Professional Documents
Culture Documents
Client:
Contractor:
Project reference:
967-1904-008-EGY
Document number:
MS-967-1904-008-EGY-ND
Client
Rev 00 22-Jan-20
T.D.Williamson © Page 1 of 46
T.D. Williamson sprl. 22 January 2020
Contents
1. REVISION HISTORY ....................................................................................................................................... 4
3. INTRODUCTION............................................................................................................................................... 5
T.D.Williamson © Page 2 of 46
T.D. Williamson sprl. 22 January 2020
T.D.Williamson © Page 3 of 46
T.D. Williamson sprl. 22 January 2020
1. REVISION HISTORY
T.D.Williamson © Page 4 of 46
T.D. Williamson sprl. 22 January 2020
2. CONFIDENTIALITY
This document contains information which T.D. Williamson sprl considers confidential to itself and its affiliated
companies. No part of it may be disclosed to third parties without the prior written approval of T.D. Williamson sprl.
This document and all of its parts, including tables, drawings and photographs, are © T.D. Williamson sprl, 2010.
Unauthorised copying or distribution is prohibited.
3. INTRODUCTION
The contract 967-1904-008-EGY includes the execution of one single position STOPPLE® train operation according to
the information on the application data sheet (paragraph 8.5). As the existing line cannot be taken out of service, the
“IN service STOPPLE® method” offered by T.D. Williamson sprl has been adopted.
The approach described in this document are based upon API RP 2201 and proven TD Williamson methods to achieve
the required results with total security for both equipment and personnel.
4. OBJECTIVES
TD Williamson is strongly committed to safety. Our HSE program focuses on ensuring that our personnel, the
environment and you remain protected and confident in knowing safety is our number one priority. This method
statement is focused on taking the necessary “proactive” steps to ensure that personnel exposure to HSE hazards are
eliminated or managed to an acceptable level.
This method statement is intended to prepare the Hot Tap and Plugging activities.
It describes the responsibilities of both parties to ensure a successful job completion. It records the technical data
utilized by TDW to select and prepare equipment to be mobilized and used on site. It also gives an overall view of the
operation sequences.
The document should be read carefully, commented upon (where necessary) and returned signed, to TDW. The
signature will mean that the client agrees and approves the responsibility matrix. In case of any doubt please call the
TDW Project Coordinator.
Note: The procedure included in this document is not sufficient to perform any part of TDW works without the presence
of TDW Field technicians. Only TDW Field technicians are qualified to perform these activities.
5. DEFINITIONS
The Hot Tap operation is the technique of drilling a pipeline in service.
The STOPPLE® operation is the technique of isolating a section of pipeline in service.
The Plugging operation is the technique of setting a plug onto a fitting.
A gasbag is a balloon insert in the pipeline to increase the security and containment of any leaks.
The Equalization is the technique of balancing the pressure between equipment.
The By-pass is the technique of by passing a section of pipeline.
The Fitting LOR ® is a welded branch fitting which is working with the Lock-O-Ring ® Plug.
The Fitting TOR™ is a welded branch fitting which is working with the Thread-O-Ring™ Plug.
The Sealing Element is a seal inserts in the pipeline to isolate a section.
T.D.Williamson © Page 5 of 46
T.D. Williamson sprl. 22 January 2020
6. RESPONSIBILITIES
6.1. TABLE OF RESPONSIBLITIES
Final
Step Task Responsible* Assistance** Paragraph****
Approval***
Mobilization Process
Stay Client NA TDW 6.5.2
T.D.Williamson © Page 6 of 46
T.D. Williamson sprl. 22 January 2020
T.D.Williamson © Page 7 of 46
T.D. Williamson sprl. 22 January 2020
Rigging and lifting operation. Check stack up for equipment dimension and weight. Cranes have to
Crane 2
be able to turn Tapping Machines and Sandwich valves form horizontal to vertical and vice-versa.
Chain Block 2 Rigging and lifting operation. Check stack up for equipment dimension and weight.
Rigging
Lifting Belts 4 Rigging and lifting operation. Check stack up for equipment dimension and weight.
Chain set 2 Rigging and lifting operation. Check stack up for equipment dimension and weight.
Flogging Spanners 2 Bolting operation. All Studs and Nuts from TDW are Heavy Hex. with UN design.
Bronzed faced
2 Bolting operation.
Bolting
Hammer
Nitrogen Pack * Leak testing. Check equipment stack up for equipment volume.
pressure Hose
1/4" NPT pressure
4 Leak testing control. Check pipeline pressure for maximum allowable pressure
Gauge
TD Williamson technicians need free and safe access to the top of tapping machine. Check stack up
Scaffolding *
for dimension. Guidelines for scaffolding are available in separate document HSE 0028.
Civil Work
Tapping Machine
* For all Hot Tapping operations. Check Stack up for equipment weight
Support
Air compressor 1 For tapping machine with air operated. Minimum Power: 150CFM to 90 PSI 180m³/h
T.D.Williamson © Page 8 of 46
T.D. Williamson sprl. 22 January 2020
6.5.3. Timetable
TD Williamson Field technicians have a flexible timetable. They will organize their timetable with the Client
representative. TDW Field technicians are allowed to work 10 hours a day (from/to accommodation) as long as all
safety precautions are undertaken. All overtime work has to be approved by TD Williamson Project Coordinator.
T.D.Williamson © Page 9 of 46
T.D. Williamson sprl. 22 January 2020
6.6. MANPOWER
All personnel (mentioned in the box below) are required to ensure the operation stays in line with the work schedule.
This list is not exhaustive and should be revised following the Risk analysis and the Client requirement. The TDW field
technicians will wear their own standard PPE. This consists of safety shoes, hard hat, gloves, safety glasses, fire
retardant clothing, hearing protection, safety harness and personal gas monitor. The client will provide PPE for all other
personnel involved for the work. In the case of any special PPE requirements, the client will provide this for all
personnel including TDW Field Technicians.
Coordinate all operations. Sign and approve all documents. Provide all documents work permit,
Client representative 1
Risk analysis… Ensure contact with management.
TD Williamson Field
2 Performs all Hot tap and STOPPLE® processes
Technicians
For rigging and lifting operations, bolting operations, assisting the TDW Field technicians (in all
Riggers/Fitters 2
his activities, as required)
T.D.Williamson © Page 10 of 46
T.D. Williamson sprl. 22 January 2020
7. WORK METHODOLOGY
A3 A2 A1
533mm
965mm
1150mm
1880mm
** The TOR Bleed port must be rolled over 45 or 60 degrees to allow clearance for the valve to be installed.
BLEED PORT
711mm
T.D.Williamson © Page 11 of 46
T.D. Williamson sprl. 22 January 2020
7.2.1. Before starting operation ensure that pipeline operator is in continuous communication with site operation officer as per communication
procedure.
7.2.2. Inspect all Lock O Ring ® Fittings. Control and confirm the perfect working
conditions (no rust, no scratch in O-rings location and no visual showing critical to A1 TDW field Technician
quality and safety)
7.2.3. Install the spool. Align the spool with fitting bore.
A1 TDW field Technician
(TDW will specify the applicable torque value for TDW equipment)
7.2.4. Install the valve. Align the valve with the spool bore. Open and close the
valve to ensure the workability A1 TDW field Technician
(TDW will specify the applicable torque value for TDW equipment)
7.2.5. Install and Align the valves with fitting bore. Open and close the valves to
A2 A3 TDW field Technician
ensure the workability.
7.2.6. Measure and record the distance from the top face of the SANDWICH®
A1-A2-A3 TDW field Technician
Valve, including gasket.
7.2.7. Perform the Leak Test and Hot Tap on equalizations 2” positions and Drain A2 A3 7.5.1
7.2.8. Perform the Hot Tap on STOPPLE® A1 7.5.2
7.2.9. Install bolt on support clamp A1 TDW Field Technician+ 7.1
7.2.10. Prepare the Stopple® train assembly. A1 7.5.3
7.2.11. Measure and record all the required measurement to set the Stopple® train
A1 7.5.3
Set Clearance B as per requirements 7.5.3.3 and record.
T.D.Williamson © Page 12 of 46
T.D. Williamson sprl. 22 January 2020
replace the sealing element with a new one and recommence the operation
until an acceptable working seal is achieved
Isolated section
decommissioning
7.2.17. Work on the isolated section can start. A1
according to the customer
procedure
7.2.18. Work on the isolated section is completed NA Client
7.2.19. Close the Stopple train® bleed port and set the bleed port plug. A2 TDW field technician
7.2.20. Equalize pressure in the isolated section A3 Client
CAUTION
Pressure must be equalized across the plugging head before the head can be withdrawn. If a line pressure differential exists, the plugging
head will remain locked in the line. Attempts to retract it will result in damage to the hydraulic cylinder.
Equalize pressure before retracting, and keep it equalized and ensure the zero-flow condition.
7.2.21. Retract the STOPPLE Train plugging head fully following proper retraction
A1 7.5.3
procedures.
New section is now commissioned according to the customer procedure
7.2.22. Sandwich valves can be closed. A1 TDW Field technician
7.2.23. Stopple assembly can be vent according customer procedure. A1 Client
7.2.24. Insert LOR Plug in the STOPPLE®, bypass fittings and remove temporary
A1 7.6
valves
7.2.25. Install blind flange and torque it to the right torque value A1 Client + 8.6
7.2.26. Insert TOR™ Plug in the equalization fittings and remove temporary valves A3 7.5.1.2
7.2.27. Equipment Cleaning and Job completion 6.3.5 NA
CAUTION
Make sure all pipeline product is removed from the components.
This is necessary prior to proceeding to the next job or returning components to storage.
T.D.Williamson © Page 13 of 46
T.D. Williamson sprl. 22 January 2020
7.3.1.1.1. Perform the leak test after the installation of the TDW equipment on the valve. This test will be executed before
working on the line.
7.3.1.1.2. The test medium shall be Nitrogen (N2), pipeline product or both. Note that if there is a leak between the
connections, all of the assembly will have to be drained.
7.3.1.1.3. Warning! Leak test performed at a higher pressure could collapse the pipe wall. Do not exceed the maximum
working pressure for each element of the tapping machine assembly.
Nitrogen regulator
Pressure Gauge ¼’’ high pressure Hose
Machine
¼’’ Valve
N2
T.D.Williamson © Page 14 of 46
T.D. Williamson sprl. 22 January 2020
7.4.1 Procedure
T.D.Williamson © Page 15 of 46
T.D. Williamson sprl. 22 January 2020
7.5.1.2.8. If the Thread O Ring™ Plug does not seal, remove the Thread O
T.D.Williamson © Page 16 of 46
T.D. Williamson sprl. 22 January 2020
T.D.Williamson © Page 17 of 46
T.D. Williamson sprl. 22 January 2020
T.D.Williamson © Page 18 of 46
T.D. Williamson sprl. 22 January 2020
7.5.3.2.11. TD Williamson does not guarantee a perfect seal. Several manipulations and chip sweeping of the STOPPLE® head
may be required to reach an acceptable working seal. If seal quality is not acceptable to work on the line, re-
establish the pressure in the isolated section, retract the stopple machine, replace the sealing element with a new
one and recommence the operation until an acceptable working seal is achieved.
7.5.3.2.12. Tighten the cap screw on the bar lock clamp. Torque: 230-245 Nm
T.D.Williamson © Page 19 of 46
T.D. Williamson sprl. 22 January 2020
T.D.Williamson © Page 20 of 46
T.D. Williamson sprl. 22 January 2020
T.D.Williamson © Page 21 of 46
T.D. Williamson sprl. 22 January 2020
7.7.1.2. Installation
CAUTION!
TDW recommends the installation of the centering device in the presence of a TDW Field Technician.
7.7.1.2.1. Install and weld the fitting in accordance with the applicable WPS.
7.7.1.2.2. Check the verticality and horizontality of the flange after welding of the longitudinal weld.
7.7.1.2.3. Grind all longitudinal and spiral weld seams that pass by the nozzle.
7.7.1.2.4. Fix the centre of the flange by using plumb ball, laser pointer or any other suitable means.
DO NOT use the centre of the branch ID as a reference point as it may differ from the
centre of the flange.
7.7.1.2.5. Axis of the bar of the tapping machine will be represented using the plumb ball, laser pointer
or any other suitable means.
7.7.1.2.6. Mark the position of the pilot drill on the header using permanent ink or punch mark.
T.D.Williamson © Page 22 of 46
T.D. Williamson sprl. 22 January 2020
7.7.1.2.7. Install the coupon reinforcement, aligning the centre of the centering device with the
permanent mark.
Red – Mandatory
Orange - Recommended
7.7.2.1.7. Continuous welds seams are RECOMMENDED depending on the space between pipe and
reinforcement coupon as highlighted by the locations in orange.
7.7.2.1.8. Use same pre-heating and electrodes as required by WPS used to weld the fitting on the line.
7.7.2.1.9. Each bead will be immediately reinforced by another pass on top, before starting another
one.
7.7.2.1.10. The weld seam length depends of the space between pipe and reinforcement coupon.
T.D.Williamson © Page 23 of 46
T.D. Williamson sprl. 22 January 2020
7.8. STACK UP
7.8.1. Stack up of the 28” Hot Tap on the STOPPLE® position (A1)
The same Stack up is applicable for the LOR® Plug Setting
T.D.Williamson © Page 24 of 46
T.D. Williamson sprl. 22 January 2020
T.D.Williamson © Page 25 of 46
T.D. Williamson sprl. 22 January 2020
T.D.Williamson © Page 26 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
Single Position STOPPLE® Train 28in Review: 00
8. ATTACHMENT
8.1. DATA SHEET
T.D.Williamson © Page 27 of 46
T.D. Williamson sprl. 22 January 2020
Rigging Equipment Needed: Correct weight rated adjustable single-leg chain sling with safety hook and a correct weight rated
device. See stack up for Weights and dimensions.
Rigging Equipment Needed: Two – correctly weight rated nylon slings and a correct weight rated device. See stack up for
weights and dimensions.
1) Position crane directly over the load to be moved. If other personnel are present, inform them of the move and the
need to leave the immediate area. Clear travel path of any obstacles.
2) Secure both nylon slings to hydraulic cylinders using choker hitch. Use device to connect both nylon slings
together. Attach device to hook on crane.
3) Perform a “lift test”. (Raise load slightly to test balance of the load, if load is not balanced, change sling location
and re-test)
4) Move load to the appropriate position, keeping load as low as possible, for as long as possible.
T.D.Williamson © Page 28 of 46
T.D. Williamson sprl. 22 January 2020
Rigging Equipment Needed: Correct weight rated “no hook” design four-legged lifting sling and four “shouldered” lifting eyes.
Note: A two-legged sling can be used if load rating is suitable.
1) Attach correctly weight rated lifting sling to crane using master link. Ensure safety latch is closed.
2) Install lifting eyes in Sandwich® valve outside plate holes as shown.
3) Position crane directly over the load to be moved. If other personnel are present, inform them of the move and the
need to leave the immediate area. Clear travel path of all obstacles.
4) Run chain through both lifting eyes on one end and secure chain in hook back at top near master link. Do the
same with other sling leg.
5) Perform a “lift test”. (Raise load slightly to test balance of the load, if load is not balanced, change the length of
chain leg and re-test)
6) Move load to the appropriate position, keeping load as low as possible, for as long as possible.
T.D.Williamson © Page 29 of 46
T.D. Williamson sprl. 22 January 2020
______________________________________________________________
______________________________________________________________
______________________________________________________________
T.D.Williamson © Page 30 of 46
T.D. Williamson sprl. 22 January 2020
T.D.Williamson © Page 31 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
T.D.Williamson © Page 32 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
Once the bolts /nuts are hand tight the application of torque can begin. It is recommended that the
torque be applied in a minimum of 4 stages
T.D.Williamson © Page 33 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
T.D.Williamson © Page 34 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
T.D.Williamson © Page 35 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
4. Connecting to structures
T.D.Williamson © Page 36 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
6. Access to scaffolding
T.D.Williamson © Page 37 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
Safety checklist
Check from ground Check from inside scaffold or connecting structure
1. Base soundness; adequate spread of load;
1. Check connection
manholes, excavations, power lines etc.
2. Ties, particularly on lift below working platform or,
2. Line of standards and ledgers. Standards vertical
in early vertical
3. Working on platform: Check line and even support
3. Platform loading
of boards; overhang; lapped boards and fillets
4. Guard rails and toe-boards 4. Condition of tubes and fittings
5. Security of boards, toe-boards and guardrails 5. Damage from falling material
6. Longitudinal bracing 6. Security of stacked materials
7. Means of access
T.D.Williamson © Page 38 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
Safety Checklist
Check from inside scaffold or connecting structure Check from inside scaffold or connecting structure
1. Ties, particularly on lift below working platform or,
in early stages, rakers on alternate standards.
1. Base soundness; adequate spread of load;
Special attention to 'through' ties on large flank
manholes, excavations, power lines etc.
ends without windows. Load-bearing couplers to
be used
2. Special loadings by protective fans, wind sails,
2. Line of standards and ledgers. Standards vertical
etc.; anchorage and spread of load
3. Working on platform: Check line and even support
3. Security of boards, toe-boards and guard-rails
of boards; overhang; lapped boards and fillets
4. Guard rails and toe-boards 4. Condition of tubes and fittings
5. Damage from, by loads swinging from cranes or
5. Security of boards, toe-boards and guardrails
by falling material
6. Longitudinal, ledger and plan bracing 6. Security of stacked materials
7. Means of access 7. Overloading of platform
8. Security and correct use of all fittings (couplers),
8. Staggering of joints (vertical and horizontal
particularly on transoms and bracing
9. Staggering of joints
9. Bridcage scaffold
1. Safety checklist
T.D.Williamson © Page 39 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
2. Base
4. Line of transoms
6. Plan bracing
13. Overloading
T.D.Williamson © Page 40 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
10. Check at each inspection that your scaffold does not have these faults:
Description Good Average Poor N/A Comments
Footings
Soft and uneven ☐ ☐ ☐ ☐
No base plates ☐ ☐ ☐ ☐
No sole plates ☐ ☐ ☐ ☐
Undermined ☐ ☐ ☐ ☐
Standards
Not plumb ☐ ☐ ☐ ☐
Jointed at the same height ☐ ☐ ☐ ☐
Wrong spacing ☐ ☐ ☐ ☐
Damage ☐ ☐ ☐ ☐
Ties
Some missing ☐ ☐ ☐ ☐
Loose ☐ ☐ ☐ ☐
Bracing
Some missing ☐ ☐ ☐ ☐
Loose ☐ ☐ ☐ ☐
Wrong fittings ☐ ☐ ☐ ☐
Putlogs and transoms
Loose ☐ ☐ ☐ ☐
Wrongly spaces ☐ ☐ ☐ ☐
Wrongly supported ☐ ☐ ☐ ☐
Boarding
Bad boards ☐ ☐ ☐ ☐
Trap boards ☐ ☐ ☐ ☐
Incomplete ☐ ☐ ☐ ☐
Insufficient support ☐ ☐ ☐ ☐
Ledgers
Loose ☐ ☐ ☐ ☐
Not level ☐ ☐ ☐ ☐
Joint in same level ☐ ☐ ☐ ☐
Damage ☐ ☐ ☐ ☐
Couplings
Wrong fitting ☐ ☐ ☐ ☐
No check couplers ☐ ☐ ☐ ☐
Loose ☐ ☐ ☐ ☐
Damaged ☐ ☐ ☐ ☐
Guardrails and toe-boards
Loose ☐ ☐ ☐ ☐
Wrong height ☐ ☐ ☐ ☐
Some missing ☐ ☐ ☐ ☐
Bridles
Weak support ☐ ☐ ☐ ☐
Wrong spacing ☐ ☐ ☐ ☐
Wrong coupling ☐ ☐ ☐ ☐
Ladders
Not tied ☐ ☐ ☐ ☐
Damaged ☐ ☐ ☐ ☐
T.D.Williamson © Page 41 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
High A3 B3 C3
Likelihood of
potential
consequence Medium A2 B2 C2
being realized
Low A1 B1 C1
Low 1 person at risk from that hazard Nonessential systems at risk, or essential 1
systems with immediate back-up available.
Failure would require minor adjustments to
system parameters or procedures.
Medium 2 to 4 people at risk from that hazard Essential systems at risk, back-up available 2
or repairs feasible, but not immediately.
Failure would require minor modifications or
repairs to equipment and systems or
procedural rewrite.
High 5 or more people at risk from that Essential systems at risk, no back-up. 3
hazard Failure would require major modifications or
repairs to equipment and systems, or
organizational change.
High Lost Time Incident and/or a fatality More than $2,500.00 U.S. C
or fatalities
In front of each risk you will find a fifth column, the mitigation, which leads to the final risk rating.
T.D.Williamson © Page 42 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
Poor communication - No Personnel not aware of Hold safety meeting with all involved personnel present
toolbox prior to start the job steps or hazard C3 Emergency duty call list from client and adequate B2
activity potential communication means ( satellite phone if needed)
Work without permission
Lack of adequate
& pre-job assessment C3 Job not to start without appropriate supervision B2
supervision on site
not signed
Elevated above work Only use approved/certified scaffolding + Fall arrest
Falling from height C1 B1
surface equipment
Excavation work (trench/ Collapsing of the
C2 Shoring (trench box, sheeting, timbers) B2
pit) excavation
Poor communication of the
Panic in case of incident
emergency procedures, C2 Safety meeting and pre-jobsite assessment completed B1
/ bad reactions
signals and muster points
Panic in case of incident 2 escape routes opposed to each other at a maximum
No escape routes C2 B2
/ bad reactions distance of 25 feet from the workers
Exposure to asbestos and Job to be stop awaiting decontamination + reporting to
Health hazard C3 C3
lead Nivelles
Exposure Bio/ radioactive Job to be stop awaiting decontamination + reporting to
Health hazard C3 C3
hazard Nivelles
Exposure to asphyxiates Health hazard C3 Continuous atmospheric monitoring B2
Exposure to H2S or sulphur
Health hazard C3 Continuous atmospheric monitoring B2
dioxide
Flammable gas/
Appropriate PPE following MSDS recommendation;
combustible gases or Explosion/burns C3 B2
continous atmospheric monitoring
corrosive liquids
Exposure to chemicals Contamination C1 Emergency eyewash/ shower/ appropriate PPE B1
Overhead or swinging Injury to personnel or
C2 Access to jobsite to be restricted and banksman B2
loads damage to equipment
Hearing loss/unable to
High noise levels C1 Hearing protection B1
Hear instructions
Unstable footing (muddy/
Slip, trip and fall B1 Floor stabilized A1
loose material)
Static electricity Electric shock / ignition C3 Earthing B1
Extreme temperature (hot/ Hypothermia/ Appropriate PPE / sun protection (shading) / adequate
C1 B1
cold) dehydration / heat water supply
T.D.Williamson © Page 43 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
exhaustion
Electric cables ( Electric shock / ignition Lock out tag out procedure to be in place, lines located
C3 B2
underground or overhead) Source and properly marked
Rotating parts Caught by C1 Proper guarding, barricade when guarding not practical B2
Simultaneous operations Bad communication C2 Safety meeting and pre-jobsite assessment completed B2
2 escape routes opposed to each other’s at a
Potential of flooding Drowning C1 B1
maximum distance of 25 feet from the workers
Handling equipment with Wear the appropriate type of gloves and manual
Cut C1 B1
sharp edges handling devices - use mechanical lifting equipment
T.D.Williamson © Page 44 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
Hot tap
Pneumatics hose
Flying objects C1 Whip checks in place B1
disconnected
Climbing on the machine Falling from height C1 Work platforms, ladders or scaffolding B1
Flying particles or debris
Projection during purging C1 Safety glasses / Goggles (Particle or Chemical) B1
/ chemicals splash
Handling heavy or sharp Wear the appropriate type of gloves and manual
Cut C1 B1
equipment handling devices - use mechanical lifting equipment
Simultaneous operations Bad communication C2 Safety meeting and pre jobsite assessment completed B2
Uncontrolled risks
Machine failure C3 Stop the activity and call Nivelles C3
during the operation
Fluids, high pressure gas Leak / explosion C3 Pressure test before the job B2
Environmental damage,
Spill of chemicals C3 Spill response kit, escape routes in place, proper PPE B2
injury to personnel
Remove the hot tap machine
Pure Safety lifting training + TDW rigging manual +
Manual lifting Back injury C1 B1
used of certified and checked equipment
Handling heavy or sharp Wear the appropriate type of gloves and manual
Cut C1 B1
equipment handling devices - use mechanical lifting equipment
Obstruction within the work
Slip, trip and fall B1 Good housekeeping A1
area
Obstruction of the escape No emergency
C2 Good housekeeping - keep escape routes clear B2
routes evacuation possible
Pure Safety lifting training + TDW rigging manual +
Bad posture Back injury C1 B1
used of certified and checked equipment
Handling heavy or sharp Wear the appropriate type of gloves and manual
Cut C1 B1
equipment handling devices - use mechanical lifting equipment
Obstruction within the work
Slip, trip and fall B1 Good housekeeping A1
area
Obstruction of the escape No emergency
C2 Good housekeeping - keep escape routes clear B2
routes evacuation possible
T.D.Williamson © Page 45 of 46
T.D. Williamson sprl. 22 January 2020
Repair and Rehabilitation Services Project N°: 967-1904-008-EGY
Handling heavy or sharp Wear the appropriate type of gloves and manual
Cut C1 B1
equipment handling devices - use mechanical lifting equipment
Obstruction within the work
Slip, trip and fall B1 Good housekeeping A1
area
Obstruction of the escape No emergency
C2 Good housekeeping - keep escape routes clear B2
routes evacuation possible
Pure Safety lifting training + TDW rigging manual +
Bad posture Back injury C1 B1
used of certified and checked equipment
Overhead or swinging Injury to personnel or
C2 Access to jobsite to be restricted and banksman B2
loads damage to equipment
Health Concern
Loss of hearing, unable
High noise levels C1 Hearing protection B1
to hear instructions
Potential contact with local
Health hazard C2 Vaccination B1
sickness
T.D.Williamson © Page 46 of 46