Professional Documents
Culture Documents
Workover & Completion Well Control PDF
Workover & Completion Well Control PDF
and Completion
1
Outline
We assume that you’ve already had a basic or advanced ‘Well Control’ course. We
will review most of the concepts from that course. If you haven’t had the well-
control course, you’ll be able to understand almost all the concepts and
fundamentals of well control, we just won’t go into great detail on the calculations
and work sheets used in those courses.
2
Pressure Basics
Pressure is
3
Hydrostatic Pressure
Air is also a fluid. A column of air that measures 1” by 1” and is 60 miles high
weighs 14.7 pounds or 100 kPa. Another way of saying this is that the column
exerts a pressure of 14.7 pounds per square inch.
4
Hydrostatic Pressure
In most cases in the oilfield, we’re talking about the hydrostatic pressure of liquids.
The most common oilfield unit of density is ‘Pounds per Gallon’, derived from the
old usage for mixing drilling mud. The equivalent metric unit is kilograms per cubic
meter.
5
Pressure Calculations
Static Pressure
Hydrostatic pressure at any point in the fluid column
P = TVD x MW x K where
We can calculate the hydrostatic pressure exerted by the weight of the fluid column,
considered at any point in the fluid column. An example is presented on the next
slide.
6
Example Static Pressure
Assume:
TVD = 8,202 ft (2500 m)
MW = 11.1 ppg (1330 kg/m3)
7
Hydrostatic pressure expressed
as Equivalent Mud Weight
It is also common to express the weight of the fluid column as an ‘equivalent mud
weight’ rather than as psi. We say ‘equivalent’ mud weight because the fluid
column may not be composed of mud, but of water, oil, gas or other fluids, but the
pressure is stated as if the column were mud. Example on next slide.
8
Hydrostatic pressure expressed
as Equivalent Mud Weight
9
Hydrostatic pressure expressed
as Equivalent Mud Weight
Here’s
10
Hydrostatic pressure expressed as
Hydrostatic Gradient
Another way to express pressure is as an ‘Average Gradient’. The units we use are
‘psi per foot of depth’ or kPa per meter.
This is a simple calculation that assumes that the entire hydrostatic column is
composed of a homogeneous fluid, and that’s not always the case. On the other
hand, ‘Average Gradient’ is a convenient way to allow interpolating pressure
between depths.
11
Hydrostatic pressure expressed
as Hydrostatic Gradient
Assume:
kg/m3)
BHP = 4734 psi, TVD = 8,202 ft (2500 m), MW = 11.1 ppg (1330 kg/m
K = 0.052 (.0098)
G = BHP ÷ TVD
= 4734 psi ÷ 8202 ft = .577 psi/ft
= 32,585 kPa ÷ 2500 m = 13.03 kPa/m
G = MW x K
= 11.1 ppg x 0.052 = .577 psi/ft
= 1330 kg/m3 x 0.0098 = 13.034 kPa/m
12
The well as a ‘U-Tube’
The primary concept of well control is that we can describe the pressure behavior of
the well as a ‘U-Tube’, with the work string as one leg and the annulus as the other.
If both legs are filled with fluid of the same density, the Fluid level is same on both
sides, Hydrostatic pressure is the same on both sides, and there is No potential for
flow from one leg to the other.
13
The well as a ‘U-Tube’
In a U-tube and in the well, the fluid columns try to achieve balance. Suppose we
fill the annulus with a heavier fluid, say 11 pounds per gallon. The annulus is filled
with fluid that weighs only 10 pounds per gallon. We can calculate the pressure at
the bottom of each fluid column using the equation from a previous slide. The result
shows that, before balance, the work string side exerts 5720 psi at the bottom,
compared to only 5200 psi on the annulus side. We would say that there is a 520
psi pressure differential from the work string to the annulus. If we put the system in
motion, flow would immediately occur from the work string side to the annulus side,
until balance is reached.
A key point to remember is that when balance is achieved, the height of the heavy
side is less than the height of the lighter side. One way to look at it is that it takes
more of the lighter fluid to balance the heavier fluid. Imagine a balance-beam scale.
It would take a huge pile of feathers on one side to balance a small piece of lead on
the other.
14
Types of Pressure
Hydrostatic pressure
<- Pressure exerted by the fluid
column in the wellbore
Formation pressure
<- Hydrostatic pressure exerted
by fluids in the formation
15
Types of Formation Pressure
Normal
– Equal to a column of water
– 0.468 psi/ft, 9.0 PPG, or 1.08
SG
Subnormal
– Less than the pressure
exerted by a full column of
water
Abnormal
– Overpressure, geopressure
– Greater than normal pressure
– Up to EMW of 19.9 PPG
Formation pressure varies with the depth of the hole and other geologic conditions.
Formation Pressure can be determined by shut-in drill pipe pressure (SIDPP), or
measured using an MWD recorder or a wireline pressure bomb.
16
Operating Pressures
slide
17
Circulating Pressure Losses
Friction is resistance to
movement
It takes force to get a stationary
object to move
– Suppose it takes 50 psi to move
fluid up the annulus
When pump is running, it adds 50psi
to the hydrostatic column at bottom
When pump is shut off, BHP is
reduced 50 psi
Annulus pressure loss is the pressure required to move fluid up the annulus. It
typically ranges from 40 to as much as 200 psi. The important thing to remember is
that when the pump is running, the APL is added to BHP. When the pump is shut
off, the 50 psi is no longer available and BHP is reduced by 50 psi. This can be the
difference that allows the well to become ‘underbalanced’ and for a ‘kick’ to occur
(formation fluids enter the wellbore).
18
Circulating Pressure Losses
Example
This is an example of the pressures and pressure losses in an active pumping well.
In a static well, the BHP is 5200 psi (see next slide for calculation).
19
Pressure Calculations
Static Pressure
Hydrostatic pressure at any point in the fluid column
P = TVD x MW x K where
P = pressure, psi (kPa)
TVD = true vertical depth, ft (m)
MW = mud weight or fluid density (PPG) (kg/m3)
K = .052 (.0098)
We can calculate the hydrostatic pressure exerted by the weight of the fluid column,
considered at any point in the fluid column. Using the example of the previous
slide, the static bottom hole pressure is 5200 psi.
20
Circulating Pressure Losses
Example
1. Circulating pressure losses can exceed 2,400 psi
When the pump is shut off, the surface pressure at the pump is 0 psi and the
surface pressure at the return line is also 0. When the pump is on and the well is
circulating, the surface pressure at the pump is 2,400 psi, but the pressure at the
return line is still zero (unless the well is being controlled with choke back-pressure).
The 2,400 psi of pumping pressure has been expended in moving fluid through the
system: 650 psi friction loss in the work string, 1700 psi through the bit nozzles, and
50 psi to move fluid up the annulus. As the mud spills out of the return line, the
pressure is zero.
If the well were being controlled with the choke, we would add choke back-pressure
to the pumping losses (and the pump pressure would be higher by that same
amount).
We calculated the static BHP as 5200 psi. When the well is pumping, the BHP is
5250 psi (adding the APL).
21
Circulating Pressure Losses
Example
1. Circulating pressure losses can exceed 2,400 psi
2. When the pump stops, annulus BHP is reduced 50 psi
Remember, when the pump stops, BHP is reduced by 50 psi (the annulus pressure
loss).
22
Differential Pressure
23
Outline
1. Pressure and Basic Calculations
» 2. Review: Well Control fundamentals
3. Review: Well Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
9. Well control situations during workovers
24
Kick Fundamentals
The most important principle in well control is the definition of a ‘KICK’. A ‘Kick’ is an
unwanted flow of formation fluids into the wellbore. The formation fluids may be
Water, gas, or oil; and it Occurs when well is ‘underbalanced’, that is, BHP is lower
than formation pressure. The TWO most important aspects to remember are that
flow from the formation into the wellbore, unless counter-acted, will continue until
the two pressures are equalized, and that formation fluids are usually lighter than
fluids in the wellbore, and with the introduction of lighter fluids BHP is reduced
further, which allows more inflow, which reduces BHP further, etc etc - it’s a vicious
cycle.
25
Cause of Kicks
26
Reasons for Insufficient
Hydrostatic pressure
Let’s summarize the ways that hydrostatic pressure can be reduced and a ‘kick’
encountered.
27
Reasons for Insufficient
Hydrostatic pressure
28
Reasons for Insufficient
Hydrostatic pressure
29
Reasons for Insufficient
Hydrostatic pressure
Equipment failure
Rig and well equipment designed to control
pressures can fail due to corrosion or fatigue
Human Error
Poor judgment, lack of attention, poor training
cause mistakes in well operation
30
Kick Warning Signs
Pit Gain
– Pit-
Pit-level device registers
increase in flow from the
well
The Number One warning sign of formation inflow is called ‘Pit Gain’. Under normal
circumstances, the amount of fluid circulated into the well will equal the volume
coming out. Any increase is almost always due to formation fluid inflow. Any
difference in mud volume is measured by level, volume, or rate measuring devices
in the mud tanks.
31
Kick Warning Signs
Flow Check
– Stop circulating, check for
continued outflow from
well
A surefire way to check for inflow is with a flow check. Simply shut in the mud
pump – if there is flow still coming from the return line, you are experiencing a kick.
32
Kick Warning Signs
When a stand of pipe is pulled from the well, the fluid level in the well goes down to
reflect the amount of fluid displaced by the pipe. For purposes of well control, it is
important to refill the well when pipe is pulled. The amount refilled should
correspond to the volume displaced by the pipe. If the well takes less to fill up, it
may be an indication that formation fluid is entering the wellbore.
33
Kick Warning Signs
34
Kick Warning Signs
35
Gas behavior in Kicks
If the kick fluids are composed of liquids such as salt water or oil, the kick can be
controlled fairly easily. The real problems in well control arise when the fluids are
gas. As gas migrates up the annulus, it expands as depth (and confining pressure)
becomes less. As the gas expands, it exerts a greater pressure. If not controlled,
the increasing pressure can rupture casing or cause ‘underground blowouts’. We’ll
talk about underground blowouts in a few slides.
36
Gas behavior in Kicks
An even greater danger is gas DISSOLVED in the drilling fluids. Dissolved gases
don’t show the warning signs of a ‘kick’ until they are near the surface, when they
come out of solution and begin to expand like conventional gas kicks. There is
much less time to recognize and react to a ‘dissolved-gas’ kick.
37
Gas behavior in Kicks
These factors affect the amount of annulus pressure increase during gas kicks.
38
Gas behavior in Kicks
39
Underground
Blowout
Increasing gas pressure in
annulus exceeds fracture
pressure of another formation
Usually shallowest, uncased zone
Fracture pressure increases with depth
40
Underground Blowout
Shallow underground
blowout offshore
Gas migrates to surface
Capsize rig or drillship due to
reduced density of frothy water
Fire risk, can be uncontrolled
Underground Blowouts
very difficult to control
– May require relief well
Offshore, the situation becomes even more critical. Not only is there the risk of fire,
but the reduction in water density due to gas frothing can capsize a drill ship or
platform.
41
Barriers to Kicks
It’s important to consider the ‘barriers’ that protect us from ‘kicks’. The primary
barrier in any well operation is the ‘overbalance’ provided by drilling or other
workover fluids. The fluid system density can also be changed to prevent or stop
formation fluid inflow. If the primary barrier fails, there is a wide range of equipment
commonly used on rig sites to shut in the well and control inflow. Furthermore, a
series of well control ‘procedures’ have been tested and developed over the years
that allow us to circulate out the kick, prevent additional inflow, and resume normal
operations.
42
Outline
43
Barriers to Kicks
Well-control equipment is the second barrier we utilize to prevent and control the
inflow of formation fluids.
44
BOP Stack Assemblies
Blowout Preventers, also called BOPs, are the first thing we think of as well-control
equipment. There are 3 basic types of BOPs: Annular Preventers, Pipe rams, and
Blind rams.
45
BOP stack components
Annular Preventer
– Top of stack
46
BOP stack components
Pipe Ram
– Sized to close around
pipe of a specific
diameter
– Usually several sizes of
pipe and pipe rams
– Will not close on tool
joint
47
BOP stack components
48
BOP stack components
Blind rams
– Features large elements that
close on open hole ->
‘Shear’
Shear’ rams
– Have special blades that can cut
through any size well tubulars in
an emergency
‘Blind-
Blind-Shear’
Shear’ rams ->
– Special blind ram that
incorporates a shear
– Cuts, also seals open hole
49
BOP Operating Units
Hydraulically
operated closing
systems
– 3,000 psi closing
pressure
– Air-
Air-pressurized
cylinders contain
hydraulic fluid
– Control panel ->
on module or rig
floor
The operating module provides the hydraulic pressure to close and open the
blowout preventers. The system consists of several bottles or cylinders (called
‘accumulators’) that contain hydraulic fluid under up to 3000 psi pressure.
Triggered by operating controls on the module or on a remote control panel on the
rig floor, the pressurized fluid provides the force to operate the annular and ram
preventers. As the cylinders are depressurized, an air pump automatically starts to
re-pressurize them.
50
BOP Testing
51
Kelly Cock safety valve
Full-opening safety
valve
– Made up to top of
work string
– Isolates tubing
52
Choke Manifolds
53
Downhole safety valves
– Spring-
Spring-type, simple
flapper, and pump-
pump-down
54
Outline
55
Barriers to Kicks
The third set of barriers to kicks are well-control techniques that circulate out the
kick, prevent further inflow, and resume safe operation.
56
Shut in the well
The first and primary reaction to a kick is to shut in the well. Shutting in can help to
stop the inflow from the formation if the pressures can find equilibrium. Most
important, shutting in serves to protect the crew and rig from the effects of a
possible blowout.
57
Typical shut-in procedures
These are the steps in a typical shut-in procedure, when pipe is on bottom and well
is circulating. Note that this procedure uses a ‘soft’ shut-in, in that the choke is
open when the BOP is closed. A ‘hard’ shut-in happens when the choke is closed –
it is a little quicker but increases the risk of fracturing an intermediate formation.
58
Review: Well Control
Techniques
Purposes of shut In
Stop the inflow from the formation
Protect the crew and rig
» Measure key pressures
– SITP and Annulus (casing) pressures
Diagnose and organize the Kill procedure
59
Measure Key pressures
After the well is shut in, measure the shut-in tubing pressure, also called SIDPP for
‘shut-in drill-pipe pressure’. Whatever you call it, the pressure should stabilize
within 5 minutes or so. SITP is the key to determining the formation pressure that
has caused the ‘overbalance;’ and inflow. If the tubing is on bottom, calculate BHP
from the mud weight, and add the SITP you recorded.
60
Measure Key pressures
SITP also allows a calculation for a new mud weight to counteract the formation
pressure and bring the situation back into balance.
61
Measure Key pressures
Low or No SITP
– Reasons
Gauges shut off
Float or safety valve in tubing
Gauge scale too high
Well has no or little pressure
If there is no SITP shown on the standpipe gauge, try these actions to diagnose the
problem.
62
Measure Key pressures
SICP, or annulus pressure, should also be measured, and there are several
methods to try to calculate the ‘kick density’, that is whether oil, gas, or water.
Almost all company procedures require that you treat EVERY kick as gas, however,
and take the appropriate actions instead of trying to calculate a density.
63
Review: Well Control
Techniques
Purposes of shut In
Stop the inflow from the formation
Protect the crew and rig
Measure key pressures
– SITP and Annulus (casing) pressures
» Diagnose and organize the Kill procedure
The third step for shut-in is to allow you to diagnose and organize the procedures to
bring the well back into balance with formation pressure.
64
Review: Well Control
Techniques
65
Review: Well Control
Techniques
66
Review: Well Control
Techniques
The basic objective of all control methods is to bring the well back into balance with
formation pressure. To achieve that balance, a new mud weight is necessary to
provide the additional BHP to counteract the new formation pressure that caused
the kick. The new mud of increased density is called ‘Kill-Weight Mud’.
67
Review: Well Control
Techniques
Driller’s method
– Hold casing pressure
constant as pump is
brought up to ‘kill rate’
rate’, to
determine ICP
– Pump at kill rate, holding
FTP constant using choke
adjustment
– Calculate KWM, tubing
capacity, strokes to bit
Here are the basics of the Driller’s method. A worksheet is used to calculate the
key parameters of the circulating program.
68
Review: Well Control
Techniques
Driller’s method
– Advantages
Simple, few calculations
Circulation starts immediately
– Disadvantages
Highest surface pressures if gas kick
– KWM not used to circulate kick; all control pressure is
choke pressure
– Highest risk of ‘Underground Blowout’
Blowout’
Longest time to kill (2 complete circulations)
69
Review: Well Control
Techniques
‘Wait & Weight’ method
– Prepare Kill-
Kill-weight mud
– Circulate KWM as kick
circulated out
– Constant pump rate,
rate, but
pump pressure decreases as
heavier mud replaces lighter
– Casing pressure increases as
kick circulated, but BHP kept
constant using choke
Graph of DPP versus time,
DPP corrected with choke
The ‘Wait and Weight’ method uses a combination approach – the mud weight is
increased to kill weight and pumping begins. As the new mud displaces the older,
lighter mud in tubing, the BHP increases gradually and proportionally.
70
Review: Well Control
Techniques
– Disadvantages
‘Wait’
Wait’ for full load of KWM to be mixed
More complex procedure to design and operate
The name of the method comes from having to ‘Wait’ to mix an entire new batch of
kill-weight mud (‘Weight’) before pumping starts.
71
Review: Well Control
Techniques
‘Concurrent’ method
– Combination of ‘Driller’
Driller’s and ‘Wait’
Wait’
Mud weighted up in series of steps,
rather than KWM all at once (as in
‘Wait’
Wait’ method)
– Constant pump rate,
rate, but pump
pressure decreases as heavier
mud replaces lighter
Graph of DPP versus time is
complicated by periodic increases in
mud weight
– Casing pressure increases as kick
circulated, but BHP kept constant
using choke
Projected DPP corrected with choke
72
Review: Well Control
Techniques
‘Concurrent’ method
– Advantages
Starts sooner than ‘Wait’
Wait’ method
Potential for less surface pressure than ‘Driller’
Driller’s but
not as good as ‘Wait’
Wait’
– Disadvantages
Even more complicated to design and operate than
‘Wait’
Wait’ method
Mud weighting in steps must not compromise mud
quality
73
Review: Well Control
Techniques
– Reverse Circulation
Circulates down annulus, up tubing
Better control of surface pressures in drill pipe
Circulating up through bit jets is slow, maybe slower
than gas percolation in annulus
There are several modifications and additions to the 3 control methods. The most
common are these two.
74
Review: Well Control
Techniques
Special Considerations
– Pipe off bottom (or out of hole)
Run pipe in, by stripping or snubbing (next slide)
– Off-bottom Kill
KWM calculated using TVD to bottom of tubing,
not bottom of hole (results in heavier mud)
More risk of lost circulation, underground blowout
If a kick occurs when the pipe is off-bottom, most procedures specify that pipe be
run into the hole to bottom. For a kick that occurs when the pipe is not on bottom,
the procedures are the same except that the density of the kill mud is calculated to
the bottom of tubing, not to total well depth. Off-bottom kills are more risky than
having the pipe on the bottom, because there is more hole exposed to potential
inflow and the risk of fracturing an intermediate formation is greater.
75
Stripping and Snubbing
If a kick occurs when the pipe is off-bottom, most procedures specify that pipe be
run into the hole to bottom. If there is not enough pipe in the hole to ‘pull’ it down
against pressure by using the weight of the pipe, then a ‘Pipe Light’ scenario
occurs. In a ‘pipe light’ situation, BHP is sufficient to force or float the pipe out of
the well. In this situation, it becomes necessary to ‘Snub’ the pipe, mechanically
force the pipe downward into the hole against a greater, upward-acting pressure.
76
Outline
The following section is a summary of workover and completion operations, and the
well-control aspects associated with each.
77
Completion and Workover
Completion
Preparing a well to produce oil and gas
Establishes one or more flow paths for the efficient
production of reservoir fluids
Workover
After completion, any operation to restore or
increase production, or to abandon temporarily or
permanently
Completion is performed once, before the well is put into service. After the well is
initially completed, workovers may be necessary to repair the well, restore or
increase productivity, or abandon the well.
78
Types of Completions
Conventional
– Casing set and
cemented through pay
zone
– Perforated casing
– Packer on tubing, set
above pay zone
– 75% of onshore wells
79
Types of Completions
Packer
– Mechanical device with
sealing element
– Seals OD of tubing to ID
of casing
– Creates ‘tubing-
tubing-casing’
casing’
annulus, usually filled
with corrosion-
corrosion-inhibiting
fluid
‘annulus’
annulus’ or ‘packer’
packer’ fluid
80
Types of Completions
Dual completion
– Separate flow paths for
2 pay zones in one well
– Casing set and
cemented through 2 pay
zones, perforated
– 2 tubing strings
– Dual-
Dual-string and single
packers, set above pay
zones
As we’ll see in detail in the following section, a ‘Blast joint’ is specially reinforced
pipe, to resist the abrasion effects of sand produced from the shallower production
zone.
81
Types of Completions
82
Types of Completions
Tubingless completions
– Open hole (‘
(‘barefoot’
barefoot’) ->
– Cased hole perforated (below)
– No tubing or packer,
production flow is up casing
– Casing as small as 3.5”
3.5”
– Sometimes ‘packerless’
packerless’
Has tubing, but no packer
83
Types of Completions
Pumping wells
‘Sucker rod’
rod’ pump completion
84
Types of Completions
85
Types of Completions
86
Completion and Workover
Workover objectives
Control water, gas, or sand production
Repair mechanical problems
Stimulate the reservoir and increase production
Re-
Re-complete into additional or new reservoir
Plug and Abandon (‘(‘P&A’
P&A’) the well
Completion is performed once, before the well is put into service. After the well is
initially completed, workovers may be necessary to repair the well, restore or
increase productivity, or abandon the well.
87
Workover
During the life of an oil well, the interface between oil and water zones may change
(or the well may have been improperly completed from the beginning). A common
scenario is ‘up-coning’ of the oil-water interface due to changes in reservoir
pressure or increased production rates. Once water has ‘wetted’ the pores near the
wellbore, water will be produced in preference to oil. The oil is still there - It just
can’t flow into the wellbore. Workover solutions usually involve treatment chemicals
to restore oil permeability, squeeze-cementing the lower perforations, or re-
completing the well higher in the zone.
88
Workover
Similarly, the interface between gas and oil zones may change with time and
production. A common scenario is gas short-circuiting to the oil perforations.
Workover usually involves squeeze-cementing the upper perforations or re-
completing the well lower in the oil zone.
89
Workover
90
Completion and Workover
91
Workover
Perforating
– Completion or workover
– Primary tool for water
control
– Jet-
Jet-charge guns run on
wireline, coiled tubing, or
tubing
– ‘Underbalance’
Underbalance’ BHP during
perforating
92
Workover
Squeeze cementing
– Excludes water or gas zones from the well
– Allows a new zone to be completed
– Repairs damaged or corroded casing
– Correct problems with the primary cement
job
– Squeezed through perforations to emplace
behind casing
93
Workover
Squeeze cementing
– Usually special squeeze-
squeeze-
tool run on work string
– Has packer(s) to isolate
zone in casing
– Tool positioned above or
astride zone to be
cemented
– Cement pumped, then
excess reversed out
94
Workover
95
Workover
Drill-stem testing
– Setting a temporary completion to determine the productivity of a zone
– Zone isolated with packer and downhole valve
– Flow to surface, then valve closed and pressure build-
build-up recorded
96
Workover
Acidizing
– Clean up mud invasion and/or dissolve minerals to
improve zone permeability near the wellbore
97
Workover
Fracturing
– Pumping fluid into a zone
until the fracture pressure is
exceeded; zone ‘breaks
down’
down’ and fracture created
– Fracture then filled with
plastic beads or sand to
‘prop’
prop’ open
– Fractures are vertical and
extend from the wellbore as
‘wings’
wings’
– Radical increase in drainage
and permeability near well
98
Workover
Sand control
– Production of sand a major
problem in some areas,
some reservoirs
– Cleanout involves washing
in with hi-
hi-gel fluid
– Recompletion techniques
to prevent sand inflow
Simple perforation allows
sand into wellbore
Gravel-
Gravel-packing most
common
99
Sand control
Some completions use screen or slotted liner only
Screen liner with gravel pack
Perfs washed to remove sand; sized gravel or beads
pumped to bottom; screen or slotted liner washed in
100
Workover
Plugback
– Moving the producing interval from a deeper to a
shallower one
– Wellbore below the new zone is plugged and
abandoned
Old perforations squeezed off
Cement plug and/or permanent packer to ‘plug-
plug-back’
back’ depth
(new well TD)
Deepening
– Upper perfs squeezed off, new zone drilled out
– Liner hung and cemented off old casing
– New, deeper zone perforated and put on production
101
Workover
Sidetracking
– Another way to abandon or
bypass the lower part of a well
Damaged casing, permanent
junk, or skin-
skin-damaged zone
– Cut casing window, then a
whipstock packer used to
direct drilling off-
off-axis
– Plugback old well; liner hung
and cemented off old casing
– New zone perforated and put
on production
102
Workover
Plugging
– Well abandoned for mechanical or
economic reasons
– All States have plugging regs and
requirements
– Perforations squeezed
– Plugs set to prevent:
Migration from one zone to another
in the wellbore
Contamination of freshwater
Blowouts after casing deteriorates
103
Outline
The fluids used in workover and completion include water- and oil-based muds, as
well as a variety of brines, foams, and treating chemicals.
104
Fluid systems
Workover fluids
For perforating, cementing, fracturing etc
Gases, brines, muds, acids, gels, foams, etc.
Packer fluids
Annulus fluids that are non-
non-corrosive, may feature
other properties; must be stable for life of well
Completion fluids
Designed to prevent damage to formation
permeability during completion
105
Fluid systems
Fluid characteristics
Dense enough to control well pressures, but not so
heavy to fracture formation
Cost effective; many fluids available for different
purposes
Non-
Non-corrosive, non-
non-reactive, stable
Free of solids
Not hazardous to personnel if handled correctly
106
Fluid functions
Circulate materials
IN: cement, pills, gravel and sand, frac materials
Out: used cement, cuttings, debris and sand, etc.
Pressure control
Well must be killed for workover or completion
107
Fluid functions (cont’d)
108
Types of Fluids
109
Types of Fluids
Oil-Emulsion fluids
– Oil-in-water emulsion commonly uses diesel
Emulsifying agents make stable
Heavier than diesel, but still non-
non-reactive and
formation-
formation-friendly
– ‘Inverse’ emulsion is water droplets in oil
More physically stable, but breaks down over 200°
200° F
110
Types of Fluids
Water-based fluids
– Brines
Sodium, calcium, and
potassium chloride salts
Calcium and zinc bromide
add weight to solutions for
pressure control
Salt saturation can cause
crystals to form
– Muds
Inexpensive but solids a problem
Brines make an excellent completion and workover fluid, and they are very
inexpensive and easy to produce and handle. Bromide salts allow the brine to be
‘weighted’ for pressure control and killing the well initially.
111
Types of Fluids
Water-based fluids
– Acids
Water-
Water-diluted acids (5% - 25%) for permeability
enhancement near wellbore
– Hydrochloric (HCl) dissolves limestone (and carbonate
cements in sandstones)
– Hydrofluoric (HF), called ‘mud acid’
acid’, dissolves mud-
mud-solids
invasion of pores
– Acetic and formic acids (H or CH3 COOH) dissolve asphalts,
paraffin, and other oil solids blocking pores
112
Types of Fluids
Water-based fluids
– Foams
Requires ‘foaming agent’
agent’
Foam is an emulsion; fluids
uniformly distributed, do not
separate easily
Has structure and strength:
– bubbles of gas surrounded by
liquid film
– water around gas forms 12-
12-sided
structure (deforms but does not
shear when pumped)
113
Foam fluid systems
Compared to water and mud, foam has a much higher capacity to lift cuttings, sand,
and debris. This enhanced capacity is probably due to the unique structure of the
water molecules in foams, which deforms during flow but does not shear. A greater
capacity to lift solids means that a lower pumping rate and lower annular velocity is
necessary to lift cuttings. Typical pumping rates in foam systems are as low as 20
gallons per minute of water and 266 cubic feet of gas per minute to achieve normal
120 feet per minute annular velocity, 10-times better hydraulic performance than a
typical mud system.
114
Types of Fluids
Plugs and pills are dense fluid/solid mixtures. They are ‘spotted’ into tubing, casing,
or open-hole and act like temporary plugs to control flow or pressure.
115
Types of Fluids
116
Types of Fluids
‘Soft’
Soft’ Plugs (pumpable): Examples of polymer gel plugs
117
Types of Fluids
118
Types of Fluids
Packer fluids
Provides formation pressure control
Prevents casing collapse, tubing burst
Prevents corrosion, stable for life of well
Compatible with seal elements
– Typical fluids
Brines with commercial additives (75%)
Diesel or crude oil
119
Outline
120
Production
pressure control
121
Production pressure
control equipment
Christmas Tree
First device
encountered
during workover
Assembly of
valves, spools, and
flanges that
control pressure
and the flow of
fluids from the well
122
Wellhead
Christmas tree
– Control assembly set
above the ‘wellhead’
123
Wellhead
Casing hanger
Slips-
Slips-and-
and-seal assembly
from which the casing
string is suspended
Tubing hanger
Suspends the tubing
string, seals off the
upper casing annulus,
and allows flow to the
tree
Valves
Allow access to casing
and tubing annuli
124
Component
parts of
a wellhead
125
Component Heads and
Hangers
Casing Tubing
126
Wellhead
Casing hanger
Slips-
Slips-and-
and-seal
assembly from which
the casing string is
suspended
Tubing hanger
Suspends the tubing
string, seals off the
upper casing
annulus, and allows
flow to the tree
127
Christmas Tree
Master valve
Primary shut-
shut-off valve
Wing valve
Flow control valve
Choke
Adjusts the amount of
flow from the well
Crown or swab valve
Allows access for
wireline etc.
128
Removing the Tree
129
Casing
A well’s construction
program usually consists of
several sizes and lengths of
steel casing
– Casing is run from the surface
(and cemented)
130
Liners
131
Tubing and packer
Tubing
– Conducts flow from pay zone to surface
– May be pulled for workover, replaced
with ‘work string’
string’
Packer
– Mechanical device with sealing element
– Seals OD of tubing to ID of casing
– Creates tubing-
tubing-casing annulus, usually
filled with corrosion-
corrosion-inhibiting fluid
‘annulus’
annulus’ or ‘packer’
packer’ fluid
132
Removal of Packers
Retrievable Packers
– For workover, packer is removed
using
Hydraulic: hydraulic pressure to
seat/unseat
Mechanical: rotation and/or pull
Wireline and slickline: set and
retrieved using remote methods
Permanent Packers
– Must be milled out
133
Seal Nipples
134
Bridge Plug
135
Miscellaneous tools
136
Miscellaneous
tools
Sliding Sleeve ->
– Wireline-
Wireline-actuated port that
allows circulating from
tubing into casing
– For treatment, well kill, etc.
Mandrels
– Usually for gas lift, allows
injection from casing into
tubing
– Usually several at bottom
in gas-
gas-lift well
137
Miscellaneous tools
138
Miscellaneous
tools
Sliding Sleeve ->
– Wireline-
Wireline-actuated port that
allows circulating from
tubing into casing
– For treatment, well kill, etc.
Mandrels
– Usually for gas lift, allows
injection from casing into
tubing
– Usually several at bottom
in gas-
gas-lift well
139
Miscellaneous tools
140
Miscellaneous tools
141
Miscellaneous tools
Packer mills
– For removal of ‘permanent’
permanent’
packers and cement retainers
– Cuts only the packer slips
– A ‘picker’
picker’ latches into the
packer body for retrieval
142
Outline
1. Review: Pressure and Basic Calculations
2. Review: Well Control Fundamentals
3. Review: Well Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
» 8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
9. Well control situations during workovers
143
Conventional workover rig
Self-propelled
(highway or barge)
Capabilities:
– Pressure control
– Tripping
– Rotate
– Circulate
144
Conventional workover rig
Hoisting system
– Derrick
– Drawworks
– Crown block
– Traveling block
– Wire rope
– Hook and elevators
145
Conventional workover rig
Rotating systems
– Rotation necessary to
Drill cement
Place packers or plugs
Mill
Fish
Set downhole tools
146
Conventional workover rig
147
Conventional workover rig
Power swivel
– Light duty workover
operations
– May use rig’
rig’s hydraulic
system or portable power
unit
Skid or trailer mounted
148
Conventional workover rig
Circulating system
– Pumps
– Lines
– Standpipe
– Rotary hose
– Swivel
– Kelley
– Shale shaker
– Tanks and/or pits
– manifolds
149
Conventional rig pressure
control
150
BOP stack components
Annular Preventer
– Top of stack
151
BOP stack components
Pipe Ram
– Sized to close around
pipe of a specific
diameter
– Usually several sizes
pipe/pipe rams
– Will not close on tool
joint
152
BOP stack components
153
BOP stack components
Blind rams
– Features large elements that
close on open hole ->
‘Shear’
Shear’ rams
– Have special blades that can cut
through any size well tubulars in
an emergency
‘Blind-
Blind-Shear’
Shear’ rams ->
– Special blind ram that
incorporates a shear
Cuts, and seals open hole
154
BOP Operating Units
Hydraulically
operated closing
systems
– 3,000 psi closing
pressure
– Air-
Air-pressurized
cylinders contain
hydraulic fluid
– Control panel ->
on module or rig
floor
The operating module provides the hydraulic pressure to close and open the
blowout preventers. The system consists of several bottles or cylinders (called
‘accumulators’) that contain hydraulic fluid under up to 3000 psi pressure.
Triggered by operating controls on the module or on a remote control panel on the
rig floor, the pressurized fluid provides the force to operate the annular and ram
preventers. As the cylinders are depressurized, an air pump automatically starts to
re-pressurize them.
155
BOP Testing
156
Kelly Cock safety valve
Full-opening safety
valve
– Made up to top of
work string
– Isolates tubing
157
Choke Manifolds
158
Wireline workover
159
Wireline workover
Wireline workovers
– Setting and retrieving equipment
gas lift valves, chokes, plugs, packers, etc.
– Fishing and jarring
– Logging and sampling
– Perforating
– Spot treating or spot cementing
Wireline ‘basket’
basket’ dumps chemicals or cement
at selected interval
– Bailing and paraffin cutting
Sand bailer at right ->
160
Wireline workover
161
Wireline workover
162
Coiled Tubing workover
163
Coiled Tubing workover
Capabilities:
– Pressure control
– Tripping (no connections)
– Circulate
– No rotate BUT downhole
rotating tools are available
Advantages
– Faster, cheaper, self-
self-
contained
164
Coiled Tubing workover
Advantages (cont’d)
– Because it is not jointed,
coiled tubing can be run at
much faster speeds into or
out of a well
165
Coiled Tubing workover
Disadvantages of coiled
tubing
– Only light drilling
– Tubing sizes limited
– Tubing collapse and
yield strength low
– In gas and H2S
environments, potential
for gas-
gas-filled tubing on
reel
166
Coiled Tubing workover
167
Coiled Tubing workover
CT pressure control
– Injector head
pulls/pushes tubing,
not reel
– Stripper assembly
Seal elements surround
the tubing, hydraulic
force provides seal
– BOP stack
Blind, cutter, slip, and
pipe rams
168
CT BOP – typical 15K ‘Quad
stack’
Injector Head
169
Hydraulic Workover Unit
170
Hydraulic Workover Unit
Advantages (cont’d)
– Heavier pipe than CT
unit
– Rotary table for drilling
Disadvantages
– Slower trips, because
all pipe must be
snubbed into well
– Procedures generally
more complicated
171
Hydraulic Workover Unit
HWO workovers
– Pressure control
– Fishing and milling
– Drilling cement and bridge plugs
– Acidizing, jetting, and chemical
treating
– Squeeze cementing, plugback, and
P&A
– Sand washing and consolidation
treatments
– Perforating (underbalanced)
172
Hydraulic Workover Unit
173
Hydraulic Workover Unit
– Equalizing loop
Adjusts pressure between
stripper rams
174
Outline
175
Well control during
workovers
Work string off-bottom
Quicker reaction means less difficult situation
176
Well control during
workovers
177
Well control during
workovers
Stripping in using RAM preventers
1. Measure carefully between the pipe rams, and adjust
closing pressures to 500 psi or less
2. With upper ram closed, lower the pipe until the tool
joint is 2 feet above the upper ram
3. Close the lower ram; bleed off the pressure between
the upper and lower rams
4. Lower the pipe until the tool joint is between the 2
rams; stop lowering and close the upper ram
5. Pressure up the space between the rams to well
pressure, and open the bottom ram.
6. Repeat steps 2- 2-5.
RAM preventers can be used for pipe stripping if annulus pressure is too high to
allow using an annular preventer, if rubbers on the tubing cannot be removed, or if
an annular preventer is inoperable or not available.
As in the method using an annular preventer, Maintain a constant SICP with choke.
If gas is migrating up the hole, bleed pressure using the volumetric method of Section 4. Every
stand should displace fluid; if not, circulation has been lost.
178
Well control during
workovers
179
Well control during
workovers
Hole in work string during kick circulation
FTP decreases but no decrease in FCP
Closing choke causes higher FCP but little
increase in FTP; higher FCP may cause other
problems
Hole exposes the tubing to pressure in
annulus
180
Well control during
workovers
Hole in work string during kick circulation
(cont’d)
1. Is hole above or below kick fluids?
If above kick, it may be difficult (or impossible) to
maintain constant BHP
Hole exposes the tubing to pressure in annulus
– If SITP is much higher than expected (or
SITP=SICP) and does not decrease when a
small amount bled from tubing = hole is likely
ABOVE the kick fluids
181
Well control during
workovers
182
Well control during
workovers
Hole in work string during kick circulation
183
Well control during
workovers
Hole in work string during kick circulation
184
Well control during
workovers
185
Well control during
workovers
Plugged work string during kick circulation
(cont’d)
2. Surging doesn’t clear the blockage, but tubing is
only partially plugged
A. Stop the pump and close the choke; record SITP
and SICP
B. Open the choke, start the pump, and bring the rate
up to the original ‘kill rate’
rate’ while keeping annulus
pressure constant
C. When the pump is up to ‘kill rate’
rate’, note FTP; this is
the new circulating pressure.
D. If this pressure is too high for the pumps to handle,
use a slower pump rate and repeat the steps.
186
Well control during
workovers
Plugged work string during kick
circulation (cont’d)
187
Well control during
workovers
188
Well control during
workovers
Hole in casing or Lost Circulation during
well control (cont’d)
Reasons for lost circulation:
Bad cement job at shoe
– can cause broaching to surface
Induced fractures
– may heal when pressure relieved
Vuggy or naturally fractured formations
– additional pressure during well control can
induce communication with an existing fracture
network
189
Well control during
workovers
190
Well control during
workovers
191
Well control during
workovers
192
Well control during
workovers
193
Well control during
workovers
Hole in casing or Lost Circulation during well
control (cont’d)
2. Well control with total or severe lost returns
F. If losses can not be stopped, use a barite or ‘gunk’
gunk’
plug in the wellbore to seal off the kick zone
• The ‘Kick’
Kick’ zone is most likely located below the ‘loss’
loss’ zone
• Mix a plug of 18 to 22 ppg barite or ‘gunk’
gunk’ (bentonite and
diesel), sized for 500 feet of tubing
• Spot the plug, then pull up above the plug, hold back-
back-pressure
on the annulus, and circulate
• Isolate the kick zone, then solve the Lost Circulation problem
194
Well control during
workovers
195
Outline
196
Well Control for Workover
and Completion
The End
Thank you for your attention
197