Date: 25.02.

2020
Inspection and Test Plan (ITP) Rev.: 00
Page: 1 of 3
I.T.P No.: JV19-016-ITP-FAB
Project: Project: Aqaba Screening Project task 5 of APC storing NEG Job No.: Engineer: DAR
JV19-016
Part Description: Steel Structure Fabrication Client: ARAB POTASH COMPANY Ltd APC
Hold Point H
Type of Test Symbol Ref.Procedure Remarks
Witness Point W
Report Review Visual Inspection VT NEG-VT-AWS-02-(REV-0)
Rev.
Record R Magnetic Test MT NEG-MT-AWS-03-(REV-0) REFERENCE AWS D1.1 ed.2015 &
Test T Client specification

Monitoring M Penetrant test PT NEG-PT-AWS-04-(REV-0)

Internal Document X
Radiographic Test RT NEG-RT-AWS-07-(REV-0)
Quality Control QC
Welding Engineer WE
Ultrasonic Test UT NEG-UT-AWS-05-(REV-0)
Fabrication Fab
Spot witness SW
Full Penetration F.P.
In Process IP
DWG. Review DWG.
Third party TPI

Rev. Date Description Prepared Approved Accepted Accepted


0 25.02.2020 Issue for Approval Quality Manager 3rd Party (Safe Guard) DAR APC
Date: 25.02.2020
Inspection and Test Plan (ITP) Rev.: 00
Page: 2 of 3
ITP No.: JV19-016-ITP-FAB
Sr. NEGEMCO APC DAR TPI
NEG APC TPI Acceptance
SEQUENCE
Scope
DAR Scope
Scope Scope Criteria REMARKS
No. Sign. Date Sign. Date Sign. Date Sign. Date

1 DOCUMENTS
1.1 Reviewing Q.C Plan Rev. Rev. Rev. Rev. Project Specs.

1.2 Reviewing Inspection and Test plan H Rev. Rev. Rev. Project Specs.

1.3 Approved Third party prequalification H H H X Project Specs.


EN 10025-2 & Project
1.4 Material Receiving Inspection H H Rev. H
Specs.
1.5 Reviewing WPSs& Supporting PQRs H Rev. Rev. Rev. AWS D1.1 ed.2015

1.6 Reviewing WPQ documents H Rev. Rev. Rev. AWS D1.1 ed.2015
AWS D1.1ed.2015,
1.7 Reviewing NDT Procedure H Rev. Rev. Rev.
ASTM E709 & E164
1.8 Approved fabrication work schedule H Rev. Rev. Rev. Project Specs.
Project Specs., DAR
1.9 Approved Shop drawing for each member H H Rev. H design
2 FABRICATION

2.1 Cut to dimension marking & Drilling H Rev. Rev. Rev.


DWG, WPS &
2.2 Assembly, Fit up and marking check H Rev. Rev. Rev. Project Specs.,
AWS D1.1 ed.2015
2.3 Welding check (before & during & after) H SW Rev. Rev.
Name Sign. Date
Issued by
Eng. M. Abdel Nasser 25.02.2020
Position Quaity Manager

Issuing Status Proposal FOR APPROVAL 25.02.2020


Distribution NEGEMCO
Date: 25.02.2020
Inspection and Test Plan (ITP) Rev.: 00
Page: 3 of 3
I.T.P No.: JV19-016-ITP-FAB
Sr. NEGEMCO APC DAR 3rd Party
NEG APC TPI Acceptance
SEQUENCE
Scope
DAR Scope
Scope Scope Criteria Remarks
No. Sign. Date Sign. Date Sign. Date Sign. Date

3 NDT FOR MAIN STEEL STRUCTURE


3.1 Q.C Dimensional check H Rev. Rev. Rev. Project Specs.

AWS D1.1ed.2015,
3.2 100%VT for all welds H Rev. Rev. W Project Specs.

AWS D1.1ed.2015 Tabel


3.3 100% UT or RT on F.P welds H W Rev. H 6.1

AWS D1.1ed.2015,
3.4 10% MT OR PT ON ALL WELDS H W Rev. H Project Specs.

AWS D1.1ed.2015,
3.5 Conformance control report from third part H H Rev. H Project Specs.

4 PAINTING
4.1 Check Sandblast H Rev. Rev. W

4.2 Verification of material / quality H Rev. Rev. Rev.

4.3 Certificates of painting material H Rev. Rev. Rev.

4.4 Ambient Conditions H Rev. Rev. Rev.


ISO 8501, SSPC PA2 &
Project Specs.
4.5 Check surface condition for painting H Rev. Rev. H

4.6 Measuring coat thickness H Rev. Rev. H

4.7 Number of coats H Rev. Rev. H

4.8 Conformance control report from third part H Rev. Rev. H

5 MARKING AND PACKING


All parts shall be marked H Rev. Rev. Rev.

5.2 Check packing H Rev. Rev. Rev. NEG SPEC, DRW

5.3 Conformance control report from third part H Rev. Rev. H

6 Final Documentation and handover H Rev. Rev. Rev. contract & specification

6.1 Conformance control report from third part H Rev. Rev. H contract & specification

Name Sign. Date


Issued by
Eng. M. Abdel Nasser 25.02.2020

Position Quaity Manager


Issuing Status Proposal FOR APPROVAL 25.02.2020