Professional Documents
Culture Documents
SPECIFICATION-ACCOMMODATION HVAC
P2104-F-MR-SOW-5002 C0 2/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
REVISIONS REVISIONS
SHEET SHEET
C0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
P2104-F-MR-SOW-5002 C0 3/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
CONTENTS
1 INTRODUCTION ..................................................................................................................... 9
1.1 PROJECT BACKGROUND ........................................................................................... 9
1.2 PROJECT OVERVIEW ................................................................................................. 9
1.3 REFERENCES DOCUMENTS .................................................................................... 11
2 BASIC DESIGN INFORMATION ........................................................................................... 12
2.1 General ....................................................................................................................... 12
2.2 Objective ..................................................................................................................... 12
2.3 Design Lifetime, Availability and Reliability .................................................................. 12
2.4 Environmental and utility Data ..................................................................................... 13
2.5 Noise and Vibration ..................................................................................................... 13
2.6 Marine Environment .................................................................................................... 13
3 GENERAL FUNCTIONAL REQUIREMENTS ........................................................................ 14
3.1 General ....................................................................................................................... 14
3.2 Existing Accommodations ........................................................................................... 14
3.2.1 MAIN DECKS .......................................................................................................... 14
3.2.2 A DECKS ................................................................................................................. 14
3.2.3 B DECKS ................................................................................................................. 15
3.2.4 C DECKS................................................................................................................. 15
3.2.5 NAV BRIDGE DECK ................................................................................................ 15
3.3 Specific Requirements ................................................................................................ 16
3.4 New Accommodations ................................................................................................. 16
3.5 A Deck ........................................................................................................................ 16
3.6 B Deck ........................................................................................................................ 16
3.7 C Deck ........................................................................................................................ 16
3.8 Nav Bridge Deck ......................................................................................................... 17
3.9 Specific Requirements ................................................................................................ 17
3.10 HVAC intake louvers ................................................................................................... 18
3.11 Provision refrigerant plant............................................................................................ 18
3.12 Electrical Requirements............................................................................................... 19
3.13 Instrument and Control ................................................................................................ 19
P2104-F-MR-SOW-5002 C0 4/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
4 NAMEPLATES ...................................................................................................................... 20
5 TAG NUMBERING ................................................................................................................ 20
6 INSPECTION AND TESTING ................................................................................................ 20
6.1 General ....................................................................................................................... 20
6.2 Inspection .................................................................................................................... 21
6.3 Mechanical Running Test ............................................................................................ 21
6.4 Function Test .............................................................................................................. 21
6.5 Acceptance Test ......................................................................................................... 22
7 MAINTENANCE REQUIREMENTS ....................................................................................... 22
8 CERTIFICATION ................................................................................................................... 22
9 SURFACE PREPARATION, PAINTING AND COATING ...................................................... 22
10 PRESERVATION, PACKING AND PREPARATION FOR SHIPMENT.................................. 23
10.1 General ....................................................................................................................... 23
10.2 Protection .................................................................................................................... 23
10.3 Non-Installed Items ..................................................................................................... 23
11 SPARE PARTS AND SPECIAL TOOLS ............................................................................... 24
11.1 Spare Parts ................................................................................................................. 24
12 INSTALLATION AND START-UP SUPERVISION ................................................................ 24
13 PRE-COMMISSIONING......................................................................................................... 24
14 COMMISSIONING ................................................................................................................. 24
15 QUALITY ASSURANCE........................................................................................................ 25
16 DOCUMENTATION ............................................................................................................... 25
16.1 Document Submission ................................................................................................ 25
16.2 Document Review ....................................................................................................... 25
16.3 Final Documentation ................................................................................................... 26
17 HEALTH, SAFETY AND ENVIRONMENTAL REGULATIONS ............................................. 26
17.1 General ....................................................................................................................... 26
17.2 HAZARDOUS MATERIAL ........................................................................................... 26
17.3 HSE MANAGEMENT SYSTEM ................................................................................... 27
17.4 HUMAN FACTORS ..................................................................................................... 27
18 VENDOR RESPONSIBILITY ................................................................................................. 27
P2104-F-MR-SOW-5002 C0 5/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
19 GUARANTEE ........................................................................................................................ 28
19.1 Mechanical Guarantee ................................................................................................ 28
19.2 Performance Guarantee .............................................................................................. 28
P2104-F-MR-SOW-5002 C0 6/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
DISTRIBUTION LISTING
Master (signed hardcopy) Document Control Center (DCC)
Hardcopy distribution
001
002
003
004
005
006
007
008
009
010
REVISION CONTROL
Description of Change Date
Copyright in the whole and every part of this document belongs to Consortium Hanochem Cakra
MTCE and the information herein contained may not be used, sold, transferred, disclosed, copied or
reproduced in whole or part in any manner or form to any person without the prior consent of
consortium.
P2104-F-MR-SOW-5002 C0 7/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
DEFINITION
BKI PT.Biro Klasifikasi Indonesia
CHARTERER MEDCO E&P NATUNA LTD (MEPN)
CLASS Appointed classification society by OWNER
MIGAS Direktorat Jenderal Minyak dan Gas Bumi (Directorate General of Oil & Gas)
OWNER Consortium of PT Hanochem Tiaka Samudera, PT Cakra Bahana & MTC
Engineering Sdn. Bhd.
PROJECT Forel FPSO Time Charter
SKKMigas Satuan Kerja Khusus Pelaksana Kegiatan Usaha Hulu Minyak dan Gas
Bumi (Special Task Force for Upstream Oil & Gas Business Activities)
VENDOR The party, which performs supply of equipment and/or material to OWNER
under CHARTERER approval
P2104-F-MR-SOW-5002 C0 8/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
ABBREVIATION
P2104-F-MR-SOW-5002 C0 9/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
1 INTRODUCTION
1.1 PROJECT BACKGROUND
The Forel Field was discovered in 1984 by the Forel 1A well and was appraised by Forel-2 well
that was drilled in 1985. The reservoirs are at depth of approximately 5000 to 5500 ft below mean
sea level in a 10 km2, 4-way dip closure. The structure is a bilobate elongated asymmetric
anticline located on the boundary high trend. These anticlines are approximately 2 km apart
separated by a low saddle as per 3D seismic interpretation. Forel-1A drilled on the Western lobe
and Forel-2 drilled on the Eastern lobe which shares the same hydrocarbon bearing reservoir with
similar depositional facies. The oil reservoirs comprise of lacustrine deltaic sands Environment of
Lower Gabus. The reservoir properties of this field such as porosity was in a range from 17% to
25%, and water saturation was in a range from 27% to 46% with average net pay thickness were
approximately 65 ft.
The 4 DST tests in Lower Gabus Formation flow oil up to 1740 bopd with GOR approximately 228
scf/stb and measured initial reservoir pressure of 2300 psi. The estimated Oil-in-place (P10-P50-
P90) of this field was calculated in a range from 54-98-148 mmbo.
Forel field development require gas injection source for pressure maintenance and lifting gas to
the reservoir. Gas lift source is also required to optimize Forel’s crude oil production. The
requirement of gas injection and gas lift at Forel will be supplied by Bronang field.
The design of Forel and Bronang field production facilities are dry tree concept where all
production wells will be placed on a wellhead platform (WHP) that is designed unmanned with
the concept of the Minimum Facility Platfrom (MFP) which is designed with a simple technology
system but has a high level of reliability and requires minimum intervention and maintenance.
Forel MFP will be routed to Floating Production, Storage and Offloading (FPSO) via multiphase
flexible pipeline for further processing to meet crude oil market requirement, while the gas is
boosted to meet the gas lift and gas injection pressure requirement. The Bronang production will
P2104-F-MR-SOW-5002 C0 10/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
be also routed to FPSO via Forel WHP to supply gas injection at initial production phase and fuel
gas throughout Forel production lifetime.
P2104-F-MR-SOW-5002 C0 11/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
P2104-F-MR-SOW-5002 C0 12/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
The VENDOR shall design the HVAC system and all associated ancillary systems for the full range
of operational and environmental conditions.
2.2 OBJECTIVE
This Specification covers the minimum requirements for the design, engineering, materials,
fabrication, inspection, testing, delivery, pre-commissioning and commissioning of all Heating,
Ventilating and Air Conditioning (HVAC) System related on existing Accommodation of the FPSO
and new installation.
The system/equipment shall be provided in accordance with this specification and the datasheets
referenced in the RFQ/PO.
Any enhancements that the VENDOR believes will promote ease of operation or reduce
maintenance may be considered in addition to these requirements.
Any exception or deviation from this specification, the datasheets, industry standards or supporting
specifications shall be clearly noted in the VENDOR’s quotation.
P2104-F-MR-SOW-5002 C0 13/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
In making assessments of the availability and reliability, the VENDOR will need to estimate
maintenance and repair times. For the purpose of making such estimates, the VENDOR may
assume that the spares holding is in accordance with its submitted recommendations unless
otherwise stated. The VENDOR may also ignore any delay caused by factors not directly related to
the package in question, unless a basis for estimating such delays is provided by the OWNER. In
the case of failure modes that make a significant contribution to the overall unavailability, the
VENDOR may be required to demonstrate that it’s assumed repair times can be achieved.
To facilitate the online preventative maintenance and calibration, the VENDOR shall provide
necessary equipment to achieve the maximum online availability and minimum preventative
maintenance down time.
In general, the maximum sound pressure level at any location one meter from the equipment shall
not exceed 85 dB (A) unless defined otherwise in the equipment data sheet. If the sound pressure
limit cannot be satisfied, VENDOR shall propose silencing measures to meet the limit. The initial
sound pressure level (i.e., without measures) and the proposed measures
VENDOR shall provide as necessary all information with regards to loads dynamic stiffness and
vibration transmitted by the base frame supports to the deck under all conditions of static and
dynamic loading.
P2104-F-MR-SOW-5002 C0 14/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
The HVAC minimum technical requirements for engineering, construction and outfitting for the
conversion and refurbishment specification for Living Quarters in FPSO shall be in accordance with
Specification of ID-F-FT-PP1-PHI-FP-00-0002- LQ and Additional LQ in FPSO Forel Bronang
Development Project [C8]
In general, the air conditioning system are divided into two (2) areas: -
• Existing Accommodation
• New Accommodation
The existing accommodation block will be retained without major modifications to the existing
ducting system, but necessary changes are foreseen due to re-arrangements of existing spaces and
the creation of new spaces.
The HVAC system may be divided into several areas, The areas are:
3.2.2 A Decks
• Recreational room- New (this room is within the existing LQ block but re-arranged/modified.)
• Smoking Room- New (this room is within the existing LQ block but re-arranged/modified.)
• Main Office Room/ICC- New (this room is within the existing LQ block but re-
arranged/modified.)
P2104-F-MR-SOW-5002 C0 15/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
• Central Control Room- New (this room is within the existing LQ block but re-
arranged/modified.)
• Cargo Oil Control Room
• Galley (There is possible changes in the galley due to changing off hot plate to a bigger size)
• Main Mess Room/ Temporary Refuge-New Extension
• Daily Provision Store
• Laundry-New
• Common Toilet
• Pipe Space
• Electrical Cable Space
• Locker Space
• Pipe and Ducting Space
3.2.3 B Decks
• 2 Men Bedroom (Owner)
• Electrical Cable Space
• Pipe and Ducting Space
• Crew’s Bathroom– Existing Area (this room is within the existing LQ block but re-
arranged/modified.)
• Crew’s Toilet
• Locker Space
3.2.4 C Decks
• 1 Man Bedroom (Owner) – Existing Area
• 2 Men Bedroom (Owner) - Existing Area
• 1 Man Bedroom (Medco) - Existing Area
• Medco OIM Office- New (this room is within the existing LQ block but re-arranged/modified.)
• Conference/Meeting Room- New (this room is within the existing LQ block but re-
arranged/modified.)
• Filing Room- Existing Area
• Medco Office No1- New (this room is within the existing LQ block but re-arranged/modified.)
• Medco Office No2- Existing Area (this room is within the existing LQ block but re-
arranged/modified.)
• Owner Office- New (this room is within the existing LQ block but re-arranged/modified.)
• Pantry- Existing Area (this room is within the existing LQ block but re-arranged/modified.)
• Pipe space- Existing Area (this room is within the existing LQ block but re-
arranged/modified.)
P2104-F-MR-SOW-5002 C0 16/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
• Surau – New (this room is within the existing LQ block but re-arranged/modified
• Ablution New (this is new space created within the existing LQ block)
• Water Closet (W.C)
The systems will be used to provide ventilation air, conditioned or not conditioned, into spaces in
order to maintain the required ambient conditions within acceptable limits. Normally air will be
supplied by means of fans. The blown in air will leave the spaces through air ducts via over pressure.
Sometimes extraction fans will be installed. In some cases, the ventilation of spaces may be done
by means of natural ventilation.
The existing HVAC air-conditioning system used for the accommodation shall be refurbished. This
includes the air-conditioning compressor and the air-handling unit in the air conditioning unit room.
VENDOR shall evaluate, calculate, and verified existing ACU capacity and heat load dissipation.
On all decks, VENDOR shall reroute any ducting as required in way of the modified accommodation
plan. Fire dampers shall be installed in ducts passing through steel accommodation decks or
bulkheads where necessary, throughout the existing accommodation.
Manual operated fire dampers shall be capable of being closed from inside the rooms.
The temperature difference in each individual room shall not exceed 3°C. Storerooms, working
rooms, laundry rooms for clothes, provision rooms and cooling and refrigerating rooms are
exempted from this requirement.
New accommodation block including but not limited to new helicopter briefing room, laundry, shall
be installed with new fully functional HVAC system.
The HVAC may be divided into several independent areas, The areas are:
3.5 A DECK
• Main Mess Room/ Temporary Refuge-New Extension
• Laundry-New
3.6 B DECK
• 4 Men Bedroom (Owner)- New Accommodation Area
3.7 C DECK
• 2 Men Bedroom (Medco) -New Accommodation Area
• 4 Men Bedroom (Medco) - New Accommodation Area
P2104-F-MR-SOW-5002 C0 17/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
New accommodation AHU room to be located at main deck next to the emergency generator room
The new smoking room shall have ventilation outlets directly to the outside.
The ventilation system with air intakes shall be located and constructed so that fire-hazardous,
noxious, or unwholesome gas, dust, etc. are prevented from penetrating into the accommodation.
The air conditioning and mechanical ventilation system shall be designed to evacuate the heat
dissipated from equipment, solar radiation etc. and to have the minimum rate of air changes per
hour, based on the volume of each compartment, as per the requirements of the relevant recognized
international standard. The performance of the system is to be specified according to MET ocean
data. The capacity of the air conditioning plant shall be designed to meet the fresh air rate
requirement of the authorities.
The temperature difference in each individual room shall not exceed 3°C. Storerooms, working
rooms, Laundry and drying rooms for clothes, provision rooms and cooling and fish and meat rooms
are exempted from this requirement.
The air-conditioning system for the extended room including Main mess Room/ Temporary shall be
supplied from the existing accommodation building through a connection to the existing ducting
system. it is to be ensured that the HVAC system is capable to meet the requirement especially for
the new and extension rooms, either by using the existing HVAC system alone OR by combination
of existing and NEW HVAC systems working in complement of each other.
A split-unit air- conditioning system shall be installed in the new helicopter briefing room if required.
All air inlets shall be located clear of hazardous areas, extraction outlets, and engine exhausts.
All intakes shall be provided with gas and smoke detectors and gas tight automatic operated closing
devices. It shall be possible to operate the dampers remotely from the Central Control Room and
locally at the dampers. Dampers shall close automatically in the event of power/air failure.
When fire is detected inside the accommodation, the air supply to and exhaust from the level on
which the fire is detected will be automatically isolated by closing the relevant dampers and stopping
relevant ventilation fans.
P2104-F-MR-SOW-5002 C0 18/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
Mechanical ventilating hoods of stainless steel with washable stainless steel grease filter to be
provided over the cooking range, deep fryer, griddles, and frying pan in galley; they will be fitted with
a fire extinguishing system.
Outlet terminal of exhaust fan from the sanitary space and galley are to be arranged away from air
intakes as far as practicable.
Duct systems shall be designed to recognized standards, such as ASHRAE and CIBSE guides, and
sized to give the design throughput at velocities that do not give rise to unreasonable noise.
Proper fittings, equipment isolation to retrieve, store and reuse of the gas from operating plant shall
be provided.
P2104-F-MR-SOW-5002 C0 19/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
Motor starters shall be incorporated within the OWNER’s switchboard / Motor Control Centre (MCC)
and interfaced with the HVAC Equipment Unit Control Panel (UCP) via either hardwired signals
direct to MCC or via Process Control System.
VENDOR scope of supply should be, but not limited to, as follows:
• HVAC Unit Control Panel i.e., UCP (shall be installed either in the CCR or ER)
• Starter panel which consists of DOL starter and contact which is hardwired from FGS / DCS
for motor to close damper upon gas detection at air intake/outlet. OWNER envisaged that
the starter panel will be installed in the same panel of the UCP.
• Local and remote control of gas tight automatic operated closing and reset devices.
VENDOR scope demarcation:
• OWNER will give power feeder to the motor damper via UCP
• Gas detector and smoke detector located in all air intakes will be under VENDOR scope of
supply
P2104-F-MR-SOW-5002 C0 20/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
4 NAMEPLATES
VENDOR shall attach a corrosion resistant nameplate on each item of equipment and valves; in an
accessible location, fastened with corrosion resistant pins. The nameplate information shall include,
as a minimum, the following in the English language:
• Purchase order and item tag number.
• Manufacturer, model & serial numbers and year built.
• Major and ancillary equipment’s serial number and type.
• Capacity Air Volume m3/s
• Weight Dry, Operation, kg
• Electrical information.
• Design code.
• Design temperature and pressure.
• Operating temperature and pressure.
5 TAG NUMBERING
Tagging of all instrumentation, electrical, mechanical, and piping items (including valves) shall be
carried out by the VENDOR in accordance with document Project Tag Coding and Equipment
Numbering System – ID-F-BU-YYO-PRO-GN-00-0001 [C5].
The main items shall have individual tag numbers as dictated by the OWNER. The actual tag numbers
will be advised to the VENDOR after award.
Tags shall be supplied with the number and description in the English language, unless otherwise
stated in the project data sheets.
Valves and instruments shall be tagged with the applicable number only.
All safety signs shall be in the English language, unless otherwise stated in the project data sheets.
Tag numbers for remaining ancillary equipment shall be given after Purchase Order placement.
P2104-F-MR-SOW-5002 C0 21/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
The VENDOR shall supply information on its quality control system, a representative quality control
plan, and a representative inspection and testing plan in his bid package. A detailed quality control
plan and an inspection and testing plan with specified inspection such as "Review, Witness & Hold
Point" for review & approval are required as part of the contract for the specified equipment.
Inspection and testing requirements shall be referring to OWNER Engineering Criticality Ratings,
applicable CHARTERER specifications, applicable code-standards, and applicable local regulation.
Acceptance will be predicted on hydraulic and mechanical performance during the witnessed
performance test as specified in the applicable industry design specification/standard.
VENDOR shall provide comprehensive inspection and test records. These records shall include all
inspection and test reports, whether undertaken by VENDOR or furnished by material or equipment
manufacturer, all certificates such as mill certificates etc., all manufacturer warranties, equipment
parts drawings, check sheet and any other documents relevant to the provision of a comprehensive
record of the quality of the work. These records shall be provided for the OWNER.
6.2 INSPECTION
The VENDOR shall provide free access to his works and that of Sub-VENDORs for the authorized
representative of the CHARTERER / OWNER and the Certifying Authority (if required).
All necessary certification on materials, shop test data, etc., shall be made available to verify that
the requirements of the purchase order are being met. No equipment surface shall be painted until
all inspection is completed.
Approval of all VENDOR's drawings, weld procedures, calculations, etc., is required by the OWNER
and the certifying authority, where applicable, prior to the commencement of fabrication.
VENDOR shall maintain acceptance/rejection forms for all types of inspection as specified. These
documents shall contain all details as required by code, including details such as item number,
quantity, specification, date of inspection, type of inspection, result, third party inspection,
certification, etc.
P2104-F-MR-SOW-5002 C0 22/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
7 MAINTENANCE REQUIREMENTS
The packages shall be designed such that all maintenance can be carried out with the minimum of special
tools. Maintenance space requirements shall be kept to a minimum.
The VENDOR shall, where appropriate, make recommendations necessary to maximize ease of operation
and maintenance for the equipment concerned, having due regard to the remote location of the oil and
gas field.
Any improvements to equipment design, material changes, or specific spares that may improve the
equipment availability shall be submitted for review by the OWNER.
As part of the installation, operation and maintenance manuals, the VENDOR shall furnish all the
necessary details for operating and maintaining the equipment in peak condition.
The Schedule of Maintenance Requirements shall be comprehensive, and shall include:
• Scheduled time for maintenance (hours run, weeks, etc.)
• Time required for activity.
• Facilities required (including personnel)
• Total costs required for activity.
8 CERTIFICATION
The VENDOR shall maintain an effective system for quality assurance and quality control, planned and
developed in conjunction with all fabrication and application functions necessary to meet the requirements
of the Purchase Order and Specification.
Material certification shall be in accordance with EN 10204. All material certifications shall be kept for
OWNER’s review.
In the event the VENDOR cannot comply with the OWNER’s painting code, the VENDOR may offer a
standard finish suitable for the environmental conditions as defined in section 3. The VENDOR shall
provide full details of the proposed paint finish with the requisition enquiry response.
The VENDOR shall obtain prior written approval of the paint specification and application procedure from
the OWNER. The decision from the OWNER is final.
P2104-F-MR-SOW-5002 C0 23/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
Each item of equipment package shall be clearly marked with the name of the VENDOR, Order
Reference number and cross referenced to a packing list, in accordance with the requirements
stated in the purchase order.
The VENDOR shall notify the OWNER prior to shipment and shall only ship upon authorization from
the OWNER.
10.2 PROTECTION
All supplied items shall be thoroughly cleaned and made free of any loose mill scale, weld spatter,
rust, etc. prior to shipment.
All components shall be pre-assembled to maximum extent possible.
All items shall be adequately packed and protected against damage during shipment. Each crate,
bag or packages shall be clearly identified with the purchase order number and identification symbol
and shall be securely fastened to the package.
Any instrumentation, internal / external parts and other equipment which might be subjected to
damage or displacement during shipment shall be protected with appropriate supports, bracing,
framing, etc. or shipped loose if appropriate with proper tagging, packing, etc.
All electrical control enclosures shall be appropriately plugged at entries and loaded with silica gel
bags.
The VENDOR shall protect all machined surfaces and flange faces with suitable removable rust
preventive.
Unless specified otherwise on the equipment data sheets, all flanged openings and flange faces
shall be protected and made waterproof by suitable metal covers with rubber gaskets. Screwed
connections left open for shipment shall be protected with plastic plugs.
When specified on the data sheets, the equipment shall have their interiors protected with a rust
inhibitor.
P2104-F-MR-SOW-5002 C0 24/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
13 PRE-COMMISSIONING
VENDOR shall make available the services of field service technical personnel to be present during pre-
commissioning activities at the OWNER’s fabrication yard.
The pre-commissioning procedures shall be developed by the VENDOR and subjected to approval by the
OWNER.
14 COMMISSIONING
VENDOR shall make available the services of field service technical personnel to supervise the
commissioning test activities.
The VENDOR shall provide in his bid the estimated costs for travel and subsistence to and from the site
location described in the inquiry. Also, the VENDOR shall provide labour rates for 12-hour workdays
onshore, as well as standby rates for the site location.
Support equipment and commissioning procedure shall be submitted by the VENDOR for approval before
loading out from VENDOR’s site.
P2104-F-MR-SOW-5002 C0 25/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
15 QUALITY ASSURANCE
The VENDOR shall operate a Quality Management System commensurate with the equipment package
and services provided. The system should generally satisfy the requirements of ISO 9001-2015 Quality
Management System [C6] or other appropriate OWNER agreed internationally recognized standard. The
VENDOR’s system shall specifically include provision for the management of sub-VENDORs.
Where possible, all testing of the equipment package shall be carried out at the VENDOR’s works in order
to minimize construction site testing. The OWNER will witness testing in accordance with an agreed test
schedule. To facilitate the identification of OWNER involvement, the VENDOR shall submit a
comprehensive Inspection and Test Plan (ITP), upon which OWNER and CHARTERER their ‘Review’,
‘Observe’, ‘Witness’ & ‘Hold’ requirements.
The ITP shall include all inspection and testing activities carried out at both VENDOR’s and sub-VENDORs
works and shall refer to all relevant testing procedures, control documents and resulting records and
reports.
16 DOCUMENTATION
16.1 DOCUMENT SUBMISSION
Document submission requirements will be specified and provided as per VENDOR
All drawings and literature shall be in English language and metric units consistent with this
specification. QA / QC documentation shall be separated from the Operating and Maintenance
Manual.
VENDOR shall also provide a master listing of his sub-VENDOR’s supplied items with description
and drawings. Data Requirement List (VDRL) in the Technical Requisition.
Hard copies of documents shall be submitted for review to the address identified on the purchase
order. Alternatively, documents may be submitted by electronic mail in original or PDF format.
P2104-F-MR-SOW-5002 C0 26/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
If goods from a VENDOR contain any substance that may be hazardous to health or the environment
as defined in OSH (Use and Standards of Exposure of Chemicals Hazardous to Health) Regulations
2000, then a Chemical/Material data sheet (in English and Bahasa Malaysia), for each substance,
signed by an authorized representative of the VENDOR shall be provided to CHARTERER.
If the consignment does not contain any hazardous substances, then a formal statement to that
effect, signed by an authorized representative of the VENDOR shall be provided to the OWNER.
P2104-F-MR-SOW-5002 C0 27/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
Where required by Purchase documentation, VENDOR shall develop a project specific Safety &
Environmental Protection Plan in compliance with the Occupational Safety and Health Act (OSHA)
1994, in particular Part V – General Duties of Designers, Fabricators and VENDORs. This shall
identify the methods, practices and procedures for ensuring the safety and environmental integrity
of the goods and how any design and assembly is managed in this respect, particularly where sub-
VENDORs are involved.
18 VENDOR RESPONSIBILITY
The VENDOR shall be responsible for the technical integrity of the equipment package including design,
materials, fabrication, assembly, testing, certification, and performance of engineering services. The
equipment package design shall reflect good engineering practice, which is fit for purpose.
The VENDOR shall be responsible for implementing any Local & National Statutory Regulations
concerning the Design, Material, Fabrication, Inspection & Testing and Preparations of Shipment of the
equipment package.
Compliance with this specification, codes and standards does not relieve the VENDOR or Sub-VENDOR
of the responsibility of supplying the equipment of proper design and construction fully suitable for all
specified operating conditions and intended services.
The VENDOR shall include for all items necessary for the safe and satisfactory operation of the equipment
package and its completion in all detail whether such items be specifically mentioned or not.
The VENDOR shall provide all special tools and equipment required for installation, commissioning and
maintenance purposes.
Any ambiguities or conflicts arising from the various codes, standards, regulations, drawings and data
sheets shall be brought to the attention of the OWNER. Any errors / omissions contained within this
P2104-F-MR-SOW-5002 C0 28/28
TITLE: SPECIFICATION-ACCOMMODATION HVAC
specification shall be brought to the attention of the OWNER. In cases of conflict the most stringent
requirements shall apply unless otherwise instructed in writing.
19 GUARANTEE
19.1 MECHANICAL GUARANTEE
The VENDOR shall guarantee the equipment package against defective materials or parts and poor
workmanship for a period of 12 months from commissioning or 24 months from date of delivery,
whichever is earlier.
VENDOR shall warrant and guarantee that all the materials and equipment incorporated in the entire
equipment under his scope shall be new, and all work shall be of good quality.
VENDOR shall also be responsible for all system and detailed designing, the aspects of which may
not have been covered in this specification as regards the workmanship, performance etc., of the
equipment supplied by him.
VENDOR shall, upon notice from OWNER, make good at his own expense all defects found during
the warranty period expeditiously.
VENDOR shall, if required, supply the services of an experienced engineer to supervise the
correction of any defects found during the warranty period.
VENDOR shall also warrant and guarantee all work, materials and equipment furnished by any sub-
VENDOR and which is incorporated in the package.