Daily Progress Report No Work Ref Pictures


Client KHABARI GENERAL TRADING LLC Date 26/01/2020
Removal and Installation of light luminaires on External Grid Facade of
Subject Job on Schedule Yes
YAS W Hotel
Purchase Order Job Number DMES-20-226 LS/DR
Work day (Hours) 10 Overtime 2 Stand-by NO
Team Size L3-2 L2/L1-14 GST-4 Job Duration 61 Days Exp Tech Days
Actual Start Date 18/01/2020 Target Finish Date 19/03/2020 Exp. Total Mandays

Client Contact VIJAY 565591665 Sales Manager Preet Sagar


Actual Team Size L3-4 L2/L1-14 GST-4 Current Duration 8th Day Act. Mandays 146
Completion
Stand-by today NO Overtime today 2 19/03/2020
Date
00:00
01:00
02:00
03:00
04:00
05:30
Leaving from camp
06:00
07:00 Arrived at site
08:00 Tool box Conducted, Material arrangement, Rope rigging & LED Light removal & Installation Started.
09:00 LED Light removal & Installation Going on
Daily Activity
10:00 LED Light removal & Installation Going on
11:00 LED Light removal & Installation Going on
12:00 Lunch Break
13:00 LED Light removal & Installation Going on
14:00 LED Light removal & Installation Going on
15:00 LED Light removal & Installation Going on
16:00 LED Light removal & Installation Going on
17:00 LED Light removal & Installation Going on
18:00 Job completed for today and done good house keeping.
19:00

Comments

Productivity LIGHT PROGRESS / DAY


TOTAL MAN POWER ZONE BALANCE LIGHTS BALANCE LIGHTS FOR
Removed INSTALLED
FOR REMOVAL INSTALLATION
22 TOWER-B,Zone-6 & 7 220 3577 4 4874

Dive-Tech Picture
PRANESHKUMAR GOVINDA GHALE ZONE 6 & 7
Project Manager Supervisor Comments