Rafal Tower

King Fahad Road Riyadh K.S.A

Attn: Mr. Ibrahim Al-Imran


Sub: FCU shifting and extension of fire fighting lines

Dear Sir,
Thank you for allowing Mohammed Mahmoud Al-Mowalid Contracting Est. to inspect the site and
submit our best proposal.
S/NO Description Unit price Total price
1 Removal of threaded Rod from unit
Disconnecting chill water pipe lines connections both lines from unit
Disconnecting chill water pipe line also from main supply line
Supply and Installation of joint fitting to cover the connection area
Supply and Installation of new threaded rod on new location 10mm with 5,000 5,000
clamp
Fixing of unit in to new location after hanging with threaded rod
Need to take connection for chill water line from main line and connect
in to unit
Supply and Installation of insulation only on to extension pipe.
Removal of fire line sprinkler as shown by client
Supply and Installation of new line with sprinkler after the gap of
2.40cm
Supply and Installation of water sprinkler 3pcs new with complete
accessories.
TOTAL AMOUNT 5,000
VAT 5% 250
NET AMOUNT 5,250

For the above scope of work our charges will be (5,250) Five Thousand Five Hundred and Fifty Saudi riyals
only.

Note:
1) If any spare part or equipment required will be charged separately.
2) We will follow only above mention scope of work. If client need any work other than our scope of work
will be charged separately.
3) Work will be done with in 4working days.

Payment Terms
50% Advance
50% after the work within 3 days
Best Regards,
Shakeel Raza
Project Incharge
0566406968
Mohammed Mahmoud Al-Mowalid Contracting Est.