Professional Documents
Culture Documents
Ch.1 Introduction
12/10/2017
Estimation
Estimation is a process of calculating the quantities and costs of the various items
required for the work and expenditures likely to be incurred in the construction of a
proposed work and therefore to determine the final cost and the time required for
the construction before starting the work or taken up.
Purpose of estimation:
5. To fix the completion period from the size of works involved in the estimate.
* Usually the estimating cost must be more than the actual cost.
Estimating Accuracy
Estimating accuracy increases during the life of the project as more knowledge is
gained about the project.
100
50
Accuracy (%)
50 100
1
Estimation
Ch.1 Introduction
12/10/2017
Importance of accurate estimates
1. Inaccurate time estimates can result in inefficient use of resources and late
delivery.
2. Inaccurate cost estimates can result in insufficient budget being allocated, or
excess budget being set aside for the project when it could be used for other
projects.
3. If the cost or benefits estimates are inaccurate this can lead to incorrect
decisions about proceeding with the project being made.
An Engineer who has a good knowledge and experience about the construction
processes and usually the estimator does not give a fixed number of
estimation, but gives a number between two edged may exceed one of theme
the final cost.
Client (OWNER):
1. A person or organization, who built the project, expends money and get
benefits from the project.
2. An organization built a project but doesn't get any benefits from the project
like service projects like (government offices, roads, etc.)
Types of estimation:
1. Approximate estimation.
2. Detailed estimation.
2
Estimation
Ch.1 Introduction
12/10/2017
Approximate estimation (QUICK ESTIMATIOM):
The Estimator will estimate the cost of the project roughly; depending on the
entire area or volume of the building and the unit rate of previous buildings
have the same conditions.
The area or volume of the building is multiplied by the cost of one unit of
measurement
1- Area Method
2- Cubic Method
This type of estimation is done after preparing all required plans, details,
specifications, prices of materials, fees of workers, equipment, additional
fees and expenditures, profits.
The project works are divided into many activities, scheduled and the
quantity and rate of each activity (ITEM) is tabulated and finally the total cost
(AMOUNT) of the building will be calculated.
Average fees:
1- Ordinary fees
2- Additional fees
When the works require preparing at two or more stages, therefore, the owner must
spend an over times for the workers and equipment.
The amount of worker and equipment fees will be more than the ordinary fees.
Daily fees
Additional fees of one working hour =
Number of working hours per day
3
Estimation
Ch.1 Introduction
12/10/2017
Working days = 8 working hours
The additional hour fees may increase at the holidays or when the working hours
exceeds the limits.
5. Weather conditions.
6. Preparation works.
Profit:
Profit = {is an amount that is given to the contractor during the execution
periodically – [cost expended to the executed items + (salary, insurance, taxes...)]}
** The profit usually ranges between 10-15 % and may reach 20% or more in
some times