Boiler Erection

Date: 13/01/2017 By
https://boilersinfo.com/
BOILER ERECTION

• Column erection
• Pressure part erection
• Miscellaneous
COLUMN ERECTION

• The boiler presently in use are hanging type.


• The column are broken up during manufacture
into several pieces and transported to site
• Where it is pre assembled in two or three pieces
and erected.
• Utmost care is taken in the pre-assembly stage
to maintain the matching of the of the column
end faces and to achieve vertically well within
the tolerance limit
COLUMN ERECTION

• Verticality is single most important factor


and is given top priority
• The maximum column verticality is 20mm.
• Once the column erection is over up to the
full height cross beams are placed
securely over the column which supports
the main boiler
COLUMN ERECTION

• In order to carry out this job special


erection tool like cranes with extra long
boom to carry heavy loads at that height
are used.
• After cross beam erection, entire structure
is adequately braced to achieve sufficient
strength.
PRESSURE PART
3. Advantage and Weakness of Construction Method

Description ▣ Modulization / Concurrence


\Type
▣ Typical Construction Method
Construction Methods

⊙ Earlier completion through Modulization ⊙ Many years of experience and Know-How


/Concurrence Construction To utilize standard data /Data base
Advantage
⊙ Competitive time for completion ⊙ Reduction design M/H
Curtailment of S/S materials
Reduction manufacturing/installation cost

⊙ Lay down Area need for pre-ass’y at site

⊙ Increasing Equipment / Construction Labor ⊙ Long time for completion


Cost
⊙ High risk of safety accident due to lots of
Weakness ⊙ Increasing Module temporary material and works
S/S materials (about 50% ) at the high elevation

⊙ Long duration for S/S design


and Complicated design
2. Comparison of Construction Methods

▣ Modulization / Concurrence ▣ Typical Construction Method


Construction Methods

⊙ Concurrent construction of S/S and Boiler ⊙ Boiler installation after completion of S/S
installation
⊙ S/S Modulization on the ground
⊙ Core Frame, Subsidiary S/S and Boiler ⊙ Separate installation of S/S 1Tier ~ 5 Tier
installation at the same time with Bottom-Up method

⊙ Lifting after Moduliztion on the ground, Erection ⊙ Unit Lifting and installation
⊙ Using special Lifting device : ⊙ Using ordinary construction lifting device
Hydraulic jack - to be able to lift Module
[2,500Tons] ⊙ Site assembly of Boiler equipment
⊙ Site assembly of Boiler equipment ▶ - Ground assembly : 20%,
▶ - Ground assembly : 70%, - Assembly after installation : 80%
- Assembly after installation : 30%
⊙ Planning and scheduling for concurrent
construction sequence Planning
Compare to Main Erection Process

Modulization / ConcurrenceConstruction Methods Typical Construction Method

660MW x 2 Units 560MW x 2 Units


Main Proper 5,643tons Main Proper 5,103tons
Boiler weight Boiler weight
S/S 9,191tons S/S 5,200tons
Duration Duration 1990.07.16~1992.08.14
15.5 Momth
(S/S at site~Firing) (S/S at site~Firing) (25 M)
HxWxD 76m x 41m x 41m HxWxD 76m x 37m x 42m
▷ Lifting S/S after pre-Ass’y Core Frame After Starting
▷ Separately lifting STL/STR
on the ground S/S
▷ Pressure Parts unfurnished
▷ Pre-assembling Pressure Parts

Core
Frame

Module
Work Stand 1Tier

Modulization/Concurrent Erection Method Typical Construction Method


▷After installation of S/S Core Frame to install
2 month after
Pressure Panel and subsidiary-S/S at the same time ▷Completion S/S 2 tier
▷ Coil Modulization on the ground starting S/S

?
Panel
Ass’y

?
?

Sub-S/S
Ass’y
2Tier

1Tier

Module
Work
Modulization/Concurrent Erection Method Stand
Typical Construction Method
▷ In the process of Modulization of Heavy Girder ▷ S/S Heavy Girder installation
Boiler Furnace & Back Pass on the ground (Using Crane)
▷ S/S Heavy Girder installation (Using Crane)
Lifting
※ 6 month after starting S/S
※ 2 month after Starting S/S

? Heavy Girder
Heavy Girder Installation
?
Installation

Module Ass’y
on the Ground

Modulization/Concurrent Erection Method Typical Construction Method


▷After S/S Core Frame / Heavy Girder completion ▷ After completion of S/S 1~5 tiers
starting sub-S/S installation and DRUM starting pressure parts installation
20% of Pressure parts installation
※3 month after starting S/S Lifting ※ 7.5 month after starting S/S
▣ 4.5 month earlier in comparison with Typical Method
[Drum lifting point]
▷ S/S Core Frame design for Boiler load support
Winch
▷ Module work on the ground and concurrence installation
of S/S and Boiler

Lifting using
Hydraulic Jack

?
Drum

Drum

Pressure Parts
Module
assembly on the
ground

Modulization/Concurrent Erection Method Typical Construction Method


▷ Back Pass module assembly on the ground
After Drum ▷ Completion of S/S installation
▷ Lifting after Boiler Coil Module work
▷ Separate installation of Boiler Pressure
(Using Hydraulic Jack) lifting parts (Using Winch)
▷ Lifting after Sub-S/S module assembly

Hydraulic Jack Winch

Coil Module ?
Lifting

Back pass Module


assembly on the
ground

Modulization/Concurrent Erection Method Typical Construction Method


▷ 50 % completion of total S/S installation ▷ Completion of S/S installation
▷ Concurrent Lifting Boiler Back Pass and Back Pass ▷ Separate installation of Boiler Back Pass
S/S Support (Using Hydraulic Jack System) Lifting (Using Winch)
※ 8.5 month after starting S/S ※ 16.5 month after starting S/S

Hydraulic Jack
Winch

Back pass
Module
Lifting 中

? ?

Modulization/Concurrent Erection Method Typical Construction Method


60 % completion of total S/S installation ▷ Completion of S/S installation
100% completion of Boiler pressure parts Hydro Test ▷ Completion of Boiler pressure parts
installation installation
※10 month after starting S/S ※ 19 month after starting S/S
▣ 9 month earlier in comparison with Samchunpo
[Hydro test point]
▷ Installation S/S Aux. after Hydro test
▷ Ground Module assembly and S/S & Boiler concurrent construction

Modulization/Concurrent Erection Method Typical Construction Method


Completion of S/S installation Completion of S/S installation
Completion of Boiler installation First Firing Completion of Boiler installation
※ 15.5 month after starting S/S ※ 24.5 month after starting S/S
▣ 9 month earlier in comparison with Typical Method
[First firing point]
▷ Ground Module assembly and S/S & Boiler
concurrent construction

Modulization/Concurrent Erection Method Typical Construction Method


Sequence of Modulization / Concurrent Installation
Sequence of Modulization / Concurrent Installation
Sequence of Modulization / Concurrent Installation
Sequence of Modulization / Concurrent Installation
Install Heavy
Girder after
Panel Erection
Sequence of Modulization / Concurrent Installation
Sequence of Modulization / Concurrent Installation

Assemble RH Final &


SH Final Tube Module
Sequence of Modulization / Concurrent Installation

Install
Jack for
Drum
Sequence of Modulization / Concurrent Installation

DRUM
LIFTING
Sequence of Modulization / Concurrent Installation

Install
Downcomer
pipes (6ea)
Sequence of Modulization / Concurrent Installation
Sequence of Modulization / Concurrent Installation

Assemble Back Pass Module


Prepare the (Hanger rods, roof panel, LTRH)
Assembling of
SH DIV. Module
Sequence of Modulization / Concurrent Installation

Lift the Sub-


assembled SH
DIV. Module
Sequence of Modulization / Concurrent Installation

Install the Jack


for SHP & RHP
Sequence of Modulization / Concurrent Installation
Sequence of Modulization / Concurrent Installation
Sequence of Modulization / Concurrent Installation

Install the Jack


for Back Pass
Module Lifting
Sequence of Modulization / Concurrent Installation

Install the Wire


for Back Pass
Module Lifting
Sequence of Modulization / Concurrent Installation

1’st Lifting
of
Back Pass
Module
Sequence of Modulization / Concurrent Installation
Sequence of Modulization / Concurrent Installation

Assemble the
Back Pass
Wall Panel
Sequence of Modulization / Concurrent Installation

SH tube
bundle
lifting

Lower panel lifting

Assemble Back
Pass LTRH

Arch lifting
Sequence of Modulization / Concurrent Installation
Sequence of Modulization / Concurrent Installation

Assemble Eco
Tube, Eco Header
Sequence of Modulization / Concurrent Installation

Back Pass
Module
Final Lifting
Sequence of Modulization / Concurrent Installation

Install the
Burner windbox,
Low water panel,
Hopper panel,
Water inlet header,
Suction inlet piping.