1) Construction Drawing
4) Material preperation
Guide Wall 2) Is the trench face of the guide wall on the trench nearest line
to the subsequent main excavation vertical to with in 1:200?
2a) Does the top edge of this guide wall face not varying from a
straigth line or the specified profile by more than +15mm in
3mm and shall be without redhges or abrupt irrrgularities.
9) Couplers Fixed