7.

The front door of the Distribution Cabinet will be closed after all wiring connections have been
completed.

Figure 7: Installing Optional GMT Fuse Assembly, Part No. 545333, in 1-Row Distribution Cabinet

Covers & front door omitted.


Note: Cannot be installed in 19” system shown.
positions 3, 4, 5, 9 or 10. 23” system similar.

DO FIRST DO THIRD
Remove 2 load busbars where GM T Connect to return busbar
Fuse Assembly will be installed. with 1/4-20 nut & lock washe r.
While depressing tab sideways, Torque to 72 in.-lbs.
slide busbar up and out.

DO SECOND
Plug GMT Fuse Assembly into
supply busbar

Vertiv | NetSure -48 VDC Power Systems Installation Instructions (Section 6025) | Rev. X 15