FOUR STAR INDUSTRIES

POWER PRESS - CONTINGENCY PLAN


S.No. Emergency Situation Action to be taken to deal with the Responsibility Information to Remarks
contingency be given to
Cirtical spare parts list made & spare parts inventory to be
01 Power press break down due to spare parts maintain Head - Maint. Head - Production

Power press long time mechanical break Production to be manage on available same capacity machine
02 Head - Maint. Head - Production
down & M/c maintainance to be done form out source

Power press break down due to electric Spare electric motors to be maintain in inventory 5HP , 7.5HP,
03 Head - Maint. Head - Production
motor 10HP, 15HP.

Prepared By :- Checked By:- Approved By:-