Jeddah Heights - Prince Fawaz Housing Project

Physical Progress Tracking Sheet - CMU works


Act % = Performance Achieved by Sub Contractor Activities are in Progress (Plan %) Status Date 14-Jul-20

CMU Gr. Floor CMU 1st Floor CMU 2nd Floor CMU 3rd Floor CMU 4th Floor CMU 5th Floor CMU 6th Floor
Sl Block Build. Build. Cum. Act Prog
Contractor Remarks
No No. Type No. % CMU Works
Act % Act % Act % Act % Act % Act % Act %

1 Al Taiser & Al Baraka 1 A 1 70% 9.70%

2 Al Taiser & Al Baraka 1 A 2 70% 9.70%

12 Al Taiser & Al Baraka 4 A 1 85% 11.78%

13 Al Taiser & Al Baraka 4 A 2 85% 11.78%

Saudi Chinese
47 6 B 7 85% 11.78%
contracting Co
Saudi Chinese
55 6 B 15 95% 13.16%
contracting Co
Saudi Chinese
56 6 A 16 85% 11.78%
contracting Co
Saudi Chinese
57 6 A 17 85% 11.78%
contracting Co

78 Golden Centre 11 B 2 85% 11.78%

79 Golden Centre 11 A 3 85% 11.78%

82 Golden Centre 11 B 6 85% 2% 12.06%

83 Golden Centre 11 A 7 10% 1.39%

84 Golden Centre 11 A 8 85% 11.78%

86 Golden Centre 11 A 10 2% 0.28%

88 Golden Centre 11 B 12 2% 0.28%

89 Golden Centre 11 A 13 85% 11.78%

96 ayoubi 13 A 4 5% 0.69%

98 ayoubi 13 A 6 5% 0.69%

101 En jaz Soma 14 A 3 5% 0.69%

117 Daleel Al Salah 16 A 7 5% 0.69%

118 Daleel Al Salah 16 A 8 5% 0.69%

123 Daleel Al Salah 17 B 5 5% 0.69%

124 Daleel Al Salah 17 A 6 55% 7.62%

125 Daleel Al Salah 17 A 7 25% 3.46%

151 Rakaez AL Hadeed 22 B 1 30% 4.16%

165 Al Harefy 26 B 1 60% 5% 9.01%

166 Al Harefy 26 B 2 70% 9.70%

167 Al Harefy 26 B 3 5% 0.69%

170 Al Harefy 26 A 6 10% 1.39%

171 Al Harefy 27 A 1 95% 50% 20.09%

172 Al Harefy 27 A 2 5% 70% 10.39%

173 Al Harefy 27 A 3 80% 11.09%

174 Al Harefy 27 A 4 95% 13.16%

175 Al Harefy 27 B 5 30% 4.16%

176 Al Harefy 28 A 1 10% 1.39%

182 Al Harefy 28 A 7 95% 90% 25.64%

185 Al Harefy 28 B 10 50% 30% 11.09%

186 Al Harefy 29 A' 1 40% 5.54%

211 Al Mo'jel 34 A 5 70% 9.70%

229 Al tasmim 37 A 1 80% 11.09%

230 Al tasmim 37 B 2 60% 5% 9.01%

232 Al tasmim 37 B 4 80% 50% 18.01%

257 Al Tayyar al arabi 43 B 1 65% 9.01%

258 Al Tayyar al arabi 43 C 2 90% 12.47%

259 Al Tayyar al arabi 43 C 3 85% 11.78%

260 Al Tayyar al arabi 43 C 4 95% 13.16%

Progress Tracking Sheet_CMU_JHP_as of 15-Jul-20 CMU_Progress Update Page 1 of 2


Jeddah Heights - Prince Fawaz Housing Project
Physical Progress Tracking Sheet - CMU works
Act % = Performance Achieved by Sub Contractor Activities are in Progress (Plan %) Status Date 14-Jul-20

CMU Gr. Floor CMU 1st Floor CMU 2nd Floor CMU 3rd Floor CMU 4th Floor CMU 5th Floor CMU 6th Floor
Sl Block Build. Build. Cum. Act Prog
Contractor Remarks
No No. Type No. % CMU Works
Act % Act % Act % Act % Act % Act % Act %

261 Al Tayyar al arabi 43 C 5 75% 10.39%

262 Al Tayyar al arabi 43 A 6 92% 15% 14.83%

263 Al Tayyar al arabi 44 B 1 5% 0.69%

266 Al Tayyar al arabi 44 B 4 100% 13.86%

268 Al Tayyar al arabi 44 B 6 10% 1.39%

340 Hololana Company 58 A 4 10% 1.39%

341 Hololana Company 58 A 5 10% 1.39%

342 Hololana Company 58 A 6 10% 1.39%

345 Al Baraa 58 B 1 60% 8.31%

346 Al Baraa 58 A 2 50% 6.93%

347 Al Baraa 58 B 9 80% 20% 13.86%

348 Al Baraa 58 A 10 80% 40% 16.63%

349 Al Baraa 58 A 11 10% 1.39%

350 Al Baraa 58 B 12 20% 60% 11.09%

351 Al Baraa 58 A 13 80% 10% 12.47%

352 Al Baraa 58 B 14 80% 11.09%

364 Htan Da Khel ALLah 60 A 6 70% 9.70%

Grand Total in Percenatge 8.1% 1% 1.27%


. . . . . . .

Sl Total No of
Description CMU Gr. Floor CMU 1st Floor CMU 2nd Floor CMU 3rd Floor CMU 4th Floor CMU 5th Floor CMU 6th Floor
No Floors
No. of Floors Comp 100% and
1 1 1
Approved by SAK
No. of Floors Comp 100% and
2 7 1 8
Waiting for Apprval by SAK
No. of Floors Comp. up to Lintel
3 18 18
Level (85%)

Grand Total 27

Sl
Description Type A Type A' Type B Type C Total
No
No. of Floors Comp 100% and Approved
1
by SAK 1 1

No. of Floors Comp 100% and Waiting


2
for Apprval by SAK 5 1 2 8

No. of Floors Comp. up to Lintel Level


3
(85%) 11 6 1 18

Grand Total 27

Progress Tracking Sheet_CMU_JHP_as of 15-Jul-20 CMU_Progress Update Page 2 of 2