Rea Project Supervision PDF
Rea Project Supervision PDF
Table of Contents
List of Acronyms v
FOREWORD vi
1. Introduction 1
2. Contract Effectiveness 2
8. Construction Supervision 16
9. Progress Reports 19
11. Connections 24
and Experience 65
ANNEX 24: Invitation Letter for Commissioning of Bulk Metering Units and Auto Reclosers (UETCL) 75
List of Acronyms
BOQ Bills of Quantities
ERA Electricity Regulatory Authority
ESMP Environmental and Social Management Plan
MV Medium Voltage
NEMA National Environmental Management Authority
NSSF National Social Security Fund
PPE Personal Protective Equipment
PPDA Public Procurement Disposal of Public Assets Authority
REA Rural Electrification Agency
UNRA Uganda National Roads Authority
UWA Uganda Wildlife Authority
VAT Value Added Tax
SCC Special Conditions of the Contract
FOREWORD
The Rural Electrification Agency (REA) Project Management Manual is a guideline that contains proce-
dures, processes, policies, checklist, and parameters needed to enable the day to day management
and supervision of REA projects from the design stage through to the construction and commissioning
stages; including connections in line with environmental and social safeguards.
Anchored in the dictates of the Rural Electrification Strategy and Plan (RESP 2013-2022) for REA to adopt
technical standards for all construction design, this manual is part of the Agency efforts towards ensuring
a 26% rural electrification access in an effective and efficient manner by 2022. In this regard, therefore,
the manual offers guidance on a range of key project management aspects including; project docu-
mentation and progress reporting; engineering design and survey; tests and inspections; change man-
agement, commissioning, achieving connections, risk analysis and stakeholder engagement.
Actual templates are provided in the manual to offer practical guidance on how to handle documen-
tation for the various supervision aspects throughout the project cycle including; Factory Acceptance
Test (FAT) checklists for power line components and equipment; checklist for legal and regulatory com-
pliance; payment certificates, contract change order form, site inspection checklist, report templates;
shut down and commissioning documentation templates and sub-contracting criteria.
The Agency acknowledges the efforts that have been put into this process to produce working docu-
ments for better service delivery. This manual has been developed through a collective effort of a team
of Engineers, environmental and Social Safeguards personnel with vast experience in power line con-
struction and project management. The REA Project Development and Management team, led by the
Department Manager, has particularly been instrumental in developing this manual.
It is my hope, therefore, that all project management teams at the Agency will adhere to the guidelines
here to ensure effectiveness and efficiency as REA dedicates its work to the socio-economic transforma-
tion, in an equitable and sustainable manner for rural development.
EXECUTIVE DIRECTOR
Revision Record
ISSUE
For issue to all REA and Accredited Contractors’ or Consultants’ staff involved with the design, construc-
tion and supervision of overhead distribution lines, and is for reference by field, technical and engineer-
ing staff.
Where this Manual is issued as a controlled document replacing an earlier edition, remove and destroy
the superseded document.
DISCLAIMER
REA Manuals are subject to on-going review, the information contained in this document may be
amended by REA at any time. Inconsistencies may exist between standard documents. In such instanc-
es, the most recent Manual shall prevail.
This document has been developed using information available from field and other sources and is
suitable for most situations encountered in Rural Electrification. Particular conditions, projects or locali-
ties may require special or different practices. It is the responsibility of the Project manager, Engineering
supervisor, Contractor, assured quality controller and the individuals involved to make sure that a safe
system of work is employed and that statutory requirements are met.
REA disclaims any and all liability to any person or persons for any procedure, process or any other thing
done or not done, as a result of this Standard.
INTERPRETATION
In the event that any user of this manual considers that any of its provisions is uncertain, ambiguous or
otherwise in need of interpretation, the user should request REA to clarify the provision. REA’s interpreta-
tion shall then apply as though it was included in the Standard.
1. Introduction
Rural Electrification Agency (REA) is a semi-autonomous body created by an Act of parliament under
Ministry of Energy and Mineral Development. REA is mandated to implement rural electrification pro-
grams in Uganda and has a vision of achieving universal access to electricity by 2035. Since its formation
in 1999, Government of Uganda through Rural Electrification Board and REA has implemented several
rural electrification projects.
To effectively carry out this function on behalf of the Government of Uganda, REA has placed emphasis
on Project implimentation and Supervision.
This supervision manual is designed to guide the Project Personnel in the day-to-day supervision of Imple-
mentation of Rural Electrification projects with a key emphasis placed on ensuring quality in delivery of
the projects as a whole.
This manual issues guidelines, content checks and quality checks in activities, procedures and docu-
mentation used to manage factors affecting project implementation including Cost Management, Time
Management, Quality Management, Scope Management, Stakeholder Management and Risk Man-
agementS.
The manual discusses key areas of project implementation including contract effectiveness, initial proj-
ect documentation, Engineering Design and Survey, Tests and Inspections of materials and equipment,
considerations for effectively managing the contract, construction supervision, report formats, pre-com-
missioning and commissioning guidelines, connections and project closure.
i. Project Contract
ii. REA Construction Manual
iii. Manufacturing manuals, Standards and Specifications for materials
The scope of work consists of supervising all works including designing, surveying and line route profiling;
pegging and bush clearing; procurement and delivery to site of MV and LV overhead line construction
materials including distribution transformers, bulk metering equipment and switchgears, overhead bare
conductors, treated wooden poles, line insulators and related hardware accessories and protection
devices; medium voltage and low voltage network construction; installation of distribution transformers
and protection equipment and network testing; pre-commissioning and commissioning; development
and submission of as built drawings.
The manual contains a Project Implementation Cycle chat that clearly highlights the documentation,
approvals and stakeholders involved at each stage of the project
2. Contract Effectiveness
The Project Engineer should ensure the following documents have been filed.
Notes:
a) Advance payment will be paid to the Contractor within 30 days after presentation of an uncon-
ditional Bank Guarantee of an equivalent amount from a reputable licensed commercial bank
acceptable to the employer. The Advance Payment will be repaid by deducting twenty percent
(20%) from each certificate paid.
b) Insurance Cover
The minimum cover for insurance of the Works, Plant and Materials is: Full Replacement Value
i. The minimum cover for insurance of Equipment is: Full Replacement Value
ii. The minimum cover for insurance of property is: Full Replacement Value
c) The standard form of Performance Security acceptable to the Employer shall be an Unconditional
Bank Guarantee in the format presented in Section 9 of the Bidding Documents
Refer to Section 8: SCC and Section 9 of the Contract for more details on Performance Security and
Advance Payment.
The Project Engineer shall review them to ensure compliance to REA’s requirements for those materials
and shall issue an Approval of Technical Specifications when compliance is met.
Drawings marked Returned for Correction shall be corrected by the Contractor and sent to the Engineer
for further review. When a drawing is marked Reviewed or Reviewed as Amended, the Contractor will
be allowed to use the drawing for manufacture of the products. The Contractor shall, however, make
corrections according to the remarks given by the Engineer. Manufacturing starting prior to receipt of
“REVIEWED” drawing is done at the Contractor’s own responsibility.
The Engineer’s approval does not in any way relieve the Contractor of his full responsibility for the correct-
ness of his documentation and the proper functioning, quality and compliance with the Specifications of
all plant and equipment supplied by him.
i. Major Tasks – Brief description of major tasks involved in the project implementation
ii. Implementation Schedule – Use MS Project or equivalent and present using a Gantt Chart
iii. Risk Assessment – Indicate possible risks to this plan and mitigation actions
iv. ESMP and HSP (Refer to Annex 5)
Chapter three: Implementation Support
Action by REA
The Engineer shall review the Implementation plan, prepare an assessment report and make recom-
mendation for approva, rejection or modification where applicable. The report shall entail the following:
The amount to be withheld for late submission of an updated Program is: 0.2% of the contract sum
Action by REA
The Engineer shall ensure that the Procurement plan is submitted within 28 days after contract start date.
The Engineer in consultation with Procurement and Disposal Unit shall review the plan, prepare an assess-
ment report recommending approval of Supplier, Clearing Agents, Method of Packaging, Transporter
and Risk management plan.
i. Certificate of Incorporation
ii. Valid trading license
iii. Income tax clearance
iv. Valid VAT registration certificate
v. Valid PPDA registration certificate
vi. Articles and Memorandum of Association
vii. Particulars of the Directors (Company form 7) with copy of identification(driving permit, national
ID or passport) and detailed CVs with passport photos attached
viii. Office premises
ix. Valid NSSF registration certificate
x. Audited books of accounts for the previous 1 years
xi. Should not be suspended by PPDA or development partners
xii. Recommendation from registered engineer
xiii. Acceptable code of conduct
Minimum Technical Experience and Capability of the Firm shall be: Proof of existence of the company
for 2 years and proof of two (02) similar works done in the last 2 years similar in scope, amount and com-
plexity.
Table 2: Key personnel with the minimum level of qualification and experience
1 Project Manager/ Electri- BSc. Electrical Engineering with Class B ERA certificate 2 years
cal Engineer
2 Foremen Ordinary diploma in electrical or equivalent 5 years
Action by REA
The Engineer shall review the company profiles (Attached in Annex 28 is the full subcontracting criteria),
prepare and submit an assessment report recommending approval, rejection or modification where
applicable.
Chapter one: Brief description of the general geographical, environmental and physical characteristics
of the site (include soil types, general topography, vegetation and plantations in the area, swamps, farm
lands, rivers, water bodies e.t.c), game reserves
Chapter two: Economic Analysis – economic activities carried out in the area
Chapter three: Development projects and plans within the project area – such as resorts, tourist attrac-
tions, cultural sites, local council and district development plans especially concerning water and roads
which can be obtained from UNRA and District physical planners
Chapter four: General Technical Considerations: This chapter should briefly discuss the existing power
network from which the Tee-off will be; taking into consideration the following:
a) Substation
i. Installed capacity, protection settings (grading)
ii. Any future expansion plans such as construction of spare bays
b) General condition of the existing power line
i. The construction type
ii. The length of the line
iii. Details of the primary substation from which the existing line originates
iv. Current voltage profile and load profile of the primary substations (Should be within the 10%
voltage drop tolerance)
v. Nature of load that the feeder serves - Industrial loads or domestic loads
vi. Voltage at the point of connection (Measured from the nearest Transformer)
Chapter five: Survey methodology – the methodology shall detail the line route survey, structure spotting,
and profiling. The line route survey shall be conducted using high precision survey equipment that shall
be compatible with PLS CAD. The profiling and network modelling shall be done using PLS CAD. Should
describe considerations taken during the survey activity, Personnel experience and qualification of team
executing the survey activity, Tools used (RTK, GPS). Survey Methodology is attached as Annex 6.
Chapter six: Design criteria – describe type of structures used, power line components sizing, type of
construction and their justification (simulations and calculations done).
Chapter seven: Construction Methodology – should constitute of the quality control plan, considerations
to ensure that the method presented is followed, the construction type, transition from one stage to an-
other, how to ensure quality of works and how to ensure timely completion among others. Methodology
on how to deal with swamps, Safety of personnel, PPE, e.t.c.
Chapter two: Findings from site inspection and review of Engineering Design and Survey Report by the
contractor
For other materials and accessories, the manufacturer shall submit for review and approval material
specifications and production line/ routine test reports (should include serial numbers) for REA materials
prior to dispatch.
Action by REA
The Engineer shall review production line test reports and the manufacturer’s test procedures and pro-
tocols in line with respective REA manuals and/or IEC Standards, and recommend approval for FATs or
dispatch.
Below is a list of major equipment and tests which shall be carried out.
5.2 Poles
The following tests and checks will be carried out in accordance with REA Wooden Pole Treat-
ment, Transportation, Handling and Erection Manual:
i. Visual inspection
ii. Measure of Pole Lengths
iii. Measure of Pole Top Diameters
iv. Cantilever test to assess mechanical strength
v. Midpoint test to assess mechanical strength
vi. Retention tests to measure how much treatment chemical has been retained in the pole
vii. Penetration tests to ascertain how far the chemical has penetrated into the sap wood
Attached is the Pole’s Pre-dispatch Checklist as Annex 7.
5.3 Transformers
The following tests should be carried out in accordance with REA Transformer Manufacturing Manual:
i. Insulation resistance test to assess the condition of insulation of all insulated parts of a transformer
ii. Vector group test to confirm that the vector group is provided
iii. Voltage ratio test to ensure that the turns ratio of the windings is correct and that the tapping on
any of the windings have been made at correct position
iv. DC winding resistance test to measure the DC resistance between lines of all windings and to
detect faulty or poorly made connections. Test results are important in full load loss measurement
v. Oil dielectric test to confirm the electrical strength of the transformer oil
vi. Separate source voltage withstand test to determine the integrity of the insulation between wind-
ings and earth
vii. Induced over voltage test at high frequency to verify voltage withstand strength between the
windings and Earth, the withstand strength between the phases, and between turns of a phase
under test
viii. No load test (core loss- hysteresis loss and eddy current loss) to determine the No Load losses of a
transformer. It also checks whether any damages have been caused to windings and insulation
from prior tests
ix. Full load loss test (copper losses) to assess the Full Load Loss (copper loss) and the impedance
voltage of a transformer
x. Zero sequence impedance test to determine the zero sequence impedance of the transformer
xi. Sound level test to determine the sound level of the transformer
xii. Temperature rise test to determine the temperature rise of the transformer
xiii. Measurement of electrical break through voltage of copper wire to assess the insulation of copper
wire
xiv. Dry power frequency voltage withstand test to identify any flashover or punch of the bushings
xv. Pressure testing to ensure that the finished transformers withstand high pressure and to detect any
leak points
Attached in Annex 8 is the FAT Checklist for Transformers
5.4 Conductors
The following tests should be carried out in accordance with IEC 61089 and IEC 889;
5.5 Insulators
Tests are carried out for the different insulators
a) Composite line post insulators tested in accordance with IEC 61952 and IEC 62217
i. Tensile load test
ii. Visual examination
iii. Verification of dimensions
iv. Tests on interfaces and connections of metal fittings
v. Thermal-mechanical pre-stressing
• Water immersion pre-stressing
• Verification tests / visual examination
• Steep-front impulse voltage test
• Dry power frequency voltage test
vi. Test of housing
• Accelerated weathering test
• Tracking and erosion test
• Flammability test
vii. Test for the core material
• Dye penetration test
• Water diffusion test
viii. Assembled core load tests
• Verification of the maximum design cantilever load
• Tensile load test
ix. Dry lightning impulse withstand voltage test
x. Wet power frequency test
xi. Cantilever failing load test
Attached is the checklist for Composite Line Post Insulators in Annex 13
b) Pin insulators tested in accordance with IEC 60383
i. Power frequency puncture voltage
ii. Mechanical failing load test
iii. Proposity test
iv. Verification of dimensions
v. Visual inspection
Attached is the checklist for Pin Insulators in Annex 14
The Engineer shall move with the list of materials’ serial numbers issued by the manufacturer during the
FAT and carry out a visual Inspection to confirm delivered quantities and serial numbers at the site store
or yard.
Chapter one: Introduction – details of contract, brief of procurement process and relevant approvals
issued
Chapter two: Assessment of manufacturer’s Legal and Regulatory Compliance certification and experi-
ence (Checklist is attached in Annex 16)
Upon submission by the contractor, the User Department shall then review the above mentioned doc-
umentations and submit to Contracts Committee through Procurement and Disposal Unit for consider-
ation.
Based on the facts collected from the site, payment assessment and certification shall be done by Engi-
neer. The certificate shall then be forwarded for payment.
The amount to be withheld for late submission of an updated Program is: 0.2% of the contract sum
Time Extension
The contractor shall formally request for time extension with justification. The Engineer shall review and
recommend for time extension if the grounds are acceptable. This shall be issued through a Change
Order. (Attached as Annex 18)
Note: In-case there is a cost implication involved, a contract variation shall be initiated by the Engineer.
No Contract
Contract Amendment
Amendment
Background to the issue
a) Submission of Change
Proposal Stakeholder Stakeholder
Request
Justification/ Benefits
Justification
Cost/ Benefit Analysis
Impact on Cost
Impact on time
b) Review and Assessment Engineer Engineer
Impact on Quality
Impact on stakeholders
Qualification
Recommendation
Action by REA
The Engineer shall use the above mentioned checklist to ensure compliance and the findings shall be
included in the monthly progress report.
8. Construction Supervision
The Engineer shall do a walk-patrol while inspecting works carried out on the power line and the following
minimum checks shall be done at each stage of construction:
a) Pit Excavation
Check that pole pits have been excavated to the right depths (1/6 of the pole height) and widths. Ensure
that poles are positioned prior to pit excavation. Take note of the type of soil where each pit has been
dug.
After the inspection and verification of all pits, the Engineer or his representative shall issue an approval
prior to pole erection.
b) Pole Erection
Ensure that all poles erected are in a good physical condition as per the REA Pole Treatment,
Handling, Transportation and Erection Manual. Ensure that in swampy areas, murram is ade-
quately filled. Erected poles must be fitted to be firm, plumb and are properly aligned with other
structures in the line route. Poles should not be interfered with by cutting to make up for shallow
pits. Verify that the poles erected have the manufacturer’s pole tags.
For construction of lines with overhead continuous earth-wire, ensure that the earth-wire is in-
stalled on every other pole for both MV and LV. No pole shall be erected without earth-wire.
After the inspection and verification of erected poles, the Engineer or his representative shall
issue an approval prior to dressing.
c) Dressing
Check to ensure that all the required pole hardware and accessories as per the approved struc-
ture drawings have been installed on the respective structure type.
After the inspection and verification of all dressed pole structures, the Engineer or his represen-
tative shall issue an approval prior to conductor stringing.
d) Installation of Stays
Ensure that the required number of stays per structure, as per the approved structural drawings
have been installed. Ensure that stay pits are to the standard depths (1/6 pole height). Ensure
that the required materials for a stay assembly as per the REA structural drawings are there. En-
sure that the stay blocks are concrete or galvanized steel plates.
e) Conductor Stringing
Ensure that stringing is conducted using conductor drums installed on standard drum jerks. En-
sure that conductor is not be rolled on the ground to avoid damage of conductor surface. Care
should be taken while stringing/ running out conductor to avoid kinking, twisting or abrading the
conductor in any manner. Stringing shall be planned in such a way that terminations are done
at section structures.
After the inspection and verification of all stringing works, the Engineer or his representative shall
issue an approval prior to installation of stays.
f) Conductor tensioning and Sagging
Check that the conductors have been strung with precision to ensure that the correct ground
clearance and tension is attained.
After the inspection and verification of all tensioning and sagging works, the Engineer or his rep-
resentative shall issue an approval prior to Installation of Jumpers.
g) Jumpers for section structures
Check to ensure that jumpers are of proportionate length shall be used to avoid compromising
clearance during windy conditions. Jumpers joining adjacent conductors having angle of sepa-
ration greater than 120% shall be supported by a pilot spindles. Ensure that a pair of adequately
sized PG clamps are used in jumper terminations.
After the inspection and verification of all jumpers, the Engineer or his representative shall issue
an approval prior to earthing of transformers.
h) Earthing of transformers
Ensure that the earthing of transformers is as per the Construction Manual. Ensure that the earth
values do not exceed 5 ohms for both LV and HV. The HV side and LV side of the transformer shall
be earthed separately and the respective earth pits shall be located a distance not less than 5m
apart. The earth wires used/running from the transformer to the ground shall be neatly stapled
on the wooden structure. The earth pits shall be dug up and earth pits filled with components
required for earthing such as charcoal, salt, water, copper rod among others.
After the inspection and verification of all earthing works, the Engineer or his representative shall
issue an approval prior to installation of surge arresters.
i) Installation of Surge Arrestors
Ensure that surge arrestors have been installed on all transformers, underground cables, and
terminal poles. Ensure that surge arresters have installed every 10 km for lines without continuous
overhead earth-wire.
After the inspection and verification of all surge arresters installation works, the Engineer or his
representative shall issue an approval.
The Engineer shall ensure that the consultant has deployed the required human resource as per the
contract.
The Engineer shall submit a daily report in the format provided by REA. The consultant shall also submit
monthly and quarterly reports in the format provided below.
The consultant shall certify works and recommend payment by submitting a payment certificate based
on the contractor’s claim. The format shall be in the form of BoQs of works.
The Consultant shall review and approve all technical specifications, attend FATs, issue approvals after
every stage of installation works through the clerk of works.
9. Progress Reports
These will be written by all focal stakeholders as expounded below;
Also, after every site inspection, the Engineer shall submit a monthly report including:
Chapter three; Stakeholders engagement – district meetings, site meetings, interactions with the com-
munity, service providers
Chapter four; Findings from the site inspection – stores, yard, office, quality of workmanship, level of
deployment, observations and instructions from the works inspection including aspects of; engineering,
environment (consideration for forest reserves, wetlands, trees, crops, human settlements, tourist/cultural
sites), social (engagement and participation), health and safety (accident, use of PPE, safety of people
around)
Chapter six: Update on payments, date certificate was submitted, amount paid and date payment was
made
Chapter two; Update on payments; date certificate was submitted, amount requested for, amount re-
ceived and date payment was received
Chapter three; List of materials at the site stores to support claims made in certificate
Chapter four; Personnel deployment for the next month (details on sub-contractors if any)
Chapter six; Progress of works and actions taken to address instructions given at previous site inspection
including aspects of; engineering, environment
Monthly report:
Chapter one; Introduction - consultant’s contract details, summary of works contract
Chapter two; Deployment of Personnel, work done and actual input man hours
Chapter three: Assessment of level of compliance to Approved Engineering Design and Survey Report
Quarterly report:
In addition to the content of the monthly report, chapters on the following should be included in the
quarterly report
Upon completion of works, the contractor shall formally communicate to REA which shall then schedule
a Pre-Commissioning date. On successful completion of this exercise, the commissioning and handover
of the power network shall then carried. Procedures for both activities are explained below.
On rectifying snags, the contractor shall request the project manager to issue a certificate of practical
completion of works, and the project manager will do so upon deciding that the work is complete. The
employer shall take over the site and works within seven days of issuing the certificate of completion.
However, the Contractor is liable for any defects that may arise during the Defects Liability Period.
i. As-built drawings
ii. Pole schedules
iii. Warranties for materials
iv. Letter from any LC Chairman affirming that all complaints from the community have been dealt
with.
• Data specifications
• Routine test certificates
• Data lists with required amendments by the Engineer shall be incorporated. The contents
of the lists shall correspond to the schedules of this document. Data lists will be regarded
as binding for the manufacturer.
• Dimension drawings. They shall be regarded as binding for the manufacturer and shall
contain measures, weights and features of the apparatus.
• Detail drawings as required by the Engineer.
• List of components and details on the apparatus. They may preferably be included in
the dimension sketch.
The date by which operating and maintenance manuals are required is: ten (10) days before commis-
sioning
The amount to be withheld for failing to produce “as built” drawings and/or operating and
maintenance manuals by the date required is two percent (2%) of the final contract price.
b) No-load testing of the network
Activities carried out include;
i. Pole sounding
ii. Visual inspection of the network
iii. Measuring of earth resistances
c) On-load tests of the network
Activities carried out shall include;
i. Testing of transformers
ii. Configuring of bulk energy meters, configuring switch gears
iii. Network protection grading
The expected outcome of this activity is a detailed Pre-Commissioning report from the Project Engineer/
Manager highlighting the following;
Attachments: Transformer Commissioning Report(See Annex 26), Metering Unit Commissioning Report,
Auto-reclosure Commissioning Report, Signed attendance list of all participants
The expected outcome of this activity is a detailed commissioning report from the Project Engineer/
Manager highlighting the following;
Attachments: Pictorial evidence of activity, Original Copy of the Asset Handover Instrument
Chapter one: Background information including Contract particulars, Objective of the project, output,
Number of Connections
Chapter two: Project performance assessment – Final account of cost, scope, duration of the project
(Contractual vs Final)
Chapter four: Administrative reviews - Consultant’s performance (measure against the expected deliv-
erables)
Attachments: Certificate for operational acceptance, Certificate of practical completion and pre-com-
missioning test reports
11. Connections
The Engineer shall ensure that every single phase no-pole service connection entails the following mate-
rials as stipulated by ERA.
For customers who have been connected using Ready boards, the Engineer shall ensure that it is in-
stalled at least 150cm from the ground level and shall incorporate:
The Copper Bonded Earth Rods shall be molecularly bonded with atleast 99.98% pure Electrolytic grade
Copper over a low carbon tensile steel rod with the thickness of 254 micron copper coating. All the rw
materials used in the Composition shall strictly comply with the certified standards. The carbon tensile
steel shall comply with BS 970 & AISI 1018 and should have a great capacity of being stretched or extend-
ed at least up to 600 N/mm2. The copper used in manufacturing these earthing rods shall conform to BS
4360 grade 43A. The rod shall be treated in such away as to prevent oxidation.
The bonding of the copper layer to steel core shall be by electrolytic process to ensure a perfect and
tough bonding between the steel and the copper. The copper bonded rods shall comply with RDSO/
SPN/197/2008 or Latest standards.
Nominal Diameter (in inch) Length (in feet) Wt./100 (pcs in Ibs)
3/4” 8 1035
6 Soil 83A
Air 64A
Site inspections and meetings to be scheduled on a quarterly basis or when the need arises. The purpose
of which is to find out the condition of the line, confirm that all snags identified after commissioning have
been corrected by the contractor, get feedback from the stakeholders namely but not limited to Local
leaders, beneficiaries, service providers among others.
If there are any defects reported by the operator, the contractor shall immediately tasked to rectify
them.
A DLP Inspection Report shall be issued by the Engineer after every DLP site inspection and it shall include
in detail, but not be limited to.
Chapter three: Observations, instructions and timelines from the works inspection including aspects of;
engineering, environment (consideration for forest reserves, wetlands, trees, crops, human settlements,
tourist/cultural sites), social (engagement and participation), health and safety (accident, safety of peo-
ple around)
At the end of the DLP, an Operational Acceptance Certificate shall be issued to the contractor.
This shall be issued only after the contractor has achieved the required connections as per the contract.
Chapter one: Background information including Contract particulars, Objective of the project, output,
Number of Connections
Chapter two: Project performance assessment – Final account of cost, scope, duration of the project
(Contractual vs Final)
Chapter four: Administrative reviews - Consultant’s performance (measure against the expected deliv-
erables)
Attachments: Certificate for operational acceptance, Certificate of practical completion and pre-com-
missioning test reports
Note: For the Consultant, the report shall entail a cumulative account of their monthly reports.
• Details of the
REA Project Management Manual
Contract
• Methodology
for implement-
30
Frequency of Personnel
Interest/ Role by the Information Source of Infor- Methods of infor-
No. Stakeholder Description Excecution Responsi-
Benefits stakeholder Required mation mation collection
of Role ble
• Contract
Management
• Project
monitoring and Monthly • Technical • Project Procure-
sheets • Contractor’s
• Issuance of • Details of the monthly progress • Review of reports
The primary techni- Approvals for Contract report and Plans
Subcontractors,
31
bers and Inspections
Frequency of Personnel
Interest/ Role by the Information Source of Infor- Methods of infor-
No. Stakeholder Description Excecution Responsi-
Benefits stakeholder Required mation mation collection
of Role ble
•Identification
of areas likely
to be affected,
Monthly
give measures
on how to mini-
32
Frequency of Personnel
Interest/ Role by the Information Source of Infor- Methods of infor-
No. Stakeholder Description Excecution Responsi-
Benefits stakeholder Required mation mation collection
of Role ble
When re- • Review of
• Ensure quested for Project Engineer’s
• Issue pay- • Project Engi-
issued pay- through the monthly reports
Team responsible ments neer’s monthly
ments are payment • Projected • Review of Ap-
for issuing payments reports
33
Frequency of Personnel
Interest/ Role by the Information Source of Infor- Methods of infor-
No. Stakeholder Description Excecution Responsi-
Benefits stakeholder Required mation mation collection
of Role ble
External Stakeholders
34
Frequency of Personnel
Interest/ Role by the Information Source of Infor- Methods of infor-
No. Stakeholder Description Excecution Responsi-
Benefits stakeholder Required mation mation collection
of Role ble
• Details of the
Daily, Contract
• Construction
Monthly and • Methodology
Supervision
Quarterly for implement-
35
Frequency of Personnel
Interest/ Role by the Information Source of Infor- Methods of infor-
No. Stakeholder Description Excecution Responsi-
Benefits stakeholder Required mation mation collection
of Role ble
• Providing right
of way
Throughout
• Imple- • Participation
the entire
mentation in implementa-
project life • Objectives of
of a project tion • Contract
cycle
36
Frequency of Personnel
Interest/ Role by the Information Source of Infor- Methods of infor-
No. Stakeholder Description Excecution Responsi-
Benefits stakeholder Required mation mation collection
of Role ble
• Contents of • Approved Proj-
Approved Proj- ect scope
• Review of Ap-
ect scope • Approved
proved Project
• Implementa- • Approved de- design and survey
scope
37
Frequency of Personnel
Interest/ Role by the Information Source of Infor- Methods of infor-
No. Stakeholder Description Excecution Responsi-
Benefits stakeholder Required mation mation collection
of Role ble
• Details of the
• Smooth Contract
implemen- Throughout • Details of proj- • Contractor’s
Contractor’s Prefinancers of the Contrac-
tation of the Provide con- the entire ect financing contract Meeting with con-
16 Financial project including tor
project tract financing project life • Progress of • PAD tractor
Partners banks. REA-Client
Poor handling
and transporta- Damage of transformer
2 3 6 • Well functioning self-loaders should be used
tion of transform- bushings
ers
Loading fragile
• Fragile materials should be transported seperately
materials with Damage of materials 3 3 9
• Large vehicles with sufficient space should be used
non-fragile ones
Damage of materials
Accidents leading to
Overspeeding 3 3 9 Drivers should not exceed a speed limit of 60 Km/hr
body injuries and/or
deaths
Development of
Using short vehi-
sweeps on poles • Tracks with a minimum length equivalent to the height of
cles to transport 2 2 4
Mechanical damage the pole should be used
poles
on poles
40
Thorny plants,
Body scratches 3 1 3 • Workers wear Full Personal Protection Equipment
trees stumps etc
Having a live net- • Trees should be cut gradually and carefully to avoid
work within the Live shocks/ Electro- contact with the power line
2 3 6
falling distance of cutiion • Shutdowns should be requested for in cases where it is
the tree impossible to avoid contact with the live network
Failing to oba-
tined the required Live shocks/ Electro- The contrcator should be careful adhire to the minimum
3 2 6
ground clear- cutiion clearances provided for in the construction guidelines
ance
41
Loss of supply
Damaged pipes and
Energised under- cables • Seek Utilities layouts and plans from District Physical
ground cables Body injuries and Planners
3 3 9
and pressurised death from damaged • Take caution when excavating
water pipes pressurised pipes and • Report any damage to the concerned asset manager
exposed energised
cable
tion tools
Injury due to vehicles
Use of reflective road signs to alert road users of on-going
Moving traffic swerving off the road 2 3 6
42
Poor handling
• Poles should be offloaded using cranes
or offloading of
Mechanical damage • Poles should be offloaded in the presence of the pole
poles by throw- 3 3 9
and splitting treatment plant representative and the contractor while
ing them off the
ensuring no poles are dropped
track
Phyiscal damage to
Dragging and • Poles should be moved on rollers or carried using tracks
Pole posi- the pole and hence
43
Fatigue due to
Body injuries and death All linesmen must anchor themselves with tied belts all the
working long 1 2
due to falling time while working height
hours at height 2
Wornout climbing Body injuries and death
2 3 6 Climbing irons should be replaced if worn out
irons and Belt due to falling
Existing near live Body injuries and death Minimum clearance must be observed or live lines de-en-
2 3 6
line due to electrocution ergised and earthed
down
Failing to use the Body scratches and Contractor should ensure that all workers have the re-
2 3 6
required PPE injuries quired PPE before moving to site
44
Using unsuitable All stay assemblies should be inspected and approved by
materials e.g Poor quality of works 2 3 6 the Clerk of Works during installation to ensure appropriate
wood stay stubs materials such as concrete stay stubs are used
Reduced firmness of
the stay’s foundation
Reduced support
Installing the strength of the stay Engineer should inspect all stays to ensure they are appro-
2 1
45
Reduced clearance
Installing short between the jumper All jumpers should be inspected by the Engineer and Clerk
2 3 6
jumpers and the support struc- of Works
ture
Reduced clearance
Cable
10 Installing loose between the jumper All jumpers should be inspected by the Engineer and Clerk
Joining 2 3 6
jumpers and the support struc- of Works
ture
Clumps
Failing to put all
Obtaining poor earth- Earthing should be done under supervision by the clerk of
required compo- 3 3 9
Connec-
• The live lines are isolated, earthed and a work permit
tion of
issued before commencement of works
13 new lines Live lines Electrocution 2 3 6
• All personnel working at the T-off should wear protective
to existing
gear such as gloves, overalls, eye protectors etc
live Grid
46
Working in Infection with associat-
15 Dirty environment 2 2 Workers wear Gumboots and rubber gloves
dirty areas ed diseases 4
Road accidents result-
Driving long dis- Drivers are encouraged to limit journeys to manageable
ing in bodily injuries or 3 3 9
tances distances based on their judgement and capabilities
loss of lives
Driving to
16
site Road accidents result- • Installation of speed governors to control speed limits
Regulation 51(3)
Subject of Procurement
Provider
Contract Value
Contract Completion
Date of taking over certificate (Release of % of Retention where applicable)
Extension of time, if any
Delay, if any
Liquidated damages due, if any
(date of taking over certificate + defects noti-
Date of performance certificate fication period and release of remaining % of
retention)
Return of performance security
Amount
Final Payment
Date
Retentions (Where applicable)
Environmental Confirmation of
Category Main checks environmental
item considerations
1. Permits, 1. EIA and other 1. Has EIA been completed?
certificates permits 2. Have EIA reports been approved by NEMA?
and 3. Have EIA reports been unconditionally approved? If conditions
explanations are imposed on the approval, then an adjusted EMP must be
developed.
4. In addition to the above approvals, have other required
environmental permits been obtained from relevant authorities?
2. Explanation to 1. Are contents of the project and the potential impacts adequately
the public explained to the public based on appropriate procedures,
including information disclosure?
2. Are proper responses made to comments from the public and
regulatory authorities?
2. Mitigation 1. Water quality 1. Is there a possibility that soil runoff from the bare lands resulting from
Measures earthmoving activities, such as cutting and filling will cause water
quality degradation in downstream water areas? If water quality
degradation is anticipated, are adequate measures considered?
2. Are measures adequately considered to mitigate potential
pollution of cresol from the poles yard
3. Are measures adequately considered to mitigate potential
hydrocarbon pollution from any spillages
4. If the magnitude of potential pollution is big, has DWRM been fully
engaged?
2. Protected Areas 1. Is there a possibility that the project will affect protected areas?
2. Has UWA been fully engaged in case of Wildlife areas?
3. Has NFA been fully engaged in case of forest reserves?
3. Ecosystem 1. Are adequate measures taken to prevent disruption of migration
routes and habitat fragmentation of wildlife, and livestock?
2. Is there a possibility that the project may cause impacts, such as
reduction in wetland areas, and disturbance of ecosystem due to
introduction of foreign materials?
If significant ecological impacts are anticipated, are adequate pro-
tection measures taken to reduce such impacts on the ecosystem?
4. Topography and 1. Is there a soft ground on the route of power transmission lines that
geology may cause slope failures or landslides? Are adequate measures
considered to prevent slope failures or landslides, where needed?
2. Is there a possibility that civil works, such as cutting and filling
will cause slope failures or landslides? Are adequate measures
considered to prevent slope failures or landslides?
3. Is there a possibility that soil runoff will result from cut and fill areas,
and borrow sites? Are adequate measures taken to prevent soil
runoff
6. Living and 1. Is there a possibility that the project will adversely affect the living
livelihood conditions of inhabitants? Are adequate measures considered to
reduce the impacts, if necessary?
2. Is there a possibility that diseases, including communicable
diseases, such as HIV will be introduced due to immigration of
workers associated with the project? Are adequate considerations
given to public health, if necessary?
7. Heritage 1. Is there a possibility that the project will damage the local
archaeological, historical, cultural, and religious heritage sites? Are
adequate measures considered to protect these sites?
8. Ethnic Minorities 1. Where ethnic minorities and indigenous peoples are living in the
and Indigenous rights-of-way, are considerations given to reduce impacts on the
culture and lifestyle of ethnic minorities and indigenous peoples?
People
9. Impacts during 1. Are adequate measures considered to reduce impacts during
construction construction (e.g. noise, vibrations, turbid water, dust, exhaust
gases, and wastes)?
2. If construction activities adversely affect the natural environment
(ecosystem), are adequate measures considered to reduce
impacts?
3. If construction activities adversely affect the social environment,
are adequate measures considered to reduce impacts?
4. Are health and safety measures in place? is health and safety
education (e.g., traffic safety, public health) provided for project
personnel, including workers?
10. Monitoring 1. Project specific EMP developed by REA and given to the
Contractor for implementation and supervising firm for monitoring
purposes.
2. Has the contractor developed CEMP?
3. The Contractor and the supervising firm must therefore have an
environmentalist for guiding and monitoring environmental aspects
Control Survey
Horizontal Control Survey: Horizontal control survey will be done by using High precision duel frequency
GPS receivers. All GPS points will be established the accuracy of 5mm+/- 1ppm.
Vertical Control Survey: Vertical control will be done using electronic tachometry based on MSL Datum.
Preliminary Survey
Preliminary survey will be carried out with reference to the technical specification in using GPS instru-
ments and intelligent total stations. Preliminary drawings and other details will be provided according to
the item no. 2 of Technical Specification in tender document.
Profile Survey
Profile survey will be done using only data recordable total stations according to the item no. 3 of Tech-
nical Specification in tender document.
Data will be recorded using string system method. This string system data is useful for complete drawings
by Auto mapping System.
Longitudinal section survey will be carried out by heighting along the proposed line center at 20m inter-
vals. Significant change of slope between 20m spot heights also will be heighted. Where ground slope
across the line route exceeds 1 in 25 the level of ground left and right of the center line will be recorded
at an offset distance of 10m. All spot height leveling for the longitudinal section will be done by electronic
tachometry. Profile drawings will be provided according to the item no. 3 of Technical Specification in
tender document.
Flow chart of the method statement - Technique Based on Satellite images and GPS
Date
Cantilever (Ex-
Pole Top Diam- Retention >115kg/ Mid-point (Expected Results
NO Pole Length Penetration >15mm Mid-point pected Results Cantilever Visual Inspection
eter m3 according to SANS)
Name Date Signature
REA Representative
Contractor
Treatment Plant Manger
54
REA Project Management Manual
No. Aspect of inspection Methods of inspec- Sampling rate Acceptance Equipment Remarks
tion criteria
Hot dip zinc
Galvanized, Use coating
External surface coating Visual and powder thickness
1 10%
of tanks measurement coated, ≥ gauge.
100µm (BS (Elcometer)
729)
1 per type Oil resistant
2 Internal surface of tank Visual
& Size paint
Dimension and Physical check and 1 per type Approved
3 measurement
construction & Size drawing
a. Outdoor bushing
a. Approved as per the
Creepage distance
specification and
b. Phase to phase
drawing
clearance
b. 40mm/kV 1 per type Approved
4 c. Phase to Earth
c. 800mm & Size drawing
clearance
d. To be
d. Bi-metallic crimping
provided with
connector for
hardware
conductor.
Should be
Visual inspection of above active
5 Oil level inside tank to the oil level gauge.
1 per type &
part when the
be checked Note: Ambient Size
Oil gauge is
at minimum.
Should be as per
6 Packing Physical inspection specification
Routine Test
Aspect of Applicable Sampling
No. Acceptance criteria Equipment Remarks
inspection standard rate
3 Performance of conductor
Unit of Test
No. Aspect of inspection/test Expected Results Results
Measure
Nominal system Voltage kV 33
1 Visual examination
2 Verification of dimensions
Nominal Height mm 240
Minimum Nominal Creepage distance mm 2400
3 Tensile load test (applied 9.4kV for 10s) kV No damage (deformation/cracking)
seen
4 Tests on interfaces and connections of metal
fittings:
Thermal-mechanical pre-stressing (4.0kV for 48h) kV ok ( same oC for CT and HT)
Water immersion pre-stressing No cracks/damage
Verification tests / visual examination No cracks
Steep-front impulse voltage test No puncture
Dry power frequency voltage test kV >180
Min Power Frequency withstand Voltage (Dry) kV >160
5 Test of housing
Accelerated weathering test
Tracking and erosion test No tracking and no erosion,
no shed punctured
Flammability test No drops
6 Test for the core material
2 System Voltage kV 33
Verification of dimensions
Nominal Voltage kV 33
Steep front impulse voltage with-
1 kV No Puncture
stand test (1000-1500kV)
Lightning impulse flashover voltage
2 kV
test
3 Radio interference voltage test <200µV
10 Thermal Test.
1 Engineering Design
4 HV installation works
5 LV installation works
6 Equipment commissioning
………………)
Following receipt of the contractor’s claim, a site meeting preceded by an inspection of works
and material verification, was conducted and I certified progress as tabulated below
(……………..
Signature:
(…..insert project engineer’s name….)
e) Condoms
f) Clean Toilets
g) Clean and suitable rooms for accommodation
The following considerations for the Yard have been made:
√/X Comments
a) Vegetation growth shall be well maintained
The yard spacious enough to accommodate
b) materials
c) There is security
The yard is accessible in accordance with
d) environmental management plan
The yard is distant enough from homesteads and
e) other people-congested areas
Officers
Date Signature
Names
Project Details Name
Scope
Day’s Work Section
Scope
Start End Remarks
Work Duration
Materials received
Material
Quantity
Materials Rejected
Materials Used
Material
Quantity
Total Work Done
Ground Rocky Sandy Swampy Normal Remarks
No. of Pits Excavated
HV LV
No. of Poles Erected
No. of Structures Dressed
No. of Structures Strung
No. of Equipment Installed
Others
Instructions Issued
Changes Proposed
PPE for Workers Incidents Accidents
Safety Issues
Challenges Faced
Poles Erected
Structures Dressed
Structures Strung
Equipment Installed
Others
Instructions Issued
Proposed Changes
Qualification Statement
Safety
Environmental and Social Safeguards
Community Involvement
Project Administration
Risks and Mitigation Measures
Risks Mitigation Measures
Project Engineer’s Signature
Name Signature
Request for shut down, Commissioning and Handover of (….insert actual name of the scheme,
indicating the district…..)
The Government of Uganda represented by the Rural Electrification Agency contracted (….in-
sert name of contractor…) (here in called the contractor) for the implementation of the (…..
insert name of the scheme..) located in (…..insert District..)
The works have been completed and off-load testing of the network successfully conducted
and commissioning and final takeover scheduled from (….insert date…..)
This network falls under (….insert the name of the service territory..) and shall be operated by
(….name of the service provider…) as per the lease agreement signed with the Rural Electrifica-
tion Agency.
The scope of works include:-
(….insert
As Built Scope
Scheme
No. District Feeder HV LV LV (3Phase) Transformer Capacity
Name
(1Phase)
……)
This is to request you
i. Grant a shut down on the above feeder to enable interconnection
ii. Nominate a team that will facilitate the final inspection and commissioning of the network
Please liaise with (……insert name of project engineer…) on behalf of the Agency and (…..insert
name of the project engineer….) on behalf of the contractor, who will coordinate the above
exercise.
Your corporation shall be highly appreciated
For your reference, attached hereto is the as-built drawings and the pre-commissioning test re-
sults
Signature
(….Insert name of Project Manager…)
For: Executive Director
Request for shut down, Commissioning and Handover of (….insert actual name of the scheme, indicat-
ing the district…..)
The Government of Uganda represented by the Rural Electrification Agency contracted (….insert name
of contractor…) (here in called the contractor) for the implementation of the (…..insert name of the
scheme..) located in (…..insert District..)
The works have been completed and off-load testing of the network successfully conducted and com-
missioning and final takeover scheduled from (….insert date…..)
This network falls under the UMEME Service Territory and shall be operated as per the new Electricity
Distribution Network Agreement signed with the Rural Electrification Agency.
(….insert
As Built Scope
No. Scheme Name District Feeder HV LV LV Transformer Capacity
(1Phase) (3Phase)
……)
Please liaise with (……insert name of project engineer…) on behalf of the Agency and (…..insert name
of the project engineer….) on behalf of the contractor, who will coordinate the above exercise.
For your reference, attached hereto is the as-built drawings and the pre-commissioning test results
Signature
RE: COMMISSIONING OF BULK METERING UNITS AND AUTO RECLOSERS IN (…insert district name…)
The Government of Uganda represented by the Rural Electrification Agency contracted (…insert name
of the Contractor…) (herein called the contractor) for the implementation of construction works from (…
insert project details…).
The works have been completed with a metering unit and auto recloser installed at the start of each
tee-off listed in the table below. Off-load testing of the network was successfully conducted and com-
missioning and final takeover scheduled for (…insert date…).
This network falls under the (…insert name of the Service Territory…) and shall be operated by (…insert
name of the Service Provider…) as per the new Electricity Distribution Network Agreement (this is for
UMEME) or lease agreement (other Service Providers) signed with the Rural Electrification Agency.
Scheme No. Description Feeder District TX Capacity (kVA) MV Route LV Route Length
Name Length
This is to request you nominate a team that will commission the bulk meters and system protection switch
gears. The key stake holders include; REA (the client), UETCL (systems operator), (…insert name of op-
erator of feeder network…) (operator of feeder network) and (…insert name of operator of the newly
constructed network…) (operator of newly constructed network).
Activities will involve energizing the networks, taking initial readings on the meters, checking protection
settings and verification of the functional operation of the interfacing switch gears.
Please liaise with (…insert name and contact of REA representative…) on behalf of the Agency and (…
insert name and contact of the Contractor’s representative…) on behalf of the contractor, who will co-
ordinate the above exercise.
The Government of Uganda represented by the Rural Electrification Board signed a contract with (…
insert name of the contractor…) to execute (…insert name of the project…).
The works have been completed and off-load testing of the network successfully conducted. Commis-
sioning and final takeover have been scheduled from (…insert date…). The line is therefore ready for
commissioning and/or eventual takeover.
These networks fall under the (…insert name of service territory…) and will be managed by UEDCL under
the Management and Operations Agreement.
The purpose of this communication is therefore to request you to nominate a team of this is to request
you to;
i. Nominate a team that will facilitate the final inspection and commissioning of the network.
Please liaise with (…insert name, phone contact and e-mail of REA representative(s)…) on behalf of the
Agency and (…insert name, phone contact and e-mail of Contractor’s representative(s)…) on behalf of
the Contractor, who will coordinate the above exercise.
For your reference, attached hereto is the as-built drawings and the pre-commissioning test results.
Signature
OIL LEVEL
SURGE ARRESTORS R (M Ω) Y (M Ω) B (M Ω)
PHASE SEQUENCE
GENERAL ASSESSMENT PASS FAIL
Name
Designation
Signature
Date
We hereby certify that subject to the contractor’s liability to remedy all defects which may be-
come apparent during the Defects Liability Period, the works under the signed contract were practically
completed on ………… and that in relation to the said works, the said Defects Liability Period of One
calendar Year will end on ………………..
(…insert Name…)
EXECUTIVE DIRECTOR
Main Contractor
a) Definition
A main contractor is a company contracted by REA to carry out design, supply or construction of 33kV
or 11kV lines and associated low voltage networks in rural electrification projects areas
Sub-Contractor
a) Definition
A sub-contractor is a company contracted by the main contractor to undertake specifics part of the
contract.
Qualification Requirements
a) Eligibility
i. Certificate of Incorporation
ii. Valid trading license
iii. Income tax clearance
iv. Valid VAT registration certificate
v. Valid PPDA registration certificate
vi. Articles and Memorandum of Association
vii. Particulars of the Directors (Company form 7) with copy of identification(driving permit, na-
tional ID or passport) and detailed CVs with passport photos attached
viii. Office premises
ix. Valid NSSF registration certificate
x. Audited books of accounts for the previous 1 years
xi. Should not be suspended by PPDA or development partners
xii. Recommendation from registered engineer
xiii. Acceptable code of conduct
i. Engineering
ii. Finance
iii. HR
1.4 Key personnel with the minimum level of qualification and expe-
rience
No. Personnel Minimum Qualification/Expertise Experience
Project Manager/ Electri- Bsc. Electrical Engineering with Class B ERA certificate 2 years
cal Engineer
Foremen Ordinary diploma in electrical or equivalent 5 years
Guidelines to Sub-Contracting
a) Supervision
The main contractor shall be responsible for supervising the sub-contractor. The main contractor shall
assign at all a resident engineer with a minimum of bachelor’s degree in electrical engineering who will
be responsible for supervising the sub-contractor.
b) Approvals
Main contractor shall seek written approval from the employer prior to engagement of the sub-contrac-
tor. Profile of the sub-contractor with all the required information shall be submitted to the client with a
draft sub-contract agreement in line this criteria. The clients respective project engineer shall be a wit-
ness on behalf of the main contractor in the sub-contract agreement.
The main contract shall retain 10% of the contract sum as security for performance.
In seeking for the above approval, the main contractor shall clearly indicate the section of the work they
intend to subcontract and the level of engagement in line with line construction i.e surveying, pit exca-
vations, erection, dressing and stringing
c) Scope of work to be contracted
The minimum amount of work to be subcontracted shall be 25km of HV and associated low voltage
networks
The following tasks shall not be sub-contracted and shall remain the responsibility of the main contractor;
The under-listed conditions shall form part of the conditions for termination by of the contract and shall
be part of the sub-contract agreement
Issuance of advance payment shall be at per the terms and conditions of the main contractor
Sub-contractor payments for works completed shall not be subject to client’s payment to main contrac-
tor
21 Angle Section Per Structure
Erection No. 1 100,000
Dressing No. 1 140,000
Total 240,000
22 Equipment Structure Per Structure
Erection No. 1 100,000
Dressing No. 1 140,000
Total 240,000
23 Tee-off Per Structure
Erection No. 1 100,000
Dressing No. 1 140,000
Total 240,000
24 Terminal Per Structure
Erection No. 1 100,000
Dressing No. 1 140,000
Total 240,000
Three Member Structures
25 Support/Intermediate Per Structure
Erection No. 1 150,000
Dressing No. 1 210,000
Total 360,000
26 Straight Section Per Structure
Erection No. 1 150,000
Dressing No. 1 210,000
Total 360,000
27 Angle Section Per Structure
Erection No. 1 150,000
Dressing No. 1 210,000
Total 360,000
Stays and Galvanised steel wires Per Complete Stay
The unit cost shall include the complete installation 7/4 stay wire, stay
rods, buckles, stay insulators and all the necessary accessories for a
complete stay assembly.
28 Conventional Stay Assembly No. 1 125,000
29 Flying Stay Assembly No. 1 150,000
30 Short Stay Assembly No. 1 135,000
31 Prop (Guy) pole Stay No. 1 150,000
Conductors Stringing Per KM
The unit cost shall include the proper handling and storage and instal-
lation on assembled structures. Including stringing, sagging, connecting
jumper and installing all necessary termination hardware accessories.
32 AAAC100 km 1 900,000
33 AAAC50 km 1 800,000
36 Survey, Bush Clearance, Profiling, Line designs and Pegging (LV) km 1 200,000