You are on page 1of 3

PROVISIONAL QUANTITY

Bil. Perihal barang-barang/perkhidmatan dan syarat-syarat Unit ukuran Kuantiti / Kadar Harga (RM)
khas Kekerapan (RM)
Untuk diisi oleh Jabatan/Unit Diisi oleh Penyebut

Preliminaries works
i) Prepare insurance i.e. CAR, workmen compensation,
damage to property where necessary
ii) Prepare & supply item required for commencement
of works including site and work preparation i.e. Sum
temporary water and power, procedure of works,
provide all plant and equipment required for the
works, temporary protection
iii) Clearing, cleaning and making good on completion

1 Granular filling (Hard core)


150mm THK Well compacted granular material hard M2 96
core

2 In Situ Concrete Design Mix


Rate for in situ concrete designed mix shall be deemed
to include placing and compaction of concrete.

Reinforced concrete grade C25


a Slabs and appron spread to required dimension M3 14.3
b Perimeter and Ribbed beam to required dimension M3 3.3
c stump & Column to required dimension M3 0.4
d Foundation to required dimension M3 1.6

3 Formwork
Rate for formwork shall be deemed to include the
projections and intrusions and any temporary staging
required.
a Rough finish to ground slabs, apron and column M2 15

4 Reinforcement
Rate for reinforcement shall be deemed to include
labour for cutting, bending, and placing.

a Welded steel fabric reinforcement of 200mm x 200mm M2 96


mesh weighing 3.95 kg/ms and embeded in concrete
(MSA252/A8)
b High tensile bars:nominal diammeter T12(0.888kg/m) Kg 575

6 Steel column
a Supply and install 101.6mm x 4.0mm (9.628Kg/m) mild
steel circular hollow section including cutting, drilling, KG 405
assembling , welding, painting etc.

TOTAL BRING FORWARD


PROVISIONAL QUANTITY

Bil. Perihal barang-barang/perkhidmatan dan syarat-syarat Unit ukuran Kuantiti / Kadar Harga (RM)
khas Kekerapan (RM)
Untuk diisi oleh Jabatan/Unit Diisi oleh Penyebut
TOTAL CARRIED FORWARD harga

7 Roof truss, roof covering, gutter, downpipe


Design, supply, fabricate and deliver to site incuding
fixing and hoisting in position steelroof truss, rafters,
chord, bearers, ties, struts, wall plates, truss
connectors, straps, bolts and nuts and other associated
works including any materials and labour required to
complete the installation of the fabricated steel
trussess
a Roof Truss (Bottom&Top chord)
100x50x16x1.6mm THK Lipped C-Channel Cold Formed Kg 168
as top&bottom chord
b Roof Truss (Diagonal)
75x45x16x1.6mm THK Lipped C-Channel Cold Formed Kg 158
as diagonal
c Purlin
100x45x16x1.6mm THK Lipped C-Channel Cold Formed Kg 224
as purlin
d Roof covering
Metal sheet roof covering including accecories & M2 96
fittings i.e. gutter, rafter, rainwater downpipe
e Tie truss
21.7x2.0mm THK CHS Welded as tie truss bracing Kg 162
f Tie purlin
10mm Diam. Every 1.5m as tie purlin Kg 50

11 Signages
a 1200mm(P) X 600mm(L) signages Sum
b 3200mm(P) X 1200mm(L) signages with G.I steel post

TOTAL BRING FORWARD


PROVISIONAL QUANTITY

Bil. Perihal barang-barang/perkhidmatan dan syarat-syarat Unit ukuran Kuantiti / Kadar Harga (RM)
khas Kekerapan (RM)
Untuk diisi oleh Jabatan/Unit Diisi oleh Penyebut
TOTAL CARRIED FORWARD

*Notes (Shall be read for all item inside this bills of quantities)
1. All Mechanical & Electrical (M&E) / building/ infrastructure/project
components works shall functioning/working well and shall serve its
purposes
2. All M&E/building specifications shall follow JKR and MS standard
or equivalent/ relevant standard
3. All works procedure at all time shall follow JKR & MS standard or
other relevant standard and if any related approved by professional
engineer with practicing certificate before commencment of works.
4. Contractor shall take responsibilty themselves during construction
works until completion of this project of any risk taken
5. All workers shall have valid registration and requirement to
conduct specific task/works according to CIDB, JKR, and other related
local authority requirements
6.If none other stated in this bills of quantities, all brand and material
shall have valid certification from local authorities and standard and
valid liability period.
7(a).Contractor at all time shall satisfy client (KO-Nelayan) quality,
wormanship, instructions for any related works and project
component for this projects.
7(b).Contractors at all time shall refer to KO-Nelayan officer before
proceed for execution of works in oder to satisfy project components
8. Contractor shall follow local authorities S.O.P and relevant
standard during commencement of this project (During this
pandemic COVID 19)
9. Contractor shall at all time bound by rules, regulations and
instruction from KO-Nelayan, contractor have no obligation regarding
to overpowered client (KO-Nelayan) of any charges, complaint and
other related law measurement
10. This Bills of Quantities reads junction with attached drawings(if
any related)
11. If any discprencacies, queries or improvement regarding
specification during construction, contractor shall liase with KO-
Nelayan officer before proceed for execution

TOTAL BRING FORWARD

You might also like