You are on page 1of 9

RTT Script

Slide no: 1

1. Self introduction
2. Introduction about the Surveying, explaining the importance of surveying.
3. Explain about the construction methods used in civil works.
Like GBT & RTT and its differences.

Slide no: 2, 3,

1. By showing the indexes go through the total over view of RTT survey & construction
procedure.

Slide no: 4

1. From slide 4 explain about the survey procedure to be fallowed for RTT construction.

Slide no: 5

1. Explain about the various tools required for surveying.


2. Brief them about the rough layout and its importance.
3. Guiding in proper handling & usage of the equipments/tools.
4. Explain them, what are the data to be carried to field, for site survey.

Slide no: 6

1. Brief them about the site selection to carry out further works.
2. Giving importance to those buildings which are more suitable for RTT constructions.
3. Explain about the advantages & Disadvantages while selecting the site.

Slide no: 7 -

1. By showing the heading ask them about the surveying & tools required for surveying, in
order to recollect.
2. Survey procedure will be explained in the fallowing slides.

Slide no: 8 – Preparation of layout drawing

1. Explanation about the steps to be fallowed while preparing the layout drawing on the
proposed site.
2. Go for the various procedure & checks to be performed while drawing the layout drawing.
3. Following are the steps to be followed while taking the layout drawing.
a. Firstly write down the site name, Tower height & site address at the very top of the
page, for the sake of identifying that particular site.

1
b. Explain what will be the disadvantages with an example. If the details of that particular
site is not mentioned properly.
c. Go for drawing the terrace out line on the paper (excluding the dimensions of parapet
wall if exist).
d. All the measurements should be taken in mm, using steel tape.
e. Explain about how to use the tape & how to take measurements of it.
f. Indicate the NORTH direction, by using compass. Explain the reason behind of
indicating the North direction.
g. Explain how to mark the column positions with size, c/c distances, and orientation with
steel details.
h. In case column positions are not visible, then go for taking measurements by using
Theodolite & ranging rods.
i. Explain how to mark the beams positions.
j. Similarly mark the stair case, stair case head room, water tank, lift room, etc., & tell what
if they are not mentioned in the layout drawing.
k. Mark the adjacent roads, surrounding structures and its distances and it’s important.
l. Similarly explain the indicating height, floors of the building, mark proposed area for
tower, DG, shelter and earth pit details.
m. Indication of EB pole & its importance.
n. For all these from whom you need to take the permissions.
o. After completion of rough layout to whom this to be carried off.

Slide no: 9, 10, 11, 12, 13, 14, and 15

1. Explanation regarding placing the tower,


2. What are the various methods can be adopted placing 4 leg & triangular tower.

Slide no: 16

1. First explain the base width of the tower.


2. What is the tower area?
3. How this base width of tower & tower area is interred linked.

Slide no: 17

1. Placing the Tower, Shelter on the roof top.

Slide no: 18

1. Placing the DG on the roof top.


2. Explain how DG bed size will depends on the DG base size while placing the DG on the roof
top.

Slide no: 19

1. Index showing the various steps involved in design procedures for RTT.

2
Slide no: 20 and 21

1. By showing a sample example of the CAD layout, explain how a drawing can be read out
what are the nameplate details, and its importance.

Slide no: 22 - CONSTRUCTION PROCEDURE FOR RTT SITE

1. Before going in deep just go through the topics we have covered.


2. Inter link the previous drawing with the coming construction works & it’s important.

Slide no: 23

1. This slide show various steps involved in RTT construction.

Slide no: 24 and 25

1. After completion of the CAD layout the designer will design the foundation drawings.
2. With the help of CAD layout one should go for marking on the proposed site.
3. Before marking following points are to be noted
a. First check out the CAD layout with rough layout.
b. Check for proper site address & Site name with the layout drawings.
c. Compare all the dimensions given in the drawings with the proposed site. For Ex: c/c
distance of the pedestal etc.
d. What if the above points are not correct and their importance.
4. Go for marking the column positions of the building, tower columns, DG bed & shelter
position.

Slide no: 26

• Check to be performed while marking: Actual position of columns and beams etc will be
marked properly to enable the perfect steel binding and shuttering in place.

Slide no: 27 – Chipping

1. What is chipping
2. Why it is required

Slide no: 28

1. Explanation about the chipping purpose: To connect the foundation column reinforcement
to existing column reinforcement, and to develop the bond between old concrete with new
concrete.

3
Slide no: 29, 30, 31, and 32

1. Explaining the various types of terrace available


a. Plain terrace
b. Terrace with existing reinforcement
c. Terrace with dummy columns
2. From the above mentioned which one is most preferred.

Slide no: 33 to 39

1. Enplaning about the Chipping procedures for various terraces.

Slide no: 40

Checks to be performed while chipping

1. Ensure that civil team does the chipping of the existing columns as per the drawing and
layout given to them.

2. Proper precaution must be taken during chipping to prevent the roof getting punctured due
to chipping. For this exact position of the existing column must be marked by PMC site
engineer.

3. Chipping should be done with hand drills only.

4. Chipping should be start from center of column.

Slide no: 41, 42, and 43

1. Explaining the procedure preferred for connecting the column reinforcement to the existing
reinforcement.
2. Giving the importance of lap & welded joints.
3. After connecting what are the precautions to be taken.

Slide no: 44 and 45

 Explanation given for the critical conditions were reinforcement is not exposed properly.
 If this is the case such sites should not be selected for the construction.

Slide no: 46 and 47- grouting

1. To create a bound between old & new concrete apply grouting chemical at the chipped
portion to develop good bondage.
2. This grouting material should be water proof.
3. This water proof material will avoid the leakage of water from the chipped portion of the
slab.
4. In the slide no.47 it shows a sample example for the reinforcement, which is not connected
properly with the existing reinforcement.

4
Slide no: 48

Checks to be performed while connecting the reinforcement.

1. Sufficient lap length should be maintained at joints of reinforcement steel.

2. Proper welding techniques should be followed (as specified in drawing/ by customer


engineer).

Slide no: 49

1. Bar banding schedule is a document which gives the details of the reinforcement bars.
2. It is generally used for laying the columns and beams.
3. From whom did we get the bar bending details, and all of the things are explained.
4. Conforming the reinforcement details before use.

Slide no: 50

1. Explanation about the stirrups: which are used to tie up the columns & beams in their own
positions.
2. It is tied up by means of 18 gauge annealed wire.

Slide no: 51

This slide shows the arrangement of stirrups with the reinforcement bars.

Slide no: 52

1. Discuss about the checks to be performed on re- bars.


2. Which includes bar conformation, Color of the bars, it should be free from oil, paints and
corrosion.
3. Test certificate should be collected from the Vendor.

Slide no: 53 - shuttering

1. What is shuttering?
 The shuttering is used to provide profile to the concrete.
2. What are the materials to be used as shutters?
 Ply wood
 Steel Plate
3. Why it is given importance to the shuttering is explained.
4. What are the precautions are to be taken while shuttering is explained.
5. Column shuttering: the shuttering provided to the columns is called as column shuttering.
6. Bottom shuttering: the shuttering provided to the beam bottom is called as bottom
shuttering.
7. Checks to be performed before shutters are placed like:
 PMC engineer will ensure that only good quality steel or plywood shuttering is being
used for the RCC work. Wooden planks should not be used at all.

5
Slide no: 54, 55, and 56

1. Cover blocks are used to provide a gap between outer reinforcement to the inner
shuttering. So, the outer reinforcement bars will be protected from distortion.
2. Cover blocks are used below, and sides of the reinforcement bars.
3. We will discuss about the shuttering process.
4. Discuss about the various Checks performed after shuttering.
a. Shuttering material facing the concrete are to be applied with adequate shuttering oil in
order to get neat form finish.
b. There should not be any gaps in shuttering joints, to avoid leakage of concrete slurry.
c. To cover the gaps, Plaster of Paris or polythene covers etc., can be used inside the
shuttering.
d. Shuttering should be straight from end to end of beams.

Slide no: 57

This slide gives an example for deface form of work, if shutters are not align properly.

Slide no: 58, and 59

Discuss about the points if the shutters gaps are not properly covered.

a. Concrete slurry – leakage


b. Water cement ratio – reduces
c. Resulting honeycombs in concrete
d. Finally concrete strength will reduce

Slide no: 60 - Template & Foundation bolts

1. Explain about the foundation bolts, identify the bolt and nut.
2. Purpose of using foundation bolt is for providing bond between the columns to the tower
leg.
3. Type of bolt used in foundation can be anchor bolt, J, L bent bolt in order to sustain the
uplift pressure coming from the tower.
4. Foundation bolts should be tied with reinforcement to avoid shaking of bolts while
concreting by using 18 gauge annealed wires.
5. Template is the temporary member used for giving positions to the bolts in their respective
columns.

Slide no: 61and 62 - Checks to be performed on Template & Foundation bolts fixing

1. Checks to be performed before foundation bolt fixing.


a. Checks to be performed on dimensions as per given drawings are not.
b. Checks to be performed on alignment of shuttering & foundation bolts.
2. Measures before fixing the template on foundation by calculation of diagonal distances.
3. Check the water level for all template plates
4. Protect the threading portion of the fn. Bolts before placing on the columns.

6
Slide no: 63

1. Procedure for placing the template on columns.


2. Template is checked for its leveling by using water tube method.
3. After fixing the template check for the levels of the foundation bolts.
4. Protect the threading portion of the foundation bolts with oil or grease or polythene papers.

Slide no: 64

1. If foundation bolts are not vertical the tower leg can’t be fixed properly. So, that the columns
fails to transfer the tower load to the ground. Hence the life time of the tower get reduced.
2. That’s why ensuring that the proper attention to be taken in the beginning stage it self.

Slide no: 65

 If Template is not fixed properly : then Results in eccentricity


 Foundation bolts are not at the center of the beam/column hence, twisting moments
will develop in beam/column

Slide no: 66, 67, 68, and 69

1. Checks: before concreting


 Check whether all inner dimension of the shuttering are tallying with beam & column
sizes mentioned in the drawing.
 Check whether all shuttering gaps, reinforcement is as per drawing or not, foundation
bolts are vertical or not
 Bottom nut of the foundation bolt should be placed such a way that, it should be exactly
on the top of the concrete.
 Cover the threading portion of the foundation bolts with the polythene covers to avoid
sticking of the concrete
 One should NOT walk on the reinforcement or template while concreting.

Slide no: 70 -

1. Concrete: Concrete is a building material made up of aggregates which are joined together
by a gel, called as hydrate, formed due to chemical reaction between cement & water.
2. Material Used in Concrete
a. Fine aggregates
b. Course aggregates
c. Cement (OPC – 43 / 53 grades): explanation on grades of cement.
d. Water: water cement ratio is explained

7
Slide no: 71

1. Mixing of concrete
• Concrete mix should be machine mix. In some cases we go for hand mixing were 10%
more cement shall be used.
2. Concrete MIX
a. Generally used mix is M20, until and unless specified by the designer ‘M’ indicates MIX ,
’20’ indicates compressive strength of concrete cube (150x150x150mm) after 28days
curing.
b. Explain about the other mixes used in constructions in a table.

3. Concrete shall be placed properly & compacted using vibrator


a. Precautions are to be explained while using the vibrators.
b. In case of failure of vibrator/not available tamping rod should be used.
c. Tamping rod should be the diameter of 16, & should be poked 100 times in area of
200 Sq mm.

Slide no: 72, 73, 74, 75, and 76

1. Removing of shuttering
a. Side shuttering can be removed after 24hrs of concreting
b. Template can also be removed after 12hrs of concreting
c. Bottom shuttering should be removed after 28days of the concreting

Slide no: 77 and 78

 Curing is a process that aids the hydration of the concrete.


 A correct curing process is essential for the good quality of the concrete.
 Explain about the time period required for the curing.
Slide no: 79 and 80

Copping: Water proof coping should be done to avoid leakages in the slab due to chipping.

Copping should be done after removing the shutters.

Slide no: 81

In the same way construct Shelter foundation and DG foundation as per the specifications
given in the drawing.

********************

8
9

You might also like