The Status Quo of Research On High-Voltage AC Transmission Lines in High-Altitude Areas
The Status Quo of Research On High-Voltage AC Transmission Lines in High-Altitude Areas
Abstract—Along with the rapid economic development in recent element method to calculate relevant parameters, as well as
years, people's demands for electricity have also been increasing the status quo of domestic and foreign researches on power
very rapidly, which makes the power industry grow very fast, transmission lines in high-altitude areas.
however, there have also been new challenges for the safety of
the grid. Due to the complexity of China's topography, many II. RESEARCH ON HIGH-VOLTAGE AC TRANSMISSION
power transmission lines under construction and planning are LINES IN HIGH-ALTITUDE AREAS
inevitable to pass through the high-altitude areas. Due to the
high altitude and low air pressure, a number of external A. Research Background
environmental factors are quite different from these of the At present, the voltage level of 500 kV has been widely
low-altitude areas, and all these factors have a great impact on applied in many substations in China that we have
the power transmission lines, which will bring a lot of special accumulated a wealth of design and manufacturing experience.
problems to the design and operation of the power transmission
We have built 500 kV Caopu Substation at an altitude of
lines. This paper describes the finite element method analysis
which is used to calculate the relevant parameters of power 1,800m in Yunnan in 1991, 500 kV Zhaojue Substation at an
transmission lines in high-altitude areas, as well as the status quo altitude of 2,100 m in Xichang, Sichuan Province in 1993, and
of the research on high-voltage AC power transmission lines in 500 kV Qujing Substation at an altitude of 1,800mm in Yunan
high-altitude areas. By analyzing the status quo of these studies in 2002. However, we still haven’t built any substation
and combined with the actual terrain situations of high-altitude which is located in a place at an altitude higher 3,000m, and
areas, we can provide the construction of high-voltage AC power there are also some unreasonable situations in the established
transmission line in high-altitude areas with some valuable substations in high-altitude areas, which still need to be
references, thus to ensure the safe operation of such power further improved. For example, for the insulator strings of
transmission lines.
power transmission lines, the higher the altitude is, the smaller
Keywords- high-voltage AC power transmission lines; finite the air density will be, therefore, the discharging voltage of
element method; altitude correction factor the insulator strings of power transmission lines and air gaps
will be reduced, which can not fully ensure the safe operation
of power transmission lines in high-altitude areas. In addition,
I. INTRODUCTION
the interference of power transmission lines and substations
Since the geographical and meteorological conditions of (or booster stations) on the communications, radio and
high-altitude areas are quite different from these of low- television has become obvious, the sources of the interference
altitude areas, the insulation coordination parameters of low- are mainly divided into two types, corona discharge and gap
altitude areas can not be fully applied for power transmission discharge. How to reduce the interference of these two
line design in high-altitude areas. Therefore, to directly apply negative effects is also an important issue that we need to
the insulation coordination parameters of high-altitude areas explore. In addition, the insulation performances of
has a great importance in safe and economic operation of such high-voltage power transmission lines in high-altitude areas
power transmission lines. are still needed to be further studied. Since the geographical
Currently, there are two main means to obtain such and meteorological conditions of high-altitude areas are quite
parameters, one is to directly carry out relevant tests in high- different from these in low-altitude areas, the insulation
altitude areas to obtain insulation coordination parameters in coordination parameters of low-altitude areas can not be fully
high-altitude areas, currently, Yunnan Electric Power Test & applied for power transmission line design in high-altitude
Research Institute has obtained the first batch of experimental areas. Therefore, to directly apply the insulation coordination
data needed for design of power transmission lines in parameters of high-altitude areas has a great importance in
high-altitude areas; the other is to set up three-dimensional safe and economic operation of such power transmission
electrostatic field model by virtue of the software like Ansys lines.
and carry out stimulation and calculation on the computer by B. Research Significance
virtue of finite element method, and then draw the relevant The development and application of fittings for 500 kV
parameters. substations in high- altitude areas can effectively reduce
This paper describes the significance of using finite environmental pollution caused by the noise generated by