Professional Documents
Culture Documents
Guideline
on
the Cost Estimation
for Construction Packages
in Viet Nam
T h e G o v e r n m e n t o f t h e S o c i a l i s t R e p u b l i c o f Vi e t N a m ( h e r e i n a f t e r r e f e r r e d t o a s G O V ) m a i n t
sustainable economic growth and implements a large number of major infrastructure d
p r o j e c t s . H o w e v e r d u e t o i n s u f f i c i e n t p r o j e c t m a n a g e m e n t
management in construction works, lots of construction accidents in quality and safety
recorded. I a nt ddition,
h b m dhere i cave een
c many isputes
i V N n onstru
during construction implementation. Hence, those obstruct smooth implementation of
projects.
The GOV requested JICA to run a technical cooperation project and then the Project for C
Enha nc em e nt i n Cos t Es t im a ti on, Cont r ac t M a na ge me nt , Qua l
Investment Projects (hereinafter referred to as CCQSP) has been implemented since May 2015.
As o onet o f he
o C utputs
t G f o CQSP,
C E his
f C uidelineC Wn ost stim
has b een
f ormulated
f i o c or cmprovement
e s i G f T urrent
o o ost
t stimation
Guideline are as follows.
To a s s i s t t h e S t a t e A u t h o r i t i e s , P r o j e c t o w n e r s a n d P r o j e c t M a n a g e m e n
importance of cost estimation system for public construction works and to understand necessity of
improvement of current system to the international standard level
To h e l p t h e s t a f f s c o n c e r n e d o n c o s t e s t i m a t i o n c o m p r e h e n d t h e c o n c e p
estimation s e ystema d nhanced
c a e nd metailed o D ontents
a I nd stima
Cost structured package price of construction project
W i t h t h i s s t u d y a n d o au pt pa uc it t, yc f o r i n t e g r a t i n g q u a l i t y a n d s a f e t y m a n a g e m e n t i n t o
estimation of construction works is enhanced and more appropriate and internationally standard cost
estimation system will be realized.
This Guideline illustrates basic principles and methodologies recommended for proper cost estimation
system of Direct and Indirect Cost in package price of construction projects; therefore, it is important
for not only staffs concerned and also all officers in GOV to review and understand the contents i
order to promptly improve current stale cost estimation system in Viet Nam.
H ow e v e r, i t w i l l t a ke m uc h m o r e t i m e t o c om p l e t e t hi s Gu i d e l i n e i n d e t a i l w i t h d e e pe r s
f i n a l l y, i t i s e x p e c t e d t h a t t h i s G u i d e l i n e c o n t r i b u t e s t o t h e e s t a b l i s h m e n t o f s t a t e
Estimation System in Viet Nam in near future so as to produce fairer and more appropriate package
price of each public construction work.
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Table of Contents
Chapter 1 Purpose.....................................................................................................................................1
i
Guideline on the Cost Estimation for Construction Packages in Viet Nam
ii
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Chapter 7 Overhead................................................................................................................................72
7.1 Definition..........................................................................................................................72
7.2 Component........................................................................................................................72
(1) Head and Branch Offices Expenses..................................................................................72
(2) Profit.................................................................................................................................72
7.3 Method of Estimation.......................................................................................................73
(1) Present State.....................................................................................................................73
(2) Estimation Method Suggested..........................................................................................74
iii
Guideline on the Cost Estimation for Construction Packages in Viet Nam
APPENDIX
1 Comparison Tables between Current Regulations on Cost Estimation for Construction
Works and the Contents of GLCE............................................................................................A-1
2 Comparison of Structure of Cost............................................................................................A-13
3 Definition of Type of Occupations.........................................................................................A-15
4 Machinery Operation Unit Price............................................................................................A-20
5 Detail Explanation on Common Indirect Cost Items by rate.................................................A-23
6 Detail Explanation on Common Indirect Cost Items by piling up.........................................A-28
7 Detail Explanation on Site Management Cost Items..............................................................A-30
8 Schedule and Organization Chart...........................................................................................A-36
9 Survey Form of Unit Price of Material..................................................................................A-37
10 Survey Form of Unit Price of Labor......................................................................................A-38
11 Survey Form of Unit Price of Machinery...............................................................................A-40
12 Survey Form of Productivity Rate..........................................................................................A-43
13 Expense Trend Survey Form for Project Owner....................................................................A-50
14 Expense Trend Survey Form for Contractor..........................................................................A-53
iv
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Chapter 1 Purpose
Construction projects are not implemented in exactly the same conditions in any construction
objects because wide variety of structures are produced on the basis of each individual
specifications in the infinite variety of conditions of weather, geography, terrain, environment,
society, and so forth. In this production form for implementation of construction projects by
contract agreement, project owners have to perform series of acts such as planning, research,
design, cost estimation, tendering and contracting, construction, supervision and inspection, and
so forth. in each individual project. Cost estimation is positioned as an important and inevitable
work closely related to all activities in these procedures.
Therefore, cost estimation must be carefully implemented with close link to the specification,
construction site, construction environment, construction period, and construction method
regulated by site conditions. In addition, it is deeply involved in the matters related to the project
cost such as design changes, supervising, and inspection works and so forth.
Current cost estimation methodology of Viet Nam was first established nearly 30 years ago.
Therefore, it has not adjusted to present social economic state of Viet Nam. Moreover, it has not
reflected required quality and safety management cost matching international standard for public
construction projects. Therefore, the existing cost estimation methodology shall be immediately
improved in order to match and harmonize enhancement of construction management methods
toward international standard. This Guideline has been prepared for establishment of new fair and
proper cost estimation methodology which shall be improved in near future for further
enhancement of contract management in Viet Nam.
1
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Current regulations stipulating the matters regarding cost estimation in Viet Nam are as follows.
(as of 1/2018)
Table 2.1 Regulations for Cost Estimation
Sign Category Subjects
50/2014/QH13 Law Law No. 50/2014/QH13 dated June 18, 2014 on the
construction
43/2013/QH13 Law Law No. 43/2013/QH13 dated November 26,2013 on
bidding
32/2015/ND-CP Decree Decree No. 32/2015/ND-CP dated March 25, 2015,
construction cost management
37/2015/ND-CP Decree Decree No. 37/2015/ND-CP dated April 22, 2015, detailed
regulations on construction contract
46/2015/ND-CP Decree Decree No. 46/2015/ND-CP dated May 12, 2015, on
quality control and maintenance of construction works
59/2015/ND-CP Decree Decree No. 59/2015/ND-CP dated June 18, 2015, on
construction project management
06/2016/TT- Circular Circular No. 06/2010/TT-BXD dated March 10, 2016,
BXD guiding the determination and management of construction
investment costs
05/2016/TT- Circular Circular No. 05/2016/TT-BXD dated March 10, 2016,
BXD providing guidance on determination of the unit labor cost
in the construction cost management
1134/QD-BXD Decision - Norm Decision No. 1134/QD-BXD dated October 08, 2015, on
promulgation of the consumption norm for determining
construction machines and equipment shift prices
1776 /BXD-VP Notifications - Norm Notification No. 1776 /BXD-VP issued on 16/8/2007 of
Ministry of Construction promulgating the construction
estimation norm - Construction portion
1091/QD-BXD Decision - Norm Decision No. 1091/QD-BXD dated December 26, 2011, on
promulgation of the construction estimation norm -
Construction portion (Amendment)
1172/QD-BXD Decision - Norm Decision No. 1172/QD-BXD dated December 26, 2012, on
promulgation of the construction estimation norm -
Construction portion (Adjustment and amendment)
588/QD-BXD Decision - Norm Decision No. 588/QD-BXD dated May 29, 2014, on
promulgation of the construction estimation norm -
Construction portion (Adjustment and amendment)
235/QD-BXD Decision - Norm Decision No. 235/QD-BXD dated April 4, 2017, on
promulgation of the construction estimation norm -
Construction portion (Adjustment and amendment)
1329/QD-BXD Decision - Norm Decision No. 1329/QD-BXD dated December 19, 2016, on
promulgation of the norm for using material in construction
Source: JICA Project Team
2
Guideline on the Cost Estimation for Construction Packages in Viet Nam
(2) Necessity
The purpose of the public construction project is to complete a wide variety of target products
under infinite various environments. Therefore, it does not fit commercial deals like automobile
and electric appliance selling in which the price is decided by previously offering from the
manufacturers. In the case of construction projects, the price of the work has to be decided by
project owner’s calculation or estimation order to contractors by presentation of drawings,
specification, bill of quantities, execution conditions, construction period and so forth. This is the
reason why cost estimation is required because price is determined for each project every time.
The following description is the necessities of cost estimation to all stakeholders on construction
projects.
1) Project Owner
To understand the framework of the funding measures
To ensure the fulfillment of appropriate quality
To allow the contractors to obtain appropriate profit
2) Bidders
To ensure the fulfillment of required quality
To determine the appropriate price so as not to lose
To make favorable bid strategy
3) Successful Bidder (Contractor)
For good budget management
To obtain the proper benefits with ensuring appropriate quality for construction
4) Social Demand
To ensure implementation of the fulfillment of appropriate quality of construction
To eliminate the bidders disturbing social regularity
Not to enforce the unfair benefit and unreasonable price to contractors
3
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Construction
Net
Cost
Construction
Construction Cost
Package
Estimate Value-added
Tax
Total Overhead
Contingency
Construction Cost
Cost
4
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Execution method
Source cost (workers,
Work schedules
materials, machines)
Machinery plan Operation rate
Cost of construction
Scaffoldings Productivity
Workers plan . Cycle time . Direct cost
Indirect cost
Quality plan Reuse
Overhead cost
Safety plan Wastage
Profit
Protection of Workers
VAT
surroundings
etc.
etc.
5
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Net Construction
Cost Labor Cost
Construction
Cost Machinery Cost
Overhead
Indirect Cost
Contingency Site Management
Cost Cost
6
Guideline on the Cost Estimation for Construction Packages in Viet Nam
5) Overhead
Construction work cannot be carried out by not only net construction cost, but contractors have to
obtain profit as the commercialized organization. They need to get money for management of
company such as personnel expenses of the owner, executives and administrative staffs, office
fee, utility cost, insurance and tax so forth. Those not related to main construction works are
called Overhead.
6) Direct Cost
Direct Cost is the cost that is used only for purely creating the construction objects. This cost is
composed of 3 main elements such as construction material, labor and machines.
7) Indirect Cost
Indirect Cost, which is the other costs not dealt as Direct Costs, basically doesn’t become contract
unit price items. It is composed of Common Indirect Costs and Site Management Costs and
mostly calculated by rate for labor and time saving of estimation work due to complicated
contents. However, there are cases of estimation by piling up in particular projects with regard to
Common Indirect Cost. Quality control and safety management costs are treated in this Indirect
Cost.
7
Guideline on the Cost Estimation for Construction Packages in Viet Nam
1) Elimination of Absurdity
For compensation of the lack of time due to improper construction period, unreasonable works
such as rush work must not be implemented on work pause period.
2) Elimination of Futility
Rush construction work such as night works with additional work force and machines should not
be carried out in order to regain the delay due to oversight of work prohibition period.
3) Elimination of Non-uniformity
The state that the number of workers and machines in the construction field are temporarily
increased due to overlap of many kinds of construction works should be avoided.
Work Quantity
Required number of days =
Daily average amount of work
Daily average amount of work: standard work volume that can be done per day. This value is
decided in each construction work statistically in advance.
e.g. placing concrete by pump is xxm3/day.
4) To seek the Required number of days for each main work. In the case that the component works
of the main work are executed in series, one after another, the required number of days for each
main work will be the sum of the required number of days for all of the component works. If the
construction periods of component works overlap, make critical path and the required number of
days for the main work will be the length of the main work’s critical path on the time axis.
5) To seek the Required number of days to complete all of main works. In the case that the main
works are executed in series, one after another, the required number of days to complete all of
8
Guideline on the Cost Estimation for Construction Packages in Viet Nam
main works will be the sum of the required number of days for all of the main works. If the
construction periods of main works overlap, make critical path and the Required number of days
to complete all of the main works will be the length of the whole main works’ critical path on the
time axis. The Required number of days to complete all of construction works will be the
Required number of days to complete all of the main works.
6) To count the number of non-working days. Non-working days are composed of holidays and
work impossible number of days that are weatherly bad days such as rain, strong wind, flood and
so forth. It is decided based on the natural conditions on the site. Furthermore, overlapping days
of both should be considered.
7) To set up Rate of operation. Rate of operation is one of important elements to decide the
construction period. This is calculated with the following formula.
Rate of operation is defined as the rate of actual number of operation days to calendar days. The
rate is most affected by non-working days and non-working days is affected by weather.
Therefore, the rate of operation is determined by the location with proper weather conditions. The
district with specific weather in whole year has its own rate of operation in certain country. The
rate of operation is classified with some districts with similar weather in Viet Nam.
Here, Number of overlapping days are calculated by the following formula.
Holidays
Number of overlapping days = Work impossible number of days ×
Calendar days
8) To determine Required calendar days. Required calendar days is calculated by the following
formula.
The Required number of days in the above formula is the required number of days to complete all
of construction works determined by the sub-clause ”5)” above.
9) To determine Days for preparation and cleaning. Days for preparation and cleaning actually
differs by scale and kinds of construction work; however, normally the following days can be
used in general.
Days of preparation – 1 month
Days of cleaning – 10~20 days
9
Guideline on the Cost Estimation for Construction Packages in Viet Nam
4.1 Definition
Direct cost is the costs directly charged to the desired objects for their construction, other than
indirect construction costs. The costs for temporary works for main structures are included in
direct cost. Main items of direct cost consist of material, labor and machinery costs for
construction and temporary works. Temporary works included in direct cost are form, support,
scaffolding, earth retaining, steel sheet pile, dewatering, temporary deck and bridge and various
plants for concrete and asphalt and so forth.
4.2 Structure
The structure of the direct cost is shown in Figure 4.1.
Material Cost
Work items (excavation,
embankment, placing
Direct Cost Labor Cost
concrete, asphalt paving
and etc.)
Machinery Cost
Material Cost = Quantity by design x (1+Wastage factor) x (Purchase price + transportation fee)
[Necessary quantity] means design quantity including appropriate wastage due to execution. This
is decided with wastage factor in each specific material at design stage.
In principle, the price of material is determined based on market prices provided by Department
of Construction. The price of material generally includes purchasing fee by suppliers and
transportation cost from a purchasing place to a construction site. The price varies depending on
the conditions such as purchase location, delivery location, purchase quantity, condition of
payment and so forth.
10
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Unit price of material includes purchase price of material from average market price at the time
of estimation and transportation cost to the construction site. Therefore, the material should be
available at the provider nearest to the construction site in order to minimize transportation cost.
(2) Issues
1) Material prices are constant in any quantity. Generally, if the order is large quantity, a unit price
goes down in accordance with market price.
2) The transportation cost in alleys is insufficient in case of this situation, that narrow road is not
practicable for a large transportation vehicle.
3) The standard method of application of unit price of material is not existing. The target
construction cost of project may be changed without standard method of application.
11
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The unit labor price of a worker who performs construction works shall be determined according
to the following formula:
1
GNC =LNC ×H CB ×
t
Where:
- GNC: the unit labor price paid to a worker who performs construction works in a working day.
- LNC: the monthly input base salary which is used to calculate the unit labor price paid to a
worker who directly performs construction works in a working day, including allowances
according to characteristics and the nature of construction works according to market factors
and types of insurance premiums paid by the worker as regulated (including social insurance,
medical insurance and unemployment insurance).
- HCB: the salary coefficient which is applied to workers who perform construction works and
regulated in Annex 2 of this Circular.
- t: 26 working days per a month.
Source: Circular No.05/2016/TT-BXD
12
Guideline on the Cost Estimation for Construction Packages in Viet Nam
4) Grouping
In current cost estimation system, there are two groups consisting of nine kinds in group I and
some kinds in group II. The classification of occupation is shown in Table 4.3.
Table 4.4 Grouping of Occupations
Group Description
Group I Workers who perform the following works:
1) woodwork, 2) bricklaying, 3) metal work, 4) concrete work (except for asphalt
concrete), 5) formwork, 6) completion work and 7) earthwork (excavation and
embankment, 8) Construction survey(including measurement), 9) operation of construction
machinery and equipment (earthwork machinery, rammer, lifting equipment, drilling
equipment, pile driver, pump, welder, so forth.). This group includes manual workers who
perform construction works.
This group includes manual workers who perform construction works.
Group II Workers who perform construction works other than those are specified in group I
Source: Circular No.05/2016/TT-BXD
(2) Issues
1) The current unit labor price does not includes the temporary salary such as bonus and so forth.
2) Kinds of labors seem insufficient to cover all work items.
3) In the current norm system, the labor occupation is not mentioned and unit labor price is mixed
into group I and group II.
4) Both groups are divided into seven grades with coefficient. It is difficult that the criteria of
coefficient is set for every working items.
5) Kinds of labors and calculation do not reflect actual work on site as too theoretical.
13
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The public work unit labor price excludes the following components.
a) Extra wage such as overtime, holiday and midnight working
b) Allowance for an excessive amount of normal working content or condition
c) Site management cost (legal welfare paid by employer, safety training cost and so forth.) and
various cost of overhead cost.
n n
BSi PSi
EBS=∑ ✕ 8 hours /n∨EBS=∑ ✕ 8 hours /n
i=1 SHi i=1 SHi+ EHi
In which:
EBS: Equivalent basic salary
BS: Basic salary
PS: Piecework salary
SH: Scheduled working hour*3
EH: Extra working hour
n
BAi
EBA=∑ ✕ 8 hours /n
i=1 SHi
In which:
EBA: Equivalent basic allowance
BA: Basic allowance
SH: Scheduled working hour
c) Temporary salaries
14
Guideline on the Cost Estimation for Construction Packages in Viet Nam
n
ASi
TS=∑ /n
i=1 ADi
In which:
TS: Temporary salary
AS: Annual total temporary salaries
AD: Annual working days
Source: JICA Project Team
Figure 4.6 Public Work Unit Labor Price Component
*2 Temporary salary
The temporary salary includes the following items.
1. Bonus: the payment is paid regularly (2~3 times per year) or temporary in accordance with the
work performance of labor and this amount of payment shall be not fixed.
2. Allowance for injury except industrial accident, consolatory present of money and the sudden
and temporary payment.
3. The payment shall occur indeterminately and unusually such as marriage allowance, retirement
allowance, maternity allowance and so forth.
15
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Regular
Wage Basic wage Basic Salary
wage
Piecework salary
2. Basic allowance
Various
Supplemental allowance Family allowance
allowance
commuting allowance
Housing allowance
Site allowance
Allowance for duties,
abilities and employment
Skilled allowance
3. Temporary salaries
Temporary
Bonus (Terminal allowance)
salaries
16
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Regular
Wage Basic wage Basic Salary
wage
Piecework salary
2. Basic allowance
Various
Supplemental allowance Family allowance
allowance
commuting allowance
Housing allowance
Site allowance
Allowance for duties,
abilities and employment
Skilled allowance
3. Temporary salaries
Temporary
Bonus (Terminal allowance)
salaries
17
Guideline on the Cost Estimation for Construction Packages in Viet Nam
2) Type of Occupations
There are group I including nine occupations and group II including the different occupations of
group I in the current system. Even more than nine occupations are indicated in Circular
No.05/2016/TT-BXD, there is only one item of labor in the norm. Therefore it is recommended
that the type of occupation are increased and specified each occupation in the productivity table.
The increased type of occupations is recommended shown in Table 4.4. The definition of each
occupations is indicated in Appendix 3 Definition of Type of Occupations.
Table 4.5 Type of Occupation
Type of Occupations
Infrastructure Work Building Work Other Work
1 Special worker 19 Tunnel special worker 37 Carpenter 53 Construction survey
18
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Wage status
Result of actual
condition survey
Social insurance
participation status
Depreciation Cost
Unit price of machinery consists of machinery ownership cost and operation cost. The assembly
cost, disassembly cost and transportation cost are to be included in the indirect cost, the details
are stipulated in Chapter 6.
19
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Machinery shift prices of construction machines and equipment for works shall be in accordance
with the Price List of machinery shift prices (issued by competent Authorities such as PPCs) or
the Machinery-hiring Price List (following market prices). As for machines and equipment those
are required for construction works but not available in Viet Nam and in need of temporary
import, then their machinery shift prices shall be determined according to their hiring prices in
the region market (ASEAN, Asia) or the machinery shift prices of similar machines and
equipment which have been used in Viet Nam.
Price of machinery shift includes all or part of the cost items like cost of depreciation, repair, fuel
or energy, operator and other costs and is calculated with the formula below:
a) Depreciation cost
The cost of depreciation is calculated by reduction of prime cost of machinery into an
operation cost during the period of use. The percentage of machinery depreciation are
determined at each type of machinery by Ministry of Finance.
The cost of depreciation in the price of machinery shift is determined by the formula:
(G−GTH )×Đ KH
C KH =
N CA
In which:
- CKH: cost of depreciation in the price of machinery shift (VND/shift)
- G: prime cost of machinery before tax (VND)
- GTH: recovery value (VND)
- DKH: rate of machinery depreciation (% / year)
- NCA: number of working shifts of machinery in a year (shift/year)
Source: Circular No.: 06/2016/TT-BXD
20
Guideline on the Cost Estimation for Construction Packages in Viet Nam
b) Repair cost
The cost of machinery repair includes regularly or irregularly maintenance and repair cost of
machinery during the number working shift of machinery in a year in order to maintain and
restore the operation capacity of machinery.
The cost of repair in the price of machinery shift is determined by the formula:
G×ĐSC
CCS =
N CA
In which:
- CSC: cost of repair in the price of machinery shift (VND/shift)
- DSC: rate of machinery repair (% year)
- G: prime cost of machinery before tax (VND)
- NCA: number of working shift of machinery in a year (shift/year)
Source: Circular No.: 06/2016/TT-BXD
21
Guideline on the Cost Estimation for Construction Packages in Viet Nam
conditions for machinery use and price level of machinery maintenance and repair on the
market.
c) Fuel and/or power cost
The fuel and energy for one working shift of machinery are diesel / gasoline, oil, power, gas
or compressed air for operation of the construction machineries. Those items are called main
items.
Other than fuel and energy are lubricants, transmission oil and so forth., which are called as
auxiliary fuel in a working shift of machinery.
The cost of fuel and energy in the price of machinery shift is determined by the formula:
n
C NL=∑ Đ NLi ×G NLi ×K Pi
i=1
In which:
- CNL: cost of fuel and energy in the price of machinery shift (VND/shift).
- DNL: fuel consumption rate and energy of the working time of machinery in a shift.
- GNL: price of fuel
- Kp: coefficient of price of auxiliary fuel
- n: number of types of fuel used in a machinery shift.
Source: Circular No.: 06/2016/TT-BXD
Fuel consumption rate and energy per one working shift of machinery
Fuel consumption rate and energy per one working shift of machinery is determined on the
principle of conformity with the actual working time of machinery in a shift, consumption of fuel
and energy of machinery and the specific conditions of works or similar machinery issued by
MOC.
Coefficient of price of auxiliary items for one working shift of machinery
The coefficient of cost of auxiliary fuel is valued within the range as follows.
Petrol engine Diesel engine Electric engine
Coefficient 1.01 – 1.03 1.02 – 1.05 1.03 – 1.07
Source: Circular No.: 06/2016/TT-BXD
In case of determining the price of machinery shift of types of machinery to perform some
activities (survey, testing and others) but the cost of fuel and energy was included in the cost
of materials in the unit price, it shall not be included in the price of machinery shift.
The main fuel consumption rate of machinery types used for work with the actual working
time (number of hours) of machinery in different shifts, the fuel consumption rate should be
developed on the principle of consistence with the number of actual working hours of
machinery in a shift of each type of work.
22
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The cost of controlling labor in the price of machinery shift is determined by the following
formula:
n
CNC Ni CTLi
i 1
In which:
- N: number of operator's grade of machinery in one machinery shift.
- CTL: workday unit price of worker’s controlling grade of machinery
- n: number and type of operator in one machinery shift.
Source: Circular No.: 06/2016/TT-BXD
In case of determining the price of machinery shift of machinery types to perform some
work (such as survey, testing and others) but the labor cost of machinery operating for
survey, testing and others is included in labor cost in the unit price.
e) Other cost
The other costs are necessary to ensure the machinery operation. The other costs include the
insurance of machinery during the period of use, storage and service for the technical
maintenance in machinery storage, register, and movement of machinery within the
construction site and the other relevant costs directly related to the management and use of
machinery at the construction site.
The other costs in the price of machinery shift is determined by the formula:
G GK
CK
NCA
In which:
- CK: other costs in the price of machinery cost (VND/shift)
- GK: rate of other costs of machinery (% year)
- G: prime cost of machinery before tax (VND)
- NCA: number of working shifts in a year (shift/year).
Source: Circular No.: 06/2016/TT-BXD
23
Guideline on the Cost Estimation for Construction Packages in Viet Nam
type of machinery, size of machinery and conditions for operation and use of respective
machinery corresponding to the specific conditions of works.
(2) Issues
1) Depreciation cost is calculated according to the rate promulgated by Ministry of Finance (MOF).
The data using for calculation may not be the same, therefore, there is gaps between calculation
of MOC and MOF.
2) The financial cost is not included in the machinery shift price.
3) The working hour and one working shift are not clear to calculate the unit machinery price for
each machinery.
4) Number of the working day / year is comparatively large.
5) Fuel consumption rate per hour is not clear even the fuel consumption rate per shift converts to
that rate per hour. Because the machinery shift includes operating, waiting and moving hour.
6) Prime cost of machinery seems relatively low, comparing with that as international level
7) Annual working hours of machinery seems relatively long and not reflect practice on site,
comparing with that as international level. The working hours seems theoretical calculation.
The machinery ownership cost is calculated as unit price per one operation hour and unit price
per one day of service based on the above formula for cost estimation.
The unit of machinery ownership cost in current system is applied “machinery shift”. It is
recommended that “machinery shift” should change into “days of service” to clear the
productivity rate and specify the performance and mechanical property of each machinery. The
days of service shall be surveyed by the actual condition survey.
The detail description regarding the “machinery shift” is described in (1).
2) Operation Cost
There are four components in the operation cost. Operation cost for operator and labor and fuel,
oil or electric cost are main items of operation cost. Regarding the operator cost are applied three
types of occupations such as operator (special), operator (ordinary) and special worker depending
on the machinery type. The determination of those unit labor cost is applied from the public work
unit labor price in labor cost.
24
Guideline on the Cost Estimation for Construction Packages in Viet Nam
3) Days of service
As stated above, the unit of construction machinery is applied the “one working shift” in current
system. However, the operation hour per day should be different depending on the construction
conditions. Therefore, it is recommended that the days of service should be applied instead of
“one working shift” to reflect the current construction condition at a site.
The concept of days of service is composed with the period which is from the day of carrying-in
the construction machinery at a site to the day of carrying-out a construction machinery from a
construction site and days of assembly and disassembly are included.
The detail of the days of service is shown in the following items.
a) Operation day
b) Number of work pause day on Sunday and National holiday
c) Number of work pause day due to bad weather
d) Number of work pause day for maintenance or replacement consumable
e) Day of assembly and disassembly
Construction Flow
Transportation Assembly Construction Disassembly Transportation
Provided by Provided by
Transportation Transportation
cost in Indirect
Operation hour / day cost in Indirect
Cost Cost
Days of service
Construction Flow
Transportation Assembly Construction Disassembly Transportation
Provided by Provided by
Transportation Operation hour / day Transportation
cost in Indirect cost in Indirect
Days of service
Source: JICA Project Team
Figure 4.11 Concept of Days of Service
25
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The flow of determination of machinery cost is shown in Figure 4.9. The example of machinery
operation unit price is shown in Appendix 4 Machinery Operation Unit Price.
5) Prime Cost
Prime cost is base figure to calculate a lot of elements for unit price of machinery. Therefore, the
prime cost has a significant influence for the calculation of unit price. The elements that are
related with the prime cost are “maintenance and repair cost”, “annual management cost”,
“residual value”, “conversion value machinery ownership cost per an operation hour” and
“conversion value machinery ownership cost per a day of service”.
Additionally, the unit price of machinery is considered of depreciation rate for calculation.
Therefore, it is recommended that the prime cost should be surveyed based on new machinery
(not used or old one).
6) Depreciation
The machinery ownership cost consists of the depreciation cost, maintenance and repair cost, and
management cost. The machinery ownership cost can be separated in “variable cost” and “fixed
cost”. The maintenance and repair cost belongs to “variable cost” and management cost belongs
to “fixed cost”. On the other hand, the depreciation cost shall be divided due to its characteristics.
The depreciation cost is necessary whether machinery is operated or not during the occupation at
the site because it cannot be shifted to the other construction site. Therefore, the depreciation cost
shall be divided and the half of depreciation cost shall be calculated taking into the “variable
cost” and other shall be calculated on “fixed cost” because of the above condition.
Therefore, the half of the depreciation cost shall be added in the “variable cost” and the another
shall be added in the “fixed cost”. Figure 4.10 explains recommended Structure of Machinery
ownership cost.
26
Guideline on the Cost Estimation for Construction Packages in Viet Nam
27
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Items Description
(4) Annual operation Annual operation day is determined based on the result as well as operation hour by
day actual condition survey of a machinery and same or similar machinery. It is
accumulated days that machinery is operated in actually.
(5) Annual standard Annual standard days of service is determined based on the use result as well as
days of service operation hour and operation day by actual condition survey of this machinery and
same or similar machinery. It is from a day of carrying in machinery to a day carrying
out at a construction site. Refer to (3) improvement 3) Days of service in Chapter 4.
(6) Maintenance and Maintenance and repair rate is the percentage of the total maintenance and repair cost
repair rate in the period of standard number of life years in use to the prime cost.
(7) Annual Annual management rate is the percentage of the total annual management cost to the
management rate prime cost. This cost is the necessary management cost to have a machinery. The
management cost includes the insurance, tax and storage cost.
Item Rate Remark
Truck X% Except the vehicles cannot travel on the public road
Heavy machinery X% Machinery which required the high skill capacity for operating
Other X% Machinery which prime cost is generally lower
Residual value Residual rate is the percentage of the remaining value after the life years in use to the
Remaining value
prime cost.
Basic Price
Remaining value
Residual rate (%) =
Prime cost
Depreciation rate (%) = 100 – residual rate (%)
(8) Machinery Machinery ownership cost rate per an operation hour (or per day) is related with
ownership cost maintenance and repair cost and half of the depreciation cost.
rate per an 1
operation hour ∗Depreciationrate+(6)
2
(or per day) (8) = ∗1
( 2)
( 3 )∨(4 )
(9) Machinery Machinery ownership cost per an operation hour (or per day)is added the element of
ownership cost “Price” based on the (8).
per an operation (9) = (1) x (8)
hour (or per day)
(10) Machinery Machinery ownership cost per day of service is related with management rate and half
ownership cost of the depreciation cost.
rate per a day of 1
service ∗Depreciationrate
(10) = 2 }∗1
{ +(7)
(2) (5)
(11) Machinery Machinery ownership cost per a day of service is added the element of “Price” based
ownership cost on the (10).
per a day of (11) = (1) x (10)
service
(12) Conversion value Conversion value machinery ownership cost rate per an operation hour is integrated
machinery variable expense and fixed expenses divided by an operation hour.
ownership cost Depreciationrate+(6) }∗1
rate per an (12) = { +(7)
operation hour
(2) ( 3 ) ∨( 4)
It is expressed “per day” rather than “an operation hour” depending on a machinery
type.
(13) Conversion value Conversion value machinery ownership cost per an operation hour is added the element
machinery of “Price” based on the (12).
ownership cost (13) = (1) x (12)
per an operation
hour
(14) Conversion value Conversion value machinery ownership cost rate per a day of service is integrated
machinery variable expense and fixed expenses divided by a day of service.
28
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Items Description
ownership cost Depreciationrate+ (6 )
rate per a day of
service (14) = { ( 2)
+ ( 7 ) ∗1
}
(5)
(15) Conversion value Conversion value machinery ownership cost per a day of service is added the element
machinery of “Price” based on the (14).
ownership cost (15) = (1) x (14)
per a day of
service
(16) Fuel Fuel consumption rate per an operation hour is fuel consumption per an operation hour,
consumption rate per 1 kW. The same type machinery is applied the same rate.
per an operation
hour (ℓ / kW•h)
(17) Fuel The fuel consumption is expressed consuming fuel per an operation hour. It is changed
consumption (ℓ / in proportion as a capacity.
h) (17) = capacity x (16)
E: Electric
G: Gasoline
Unless it is not specified, it is diesel.
Source: JICA Project Team
29
Standard Year standard operation Per/hour Per/day Conversion value Remark
(1)
(2)
(6)
(7)
use
(%)
(%)
(year)
(3)
(4)
(5)
(8)
(9)
Per/hour for operation Per/day for operation
day
(10)
(11)
(16)
(17)
(l/h)
hour
(day)
(day)
(hour)
service
(x10-6)
(x10-6)
Basic price
(l/kW-h)
cost
cost
(12)
(13)
(14)
(15)
(million VND)
(x10-6 )
(x10-6 )
Output Weight
operation hour
(%)
(thousand VND)
(thousand VND)
Rate of rent
Rate of rent
kW(PS) (t)
Classification
Residual ratio
Specification
per an operation hour
(thousand VND)
(thousand VND)
Example
073 [Backhoe with crane - Second standard value]
Standard bucket capacity
Full pile [Flat] Suspensi
3 3
(m ) (m ) on (t)
0.28 [0.2] 1.7 41(56) 7.0 1,306 9.0 730 120 190 45 9.0 14 134 175 725 946 323 422 1,240 8,100 0.175 7.2
0.45 [0.35] 2.9 60(82) 11.8 1,802 9.0 730 120 190 45 9.0 14 134 242 725 1,306 323 582 1,240 11,200 0.175 11.0
0.5 [0.4] 2.9 64(87) 12.1 2,080 9.0 730 120 190 45 9.0 14 134 278 725 1,508 323 672 1,240 12,900 0.175 11.0
0.8 [0.6] 2.9 104(141) 19.8 3,000 9.0 730 120 190 45 9.0 14 134 402 725 2,180 323 970 1,240 18,600 0.175 18.0
074 [Backhoe with crane - Third standard value]
Standard bucket capacity
Full pile [Flat pile] Suspensi
3 3
(m ) (m ) on (t)
0.8 [0.6] 2.9 104(141) 19.8 3,220 9.0 730 120 190 45 9.0 14 134 432 725 2,340 323 1,040 1,240 20,000 0.175 18.0
30
083 [Backhoe with crane - Ultra-low noise type - Second standard value]
Standard bucket capacity
Full pile [Flat pile] Suspensi
3 3
(m ) (m ) on (t)
0.8 [0.6] 2.9 110(150) 19.4 3,040 9.0 730 120 190 45 9.0 14 134 408 725 2,200 323 982 1,240 18,800 0.175 19.0
084 [Backhoe with crane - Ultra-low noise type - Third standard value]
Standard bucket capacity
Full pile [Flat pile] Suspensi
3 3
(m ) (m ) on (t)
0.8 [0.6] 2.9 117(159) 19.9 3,640 9.0 730 120 190 45 9.0 14 134 408 725 2,640 323 1,176 1,240 22,600 0.175 20.0
092 [Backhoe with crane - Rear ultra small revolving type - Second standard value]
Standard bucket capacity
Full pile [Flat pile] Suspensi
3 3
(m ) (m ) on (t)
0.28 [0.2] 1.7 41(56) 7.0 1,568 9.0 730 120 190 45 9.0 14 134 210 725 1,136 323 506 1,240 9,720 0.175 7.2
0.45 [0.35] 2.9 60(82) 11.8 2,020 9.0 730 120 190 45 9.0 14 134 270 725 1,464 323 652 1,240 12,500 0.175 11.0
0.5 [0.4] 2.9 64(87) 12.1 2,180 9.0 730 120 190 45 9.0 14 134 292 725 1,580 323 704 1,240 13,500 0.175 11.0
0.8 [0.6] 2.9 104(141) 19.8 2,920 9.0 730 120 190 45 9.0 14 134 392 725 2,120 323 944 1,240 18,100 0.175 18.0
Common A26 Backhoe 0.8m3 per operation day for Foundation excavating work
Machinery Ownership Cost correction (C13) = (C9) x coefficient + (C11) / t, t = 730 h / 190 day = 3.8 h [operation time per days of
service]
Common A27 Backhoe 0.8m3 per operation day for Foundation or Backfilling of crushed stone
Operator 0.58 3,460,000 2,006,800 From book of materials and labor unit
Person
(Special) 0.90 3,460,000 3,114,000 price
41 21,900 897,900
Fuel Cost Diesel L Ditto
65 21,900 1,423,500
Machinery 0.79 3,500,000 2,765,000
Days of
Ownership Backhoe 0.8m3
service 1.00 3,500,000 3,500,000
Cost
Miscellaneous 300
L.S. 1 Treatment of fractions
Expense 2500
31
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Common A26 Backhoe 0.8m3 per operation day for Foundation excavating work
Machinery Ownership Cost correction (C13) = (C9) x coefficient + (C11) / t, t = 730 h / 190 day = 3.8 h [operation time per days of
service]
Common A27 Backhoe 0.8m3 per operation day for Foundation or Backfilling of crushed stone
Operator 0.58 3,460,000 2,006,800 From book of materials and labor unit
Person
(Special) 0.90 3,460,000 3,114,000 price
41 21,900 897,900
Fuel Cost Diesel L Ditto
65 21,900 1,423,500
Machinery 0.79 3,500,000 2,765,000
Days of
Ownership Backhoe 0.8m3
service 1.00 3,500,000 3,500,000
Cost
Miscellaneous 300
L.S. 1 Treatment of fractions
Expense 2500
According to the above example, the unit price shall be different even the same machinery in case
different work item.
32
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Fuel consumption
= Capacity (kW) x Fuel consumption rate (ℓ/kW•h)
per hour
Source: JICA Project Team
Figure 4.15 Formula of Fuel Cost
33
Guideline on the Cost Estimation for Construction Packages in Viet Nam
5.1 Introduction
The contents of Item 5.4 to 5.7 in this chapter are mainly taken from the cost estimation guideline
of Ministry of Land, Infrastructure and Transport (MLIT) in Japan published in 2011 and 5.8 is
taken from Cost Estimation Guideline of MLIT in Architecture and Building Department
published in 2015. After the review and comparison of the current system of Viet Nam and the
above guideline, some points to be improved have been found.
With review of current cost estimation method in Viet Nam, it turned out that there exist a lot of
independent norm tables and cost estimators have to select most suitable one based on their
experiences and judgements. Therefore, current Vietnamese method has problem that unified
norm cannot be always used at same kind of construction work and it varies with decision of cost
estimator concerned.
In comparison with this, the significant feature of Japanese cost estimation system is that the cost
estimation task is systematically computerized in accordance with the cost estimation guideline.
In this method, the most suitable selection of various parameters for estimation can be done
automatically with consideration of construction conditions at the site. Because the construction
conditions such as construction volume, construction areas, height of construction and so forth.
are clearly described in the guideline, the most suitable norm table can be easily selected and
followed in task process of cost estimation. Therefore, Japanese method is significantly
recommended for improvement of current method of Viet Nam in this guideline.
In addition, the other reasons why Japanese practice should be adopted for improvement are as
follows,
1) Japan's estimation system has a very long history and has high maturity compared to other
countries.
2) Japan is located near the ASEAN nations and business practice, culture, ideas and so forth.
are similar of Japan.
3) Frequent renewal has been implemented based on the actual surveys of material prices, labor
prices and so forth. and their productivities for long years; as a result, real state of
construction cost expenditures is reflected in estimation tasks.
4) Reference of Japan’s practice seems to be very internationally appropriate and suitable to
Viet Nam, which is developing drastically now to the level of advanced countries.
In this section, the productivity (norm) of “earth work”, “concrete work” and “road pavement
work” are described. The reason of the selections for the above construction works is that those
are major and basic construction works among all construction works.
In addition, the temporary work and building work as concrete block work, plastering work and
tiling work have been added for reference.
34
Guideline on the Cost Estimation for Construction Packages in Viet Nam
35
Guideline on the Cost Estimation for Construction Packages in Viet Nam
2) Issues Identified
As a result, following issues are pointed in current practice.
a) Some norms are inapplicable to present techniques and site conditions.
b) Since the grades of labors are theoretical, productivity rate of labors for each work item in
construction estimation norms does not reflect the actual workings.
c) The wages of labors are calculated with the grading which is mentioned in Chapter 4. Even
there are many different occupation of labors at construction site, the occupation of labors are
not taken into consideration in the each productivity of labors.
d) The productivity rate of labor is only determined according to one construction condition and
one labor productivity, and different working conditions are not taken into consideration.
e) The productivity rate of machinery shift is calculated as an average distribution per each work
without consideration of the execution organization plan and the actual construction
condition.
(1) Component
The structure of all kinds of earth work is shown in Figure 5.2. This section indicates the
excavations by a bulldozer and backhoe in the soil, earth and so forth.
36
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Rocks
The bulking and shrinkage factor of soil, earth and so forth. based on soil classification is shown
in Figure 5.3. the calculation of excavation and embankment is used these factors for the
distribution plan of soil volume.
37
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Clay of low
Gravelly soil Sand & Sandy soil Soft rock Hard rock
plasticity
Clay of Rock /
Main
low Cobble
division Clay of
gravelly Sandy plasticity stone Soft rock Soft rock Medium Hard
Gravel Sand low
Name of soil soil of high I II hard rock rock I
Classification plasticity moisture
content
(GW) (GM) (SW)(SP) (SM) (ML) (MH)
(GP) (GC) (Spu) (SC) (CL) (CH)
Mark (GPs) (GO) (S-M) (SV) (OL)
(G-M) (S-C)
(G-C) (S-V)
L 1.20 1.20 1.20 1.20 1.30 1.25 1.20 1.30 1.50 1.60 1.65
Factor
C 0.95 0.90 0.95 0.90 0.90 0.90 1.00 1.15 1.20 1.25 1.40
GW: Gravel of good gain size GM: Silty gravel MH: Silt (high liquid limited) SW, SP: Sand of good/poor gain size
GP: Gravel of poor gain size GC: Clayish silt ML: Silt (low liquid limited) CL: Clay of low plasticity
GPs: Poor gain size GO: Organic gravel S-M: Sand with silt OL: Organic clay of low plasticity
(step)
G-M: Gravel with silt CH: Clay S-C: Sand with clay Spu: Sand of poor gain size ( uniformity)
G-C: Gravel with clay S-V: volcanic sand soil
Source: Cost Estimation Guideline of MLIT published in 2011
Figure 5.18 Bulking and Shrinkage Factor of Soil Based on Soil Classification
1) Flow of Construction
The working surround with the dotted line is not included in this item.
Loading
Excavation Transportation
material
Excavation for
Backfilling
foundation
To bring in To bring out
machinery machinery
Rock Loading
Transportation
excavation material
Excavation and
Transportation
loading
38
Guideline on the Cost Estimation for Construction Packages in Viet Nam
2) Construction Form
In case of excavation work, there are three construction forms divided “wide type cutting”,
“narrow type cutting” and “mixed type cutting”. The machineries are selected based on the
construction form because of taking into consideration of construction condition. The
construction form and selection of machinery type are shown as follows. In case of the
excavation for foundation, the different productivity shall be applied.
Wide type cutting Mixed type cutting Narrow type cutting
39
Guideline on the Cost Estimation for Construction Packages in Viet Nam
40
Guideline on the Cost Estimation for Construction Packages in Viet Nam
as surrounding structures, traffic condition and so forth., and in case continuous excavation is not possible.
2. The obstacle for loading of loosened is that there are limitations of construction condition such as surrounding structures,
traffic condition and so forth. and/or strutting and waling.
Source: Cost Estimation Guideline of MLIT published in 2011
a) Selection of machinery
The selection of backhoe based on the construction condition is shown in Table 5.11.
Table 5.18 Selection of Backhoe
Type of works Construction condition Specification
Average width > 2m Backhoe 0.8m3
Excavation for foundation Average width < 2m Backhoe 0.45m3
Average width < 1m Backhoe 0.28m3 or 0.13m3
Source: Cost Estimation Guideline of MLIT published in 2011
41
Guideline on the Cost Estimation for Construction Packages in Viet Nam
4) Transportation
The productivity rate of 10t dump truck per 100 m 3 with two types of backhoe is shown in Figure
5.6.
(Per 100m3)
3
Specification of Machinery for Loading Backhoe 0.8m
Specification of Machinery for Transportation 10t Dump Truck
Less Less Less Less Less Less Less Less Less Less Less Less Less Less Less Less
Transportation
than than than than than than than than than than than than than than than than
Distance(km)
0.3 0.5 1.0 1.5 2.0 3.0 4.0 5.5 6.5 7.5 9.5 11.5 15.5 22.5 49.5 60.0
Number of days to
0.65 0.75 0.85 0.95 1.1 1.3 1.5 1.8 2.1 2.4 2.7 3.1 3.8 4.7 6.3 9.4
Transport
3
Specification of Machinery for Loading Backhoe 1.4m
Specification of Machinery for Transportation 10t Dump Truck
Less Less Less Less Less Less Less Less Less Less Less Less Less Less Less Less Less Less
Transportation
than than than than than than than than than than than than than than than than than than
Distance(km)
0.3 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.5 6.0 7.0 8.5 10.0 12.5 16.5 23.5 51.5 60.0
Number of days to
0.5 0.6 0.7 0.8 0.9 1 1.2 1.3 1.5 1.8 2.1 2.4 2.7 3.1 3.8 4.7 6.3 9.4
Transport
Source: Cost Estimation Guideline of MLIT published in 2011
Figure 5.21 Number of Day to Transport per 100 m3 by 10t Dump Truck
In case of Japan, the transportation condition in Densely Inhabited District (DID) section is
considered to determine the productivity rate. In case the transportation vehicle go through DID
section, the productivity rate shall be increased.
42
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The construction volume per day is able to be changed depending on the construction condition
such as soil classification, soil condition and so forth.
43
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The structures such as retaining wall, pipe and box culvert, abutment and pier of bridge and so
forth are not applicable in this concrete work. The productivity rate of above concrete works
should be prepared separately because of different construction condition.
Preparation
Concrete Compaction Surface
of concrete Curing
placing of concrete finishing
placing
Source: JICA Project Team
Figure 5.22 Construction Flow
H : Concrete placing height above the ground L : Concrete placing horizontal distance
Source: JICA Project Team
Figure 5.23 Selection of Concrete Placing Method
44
Guideline on the Cost Estimation for Construction Packages in Viet Nam
3) Wastage Factor
The necessary quantity is calculated based on the following equation.
[Necessary quantity] = [Quantity by design] x [1 + Wastage factor]
The wastage factor should be differed depending on structure type.
Table 5.22 Wastage Factor of General Concrete Structure
Material Structure Wastage Factor
Ready mixed concrete Plain concrete structure +0.04
Reinforced concrete structure +0.02
Minor structure +0.06
Source: Cost Estimation Guideline of MLIT published in 2011
b) Productivity rate of concrete placing by concrete pump vehicle in the major structure
The productivity rate of concrete placing by concrete pump vehicle in the major structure is
shown in Table 5.17. Depending on the construction volume, the productivity rate shall be
changed.
Table 5.24 Productivity Rate of Concrete Placing by Concrete Pump Vehicle in the Major
Structure
(Per 10 m3)
Design placing concrete volume
10 m3 to 300 m3 300 m3 to 600 m3
Description Unit
Standard placing volume per day
81 400
Foreman person 0.14 0.04
Special worker person 0.40 0.20
Ordinary worker person 0.54 0.22
Concrete pump vehicle Day 0.19 0.05
Miscellaneous cost rate % 1 1
1. This productivity rate is included the tip operation of concrete feed pipe.
2. In case the working range is more than 30 m from a concrete pump vehicle, the machinery ownership cost of concrete
feed pipe is added.
3. The miscellaneous cost includes the depreciations of vibrator and fuel and /or electricity. The miscellaneous cost is
calculated that the miscellaneous cost rate multiplied by the sum of labor cost and concrete pump vehicle cost.
Source: Cost Estimation Guideline of MLIT published in 2011
45
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Table 5.25 Productivity Rate of Assembly and Disassembly of Concrete Feed Pipe
(Per 10 m)
Description Unit Assembly Disassembly
Ordinary worker person 0.26 0.20
Source: Cost Estimation Guideline of MLIT published in 2011
46
Guideline on the Cost Estimation for Construction Packages in Viet Nam
5) Curing
a) Productivity rate of curing
The productivity rate of curing work is shown in Table 5.23.
Table 5.30 Productivity Rate of Curing
(Per 10 m3)
Major Structure Minor structure
Description Unit
Plain Concrete Reinforced Concrete
Ordinary worker Person 0.30 0.16 0.69
Miscellaneous cost rate % 17 33 19
1. The miscellaneous cost includes the curing sheet, curing mat, timber, pipe, depreciations of machinery of shrinking water,
and fuel and / or electricity. The miscellaneous cost is calculated that the miscellaneous cost rate multiplied by the sum of
labor cost.
Source: Cost Estimation Guideline of MLIT published in 2011
47
Guideline on the Cost Estimation for Construction Packages in Viet Nam
b) The price schedule of assembly and disassembly of concrete feed pipe (L>30 m) per 10m
Description Specification Unit Quantity Remark
Ordinary worker Person 0.46 x L / B Refer to Table 5.18
Miscellaneous cost L.S. 1
Total
1. “L” means that the length of concrete feed pipe which is exceeding more than 30 m from the working range of concrete
pump vehicle.
2. “B” means that the standard placing volume per day in Table 5.17.
c) The price schedule of concrete placing by man-power in the major structure per 10m 3
Description Specification Unit Quantity Remark
Foreman Person Refer to Table 5.19
Special worker Ditto Ditto
Ordinary worker Ditto Ditto
Concrete m3
Curing L.S. 1 Refer to Table 5.23
Miscellaneous cost L.S. 1 Refer to Table 5.19
Total
d) The price schedule of concrete placing by crane in the minor structure per 10m3
Description Specification Unit Quantity Remark
Foreman Person Refer to Table 5.21
Special worker Ditto Ditto
Ordinary worker Ditto Ditto
Concrete m3
Truck crane or crawler crane Day Refer to Table 5.21
Curing L.S. 1 Refer to Table 5.23
Miscellaneous cost L.S. 1 Refer to Table 5.21
Total
e) The price schedule of concrete placing by man-power in the minor structure per 10m3
Description Specification Unit Quantity Remark
Foreman Person Refer to Table 5.22
Special worker Ditto Ditto
Ordinary worker Ditto Ditto
Concrete m3
Curing L.S. 1 Refer to Table 5.23
Miscellaneous cost L.S. 1 Refer to Table 5.22
Total
48
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Processing Assembly
To bring in and and Concrete Disassembly To bring out
materials manufacturing installation placing and removal materials
of form of form
49
Guideline on the Cost Estimation for Construction Packages in Viet Nam
50
Guideline on the Cost Estimation for Construction Packages in Viet Nam
(1) Component
The structure of the main component of road pavement work is shown in Figure 5.10. This
guideline indicates the sub-base and base course work and asphalt concrete pavement work.
51
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The construction flow of sub-base and base course work is shown in Figure 5.11. The
unevenness correction work after sub-base course is added if necessary.
To bring in Unevenness correction To bring out
Sub-base course work Base course work
materials work materials
52
Guideline on the Cost Estimation for Construction Packages in Viet Nam
this rate is not applied for unevenness correction work. The contents of miscellaneous cost are the
water sprinkler by vehicle and necessary cost of auxiliary machinery for narrow width.
Table 5.36 Miscellaneous Cost Rate
Working Item Construction width Unit miscellaneous cost rate
More than 3 m % 9
Sub-base and base course work
Less than 3 m % 3
Source: JICA Project Team
5) Wastage Factor
The necessary quantity for sub-base course and base course is calculated based on the following
equation.
[Necessary quantity (m3)] = [Quantity by design (m3)] x [1 + Wastage factor(K)]
K: Wastage factor +0.27 is applied.
b) The price schedule of unevenness correction work and sub-base course and base course work
(construction width < 3.0 m ) per 100m2
Description Specification Unit Quantity Remark
Special worker Person Refer to Table 5.28
Ordinary worker Ditto Ditto
Material of sub-base course or base course m3
Vibrator roller 3~4t Day 100 / D Refer to Table 5.27
Backhoe 0.11 m3 Ditto 100 / D Ditto
Miscellaneous cost L.S. 1 Refer to Table 5.29
Total
D: Construction volume per day
Source: Cost Estimation Guideline of MLIT published in 2011
53
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Cleaning of
surface
Distribution of
Installation of asphalt mixture Removal of
and bituminous Leveling Compaction
form form
material
Distribution
of sand
Each layer
Source: JICA Project Team
Figure 5.28 Construction Flow of Asphalt Concrete Pavement Work
3) Wastage Factor
a) Asphalt mixture
The necessary quantity is calculated based on the following equation.
[Necessary quantity] = [Quantity by design (m 2)] x [finishing thickness (mm)] x [Density
after compaction (t/m3)] x [1 + Wastage factor(K)]
K: Wastage factor +0.07 is applied.
Table 5.37 Density After Compaction (t/m3)
Description Density after compaction (t/m3)
Coarse / Dense graded asphalt concrete 2.35
Fine graded asphalt concrete 2.30
Open graded asphalt concrete 1.94
Bituminous stabilization base course 2.35
Source: Cost Estimation Guideline of MLIT published in 2011
b) Bituminous material
The quantity of bituminous material is shown in Table 5.31.
Table 5.38 Quantity of Bituminous Material
(Per 100 m2)
Description Unit Quantity
Tack coat ℓ 43
Prime coat Ditto 126
Source: Cost Estimation Guideline of MLIT published in 2011
4) Selection Flow
The selection of construction method for asphalt concrete pavement work is shown in Figure
5.14. The selection mechanism is effective and useful to make a cost estimation systematically.
For this work, the productivity rate is varied by the construction width.
54
Guideline on the Cost Estimation for Construction Packages in Viet Nam
55
Guideline on the Cost Estimation for Construction Packages in Viet Nam
56
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Table 5.44 Productivity Rate of Labor Cost for Asphalt Concrete Pavement Work by Man-
power
(Per day ·1 layer)
Working Item Description Unit t ≦ 50 50 < t ≦ 70
Asphalt concrete pavement work Foreman Person 1 1
by man-power Special worker Ditto 2 3
Ordinary worker Ditto 4 4
Source: Cost Estimation Guideline of MLIT published in 2011
57
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The selection of construction method for scaffolding work is shown in Figure 5.16. The selection
mechanism is effective and useful to make a cost estimation systematically.
Start
Slope of
structure surface No
(1:n) n<0.1
Yes
Grounding surface No
is flat
Yes
Pipe scaffold
Prefabricated scaffold Pipe scaffold
along an inclined slope
Source: JICA Project Team
Figure 5.31 Selection of Construction Method
58
Guideline on the Cost Estimation for Construction Packages in Viet Nam
materials cost are described in the productivity rate. The small items such as joint goods are able
to be included in miscellaneous cost.
Table 5.46 Productivity Rate of Scaffolding Work
(Per 100 m2)
Prefabricated Pipe scaffold
Description Unit Pipe scaffold
scaffold along an inclined slope
Foreman Person 1.4 1.7 1.4
Scaffold erector Ditto 5.8 (7.2) 5.8 (7.2) 3.8 (5.2)
Ordinary worker Ditto 1.4 1.9 2.9
Rafter truck crane Day 1.2 0.7 0.7
Miscellaneous cost rate % 36 23 24
1. If the safety net is necessary, the productivity rate in parenthesis shall be applied.
Source: Cost Estimation Guideline of MLIT published in 2011
2) Construction Flow
The construction flow of concrete block work is shown in Figure 5.17.
59
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Processing and
To bring in Concrete block To bring out
assembly of Filling of mortar
materials building materials
reinforced bar
Source: JICA Project Team
A dotted line is not included in this productivity rate.
Figure 5.32 Construction Flow
Table 5.49 Productivity Rate of Concrete Block Work for Building of Exterior Curtain Walls
(Per 1 m2)
Description Unit t=100 mm t=120 mm t=150 mm t=190 mm
Blocks pcs 13 13 13 13
Cement kg 13.1 16.6 24.2 35.3
Sand m3 0.03 0.03 0.05 0.07
Reinforced bar D10 kg 1.6 1.6 1.6 1.6
Reinforced bar D13 kg 4.0 4.0 4.0 4.0
Building block worker Person 0.12 0.13 0.14 0.16
Ordinary worker Ditto 0.06 0.07 0.08 0.11
Miscellaneous cost rate % (Material cost + labor cost) x 10~15%
Source: Cost Estimation Guideline of MLIT in Architecture and Building Department published in 2015
60
Guideline on the Cost Estimation for Construction Packages in Viet Nam
b) The price schedule of concrete block work for building of exterior curtain walls per 100 m 2
Description Specification Unit Quantity Remark
Blocks pcs Refer to Table 5.42
Cement kg Ditto
Sand m3 Ditto
Reinforced bar D10 kg Ditto
Reinforced bar D13 kg Ditto
Building block worker Person Ditto
Ordinary worker Ditto Ditto
Miscellaneous cost L.S Ditto
Total
Source: JICA Project Team
2) Construction Flow
The construction flow of plastering work is shown in Figure 5.18.
61
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The productivity rate of plastering work for floor in Japanese practice is shown in Table 5.47.
Table 5.54 Productivity Rate of Plastering Work for Floor
(Per 1 m2)
Base for
floor Mortar Base for Base for Base for
Description Unit
material of finishing mosaic tile general tile waterproof
vinyl
Cement kg 13.9 16.9 11.0 18.4 9.0
Fine aggregate (sand) m3 0.035 0.035 0.027 0.046 0.022
Plasterer Person 0.045 0.045 0.04 0.05 0.04
Ordinary worker Ditto 0.034 0.036 0.026 0.044 0.022
Miscellaneous cost rate % (Material cost + labor cost) x 13~18%
Source: Cost Estimation Guideline of MLIT in Architecture and Building Department published in 2015
62
Guideline on the Cost Estimation for Construction Packages in Viet Nam
2) Construction Flow
The construction flow of tiling work is shown in Figure 5.19.
63
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Table 5.58 Productivity Rate of Tiling Work for Exterior and Interior Walls
(Per 1 m2)
Exterior Interior
Description Unit (Improved piling sticking) (Improved piling sticking)
t=100 mm t=100 mm
Exterior tile pcs 102 102
Cement kg 5.8 5.8
Fine aggregate (Sand) m3 0.019 0.019
Tiler Person 0.25 0.25
Ordinary worker Ditto 0.08 0.08
Miscellaneous cost rate % (Material cost + labor cost) x 10~15%
Source: Cost Estimation Guideline of MLIT in Architecture and Building Department published in 2015
64
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Total
Source: JICA Project Team
65
Guideline on the Cost Estimation for Construction Packages in Viet Nam
6.1 Definition
Indirect Cost is not the cost of construction objects targeted like Direct Cost, but the necessary/
supporting cost for completing the objects indirectly. Therefore, what is the targets payed as
Indirect Cost basically does not remain on the site in the final stage of the project. This cost is
calculated based on the Direct Cost with some rates and paid by set.
6.2 Structure
Indirect Cost can be divided into two categories; which are Common Indirect Cost and Site
Management Cost as shown in Figure 6.1.
66
Guideline on the Cost Estimation for Construction Packages in Viet Nam
67
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The details of each item are shown in Appendix 5 and 6. Those items are basically combined with
the cost by rate and estimated together as Indirect Cost with the Site Management Cost described
below. The difference between Common Indirect Cost estimated by rate and that of estimated by
piling up is as follows. The former includes costs of items that are basically necessary besides
Direct Cost items in standard construction works and the latter includes Indirect Cost items that
are especially necessary as features of the concerned construction projects.
68
Guideline on the Cost Estimation for Construction Packages in Viet Nam
69
Guideline on the Cost Estimation for Construction Packages in Viet Nam
70
Guideline on the Cost Estimation for Construction Packages in Viet Nam
71
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Type of Works
In case of VN Norm
Comparison
Type of Works
Road Works Bridge Works
Item
Max of Min of Max of Min of
Rate Rate Rate Rate
In case of VN Norm
(1) General Cost 5.5% 4.2% 5.5% 4.2%
(2) Advance Calculated Taxable Income 6% 6% 6% 6%
Cost of temporary office &houses on site for dwelling and
(3) 2% 2% 1% 1%
construction management under General Item
Cost of some works undeterminable in the design under General
(4) 2% 2% 2% 2%
Item
Rate of Indirect Cost in construction cost in VN (to Direct cost)
(5) 16.30% 14.87% 15.18% 13.77%
(5) = [1+ (1)]*[1+(2)]*[1+(3)+(4)] - 1
Rate of Indirect Cost in construction cost in VN (to Direct cost)
excluding the Enterprise's management Cost (to be assumed
(6) 15.20% 14.03% 14.08% 12.93%
accounting for 20% of General cost)
(6) = (5) - (1)*20%
In case of Japan Norm
(7) Common Indirect Cost 26.94% 4.37% 27.04% 7.05%
(8) Site Management Cost 25.89% 22.58% 27.79% 19.33%
Rate of Indirect Cost in construction cost in Japan (to Direct cost)
(9) 59.80% 27.94% 62.34% 27.74%
(9) = [1+ (7)]*[1+(8)] - 1
Comparison
72
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Source; Viet Nam : Circular No. 06/2016/TT-BXD Japan : Cost estimation Manual (MLIT)
From the comparison of the rates between Viet Nam and Japan in Indirect Cost, the big
differences are found from the results in Table 6.4. The rate of Japan is 4.43 times higher at
maximum and 1.99 times at minimum than Viet Nam. In average, it is 3.13 times higher in Japan.
Focused on each item, all rates are higher in Japan and especially, average of Site Management
Cost is 23.9 % and the highest of all rates. This rate is much bigger compared to 5.5%, which will
be almost equal to Site Management Cost in Viet Nam, Therefore, the rate of Site Management
Cost is supposed to mostly cause the difference of Indirect Cost rate in both countries.
Basis of the present values of rate of Japan is from statistical processing from huge data gained
from the surveys for long years. That is why each content rate of detail items of Indirect Cost
items is not cleared and not specifically decided. Therefore, it is difficult to compare the rate in
detailed items one by one in Indirect Cost.
The rate difference is supposed to be caused by several reasons such as due to some missing
items including Indirect Cost in Viet Nam, difference of cost of personnel and materials in both
countries and so forth. Among them, because biggest cause is the difference of Site Management
Cost rate, analysis is carried out with focusing on this Site Management Cost.
73
Guideline on the Cost Estimation for Construction Packages in Viet Nam
1) Cost of all necessary tests described in ・ List up of all necessary tests for quality management
Construction Specification (For ・ Decision of number of tests of each test necessary for
Quality Management Plan) quality management
2) Cost for the Quality Management ・ Salary of quality control engineers
Division
Source: JICA Project Team
Herewith, the study figured out the discrepancy of quality management cost in rate
calculation for case study projects and the case applying SPQM to the project. Through the
comparison, discrepancy in ratio of quality management cost belongs to “cost of rate
calculation” of Indirect cost is identified. Based on the gap analysis in the case study, the rate
of additional necessary quality management cost for infrastructural construction project in
Viet Nam (to the direct cost) is proposed as shown in Table 6.6. Those values have to be plus
on current ones.
Table 6.64 Proposed Additional Rate of Quality Management Cost for Indirect Cost
Proposed Rate to Direct Cost Remarks
1) Cost of all necessary tests described in
0. 61% Common Indirect Cost
Construction Specification
2) Cost for the Quality Management
0.61% Site Management Cost
Division
TOTAL 1.22%
Source: JICA Project Team
74
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Herewith, the study figured out the discrepancy of safety management cost in rate calculation
for case study projects and the case applying SPSM to the project. Through the comparison,
discrepancy in ratio of quality management cost belongs to “cost of rate calculation” of
Indirect cost is identified. Based on the gap analysis in the case study, the rate of additional
necessary safety management cost for infrastructure construction project in Viet Nam (to the
direct cost) is proposed as shown in Table 6.8. Those values also have to be plus on current
ones as well as Quality management cost rate.
Table 6.66 Proposed Additional Rate of Safety Management Cost for Indirect Cost
Proposed Rate to Direct Cost Remarks
1) Cost of all necessary items as Common Common Indirect
1.08%
Indirect Cost by rate Cost
2) Cost for the training and education for Site Management
0.19%
workers at site Cost
TOTAL 1.27%
Source: JICA Project Team
75
Guideline on the Cost Estimation for Construction Packages in Viet Nam
As shown in the table, Both Common Indirect Cost and Site Management Cost rates should
be much increased from current figures in present Norm. Common Indirect Cost is increased
by 1.69% and Site Management Cost is 8.55% and much bigger than 4.4% compared to
current Norm case in accordance with analysis results. It is recognized that personnel cost at
the site, which has the biggest share in site cost, is much more necessary than current case
from those analyses. Those rates are strongly recommended with this study’s results.
76
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Chapter 7 Overhead
7.1 Definition
Overhead is the cost necessary to continue operation of the company in charge of construction
project and is referred to as head and branch offices expenses and profit. Therefore, it includes
actual expenses of head and branch offices and profit of the company; herewith Overhead is
divided into two big categories such as Head and branch offices expenses and Profit.
7.2 Component
(1) Head and Branch Offices Expenses
Head and branch offices expenses are composed of the following 21 components.
Table 7.68 Component of Head and Branch Offices Expenses
Component
a) Executive salaries
b) Employee salaries
c) Severance pay
d) Legal welfare expenses
e) Welfare expenses
f) Maintenance expenses of offices and facilities
g) Office supplies costs
h) Communication transportation expenses
i) Power, water utility costs
j) Research and Development expenses (R&D)
k) Advertising expenses
l) Social expenses
m) Donation
n) Rent expenses of land, office and accommodation
o) Depreciation and amortization
p) Experimental research expenses amortization
q) Development costs amortization
r) Taxes and dues, fees ,charges as per regulation
s) Casualty insurance
t) Contract guaranty costs
u) Miscellaneous expenses
Source: Cost Estimation Guideline of MLIT published in 2011
(2) Profit
Profit includes the following components. The extra money will be accumulated as Retained
earnings and prepared for new businesses.
Table 7.69 Component of Profit
Component
a) Various taxes (Corporate tax, Prefectural tax and so forth.)
b) Shareholder dividend
c) Bonuses for executives
d) Retained earnings
e) Others
Source: Cost Estimation Guideline of MLIT published in 2011
77
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Table 7.4 shows the overhead rate of some major Vietnamese contractors. Those figures are from
financial statement of those companies.
Table 7.71 Major Construction Company’s Overhead Rate in Viet Nam
Thăng Long–
Company Cienco4–JSC. Cienco1–JSC. Cienco6–JSC.
JSC.
Sales
(Bill. VND) 4,149 5,822 1,458 1,669
Overhead
(%) 7.3% 6.2% 7.0% 10.9%
(2014)
Source: JICA Project Team
From those actual facts, it is recognized that Overhead rates in Viet Nam distribute between low
one 6.2% to high one 10.9%. Average rate is 7.8%. Further appropriate value shall be determined
by the suggestion in next Chapter.
78
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Based on this formula, Overhead rates of many construction projects in the past are calculated
and average rate is extracted. Then, with regression analysis, appropriate Overhead rate in Viet
Nam is determined with referring rates of other Asian countries.
2) Practice of Japan
In Japan, the formula to decide Overhead rate is defined based on statistical analysis with usage
of the data of construction works for long period. This is just applicable to the projects in Japan;
however, this will be applicable to another country including Viet Nam as the maximum value
level because it is formulated with taking account into high quality and long sustainability of the
targeted objects. The rate calculated with this formula will become one of the target value of
Overhead rate. Therefore, this formula is also recommended in cost estimation methodology in
Viet Nam.
Use this formula based on the following conditions about rate of advanced payment.
a) In case of advance payment rate is less than 35% use the following correction factors.
Advance payment rate 0% ~ 5% 5% ~ 15% 15% ~25% 25% ~35%
Correction coefficient 1.05 1.04 1.03 1.01
79
Guideline on the Cost Estimation for Construction Packages in Viet Nam
80
Guideline on the Cost Estimation for Construction Packages in Viet Nam
81
Guideline on the Cost Estimation for Construction Packages in Viet Nam
a) Survey flow
The survey flow is shown in Figure 8.1.
Preparation
Preparation of survey plan
stage
Implementation
Implementing the survey
stage
Survey result
Collection of survey result
stage
Decision of price
Verification
stage
b) Guideline of survey
There are 3 types of survey method such as interview survey, survey by telephone and survey
by email / fax. The interview survey shall be implemented mainly to survey the unit price of
materials.
This survey grasps transaction conditions in the construction market. However, the
transaction price between a seller and a buyer is not opened to a public normally. Therefore, it
is difficult to grasp current transaction condition by surveying with email or some
communications means only.
(i) Preparation stage
Selection of suppliers
The suppliers which have target materials of relatively large amount of handling and high
reliability are selected. In principle, the suppliers should be selected at least three or more.
Survey stage
There are some distribution channels of materials in the market. The image of distribution
channel is shown in Figure 8.2. The survey stage should be checked on the distribution
channel and mentioned with publishing price such as stage I, II and III based on Figure
8.2. The unit price of material shall be changed depending on the survey stage.
82
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Special shops
II
83
Guideline on the Cost Estimation for Construction Packages in Viet Nam
84
Guideline on the Cost Estimation for Construction Packages in Viet Nam
a) Survey Flow
Before the commencement of the survey, the target project and survey month should be
decided from the public construction works. Depending on the construction works, its
working is not implemented due to the weather condition and so forth. Therefore, the more
appropriate month which is implemented the survey should be considered.
Preparation
Selection of target project
stage
Venue survey
b) Guideline of Survey
This item shows procedure of the actual condition survey for unit labor based on Japanese
system. It shall be adjusted to the Viet Nam condition after the pilot survey.
The venue survey shall be implemented mainly to survey an unit price of labor. The
contractors shall fill in the survey form before the venue survey.
(i) Preparation stage
Selection of the contractors
The target project shall be selected by DOC. The main contractor which has taken the
selected project shall correspond this survey.
Flow of survey request
Every project owner request the survey to main contractors. They shall not request the
survey to sub-contractors directly. Main contractors shall request the survey to sub-
85
Guideline on the Cost Estimation for Construction Packages in Viet Nam
contractors.
Project Owner
Main Contractor
Sub-contractor
86
Guideline on the Cost Estimation for Construction Packages in Viet Nam
87
Guideline on the Cost Estimation for Construction Packages in Viet Nam
a) Survey Flow
88
Guideline on the Cost Estimation for Construction Packages in Viet Nam
The survey flow is shown in Figure 8.5. The implementation of survey includes the survey
by interview, site survey and survey by telephone and by email or fax in written.
Preparation
Preparation of survey plan
stage
Implementation
Implementation of survey
stage
Survey result
Collection of survey result stage
Decision of price
Verification stage
b) Guideline of Survey
Before implementing the actual condition survey for unit price of machineries, it is
recommended that independent organization should be established.
In the next step, information of contractors and suppliers shall be collected and listed up. This
actual condition survey is done first time in Viet Nam and an independent organization should
have a seminar to explain to contractors and supplies to disseminate it.
(i) Preparation stage
Selection of the contractors
The target contractors which are reliable and have good results shall be selected by
independent organization. The criteria of contractor is to retain more than 15 construction
machineries which have been operated during the target survey period.
(ii) Implementation stage
Implementing the survey
The interview survey shall be carried out by independent organization. The form of survey
shall be sent to the selected contractors and shall be filled in by them. After the completion
of filling in form, the interview survey shall be carried out based on the daily working
report.
Summary of Survey Items
In order to fill in these survey items, the daily working report is necessary and important
document. Based on the result of the survey, the standard and appropriate value should be
calculated by analyzing.
For example, the loading of machinery varies depending on material types and combination
with other machinery. The difficulty of construction works, space of the work yard,
weather condition, a degree of new and old of its machinery, quality of operation and
management, ability of operation have an impact on the machinery capacity.
89
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Items Description
Usage condition
1 Summary of holding and usage Capacity, weigh and specification and so forth.
of machinery
2 Purchase record Date, method, price of purchase, division of new or old and accessory
3 Operation record Number of years in use, number of holding, main operation location,
annual operation hour, annual operation day, annual days of service
4 Maintenance and repair record Annual maintenance and repair cost, cumulated maintenance and
repair cost
Management condition
1 Management record Location of machinery, storage facility cost, management cost, utility
cost (water, gas, electricity and so forth., taxes, insurances and
number of holding machinery
Disposition record
1 Summary of disposition of Capacity, weigh and specification and so forth.
machinery
2 Purchase record Date and price of purchase
3 Disposition record Date, method and price of disposition, objective of disposition
4 Maintenance and repair record Annual maintenance and repair cost, cumulated maintenance and
repair cost
Source: JICA Project Team
90
Guideline on the Cost Estimation for Construction Packages in Viet Nam
condition at a site, operation condition and so forth. It is the different from the durable
years.
Operation hour, operation day and days of service
Operation hour, operation day and days of service are surveyed based on the daily working
report which is prepared by contractors. The standard value should be decided based on the
result of survey after analyzation. These data has large variations depending on the total
construction volume in the contract, operation management as well as construction works.
Maintenance and repair cost rate
The maintenance and repair cost rate indicates the proportion of maintenance and repair
cost to the prime cost. This cost does not includes the consumable parts. The maintenance
cost is the cost for prevention of the out of order, periodic inspection to recovery of the
deterioration of performance. This cost is relatively large scale repair.
The repair cost is the cost caused by drive mistakes, an accident during the operating and so
forth. This cost is relatively small scale repair which can be repaired at a site.
Management cost rate
The management cost rate indicates the proportion of annual necessary management cost to
the prime cost. This cost is the necessary management cost to have a machinery. The
management cost includes the insurance, tax and storage cost.
(iv) Decision of price stage
Setting of machinery unit price should be implemented by an independent organization.
After setting its price, the verification and decision of price are carried out by MOC.
c) Survey form
The survey form is shown in Appendix 11.
91
Guideline on the Cost Estimation for Construction Packages in Viet Nam
a) Survey flow
The survey flow is shown Figure 8.6.
Preparation
Preparation of survey plan
stage
Implementation
Implementation of survey
stage
Survey result
Collection of survey result
stage
Decision of
Review conference and opinion collection
productivity rate
stage
Amendment / decision of productivity rate
b) Guideline of survey
The actual condition survey for productivity rate shall be conducted one time per year.
However, all construction work items are not able to be investigated for 1 time. It is
recommended that the plan to carry out the actual condition survey for productivity rate
should be prepared.
(i) Preparation stage
Selection of the contractor
The target project shall be selected by an independent organization. The main contractor
which has taken the selected project shall correspond this survey. the criteria of the project
shall be selected a project which includes the target construction work to obtain the said
productivity rate.
(ii) Implementation stage
Implementing the survey
There are two surveys for productivity rate. The survey form shall be sent to the selected
contractors by independent organization. Additionally, the site visit survey shall be
implemented in order to confirm whether the site condition reflects to the entry contents in
the survey form.
(iii) Survey result stage
92
Guideline on the Cost Estimation for Construction Packages in Viet Nam
93
Guideline on the Cost Estimation for Construction Packages in Viet Nam
94
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Item Description
9 Wear parts name If the wear parts are replaced, its name and quantity are filled
10 Wear parts quantity in.
Source: JICA Project Team
95
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Table 8.87 Recommended Indirect Cost Rate of Construction Project in Viet Nam
In case of current VN Norm Recommended
Description Norm Remark Description Rate Remark
General Cost 5.5% Max value General Cost 5.5%+β
Advance Calculated 6.0% Advance 6.0%+γ
Taxable Income Calculated
Taxable Income
Cost of temporary 1.0 or 2.0% 1.0% for projects Cost of temporary 1.0 or 2.0% 1.0% for
office & houses on besides road office & houses projects besides
site for dwelling and 2.0% for road on site for road 2.0% for
construction project dwelling and road project
management under construction
General Item management
under General
Item
Cost of some works 2.0% Cost of some 2.0%+α Cost of some
undeterminable in the works works
design under General undeterminable in undeterminable
Item the design under in the design
General Item under General
Item
Overhead 7.43% Overhead 7.43% Overhead
Total {(1+0.055) x Total 15.21% Total
(1+0.06) x (16.30%) +δ
15.18% (1+0.01(0.02)+0.
(16.30%) 02)-1} x 100% =
15.18%
(16.30%)
Common 3. 69%+1% From Table 6.9
Indirect Cost (2%)=4.69%
(5.69%)
Site Management 8.55% From Table 6.9
Cost
Overhead 7.43% Same value as
Norm
Total 20.67% 4.69% (5.69%)
(21.67%) +8.55%+
7.43 % =
20.67%
(21.67%)
Source: JICA Project Team
The rates recommended here are derived from the analysis based on a few case study projects. As
a result, total rate 21.67% is recommended for road project and 20.67% for other projects. More
reasonable values should be determined from studies and analysis on much more number of
projects implemented so far in Viet Nam. The more number of projects, the better results
extracted. Those studies and analysis must be done thereafter by Vietnamese staffs concerned.
These decision methods of appropriate rates are described in next section, which have been
practiced in Japan and should be significantly recommended in Viet Nam as well for
improvement of cost estimation system.
96
Guideline on the Cost Estimation for Construction Packages in Viet Nam
97
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Report of
results of
Procuring Entities analysis
(Ministry) Targeted
Projects
decided are
reported
Extraction Report of
request of Targeted Data
Targeted Projects Projects Delivery of accumulation
and approval extracted Survey Form and analysis
(for Owner &
Contractor)
Procuring Entities Survey
(PPC etc.) Agency
Submission
of Survey Form
Delivery of Submission (for Owner &
Survey Form of Survey Form Contractor)
(for Owner & (for Owner &
Contractor) Contractor)
Question
inquiry&
Delivery of Submission hearing if
Survey Form of Survey Form necessary
(for Contractor) (for Contractor)
Prime Contractor
Delivery of Submission of
Survey Form Survey Form
(for Sub (for Sub
contractor) contractor)
Sub-Contractor
98
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Procedures Month 1 2 3 4 5 6 7 8 9 10 11 12
1) Extraction request of Target Projects
2) Report of Target Projects decided
3) Targeted Projects reported to Agency
4) Making Survey form
5) Delivery of form to Procuring Entities (PPC)
6) Delivery of form to PMU
7) Delivery of form to Contractors
8) Filling out in form by contractors
9) Submission of form to PMU
10) Submissin of form to Procuring Entities
11) Submission of form to Agency
12) Analysis at Agency
13) Report of results of analysis to MO C
14) Decision of new Rates
15) Amendment of estimation system
16) New Circular promulgation
99
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Procedures Month 1 2 3 4 5 6 7 8 9 10 11 12
1) Extraction request of Target Projects
2 ) Report of Target Projects de cid ed
3 ) Targeted Projects reporte d t o A gen cy
4) Making Survey form
5 ) Delivery of form to PE (P PC)
6 ) Delivery of form to PMU
7 ) Delivery of form to Contr act ors
8 ) Filling out in form by co ntr act ors
9) Submission of form to PMU
10) Submissin of form to PE
1 1) Submission of form to Ag enc y
12) Analysis at Agency
13) Report of results of analysis to MOC
1 4) Decision of new Rates
1 5) Amendment of estimation sys tem
1 6) New Circular promulgatio n
3) Analysis
It is required that more than 30 targeted projects in every field are necessary for highly accurate
analysis. Regression analysis is used as an analysis method for rate determination of Common
Indirect Cost, Site management Cost, and
Overhead. Figure 8.9 is an example of
regression analysis. From plot of data on
X-Y coordinate axis, linear regression
formula is found as follows.
log (Y) = α × log (X) + β
Y: Amount of money (Common
Indirect, Site management,
Overhead)
X: Amount of money of whole Project
Thus, Rate is calculated by Y/X.
With this analysis, rates reflecting actual
state of construction works can be decided.
Afterwards, evaluation analysis shall be
implemented by taking into account of
rates of international standard level, then
appropriate and suitable rates for Viet Nam Figure . Regression Analysis
are suggested to the Survey Committee
(described later) to be authorized.
100
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Organization called “Survey Agency” shall be established under the control of MOC as an
auxiliary organization. Beginning from preparation office in MOC, it shall gradually become
substantive organization as real agency.
2) The functions of the Agency
Functions of this agency shall be as follows.
Making Survey forms and print
Delivering forms to Procuring Entities to reach the bodies to be surveyed
Collecting forms filled out from the bodies to be surveyed
The data collected shall be appropriately analysed
The results of survey and analysis shall be reported to MOC
3) Management method
Survey Committee
Survey Committee shall be organized in MOC. The purpose of this Committee is to authorize all
values and prices and so forth., resulted from analysis based on collected data in order to regulate
them for new Circular with discussion of members concerned from all relevant sectors and
provinces. Committee member will be composed of Chairman: Vice Minister of MOC, Deputy-
Chairman: DG of SACE, and other members concerned from the ministries and sectors
possessing targeted project such as MOC, MOT and so forth. and/or targeted provinces. The
decision matters with this Survey Committee shall be reflected to regulation smoothly and
disseminated. The Survey Agency shall be as the standing and assisting Agency for the
Committee.
101
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-1
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-2
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-3
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-4
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-5
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-6
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-7
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-8
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-9
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-10
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-11
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Overhead Cost Items In GLCE Overhead Cost Items in Viet Nam Remark
19) Casualty insurance
Fire insurance and other nonlife insurances 1.2.1 Enterprise’s Administration Cost
(11) Insurances
20) Contract guaranty cost
21) Miscellaneous expenses
Cost of database system, external meeting cost
and association activity cost
22) Profit 1.3 Advantage calculated taxable
Income
a) Various taxes (Corporate tax, Prefectural tax
etc.)
b) Shareholder dividend
c) Bonuses for executives
d) Retained earnings
e) Others
A-12
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Machinery Cost
Net Construction Cost
Construction Cost Common Indirect
Overhead Cost
Indirect Cost
Construction Packages Value-added Tax
Site Management Cost
Contigency Cost
Advance calculated
Cost of General Item
taxable Income (Profit)
Construction Packages
Value-added Tax
Contigency Cost
A-13
Guideline on the Cost Estimation for Construction Packages in Viet Nam
1.1.3.Machinery Cost
1.2.1.Enterprise's
Administration Cost
1.Construction Cost
1.2.2.Site Production
Management Cost
1.2.3.Worker-serving
1.2.General Cost
Cost
1.2.5.Enterprise's other
Management Costs
Construction Packages
2.4.Cost for moving labor force within the
construction site
2.Cost of General Item 2.5.Cost for pumping and dredging mud irregularly
Contigency Cost
A-14
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-15
Guideline on the Cost Estimation for Construction Packages in Viet Nam
steep slope
c) Finishing work of mortar-concrete shot and seed spraying
6. Scaffold erector
Workers having considerable degree skills and advanced physical condition about works at high location
and in the air and can subjectively do the following works
a) Assembly and disassembly of scaffoldings and support works
b) Erection of wood bridges
c) Driving and pull out of piles and sheet piles (excluding operation of pile machine)
d) Setting, assembly and disassembly of temporary elevator, pile driver, winch, cableway etc.
e) Setting and winding up of heavy objects such as huge block and large-size covering plate (excluding
operation of crane)
f) Winding up of steel frames (excluding operation of crane)
7. Mason
Workers having considerable degree skills and advanced physical condition about stone processing works
and can subjectively do the following works
a) Processing of stones
b) Rubble work and stone pitching
c) Finishing by chipping on surface of concrete structures
8. Concrete block mason
Workers having considerable degree skills on block works and can subjectively do the works of piling up
and laying of piling up block, laying block, linking block, and pavement block (excluding block work in
building works)
9. Electrician
Workers having considerable degree skills and necessary qualifications on electric works and can
subjectively do the following works relevant to power receiving facility, substation facility, distribution
line, power facility, power generation facility, and telecommunication facility indoor and outdoor
a) Installation, attachment and removal works of distribution equipment, lighting appliance, generator,
telecommunication equipment, various boards
b) Installation, attachment and removal works of electrical wire and electrical wire pipe
Necessary qualification is division of electricity work in supervision for facility equipment.
10. Rebar man
Workers having considerable degree skills on processing / assembly works of rebar and can subjectively do
the following works such as cutting, bending, shaping, assembly and fixing in reign forced concrete works.
11. Steel worker
Workers having considerable degree skills on assembly works of steel and can subjectively do the
following works such as assembly of steel, tightening high-tension bolts, etc. in construction of steel tower,
steel pier and hi-rise building. (Excluding workers of production in factory, bridge erection and scaffolding
works for steel assembly )
12. Painter
Workers having considerable degree skills on painting works with paint and finishing paint, etc. and can
subjectively do the various painting works including surface treatment for painting. (Excluding workers of
scaffoldings for painting works)
13. Welder
Workers having considerable degree skills on welding works and can subjectively do welding of steel pile,
sheet pile, steel pipe and rebar (including gas-pressure welding) or cutting by the methods of oxygen,
acetylene gas, hydrogen gas and electricity etc. (Excluding workers in factory)
14. Operator (Special)
Operators having official license and considerable degree skills on driving and operation of heavy
machines and can subjectively do the following works with driving and operation of them.
a) Excavation, loading and carrying of earth with driving and operation of bulldozer, tractor, power
shovel, backhoe, clamshell, dragline, loading shovel, tractor shovel, rake-dozer, tire-dozer, scrape-
dozer, scraper, motor-scraper, etc. weighing more than 3 tons.
b) Carrying of equipment with driving and operation of truck, crawler crane, truck crane, wheel crane
with crane equipment capable of lifting more than 1 ton and winch lifting more than 5 tons
c) Scraping and compaction works of earth with driving and operation of road roller, tire roller, vibrating
roller weighing more than 3 tons (self-propelled), stabilizer, motor grader, and etc.
d) Pavement of roads with driving and operation of concrete finisher, asphalt finisher and etc.
A-16
Guideline on the Cost Estimation for Construction Packages in Viet Nam
e) Piling and pulling out of pile and sheet pile with driving and operation of pile driver
f) Driving and operation of concrete pumping car and road sweeping car ( 3 wheel-type)
15. Operator (Ordinary)
Operators with official license who can subjectively do the following works with driving and operation of
machine
a) Driving truck carrying equipment
b) Driving watering car
c) Excavation, loading and carrying of earth with driving and operation of tractor (wheel type), tractor
shovel (wheel type), backhoe (wheel type) weighing less than 3 tons.
d) Carrying of equipment with driving and operation of wheel crane and truck with crane equipment
capable of lifting less than 1 ton
e) Emulsion spraying with driving and operation of asphalt distributor
f) Driving and operation of road sweeping car (4wheel-type)
16. Worker for caisson
Workers having considerable degree skills and advanced physical condition about works in a pressurized
closed room and can do the works of excavation and carrying of earth in caisson and shield (high
atmospheric pressure)
17. Foreman for caisson
Workers having considerable degree skills about works in a pressurized closed room and can do the
leadership works for the works in caisson and shield (high atmospheric pressure)
18. Jumper
Workers having considerable degree skills and advanced physical condition about work in rock excavation
and can subjectively do the works of blast and excavation of rock (excluding works in tunnel) with use of
dynamite and rock drill.
19. Tunnel special worker
Workers having considerable degree skills and advanced physical condition about works in tunnel and can
subjectively do the following works
a) Blast and excavation of rock with use of explosive and rock drill.
b) Installation, maintenance, and inspection of tunnel support
c) Placing concrete at arch, sidewall sections and invert
d) Driving work of muck loading vehicle, battery car and mine cars etc.
e) Assembly, installation, and removal of frames of arch and side wall sections
f) Various works of shield work method (excluding works in high atmospheric pressure)
20. Tunnel worker
Workers having normal skills and physical condition about works in tunnel and can do the following
manpower works
a) Auxiliary works for all works in tunnel
b) Material carrying by manpower
c) Auxiliary works for all kinds works of shield method (excluding works in high atmospheric pressure)
21. Tunnel foreman
Workers having considerable degree skills about works in tunnel and can do leadership task
22. Bridge special worker
Workers having considerable degree skills about bridge construction and can do the following works
(excluding works in factory)
a) Grouting and assembly, tension and transverse tighten works of sheathes and cables in construction
works of PC bridge
b) Erection works of concrete or steel bridge and assembly, disassembly and movement works of
temporary facilities for bridge erection
c) Assembly and disassembly works of scaffoldings and support for erection works of concrete or steel
bridge
23. Bridge painter
Workers having considerable degree skills about painting works for bridges and can subjectively do the
work of painting and surface treatment of bridge and flood gate ( including works in factory)
24. Bridge foreman
Workers having considerable degree skills about all bridge works and can mainly do the leadership works
( including works in factory)
A-17
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-18
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Workers having considerable degree skills about chipping work and can subjectively do the following
works
a) Chipping of wall surface made of concrete, stone brick and tile etc.
b) Making holes on floor or wall
41. Waterproofing worker
Workers having considerable degree skills about waterproofing work and can subjectively do the works of
waterproofing of roof, floor in underground and wall by using asphalt, sheet, cement and sealing materials
etc.
42. Sheet metal worker
Workers having considerable degree skills about sheet metal work and can subjectively do the works of
processing and assembly works such as cutting, bending, shaping, and joining sheet metal and roofing with
sheet metal ( excluding works of 48.)
43. Tiler
Workers having considerable degree skills about tile works and can subjectively do the works of tile
sticking and jointing of outer wall, inner wall, floor etc.
44. Sash worker
Workers having considerable degree skills about sash works and can subjectively do the works of
installation of metal sash
45. Interior worker
Workers having considerable degree skills about interior works and can subjectively do the works of
affixing interior materials such as vinyl floor tile, vinyl floor sheet, carpet, flooring, wall paper and gypsum
board on floor, wall and ceiling and works of installation of window shade and curtain rales
46. Glassworker
Workers having considerable degree skills about glass works and can subjectively do the works of
installation of grass into various joinery
47. Joiner
Workers having considerable degree skills about joinery works and can subjectively do the works of
production, processing, and installation of doors, windows and frames etc.
48. Air duct worker
Workers having considerable degree skills about duct works and can subjectively do the works of
production and installation of ventilation duct by processing metal or nonmetal sheet (excluding works of
42.)
49. Heat retention worker
Workers having considerable degree skills about heat retention works and can subjectively do the works of
installation of heat retention materials (including cold insulation, anti-dew and thermal insulation ) on
various building equipment, plumbing and duct
50. Equipment worker
Workers having considerable degree skills about equipment works and can subjectively do the works of
installation, adjustment and removal of heavy weight machines such as freezing machine, blower, boiler,
pump and elevator etc.
51. Building block worker
Workers having considerable degree skills about building block works and can subjectively do the works of
piling up and joint making of cavity concrete brock and brick for construction and refurbishment of
building frame and curtain wall ( excluding contents described in 8.)
52. Artisans
Being highly skilled craft workers and can subjectively do the works of making or creating things by hand
that may be functional or strictly decorative such as furniture, decorative arts, sculptures, etc. for buildings
53. Construction survey
Workers having considerable degree skills about construction survey works and can subjectively do the
works of topographical surveying, geological surveying, etc.
54. Survey and testing engineer
Engineers having professional qualifications about construction survey and testing works and can do the
leadership works, data analysis works and making reports for the works of topographical surveying,
geological surveying, etc. and tests
55. Traffic guide
Traffic induction guide persons possessing official qualification for traffic guide
A-19
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-20
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-21
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Wear expenses h
Miscellaneous Expenses L.S. 1
Total
A-22
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-23
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-24
Guideline on the Cost Estimation for Construction Packages in Viet Nam
[data to prepare]
List of works: number and duration
Distance between quarters and site, and usual mode of transport
2) Preparation Work
(1) Cost for preparation and clean- up
a) Cost of preparation work for commencement
[items to calculate]
Costs of workers, some equipment (excavators etc.) with dump trucks and disposal for debris
in area of temporary facilities (office etc.)
details [data to prepare]
Area to prepare temporary facilities (office, laboratory, storage area, workshop, precast yard
etc.): estimate number of workers and equipment based on area
(note: Clearing of site for permanent works to be calculated under direct works)
b) Daily preparation and clean- up work
[items to calculate]
Costs of workers for clean-up (tidy up on site) every day
details [data to prepare]
Estimate of number of worker to involve daily clean-up: e.g. 20 % of work group in last 30
minutes of working hours
c) Irregular cots for pumping, dredging sludge and unable to be determined volume from the
design
[items to calculate]
Costs of machine for pumping and dredging and labor for working on them
details
[data to prepare]
Number of machines and equipment necessary and workers involved
d) Final clean-up of the work
[items to calculate]
Costs of workers, some equipment (excavators etc.) with dump trucks and disposal for debris
in whole site for permanent works
Costs of workers, some equipment (excavators etc.) with dump trucks and disposal for debris
in area of temporary facilities (office etc.)
details
[data to prepare]
Area of whole site: estimate number of workers and equipment based on area (e.g. 5days with
50 % of all workforce)
Area of temporary facilities (office, laboratory, storage area, workshop etc.): estimate number
of workers and equipment based on area
(2) Cost for general survey, ground survey, finishing stake and so forth
a) Basic ground survey before work
[items to calculate]
Costs of survey group (assistants, workers, equipment, car or small truck, pegs & other
consumables): field survey only (review of data provided by PO/PMU to be done within site
details management staff)
[data to prepare]
Area of whole site: estimate required days for basic survey (e.g. 1 week, 10days, 2 weeks or
more in case hilly or mountainous area with cutting trees and clearing bushes
b) Check of drawings provided in contract documents
[items to calculate]
Costs of survey group (assistants, workers, equipment, car or small truck, pegs & other
details materials): field survey only
[data to prepare]
Number of drawings to be reviewed with field survey: estimate required days for check survey
c) Confirmation of construction site
A-25
Guideline on the Cost Estimation for Construction Packages in Viet Nam
[items to calculate]
Costs of survey group (assistants, workers, equipment, car or small truck, pegs & other
details materials): field survey for set of boundary position with PO/PMU
[data to prepare]
Area of whole site & length of boundary perimeter: estimate required days for set of boundary
d) Survey works during construction
[items to calculate]
Costs of survey group (assistants, workers, equipment, car or small truck, pegs & other
details materials): field survey only (calculation for survey to be done within site management staff)
[data to prepare]
Whole work volume: estimate required number of survey group
3) Safety Cost
(1) Cost of monitoring and correspondence for safety management in the whole construction site
[items to calculate]
Cost of regular safety patrol: safety experts from outside organization (site management staff
shall carry out together, cost of which is within site management cost).
details
[data to prepare]
Frequency of safety patrol and number of safety experts: e.g. once in a month with an expert
or several experts depending on size and complexity of construction work
(2) Cost of security staffs at site entrances
[items to calculate]
Cost of security with some tools
details [data to prepare]
Number of securities on working days and on off days: estimate required number, depending
on size of construction works and number of entrances
(3) Cost of setting, removing and maintenance of safety facilities such as mark plate, sign, safety
lighting, guard fence, temporary guardrail etc.
[items to calculate]
Cost of depreciation or rental for facilities: transportation is included in 1) (2)
Cost of workers with small tools and consumable goods (wires, nails etc.) for setting &
details removing as well as maintenance
[data to prepare]
List of safety facilities: kinds, size, number and duration of use
Estimate of number of worker for setting & removing as well as maintenance
(4) Cost of lighting in the case of works necessary lighting such as night work
[items to calculate]
Cost of depreciation or purchase for lighting facilities
Cost of workers with small tools and consumable goods (wires, tapes etc.) for setting &
details removing as well as maintenance
[data to prepare]
List of lighting facilities (cables, lump, connectors etc.): kinds, size, number ad duration of use
Estimate of number of worker for setting & removing as well as maintenance
(5) Cost of safety supplies such as helmets, safety belt, safety shoes, gloves etc.
[items to calculate]
Cost of safety supplies
details [data to prepare]
Number of workers: kinds of supplies and frequency of supplies to each worker (e.g. once per
6 months or one year)
(6) Cost of safety committee and other safety activities excluding training
details [items to calculate]
Cost of work heads for safety committee (once in a month), some selected workers for safety
patrol (fortnight) and all for safety assembly (once in a year)
A-26
Guideline on the Cost Estimation for Construction Packages in Viet Nam
[data to prepare]
Details of safety committee: to hold once in a month for 2hours and site managers of
subcontractors to attend
Details of safety patrol: to carry out once in fortnight for half a day and experts of
subcontractors to attend
Details of safety assembly: to hold once in a year for full day, including emergency drill and
all workers to attend
(7) Cost of dust work preventive measures
[items to calculate]
Cost of team consisting of machines (graders, compactors, truck with water sprinkler), some
workers and materials (gravel or crusher run etc.) in order to keep site area clean with no dust
details
[data to prepare]
Area of site area including access: estimate working days (e.g. 2- 3 hours in a week etc.) and
volume of materials required (e.g. 5 m3 in each time)
4) Utility Cost
Basic charge fee for water and electricity used for construction works
[items to calculate]
Costs of Initial burden and basic charge fees for usage of electricity and water at the
construction site
details
[data to prepare]
Invoice of initial burden cost and monthly basic charge for electricity and water from power
company and water supply organization
5) Technical Management Cost
(1) Cost of all necessary tests described in Standard Construction Quality Management Plan
[items to calculate]
Costs of all tests described in Standard Construction Quality Management Plan (Concrete
mixture test, tension strength test of reinforcing bar, soil density, CBR etc.)
details Cost of test devices for above tests
[data to prepare]
List up of all necessary tests for quality management
Decision of number of tests of each test necessary for quality management
(2) As build, and all soft data of necessary documents produced by construction works
[items to calculate]
Costs of making as build and soft data produced by construction works such as construction
pictures, results of all quality control tests
details
[data to prepare]
Drawings for final construction objects constructed based on design and contract documents
List up of all necessary documents to complete construction work
(3) Cost for storage of quality record of all construction materials used
[items to calculate]
Costs of collecting and filing documents for quality records of all construction materials to be
details used for construction works
[data to prepare]
List up of quality records of all construction materials to be used for construction works
(4) Cost of quality certificate of construction materials used
[items to calculate]
Costs of making certificates of main construction materials used (Cement, aggregate,
bituminous material, steel etc.)
details
[data to prepare]
Invoice from material supplier for issuing certificate of construction materials used (Referring
the practice of other similar projects is applicable)
(5) Cost of documents made for work schedule management
A-27
Guideline on the Cost Estimation for Construction Packages in Viet Nam
[items to calculate]
Costs of making documents for work schedule management such as scheduling, work flow
chart workforce management and so forth
details
[data to prepare]
Estimate of work schedule by using critical path to finish all construction works during
contract construction period
(6) Cost of survey, drawings, pictures for inspection of completion
[items to calculate]
Costs of survey of constructed objects, making drawings for final measurements of objects
and pictures of construction for inspection of completion
details [data to prepare]
Survey data of all objects constructed, data of measurements records for reflecting and
checking original design and gathering construction pictures including already closed portions
after completion such as pile work, reinforcing, embankment etc.
6) Temporary Building
(1) Cost of setting, removing, and maintenance of site office and laboratory
[items to calculate]
Costs of building, removing, and maintenance of site office including exterior
Costs of building, removing, and maintenance of laboratory at the site including exterior
details [data to prepare]
Area, location, capacity for necessary personnel for construction project on site office
Area, location, inner arrangement of test facility and storage space of test pieces on site
laboratory
(2) Cost of setting, removing, and maintenance of staff and workers’ dwelling house on site
[items to calculate]
Costs of building, removing, and maintenance of staff and workers’ dwelling house on site
including exterior and interior facilities
details
[data to prepare]
Area, location, accommodation capacity for necessary personnel including all work force for
construction project
(3) Cost of setting, removing, maintenance of warehouse of some goods and equipment, and material
depository
[items to calculate]
Costs of building, removing, and maintenance of warehouse of some goods for construction
(rubber corn, rope, sign, tools etc.),and equipment (welding machine, generators, reinforcing
bar cutter and bender, vibrator, compressor etc.)
Costs of building, removing, and maintenance of material depository such as aggregates,
details
cement, crasher run and so forth
[data to prepare]
Area, location, capacity for necessary goods and equipment on warehouse
Area, location, capacity for necessary construction materials to be used on construction
schedule
(4) Land lease fees of above (1)(2)(3)
[items to calculate]
Costs of lease fees for land using for site office, laboratory, staff and workers’ dwelling house,
warehouse of some goods and equipment, and material depository
details
[data to prepare]
Invoice for monthly lease fees of land using for site office, laboratory, staff and workers’
dwelling house, warehouse of some goods and equipment, and material depository
A-28
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-29
Guideline on the Cost Estimation for Construction Packages in Viet Nam
[data to prepare]
List of prevention facilities: kinds, size, number and duration of use
Estimate of number of worker for setting & removing as well as maintenance
(4) Cost of life jacket and lifeboat in river and coastal construction
[items to calculate]
Cost of depreciation or rental for facilities on or near water (life jackets, lifeboat etc.):
transportation is to calculate in similar manner described in (1) in 2) of Indirect Cost Items by
details Rate (Appendix 5)
[data to prepare]
List of facilities on or near water: kinds, size, number and duration of use
Estimate of number of worker for maintenance
(5) Cost necessary for prevention of accidents from high voltage work
[items to calculate]
Cost of depreciation or rental for facilities (high voltage incoming pane, insulating devices
etc.): transportation is to calculate in similar manner described in (1) in 2) of Indirect Cost
details Items by Rate (Appendix 5)
[data to prepare]
List of facilities: kinds, size, number and duration of use
Estimate of number of worker for maintenance
(6) Cost of monitoring for blasting of rock excavation in dam, tunnel and other construction
[items to calculate]
Cost of monitoring members with small tools (hand mike and silent etc.)
details [data to prepare]
Duration of blasting works and number of blasting in a day as well as size of blasting
Composition of members for monitoring
(7) Others (in the case of necessary due to site conditions)
e.g.: Security guard necessary for the site near special area such as railways or airport etc.
4) Technical Management Cost
(1) Cost of special quality control
a) Tests besides those are regulated in quality control standard and standard construction quality
management plan such as soil test, etc.
b) In-situ tests such as geological survey, plate bearing test, boring, sounding, pile test etc.
[items to calculate]
Costs of all special tests such as ultrasonic wave test, triaxle compression test etc.
details Cost of test devices for above tests
[data to prepare]
List of special tests, including in-situ tests: kind, number etc.
(2) Cost of special cases due to site conditions
a) Setting and removing of test equipment, measurements, and data collection for soft ground
research (settlement measurement, water table, pore water pressure etc.)
b) Cost of works for test embankment
[items to calculate]
Costs of all special cases mentioned above
details Cost of required devices for above cases
[data to prepare]
List of special cases: kind, size, number etc.
A-30
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-31
Guideline on the Cost Estimation for Construction Packages in Viet Nam
[data to prepare]
Number of workers
Days and time schedule for safety activity and training
(2) Cost of meeting for safety and health education
[items to calculate]
Cost of unit price of workers, material and etc.
If necessary, cost of safety management engineer to be calculated.
details
[data to prepare]
Number of workers
Days and time schedule for safety activity and training
4) Insurance
(1) Cost of work insurance
[items to calculate]
Cost of work insurance: the objectives of insurance are construction structure, temporary
structure, materials for construction structure and temporary structure and etc.
details [data to prepare]
Construction cost excluding the VAT
Rate of insurance
Period of insurance
(2) Cost of car insurance
[items to calculate]
Cost of car insurance
[data to prepare]
details
Number of cars
Period of insurance
Type of car
A-32
Guideline on the Cost Estimation for Construction Packages in Viet Nam
6) Severance Pay
(1) Cost of the severance pay
[items to calculate]
Cost of basic salary
Cost of the managerial position, qualification, field, overtime, holiday working allowance,
bonus and etc.
details
[data to prepare]
Number of the staffs in the project
Years of experience, age and qualification of the staffs
Working period of the staffs
8) Welfare Cost
(1) Cost of amusement for recreation
[items to calculate]
Cost of social gathering, dining party, year-end party / new-year party and etc.
Cost of newspaper and magazines
details
[data to prepare]
Number of the staffs
Number of times for above parties
(2) Cost of rental clothes
details [items to calculate]
A-33
Guideline on the Cost Estimation for Construction Packages in Viet Nam
9) Office Supplies
(1) Cost of office facilities of electronic equipment
[items to calculate]
Personal computers (depreciation rate)
Printer (depreciation rate)
Rental copy machine
details
[data to prepare]
Number of personal computer and printer
Period and fee of rental copy machine
Rate of depreciation
(2) Cost of office facilities of furniture
[items to calculate]
Cost of desk, chair, cabinet, meeting table and shelves
[data to prepare]
details
Number, kind, size of furniture
Number of staffs
Area of office
(3) Cost of office supplies
[items to calculate]
Cost of papers, office supplies (stationary, extension cord and etc.)
details
[data to prepare]
Estimate of number of office supplies
(4) Cost of books
A-34
Guideline on the Cost Estimation for Construction Packages in Viet Nam
[items to calculate]
Cost of newspapers, magazines, reference book and etc.
details [data to prepare]
List of newspapers, magazines, reference book
Construction period
(5) Cost of drawings
[items to calculate]
Cost of print and copy of drawings
details
[data to prepare]
Estimate of number of drawings
A-35
Guideline on the Cost Estimation for Construction Packages in Viet Nam
[items to calculate]
Cost of entertainment for clients and visitors
Cost of gift for clients and visitors
details Cost of congratulatory and condolence for clients and visitors
[data to prepare]
List and number of clients
Estimate of number of visitors
A-36
Schedule 2014 2015
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
considered.
Construction Schedule 18 Months
Preparation 2 Months
Project Manager
A-37
Bridge Section Road Section Quality Section Safety Section
Manager
Chief Engineer Chief Engineer Engineer (Safety)
(Quality)
at least for successful completion of construction project. At cost estimation, this system has to be
Guideline on the Cost Estimation for Construction Packages in Viet Nam
study project from the view of internationally standard level. These numbers of engineers are required
Form-1(Ma) Actual Condition Survey for Unit Price of Materials
Address Tel
A-38
5
8
Appendix 9 Survey Form of Unit Price of Material
10
11
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Working day / y ear Office number of employee's pension insurance
Form-1(L) Actual Condition Survey for Unit Price of Labors Project Name
Month
Contractor
Age
Prescribed paid leave allowance that allowance that T emporary salary kind Employment Pension
No. of
Years of
leav Overtime Holiday day Basic salary Paid by the piece year including long
time
experience
Occupation
time object of extra not object of ( bonus etc.) / year insurance insurance
Employment
Type of wage
e term insurance
Prescribed
coefficient extra coefficient
1 1 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
2 2 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
3 3 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
4 4 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
5 5 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
A-39
6 6 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
7 7 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
8 8 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
9 9 ● ● ● ●
- - - - - - - - - - - - 0 0 0 0 - - - 0
0 0 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
1 1 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
2 2 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
3 3 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
Appendix 10 Survey Form of Unit Price of Labor No.1
4 4 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
5 5 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
6 6 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
7 7 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
8 8 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
9 9 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
0 0 ● ● ● ● - - - - - - - - - - - - 0 0 0 0 - - - 0
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Month
Form-2(L) Actual Condition Survey for Unit Price of Labors
Project Name
<Form-1-1> Main Contractor
Payer
※ Project Owner
Creator Name
Number of
Circumstance of employment Working day by PO Out of the basic allowance
Non-working Number of
non- balance per
Plural occupations condition
Qualification acquisition Allowance for working day due to the
No. Name No. (If a worker has plural
condition outside working Allowance for time non-working
Ranking
occupation except form1) Other State Other Per year
time, holiday and absent from work (Subject day
Private
No. of occupation
municipalities
midnight month)
Object month
Office Address
Prefectures and
1 1 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
2 2 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
3 3 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
4 4 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
5 5 0 0 0 0 0 0 - - - - - - - - -
●
- - - - -
A-40
6 6 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
7 7 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
8 8 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
9 9 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
0 0 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
1 1 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
2 2 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
3 3 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
4 4 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
Appendix 10 Survey Form of Unit Price of Labor No.2
5 5 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
6 6 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
7 7 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
8 8 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
9 9 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
0 0 0 0 0 0 0 0 - - - - - - ●
- - - - - - - -
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Form-1(Mc) Actual Condition Survey for Unit Price of Machineries (Usage condition)
1 2 3 4 5 6
1 Name of construction machinery
2 Manufacture name
4 Machinery type
of machinery
5 Specification
8 Date of acquisition
10 Method of acquisition
A-41
11 Price of acquisition
2. Acquisition record
12 Accessory
13 Number of retention
3. Operation record
Appendix 11 Survey Form of Unit Price of Machinery No.1
repair record
Cumulated maintenance and repair
21
4. Maintenance and
Guideline on the Cost Estimation for Construction Packages in Viet Nam
1. Management record
A-42
8 Utility cost at storage facility
Number of machinery
9
retention
Taxes and other public
10
duties of machinery
11 Insurances of machinery
Appendix 11 Survey Form of Unit Price of Machinery No.2
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Form-3(Mc) Actual Condition Survey for Unit Price of Machineries (Disposition record)
Category # Items 1 2 3 4 5 6
1 Name of machinery
Total acquisition cost of
2
machinery
3 Name of manufacture type
4 Machinery type
machinery
5 Specification
1. Summary of disposition of
7 Weight
8 Date of acquisition
2.
n record
9 Division of new or old
A-43
10 Date of disposition
11 Price of disposition
12 Method of disposition
13 Purpose of disposition
3. Disposition recordAcquisitio
Total operation hour until
14
disposition
4.
record
Total maintenance and
15
Maintenanc
e and repair
repair cost
Appendix 11 Survey Form of Unit Price of Machinery No.3
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Form-1(P) Actual Condition Survey for Productivity rate (Outline of the Project)
1. Location
2. Project name
3. Construction division
5. Construction period
6. Survey period
Yes No
PO
Contractor Name
A-44
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Section
Form-2(P) Actual Condition Survey for Productivity rate (Schematic diagram of construction work)
Plan
A-45
Form-3(P) Actual Condition Survey for Productivity rate (Flow chart)
Operation
Working item / / / / / / / / / / / / / /
number
A-46
8
10
11
12
Appendix 12 Survey Form of Productivity Rate No.3
13
14
15
Material
Occupation Working contents
A-47
Labor
M achinery number Machinery name
Appendix 12 Survey Form of Productivity Rate No.4
Machinery
Construction progress Construction volume
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Form-5(P) Actual Condition Survey for Productivity rate (Materials)
Material Operation
Material name Specification Manufacture name Unit Design volume Usage Unit price
number number in
1
A-48
8
10
11
12
Appendix 12 Survey Form of Productivity Rate No.5
13
14
15
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Form-6(P) Actual Condition Survey for Productivity rate (Construction machinery)
A-49
8
10
11
12
13
Appendix 12 Survey Form of Productivity Rate No.6
14
15
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-50
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A. CONSTRUCTION INFORMATION
1 Project Name
2 Construction Package Name
3 Organization in charge (1)
4 Organization in charge (2)
5 Organization in charge (3)
6 Name of Contractor
7 Final Approved Cost of Package
7-1 Construction Cost in above amount
7-2 VAT
7-3 Contingency
8 Initial Contract Amount of Package
8-1 Construction Cost in above amount
8-2 VAT
8-3 Contingency
9 Final Contract Amount of Package
9-1 Construction Cost in above amount
9-2 VAT
9-3 Contingency
10 Construction Category
A-51
Guideline on the Cost Estimation for Construction Packages in Viet Nam
B. GENERAL INFORMATION
1) REGISTRANT
1 Mail Address
2 Name
3 Position
4 Name of Organization
5 Department, Division
6 Tel. No.
7 Fax No.
2) WORK INFORMATION
1 Jurisdiction
2 Work Category
3 Work Registration No.
4 Construction Site Area
5 Other Index
A-52
Guideline on the Cost Estimation for Construction Packages in Viet Nam
C. CONSTRUCTION COST
INDIRECTCOST (1000VND)
Common Indirect Cost
Transportation cost
1
(machine,labor,material)
2 Preparation Work
Cost of Facilities for Prevention
3 Measures against Damages by
Construction
4 Safety Cost
5 Utility Cost
6 Technical Management Cost
7 Temporary Building
Site Management Cost
Total
OVERHEAD (1000VND)
Overhead
TAX (1000VND)
VAT
CONTINGENCY (1000VND)
Contingency
Grand Total
A-53
Guideline on the Cost Estimation for Construction Packages in Viet Nam
Chapter 9
A-54
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A. GENERAL INFORMATION
1) REGISTRANT
1 Mail Address
2 Name
3 Position
4 Name of Organization
5 Department, Division
6 Tel No.
7 Fax No.
2) WORK INFORMATION
1 Name of Work
2 Name of Project Owner
3 PMU
4 Name of Construction Office
5 Construction Site
6 Name of Contractor
7 Contract Amount in final
8 Tax in Amount
9 Contract Construction Period
10 Main Construction Objects
3) SUB CONTRACTOR
1 First Sub Contractor
2 Second Sub Contractor
3 Third Sub Contractor
A-55
Guideline on the Cost Estimation for Construction Packages in Viet Nam
B. CONSTRUCTION PERIOD
3) WORKING HOUR
1 Normal Work Hour (Time to Time)
2 Hours of Overtime (in total)
3 Days of Night Work
4 Hours of Night Work
A-56
Guideline on the Cost Estimation for Construction Packages in Viet Nam
C. CONSTRUCTION COST-1
DIRECT COST (1000VND)
MAIN S UB
ITEM TOTAL CONTRACTOR CONTRACTOR
1 Materiail cost
2 Labor Cost
3 Machine Cost
4 Utility (Electlicity, water etc.)
5 Others (Special Expense)
Total
A-57
Guideline on the Cost Estimation for Construction Packages in Viet Nam
C. CONSTRUCTION COST-2
INDIRECT COST (1) (1000VND)
MAIN S UB
ITEM TOTAL CONTRACTOR CONTRACTOR
A-58
Guideline on the Cost Estimation for Construction Packages in Viet Nam
A-59
Guideline on the Cost Estimation for Construction Packages in Viet Nam
(1000VND)
MAIN S UB
ITEM TOTAL CONTRACTOR CONTRACTOR
11 Social Expenses
12 Compensation Cost
13 Outsourcing Cost
14 Work Registration Cost
Other Cost not Included in
15
above Items
Total
OVERHEAD (1000VND)
MAIN S UB
ITEM TOTAL CONTRACTOR CONTRACTOR
Overhead
TAX (1000VND)
MAIN S UB
ITEM TOTAL CONTRACTOR CONTRACTOR
VAT
Grand Total
* Colum of Sub Contractor is filled with total amount of all Sub Contractors
A-60