Contract n°:
………………………………….-SPE-00001
INDEX
1.0. INTRODUCTION..........................................................................................................................................3
1.1. Purpose and Scope.................................................................................................................................3
1.2. Definitions and Abbreviations................................................................................................................4
1.3. Referenced Documents..........................................................................................................................4
1.3.1. Reference Documents.................................................................................................................5
2.0. HEALTH, SAFETY & ENVIRONMENTAL........................................................................................................6
2.1. General Safety........................................................................................................................................6
2.2. Permit to Work.......................................................................................................................................6
2.3. Tool box meeting...................................................................................................................................6
2.4. Precautions to be taken.........................................................................................................................7
2.5. Responsibilities:.....................................................................................................................................7
2.5.1. Construction manager.................................................................................................................7
2.5.2. Bending Engineer / Mechanical engineer...............................................................................8
2.5.3. Bending machine operator.........................................................................................................8
2.5.4. Safety Supervisor.........................................................................................................................8
2.5.5. QC Supervisor...............................................................................................................................8
3.0. DESCRIPTION OF WORK.............................................................................................................................9
3.1. Preliminaries..........................................................................................................................................9
3.2. Bending operation..................................................................................................................................9
3.3. Finishing bending step:........................................................................................................................10
3.4. PERSONAL AND EQUIPMENT:..............................................................................................................10
4.0. DOCUMENT..............................................................................................................................................10
03.03.16 P AGE 3 OF 13
……………………………………………………….._000_Method of statement site
survey
Replacement of 11 kilometers of the Brega- ALSHOLA ALMUDIA & Ezar for Engineering &
Misurata 34” Gas Pipeline Technical Services.
1.0. INTRODUCTION
the bending of the pipe required for Replacement of 11 kilometers of the Brega-
This document shall also act as a guide to construction personnel on how to carry
out the works safely and in accordance with environmental and contract requirements.
The works shall include the bending of the joints of line pipe, so the pipeline when
welded alongside the trench, will conform to the trench and terrain of right way .
The following expressions and derivatives thereof, appearing in capital letters in the
CONTRACT, shall have the meaning hereby assigned to them unless otherwise
specified, it being understood that such expressions appearing small letters shall have
their common meaning as the context requires. The same principle shall apply to
Definition Description
COMPANY SIRTE OIL COMPANY for Production, Manufacturing of Oil & Gas.
03.03.16 P AGE 4 OF 13
……………………………………………………….._000_Method of statement site
survey
Replacement of 11 kilometers of the Brega- ALSHOLA ALMUDIA & Ezar for Engineering &
Misurata 34” Gas Pipeline Technical Services.
CONTRACTOR Consortium between ALSHOLA ALMUDIA & Ezar for Engineering &
The following referenced documents shall apply and shall be read in conjunctions
ASME B31.8 Gas Transmission and Distribution Piping Systems,” latest edition
…………………………………………………
…………………………………………………
…………………………………………………
NDT Procedure
03.03.16 P AGE 5 OF 13
……………………………………………………….._000_Method of statement site
survey
Replacement of 11 kilometers of the Brega- ALSHOLA ALMUDIA & Ezar for Engineering &
Misurata 34” Gas Pipeline Technical Services.
CONTRACTOR and affiliates related to the project shall comply with COMPANY and CONTRACTOR
HSE policy.
All works shall be carried out under competent, experienced, certified (if required) and qualified
supervision.
Bending of pipe works shall be carried out in accordance with CONTRACTOR Health
Prior to commencing work all Contractors employees shall have attended a joint safety and
Site personnel shall adhere to the site safety policies at all times with emphasis on wearing the
correct PPE relevant to the type of operation being performed. Minimum PPE requirements shall
consist of Safety Boots Ear muff, Ear plug, Safety Glasses, Safety Helmet, Body / Coverall, Gloves,
Safety precautions shall be of paramount importance to prevent any danger to the public and any
operations carried out adjacent to public access shall be closely monitored by the Safety
Department.
Any accident / injury / near miss shall reported immediately to the contractor / Company and
appropriate authorities. Work shall stop and area secured until approved by contractor / Company
In the case major hazards works shall be stopped and appropriate and satisfactory permanent
The company work control system (PTW, Log out / tag out …) shall be applied.
A toolbox meeting shall be performed immediately before the operations, in order to confirm the
P AGE 6 OF 12
Replacement of 11 kilometers of the Brega- ALSHOLA ALMUDIA & Ezar for Engineering &
Misurata 34” Gas Pipeline Technical Services.
All personnel including the staff of a third party must receive an induction before being allowed
on the site. All operational staff on site will be present at safety training to ensure the practical
safety talks.
Such toolbox meeting shall be performed by the responsible of the operations (Mechanic
Supervisor & supported by HSE supervisor) reviewing the operation according to schedule,
verifying the composition of the team as it has been approved and the suitability of the
A signal will be emitted by the bending machine before to start the bending
Be sure that the pipe is introduced into the bending machine with uniform speed
Make sure that the mandrel still in uniform position to avoid any accident
Move off the personnel from area concerned by the evacuation of the curved pipe by
2.5. Responsibilities:
as necessary
Ensuring that all construction activities are carried out to schedule and according to
Ensure that all the persons involved are familiar with the contents of this Method
Statement.
P AGE 7 OF 12
Replacement of 11 kilometers of the Brega- ALSHOLA ALMUDIA & Ezar for Engineering &
Misurata 34” Gas Pipeline Technical Services.
Calculate the amount of bend in the pipe with knowledge of the specifics provisions
Ensuring the run of the winch hydraulically driven which moves the pipe through the
machine.
Reading and analyses the calibrated indicator rod which allow operator to make
applicable
HSSE procedures
▪ Assists the operation with risk assessment and safety plan and any required
safe WMS
▪ Perform all inspection activities and prepare all related reports as per
ITP in force.
P AGE 8 OF 12
Replacement of 11 kilometers of the Brega- ALSHOLA ALMUDIA & Ezar for Engineering &
Misurata 34” Gas Pipeline Technical Services.
▪ Check the pipe bends are free from bucking, out of round, cracks, thinning of
▪ Verify the difference between the maximum and minimum diameter at a pipe
bend does not exceed the specified amount by passing a gauge consisting of two
steel discs each with a 98% of the nominal internal diameter of the pipe
3.1. Preliminaries
Contractor engineer will set out bends and supervise bending using a cold bending machine.
The pipe bending crew will use a bending machine to make slight bends in the pipe to account for
The bending machine use a series of clamps to make a very smooth control in the pipe. All bending
is performed in strict accordance with prescribed standards to ensure integrity of the bend.
Before starting the bending the ovals and the ends of the pipe (chamfrain and from) shall be
The pipe will be marked with marker at a distance of 1D (diameter) to control the bending
steps.
The inside pipe diameter shall not be reduced at any point by more than 2.5% of the nominal
diameter
P AGE 9 OF 12
Replacement of 11 kilometers of the Brega- ALSHOLA ALMUDIA & Ezar for Engineering &
Misurata 34” Gas Pipeline Technical Services.
The seam on any two consecutive pipes is in opposite upper quadrants, separated by a
The ends of each bent length are straight and not involved in any way in the bending the
length of the straight permit easy joining. In no event is the end of the bend closer than 1m
from the end of the pipe or within one meter of a girth weld.
Cold bend shall not be cut in the bend area for bending.
The bending activities will be executed using appropriate equipment (cold bending
LIST OF EQUIPMENT
02 Side boom
01 Bending machine
Mechanical truck
LIST OF MANPOWER
01 civil inspector
04 Skilled labour
HSE Supervisor
4.0. DOCUMENT
P AGE 10 OF 12