Over view
Introduction
Mill rejection type
Our plant mill rejection
Aux rejection system
MRHS Compressor tech data / line up/ operation.
Local line up
Local isolation
Start permissive / Inter lock and Protection
Sequence of operation mode
1) Time mode
2) Probe mode
3) Manual mode
Over view
Introduction
Mill rejects will be led to respective pyrite hopper through mill rejects outlet spout and
thereafter, it is further discharged to the transport vessel. Pneumatic conveying
system has been envisaged for conveying of rejects from the transport vessel to mill
reject silo
Mill rejection type
Once all permissive are satisfied change required MRH system (I,II,III,IV,V,VI)
from Manual to Auto. Start the sequence one by one.
Vessel Inlet Dome valve will open and Pyrite Hopper I/L KGV-1 close.
Filling Timer (T-1) starts for 10sec once the KGV-1 close limit acts and Dome
valve opened.
After completion of T1 Dome valve gets closed. Completion of filling is ensured
after getting dome valve close FB and seal pressure healthy. KGV-1 opens.
Blow valve opens and conveying Time (T2) starts for 60 sec.
Simultaneously pyrite hopper quenching water SOV opens for 2sec.
Throughout conveying timer (T-2) if the vessel pressure maintains normal (<3.0
KSC) conveying cycle is completed. Sequentially cycle gap timer (T-3) starts for 15
sec. On completion of cycle gap timer sequentially next MRH system starts as per
set timer T-1, T-2, T-3 & T-4.
During conveying if vessel pressure persist above Intermediate Pressure (IPS set
pressure-3.0 KSC) , line block timer will be initiated (T-4) for 200 sec.
Conveying continues till line block timer (T-4) to clear the blockage if any.
During line block timer if High Pressure Switch (HPS) acts (HPS set pressure- 4.0
KSC) and persists till completion of T-4 line block is declared and that MRH system
changes from Auto to manual.
On completion of timer T-4 sequentially next MRH system starts the same above
said cycle.
Pyrite hopper to atmospheric rejection valves KGV-2 opens with respect to the
timer T-4 of 15 min.
Timer Mode
Following table shows the normal time setting for the sequential operation in Timer
Mode (which can be adjusted as per rejection of individual mills requirement
Check the Pyrite Hopper I/L valve KGV-1 is open of Mills which are in service.
If the Material is oversize then open the Pyrite Hopper discharge valve KGV-2
for removing oversized material.
If the level of Oversize material attained low, close the KGV-2 valve.
Open the Pyrite Hopper discharge valve KGV-3.
After removal of material, close the Pyrite Hopper discharge valve KGV-3
Unloading of rejection bunker.
Ensure tractor placed on bunker chute bottom
Check the bunker level.
Open the bunker bottom gate.
Check the level of tractor send to rejection yard.
same will follow until bunker will empty.