Greater Colombo Water and Wastewater Management Improvement Investment Programme

System Rehabilitation for NRW Reduction in South Part of Colombo City

Summary of Man Power Detail for Site Works

Date : 16-July-2020

Man Power Machineries


Sub Contractor
Day / Location /
No. Name of the road Type of Work / Compactor Remarks
Night DMA Fitter / Fusion
Direct Team Labour Excavator JCB Asphalt Cutter Generator
Skill labour Machine
Working Not working

Night 1 Kirula road 31A Thrust block concreting Direct 1 4 - 1 - 1 1 - 1

Night 2 Kassappa road 35B Pipe laying Sub 1 4 - 1 - 1 1 - 1

Night 3 Roxy garden by road 38B Pipe laying Sub 1 9 1 - 1 1 1 - 1

Night 4 Fussels lane 37B Pipe laying Sub 1 5 1 - - 1 1 - 1

Night 5 Fussels lane 37B Pipe laying Sub 1 3 1 - 1 1 1 - 1

Night 6 IBC road 38B Preliminary work Direct 1 3 - - - 1 1 - 1

Night 7 Thalakotuwa garden 33D Pipe laying Sub 1 3 - - 1 1 1 - 1

Night 8 Mayura place 37C Pipe laying Sub 1 3 - 1 - 1 1 - 1

Night 9 Thimbrigasyaya road 31A House connection - - - - - - - - - - Cancelled

Night 10 Havelock road FM Trial trench excavation Direct - 4 - - 1 1 1 - 1

Night 11 Hampden lane FM Trial trench excavation Direct - 3 - - 1 1 1 - 1

Night 12 Pamankada road FM Pipe laying Direct 1 7 - 1 1 1 1 - 1


Total Man
9 48 3 4 6 11 11 0 11
Power
TOTAL Sub Contractor 6 27

Direct Team 3 21