METHOD STATEMENT
Table of Contents
1. Revisions Status
2. Scope/Objectives
3. References
5. Responsibilities
6. Procedures /Method to be Employed
7. Manpower Requirements
8. Material Requirements
9. Equipment Requirements
The scope of this method statement covers the erection of steel platform for equipment. The
purpose of the documentation emanating from this statement is to ensure that quality control
objectives are maintained and accurate records are established for all related activities. The
objective is to ensure that the construction plan is executed, controlled and documented in
compliance with the contract drawings and specifications.
3.0 REFERENCES
• Contract Specifications
• Contract Drawings
• Program of Works
• Material & Drawings Submittal Schedule
• Related Sub-contract Works’ Method Statements
Specific safety measures have to be follow ed as applicable. All safety measures are covered
separately in the project safety plan.
5.0 RESPONSIBILITIES
• The steel platform works activities are carried out according to specifications and
drawings.
• Work progress is carried out according to the planned program and all the equipment
required to execute the works are available as per the project plannin g and are in good
condition.
• Coordination with the Consultant, Site Engineer, Safety Engineer and Subcontractors for
the safe and proper execution of the work.
• Specific attention is paid to all safety measures and quality control in coordination with
Safety Engineer and QC Engineer and in line with HSE plan and Quality plan.
• Coordination with the Safety Engineer to ensure that the works are carried out in a safe
working atmosphere.
• Coordination with the QC Engineer for test s to be carried out and initiate for the
inspection for the finished works.
• The implementation of any request that might be raised by the Consultant.
• Efficient daily progress has been obtained from all the equipment and manpower
engaged in the work and check the same against the daily report received from the
Foremen.
• The pass age of all the revised information to the Foreme n and ensure that it’s being
carried out properly.
• Coordination with the surveyor and plan the survey works in advance as per the work
sequence.
• The carrying out of the works as per the specifications and the related quality procedures.
• Inspection of the completed works and requesting for the Consultant’s approval.
• Maintena nce of complete inspe ction and test records for any further reference.
• The implementation of all safety measures in accordance with the HSE plan and that the
whole work force is aware of its proper implementation.
• The implementation of safety measures is adequate to maintain a safe working
environment on the site.
• Inspection of all the site activities and training personnel in accident prevention and its
proper reporting to the Project Manager and the Consultant.
• The site is maintained in a clean and tidy manner.
• The carrying-out the work and the proper distribution of all the available resources in
coordination with the Site Engineering on a daily basis.
• Daily reports of the works are achieved and coordinated for the future planning with the
site Engineer.
• Incorporate all the QC and Safety requirements as requested by the concerned Engineer.
• Meeting with any type of unforeseen incident or requirement and reporting the same to
the Site Engineer immediately.
QUALITY SYSTEMS MANUAL PAGE : 6 of 8
METHOD STATEMENT DOCUMENT NO : REV
• Steel chequered plate of 6mm or 8mm thickness shall be used for the construction of the
steel platform.
• Chequered plates shall be fabricated to match the platform requirements.
• Steel beams shall be erected on supporting columns as per approved shop drawings.
• Welding shall be carried out as per shop drawings.
• Handrails, staircases for the platform shall be fabricated and fixed in position as per shop
drawings.
• Painting of required color shall be done.
• Foremen
• Welders
• Helpers
• Driver
• Generator
• Welding Rods
• Cutting Sets with gas cylinder
• Steel Pipes, angles, beams and columns, chequered plates 6mm thick
• For all the steel work activities, adequate barriers, signboards, advance -warning signs,
traffic control and flashlights shall be provided. Warning tape with rope shall be installed
all around the steel platform area.
• All the quality control documentation related to the steel platform should be approved
before commencing the work. And as follows:
Ø QCP for steel works
Ø ITP for steel works
Ø Project Quality Plan
Ø Project HSE plan
Ø Check list sheets for the steel works
Ø All material approvals
QUALITY SYSTEMS MANUAL PAGE : 8 of 8
METHOD STATEMENT DOCUMENT NO : REV
Approved