You are on page 1of 197

Well Control for Workover

and Completion

1
Outline

» 1. Review: Pressure and Basic Calculations


2. Review: Well Control fundamentals
3. Review: Well Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
9. Well control situations during workovers

We assume that you’ve already had a basic or advanced ‘Well Control’ course. We
will review most of the concepts from that course. If you haven’t had the well-
control course, you’ll be able to understand almost all the concepts and
fundamentals of well control, we just won’t go into great detail on the calculations
and work sheets used in those courses.

2
Pressure Basics

 Pressure is a force that is exerted on an


area.
– In US
 force = pounds; area = square inch
 Unit is pounds per square inch (psi)
– In Metric units
 Force per area = kiloPascal (kPa)

1 psi = 6.894 kPa

Pressure is

3
Hydrostatic Pressure

 Hydrostatic pressure is the force


exerted by a column of fluid
– Force caused by weight (density) of the
fluid
– Weight is in 1 direction; pressure is in all
directions

 A column of air 1” x 1” that is 60 miles


high = 1 atmosphere = ~14.7 psi =
100 kPa

Air is also a fluid. A column of air that measures 1” by 1” and is 60 miles high
weighs 14.7 pounds or 100 kPa. Another way of saying this is that the column
exerts a pressure of 14.7 pounds per square inch.

4
Hydrostatic Pressure

 Hydrostatic pressure is the force exerted


by a column of fluid
– Force caused by weight (density) of the fluid
– For liquids, in US oilfield
 Density unit is ‘Pounds per Gallon’
Gallon’ (PPG or ppg)
 Water weighs 8.33 pounds per gallon
– In Metric units
 Density unit is kg per cubic meter (kg/m3)
1 PPG = 119.8 kg/m3

In most cases in the oilfield, we’re talking about the hydrostatic pressure of liquids.
The most common oilfield unit of density is ‘Pounds per Gallon’, derived from the
old usage for mixing drilling mud. The equivalent metric unit is kilograms per cubic
meter.

5
Pressure Calculations

 Static Pressure
Hydrostatic pressure at any point in the fluid column
P = TVD x MW x K where

P = pressure, psi (kPa)


TVD = true vertical depth, ft (m)
MW = mud weight or fluid density (PPG) (kg/m3)
K = .052 (.0098)

We can calculate the hydrostatic pressure exerted by the weight of the fluid column,
considered at any point in the fluid column. An example is presented on the next
slide.

6
Example Static Pressure

Assume:
TVD = 8,202 ft (2500 m)
MW = 11.1 ppg (1330 kg/m3)

P = 8202 x 11.1 x 0.052 = 4,734 psi

= 2500 x 1330 x 0.0098 = 32,585 kPa

7
Hydrostatic pressure expressed
as Equivalent Mud Weight

EMW = BHP ÷ TVD ÷ K


where
EMW is expressed as (ppg or kg/m)
BHP = bottom hole pressure, psi (kPa)
TVD = true vertical depth, ft (m)
MW = mud weight or fluid density (PPG) (kg/m3)
K = .052 (.0098)

It is also common to express the weight of the fluid column as an ‘equivalent mud
weight’ rather than as psi. We say ‘equivalent’ mud weight because the fluid
column may not be composed of mud, but of water, oil, gas or other fluids, but the
pressure is stated as if the column were mud. Example on next slide.

8
Hydrostatic pressure expressed
as Equivalent Mud Weight

EMW = BHP ÷ TVD ÷ K


Assume:
BHP = 4734 psi
TVD = 8,202 ft (2500 m)
K = 0.052 (.0098)

= 4734 psi ÷ 8202 ft ÷ 0.052 = 11.1 ppg


or
32,585 kPa ÷ 2500 m ÷ 0.0098 = 1,330 kg/m3

9
Hydrostatic pressure expressed
as Equivalent Mud Weight

EMW = BHP ÷ TVD ÷ K


Assume:
BHP = 4734 psi
TVD = 8,202 ft (2500 m)
K = 0.052 (.0098)

How about the ‘atmosphere’ example?


EMW = 14.7 psi ÷ (60 x 5280) ÷ 0.052
Atmospheric pressure = about 0.0009 PPG

Here’s

10
Hydrostatic pressure expressed as
Hydrostatic Gradient

Average Gradient (G) as psi per foot of depth


(kPa/m)
G = BHP ÷ TVD
or
G = MW x K
Where
BHP = bottom hole pressure, psi (kPa)
TVD = true vertical depth, ft (m)
MW = mud weight or fluid density, PPG (kg/m3)
K = .052 (.0098)

Another way to express pressure is as an ‘Average Gradient’. The units we use are
‘psi per foot of depth’ or kPa per meter.
This is a simple calculation that assumes that the entire hydrostatic column is
composed of a homogeneous fluid, and that’s not always the case. On the other
hand, ‘Average Gradient’ is a convenient way to allow interpolating pressure
between depths.

11
Hydrostatic pressure expressed
as Hydrostatic Gradient
Assume:
kg/m3)
BHP = 4734 psi, TVD = 8,202 ft (2500 m), MW = 11.1 ppg (1330 kg/m
K = 0.052 (.0098)

G = BHP ÷ TVD
= 4734 psi ÷ 8202 ft = .577 psi/ft
= 32,585 kPa ÷ 2500 m = 13.03 kPa/m
G = MW x K
= 11.1 ppg x 0.052 = .577 psi/ft
= 1330 kg/m3 x 0.0098 = 13.034 kPa/m

12
The well as a ‘U-Tube’

 Think of the well as a U-Tube


 One leg is work string
 Other leg is annulus
– If both legs are filled with fluid
of the same weight,
 Fluid level is same on both sides
 Hydrostatic pressure same on both
sides
 No flow from one leg to the other

The primary concept of well control is that we can describe the pressure behavior of
the well as a ‘U-Tube’, with the work string as one leg and the annulus as the other.
If both legs are filled with fluid of the same density, the Fluid level is same on both
sides, Hydrostatic pressure is the same on both sides, and there is No potential for
flow from one leg to the other.

13
The well as a ‘U-Tube’

 Fluid tries to reach a balance


 11 ppg fluid in work string
 10 ppg fluid in annulus
 10,000 feet well
11 ppg x 10000 x .052 = 5720 psi
10 ppg x 10000 x .052 = 5200psi

 Heavier fluid creates pressure differential


 Heavier side causes flow to annulus until
balance
 Heavier side shorter than lighter side at
balance (takes more light fluid to balance)

In a U-tube and in the well, the fluid columns try to achieve balance. Suppose we
fill the annulus with a heavier fluid, say 11 pounds per gallon. The annulus is filled
with fluid that weighs only 10 pounds per gallon. We can calculate the pressure at
the bottom of each fluid column using the equation from a previous slide. The result
shows that, before balance, the work string side exerts 5720 psi at the bottom,
compared to only 5200 psi on the annulus side. We would say that there is a 520
psi pressure differential from the work string to the annulus. If we put the system in
motion, flow would immediately occur from the work string side to the annulus side,
until balance is reached.
A key point to remember is that when balance is achieved, the height of the heavy
side is less than the height of the lighter side. One way to look at it is that it takes
more of the lighter fluid to balance the heavier fluid. Imagine a balance-beam scale.
It would take a huge pile of feathers on one side to balance a small piece of lead on
the other.

14
Types of Pressure

 Hydrostatic pressure
<- Pressure exerted by the fluid
column in the wellbore

 Formation pressure
<- Hydrostatic pressure exerted
by fluids in the formation

1. Formation pressure is the force exerted by fluids in the formation. Some


engineers also refer to this as Pore pressure or reservoir pressure. Formation
pressure varies with depth and other geologic conditions.
2. Hydrostatic pressure is exerted by the fluid column in the wellbore. 3. Standpipe
pressure is measured at the top of the drill stem. 4.Choke Pressure is Annulus
pressure at the surface in a U-tube well scenario.

15
Types of Formation Pressure

 Normal
– Equal to a column of water
– 0.468 psi/ft, 9.0 PPG, or 1.08
SG
 Subnormal
– Less than the pressure
exerted by a full column of
water
 Abnormal
– Overpressure, geopressure
– Greater than normal pressure
– Up to EMW of 19.9 PPG

Formation pressure varies with the depth of the hole and other geologic conditions.
Formation Pressure can be determined by shut-in drill pipe pressure (SIDPP), or
measured using an MWD recorder or a wireline pressure bomb.

16
Operating Pressures

– Standpipe or tubing pressure


 required to move fluid down the
tubing/drill stem
– Annular pressure loss (APL)
 Pressure required to move fluid up
the annulus
– Choke pressure
 Annulus pressure at the surface in
a U-
U-tube scenario
– Pump circulating pressure
 required to circulate fluid through
the entire hole
 Includes standpipe, APL, and choke
pressures

slide

17
Circulating Pressure Losses

 Friction is resistance to
movement
 It takes force to get a stationary
object to move
– Suppose it takes 50 psi to move
fluid up the annulus
 When pump is running, it adds 50psi
to the hydrostatic column at bottom
 When pump is shut off, BHP is
reduced 50 psi

Annulus pressure loss is the pressure required to move fluid up the annulus. It
typically ranges from 40 to as much as 200 psi. The important thing to remember is
that when the pump is running, the APL is added to BHP. When the pump is shut
off, the 50 psi is no longer available and BHP is reduced by 50 psi. This can be the
difference that allows the well to become ‘underbalanced’ and for a ‘kick’ to occur
(formation fluids enter the wellbore).

18
Circulating Pressure Losses
Example

This is an example of the pressures and pressure losses in an active pumping well.
In a static well, the BHP is 5200 psi (see next slide for calculation).

19
Pressure Calculations

 Static Pressure
Hydrostatic pressure at any point in the fluid column
P = TVD x MW x K where
P = pressure, psi (kPa)
TVD = true vertical depth, ft (m)
MW = mud weight or fluid density (PPG) (kg/m3)
K = .052 (.0098)

P = 10,000 ft x 10.0 ppg x .052 = 5,200 psi

We can calculate the hydrostatic pressure exerted by the weight of the fluid column,
considered at any point in the fluid column. Using the example of the previous
slide, the static bottom hole pressure is 5200 psi.

20
Circulating Pressure Losses
Example
1. Circulating pressure losses can exceed 2,400 psi

When the pump is shut off, the surface pressure at the pump is 0 psi and the
surface pressure at the return line is also 0. When the pump is on and the well is
circulating, the surface pressure at the pump is 2,400 psi, but the pressure at the
return line is still zero (unless the well is being controlled with choke back-pressure).
The 2,400 psi of pumping pressure has been expended in moving fluid through the
system: 650 psi friction loss in the work string, 1700 psi through the bit nozzles, and
50 psi to move fluid up the annulus. As the mud spills out of the return line, the
pressure is zero.
If the well were being controlled with the choke, we would add choke back-pressure
to the pumping losses (and the pump pressure would be higher by that same
amount).
We calculated the static BHP as 5200 psi. When the well is pumping, the BHP is
5250 psi (adding the APL).

21
Circulating Pressure Losses
Example
1. Circulating pressure losses can exceed 2,400 psi
2. When the pump stops, annulus BHP is reduced 50 psi

Remember, when the pump stops, BHP is reduced by 50 psi (the annulus pressure
loss).

22
Differential Pressure

A key ‘Differential Pressure’ is the


difference between formation pressure
and bottom-hole hydrostatic pressure in
the well

– Balanced: BHP = formation pressure


– Overbalanced: BHP > formation pressure
– Underbalanced: BHP < formation pressure

‘Differential’ pressure is a comparison of two pressures. The most important


differential pressure is the comparison of formation pressure and bottom-hole
hydrostatic pressure in the wellbore.

23
Outline
1. Pressure and Basic Calculations
» 2. Review: Well Control fundamentals
3. Review: Well Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
9. Well control situations during workovers

24
Kick Fundamentals

A ‘Kick’ is an unwanted flow of formation


fluids into the wellbore
– Water, gas, or oil
– Occurs when well is ‘underbalanced’
 BHP is lower than formation pressure
– Inflow will continue until pressure is equalized
– Inflow further reduces BHP
 Formation fluids are usually lighter than well fluids
 Allowing more inflow, and so on

The most important principle in well control is the definition of a ‘KICK’. A ‘Kick’ is an
unwanted flow of formation fluids into the wellbore. The formation fluids may be
Water, gas, or oil; and it Occurs when well is ‘underbalanced’, that is, BHP is lower
than formation pressure. The TWO most important aspects to remember are that
flow from the formation into the wellbore, unless counter-acted, will continue until
the two pressures are equalized, and that formation fluids are usually lighter than
fluids in the wellbore, and with the introduction of lighter fluids BHP is reduced
further, which allows more inflow, which reduces BHP further, etc etc - it’s a vicious
cycle.

25
Cause of Kicks

 Well Control: maintaining


sufficient hydrostatic pressure in
the wellbore to prevent inflow

 The cause of a ‘Kick’ is


insufficient hydrostatic pressure
in the wellbore
– Failure to control inflow can lead
to a blowout

26
Reasons for Insufficient
Hydrostatic pressure

 Insufficient fluid weight (density)


 Wrong weight mud for conditions
 Diluted mud
 Changed over to completion fluids

 Failure to keep the hole full


 As the work string is pulled, the
volume of metal removed must be
replaced with correct fluid

Let’s summarize the ways that hydrostatic pressure can be reduced and a ‘kick’
encountered.

27
Reasons for Insufficient
Hydrostatic pressure

 Swabbing and Surging


 Moving the string too fast or too tight clearance
 Swabbing = pulling up
 Surging = tripping in
 Vacuum or pressure causes balance upset

 Lost Circulation ->


 If the weight of the fluid column is too great,
formation strength can be overcome
 Fluid leaks into weak formation, hydrostatic level
lowered, 2nd formation kicks

28
Reasons for Insufficient
Hydrostatic pressure

 Abnormal formation pressure


 Caused by faulted structures, salt domes, geo-
geo-
pressured shales, underground blowouts

 Obstruction in the wellbore


 Such as sand bridging or plug, can trap pressure
below the obstruction

29
Reasons for Insufficient
Hydrostatic pressure

 Equipment failure
 Rig and well equipment designed to control
pressures can fail due to corrosion or fatigue

 Human Error
 Poor judgment, lack of attention, poor training
cause mistakes in well operation

30
Kick Warning Signs

 Pit Gain
– Pit-
Pit-level device registers
increase in flow from the
well

The Number One warning sign of formation inflow is called ‘Pit Gain’. Under normal
circumstances, the amount of fluid circulated into the well will equal the volume
coming out. Any increase is almost always due to formation fluid inflow. Any
difference in mud volume is measured by level, volume, or rate measuring devices
in the mud tanks.

31
Kick Warning Signs

 Flow Check
– Stop circulating, check for
continued outflow from
well

A surefire way to check for inflow is with a flow check. Simply shut in the mud
pump – if there is flow still coming from the return line, you are experiencing a kick.

32
Kick Warning Signs

 Well not taking proper


amount of fill-up during
trip stands
– Stand removal requires
correct volume to replace
metal
– Less ‘fill’
fill’ volume than
normal may indicate inflow

When a stand of pipe is pulled from the well, the fluid level in the well goes down to
reflect the amount of fluid displaced by the pipe. For purposes of well control, it is
important to refill the well when pipe is pulled. The amount refilled should
correspond to the volume displaced by the pipe. If the well takes less to fill up, it
may be an indication that formation fluid is entering the wellbore.

33
Kick Warning Signs

 Sudden increase in drilling rate


 ROP may increase or decrease as over-
over-
pressured zone is penetrated

 Increased Pump speed, but decreased


Pump pressure
 Reduced annulus pressure causes imbalance,
pump speeds up
 Pump pressure decreases because less weight
to lift in annulus

34
Kick Warning Signs

 Change in gas type or gas increase


 Requires mud gas detector
 Trip gas, gas-
gas-cut mud

 Salinity change or water-cut mud


 Water inflow from over-
over-pressured zone

 Change in flow properties of fluid


 Monitor characteristics of mud or completion
fluid

35
Gas behavior in Kicks

 For a Gas kick


– Gas is lower density, migrates
up annulus
– Higher it migrates, more it
expands
– More it expands, higher
pressure on annulus
– If not adjusted, increasing gas
pressure can
 Exceed casing max rating
 Cause ‘Underground Blowout’
Blowout’

If the kick fluids are composed of liquids such as salt water or oil, the kick can be
controlled fairly easily. The real problems in well control arise when the fluids are
gas. As gas migrates up the annulus, it expands as depth (and confining pressure)
becomes less. As the gas expands, it exerts a greater pressure. If not controlled,
the increasing pressure can rupture casing or cause ‘underground blowouts’. We’ll
talk about underground blowouts in a few slides.

36
Gas behavior in Kicks

 Gas dissolved at BHP is an


even greater concern
 H2S dissolves in water-
water-based mud
 Methane dissolves in oil-
oil-based mud

 Behaves as liquid, not noticed


until expansion/pressure
increase occurs rapidly at
~3,000 feet
 No pit gain etc. until gas is high in
the annulus
 Much less time to recognize and
react

An even greater danger is gas DISSOLVED in the drilling fluids. Dissolved gases
don’t show the warning signs of a ‘kick’ until they are near the surface, when they
come out of solution and begin to expand like conventional gas kicks. There is
much less time to recognize and react to a ‘dissolved-gas’ kick.

37
Gas behavior in Kicks

 How large an annulus pressure increase due


to gas inflow?

 Greater the ‘underbalance’


underbalance’ = higher annulus pressure
 Larger kick volume = higher annulus pressure
 Lower density of kick = higher annulus pressure
 Deeper Well depth = higher annulus pressure
 Smaller diameter annulus = higher annulus pressure

These factors affect the amount of annulus pressure increase during gas kicks.

38
Gas behavior in Kicks

 If not adjusted and controlled,


rapidly increasing gas pressure
in the annulus can
 ‘Unload’
Unload’ the hole and cause
surface blowout
 Exceed casing max burst rating
 Cause ‘Underground Blowout’
Blowout’

39
Underground
Blowout
 Increasing gas pressure in
annulus exceeds fracture
pressure of another formation
 Usually shallowest, uncased zone
 Fracture pressure increases with depth

 Causes ‘short circuit’ of gas from


deep zone into shallower zone
 Ruins productive zone
 Overpressures shallow zone
 Can blowout to surface (craters, etc)

In a nutshell, an underground blowout is a pressure increase in the annulus that


causes a fracture in another formation, and allows the gas to flow into the
shallower formation. Is that a problem? Yes indeed, because at the very least you
are draining off the gas in the production zone. Remember that without intervention
the flow will continue indefinitely, until the pressures are equalized. Worst case,
however, is that gas flow to a shallow zone can cause migration to the surface, and
this can lead to uncontrollable fires and even craters under the rig.

40
Underground Blowout

 Shallow underground
blowout offshore
 Gas migrates to surface
 Capsize rig or drillship due to
reduced density of frothy water
 Fire risk, can be uncontrolled

 Underground Blowouts
very difficult to control
– May require relief well

Offshore, the situation becomes even more critical. Not only is there the risk of fire,
but the reduction in water density due to gas frothing can capsize a drill ship or
platform.

41
Barriers to Kicks

1. The circulating mud system


 Mud density must be maintained to ‘overbalance’
overbalance’ the formation
pressure
 In the event of a kick, the mud density must be adjusted to meet
the requirements for increased BHP

2. Equipment to shut-in the well


 Kelly cock, Annular preventer, BOP stack, choke, etc.

3. ‘Well Control’ techniques to circulate out the kick,


prevent further inflow, and resume safe operation

It’s important to consider the ‘barriers’ that protect us from ‘kicks’. The primary
barrier in any well operation is the ‘overbalance’ provided by drilling or other
workover fluids. The fluid system density can also be changed to prevent or stop
formation fluid inflow. If the primary barrier fails, there is a wide range of equipment
commonly used on rig sites to shut in the well and control inflow. Furthermore, a
series of well control ‘procedures’ have been tested and developed over the years
that allow us to circulate out the kick, prevent additional inflow, and resume normal
operations.

42
Outline

1. Review: Pressure and Basic Calculations


2. Review: Well Control fundamentals
» 3. Review: Well Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
9. Well control situations during workovers

In this section, we will review well control equipment.

43
Barriers to Kicks

1. The circulating mud system


 Mud density must be maintained to ‘overbalance’
overbalance’ the formation
pressure
 In the event of a kick, the mud density must be adjusted to meet
the requirements for increased BHP

2. » Equipment to shut-in the well


 Annular preventer, BOP stack, Safety valves, choke

3. ‘Well Control’ techniques to circulate out the kick,


prevent further inflow, and resume safe operation

Well-control equipment is the second barrier we utilize to prevent and control the
inflow of formation fluids.

44
BOP Stack Assemblies

 BOP stacks may be


configured in many
different ways
– Typical:
 Annular preventer
 Pipe rams
 Blind rams

 API RP53: Blowout


Prevention Equipment
Systems

Blowout Preventers, also called BOPs, are the first thing we think of as well-control
equipment. There are 3 basic types of BOPs: Annular Preventers, Pipe rams, and
Blind rams.

45
BOP stack components

 Annular Preventer
– Top of stack

– Can close around casing,


drill pipe, tool joints,
collars, the Kelly,
wireline, and open hole

46
BOP stack components

 Pipe Ram
– Sized to close around
pipe of a specific
diameter
– Usually several sizes of
pipe and pipe rams
– Will not close on tool
joint

47
BOP stack components

 Variable-bore pipe Ram


– Sized to close around a
range of pipe diameters

– Primary barrier, or backup


to pipe rams

48
BOP stack components

 Blind rams
– Features large elements that
close on open hole ->

 ‘Shear’
Shear’ rams
– Have special blades that can cut
through any size well tubulars in
an emergency

 ‘Blind-
Blind-Shear’
Shear’ rams ->
– Special blind ram that
incorporates a shear
– Cuts, also seals open hole

49
BOP Operating Units

 Hydraulically
operated closing
systems
– 3,000 psi closing
pressure
– Air-
Air-pressurized
cylinders contain
hydraulic fluid
– Control panel ->
on module or rig
floor

The operating module provides the hydraulic pressure to close and open the
blowout preventers. The system consists of several bottles or cylinders (called
‘accumulators’) that contain hydraulic fluid under up to 3000 psi pressure.
Triggered by operating controls on the module or on a remote control panel on the
rig floor, the pressurized fluid provides the force to operate the annular and ram
preventers. As the cylinders are depressurized, an air pump automatically starts to
re-pressurize them.

50
BOP Testing

 After assembly, BOPs must be tested


– Usually low pressure (200-300 psi) water test,
followed by high pressure test
– Tests use pipe blanks, cup testers, plugs
– BOPs also tested during well operation

 Offshore testing prescribed by regulation


 MMS regulations, Part D.250

51
Kelly Cock safety valve

 Full-opening safety
valve
– Made up to top of
work string
– Isolates tubing

52
Choke Manifolds

 Choke is essential to controlling annulus pressures


– Adjustable choke, Manual or remotely operated
– Remote operation uses panel on rig floor

53
Downhole safety valves

 Downhole safety valves


are made up on tubing
– prevent backflow up
tubing from downhole

– Spring-
Spring-type, simple
flapper, and pump-
pump-down

– Also known as ‘bit float’


float’,
‘string float’
float’, and ‘I-bop’
bop’
 inside blowout preventer

54
Outline

1. Review: Pressure and Basic Calculations


2. Review: Well Control fundamentals
3. Review: Well Control Equipment
» 4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
9. Well control situations during workovers

55
Barriers to Kicks

1. The circulating mud system


 Mud density must be maintained to ‘overbalance’
overbalance’ the formation
pressure
 In the event of a kick, the mud density must be adjusted to meet
the requirements for increased BHP

2. Equipment to shut-in the well


 Annular preventer, BOP stack, Safety valves, choke

3. » ‘Well Control’ techniques to circulate out


the kick, prevent further inflow, and resume
safe operation

The third set of barriers to kicks are well-control techniques that circulate out the
kick, prevent further inflow, and resume safe operation.

56
Shut in the well

 Once a kick is detected (or suspected),


Shut In the well
 If casing set and cemented, shut in is safe step
– Purposes
 Stop the inflow from the formation
 Protect the crew and rig
 Measure key pressures
– SITP and Annulus (casing) pressures
 Diagnose and organize the Kill procedure

The first and primary reaction to a kick is to shut in the well. Shutting in can help to
stop the inflow from the formation if the pressures can find equilibrium. Most
important, shutting in serves to protect the crew and rig from the effects of a
possible blowout.

57
Typical shut-in procedures

 Fluid being circulated, tubing on bottom


1. Stop pump; check for flow
2. Open the choke
3. Close the annular BOP
4. Close the choke while watching casing
pressure
5. Record tubing and casing pressure
6. Pick up to ensure tool joint is not in BOP

These are the steps in a typical shut-in procedure, when pipe is on bottom and well
is circulating. Note that this procedure uses a ‘soft’ shut-in, in that the choke is
open when the BOP is closed. A ‘hard’ shut-in happens when the choke is closed –
it is a little quicker but increases the risk of fracturing an intermediate formation.

58
Review: Well Control
Techniques

 Purposes of shut In
 Stop the inflow from the formation
 Protect the crew and rig
 » Measure key pressures
– SITP and Annulus (casing) pressures
 Diagnose and organize the Kill procedure

The second reason to shut in is to allow accurate measurement of key pressures in


the tubing and casing. These pressure measurements allow diagnosis of the kick
and planning to remedy it.

59
Measure Key pressures

 Shut-in Tubing Pressure (SITP)


 Pumps shut in when kick detected, tubing should
be full of clean fluid
 If on bottom, SITP indicates formation pressure

Formation pressure = BHP + SITP

Example: mud weight is 11 ppg, depth 7,040 feet, SITP = 350psi


Hydrostatic = 11 x 7040 x .052 = 4027 psi
Formation pressure = 4027 + 350 = 4377 psi

After the well is shut in, measure the shut-in tubing pressure, also called SIDPP for
‘shut-in drill-pipe pressure’. Whatever you call it, the pressure should stabilize
within 5 minutes or so. SITP is the key to determining the formation pressure that
has caused the ‘overbalance;’ and inflow. If the tubing is on bottom, calculate BHP
from the mud weight, and add the SITP you recorded.

60
Measure Key pressures

 Shut-in Tubing Pressure (SITP)


 Also use SITP to calculate Kill weight of new mud

Mud increase = SITP ÷ TVD ÷ .052

Example: mud weight is 11 ppg, depth 7040 feet,


SITP = 350psi

Mud increase = 350 ÷ 7040 ÷ .052 = 0.96 ppg


Kill Mud = 11 ppg + 0.96 ppg = 12 ppg

SITP also allows a calculation for a new mud weight to counteract the formation
pressure and bring the situation back into balance.

61
Measure Key pressures

 Low or No SITP
– Reasons
 Gauges shut off
 Float or safety valve in tubing
 Gauge scale too high
 Well has no or little pressure

 Open choke and see if annulus flows


 If not, try to circulate small amount

If there is no SITP shown on the standpipe gauge, try these actions to diagnose the
problem.

62
Measure Key pressures

 Shut-in Casing Pressure (SICP)


 SICP reflects annulus, which contains the kick
fluids

 SICP can indicate the density of the kick (gas, oil,


or water) but requires accurate measurement of
kick volume (pit level increase, etc.)
– Best practice is to assume kick is gas

 Rising SICP may indicate gas percolating up


annulus
– or low-
low-permeability formation

SICP, or annulus pressure, should also be measured, and there are several
methods to try to calculate the ‘kick density’, that is whether oil, gas, or water.
Almost all company procedures require that you treat EVERY kick as gas, however,
and take the appropriate actions instead of trying to calculate a density.

63
Review: Well Control
Techniques

 Purposes of shut In
 Stop the inflow from the formation
 Protect the crew and rig
 Measure key pressures
– SITP and Annulus (casing) pressures
 » Diagnose and organize the Kill procedure

The third step for shut-in is to allow you to diagnose and organize the procedures to
bring the well back into balance with formation pressure.

64
Review: Well Control
Techniques

 Three methods of circulating out the kick, but


all have similarities
 Constant bottom-
bottom-hole pressure (BHP) must be
maintained
 Constant BHP is maintained by circulating at a
constant pump rate, and
 Adjust the choke to maintain constant BHP
 Possible to shut in at any time without jeopardizing the
well

Let’s review the basics of well-control techniques and procedures. Conventional


well-control practice recognizes three basic methods of circulating out a kick and
bringing the well back into balance with formation pressure. The methods are
called the ‘Driller’s’ method. The ‘Wait and Weight’ method, and the ‘Concurrent’
method. Rather than spend our time graphing and calculating each method, our
review will concentrate more on the characteristics of the methods, and how they
are similar (and different). I’ll also try to point out the advantages and
disadvantages to each one.

65
Review: Well Control
Techniques

 Three ‘Control’ methods have similarities


 Shut in, record SITP and SICP
 SITP added to KRP* to determine ICP, the Initial
Circulating Pressure
 Constant BHP maintained by circulating at constant
pump speed and by adjusting the choke

* predetermined ‘kill rate’


rate’ pressure of pump, at
reduced pumping rate

66
Review: Well Control
Techniques

 Main difference between the 3 methods:


– How and When ‘kill-weight mud’ is pumped
 Driller’
Driller’s method: kick circulated out with same mud
that was in the well when kick occurred, then KWM is
circulated
 Wait & Weight method: kick is circulated out at the
same time KWM is pumped in
 Concurrent method: increase mud weight in steps,
recalculate circulating pressures each step, until final
KWM is achieved

The basic objective of all control methods is to bring the well back into balance with
formation pressure. To achieve that balance, a new mud weight is necessary to
provide the additional BHP to counteract the new formation pressure that caused
the kick. The new mud of increased density is called ‘Kill-Weight Mud’.

67
Review: Well Control
Techniques

 Driller’s method
– Hold casing pressure
constant as pump is
brought up to ‘kill rate’
rate’, to
determine ICP
– Pump at kill rate, holding
FTP constant using choke
adjustment
– Calculate KWM, tubing
capacity, strokes to bit

Here are the basics of the Driller’s method. A worksheet is used to calculate the
key parameters of the circulating program.

68
Review: Well Control
Techniques

 Driller’s method
– Advantages
 Simple, few calculations
 Circulation starts immediately
– Disadvantages
 Highest surface pressures if gas kick
– KWM not used to circulate kick; all control pressure is
choke pressure
– Highest risk of ‘Underground Blowout’
Blowout’
 Longest time to kill (2 complete circulations)

69
Review: Well Control
Techniques
 ‘Wait & Weight’ method
– Prepare Kill-
Kill-weight mud
– Circulate KWM as kick
circulated out
– Constant pump rate,
rate, but
pump pressure decreases as
heavier mud replaces lighter
– Casing pressure increases as
kick circulated, but BHP kept
constant using choke
 Graph of DPP versus time,
DPP corrected with choke

The ‘Wait and Weight’ method uses a combination approach – the mud weight is
increased to kill weight and pumping begins. As the new mud displaces the older,
lighter mud in tubing, the BHP increases gradually and proportionally.

70
Review: Well Control
Techniques

 ‘Wait & Weight’ method


– Advantages
 Potential for lower surface pressures if gas kick
 Shorter time until kick is circulated out

– Disadvantages
 ‘Wait’
Wait’ for full load of KWM to be mixed
 More complex procedure to design and operate

The name of the method comes from having to ‘Wait’ to mix an entire new batch of
kill-weight mud (‘Weight’) before pumping starts.

71
Review: Well Control
Techniques
 ‘Concurrent’ method
– Combination of ‘Driller’
Driller’s and ‘Wait’
Wait’
 Mud weighted up in series of steps,
rather than KWM all at once (as in
‘Wait’
Wait’ method)
– Constant pump rate,
rate, but pump
pressure decreases as heavier
mud replaces lighter
 Graph of DPP versus time is
complicated by periodic increases in
mud weight
– Casing pressure increases as kick
circulated, but BHP kept constant
using choke
 Projected DPP corrected with choke

The concurrent method is a combination of the Driller’s and ‘Wait/Weight’ methods.

72
Review: Well Control
Techniques

 ‘Concurrent’ method
– Advantages
 Starts sooner than ‘Wait’
Wait’ method
 Potential for less surface pressure than ‘Driller’
Driller’s but
not as good as ‘Wait’
Wait’
– Disadvantages
 Even more complicated to design and operate than
‘Wait’
Wait’ method
 Mud weighting in steps must not compromise mud
quality

73
Review: Well Control
Techniques

 Additional control methods


– Volumetric (gas kick only)
 Controls BHP and surface pressures when no pipe is
in the hole or when well cannot be circulated
– As SICP rises, mud is bled off (or pumped into) the annulus
using a calculated psi/bbl relationship

– Reverse Circulation
 Circulates down annulus, up tubing
 Better control of surface pressures in drill pipe
 Circulating up through bit jets is slow, maybe slower
than gas percolation in annulus

There are several modifications and additions to the 3 control methods. The most
common are these two.

74
Review: Well Control
Techniques

 Special Considerations
– Pipe off bottom (or out of hole)
 Run pipe in, by stripping or snubbing (next slide)

– Off-bottom Kill
 KWM calculated using TVD to bottom of tubing,
not bottom of hole (results in heavier mud)
 More risk of lost circulation, underground blowout

If a kick occurs when the pipe is off-bottom, most procedures specify that pipe be
run into the hole to bottom. For a kick that occurs when the pipe is not on bottom,
the procedures are the same except that the density of the kill mud is calculated to
the bottom of tubing, not to total well depth. Off-bottom kills are more risky than
having the pipe on the bottom, because there is more hole exposed to potential
inflow and the risk of fracturing an intermediate formation is greater.

75
Stripping and Snubbing

 Stripping: running pipe into


the well under pressure
 Annular preventer or rams are
primary barrier

 Snubbing: pipe is ‘light’,


must be mechanically forced
into well
 Upward-
Upward-acting BHP greater than
weight of pipe
 Snubbing is slow

If a kick occurs when the pipe is off-bottom, most procedures specify that pipe be
run into the hole to bottom. If there is not enough pipe in the hole to ‘pull’ it down
against pressure by using the weight of the pipe, then a ‘Pipe Light’ scenario
occurs. In a ‘pipe light’ situation, BHP is sufficient to force or float the pipe out of
the well. In this situation, it becomes necessary to ‘Snub’ the pipe, mechanically
force the pipe downward into the hole against a greater, upward-acting pressure.

76
Outline

1. Review: Pressure and Basic Calculations


2. Review: Well Control Fundamentals
3. Review: Well Control Equipment
4. Review: Well Control Techniques
» 5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
9. Well control situations during workovers

The following section is a summary of workover and completion operations, and the
well-control aspects associated with each.

77
Completion and Workover

 Completion
 Preparing a well to produce oil and gas
 Establishes one or more flow paths for the efficient
production of reservoir fluids

 Workover
 After completion, any operation to restore or
increase production, or to abandon temporarily or
permanently

Completion is performed once, before the well is put into service. After the well is
initially completed, workovers may be necessary to repair the well, restore or
increase productivity, or abandon the well.

78
Types of Completions

 Conventional
– Casing set and
cemented through pay
zone
– Perforated casing
– Packer on tubing, set
above pay zone
– 75% of onshore wells

A so-called conventional completion is used in 75% or more of onshore wells.

79
Types of Completions

 Packer
– Mechanical device with
sealing element
– Seals OD of tubing to ID
of casing
– Creates ‘tubing-
tubing-casing’
casing’
annulus, usually filled
with corrosion-
corrosion-inhibiting
fluid
 ‘annulus’
annulus’ or ‘packer’
packer’ fluid

80
Types of Completions

 Dual completion
– Separate flow paths for
2 pay zones in one well
– Casing set and
cemented through 2 pay
zones, perforated
– 2 tubing strings
– Dual-
Dual-string and single
packers, set above pay
zones

As we’ll see in detail in the following section, a ‘Blast joint’ is specially reinforced
pipe, to resist the abrasion effects of sand produced from the shallower production
zone.

81
Types of Completions

 ‘Annular’ Dual completion


– Separate flow paths for 2 pay
zones in one well
– Casing set and cemented
through 2 pay zones,
perforated
– Only 1 tubing string
– 1 packer, set between zones
– Upper zone production is up
annulus, lower through tubing

82
Types of Completions

 Tubingless completions
– Open hole (‘
(‘barefoot’
barefoot’) ->
– Cased hole perforated (below)

– No tubing or packer,
production flow is up casing
– Casing as small as 3.5”
3.5”

– Sometimes ‘packerless’
packerless’
 Has tubing, but no packer

83
Types of Completions

 Pumping wells
 ‘Sucker rod’
rod’ pump completion

– Conventional completion with


tubing anchor
 Minimizes tubing movement

– Pump may be run on tubing or


on ‘rods’
rods’ set inside tubing

– Completion similar for


downhole electric or hydraulic
pumps

84
Types of Completions

 Gas Lift completion


– Conventional, oil flow through
tubing set on packer
– Gas-
Gas-lift valves run on tubing
– Gas injected down the
annulus, through the gas-
gas-lift
valves, and into tubing
– Reduced density causes oil to
flow to surface

85
Types of Completions

 HPHT ‘Treater’ string


 For high-
high-corrosion environments
(or sometimes diluent injection for
heavy oil)
– Separate tubing string run
inside tubing for treatment
injection
 Intermittent or continuous
 May be ‘kill’
kill’ string for hi pressure

– In extreme cases, may be dual


completion with one string for
treating only

86
Completion and Workover

 Workover objectives
 Control water, gas, or sand production
 Repair mechanical problems
 Stimulate the reservoir and increase production
 Re-
Re-complete into additional or new reservoir
 Plug and Abandon (‘(‘P&A’
P&A’) the well

Completion is performed once, before the well is put into service. After the well is
initially completed, workovers may be necessary to repair the well, restore or
increase productivity, or abandon the well.

87
Workover

 Controlling water production

– Static: separate oil and water zones

– Depleted, low rate production:


water can be sucked into oil-
oil-wet
zone

– Depleted, higher rate: water flows


in preference to oil as area near
wellbore becomes water-
water-wet

During the life of an oil well, the interface between oil and water zones may change
(or the well may have been improperly completed from the beginning). A common
scenario is ‘up-coning’ of the oil-water interface due to changes in reservoir
pressure or increased production rates. Once water has ‘wetted’ the pores near the
wellbore, water will be produced in preference to oil. The oil is still there - It just
can’t flow into the wellbore. Workover solutions usually involve treatment chemicals
to restore oil permeability, squeeze-cementing the lower perforations, or re-
completing the well higher in the zone.

88
Workover

 Controlling gas production

– Static: separate gas, oil, and


water zones

– Depleted: gas sucked down into


perforations
 Producing gas in an oil well uses up
reservoir energy that allows oil to
flow to well and be produced, lifted

Similarly, the interface between gas and oil zones may change with time and
production. A common scenario is gas short-circuiting to the oil perforations.
Workover usually involves squeeze-cementing the upper perforations or re-
completing the well lower in the oil zone.

89
Workover

 Controlling sand production


– Production of sand a major
problem in some areas, some
reservoirs
– Cleanout involves washing in
with hi-
hi-gel fluid
– Recompletion techniques to
prevent sand inflow
 Simple perforation allows sand
into wellbore
 Gravel-
Gravel-packing most common

90
Completion and Workover

 Basic Workover operations


 Perforating
 Remedial cementing and squeeze-
squeeze-cementing
 Drill stem testing
 Acidizing and fracturing
 Cleanout and sand control
 Plugging back, deepening, or side-
side-tracking
 Plugging

91
Workover

 Perforating
– Completion or workover
– Primary tool for water
control
– Jet-
Jet-charge guns run on
wireline, coiled tubing, or
tubing
– ‘Underbalance’
Underbalance’ BHP during
perforating

92
Workover

 Squeeze cementing
– Excludes water or gas zones from the well
– Allows a new zone to be completed
– Repairs damaged or corroded casing
– Correct problems with the primary cement
job
– Squeezed through perforations to emplace
behind casing

93
Workover

 Squeeze cementing
– Usually special squeeze-
squeeze-
tool run on work string
– Has packer(s) to isolate
zone in casing
– Tool positioned above or
astride zone to be
cemented
– Cement pumped, then
excess reversed out

94
Workover

 Types of ‘Squeeze jobs’


– Standard packer squeeze ->
– Bradenhead squeeze
 No packer or squeeze-
squeeze-tool,
cement set in casing
– Bullhead squeeze
 Uses packer, all fluids into zone
– Set-
Set-through squeeze
 Cement washed out of casing
– Circulation squeeze
 Packer set between 2 sets of
perfs, circulation established first

95
Workover
 Drill-stem testing
– Setting a temporary completion to determine the productivity of a zone
– Zone isolated with packer and downhole valve
– Flow to surface, then valve closed and pressure build-
build-up recorded

96
Workover

 Acidizing
– Clean up mud invasion and/or dissolve minerals to
improve zone permeability near the wellbore

– Inject acid below fracture pressure (matrix Acidizing),


or above (Acid-
(Acid-fracturing)

– Acids: hydrochloric (HCl), hydrofluoric (HF), acetic and


formic acids (H or CH3 COOH)

97
Workover

 Fracturing
– Pumping fluid into a zone
until the fracture pressure is
exceeded; zone ‘breaks
down’
down’ and fracture created
– Fracture then filled with
plastic beads or sand to
‘prop’
prop’ open
– Fractures are vertical and
extend from the wellbore as
‘wings’
wings’
– Radical increase in drainage
and permeability near well

98
Workover

 Sand control
– Production of sand a major
problem in some areas,
some reservoirs
– Cleanout involves washing
in with hi-
hi-gel fluid
– Recompletion techniques
to prevent sand inflow
 Simple perforation allows
sand into wellbore
 Gravel-
Gravel-packing most
common

99
Sand control
 Some completions use screen or slotted liner only
 Screen liner with gravel pack
 Perfs washed to remove sand; sized gravel or beads
pumped to bottom; screen or slotted liner washed in

100
Workover

 Plugback
– Moving the producing interval from a deeper to a
shallower one
– Wellbore below the new zone is plugged and
abandoned
 Old perforations squeezed off
 Cement plug and/or permanent packer to ‘plug-
plug-back’
back’ depth
(new well TD)
 Deepening
– Upper perfs squeezed off, new zone drilled out
– Liner hung and cemented off old casing
– New, deeper zone perforated and put on production

101
Workover

 Sidetracking
– Another way to abandon or
bypass the lower part of a well
 Damaged casing, permanent
junk, or skin-
skin-damaged zone
– Cut casing window, then a
whipstock packer used to
direct drilling off-
off-axis
– Plugback old well; liner hung
and cemented off old casing
– New zone perforated and put
on production

What’s wrong with this picture?

102
Workover

 Plugging
– Well abandoned for mechanical or
economic reasons
– All States have plugging regs and
requirements
– Perforations squeezed
– Plugs set to prevent:
 Migration from one zone to another
in the wellbore
 Contamination of freshwater
 Blowouts after casing deteriorates

103
Outline

1. Review: Pressure and Basic Calculations


2. Review: Well Control Fundamentals
3. Review: Well Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
» 6. Fluid systems used in workover and
completion
7. Production equipment and pressure control
8. Conventional, wireline, Coiled Tubing, and Hydraulic
Workover
9. Well control situations during workovers

The fluids used in workover and completion include water- and oil-based muds, as
well as a variety of brines, foams, and treating chemicals.

104
Fluid systems

 Workover fluids
 For perforating, cementing, fracturing etc
 Gases, brines, muds, acids, gels, foams, etc.

 Packer fluids
 Annulus fluids that are non-
non-corrosive, may feature
other properties; must be stable for life of well

 Completion fluids
 Designed to prevent damage to formation
permeability during completion

105
Fluid systems

 Fluid characteristics
 Dense enough to control well pressures, but not so
heavy to fracture formation
 Cost effective; many fluids available for different
purposes
 Non-
Non-corrosive, non-
non-reactive, stable
 Free of solids
 Not hazardous to personnel if handled correctly

106
Fluid functions

 Circulate materials
 IN: cement, pills, gravel and sand, frac materials
 Out: used cement, cuttings, debris and sand, etc.

 Suspension of materials when circulation stops


 High gel strength resists settling of solids, BUT
 High gel strength develops high swab pressures
– Most materials reverse-
reverse-circulated out

 Pressure control
 Well must be killed for workover or completion

107
Fluid functions (cont’d)

 Heat removal and Lubrication


 For bits, mills, and downhole motors

 Special Tool functions


 Underbalance; hydraulic energy; special logging fluids

 Avoiding Formation damage


 Solids free, non-
non-reactive, non-
non-wetting, clay compatible

108
Types of Fluids

 Oil Fluid systems


– Lease crude
 Plentiful and economic to use
 Non-
Non-reactive, no clay swelling, non-
non-wetting
 May have solids (wax, paraffin, or sand)
 May be corrosive (if H2S or CO2 present)
 About 7 ppg: perfect for depleted wells, too light for
others?
– Diesel and kerosene
 Inexpensive; cleaner and lighter; but fire hazard

The most common workover fluid in oil wells is lease crude.

109
Types of Fluids

 Oil-Emulsion fluids
– Oil-in-water emulsion commonly uses diesel
 Emulsifying agents make stable
 Heavier than diesel, but still non-
non-reactive and
formation-
formation-friendly
– ‘Inverse’ emulsion is water droplets in oil
 More physically stable, but breaks down over 200°
200° F

 Gases as completion fluids


– Natural gas or nitrogen

110
Types of Fluids

 Water-based fluids
– Brines
 Sodium, calcium, and
potassium chloride salts
 Calcium and zinc bromide
add weight to solutions for
pressure control
 Salt saturation can cause
crystals to form
– Muds
 Inexpensive but solids a problem

Brines make an excellent completion and workover fluid, and they are very
inexpensive and easy to produce and handle. Bromide salts allow the brine to be
‘weighted’ for pressure control and killing the well initially.

111
Types of Fluids

 Water-based fluids
– Acids
 Water-
Water-diluted acids (5% - 25%) for permeability
enhancement near wellbore
– Hydrochloric (HCl) dissolves limestone (and carbonate
cements in sandstones)
– Hydrofluoric (HF), called ‘mud acid’
acid’, dissolves mud-
mud-solids
invasion of pores
– Acetic and formic acids (H or CH3 COOH) dissolve asphalts,
paraffin, and other oil solids blocking pores

 Gelled acids for acid-


acid-fracturing
– Gelling agent improves viscosity for better frac hydraulics

112
Types of Fluids

 Water-based fluids
– Foams
 Requires ‘foaming agent’
agent’
 Foam is an emulsion; fluids
uniformly distributed, do not
separate easily
 Has structure and strength:
– bubbles of gas surrounded by
liquid film
– water around gas forms 12-
12-sided
structure (deforms but does not
shear when pumped)

113
Foam fluid systems

 Light weight (2-5 ppg)


– Underbalanced so no
formation damage
 Foam has exceptional
solids-lifting capacity
 Foam ‘structure’
structure’ is reason
– Best lifting: 50% - 90%
gas
– High lifting cap. means low
annulus velocity

Compared to water and mud, foam has a much higher capacity to lift cuttings, sand,
and debris. This enhanced capacity is probably due to the unique structure of the
water molecules in foams, which deforms during flow but does not shear. A greater
capacity to lift solids means that a lower pumping rate and lower annular velocity is
necessary to lift cuttings. Typical pumping rates in foam systems are as low as 20
gallons per minute of water and 266 cubic feet of gas per minute to achieve normal
120 feet per minute annular velocity, 10-times better hydraulic performance than a
typical mud system.

114
Types of Fluids

 Plugs and Pills


– Dense fluid/solid mixtures, used to
 Seal (temporarily) casing leaks
 Correct injection profile
 Stop lost circulation
 Divert acid, stop water flows
 Block flow inside tubing or casing
 Stabilize unconsolidated zones
 Seal fractures and thief zones during cementing
 Kill underground blowouts

Plugs and pills are dense fluid/solid mixtures. They are ‘spotted’ into tubing, casing,
or open-hole and act like temporary plugs to control flow or pressure.

115
Types of Fluids

 Plugs and Pills


– ‘Soft’ Plugs (pumpable)
 Neat cement mixture
 Oil-
Oil-based mud with cement thickener
 Diesel-
Diesel-cement mixture
 Diesel-
Diesel-bentonite mixture
 Bentonite-
Bentonite-cement mixture
 Polymer/plastics/silica mixtures
 May also include lost-
lost-circulation or weighting materials
and viscosifiers to make denser

116
Types of Fluids
‘Soft’
Soft’ Plugs (pumpable): Examples of polymer gel plugs

117
Types of Fluids

 Plugs and Pills


– ‘Hard’ Plugs (‘setting’ plugs)
 Usually 1 to 5 barrels volume
 Accelerant speeds up setting time
 Time-
Time-delayed, self-
self-complexing (polymer) plug
 Sometime a ‘breaker’
breaker’ enzyme added to polymers for
predictable breakdown time (1-(1-10 days)
 Example: macaroni string run in tubing, ‘packed off’
off’
with flash-
flash-set, weighted polymer plug; when the
macaroni string is pulled, the polymer plug ‘heals’
heals’ and
blocks flow until breakdown

118
Types of Fluids

 Packer fluids
 Provides formation pressure control
 Prevents casing collapse, tubing burst
 Prevents corrosion, stable for life of well
 Compatible with seal elements
– Typical fluids
 Brines with commercial additives (75%)
 Diesel or crude oil

119
Outline

1. Review: Pressure and Basic Calculations


2. Review: Well Control Fundamentals
3. Review: Well Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
»7. Production equipment and pressure control
8. Conventional, wireline, coiled tubing, and
Hydraulic workover
9. Well control situations during workovers

120
Production
pressure control

 Pressure control tools and


devices
– Surface
 Trees, pumps, lines, controls
– Subsurface
 downhole safety valves, mandrels,
packers, nipples, subs, and guides
– Some equipment installed and
left; others used only
temporarily during workover

This is a particularly complicated assembly used for workover operations, but it


basically uses ‘one of everything’.

121
Production pressure
control equipment

 Christmas Tree
 First device
encountered
during workover
 Assembly of
valves, spools, and
flanges that
control pressure
and the flow of
fluids from the well

122
Wellhead

 Christmas tree
– Control assembly set
above the ‘wellhead’

 Wellhead consists of:


– ‘casinghead’ body, which
encloses the casing
hanger assembly
– ‘tubinghead’ body, which
supports the tubing
hanger

123
Wellhead
 Casing hanger
 Slips-
Slips-and-
and-seal assembly
from which the casing
string is suspended
 Tubing hanger
 Suspends the tubing
string, seals off the
upper casing annulus,
and allows flow to the
tree
 Valves
 Allow access to casing
and tubing annuli

124
Component
parts of
a wellhead

125
Component Heads and
Hangers
Casing Tubing

126
Wellhead

 Casing hanger
 Slips-
Slips-and-
and-seal
assembly from which
the casing string is
suspended
 Tubing hanger
 Suspends the tubing
string, seals off the
upper casing
annulus, and allows
flow to the tree

127
Christmas Tree

 Master valve
 Primary shut-
shut-off valve
 Wing valve
 Flow control valve
 Choke
 Adjusts the amount of
flow from the well
 Crown or swab valve
 Allows access for
wireline etc.

128
Removing the Tree

 In many workover operations,


the tree must be removed for rig
access
– Tree is pressure-
pressure-control barrier
 Typical Steps
– Check for tubing-
tubing-casing annulus
isolation
– Pump kill fluid to bottom of tubing
– Set wireline plug in tubing
– Remove the tree and install BOP
stack

129
Casing

A well’s construction
program usually consists of
several sizes and lengths of
steel casing
– Casing is run from the surface
(and cemented)

– Liners are ‘hung’


hung’ in casing and
do not extend to the surface

130
Liners

Liners are suspended in casing


using a ‘liner hanger’
– Mechanical or hydraulic slips
– Usually cemented in place
– Run for various reasons:
 Simply shorter, it’
it’s cheaper than
a full casing string
 Isolate unexpected problems
encountered during drilling, such
as lost circulation zone or high
pressure formation

131
Tubing and packer

 Tubing
– Conducts flow from pay zone to surface
– May be pulled for workover, replaced
with ‘work string’
string’

 Packer
– Mechanical device with sealing element
– Seals OD of tubing to ID of casing
– Creates tubing-
tubing-casing annulus, usually
filled with corrosion-
corrosion-inhibiting fluid
 ‘annulus’
annulus’ or ‘packer’
packer’ fluid

132
Removal of Packers

 Retrievable Packers
– For workover, packer is removed
using
 Hydraulic: hydraulic pressure to
seat/unseat
 Mechanical: rotation and/or pull
 Wireline and slickline: set and
retrieved using remote methods
 Permanent Packers
– Must be milled out

133
Seal Nipples

 Run on bottom of tubing


string to latch into packer
– Positive seal to prevent fluid
leaks at packer/tubing union

134
Bridge Plug

 Set in tubing or casing to


isolate a zone, prevent fluid
movement
– May be permanent or
retrievable
– May be run on tubing or
wireline
– Set and retrieved similar to
packers

135
Miscellaneous tools

 Blast Joint ->


 In multiple
completions,
protects the
tubing that is
opposite the
upper completion
 Safety Joint
 Quick-
Quick-release tool
 Back off or shear,
releases stuck
tools

136
Miscellaneous
tools
 Sliding Sleeve ->
– Wireline-
Wireline-actuated port that
allows circulating from
tubing into casing
– For treatment, well kill, etc.

 Mandrels
– Usually for gas lift, allows
injection from casing into
tubing
– Usually several at bottom
in gas-
gas-lift well

137
Miscellaneous tools

 Landing and Seating nipples


– Small sub run in tubing in which flow-
flow-
control and pressure-
pressure-control devices
can be installed by wireline
– Devices:
 Blanking plug for well shut-
shut-in or pressure
test
 Equalizing check valves
 Safety valves
 Chokes (to reduce surface flow)
 Instrument hangers
– Landing nipples have latching device

138
Miscellaneous
tools
 Sliding Sleeve ->
– Wireline-
Wireline-actuated port that
allows circulating from
tubing into casing
– For treatment, well kill, etc.

 Mandrels
– Usually for gas lift, allows
injection from casing into
tubing
– Usually several at bottom
in gas-
gas-lift well

139
Miscellaneous tools

 Cement retainers and


squeeze tools
– Used for squeeze cementing
or to isolate casing
– Set on tubing or wireline
– Incorporate a packer plus
up/down flow valve and ports
– Squeeze tool is retrievable,
retainer must be milled out

Cement retainer ->

140
Miscellaneous tools

 Circulating Wash tool


– Straddle-
Straddle-packers allow zone isolation,
testing, or acidizing
– Circulating ports can open between
tubing and casing
 Can reverse sand or debris from well

141
Miscellaneous tools

 Packer mills
– For removal of ‘permanent’
permanent’
packers and cement retainers
– Cuts only the packer slips
– A ‘picker’
picker’ latches into the
packer body for retrieval

 Junk and Boot baskets ->


– Collects debris from milling
operations
– Junk basket run separately
on tubing; boot basket run
above mill

142
Outline
1. Review: Pressure and Basic Calculations
2. Review: Well Control Fundamentals
3. Review: Well Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
» 8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
9. Well control situations during workovers

143
Conventional workover rig

 Self-propelled
(highway or barge)
 Capabilities:
– Pressure control
– Tripping
– Rotate
– Circulate

144
Conventional workover rig

 Hoisting system
– Derrick
– Drawworks
– Crown block
– Traveling block
– Wire rope
– Hook and elevators

145
Conventional workover rig

 Rotating systems
– Rotation necessary to
 Drill cement
 Place packers or plugs
 Mill
 Fish
 Set downhole tools

 Conventional Rotary table

146
Conventional workover rig

 Rotating systems (cont’d)


 Top drive
– Many newer workover rigs
feature top-
top-drive technology
– Advantages
 No KB rotating on floor
 Break out work string in 2-
2- or 3-
3-
joint stands
– Faster, safer, better pressure
control
 Rapid response to kicks
– Stab in and spin up

147
Conventional workover rig

 Rotating systems (cont’d)

 Power swivel
– Light duty workover
operations
– May use rig’
rig’s hydraulic
system or portable power
unit
 Skid or trailer mounted

148
Conventional workover rig

 Circulating system
– Pumps
– Lines
– Standpipe
– Rotary hose
– Swivel
– Kelley
– Shale shaker
– Tanks and/or pits
– manifolds

149
Conventional rig pressure
control

 BOP stacks may be


configured in many
different ways
– Typical:
 Annular preventer
 Pipe rams
 Blind rams

 API RP53: Blowout


Prevention Equipment
Systems

150
BOP stack components

 Annular Preventer
– Top of stack

– Can close around casing,


drill pipe, tool joints,
collars, the Kelly,
wireline, and open hole

151
BOP stack components

 Pipe Ram
– Sized to close around
pipe of a specific
diameter
– Usually several sizes
pipe/pipe rams
– Will not close on tool
joint

152
BOP stack components

 Variable-bore pipe Ram


– Sized to close around a
range of diameters of pipe

– Primary barrier, or backup


to pipe rams

153
BOP stack components

 Blind rams
– Features large elements that
close on open hole ->

 ‘Shear’
Shear’ rams
– Have special blades that can cut
through any size well tubulars in
an emergency

 ‘Blind-
Blind-Shear’
Shear’ rams ->
– Special blind ram that
incorporates a shear
 Cuts, and seals open hole

154
BOP Operating Units

 Hydraulically
operated closing
systems
– 3,000 psi closing
pressure
– Air-
Air-pressurized
cylinders contain
hydraulic fluid
– Control panel ->
on module or rig
floor

The operating module provides the hydraulic pressure to close and open the
blowout preventers. The system consists of several bottles or cylinders (called
‘accumulators’) that contain hydraulic fluid under up to 3000 psi pressure.
Triggered by operating controls on the module or on a remote control panel on the
rig floor, the pressurized fluid provides the force to operate the annular and ram
preventers. As the cylinders are depressurized, an air pump automatically starts to
re-pressurize them.

155
BOP Testing

 After assembly, BOPs must be tested


– Usually low pressure (200-300 psi) water test,
followed by high pressure test
– Tests use pipe blanks, cup testers, plugs
– BOPs also tested during well operation

 Offshore testing prescribed by regulation


 MMS regulations, Part D.250

156
Kelly Cock safety valve

 Full-opening safety
valve
– Made up to top of
work string
– Isolates tubing

157
Choke Manifolds

 Choke is essential to controlling annulus pressures


– Adjustable choke, Manual or remotely operated
– Remote operation uses panel on rig floor

158
Wireline workover

 Electric or ‘slick’ line


 Capabilities:
– Pressure control
– No tripping (wire only)
– No rotate or circulate
 Advantages
– Faster, cheaper, self-
self-
contained

159
Wireline workover

 Wireline workovers
– Setting and retrieving equipment
 gas lift valves, chokes, plugs, packers, etc.
– Fishing and jarring
– Logging and sampling
– Perforating
– Spot treating or spot cementing
 Wireline ‘basket’
basket’ dumps chemicals or cement
at selected interval
– Bailing and paraffin cutting
 Sand bailer at right ->

160
Wireline workover

 Wireline pressure control


– Lubricator assembly
 Stuffing box seals wireline against
well pressure
 Riser joints sufficient length for
workover tools
 Valves and unions
– Lubricator assembly also may be
used with wireline BOP

161
Wireline workover

 Wireline pressure control


– Lubricators have limited
pressure control rating
 Wireline BOPs
– Hydraulic or screw-
screw-type
Rams close on wireline
– Allow workover under
pressure

162
Coiled Tubing workover

 Coiled Tubing unit


– Continuous length of ½”
to 3½”
3½” OD tubing on
reel
– Tubing injector moves
the pipe in or out of the
well

163
Coiled Tubing workover

 Capabilities:
– Pressure control
– Tripping (no connections)
– Circulate
– No rotate BUT downhole
rotating tools are available
 Advantages
– Faster, cheaper, self-
self-
contained

164
Coiled Tubing workover

 Advantages (cont’d)
– Because it is not jointed,
coiled tubing can be run at
much faster speeds into or
out of a well

– Fluid can be circulated


through the tubing while it
is being inserted into or
withdrawn from a well;
allows for work on a
pressurized well without the
need to kill the well

165
Coiled Tubing workover

 Disadvantages of coiled
tubing
– Only light drilling
– Tubing sizes limited
– Tubing collapse and
yield strength low
– In gas and H2S
environments, potential
for gas-
gas-filled tubing on
reel

166
Coiled Tubing workover

 Coiled tubing workovers


– Sand washing, cleanouts, and
jetting
– Acidizing and chemical
treatment using packers
 Advantage: can be done
‘underbalanced’
underbalanced’
– Cementing
– Light drilling and milling
 Using downhole motor
– Fracturing ->

167
Coiled Tubing workover

 CT pressure control
– Injector head
pulls/pushes tubing,
not reel
– Stripper assembly
 Seal elements surround
the tubing, hydraulic
force provides seal
– BOP stack
 Blind, cutter, slip, and
pipe rams

168
CT BOP – typical 15K ‘Quad
stack’
Injector Head

Stripper 2 9/16” 10m

CB34 Union 3 1/16” 10m


Side Door Stripper 3 1/6” 10 m
Flange 3 1/16” 15 m BX 153

Quad BOPs 3 1/16” 15m

Flange 3 1/6” 15m BX 154

Drill Spool 3 1/6” 15m flanges top/bottom


2 1/6” 15m flanges top/bottom
Single BOP 3 1/6” 15m

169
Hydraulic Workover Unit

 Aka ‘Snubbing Unit’


 Capabilities:
– Pressure control
– Tripping
– Circulate
– Rotate
 Advantages
– Faster, cheaper, self-
self-contained
– allows for work on a
pressurized well without the
need to kill the well

170
Hydraulic Workover Unit

 Advantages (cont’d)
– Heavier pipe than CT
unit
– Rotary table for drilling

 Disadvantages
– Slower trips, because
all pipe must be
snubbed into well
– Procedures generally
more complicated

171
Hydraulic Workover Unit

 HWO workovers
– Pressure control
– Fishing and milling
– Drilling cement and bridge plugs
– Acidizing, jetting, and chemical
treating
– Squeeze cementing, plugback, and
P&A
– Sand washing and consolidation
treatments
– Perforating (underbalanced)

172
Hydraulic Workover Unit

 HWO pressure control


– Stripper assembly
 Sealing elements for
well pressure less than
3000 psi
 Hydraulically or
mechanically applied
– Blowout preventer
stack

173
Hydraulic Workover Unit

 Typical HWO BOP stack


– HWO stack may be
installed on wellhead,
Christmas tree, or on top
of another BOP stack

– Two Stripper rams plus


pipe (safety), blind/shear,
and slip-
slip-type rams

– Equalizing loop
 Adjusts pressure between
stripper rams

174
Outline

1. Review: Pressure and Basic Calculations


2. Review: Well Control Fundamentals
3. Review: Well Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
» 9. Well control situations during workovers

175
Well control during
workovers
 Work string off-bottom
 Quicker reaction means less difficult situation

1. Open the annulus and stab/close the


workstring safety valve, then close BOPs
2. Strip pipe to bottom
 Control kick using original fluid, or
3. If stripping not possible, control the kick using
heavier weight fluid
 Calculate kill weight using tubing length, not TVD

A Full opening workstring safety valve and inside BOP/Gray valve


must be available on rig floor at all times during workover operations.

176
Well control during
workovers

 Stripping in using an annular preventer

1. Adjust closing pressure to a minimum, so


that element weeps fluid slightly
2. Run pipe in no faster than 1 ft/sec
3. Maintain constant SICP with choke
 If gas is migrating up the hole, bleed pressure using the
volumetric method of Section 4
4. Every stand should displace fluid; if not,
circulation has been lost

177
Well control during
workovers
 Stripping in using RAM preventers
1. Measure carefully between the pipe rams, and adjust
closing pressures to 500 psi or less
2. With upper ram closed, lower the pipe until the tool
joint is 2 feet above the upper ram
3. Close the lower ram; bleed off the pressure between
the upper and lower rams
4. Lower the pipe until the tool joint is between the 2
rams; stop lowering and close the upper ram
5. Pressure up the space between the rams to well
pressure, and open the bottom ram.
6. Repeat steps 2- 2-5.

RAM preventers can be used for pipe stripping if annulus pressure is too high to
allow using an annular preventer, if rubbers on the tubing cannot be removed, or if
an annular preventer is inoperable or not available.
As in the method using an annular preventer, Maintain a constant SICP with choke.
If gas is migrating up the hole, bleed pressure using the volumetric method of Section 4. Every
stand should displace fluid; if not, circulation has been lost.

178
Well control during
workovers

 Work string out of the well

1. Shut in well. Record SICP every 15 minutes.


2. Make preparations for stripping or snubbing
pipe in hole (see previous procedures).
3. If SICP is rising, bleed fluid from the annulus
using the volumetric method of Section 4.

179
Well control during
workovers
 Hole in work string during kick circulation
 FTP decreases but no decrease in FCP
 Closing choke causes higher FCP but little
increase in FTP; higher FCP may cause other
problems
 Hole exposes the tubing to pressure in
annulus

1. Is hole above or below kick fluids?

180
Well control during
workovers
 Hole in work string during kick circulation
(cont’d)
1. Is hole above or below kick fluids?
 If above kick, it may be difficult (or impossible) to
maintain constant BHP
 Hole exposes the tubing to pressure in annulus
– If SITP is much higher than expected (or
SITP=SICP) and does not decrease when a
small amount bled from tubing = hole is likely
ABOVE the kick fluids

181
Well control during
workovers

 Hole in work string during kick circulation

2. If the hole is below the kick fluids,


continue circulating out the kick but
reduce the kill rate
 Slower kill rate reduces chance that hole will be
washed out larger
 Probably able to continue to circulate well
without excessive back pressure

182
Well control during
workovers
 Hole in work string during kick circulation

3. If the hole is above the kick fluids, shut


in the well
– If SICP increases (gas kick), bleed pressure
from annulus using volumetric method
 Bleed tubing/observe SITP periodically until
tubing pressure indicates gas kick has risen
above hole
 Continue circulating out the kick, but at reduced
kill rate

183
Well control during
workovers
 Hole in work string during kick circulation

3. If the hole is above the kick fluids, shut


in the well
– If SICP maintains (probably not gas kick),
consider alternative control methods, e.g.
 Bullheading tubing and annulus simultaneously
 Circulation of gunk plug/heavy mud down tubing

184
Well control during
workovers

 Plugged work string during kick circulation


 When barite or other materials are used to formulate
‘kill-
kill-weight’
weight’ mud, clumps of solid material may plug a
workover tool or the work string itself
 Pump pressure suddenly increases but annulus
pressure remains constant
 Important that choke operator doesn’
doesn’t open the
choke to reduce FTP normally; lower annulus
pressure will allow additional inflow

1. Increase, then decrease the pump rate


 Surging may clear blockage

185
Well control during
workovers
 Plugged work string during kick circulation
(cont’d)
2. Surging doesn’t clear the blockage, but tubing is
only partially plugged
A. Stop the pump and close the choke; record SITP
and SICP
B. Open the choke, start the pump, and bring the rate
up to the original ‘kill rate’
rate’ while keeping annulus
pressure constant
C. When the pump is up to ‘kill rate’
rate’, note FTP; this is
the new circulating pressure.
D. If this pressure is too high for the pumps to handle,
use a slower pump rate and repeat the steps.

186
Well control during
workovers
 Plugged work string during kick
circulation (cont’d)

3. Pump Surging doesn’t clear the blockage,


and tubing is completely plugged
A. Use a string shot or charge near the plug to jar it
loose
B. Perforate the work string above the plugged tool or
area

187
Well control during
workovers

 Hole in casing or Lost Circulation during


well control
 Kicks and well-
well-control procedures cause additional
pressure in the well; care must be taken to avoid
fracturing intermediate formations or damaging
casing
 Most control procedures are designed to circulate
heavy fluid to kill the kick; holes in casing or lost
circulation make it difficult or impossible to circulate
the required fluid
 If returns are reduced or fail to flow to the surface,
it’
it’s safe to assume that circulation is lost

188
Well control during
workovers
 Hole in casing or Lost Circulation during
well control (cont’d)
 Reasons for lost circulation:
 Bad cement job at shoe
– can cause broaching to surface
 Induced fractures
– may heal when pressure relieved
 Vuggy or naturally fractured formations
– additional pressure during well control can
induce communication with an existing fracture
network

189
Well control during
workovers

 Hole in casing or Lost Circulation during


well control (cont’d)
1. Well control with partial lost returns
A. If mixing can keep up with losses, continue
the procedure
• Pressure on the ‘lost’
lost’ zone will be reduced when the
‘kick’
kick’ fluids are circulated above the zone, so problem
may solve itself

190
Well control during
workovers

 Hole in casing or Lost Circulation during


well control (cont’d)
1. Well control with partial lost returns
B. If losses worsen, shut in the well.
• After 30 minutes to 4 hours of ‘rest’
rest’, fractures may heal
or be sealed with mud as pressures equalize
• Keep SITP constant by relieving choke pressure
• If choke pressure increases by more than 100 psi, go to
Step C

191
Well control during
workovers

 Hole in casing or Lost Circulation during


well control (cont’d)
1. Well control with partial lost returns
C. Try a reduced circulating rate and a new
‘Initial Circulating Pressure’ (ICP)
• Remember, ICP is the ‘kill-
kill-rate pressure’
pressure’ (KRP, pre-
pre-
determined for different pump rates) plus SIDPP (the
amount of underbalance in the well)
• Open the choke, start the pump at the slower rate, then
close the choke until annulus pressure is the same as
when shut in
• Shift to the new, reduced-
reduced-rate ‘ICP’
ICP’ on the workstring

192
Well control during
workovers

 Hole in casing or Lost Circulation during well


control (cont’d)
1. Well control with partial lost returns
D. Mix a slug of appropriate ‘lost circulation material’
material’
and circulate at the new ‘ICP’
ICP ’

E. If returns do not improve, abandon the current well-


well-
control procedure and try to ‘bullhead’
bullhead’ the kick
• A slug of heavy mud should work if the ‘loss’
loss’ zone is
above the zone that is kicking
• After the kick is killed, solve the Lost Circulation problem

193
Well control during
workovers
 Hole in casing or Lost Circulation during well
control (cont’d)
2. Well control with total or severe lost returns
F. If losses can not be stopped, use a barite or ‘gunk’
gunk’
plug in the wellbore to seal off the kick zone
• The ‘Kick’
Kick’ zone is most likely located below the ‘loss’
loss’ zone
• Mix a plug of 18 to 22 ppg barite or ‘gunk’
gunk’ (bentonite and
diesel), sized for 500 feet of tubing
• Spot the plug, then pull up above the plug, hold back-
back-pressure
on the annulus, and circulate
• Isolate the kick zone, then solve the Lost Circulation problem

194
Well control during
workovers

 Multiple pay zones in a kicking wellbore


 In multiple-
multiple-completion wells, two or more perforated intervals
may be present in the same wellbore
 In a well-
well-control situation during a workover, kill-
kill-weight fluids
will also affect intervals that are not involved in the kick
– Causing formation damage or even a fracture and underground
blowout or lost circulation

Solution: Chemically or mechanically isolate the


uninvolved interval
• Isolate using bridge plug (if lower than kicking zone)
• Plug off using CaCO3 or commercial polymers
• Plug materials later removed using acid or chemical wash,
zone restored to production

195
Outline

1. Review: Pressure and Basic Calculations


2. Review: Well Control fundamentals
3. Review: Surface Control Equipment
4. Review: Well Control Techniques
5. Completion and Workover operations
6. Fluid systems used in workover and completion
7. Production equipment and pressure control
8. Conventional, Wireline, Coiled Tubing, and
Hydraulic Workover
9. Well control situations during workovers

196
Well Control for Workover
and Completion

The End
Thank you for your attention

197

You might also like