulators
checking and replacement.
1. Flashed /Punctured or
2. Plan for Jumper Repairing,
broken insulators
either of same conductor
2. Damaged jumper/Conductor
size or next higher size of
3. Fault due to Tree Contact
Overhead Conductor conductor size.
1 4. Faults due to Birds
Faults 3. Plan for Tree Pruning /
5. Fault due to Cracked Pole
Trimming by using Tree
6. Improper Earthing
pruner instrument.
7. Unwanted wire b/w two
4. Plan to reduce Faults due to
phase
Birds by installing bird
repellent/ falpper .
5. Proper Earthing should be
Probable Cause of Fault /
S. No. Fault / Point of Concern Remedial Action
Point of Concern
done
Power Transformers
Best practices at substation level maintenance
Note down the temperature and record the maximum daily ambient temperature.
Check that temp rise is reasonable. In case of any abnormal variation, check the cooling
system of T/F. If the same is not found in order. Shut down the T/F for further
investigation.
Check against transformer oil level/ temperature. Top up with dry oil, if necessary.
Check for any oil leakage.
Check for any abnormal sound or excessive chattering. Shut down the T/F in case of
abnormal noise, for further investigation
Examine relays and alarm contacts and their operation, fuses etc. Check for relays
functioning clean or replace the contacts if required
Measure earth resistance of the (a) T/F body, neutral and other body parts, (b) Keep
proper record of test results. (Earth testing to be done during driest part of the season)
Examine Firefighting equipments and ensure that these are in order.
In case of bushing -Test oil for dielectric strength Dehydrate or replace the oil, if
necessary.
Use LT sleeve on 11 KV side
Earthing of panels
In case of cooler fan & pump bearing all Lubricate bearings, check gear box. Examine
Contacts, Check Manual control and interlocks. Replace burnt or worn out contacts or
other parts.
I.R. values with 2.5KV rating meggar. Convert it at 700 C and compare the values with
the value taken at the time of commissioning.
Earth resistance of the (a) T/F body, neutral and other body parts, Keep proper record of
test results. (Earth testing to be done during driest part of the season)
Avoid leakage/seepage of oil from main tank to OLTC tank.
Continuously monitoring of DGA test to keep close eye on transformer condition.
To reduce eddy current, proper earthing of transformer body top cover with body is
must.
Date &
Name of Grid:
Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Safety Cotton Rag
ACTIO
PERMISSI
S. ITEM TO BE FREQUEN STATU N
BRIEF DESCRIPTION OF WORK BLE
NO. INSPECTED CY S TAKE
VALUES
N
Note down the temperature and record the
Ambient Temp Hourly NA
1 maximum daily ambient temperature.
Check that temp rise is reasonable. In case of
any abnormal variation, check the cooling
Winding/Oil Temp Hourly 100° C
system of T/F. If the same is not found in order.
2 Shut down the T/F for further investigation.
Check against rated figures. In case of any
Load/Voltage Hourly NA
3 variation, check the TPI.
Check against transformer oil level/ Daily each Above from
Oil level in transformer
1 temperature. Top up with dry oil, if necessary. shift Min level
Daily each Above from
Oil level in bushings Check for any oil leakage.
2 shift Min level
Check for cracked or broken. Replace if Daily each
Relief Vent diaphragm NA
3 necessary. shift
Check for any abnormal sound or excessive
For internal abnormal Daily each
chattering. Shut down the T/F in case of NA
noise. shift
4 abnormal noise, for further investigation.
5 Monthly
6 Dehydrating breather Ensure for free air passage Monthly NA
Tight, lid of the breather for air tightness to
Monthly NA
7 avoid entry
Check oil level in oil cup and make up oil, if
Monthly NA
8 required.
Remove oil from dash pot and pour in fresh oil
Monthly NA
9 where required.
Examine for cracks, Paint and dirt deposits and
NA
Bushing and gaskets gap settings. clean or replace it. Check gaskets Monthly
10 for leakage.
Lubricate bearings, check gear box. Examine
Cooler fan and pump
Contacts, Check Manual control and interlocks. NA
bearings, motors and Monthly
Replace burnt or worn out contacts or other
operating mechanism
11 parts.
Lubricate bearings, Check gear box oil level and
On load tap changer NA
examine contacts. Clean/Replace burnt or worn Monthly
driving mechanism
12 out contacts
Check all circuits independently. Check step by
On load tap changer NA
step operation including limit switches. Attend Monthly
automatic control
13 if found faulty.
Check the I.R.values with 2.5KV rating meggar.
Convert it at 70 0 C and compare the values > 50 M-
Insulation resistance Monthly
with the value taken at the time of ohm
14 commissioning.
Examine relays and alarm contacts and their
Relays alarms,
operation, fuses etc. Check for relays
temperature alarm and Monthly NA
functioning clean or replace the contacts if
their circuits
15 required.
Set the rods for alignment and for proper gap NA
Arcing Horns Monthly
16 adjustment.
Measuring/Protection Check for sparking and tightness of connection NA
Monthly
17 CT’s and oil level.
NA
18 Remote/Manual Switch Check for proper functioning Monthly
NA
19 Firefighting equipments Examine them and ensure that these are in order. Monthly
Note the oil level in the inspection glass of NA
Bucholtz’s relay Monthly
20 Bucholtz’s relay.
Check for dielectric strength. Dehydrate the oil,
Oil in T/F and tap
if necessary. Keep continuous record of test Quarterly NA
changer
1 results.
2 Ventilators Check that air passages are free. Quarterly NA
3 Bucholtz’s relay Check proper operation by lowering the oil Quarterly NA
4 Forced cooling system Megger testing of motors(pumps) Quarterly NA
Checking transformer ground connections for
Quarterly NA
5 tightness.
6 ThermoSyphen Filters Quarterly NA
7 Earth Resistance Check for tightness of earth connections. Quarterly NA
Measure earth resistance of the (a) T/F body,
neutral and other body parts, (b) Keep proper
Quarterly NA
record of test results. (Earth testing to be done
8 during driest part of the season)
Inspect all moving parts, contacts, brake shoes,
On load tap half yearly NA
1 motor etc. Clean, adjust or replace as required.
Check acidity, PPM & BDV & compare with
Oil in T/F half yearly NA
2 standard results.
Check Tan delta,,Sp.Resistively , sludge
Oil in T/F contents, DGA test, compare it with standard yearly NA
1 results.
Test oil for dielectric strength Dehydrate or
Oil filled bushing yearly NA
2 replace the oil, if necessary.
Check for sealing arrangements for filling holes.
Cable box yearly NA
3 Examine compound for cracks.
Examine for cracks and dirt deposits. Clean or
Surge diverter and gaps yearly NA
4 replace if necessary.
Check for tightness of bolts to avoid uneven
Gasket joints yearly NA
5 pressure. Replace damaged gasket.
Check oil pipes valves and plugs for tightness
Pipe connections yearly NA
6 and proper functioning.
7 Foundations Check for cracks, if any and setting. yearly NA
8 Bushings Test the bushings with a Hipet bushing tester yearly NA
and compare with previous figures.
Pockets holding thermo-meter should be
Temperature indication yearly NA
9 checked. Oil to be replenished, if required.
Check pointer for free operation. . Adjust, if
Dial type oil gauge yearly NA
10 required.
NA
NA
Visual observation of transformers and Reactors by going round, should be made daily to check for
any variations in noise, vibrations and any abnormality/leakages from cooler fans, oil pumps,
radiators, valves etc.
Date &
Name of Grid:
Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Safety Cotton Rag
ACTIO
Permissi
Sr. ITEM TO BE FREQUEN STATU N
BRIEF DESCRIPTION OF WORK ble
no. INSPECTED CY S TAKE
Values
N
Examine that switchgear premises doors, circuit N/A
1 General cleanliness Daily
breaker etc. for general cleanliness.
Oil Check oil leakage, if so level be also ascertained. Daily N/A
2
Check for temperature by touch and for any unusual N/A
3 Tank Daily
noise and smell.
Alarms and lamp indication Test the alarm circuit for continuity and lighting N/A
Daily
4 circuit etc. circuit and earthing system.
N/A
5 Safety aids Check safety aids for proper operation/condition. Daily
Check for load conditions on 3 phases, adjust relay N/A
Load Daily
6 setting. If necessary.
Indicating and measuring Check, indicating and measuring instruments for N/A
7 Daily
instruments correct reading and being in proper working order
N/A
1 Auxiliary fuses Check that auxiliary fuses are intact. Weekly
Check oil level in gauges of the tank/poles/oil filled N/A
2 Oil level and gauges Weekly
bushing. Replenish oil if found below normal.
Check for chipped or broken insulator, excessive N/A
Bushing or insulators Weekly
3 dirt film.
Visual inspection to see that equipment is in N/A
Closing solenoid of air
4 operating conditions Drain condensation from air Weekly
cylinder, motor or spring
cylinder.
Visual (or otherwise) inspection to see that N/A
Latch and trip mechanism Weekly
5 mechanism is in operating condition.
Visual inspection to see that solenoid trip device is N/A
6 Tripping solenoid Weekly
in operating condition.
Check cabinet heaters and see that they are in N/A
Cabinet lights and heaters service during cold weather. Replace burnt out Weekly
7 lamps.
N/A
8 Power supplies and wiring See that all power control circuit switches are closed Weekly
Check for external obstructions to breathers and N/A
Breathers and vents Weekly
9 vents and condition of silica gel.
Check whether nuts and bolts are tight and jumpers N/A
1 Nuts, bolts & Jumpers etc. Monthly
are properly connected.
N/A
2 Drain plug Check that drain plug is tight. Monthly
N/A
3 Operation counter Observe and record reading of operation counter. Monthly
Check that breaker can be operated locally and in N/A
Local remote operation Quarterly
1 remote control operation.
N/A
2 Exhaust pipes Check and clean the exhaust pipes. Quarterly
N/A
This test may be conducted and also check that all
Slow closing test Half yearly
the three contacts are made simultaneously.
3
Adjustment of gap (for N/A
MOCB)& other type to The gap may be checked and adjusted to the
4 Half yearly
check the prescribed items required value.
by the manufacturer
Check and tighten wiring connection at terminal N/A
Wiring connections points. Inspect wiring for open circuit, short circuit Half yearly
5 and damaged insulation.
N/A
Check condition of contacts and refinish with fine
file if burnt or corroded. Check contact springs,
6 Aux.Switches operating rods and levers. Check closing and Half yearly
operating position with respect to main contacts
while breaker is slowly closed and opened manually.
To check for alignment of front door N/A
Control and protection
opening/closing for loose fitting, loose wiring of Half yearly
chamber of 11KV switch
7 opening in 11KV switchgear.
N/A
Insulated, jumpers CT and To check for tightness of connections, proper
8 Half yearly
PT in 11KV switchgear insulation and proper geometry.
Check for overheating and proper connection and N/A
11KV cable connections Half yearly
9 insulation.
Check foundation for cracks and settings. Settings of N/A
the breaker tank may break bushings or cause
1 Foundation Annual
misalignment of contacts or bindings of operating
mechanism.
Check condition of paint. Inspect oil valves and N/A
Oil valves and plugs plugs. Flush out oil and clean the oil Annual
2 tank/quenching chambers.
Clean dirty gauge glasses and connections into tank. N/A
3 Oil levels and gauges Drain out and replace bushing oil if found dirty or Annual
discoloured.
N/A
Check to see that screens and baffles in vents or
Breathers and Vents Annual
breathers are not obstructed or broken.
4
Check air circuit breaker or other panels of N/A
insulating material for cracks and cleanliness. Check
5 Panels and cabinets Annual
condition of enclosing cabinets including hinges,
latches, locks door gaskets and paint.
Clean porcelain with water, chloroethene or other N/A
suitable cleaner. Repair chipped spots by painting
with lacquer such as red clay paint. Inspect gaskets
for leaks, tighten bolts. Check insulation resistance
Bushings or insulators with contacts closed and (Tan delta for condenser Annual
type). Check oil sample from bottom of bushing for
dielectric strength and moisture. Replace or
replenish oil if necessary. Check and clean interior
6 at least once every five years.
Tighten all nuts and ground connections. Refinish N/A
Main terminals and ground joint mating surface, if they have been overheated.
7 Annual
connections Inspect ground cable to see that it is not loose or
broken.
Remove the tanks or drain out oil, so that the N/A
contacts can be inspected, dress contacts, if rough
with a fine file. Check contacts voltage drop with
millivolt meter after inspecting reasonable current.
Main contacts Annual
Frequency of contact maintenance should be based
on numbers and severity of faults interrupted, rather
than a definite period. Check adjustment of gap
8 when required.
Check for loss of temperature damage or other N/A
9 Contact pressure spring Annual
deterioration.
Check flexible shunts of contact hinges for N/A
Flexible shunt Annual
10 overheating or damages. Tighten connections.
Check arc-rupturing blow out coils, magnetic circuit N/A
Magnetic, air or oil below
11 arc chutes, de ion grids, oil blasts or other Annual
out devices
interrupters for proper operations.
N/A
Check contact cross head for misalignment breaks
Cross heads Annual
bends or looseness on lift rods.
12
Check contacts for lift rods or brakes, weakening or N/A
13 Lift rods and guides wrapping and pulling out at ends. Checks adequacy Annual
of guides.
Check for loose locknuts, set screws, keys, bearing N/A
bent rods or twisted shafts etc. clean moving parts of
rust, dirt and accumulated grease and oil, wash out
Operating rods shafts and
bearings, pivots and gears with chloromethane or Annual
bell cranks
other suitable cleaner and operate breaker several
times to work out dirt and old lubricant. Lubricate
14 with new grease or oil.
Observe mechanism during several operations to see N/A
that everything is in proper working order. Check
Closing solenoid air solenoid plunger for sticking in guides. Check coil
15 Annual
cylinder, meter or spring resistance and insulation resistance. Dismantle air
cylinder and clean and lubricate. Check spring for
proper tension and closing energy.
Check for condition of valve, and refit as necessary. N/A
Solenoid valves See that moving parts are free to operate. Check Annual
16 resistance and insulation resistance of solenoid coil.
Check that the operation counter is properly N/A
17 Operation counter Annual
registering the breaker operations.
Check that position indicator is properly registering N/A
Position indicator Annual
18 the breaker operations.
N/A
Check for proper setting and adjust as necessary.
19 Dashpots Annual
Clean out and replenish liquid in liquid dashpot.
N/A
Check condition of metal and hardware. Repaint as
Mechanism cabinets necessary. See that door gaskets are tight and Annual
properly dust and vermin proof.
20
N/A
Inspect fuses of circuit breakers in all power and
21 Power supply and wiring control supply circuits, check in insulation Annual
resistance of wiring with devices connected.
N/A
Check dielectric strength of the insulating oil in the
main tanks and oil filled bushings. Oil should be
Oil dielectric test and filtered or replaced if dielectric strength is found to
acidity test dependent on below 25 KV, or if there is a noticeable amount of Annual
actual tripping carbon in suspension on the bottom of the tanks.
Also check ratio and phase angle adjustments, the
acidity of the oil.
22
N/A
Some breakers particularly those carrying high
values of current have a tendency to develop contact
heating if left closed for long periods. Operating and
closing the breakers several times at intervals, as
23 Operation Annual
system operation permit, may alleviate the heating
by wiping the oxide from the contact surfaces, as
well as demonstrate that the breaker is in operating
condition.
Date &
Name of Grid:
Time
Season
Pre-requisite for Maintenance
Caution Order/PTW No.
T&P/material/PPEs
Cotton Rag
Permissi
ITEM TO BE FREQUEN STAT ACTION
Sr. no. BRIEF DESCRIPTION OF WORK ble
INSPECTED CY US TAKEN
Values
N/A
Check for cracked or broken porcelain and
excessive dirt film and to undertake repair of
1 Insulators WEEKLY
chipped spots by painting with lacquer such as red
clay paint.
N/A
Blades and Check that blades are properly seated in the WEEKLY
2 contacts contacts..
Blades and N/A
3 latches and Check that blade latches where provided are WEEKLY
stops engaged.
Check that switches are properly locked in the open N/A
Locks and inter or closed position as required by padlocks or other WEEKLY
4 locks key type locks or interlocks.
Bolts, Nuts & Check bolts, nuts and jumpers for tightness. Apply N/A
1 Quarterly
Jumpers petroleum jelly on male and female contacts.
I.R,value and N/A
HALF
earth Check IR, value with 2.5KV megger and earth
YEARLY
1 resistance resistance. Check that double earthing is provided.
N/A
Check condition of contacts and refinish with fine
Auxiliary & file if burnt or corroded. Check contact spring HALF
2 operating rod and lever. Check closing and opening
limit switches YEARLY
position with respect to main switch contacts or
travel or motor mechanism.
N/A
To check for proper engagement of emergency HALF
Manual operating handle and further its operation is smooth YEARLY
3 operating Rod and satisfactory.
ANNUALL N/A
4
Line & ground Y
Blades and N/A
contacts ANNUALL
Y
5
N/A
N/A
N/A
N/A
Remarks:
Witnessed by:
1) Check that the colour of the silica gel in the breather is blue.
2) Check the breather for any cracks, holes, transparency and oil in the oil cup.
3) Check for any signs of No arcing/pitting mark on Bus-bar & palm connector.
4) Ensure that there is no leakage of oil from gaskets, flanges, valves, radiators,
bushings etc. Ensure oil level of conservator & cleaning of glass of conservator.
10) Check the earthing of fencing (enclosure) with two separate earths.
Witnessed by:
Test Results:
Witnessed by:
7) Check the earthing of the enclosure at two places with separate earthing point.
8) Check the earthing of the neutral with two separate earthing points.
Test Results:
Witnessed by:
1) Check that the colour of the silica gel in the breather is blue.
2) Check the breather for any cracks, holes, transparency and oil in the oil cup.
3) Check for any signs of No arcing/pitting mark on Bus-bar & palm connector.
4) Ensure that there is no leakage of oil from gaskets, flanges, valves, radiators,
bushings etc.
Test Results:
Witnessed by:
7) Check the earthing of the enclosure at two places with separate earthing point.
8) Check the earthing of the neutral with two separate earthing points.
Witnessed by:
Witnessed by:
Sub-Division
Item Description Status
A Type of Substation
B 11 kV Switchgear/RMU
1 Make
2 Physical Condition
(a) RMU Covers
(b) Earth Bus Bar Status
3 SF6 Preassure Gauge Indication
4 Voltage Indicating LED's
5 Grounding
6 Rubber Mat
7 Fault Passage Indicator
Witnessed by:
Check List:
Witnessed by:
Witnessed by:
Witnessed by:
Witnessed by:
Annexure- G.O.-1
Check List- G.O Switch
3 Operating Rod
7 Locking Arrangement
Witnessed by:
Sr
No. Parameters Observations
1 Condition & size of GI wire. It should be 7/10 SWG OK Not OK Remarks
Condition of Guy/Egg Insulator, if any damage or
2 missing observed, should be fix/replace. OK Not OK
Condition of tension screw, if any damage observed
, it has to be changed otherwise to tighten the turn
3 buckle ,if required OK Not OK
4 condition of anchor hook OK Not OK
Visual Inspection
Condition of Disc Insulator, if there is any crack,
flash mark on the surface of the disc, disc should to
5 be change. OK Not OK
Condition of strain clamp of disc insulator, If any
6 crack or flash mark on surface, it has to be change OK Not OK
Condition of Pin insulator, if there be any flash
mark on the insulator surface, it has to be change
7 otherwise check the tightness with the spindle. OK Not OK
Condition of Pin insulator spindle, if any damage
or bend, to be change otherwise check the tightness
8 of the fixing nuts. OK Not OK
Condition of Top hamper, if any tilt observed at top
hamper it has to be straight or any damage occurred
to the metal part, it is to be change, otherwise check
9 the tightness of fixing nuts bolts. OK Not OK
Condition of the V-arm. if any damage occurred on
V-arm or on the fixing clamp, it is to be changed
otherwise check the tightness of the fixing Nuts,
10 bolts OK Not OK
Condition of channel-arm, if any damage occurred
on channel-arm or on the fixing clamp, it is to be
changed otherwise check the tightness of the fixing
11 Nuts, bolts OK Not OK
All metal part to be painted by Primer &Aluminium
12 paint for increasing the durability of life span OK Not OK
13 Visual inspection of bare conductor OK Not OK
Span length should be maximum 40m /50 m (Urban
/Rural) if the length larger than it , mid pole to be
14 provided. OK Not OK
Line should be sectioned at every 4/5 span apart, if
15 more it to be reduced to 4/5 span OK Not OK
16 Visual inspection of Earthing OK Not OK
Visual inspection of Guard wire- if any
damage/broken happened, it would be drawn by 4
17 SWG GI wire. OK Not OK
Inspection of Joints – all jumpers should be done by
conductor same as line conductor or higher rating &
joints to be done by suitable C-wedge connector/ PG
Clamp/D-clamp. Mid span joint to be to be done by
Suitable Sleeves & the joint is limited to 2 no per
18 span. OK Not OK
19 Anti-climbing device OK Not OK
Witnessed by:
Witnessed by:
Witnessed by:
Witnessed by:
Witnessed by:
Witnessed by:
Date &
Name of Consumer: Time
Account No-
Sub-Division -
Permissible Action
NATURE OF WORK Frequency Status
Values Taken
Any visible Cut mark or Puncture on
24 Months N/A
service cable
Checking all required information
24 Months N/A
written on meter box and are visible.
Whether Meter/MCCB is tightly fixed
24 Months N/A
or hanging
All Seals on MCCB & Terminals are
24 Months N/A
proper and not tampered
Consumer cable is at adequate height
Min 5.8
while crossing the street/road (from 24 Months
Meters
ground)
Accuracy of Meter 24 Months ±3%
Witnessed by:
Witnessed by:
Name of DT Date
DT Rating Time
Feeder Name
Permissible Action
NATURE OF WORK Frequency Status
Values Taken
LV cable from DT shall be routed
12 Months N/A
through palm/bi-metallic connector.
Insulated cable from DT to fuse board
12 Months N/A
shall pass through DT meter CTs rings.
Only insulated cable shall be used for
connecting LV side of transformer to 12 Months N/A
fuse board.
Laying of cable from LV side of DT to
fuse board shall be separated using cleat 12 Months N/A
(wooden/PVC).
Proper size thimbles/Lugs used at cable
12 Months
end to join it to fuse board. N/A
Witnessed by: