You are on page 1of 6

NEW QUITO INTERNATIONAL AIRPORT

PROCUREMENT METHOD REPORT


Prepared by Diego Daqui – November, 2014

The New Quito International Airport (NQIA) is located in


INTRODUCTION Quito – Ecuador to 40 km from downtown in Tababela
After of 30 years of planning and halting, in 1995 the County over an undeveloped area of 1,400 hectares. The
Ecuadorian government start the process to replace the project is a green project that was designed completely
Quito Airport built in 1960’s for a new airport to face the from ground zero. The new airport has a 4,100-meter
21 Century. This report describes the procurement runway with capacity of 90,000 annual aircraft
process for the Build, Operate, and Transfer BOT movements, three (3) rapid exit ways, two (2)
concession and the Design-Build construction over a five perpendicular taxiways and one parallel taxiway. The
years until the project was awarded, these processes airport complex comprehends: a Passenger Terminal
cannot be separated because the concession process Building with a gross area of 38,050 sq. m in three levels
explain the decision made for the construction of the to accommodate 3,617,453 passengers per year, one Air
new airport. Also, describes the problems encountered Traffic Control Tower of 42 meter height and hangars for
during the construction like price escalation due to aircraft codes D and E. Additionally, during phase 1 the
construction period extension, social and environmental following ancillary facilities was built: Fuel Farm, 1
issues and subcontracts problems. Finally, it provides Hangar for Code C aircrafts, 1 Cargo building, 2 Catering
some recommendations to improve the procurement Buildings, 1 General Aviation Building, 1 Ground Service
process and the lessons learned from this analysis Equipment Building, and the related electrical, sanitary
and communication infrastructure (Quiport, 2005).

DESCRIPTION OF THE PROJECT


The former Quito International Airport “Mariscal Sucre”
(AIMS) was located in the northern part of the city over,
bounded by a local road network, the southeast, the
northeast, the north and to the west. It comprehended a
3210-meter runway at an altitude of 2800m above sea
level. In 2003 alone, it processed 2.6 million passengers
and 140,000 tonnes of cargo (Marshal Macklin
Monaghan, 2004). FIGURE 2 NEW QUITO INTERNATIONAL AIRPORT

PROCUREMENT METHOD
The procurement method used was Build, Operate, and
Transfer BOT concession for the AIMS (California Aviation
Alliance, 2001). As a previous step, the Ecuadorian
government created a local agency in charge of managing
the concession process for the operation of the former
airport and construction of the new airport. The new
FIGURE 1. FORMER QUITO INTERNATIONAL AIRPORT authority hired a consultant firm to help it to determine

CM520 - Construction Procurement System CM 520A – Term Paper


Diego Daqui V Page 2
NEW QUITO INTERNATIONAL AIRPORT
PROCUREMENT METHOD REPORT

the procurement strategy for the concession. The (Navaids, Security systems, etc.) and for treatment plants
consultant recommended a BOT concession and on (sanitary and treated water) there was an invitation to
February of 2001, one of the prequalified bidders from a bid process to Canadian and Brazilian companies.
previous bid process for the construction of NQIA sent a
proposal for the concession. At the end of 2001, Quito
municipality called for a Request for qualifications /
PROBLEMS ENCOUNTERED DURING THE
Request for proposal for the Build, Operate, and Transfer PROJECT EXECUTION
BOT concession for the AIMS (California Aviation Alliance,
Two main problems related to contract during the
2001) under a Swiss Challenge process based on the early
execution of the contract were lack of price escalation
submitted proposal. In this process, only one bidder
and an excessive supervision. First, the contract was
submitted a proposal for the concession, the other
pricing as a lump sum contract, and the contract does not
bidders resigned to submit a proposal mainly due to the
require a price escalation since the construction period
9/11 attack and the possible consequences for the
was established as 51 months, starting in 2005; however
aviation industry and their repercussions in the rest of
due to political issues with new major, the contract
Latin America.
entered in a renegotiation phase in early 2009. This
With only one bidder in the process, the authority renegotiation took one a half year, extending the original
entered in a direct negotiation process for the concession period to 2012. As a consequence, the costs were
and signed the contract in 2002 for a 35-year concession. increased but the prices were not escalated by the
Right after this, the concessionaire started a direct concessionaire. Moreover, there were some variation
negotiation with a joint-venture of construction orders issued by the owner in 2010 that must be
companies for the design-build of the new airport negotiated at 2005 prices that causes losses to the
located in Tababela County. The construction contract general contractor.
was awarded in 2005 on a Lump sum basis.
Due to the opposition from some councilmen and the
The Build-Operate-Transfer concession method was pressure from international lenders, the project was built
selected at that time because the country had started a under close supervision of three different consultants;
concession process in all areas including water, power Lender engineer, Owner engineer and environmental
generation and roads, mainly due to the oil low prices consultant. This kind of supervision lead to increase the
that reduced the government investment capacity. construction costs since all activities must be carried out
with excessive care, as example, a discharge line must be
Design-Build method for the construction was selected built from the storm water retention pond to the river in
mainly because to the cost of improve the former airport a 500-meter height slope, but due to environmental
was high. Since it was located inside the city, and it regulation, only a 2-meter wide access trail was approved
required extend the runway over streets and land by the environmental authority, and the materials only
acquisition and expropriation and the north and south can be carried in 50-kg bags by the workers. This kind of
side. Moreover, the cost of operation and maintenance excessive care increased the costs and affected the
of the former airport were high and the runway productivity. Moreover, this situation leaded to an
pavement required repairs every day. As a result, the adversarial relationship between the concessionaire and
concessionaire preferred to move the airport operations the contractor.
as soon as possible to the new airport.
Another problem that was not related to the contract but
The general contractor self-performed the earthworks, influenced in the performance of the contractor was the
asphalt and concrete pavements; the rest of works were relation with the government aviation authority (Civil
done by trade subcontractors. The subcontracts were Aviation Directorate – DAC) and municipality aviation
awarded based on a Request for Qualifications/Request authority (Corporacion Aeropuerto –CORPAQ). In the
for Proposal from a short list of the major trade contract was stated that the aviation authority must
subcontractors in the local market, for special systems review, approve and accept the navigation aids and Air
CM520 - Construction Procurement System CM 520A – Term Paper
Diego Daqui V Page 2
NEW QUITO INTERNATIONAL AIRPORT
PROCUREMENT METHOD REPORT

Control Traffic Tower equipment since they are the only A price escalation clause must be included in the
authorized to control the air traffic however they contract; this clause shall be effective in case that the
maintained out of the process due to political pressure construction period extend for more than 50% of the
since the major and the president of Ecuador did not original period when the cause cannot be attributable to
concur with the scheme applied to contract the the contractor. This can be especially applied to Variation
construction. In the same way, the municipality aviation Orders issued after the original period to recognize that
authority CORPAQ, tried to take over the security system prices increment can occur.
design and implementation but after the contract was
signed, without issuing any VO and changing the scope of Regarding the issues with aviation authority and the
the work. These events, at the time of testing and concessionaire, it advisable to incorporate them as soon
commissioning, caused disputes and a claim for the as possible in order to minimize any possible conflict and
security system; this ends in the change of the entire transform into a win-win relationship.
security system scheduled for the next year and delaying
It is advisable to use best value criteria instead of a low
the acceptance of the Navaids and ATCT equipment by
bid for subcontractors, especially in an international
DAC. As a consequence, the final completion certificate
environment since there are cultural differences in
has not been issued until the date of this report, despite
means and methods between a North American GC and
of the fact that the airport has been operating for more
South American Builders that can lead to a poor
than 18 months and the Airport has been certified by
subcontractor performance affecting the overall schedule
DAC.
and budget.
Regarding to the subcontracts, the main problem was
The materials quantification and acquisition by the
that most of subcontractors were unfamiliar with the
General Contractor must be improved in order to avoid
means and methods expected by the General Contractor
mistakes and delays caused by shortages or wrong
and the lenders requirements, especially those related to
purchases that cause losses and delays.
safety and construction methods related cost, e. g.
formwork, trenches excavation, curing methods,
documentation management practices, etc. These LESSONS LEARNED
unforeseen issues brought delays in shop drawings The analyzed project contained all of the components
approval, rework, additional costs among others and process learned in class; indeed it includes hiring a
problems (Medina, 2014). consultant to develop a procurement strategy early in
the project. Also, a Swiss Challenge process was
Another problem with subcontracts was the services
implemented because one of the bidders sent an
furnished by the general contractor like surveying,
unsolicited proposal; if the political and economic
purchase of materials. These services were not managed
conditions were different at the time of the invitation to
adequately and they causes delays and disputes
bid probably the owner could maximize its investment.
especially surveying since there was no subcontractors
surveyors, superintendents rely only in GC team Although the liquidated damages for delay (67,000 for
eliminating the possibility of double check leading to the first 60 days, 68,000 USD for the following 90 days
errors on site. Moreover, the GC material furnished – and 69,000 USD for the next 90 days and 70,000 USD
Subcontractor installed creates problems in plumbing thereafter) was not mentioned in the report, it
and mechanical trades since the contracts were awarded constitutes a powerful tool to enforce the schedule
with a 60% design and the quantity take offs were not compliment.
enough accurate, requiring new purchases with the
additional cost for the GC. Due to the review of the General Contractor contract and
all the subcontracts, a better comprehension of the
contract language and structure was gained. This will be
RECOMMENDATIONS helpful in the contracting world.

CM520 - Construction Procurement System CM 520A – Term Paper


Diego Daqui V Page 3
NEW QUITO INTERNATIONAL AIRPORT
PROCUREMENT METHOD REPORT

ACKNOWLEDGEMENTS
I want to express my acknowledgments to all the AECON
AG Staff for their collaboration, especially to Nelson
Medina, Engineering Manager at AECON AG for his
advice and long discussion along this seven years.

REFERENCES
California Aviation Alliance. (2001, 12 20). California
Aviation Alliance. Retrieved 11 29, 2014, from
Ecuador Calls For Bids On Building New Quito
Airport:
http://archives.californiaaviation.org/airport/ms
g19117.html

Explored. (1998, 07 08). Explored. Retrieved 11 29, 2014,


from Corre El Plazo De Un AÑo Para
Aeropuertos:
http://www.explored.com.ec/noticias-
ecuador/corre-el-plazo-de-un-aa-o-para-
aeropuertos-1744.html

Marshal Macklin Monaghan. (2004). Quito International


Airport - Master Plan. Quito: MMM.

Medina, N. (2014, October). Personal Interview. (D.


Daqui, Interviewer)

Quiport. (2005). Construction Agreement - Appendix K2


Design Brief. Quito.

CM520 - Construction Procurement System CM 520A – Term Paper


Diego Daqui V Page 4
Location NQIA
Former Airport

‐Quito New Quito 
Ecuador
‐ 40 Km Away International Airport
‐1.500 Hectares
‐350 Hectaresof
development
2012 New Quito Internacional Airport
Camp
AECON‐AG Passenger Terminal 
Building

Air Traffic 
Control Tower
Catering
2006 2007 Cargo
Hangar
Fire Station & 
Maintenance 
Building

General Aviation

Police Station
Alpachaca
Connector
Taxi Way
2008 2009 Run Way

You might also like