Professional Documents
Culture Documents
3) If earned value (EV) =350, actual cost (AC)=400, planned value (PV)=325,
what is cost variance (CV)?
A. 350
B. -75
C. 400
D. -50
4) Analogous estimating:
A. Uses bottom-up estimating techniques.
B. Is used most frequently during the executing processes of the
project.
C. Uses top-down estimating techniques.
D. Uses actual detailed historical costs.
5) The cost of choosing one project and giving up another is called:
A. Fixed cost.
B. Sunk cost.
C. Net present value (NPV).
D. Opportunity cost.
10) Which factor would NOT be considered when choosing between two
projects to undertake?
A. Net present value (NPV)
B. Benefit cost ratio (BCR)
C. Payback period
D. Law of diminishing returns
11) If project A has a net present value (NPV) of U.S. $30,000 and project
B has an NPV of U.S. $ 50,000, what is the opportunity cost if project B is
selected?
A. $23,000
B. $30,000
C. $20,000
D. $50,000
13) Which of the following represents the estimated value of the work
actually accomplished?
A. Earned value (EV)
B. Planned value (PV)
C. Actual cost (AC)
D. Cost variance (CV)
14) You have four projects from which to choose one. Project A is being
done over a six year period and has a net present value (NPV) of U.S.
$70,000. Project B is being done over a three year period and has an NPV of
U.S. $30,000. Project C is being done over a five year period and has an NPV
of U.S. $40,000. Project D is being done over a one year period and has an
NPV of U.S. $60,000. Which project would you choose?
A. Project A
B. Project B
C. Project C
D. Project D
18) You are asked to prepare a budget for completing a project that was
started last year and then shelved for six months. All the following would
be included in the budget EXCEPT?
A. Fixed costs
B. Sunk costs
C. Direct costs
D. Variable costs