CONT.DOC.NO: B120229PPI
DOVER DOC NO: 1502-000-90-AC-S-001
REVISION LOG
O First Issue
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 2 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
TABLE OF CONTENTS
1.0 INTRODUCTION……………………………………………………………………………………………………………………..5
1.1 General......................................................................................................................................... 5
1.2 Scope and Objectives ................................................................................................................ 6
1.3 Methodology ................................................................................................................................ 6
2.0 NOTATIONS & ABBREVIATIONS………………………………………………………………………………………..7
3.0 SPECIFICATIONS, CODES AND REFERENCES……………………………………………………………10
3.1 British & Other Codes .............................................................................................................. 10
3.2 Company’s Specifications ....................................................................................................... 10
3.3 References ................................................................................................................................ 10
4.0 SUBSTATION AND CHILLER PLANT AREA…………………………………………………………………….11
4.1 Site Description and Soil Properties ...................................................................................... 11
4.1.1 Site Description & Geology ..................................................................................................... 11
4.1.2 Soil Stratigraphy........................................................................................................................ 11
4.1.3 Soil Properties ........................................................................................................................... 11
4.1.4 Ground Water Level ................................................................................................................. 12
4.1.5 Borehole Logs ........................................................................................................................... 13
4.2 Shallow Foundation .................................................................................................................. 14
Substation and Chiller Plant Area (Borehole 12) ................................................................................ 14
4.2.1 Settlement Check ..................................................................................................................... 19
4.2.2 Safe Bearing Capacities .......................................................................................................... 22
4.3 Pile Foundation ......................................................................................................................... 24
4.3.1 300 mm Driven Pile Compression Capacity Computation ................................................. 26
4.3.2 400 mm Driven Pile Compression Capacity Computation ................................................. 31
4.3.3 600 mm Driven Pile Compression Capacity Computation ................................................. 35
4.3.4 750 mm Driven Pile Compression Capacity Computation ................................................. 39
5.0 NEW ADMINISTARTIVE BUILDING EXTENSION AREA……………………………………………….43
5.1 Site Description and Soil Properties ...................................................................................... 43
5.1.1 Site Description & Geology ..................................................................................................... 43
5.1.2 Soil Stratigraphy........................................................................................................................ 43
5.1.3 Soil Properties ........................................................................................................................... 44
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 3 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.1.4 Ground Water Level ................................................................................................................. 45
5.1.5 Borehole Logs ........................................................................................................................... 46
5.2 Shallow Foundation .................................................................................................................. 49
Admin Building Extension (Borehole 1) ................................................................................................ 49
IA (Industrial Area) Admin Building Extension (Borehole 2).............................................................. 54
IA (Industrial Area) Admin Building Extension (Borehole 3).............................................................. 58
5.3 Settlement Check ..................................................................................................................... 62
5.3.1 Safe Bearing Capacities .......................................................................................................... 69
5.4 Pile Foundation ......................................................................................................................... 71
5.4.1 300 mm Driven Pile Compression Capacity Computation ................................................. 73
(Bore Hole 1) ............................................................................................................................................ 73
5.4.2 400 mm Driven Pile Compression Capacity Computation ................................................. 77
5.4.3 600 mm Driven Pile Compression Capacity Computation ................................................. 81
5.4.4 750 mm Driven Pile Compression Capacity Computation ................................................. 85
5.5 300 mm Driven Pile Compression Capacity Computation ................................................. 89
(Bore Hole 2) ............................................................................................................................................ 89
5.5.1 400 mm Driven Pile Compression Capacity Computation ................................................. 93
5.5.2 600 mm Driven Pile Compression Capacity Computation ................................................. 97
5.5.3 750 mm Driven Pile Compression Capacity Computation ............................................... 101
5.6 300 mm Driven Pile Compression Capacity Computation ............................................... 105
(Bore Hole 3) .......................................................................................................................................... 105
5.6.1 400 mm Driven Pile Compression Capacity Computation ............................................... 109
5.6.2 600 mm Driven Pile Compression Capacity Computation ............................................... 113
5.6.3 750 mm Driven Pile Compression Capacity Computation ............................................... 117
6.0 SUMMARY…………………………………………………………………………………………………………………………..121
6.1 Shallow Foundation ................................................................................................................ 121
6.2 Deep Foundation .................................................................................................................... 122
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 4 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
1.0 INTRODUCTION
1.1 General
The expansion of the NLNG Plant from a 3-Train to a 6-Train operation coupled with the
Head Office relocation from Lagos to Port Harcourt and the move of Shipping Division to
Bonny has increased requirement for office space. Many departments are currently
fragmented in Portakabins. A two-floor Administration Building Extension is to be built to
provide office space for about 270 personnel, located south of the existing Industrial Area
Administration Building.
Existing Learning Centre is no longer adequate or fit for purpose. An additional equipment,
simulator, syndicate rooms and offices for 21 staff are required. Essential major
repairs/refurbishment cannot be carried out while currently occupied. Increased capacity
and quality of facilities is required to allow the realization of the cost savings from more
Head Office staff undertaking training in Bonny instead of using 3rd Party facilities. The
New Learning Centre will be built as part of the Admin Extension complex.
Workshops in existing Learning Centre will be modified and still be used for Training.
The existing Chiller Plant has reached the end of its useful life and operates at reduced
capacity. There is no reliable service for the existing Chiller Plant and no spare capacity for
envisaged expansion nor space for expansion in existing location. A new Chiller Plant is
required and a new LV Substation 39 and extension of existing SS31 33kV switchgear to
supply power to SS37. The existing Chiller Plant will be decommissioned after the New
Chiller is installed & commissioned.
The Administration Building Extension and Learning Centre should reflect both functionality
and a modern image of an international standard office accommodation or learning
institution. The Building Complex will be designed and constructed with same specification
as the existing as is contained in the Basic Design Package.
The IA Administration and Learning Centre Project is therefore a cluster of the following
buildings and facilities:
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 5 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
1.2 Scope and Objectives
The objective of this report is to:
• Outline soil properties as obtained from the geotechnical investigation carried out by
Amaogbo Services Nigeria Limited in November 20th, 2011 and October 10th, 2013
for NLNG IA Admin Extension/Learning Centre Project.
• Compute and outline allowable bearing capacities for shallow and deep foundation for
the Previous (Chiller/Substation) area and present (IA Admin Extension) area to be
adopted for the detailed design of the infrastructural facilities in this project. The
computations are to be based on soil properties supplied by the Soil Investigation
report, Ref: 11C08467100
1.3 Methodology
The bearing capacity computations were carried out based on the subsoil investigation
reports by Amaogbo services limited which were supplied by the Client.
Computations and checks were made for both pile and shallow foundation for the previous
(Chiller/Substation) area and present (IA Admin Extension) area using the given soil
properties and findings of the Geotechnical Investigation report to establish their resistance
capacities.
Based on the ultimate values obtained, allowable values were obtained using the partial
factors of safety as provided in the code of practice for foundation BS 5930
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 6 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
2.0 NOTATIONS & ABBREVIATIONS
Cu Coefficient of uniformity
Cu Undrained shear strength
D Outer diameter of the pile/embedment depth
E Elastic modulus of material forming pile shaft
e Void ratio
F1 Reduction factor
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 7 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
N The bearing capacity factors, with subscripts for c, q and γ
Pa Atmospheric pressure = 100kN/m2
PI Plasticity Index
PL Plastic Limit
Psi Skin resistance
Qwp Load carried at the pile point under working load condition
Qws Load carried by frictional (skin) resistance under working load condition
Se Settlement
S The shape factor of the foundation base with subscripts for c, q and γ
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 8 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Wp Effective weight of pile
γ’ The design effective weight density of the soil below the foundation base
γw Effective unit weight of water
yg Ultimate pile deflection at ground level
γsub Submerged weight density of the soil
γsub Saturated Unit weight of soil
Zf Depth to point of fixity
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 9 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
3.0 SPECIFICATIONS, CODES AND REFERENCES
3.1 British & Other Codes
BS 8004 Code of Practice for Foundation
3.3 References
• NLNG IA - Additional Administrative Building Soil Investigation Report Doc No
11C0-8467100
• Foundation Design Construction 7th Edition-2001(by MJ Tomlinson)
• Pile Design and Construction Practice , 4th Edition by MJ Tomlinson
• Foundation Analysis and Design, 5th Edition, by Joseph E. Bowles.
• Structural Design Manual for Administration Office Extension and learning centre
project Doc No B-21.1023
• Principles of Foundation Engineering 6th edition by Braja M.
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 10 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
4.0 SUBSTATION AND CHILLER PLANT AREA
4.1 Site Description and Soil Properties
4.1.1 Site Description & Geology
The site area is situated within the Niger Delta of Nigeria. Specifically, the proposed
project site is within the IA of NLNG, Bonny Island. The proposed site location is
bridged with predominately a sand filled salt marsh, tidal flat.
The investigated area is located in the Niger Delta.
Layer
S/No. Description
Thickness (m)
1 GL – 3.0 Loose Brownish Fine Sand
2 3.0 – 8.25 Moderately Dense Grey sand
3 8.25 – 9.25 Soft To Firm Drak Grey Sandy Clay
4 9.25 - 12.0 Medium Dense Dark Greyish Fine to Medium Sand
5 12.0 - 15.0 Medium Dense Dark Greyish Fine to Medium Sand
For detailed properties of soil layers, refer to Appendix B Borehole Log of Soil Investigation
Report (IA Administrative Building Extension) - Ref: 11C0-8467100
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 11 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
LAYER THICKNESS
PROPERTIES
GL - 3.0M 3.0 – 8.25M 8.25-9.25M 9.25 - 15.0 M
Moisture content (%) 24.8 23.83 37.9 19.85
3 17.51
Bulk Unit Weight (KN/m ) 16.83 16.79 14.99
Liquid Limit (%) - - 24.3 -
Plastic Limit (%) - - 20 -
Undrained cohesion (kPa) - - 45 -
Angle of Internal Friction (º) 28 29.75 3 33.25
SPT (N) Blows 7 10 3 21
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 12 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
4.1.5 Borehole Logs
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 13 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
4.2 Shallow Foundation
The design calculations for shallow foundation were carried out based on the information
given in the geotechnical report and in accordance with the procedures given in the
reference codes and standards. Spreadsheets were utilized for the calculations. The bearing
capacity for shallow foundation was computed using Meyerhof method. A factor of safety of
2.0 was used to obtain the safe bearing pressures. For symbols, annotations and
abbreviations, refer to section 2.0
The results are tabulated below showing capacities at depths of 0.5m, 1.0m, 1.2m, 1.5m,
and 2.0m below ground level for typical foundation length and width dimensions.
Kp = tan2(45+Φ/2) = 2.77
Depth factor : dγ , dq
dγ, dq = 1+ 0.1kp1/2*(Df /B)
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 14 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Meyerhof
Φ
Nc Nq Nγ
0 5.14 1 0
5 6.49 1.6 0.1
10 8.34 2.5 0.4
15 10.97 3.9 1.1
20 11.83 6.4 2.9
25 20.71 10.7 6.8
26 22.25 11.8 8
28 25.79 14.7 11.2
30 30.13 18.4 15.7
32 35.47 23.2 22
34 42.14 29.4 31.1
36 50.55 37.7 44.4
38 61.31 48.9 64
40 75.25 64.1 93.6
45 133.73 134.7 262.3
50 266.5 318.5 871.7
Note:
The effective unit weight of soil (γ') rather than bulk unit weight (γ) has been used for computations
due to the high water table reported. The effect of this is a significant reduction of the soil bearing
capacities in line with recommendations of the subsoil investigation report.
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 15 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dγ 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, 2
qult (kN/m )
2
qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.05 3.525 1.277 1.277 1.083 1.166 29.403 71.676 101.08 50.54
2.0 0.5 1.00 2.00 0.50 7.05 3.525 1.138 1.138 1.083 1.083 24.344 63.903 88.25 44.12
1.0
3.0 0.5 1.50 3.00 0.33 7.05 3.525 1.092 1.092 1.083 1.083 23.357 61.312 84.67 42.33
4.0 0.5 2.00 4.00 0.25 7.05 3.525 1.069 1.069 1.083 1.083 22.863 60.016 82.88 41.44
1.5 0.75 0.75 1.00 1.00 7.05 3.525 1.277 1.277 1.055 1.055 39.909 69.841 109.75 54.87
3.0 0.75 1.50 2.00 0.50 7.05 3.525 1.138 1.138 1.055 1.055 35.581 62.267 97.85 48.92
1.5
4.5 0.75 2.25 3.00 0.33 7.05 3.525 1.092 1.092 1.055 1.055 34.138 59.742 93.88 46.94
6.0 0.75 3.00 4.00 0.25 7.05 3.525 1.069 1.069 1.055 1.055 33.417 58.479 91.90 45.95
0.5
2.0 1.0 1.00 1.00 1.00 7.05 3.525 1.277 1.277 1.042 1.042 52.513 68.923 121.44 60.72
4.0 1.0 2.00 2.00 0.50 7.05 3.525 1.138 1.138 1.042 1.042 46.818 61.448 108.27 54.13
2.0
6.0 1.0 3.00 3.00 0.33 7.05 3.525 1.092 1.092 1.042 1.042 44.919 58.957 103.88 51.94
8.0 1.0 4.00 4.00 0.25 7.05 3.525 1.069 1.069 1.042 1.042 43.970 57.711 101.68 50.84
3.0 1.5 1.50 1.00 1.00 7.05 3.525 1.277 1.277 1.028 1.028 77.721 68.005 145.73 72.86
6.0 1.5 3.00 2.00 0.50 7.05 3.525 1.138 1.138 1.028 1.028 69.292 60.630 129.92 64.96
3.0
9.0 1.5 4.50 3.00 0.33 7.05 3.525 1.092 1.092 1.028 1.028 66.482 58.172 124.65 62.33
12.0 1.5 6.00 4.00 0.25 7.05 3.525 1.069 1.069 1.028 1.028 65.077 56.942 122.02 61.01
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dγ 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2) qa = qult/2 (kN/m2)
1.0 0.5 0.50 1.00 1.00 7.05 7.05 1.277 1.277 1.166 1.166 29.403 154.365 183.77 91.88
2.0 0.5 1.00 2.00 0.50 7.05 7.05 1.138 1.138 1.166 1.166 26.214 137.624 163.84 81.92
1.0
3.0 0.5 1.50 3.00 0.33 7.05 7.05 1.092 1.092 1.166 1.166 25.151 132.044 157.19 78.60
4.0 0.5 2.00 4.00 0.25 7.05 7.05 1.069 1.069 1.166 1.166 24.620 129.253 153.87 76.94
1.5 0.75 0.75 1.00 1.00 7.05 7.05 1.277 1.277 1.111 1.111 42.007 147.023 189.03 94.52
3.0 0.75 1.50 2.00 0.50 7.05 7.05 1.138 1.138 1.111 1.111 37.451 131.078 168.53 84.26
1.5
4.5 0.75 2.25 3.00 0.33 7.05 7.05 1.092 1.092 1.111 1.111 35.932 125.764 161.70 80.85
6.0 0.75 3.00 4.00 0.25 7.05 7.05 1.069 1.069 1.111 1.111 35.173 123.106 158.28 79.14
1.0
2.0 1.0 1.00 1.00 1.00 7.05 7.05 1.277 1.277 1.083 1.083 54.611 143.353 197.96 98.98
4.0 1.0 2.00 2.00 0.50 7.05 7.05 1.138 1.138 1.083 1.083 48.688 127.806 176.49 88.25
2.0
6.0 1.0 3.00 3.00 0.33 7.05 7.05 1.092 1.092 1.083 1.083 46.714 122.623 169.34 84.67
8.0 1.0 4.00 4.00 0.25 7.05 7.05 1.069 1.069 1.083 1.083 45.727 120.032 165.76 82.88
3.0 1.5 1.50 1.00 1.00 7.05 7.05 1.277 1.277 1.055 1.055 79.818 139.682 219.50 109.75
6.0 1.5 3.00 2.00 0.50 7.05 7.05 1.138 1.138 1.055 1.055 71.162 124.533 195.69 97.85
3.0
9.0 1.5 4.50 3.00 0.33 7.05 7.05 1.092 1.092 1.055 1.055 68.276 119.483 187.76 93.88
12.0 1.5 6.00 4.00 0.25 7.05 7.05 1.069 1.069 1.055 1.055 66.834 116.959 183.79 91.90
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 16 OF 122 Rev O
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dγ 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, 2
qult (kN/m )
2
qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.05 8.46 1.277 1.277 1.200 1.200 30.242 190.524 220.77 110.38
2.0 0.5 1.00 2.00 0.50 7.05 8.46 1.138 1.138 1.200 1.200 26.962 169.862 196.82 98.41
1.0
3.0 0.5 1.50 3.00 0.33 7.05 8.46 1.092 1.092 1.200 1.200 25.869 162.974 188.84 94.42
4.0 0.5 2.00 4.00 0.25 7.05 8.46 1.069 1.069 1.200 1.200 25.322 159.530 184.85 92.43
1.5 0.75 0.75 1.00 1.00 7.05 8.46 1.277 1.277 1.133 1.133 42.846 179.952 222.80 111.40
3.0 0.75 1.50 2.00 0.50 7.05 8.46 1.138 1.138 1.133 1.133 38.199 160.436 198.64 99.32
1.5
4.5 0.75 2.25 3.00 0.33 7.05 8.46 1.092 1.092 1.133 1.133 36.650 153.931 190.58 95.29
1.2 6.0 0.75 3.00 4.00 0.25 7.05 8.46 1.069 1.069 1.133 1.133 35.876 150.678 186.55 93.28
2.0 1.0 1.00 1.00 1.00 7.05 8.46 1.277 1.277 1.100 1.100 55.450 174.666 230.12 115.06
4.0 1.0 2.00 2.00 0.50 7.05 8.46 1.138 1.138 1.100 1.100 49.436 155.723 205.16 102.58
2.0
6.0 1.0 3.00 3.00 0.33 7.05 8.46 1.092 1.092 1.100 1.100 47.431 149.409 196.84 98.42
8.0 1.0 4.00 4.00 0.25 7.05 8.46 1.069 1.069 1.100 1.100 46.429 146.252 192.68 96.34
3.0 1.5 1.50 1.00 1.00 7.05 8.46 1.277 1.277 1.067 1.067 80.657 169.380 250.04 125.02
6.0 1.5 3.00 2.00 0.50 7.05 8.46 1.138 1.138 1.067 1.067 71.910 151.011 222.92 111.46
3.0
9.0 1.5 4.50 3.00 0.33 7.05 8.46 1.092 1.092 1.067 1.067 68.994 144.887 213.88 106.94
12.0 1.5 6.00 4.00 0.25 7.05 8.46 1.069 1.069 1.067 1.067 67.536 141.826 209.36 104.68
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dγ 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, 2
qult (kN/m )
2
qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.05 10.575 1.277 1.277 1.250 1.250 31.501 248.067 279.57 139.78
2.0 0.5 1.00 2.00 0.50 7.05 10.575 1.138 1.138 1.250 1.250 28.084 221.163 249.25 124.62
1.0
3.0 0.5 1.50 3.00 0.33 7.05 10.575 1.092 1.092 1.250 1.250 26.945 212.196 239.14 119.57
4.0 0.5 2.00 4.00 0.25 7.05 10.575 1.069 1.069 1.250 1.250 26.376 207.712 234.09 117.04
1.5 0.75 0.75 1.00 1.00 7.05 10.575 1.277 1.277 1.166 1.166 44.104 231.548 275.65 137.83
3.0 0.75 1.50 2.00 0.50 7.05 10.575 1.138 1.138 1.166 1.166 39.321 206.436 245.76 122.88
1.5
4.5 0.75 2.25 3.00 0.33 7.05 10.575 1.092 1.092 1.166 1.166 37.727 198.065 235.79 117.90
6.0 0.75 3.00 4.00 0.25 7.05 10.575 1.069 1.069 1.166 1.166 36.930 193.880 230.81 115.40
1.5
2.0 1.0 1.00 1.00 1.00 7.05 10.575 1.277 1.277 1.125 1.125 56.708 223.288 280.00 140.00
4.0 1.0 2.00 2.00 0.50 7.05 10.575 1.138 1.138 1.125 1.125 50.558 199.072 249.63 124.82
2.0
6.0 1.0 3.00 3.00 0.33 7.05 10.575 1.092 1.092 1.125 1.125 48.508 191.000 239.51 119.75
8.0 1.0 4.00 4.00 0.25 7.05 10.575 1.069 1.069 1.125 1.125 47.483 186.964 234.45 117.22
3.0 1.5 1.50 1.00 1.00 7.05 10.575 1.277 1.277 1.083 1.083 81.916 215.029 296.94 148.47
6.0 1.5 3.00 2.00 0.50 7.05 10.575 1.138 1.138 1.083 1.083 73.032 191.709 264.74 132.37
3.0
9.0 1.5 4.50 3.00 0.33 7.05 10.575 1.092 1.092 1.083 1.083 70.071 183.935 254.01 127.00
12.0 1.5 6.00 4.00 0.25 7.05 10.575 1.069 1.069 1.083 1.083 68.590 180.048 248.64 124.32
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 17 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
2 2
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dγ 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m ) qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.05 14.10 1.277 1.277 1.250 1.250 31.501 330.755 362.26 181.13
2.0 0.5 1.00 2.00 0.50 7.05 14.10 1.138 1.138 1.250 1.250 28.084 294.884 322.97 161.48
1.0
3.0 0.5 1.50 3.00 0.33 7.05 14.10 1.092 1.092 1.250 1.250 26.945 282.927 309.87 154.94
4.0 0.5 2.00 4.00 0.25 7.05 14.10 1.069 1.069 1.250 1.250 26.376 276.949 303.32 151.66
1.5 0.75 0.75 1.00 1.00 7.05 14.10 1.277 1.277 1.166 1.166 44.104 308.730 352.83 176.42
3.0 0.75 1.50 2.00 0.50 7.05 14.10 1.138 1.138 1.166 1.166 39.321 275.248 314.57 157.28
1.5
4.5 0.75 2.25 3.00 0.33 7.05 14.10 1.092 1.092 1.166 1.166 37.727 264.087 301.81 150.91
6.0 0.75 3.00 4.00 0.25 7.05 14.10 1.069 1.069 1.166 1.166 36.930 258.507 295.44 147.72
2.0
2.0 1.0 1.00 1.00 1.00 7.05 14.10 1.277 1.277 1.125 1.125 56.708 297.718 354.43 177.21
4.0 1.0 2.00 2.00 0.50 7.05 14.10 1.138 1.138 1.125 1.125 50.558 265.430 315.99 157.99
2.0
6.0 1.0 3.00 3.00 0.33 7.05 14.10 1.092 1.092 1.125 1.125 48.508 254.667 303.18 151.59
8.0 1.0 4.00 4.00 0.25 7.05 14.10 1.069 1.069 1.125 1.125 47.483 249.286 296.77 148.38
3.0 1.5 1.50 1.00 1.00 7.05 14.10 1.277 1.277 1.083 1.083 81.916 286.705 368.62 184.31
6.0 1.5 3.00 2.00 0.50 7.05 14.10 1.138 1.138 1.083 1.083 73.032 255.612 328.64 164.32
3.0
9.0 1.5 4.50 3.00 0.33 7.05 14.10 1.092 1.092 1.083 1.083 70.071 245.247 315.32 157.66
12.0 1.5 6.00 4.00 0.25 7.05 14.10 1.069 1.069 1.083 1.083 68.590 240.065 308.65 154.33
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 18 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
4.2.1 Settlement Check
For detailed foundation design calculations, immediate settlement checks shall be
carried out in accordance with the code of practice for foundation.
The immediate settlement is calculated using Burland and Burbidge method from
the formula
Se = α1* α2* α3*1.25*[(L/B)/0.25+ (L/B)] 2*(B/BR) 0.7*(q1/Pa) - Principles of
Foundation Engineering by Braja M. ( Eqn 5.57)
Where
Se = Settlement
α1 = a constant for normally consolidated sand = 0.14
α2 = compressibility index = 1.71/N1.4
α3 = correction for influence depth = 1 (for normally consolidated sand)
BR = Reference width = 0.3
q = net applied pressure
Pa = atmospheric pressure = 100kN/m2
L = Length of footing
B = Width of foundation
N = SPT value
Total settlement for the infrastructural works and foundation shall be limited to a
maximum value of 25 mm as recommended in the Structural Design Criteria (Clause
9.5.3) of the Admin building, learning centre project. Where the allowable bearing
settlements yields settlements higher than the limiting value, the limiting settlement
shall be used as a criteria to determine the safe bearing capacity for spread
foundations.
Naturally, high settlements occur at greater foundation depths. In this context,
settlement shall be checked at 0.5, 1.0, 1.2, 1.5, and 2.0 meters for shallow
foundations using the allowable bearing pressures.
The table below shows the settlement computations for the different foundation
sizes at foundation depths of 0.5, 1.0, 1.2, 1.5, and 2.0 meters using calculated
allowable pressures.
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 19 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
D (m) B(m) L(m) L/B (m) α1 α2 α3 qnet (kNm2) Se
1.00 1.00 0.14 0.11 1.00 50.54 5.530
2.00 2.00 0.14 0.11 1.00 44.12 5.961
1.0
3.00 3.00 0.14 0.11 1.00 42.33 6.168
4.00 4.00 0.14 0.11 1.00 41.44 6.276
1.50 1.00 0.14 0.11 1.00 54.87 7.976
3.00 2.00 0.14 0.11 1.00 48.92 8.779
1.5
4.50 3.00 0.14 0.11 1.00 46.94 9.083
6.00 4.00 0.14 0.11 1.00 45.95 9.243
0.5
2.00 1.00 0.14 0.11 1.00 60.72 10.793
4.00 2.00 0.14 0.11 1.00 54.13 11.880
2.0
6.00 3.00 0.14 0.11 1.00 51.94 12.292
8.00 4.00 0.14 0.11 1.00 50.84 12.509
3.00 1.00 0.14 0.11 1.00 72.86 17.203
6.00 2.00 0.14 0.11 1.00 64.96 18.935
3.0
9.00 3.00 0.14 0.11 1.00 62.33 19.592
12.00 4.00 0.14 0.11 1.00 61.01 19.937
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 20 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
D (m) B(m) L(m) L/B (m) α1 α2 α3 qnet (kNm2) Se
1.00 1.00 0.14 0.11 1.00 110.38 12.079
2.00 2.00 0.14 0.11 1.00 98.41 13.295
1.0
3.00 3.00 0.14 0.11 1.00 94.42 13.756
4.00 4.00 0.14 0.11 1.00 92.43 13.998
1.50 1.00 0.14 0.11 1.00 111.40 16.191
3.00 2.00 0.14 0.11 1.00 99.32 17.821
1.5
4.50 3.00 0.14 0.11 1.00 95.29 18.439
6.00 4.00 0.14 0.11 1.00 93.28 18.764
1.2
2.00 1.00 0.14 0.11 1.00 115.06 20.453
4.00 2.00 0.14 0.11 1.00 102.58 22.512
2.0
6.00 3.00 0.14 0.11 1.00 98.42 23.293
8.00 4.00 0.14 0.11 1.00 96.34 23.704
3.00 1.00 0.14 0.11 1.00 125.02 29.518
6.00 2.00 0.14 0.11 1.00 111.46 32.489
3.0
9.00 3.00 0.14 0.11 1.00 106.94 33.616
12.00 4.00 0.14 0.11 1.00 104.68 34.209
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 21 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
D (m) B(m) L(m) L/B (m) α1 α2 α3 qnet (kNm2) Se
1.00 1.00 0.14 0.11 1.00 181.13 19.820
2.00 2.00 0.14 0.11 1.00 161.48 21.816
1.0
3.00 3.00 0.14 0.11 1.00 154.94 22.572
4.00 4.00 0.14 0.11 1.00 151.66 22.970
1.50 1.00 0.14 0.11 1.00 176.42 25.641
3.00 2.00 0.14 0.11 1.00 157.28 28.222
1.5
4.50 3.00 0.14 0.11 1.00 150.91 29.201
6.00 4.00 0.14 0.11 1.00 147.72 29.716
2.0
2.00 1.00 0.14 0.11 1.00 177.21 31.502
4.00 2.00 0.14 0.11 1.00 157.99 34.674
2.0
6.00 3.00 0.14 0.11 1.00 151.59 35.876
8.00 4.00 0.14 0.11 1.00 148.38 36.509
3.00 1.00 0.14 0.11 1.00 184.31 43.517
6.00 2.00 0.14 0.11 1.00 164.32 47.898
3.0
9.00 3.00 0.14 0.11 1.00 157.66 49.559
12.00 4.00 0.14 0.11 1.00 154.33 50.433
Find below safe bearing pressures with limiting maximum settlement values of
25mm using 24.89mm (highest safe computed settlement value) as a reference
value.
The table below shows computed settlements greater than allowable and the safe
bearing pressures corresponding to the limiting settlements
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 22 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Computed Computed Safe qnet Safe Se
D (m) B(m) L(m)
qnet (kNm2) Se (mm) (kNm )2
(mm)
4.0 124.82 27.392 113.4 24.887
2.0 6.0 119.75 28.34 105.15 24.886
8.0 117.22 28.842 101.15 24.887
1.5 3.0 148.47 35.055 105.4 24.886
6.0 132.37 38.585 85.38 24.887
3.0
9.0 127.00 39.922 79.17 24.887
12.0 124.32 40.626 76.16 24.888
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 23 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
4.3 Pile Foundation
The Design Compressive Pile Resistance, Rc,d, or the ultimate compressive capacity, Qu of
piles is determined by the equation
Where,
Therefore,
Where,
The shaft resistance, Rs;d, of the pile is determined from the following equation;
Where,
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 24 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
C1 > 0.5 for driven piles
Cu = characteristics undrained shear strength of the clay along the pile shaft
A factor of safety of 2.0 and 3.0 was used for shaft and base resistances of the pile
respectively to get the allowable compressive capacity. A global factor of safety of 2.5 was
also used as a combined check for both shaft and base resistance as can be seen from the
tables below.
Formular Reference
1. General
γd = γ/(1+w) Foundation Analysis and Design,
e = (Gsγw/γd)-1 5th Edition, by Joseph E. Bowles.
γsat = (Gs + e)γw/(1+e) (From Eqn 4.4)
γ' = γsul = γsat - γw
Nq = eπtanφtan2(45+φ/2)
Foundation Analysis and Design,
Nγ = (Nq - 1)tan(1.4φ) 5th Edition, by Joseph E. Bowles
(Table 4-1)
Nc = (Nq - 1)Cotφ - it is usually taken as 0.9
The Meyerhof critical depth approach was used to compute shaft resistance for 300mm,
400mm, 600mm and 750mm diameter driven piles as shown below.
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 25 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
4.3.1 300 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m 3
Mg/m 3
kN/m 3
% - kN/m 2
kN/m 3
- kN/m 3
kN/m3
Loose Brownish Fine sand 3.00 3.00 9.81 1.623 15.92 24.80 2.67 0.00 12.76 1.05 17.79 7.98
Moderately Dense Grey Sand 8.25 5.25 9.81 1.712 16.79 23.65 2.67 0.00 13.58 0.93 18.31 8.50
Soft To Firm Drak Grey Sandy
9.25 1.00 9.81 1.528 14.99 37.90 2.58 45.00 10.87 1.33 16.47 6.66
Clay
Medium Dense Dark Greyish
12.00 2.75 9.81 1.785 17.51 19.85 2.58 0.00 14.61 0.73 18.76 8.95
Fine to Medium Sand
Medium Dense Dark Greyish
15.00 3.00 9.81 1.785 17.51 19.85 2.58 0.00 14.61 0.73 18.76 8.95
Fine to Medium Sand
< Borehole log - BH 12 >
γ sub =
Soil Depth Thk. α ca K δ tanδ Df q'=γ sub D f ∑q'
γ sat -γ w
Type
kN/m2 kN/m2 kN/m2
3
m m - - ˚ - m kN/m
Loose Brownish Fine sand 3 3 0.00 0.00 0.53 21.00 0.38 3.00 7.98 23.94 23.94
Moderately Dense Grey Sand 8.25 5.25 0.00 0.00 0.50 22.31 0.41 5.25 8.50 44.60 68.54
Soft To Firm Drak Grey Sandy
9.25 1.00 0.76 34.02 0.95 2.25 0.04 1.00 6.66 6.66 75.20
Clay
Medium Dense Dark Greyish
12 2.75 0.00 0.00 0.46 24.75 0.46 2.75 8.95 24.61 99.80
Fine to Medium Sand
Medium Dense Dark Greyish
15 3.00 0.00 0.00 0.43 26.25 0.49 3.00 8.95 26.84 126.64
Fine to Medium Sand
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 26 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Loose Brownish Fine sand 3.00 3.00 4.88 13.78 13.78 352.37 24.91 38.69
Moderately Dense Grey Sand 8.25 5.25 14.17 70.11 83.90 1226.02 86.66 170.56
Soft To Firm Drak Grey Sandy
9.25 1.00 36.82 34.70 118.60 98.45 6.96 125.56
Clay
Medium Dense Dark Greyish
12.00 2.75 20.95 54.30 172.90 2604.04 184.07 356.97
Fine to Medium Sand
Medium Dense Dark Greyish
15.00 3.00 26.63 75.30 248.20 4216.78 298.07 546.27
Fine to Medium Sand
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 27 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
300mm Driven Pile Tension Capacity Computation
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 28 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
300 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition, by MJ
Tomlinson
Hu = 2M u / (e+z f ) = 304.68 kN (from Equation 6.24)
Ha = 101.56 kN
where M u = ultimate Moment
= σmaxZ = 633.87 kNm
σmax = F y /1.15 = 239130 kN/m 2
4
Z = π(D ) / 32D = 0.0026507 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 29 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
300 mm Driven Pile Settlement Computation
Settlement of Piles Foundation Analysis
H p = H a + H pt & Design- 5th Edition
by Joseph E. Bowles
(from Equation 11.72)
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
2
H pt = [qD(1- μ )/ E s ]I F F 1 (from Equation 5-16a)
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 30 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
4.3.2 400 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose Brownish Fine sand 3.00 3.00 9.81 1.623 15.92 24.80 2.67 0.00 12.76 1.05 17.79 7.98
Moderately Dense Grey Sand 8.25 5.25 9.81 1.712 16.79 23.65 2.67 0.00 13.58 0.93 18.31 8.50
Soft To Firm Drak Grey Sandy
9.25 1.00 9.81 1.528 14.99 37.90 2.58 45.00 10.87 1.33 16.47 6.66
Clay
12.00 2.75 9.81 1.785 17.51 19.85 2.58 0.00 14.61 0.73 18.76 8.95
Medium Dense Dark Greyish
Fine to Medium Sand
15.00 3.00 9.81 1.785 17.51 19.85 2.58 0.00 14.61 0.73 18.76 8.95
γ sub =
Soil Depth Thk. α ca K δ tanδ Df q'=γ sub D f ∑q'
γ sat -γ w
Type
m m - kN/m
2
- ˚ - m kN/m3 kN/m
2
kN/m
2
Loose Brownish Fine sand 3 3 0.00 0.00 0.53 21.00 0.38 3.00 7.98 23.94 23.94
Moderately Dense Grey Sand 8.25 5.25 0.00 0.00 0.50 22.31 0.41 5.25 8.50 44.60 68.54
Soft To Firm Drak Grey Sandy
9.25 1.00 0.76 34.02 0.95 2.25 0.04 1.00 6.66 6.66 75.20
Clay
Medium Dense Dark Greyish 12 2.75 0.00 0.00 0.46 24.75 0.46 2.75 8.95 24.61 99.80
Fine to Medium Sand
15 3.00 0.00 0.00 0.43 26.25 0.49 3.00 8.95 26.84 126.64
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 31 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Loose Brownish Fine sand 3.00 3.00 4.88 18.38 18.38 352.37 44.28 62.66
Moderately Dense Grey Sand 8.25 5.25 14.17 93.49 111.86 1226.02 154.07 265.93
Soft To Firm Drak Grey Sandy
9.25 1.00 36.82 46.27 158.13 98.45 12.37 170.50
Clay
Medium Dense Dark Greyish 12.00 2.75 20.95 72.40 230.53 2604.04 327.23 557.77
Fine to Medium Sand
15.00 3.00 26.63 100.40 330.93 4216.78 529.90 860.83
Medium Dense Dark Greyish 12.00 2.75 72.40 230.53 25 37.70 102.10 332.63 4.00 83.16
Fine to Medium Sand
15.00 3.00 100.40 330.93 25 47.12 149.23 480.16 4.00 120.04
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 32 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
400 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
by MJ Tomlinson
Hu = 2M u / (e+z f ) = 603.55 kN (from Equation 6.24)
Ha = 201.18 kN
where M u = ultimate Moment
= σmaxZ = 1502.5 kNm
σmax = F y /1.15 = 239130 kN/m 2
Z = π(D 4 ) / 32D = 0.0062832 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 33 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
400 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 34 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
4.3.3 600 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose Brownish Fine sand 3.00 3.00 9.81 1.623 15.92 24.80 2.67 0.00 12.76 1.05 17.79 7.98
Moderately Dense Grey Sand 8.25 5.25 9.81 1.712 16.79 23.65 2.67 0.00 13.58 0.93 18.31 8.50
Soft To Firm Drak Grey Sandy
9.25 1.00 9.81 1.528 14.99 37.90 2.58 45.00 10.87 1.33 16.47 6.66
Clay
12.00 2.75 9.81 1.785 17.51 19.85 2.58 0.00 14.61 0.73 18.76 8.95
Medium Dense Dark Greyish
Fine to Medium Sand
15.00 3.00 9.81 1.785 17.51 19.85 2.58 0.00 14.61 0.73 18.76 8.95
Loose Brownish Fine sand 3 3 0.00 0.00 0.53 21.00 0.38 3.00 7.98 23.94 23.94
Moderately Dense Grey Sand 8.25 5.25 0.00 0.00 0.50 22.31 0.41 5.25 8.50 44.60 68.54
Soft To Firm Drak Grey Sandy
9.25 1.00 0.76 34.02 0.95 2.25 0.04 1.00 6.66 6.66 75.20
Clay
Medium Dense Dark Greyish 12 2.75 0.00 0.00 0.46 24.75 0.46 2.75 8.95 24.61 99.80
Fine to Medium Sand
15 3.00 0.00 0.00 0.43 26.25 0.49 3.00 8.95 26.84 126.64
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 35 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Loose Brownish Fine sand 3.00 3.00 4.88 27.57 27.57 352.37 99.63 127.20
Moderately Dense Grey Sand 8.25 5.25 14.17 140.23 167.80 1226.02 346.65 514.45
Soft To Firm Drak Grey Sandy
9.25 1.00 36.82 69.40 237.20 98.45 27.84 265.03
Clay
Medium Dense Dark Greyish 12.00 2.75 20.95 108.60 345.80 2604.04 736.27 1082.07
Fine to Medium Sand
15.00 3.00 26.63 150.60 496.40 4216.78 1192.27 1688.67
Medium Dense Dark Greyish 12.00 2.75 108.60 345.80 25 84.82 229.73 575.53 4.00 143.88
Fine to Medium Sand
15.00 3.00 150.60 496.40 25 106.03 335.76 832.16 4.00 208.04
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 36 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
600 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
by MJ Tomlinson
Hu = 2M u / (e+z f ) = 1559.5 kN (from Equation 6.24)
Ha = 519.82 kN
where M u = ultimate Moment
= σmaxZ = 5070.9 kNm
σmax = F y /1.15 = 239130 kN/m 2
4
Z = π(D ) / 32D = 0.0212058 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 37 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
600 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 38 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
4.3.4 750 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose Brownish Fine sand 3.00 3.00 9.81 1.623 15.92 24.80 2.67 0.00 12.76 1.05 17.79 7.98
Moderately Dense Grey Sand 8.25 5.25 9.81 1.712 16.79 23.65 2.67 0.00 13.58 0.93 18.31 8.50
Soft To Firm Drak Grey Sandy
9.25 1.00 9.81 1.528 14.99 37.90 2.58 45.00 10.87 1.33 16.47 6.66
Clay
12.00 2.75 9.81 1.785 17.51 19.85 2.58 0.00 14.61 0.73 18.76 8.95
Medium Dense Dark Greyish
Fine to Medium Sand
15.00 3.00 9.81 1.785 17.51 19.85 2.58 0.00 14.61 0.73 18.76 8.95
Loose Brownish Fine sand 3 3 0.00 0.00 0.53 21.00 0.38 3.00 7.98 23.94 23.94
Moderately Dense Grey Sand 8.25 5.25 0.00 0.00 0.50 22.31 0.41 5.25 8.50 44.60 68.54
Soft To Firm Drak Grey Sandy
9.25 1.00 0.76 34.02 0.95 2.25 0.04 1.00 6.66 6.66 75.20
Clay
Medium Dense Dark Greyish 12 2.75 0.00 0.00 0.46 24.75 0.46 2.75 8.95 24.61 99.80
Fine to Medium Sand
15 3.00 0.00 0.00 0.43 26.25 0.49 3.00 8.95 26.84 126.64
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 39 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Loose Brownish Fine sand 3.00 3.00 4.88 34.46 34.46 352.37 155.67 190.13
Moderately Dense Grey Sand 8.25 5.25 14.17 175.29 209.75 1226.02 541.64 751.38
Soft To Firm Drak Grey Sandy
9.25 1.00 36.82 86.75 296.50 98.45 43.49 339.99
Clay
Medium Dense Dark Greyish 12.00 2.75 20.95 135.75 432.25 2604.04 1150.43 1582.68
Fine to Medium Sand
15.00 3.00 26.63 188.25 620.50 4216.78 1862.92 2483.42
Medium Dense Dark Greyish 12.00 2.75 135.75 432.25 25 132.54 358.95 791.20 4.00 197.80
Fine to Medium Sand
15.00 3.00 188.25 620.50 25 165.67 524.62 1145.12 4.00 286.28
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 40 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
750 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
by MJ Tomlinson
Hu = 2M u / (e+z f ) = 2613.6 kN (from Equation 6.24)
Ha = 871.19 kN
where Mu = ultimate Moment
= σmaxZ = 9904.2 kNm
σmax = F y /1.15 = 239130 kN/m 2
4
Z = π(D ) / 32D = 0.0414175 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 41 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
750 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 42 OF 121 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.0 NEW ADMINISTRATIVE BUILDING EXTENSION AREA
5.1 Site Description and Soil Properties
5.1.1 Site Description & Geology
The site area is situated within the Niger Delta of Nigeria. The subsurface conditions
at the site were explored in order to determine the geotechnical properties for the
upgrade of infrastructural facilities in IA (Industrial Area) Admin Extension, Bonny
Island.
The proposed site location is bridged with predominately a sand filled salt marsh, tidal
flat. The investigated area is located in the Niger Delta
A total of 3 boreholes was drilled and soil penetration test at every 1.0 m from
existing ground level up to a depth of 15 m
Layer
S/No. Description
Thickness (m)
1 GL - 0.75 TOPSOIL, dark brownish grey, clayey
2 0.75 - 3.0 CLAY, Sandy, firm, dark brown, Lateritic
3 3.0 - 7.0 CLAY, Silty, firm, greyish brown
4 7.0 - 12.0 CLAY, Silty, firm to stiff, grey, yellowish dusty, mottled
5 12.0 - 15.0 CLAY, Silty, firm to stiff, grey, yellowish dusty, mottled
Layer
S/No. Description
Thickness (m)
1 GL - 0.75 TOPSOIL, dark brownish grey, clayey
2 0.75 - 3.0 CLAY, Sandy, firm, dark brown, Lateritic
3 3.0 - 7.0 CLAY, Silty, firm, greyish brown
4 7.0 - 12.0 CLAY, Silty, firm to stiff, grey, yellowish dusty, mottled
5 12.0 - 15.0 CLAY, Silty, firm to stiff, grey, yellowish dusty, mottled
Layer
S/No. Description
Thickness (m)
1 GL - 0.75 TOPSOIL, dark brownish grey, clayey
2 0.75 - 3.0 CLAY, Sandy, firm, dark brown, Lateritic
3 3.0 - 7.0 CLAY, Silty, firm, greyish brown
4 7.0 - 12.0 CLAY, Silty, firm to stiff, grey, yellowish dusty, mottled
5 12.0 - 15.0 CLAY, Silty, firm to stiff, grey, yellowish dusty, mottled
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 43 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
For general site vicinity map and detailed properties of soil layers, refer to Appendix A and B
(Borehole Log) respectively of Soil Investigation Report (IA Administrative Building
Extension) - Ref: 11C0-8467100
LAYER THICKNESS
PROPERTIES
GL - 3.7M 3.7 – 15.0M
Moisture content (%) 17.96 27.26
Bulk Unit Weight (KN/m3) 17.63 16.90
Liquid Limit (%) 19.75 26.15
Plastic Limit (%) - -
Undrained cohesion (kPa) - -
Angle of Internal Friction (º) 34.50 32
SPT N (Blows) 26 17
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 44 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Table 5.5: Average Soil property parameters for BH 2
LAYER THICKNESS
PROPERTIES
GL – 4.0M 4.0 – 4.7M 4.7 – 15M
Moisture content (%) 18.40 20.2 26.40
Bulk Unit Weight (KN/m3) 17.45 16.40 17.03
Liquid Limit (%) - - -
Plastic Limit (%) - - -
Undrained cohesion (kPa) - - -
LAYER THICKNESS
PROPERTIES
GL – 2.7M 2.7 – 4.6M 4.6 – 15M
Moisture content (%) 30.9 48.1 24.7
Bulk Unit Weight (KN/m3) 16.55 15.39 16.85
Liquid Limit (%) - - -
Plastic Limit (%) - - -
Undrained cohesion (kPa) - - -
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 45 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.1.5 Borehole Logs
Borehole 1
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 46 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Borehole 2
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 47 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Borehole 3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 48 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.2 Shallow Foundation
The design calculations for shallow foundation were carried out based on the information
given in the geotechnical report and in accordance with the procedures given in the
reference codes and standards. Spreadsheets were utilized for the calculations. The bearing
capacity for shallow foundation was computed using Meyerhof method. A factor of safety of
2.0 was used to obtain the safe bearing pressures. For symbols, annotations and
abbreviations, refer to section 2.0
The results are tabulated below showing capacities at depths of 0.5m, 1.0m, 1.2m, 1.5m,
and 2.0m below ground level for typical foundation length and width dimensions.
Meyerhof's Formula
Qult = cNcscdc + qNqsqdq + 0.5γB'Nγsγ
But c = 0
Qult = qNqsqdq + 0.5γB'Nγsγ
Allowable bearing capacity Qa = Qult/F.S
where
F.S = Factor of Safety = 2.0
Shape factor : sγ , sq
s γ, s q = 1 + 0.1kp (B/L)
2
Kp = tan (45+Φ/2) = 4.20
Depth factor : dγ , dq
1/2
dγ, dq = 1+ 0.1kp *(Df /B)
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 49 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Meyerhof
Φ
Nc Nq Nγ
0 5.14 1 0
5 6.49 1.6 0.1
10 8.34 2.5 0.4
15 10.97 3.9 1.1
20 11.83 6.4 2.9
25 20.71 10.7 6.8
26 22.25 11.8 8
28 25.79 14.7 11.2
30 30.13 18.4 15.7
32 35.47 23.2 22
34 42.14 29.4 31.1
36 50.55 37.7 44.4
38 61.31 48.9 64
40 75.25 64.1 93.6
45 133.73 134.7 262.3
50 266.5 318.5 871.7
Note:
The effective unit weight of soil (γ') rather than bulk unit weight (γ) has been used for computations
due to the high water table reported for Bore hole 1, 2 & 3. The effect of this is a significant reduction
of the soil bearing capacities in line with recommendations of the subsoil investigation report.
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 50 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
2
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2) qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.82 3.91 1.420 1.420 1.103 1.205 214.155 299.415 513.57 256.78
2.0 0.5 1.00 2.00 0.50 7.82 3.91 1.210 1.210 1.103 1.103 166.941 255.107 422.05 211.02
1.0
3.0 0.5 1.50 3.00 0.33 7.82 3.91 1.140 1.140 1.103 1.103 157.276 240.338 397.61 198.81
4.0 0.5 2.00 4.00 0.25 7.82 3.91 1.105 1.105 1.103 1.103 152.444 232.954 385.40 192.70
1.5 0.75 0.75 1.00 1.00 7.82 3.91 1.420 1.420 1.068 1.068 284.795 290.135 574.93 287.46
3.0 0.75 1.50 2.00 0.50 7.82 3.91 1.210 1.210 1.068 1.068 242.651 247.200 489.85 244.93
1.5
4.5 0.75 2.25 3.00 0.33 7.82 3.91 1.140 1.140 1.068 1.068 228.603 232.889 461.49 230.75
6.0 0.75 3.00 4.00 0.25 7.82 3.91 1.105 1.105 1.068 1.068 221.579 225.733 447.31 223.66
0.5
2.0 1.0 1.00 1.00 1.00 7.82 3.91 1.420 1.420 1.051 1.051 373.653 285.494 659.15 329.57
4.0 1.0 2.00 2.00 0.50 7.82 3.91 1.210 1.210 1.051 1.051 318.360 243.247 561.61 280.80
2.0
6.0 1.0 3.00 3.00 0.33 7.82 3.91 1.140 1.140 1.051 1.051 299.929 229.164 529.09 264.55
8.0 1.0 4.00 4.00 0.25 7.82 3.91 1.105 1.105 1.051 1.051 290.713 222.123 512.84 256.42
3.0 1.5 1.50 1.00 1.00 7.82 3.91 1.420 1.420 1.034 1.034 551.371 280.854 832.22 416.11
6.0 1.5 3.00 2.00 0.50 7.82 3.91 1.210 1.210 1.034 1.034 469.779 239.293 709.07 354.54
3.0
9.0 1.5 4.50 3.00 0.33 7.82 3.91 1.140 1.140 1.034 1.034 442.581 225.440 668.02 334.01
12.0 1.5 6.00 4.00 0.25 7.82 3.91 1.105 1.105 1.034 1.034 428.983 218.513 647.50 323.75
2
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2) qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.82 7.82 1.420 1.420 1.205 1.205 214.155 654.510 868.67 434.33
2.0 0.5 1.00 2.00 0.50 7.82 7.82 1.210 1.210 1.205 1.205 182.464 557.656 740.12 370.06
1.0
3.0 0.5 1.50 3.00 0.33 7.82 7.82 1.140 1.140 1.205 1.205 171.901 525.371 697.27 348.64
4.0 0.5 2.00 4.00 0.25 7.82 7.82 1.105 1.105 1.205 1.205 166.619 509.228 675.85 337.92
1.5 0.75 0.75 1.00 1.00 7.82 7.82 1.420 1.420 1.137 1.137 303.013 617.390 920.40 460.20
3.0 0.75 1.50 2.00 0.50 7.82 7.82 1.210 1.210 1.137 1.137 258.173 526.028 784.20 392.10
1.5
4.5 0.75 2.25 3.00 0.33 7.82 7.82 1.140 1.140 1.137 1.137 243.227 495.574 738.80 369.40
6.0 0.75 3.00 4.00 0.25 7.82 7.82 1.105 1.105 1.137 1.137 235.753 480.348 716.10 358.05
1.0
2.0 1.0 1.00 1.00 1.00 7.82 7.82 1.420 1.420 1.103 1.103 391.872 598.829 990.70 495.35
4.0 1.0 2.00 2.00 0.50 7.82 7.82 1.210 1.210 1.103 1.103 333.883 510.214 844.10 422.05
2.0
6.0 1.0 3.00 3.00 0.33 7.82 7.82 1.140 1.140 1.103 1.103 314.553 480.676 795.23 397.61
8.0 1.0 4.00 4.00 0.25 7.82 7.82 1.105 1.105 1.103 1.103 304.888 465.907 770.80 385.40
3.0 1.5 1.50 1.00 1.00 7.82 7.82 1.420 1.420 1.068 1.068 569.589 580.269 1149.86 574.93
6.0 1.5 3.00 2.00 0.50 7.82 7.82 1.210 1.210 1.068 1.068 485.301 494.401 979.70 489.85
3.0
9.0 1.5 4.50 3.00 0.33 7.82 7.82 1.140 1.140 1.068 1.068 457.205 465.778 922.98 461.49
12.0 1.5 6.00 4.00 0.25 7.82 7.82 1.105 1.105 1.068 1.068 443.157 451.467 894.62 447.31
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 51 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
2
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2) qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.82 9.384 1.420 1.420 1.246 1.246 221.442 812.139 1033.58 516.79
2.0 0.5 1.00 2.00 0.50 7.82 9.384 1.210 1.210 1.246 1.246 188.673 691.959 880.63 440.32
1.0
3.0 0.5 1.50 3.00 0.33 7.82 9.384 1.140 1.140 1.246 1.246 177.750 651.899 829.65 414.82
4.0 0.5 2.00 4.00 0.25 7.82 9.384 1.105 1.105 1.246 1.246 172.289 631.868 804.16 402.08
1.5 0.75 0.75 1.00 1.00 7.82 9.384 1.420 1.420 1.164 1.164 310.301 758.686 1068.99 534.49
3.0 0.75 1.50 2.00 0.50 7.82 9.384 1.210 1.210 1.164 1.164 264.382 646.415 910.80 455.40
1.5
4.5 0.75 2.25 3.00 0.33 7.82 9.384 1.140 1.140 1.164 1.164 249.076 608.992 858.07 429.03
6.0 0.75 3.00 4.00 0.25 7.82 9.384 1.105 1.105 1.164 1.164 241.423 590.280 831.70 415.85
1.2
2.0 1.0 1.00 1.00 1.00 7.82 9.384 1.420 1.420 1.123 1.123 399.159 731.959 1131.12 565.56
4.0 1.0 2.00 2.00 0.50 7.82 9.384 1.210 1.210 1.123 1.123 340.092 623.643 963.74 481.87
2.0
6.0 1.0 3.00 3.00 0.33 7.82 9.384 1.140 1.140 1.123 1.123 320.403 587.538 907.94 453.97
8.0 1.0 4.00 4.00 0.25 7.82 9.384 1.105 1.105 1.123 1.123 310.558 569.486 880.04 440.02
3.0 1.5 1.50 1.00 1.00 7.82 9.384 1.420 1.420 1.082 1.082 576.877 705.232 1282.11 641.05
6.0 1.5 3.00 2.00 0.50 7.82 9.384 1.210 1.210 1.082 1.082 491.510 600.871 1092.38 546.19
3.0
9.0 1.5 4.50 3.00 0.33 7.82 9.384 1.140 1.140 1.082 1.082 463.055 566.085 1029.14 514.57
12.0 1.5 6.00 4.00 0.25 7.82 9.384 1.105 1.105 1.082 1.082 448.827 548.691 997.52 498.76
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2)
2
qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.82 11.73 1.420 1.420 1.308 1.308 232.373 1065.287 1297.66 648.83
2.0 0.5 1.00 2.00 0.50 7.82 11.73 1.210 1.210 1.308 1.308 197.987 907.646 1105.63 552.82
1.0
3.0 0.5 1.50 3.00 0.33 7.82 11.73 1.140 1.140 1.308 1.308 186.525 855.098 1041.62 520.81
4.0 0.5 2.00 4.00 0.25 7.82 11.73 1.105 1.105 1.308 1.308 180.793 828.825 1009.62 504.81
1.5 0.75 0.75 1.00 1.00 7.82 11.73 1.420 1.420 1.205 1.205 321.232 981.765 1303.00 651.50
3.0 0.75 1.50 2.00 0.50 7.82 11.73 1.210 1.210 1.205 1.205 273.696 836.484 1110.18 555.09
1.5
4.5 0.75 2.25 3.00 0.33 7.82 11.73 1.140 1.140 1.205 1.205 257.851 788.056 1045.91 522.95
6.0 0.75 3.00 4.00 0.25 7.82 11.73 1.105 1.105 1.205 1.205 249.928 763.843 1013.77 506.89
1.5
2.0 1.0 1.00 1.00 1.00 7.82 11.73 1.420 1.420 1.154 1.154 410.091 940.005 1350.10 675.05
4.0 1.0 2.00 2.00 0.50 7.82 11.73 1.210 1.210 1.154 1.154 349.405 800.903 1150.31 575.15
2.0
6.0 1.0 3.00 3.00 0.33 7.82 11.73 1.140 1.140 1.154 1.154 329.177 754.535 1083.71 541.86
8.0 1.0 4.00 4.00 0.25 7.82 11.73 1.105 1.105 1.154 1.154 319.063 731.352 1050.41 525.21
3.0 1.5 1.50 1.00 1.00 7.82 11.73 1.420 1.420 1.103 1.103 587.808 898.244 1486.05 743.03
6.0 1.5 3.00 2.00 0.50 7.82 11.73 1.210 1.210 1.103 1.103 500.824 765.322 1266.15 633.07
3.0
9.0 1.5 4.50 3.00 0.33 7.82 11.73 1.140 1.140 1.103 1.103 471.829 721.014 1192.84 596.42
12.0 1.5 6.00 4.00 0.25 7.82 11.73 1.105 1.105 1.103 1.103 457.332 698.861 1156.19 578.10
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 52 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2)
2
qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.82 15.64 1.420 1.420 1.308 1.308 232.373 1420.383 1652.76 826.38
2.0 0.5 1.00 2.00 0.50 7.82 15.64 1.210 1.210 1.308 1.308 197.987 1210.194 1408.18 704.09
1.0
3.0 0.5 1.50 3.00 0.33 7.82 15.64 1.140 1.140 1.308 1.308 186.525 1140.131 1326.66 663.33
4.0 0.5 2.00 4.00 0.25 7.82 15.64 1.105 1.105 1.308 1.308 180.793 1105.100 1285.89 642.95
1.5 0.75 0.75 1.00 1.00 7.82 15.64 1.420 1.420 1.205 1.205 321.232 1309.021 1630.25 815.13
3.0 0.75 1.50 2.00 0.50 7.82 15.64 1.210 1.210 1.205 1.205 273.696 1115.312 1389.01 694.50
1.5
4.5 0.75 2.25 3.00 0.33 7.82 15.64 1.140 1.140 1.205 1.205 257.851 1050.742 1308.59 654.30
6.0 0.75 3.00 4.00 0.25 7.82 15.64 1.105 1.105 1.205 1.205 249.928 1018.457 1268.39 634.19
2.0
2.0 1.0 1.00 1.00 1.00 7.82 15.64 1.420 1.420 1.154 1.154 410.091 1253.340 1663.43 831.72
4.0 1.0 2.00 2.00 0.50 7.82 15.64 1.210 1.210 1.154 1.154 349.405 1067.870 1417.28 708.64
2.0
6.0 1.0 3.00 3.00 0.33 7.82 15.64 1.140 1.140 1.154 1.154 329.177 1006.047 1335.22 667.61
8.0 1.0 4.00 4.00 0.25 7.82 15.64 1.105 1.105 1.154 1.154 319.063 975.136 1294.20 647.10
3.0 1.5 1.50 1.00 1.00 7.82 15.64 1.420 1.420 1.103 1.103 587.808 1197.659 1785.47 892.73
6.0 1.5 3.00 2.00 0.50 7.82 15.64 1.210 1.210 1.103 1.103 500.824 1020.429 1521.25 760.63
3.0
9.0 1.5 4.50 3.00 0.33 7.82 15.64 1.140 1.140 1.103 1.103 471.829 961.352 1433.18 716.59
12.0 1.5 6.00 4.00 0.25 7.82 15.64 1.105 1.105 1.103 1.103 457.332 931.814 1389.15 694.57
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 53 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
IA (Industrial Area) Admin Building Extension (Borehole 2)
2
Kp = tan (45+Φ/2) = 3.85
Depth factor : dγ , dq
1/2
dγ , dq = 1+ 0.1kp *(Df /B)
Meyerhof
Φ
Nc Nq Nγ
0 5.14 1 0
5 6.49 1.6 0.1
10 8.34 2.5 0.4
15 10.97 3.9 1.1
20 11.83 6.4 2.9
25 20.71 10.7 6.8
26 22.25 11.8 8
28 25.79 14.7 11.2
30 30.13 18.4 15.7
32 35.47 23.2 22
34 42.14 29.4 31.1
36 50.55 37.7 44.4
38 61.31 48.9 64
40 75.25 64.1 93.6
45 133.73 134.7 262.3
50 266.5 318.5 871.7
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 55 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
2
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2) qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.64 9.168 1.385 1.385 1.236 1.236 145.135 591.522 736.66 368.33
2.0 0.5 1.00 2.00 0.50 7.64 9.168 1.193 1.193 1.236 1.236 124.956 509.278 634.23 317.12
1.0
3.0 0.5 1.50 3.00 0.33 7.64 9.168 1.128 1.128 1.236 1.236 118.229 481.864 600.09 300.05
4.0 0.5 2.00 4.00 0.25 7.64 9.168 1.096 1.096 1.236 1.236 114.866 468.157 583.02 291.51
1.5 0.75 0.75 1.00 1.00 7.64 9.168 1.385 1.385 1.157 1.157 203.869 553.937 757.81 378.90
3.0 0.75 1.50 2.00 0.50 7.64 9.168 1.193 1.193 1.157 1.157 175.524 476.919 652.44 326.22
1.5
4.5 0.75 2.25 3.00 0.33 7.64 9.168 1.128 1.128 1.157 1.157 166.075 451.246 617.32 308.66
6.0 0.75 3.00 4.00 0.25 7.64 9.168 1.096 1.096 1.157 1.157 161.351 438.410 599.76 299.88
1.2
2.0 1.0 1.00 1.00 1.00 7.64 9.168 1.385 1.385 1.118 1.118 262.604 535.144 797.75 398.87
4.0 1.0 2.00 2.00 0.50 7.64 9.168 1.193 1.193 1.118 1.118 226.092 460.739 686.83 343.42
2.0
6.0 1.0 3.00 3.00 0.33 7.64 9.168 1.128 1.128 1.118 1.118 213.922 435.938 649.86 324.93
8.0 1.0 4.00 4.00 0.25 7.64 9.168 1.096 1.096 1.118 1.118 207.836 423.537 631.37 315.69
3.0 1.5 1.50 1.00 1.00 7.64 9.168 1.385 1.385 1.079 1.079 380.073 516.351 896.42 448.21
6.0 1.5 3.00 2.00 0.50 7.64 9.168 1.193 1.193 1.079 1.079 327.229 444.559 771.79 385.89
3.0
9.0 1.5 4.50 3.00 0.33 7.64 9.168 1.128 1.128 1.079 1.079 309.614 420.629 730.24 365.12
12.0 1.5 6.00 4.00 0.25 7.64 9.168 1.096 1.096 1.079 1.079 300.807 408.663 709.47 354.73
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2)
2
qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.64 11.46 1.385 1.385 1.294 1.294 152.051 774.639 926.69 463.34
2.0 0.5 1.00 2.00 0.50 7.64 11.46 1.193 1.193 1.294 1.294 130.910 666.935 797.85 398.92
1.0
3.0 0.5 1.50 3.00 0.33 7.64 11.46 1.128 1.128 1.294 1.294 123.863 631.034 754.90 377.45
4.0 0.5 2.00 4.00 0.25 7.64 11.46 1.096 1.096 1.294 1.294 120.340 613.083 733.42 366.71
1.5 0.75 0.75 1.00 1.00 7.64 11.46 1.385 1.385 1.196 1.196 210.786 715.912 926.70 463.35
3.0 0.75 1.50 2.00 0.50 7.64 11.46 1.193 1.193 1.196 1.196 181.479 616.373 797.85 398.93
1.5
4.5 0.75 2.25 3.00 0.33 7.64 11.46 1.128 1.128 1.196 1.196 171.710 583.194 754.90 377.45
6.0 0.75 3.00 4.00 0.25 7.64 11.46 1.096 1.096 1.196 1.196 166.825 566.604 733.43 366.71
1.5
2.0 1.0 1.00 1.00 1.00 7.64 11.46 1.385 1.385 1.147 1.147 269.520 686.548 956.07 478.03
4.0 1.0 2.00 2.00 0.50 7.64 11.46 1.193 1.193 1.147 1.147 232.047 591.092 823.14 411.57
2.0
6.0 1.0 3.00 3.00 0.33 7.64 11.46 1.128 1.128 1.147 1.147 219.556 559.274 778.83 389.41
8.0 1.0 4.00 4.00 0.25 7.64 11.46 1.096 1.096 1.147 1.147 213.310 543.365 756.67 378.34
3.0 1.5 1.50 1.00 1.00 7.64 11.46 1.385 1.385 1.098 1.098 386.989 657.185 1044.17 522.09
6.0 1.5 3.00 2.00 0.50 7.64 11.46 1.193 1.193 1.098 1.098 333.183 565.812 899.00 449.50
3.0
9.0 1.5 4.50 3.00 0.33 7.64 11.46 1.128 1.128 1.098 1.098 315.248 535.354 850.60 425.30
12.0 1.5 6.00 4.00 0.25 7.64 11.46 1.096 1.096 1.098 1.098 306.281 520.125 826.41 413.20
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 56 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
2
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2) qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 7.64 15.28 1.385 1.385 1.294 1.294 152.051 1032.851 1184.90 592.45
2.0 0.5 1.00 2.00 0.50 7.64 15.28 1.193 1.193 1.294 1.294 130.910 889.247 1020.16 510.08
1.0
3.0 0.5 1.50 3.00 0.33 7.64 15.28 1.128 1.128 1.294 1.294 123.863 841.378 965.24 482.62
4.0 0.5 2.00 4.00 0.25 7.64 15.28 1.096 1.096 1.294 1.294 120.340 817.444 937.78 468.89
1.5 0.75 0.75 1.00 1.00 7.64 15.28 1.385 1.385 1.196 1.196 210.786 954.549 1165.33 582.67
3.0 0.75 1.50 2.00 0.50 7.64 15.28 1.193 1.193 1.196 1.196 181.479 821.831 1003.31 501.65
1.5
4.5 0.75 2.25 3.00 0.33 7.64 15.28 1.128 1.128 1.196 1.196 171.710 777.592 949.30 474.65
6.0 0.75 3.00 4.00 0.25 7.64 15.28 1.096 1.096 1.196 1.196 166.825 755.472 922.30 461.15
2.0
2.0 1.0 1.00 1.00 1.00 7.64 15.28 1.385 1.385 1.147 1.147 269.520 915.397 1184.92 592.46
4.0 1.0 2.00 2.00 0.50 7.64 15.28 1.193 1.193 1.147 1.147 232.047 788.123 1020.17 510.09
2.0
6.0 1.0 3.00 3.00 0.33 7.64 15.28 1.128 1.128 1.147 1.147 219.556 745.699 965.25 482.63
8.0 1.0 4.00 4.00 0.25 7.64 15.28 1.096 1.096 1.147 1.147 213.310 724.486 937.80 468.90
3.0 1.5 1.50 1.00 1.00 7.64 15.28 1.385 1.385 1.098 1.098 386.989 876.246 1263.24 631.62
6.0 1.5 3.00 2.00 0.50 7.64 15.28 1.193 1.193 1.098 1.098 333.183 754.415 1087.60 543.80
3.0
9.0 1.5 4.50 3.00 0.33 7.64 15.28 1.128 1.128 1.098 1.098 315.248 713.805 1029.05 514.53
12.0 1.5 6.00 4.00 0.25 7.64 15.28 1.096 1.096 1.098 1.098 306.281 693.500 999.78 499.89
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 57 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
IA (Industrial Area) Admin Building Extension (Borehole 3)
Computation for Ultimate Bearing Capacity (Qult)
Meyerhof's Formula
Qult = cNcscdc + qNqsqdq + 0.5γB'Nγsγ
But c = 0
Qult = qNqsqdq + 0.5γB'Nγsγ
where,
Allowable bearing capacity Qa = Qult/F.S
F.S = Factor of Safety = 2.0
Shape factor : sγ , sq
sγ, sq = 1 + 0.1kp (B/L)
2
Kp = tan (45+Φ/2) = 2.88
Depth factor : dγ , dq
1/2
dγ , dq = 1+ 0.1kp *(Df /B)
Meyerhof
Φ
Nc Nq Nγ
0 5.14 1 0
5 6.49 1.6 0.1
10 8.34 2.5 0.4
15 10.97 3.9 1.1
20 11.83 6.4 2.9
25 20.71 10.7 6.8
26 22.25 11.8 8
28 25.79 14.7 11.2
30 30.13 18.4 15.7
32 35.47 23.2 22
34 42.14 29.4 31.1
36 50.55 37.7 44.4
38 61.31 48.9 64
40 75.25 64.1 93.6
45 133.73 134.7 262.3
50 266.5 318.5 871.7
w = moisture content = 24.8 %
Gs = specific gravity = 2.7
3
γw =effective unit weight of water = 9.81 kN/m
3
Bulk unit weight = 16.55 kN/m
3
γ' (kN/m3) = effective unit weight = 6.74 kN/m tan2(45+Φ/2)
φ = angle of internal friction = 29 ⁰ = 59.5
void ratio e0 = 1.23
Ref: Appendix B, Borehole logs - Soil Investigation Report (IA Admin Extension)
Nq = 16.55 Nγ = 13.45
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 59 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
2
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2) qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 6.74 8.088 1.288 1.288 1.204 1.204 35.143 207.563 242.71 121.35
2.0 0.5 1.00 2.00 0.50 6.74 8.088 1.144 1.144 1.204 1.204 31.211 184.344 215.56 107.78
1.0
3.0 0.5 1.50 3.00 0.33 6.74 8.088 1.096 1.096 1.204 1.204 29.901 176.605 206.51 103.25
4.0 0.5 2.00 4.00 0.25 6.74 8.088 1.072 1.072 1.204 1.204 29.246 172.735 201.98 100.99
1.5 0.75 0.75 1.00 1.00 6.74 8.088 1.288 1.288 1.136 1.136 49.740 195.853 245.59 122.80
3.0 0.75 1.50 2.00 0.50 6.74 8.088 1.144 1.144 1.136 1.136 44.176 173.945 218.12 109.06
1.5
4.5 0.75 2.25 3.00 0.33 6.74 8.088 1.096 1.096 1.136 1.136 42.321 166.642 208.96 104.48
6.0 0.75 3.00 4.00 0.25 6.74 8.088 1.072 1.072 1.136 1.136 41.394 162.990 204.38 102.19
1.2
2.0 1.0 1.00 1.00 1.00 6.74 8.088 1.288 1.288 1.102 1.102 64.337 189.999 254.34 127.17
4.0 1.0 2.00 2.00 0.50 6.74 8.088 1.144 1.144 1.102 1.102 57.140 168.745 225.89 112.94
2.0
6.0 1.0 3.00 3.00 0.33 6.74 8.088 1.096 1.096 1.102 1.102 54.741 161.660 216.40 108.20
8.0 1.0 4.00 4.00 0.25 6.74 8.088 1.072 1.072 1.102 1.102 53.542 158.118 211.66 105.83
3.0 1.5 1.50 1.00 1.00 6.74 8.088 1.288 1.288 1.068 1.068 93.532 184.144 277.68 138.84
6.0 1.5 3.00 2.00 0.50 6.74 8.088 1.144 1.144 1.068 1.068 83.070 163.545 246.61 123.31
3.0
9.0 1.5 4.50 3.00 0.33 6.74 8.088 1.096 1.096 1.068 1.068 79.582 156.679 236.26 118.13
12.0 1.5 6.00 4.00 0.25 6.74 8.088 1.072 1.072 1.068 1.068 77.838 153.246 231.08 115.54
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2)
2
qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 6.74 10.11 1.288 1.288 1.255 1.255 36.629 270.431 307.06 153.53
2.0 0.5 1.00 2.00 0.50 6.74 10.11 1.144 1.144 1.255 1.255 32.532 240.180 272.71 136.36
1.0
3.0 0.5 1.50 3.00 0.33 6.74 10.11 1.096 1.096 1.255 1.255 31.166 230.096 261.26 130.63
4.0 0.5 2.00 4.00 0.25 6.74 10.11 1.072 1.072 1.255 1.255 30.483 225.054 255.54 127.77
1.5 0.75 0.75 1.00 1.00 6.74 10.11 1.288 1.288 1.170 1.170 51.227 252.135 303.36 151.68
3.0 0.75 1.50 2.00 0.50 6.74 10.11 1.144 1.144 1.170 1.170 45.496 223.931 269.43 134.71
1.5
4.5 0.75 2.25 3.00 0.33 6.74 10.11 1.096 1.096 1.170 1.170 43.586 214.529 258.12 129.06
6.0 0.75 3.00 4.00 0.25 6.74 10.11 1.072 1.072 1.170 1.170 42.631 209.828 252.46 126.23
1.5
2.0 1.0 1.00 1.00 1.00 6.74 10.11 1.288 1.288 1.127 1.127 65.824 242.987 308.81 154.41
4.0 1.0 2.00 2.00 0.50 6.74 10.11 1.144 1.144 1.127 1.127 58.461 215.806 274.27 137.13
2.0
6.0 1.0 3.00 3.00 0.33 6.74 10.11 1.096 1.096 1.127 1.127 56.007 206.745 262.75 131.38
8.0 1.0 4.00 4.00 0.25 6.74 10.11 1.072 1.072 1.127 1.127 54.779 202.215 256.99 128.50
3.0 1.5 1.50 1.00 1.00 6.74 10.11 1.288 1.288 1.085 1.085 95.019 233.839 328.86 164.43
6.0 1.5 3.00 2.00 0.50 6.74 10.11 1.144 1.144 1.085 1.085 84.390 207.681 292.07 146.04
3.0
9.0 1.5 4.50 3.00 0.33 6.74 10.11 1.096 1.096 1.085 1.085 80.847 198.962 279.81 139.90
12.0 1.5 6.00 4.00 0.25 6.74 10.11 1.072 1.072 1.085 1.085 79.076 194.602 273.68 136.84
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 60 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Df (m) B L B' (m) L' (m) L'/B' B'/L' γ' (kN/m3) q' =γ'*Df sγ sq dq dy 0.5 *γ'*B'*sγ*Ny*dy q' *sq*dq*Nq, qult (kN/m2)
2
qa = qult/2 (kN/m )
1.0 0.5 0.50 1.00 1.00 6.74 13.48 1.288 1.288 1.255 1.255 36.629 360.575 397.20 198.60
2.0 0.5 1.00 2.00 0.50 6.74 13.48 1.144 1.144 1.255 1.255 32.532 320.240 352.77 176.39
1.0
3.0 0.5 1.50 3.00 0.33 6.74 13.48 1.096 1.096 1.255 1.255 31.166 306.795 337.96 168.98
4.0 0.5 2.00 4.00 0.25 6.74 13.48 1.072 1.072 1.255 1.255 30.483 300.072 330.56 165.28
1.5 0.75 0.75 1.00 1.00 6.74 13.48 1.288 1.288 1.170 1.170 51.227 336.180 387.41 193.70
3.0 0.75 1.50 2.00 0.50 6.74 13.48 1.144 1.144 1.170 1.170 45.496 298.574 344.07 172.04
1.5
4.5 0.75 2.25 3.00 0.33 6.74 13.48 1.096 1.096 1.170 1.170 43.586 286.039 329.63 164.81
6.0 0.75 3.00 4.00 0.25 6.74 13.48 1.072 1.072 1.170 1.170 42.631 279.771 322.40 161.20
2.0
2.0 1.0 1.00 1.00 1.00 6.74 13.48 1.288 1.288 1.127 1.127 65.824 323.983 389.81 194.90
4.0 1.0 2.00 2.00 0.50 6.74 13.48 1.144 1.144 1.127 1.127 58.461 287.741 346.20 173.10
2.0
6.0 1.0 3.00 3.00 0.33 6.74 13.48 1.096 1.096 1.127 1.127 56.007 275.661 331.67 165.83
8.0 1.0 4.00 4.00 0.25 6.74 13.48 1.072 1.072 1.127 1.127 54.779 269.620 324.40 162.20
3.0 1.5 1.50 1.00 1.00 6.74 13.48 1.288 1.288 1.085 1.085 95.019 311.786 406.80 203.40
6.0 1.5 3.00 2.00 0.50 6.74 13.48 1.144 1.144 1.085 1.085 84.390 276.908 361.30 180.65
3.0
9.0 1.5 4.50 3.00 0.33 6.74 13.48 1.096 1.096 1.085 1.085 80.847 265.283 346.13 173.06
12.0 1.5 6.00 4.00 0.25 6.74 13.48 1.072 1.072 1.085 1.085 79.076 259.470 338.55 169.27
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 61 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.3 Settlement Check
For detailed foundation design calculations, immediate settlement checks shall be carried
out in accordance with the code of practice for foundation for BH 1, 2 and 3
The immediate settlement is calculated using Burland and Burbidge method from
the formula
Se = α1* α2* α3*1.25*[(L/B)/0.25+ (L/B)] 2*(B/BR) 0.7*(q1/Pa) - Principles of
Foundation Engineering by Braja M. ( Eqn 5.57)
Where
Se = Settlement
α1 = a constant for normally consolidated sand = 0.14
α2 = compressibility index = 1.71/N1.4
α3 = correction for influence depth = 1 (for normally consolidated sand)
BR = Reference width = 0.3
q = net applied pressure
Pa = atmospheric pressure = 100kN/m2
L = Length of footing
B = Width of foundation
N = SPT value
Total settlement for the infrastructural works and foundation shall be limited to a
maximum value of 25 mm as recommended in the Structural Design Criteria (Clause
9.5.3) of the Admin building, learning centre project. Where the allowable bearing
settlements yields settlements higher than the limiting value, the limiting settlement
shall be used as a criteria to determine the safe bearing capacity for spread
foundations.
Naturally, high settlements occur at greater foundation depths. In this context,
settlement shall be checked at 0.5, 1.0, 1.2, 1.5, and 2.0 meters for shallow
foundations using the allowable bearing pressures.
The table below shows the settlement computations for the different foundation
sizes at foundation depths of 0.5, 1.0, 1.2, 1.5, and 2.0 meters using calculated
allowable pressures.
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 62 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Settlement Check for Bore Hole 1
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 63 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
D (m) B(m) L(m) L/B (m) α1 α2 α3 qnet (kN/m2) Se
1.00 1.00 0.14 0.01 1.00 516.79 4.928
2.00 2.00 0.14 0.01 1.00 440.32 5.184
1.0
3.00 3.00 0.14 0.01 1.00 414.82 5.267
4.00 4.00 0.14 0.01 1.00 402.08 5.307
1.50 1.00 0.14 0.01 1.00 534.49 6.770
3.00 2.00 0.14 0.01 1.00 455.40 7.121
1.5
4.50 3.00 0.14 0.01 1.00 429.03 7.235
6.00 4.00 0.14 0.01 1.00 415.85 7.290
1.2
2.00 1.00 0.14 0.01 1.00 565.56 8.761
4.00 2.00 0.14 0.01 1.00 481.87 9.216
2.0
6.00 3.00 0.14 0.01 1.00 453.97 9.363
8.00 4.00 0.14 0.01 1.00 440.02 9.435
3.00 1.00 0.14 0.01 1.00 641.05 13.190
6.00 2.00 0.14 0.01 1.00 546.19 13.875
3.0
9.00 3.00 0.14 0.01 1.00 514.57 14.096
12.00 4.00 0.14 0.01 1.00 498.76 14.204
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 64 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
D (m) B(m) L(m) L/B (m) α1 α2 α3 qnet (kN/m2) Se
1.00 1.00 0.14 0.01 1.00 826.38 7.881
2.00 2.00 0.14 0.01 1.00 704.09 8.289
1.0
3.00 3.00 0.14 0.01 1.00 663.33 8.422
4.00 4.00 0.14 0.01 1.00 642.95 8.486
1.50 1.50 0.14 0.01 1.00 815.13 11.852
3.00 3.00 0.14 0.01 1.00 694.50 11.711
1.5
4.50 4.50 0.14 0.01 1.00 654.30 11.622
6.00 6.00 0.14 0.01 1.00 634.19 11.567
2.0
2.00 2.00 0.14 0.01 1.00 831.72 15.907
4.00 4.00 0.14 0.01 1.00 708.64 15.194
2.0
6.00 6.00 0.14 0.01 1.00 667.61 14.893
8.00 8.00 0.14 0.01 1.00 647.10 14.729
3.00 3.00 0.14 0.01 1.00 892.73 24.456
6.00 6.00 0.14 0.01 1.00 760.63 22.537
3.0
9.00 9.00 0.14 0.01 1.00 716.59 21.810
12.00 12.00 0.14 0.01 1.00 694.57 21.428
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 65 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
D (m) B(m) L(m) L/B (m) α1 α2 α3 qnet (kN/m2) Se
1.00 1.00 0.14 0.01 1.00 308.90 3.414
2.00 2.00 0.14 0.01 1.00 265.95 3.629
1.0
3.00 3.00 0.14 0.01 1.00 251.63 3.703
4.00 4.00 0.14 0.01 1.00 244.48 3.740
1.50 1.00 0.14 0.01 1.00 325.22 4.774
3.00 2.00 0.14 0.01 1.00 280.00 5.074
1.5
4.50 3.00 0.14 0.01 1.00 264.93 5.178
6.00 4.00 0.14 0.01 1.00 257.39 5.229
1.0
2.00 1.00 0.14 0.01 1.00 348.06 6.249
4.00 2.00 0.14 0.01 1.00 299.67 6.642
2.0
6.00 3.00 0.14 0.01 1.00 283.53 6.777
8.00 4.00 0.14 0.01 1.00 275.47 6.845
3.00 1.00 0.14 0.01 1.00 400.27 9.545
6.00 2.00 0.14 0.01 1.00 344.62 10.145
3.0
9.00 3.00 0.14 0.01 1.00 326.06 10.352
12.00 4.00 0.14 0.01 1.00 316.79 10.456
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 66 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
D (m) B(m) L(m) L/B (m) α1 α2 α3 qnet (kN/m2) Se
1.00 1.00 0.14 0.01 1.00 463.34 5.121
2.00 2.00 0.14 0.01 1.00 398.92 5.443
1.0
3.00 3.00 0.14 0.01 1.00 377.45 5.554
4.00 4.00 0.14 0.01 1.00 366.71 5.609
1.50 1.00 0.14 0.01 1.00 463.35 6.802
3.00 2.00 0.14 0.01 1.00 398.93 7.229
1.5
4.50 3.00 0.14 0.01 1.00 377.45 7.377
6.00 4.00 0.14 0.01 1.00 366.71 7.451
1.5
2.00 1.00 0.14 0.01 1.00 478.03 8.583
4.00 2.00 0.14 0.01 1.00 411.57 9.123
2.0
6.00 3.00 0.14 0.01 1.00 389.41 9.308
8.00 4.00 0.14 0.01 1.00 378.34 9.402
3.00 1.00 0.14 0.01 1.00 522.09 12.450
6.00 2.00 0.14 0.01 1.00 449.50 13.233
3.0
9.00 3.00 0.14 0.01 1.00 425.30 13.502
12.00 4.00 0.14 0.01 1.00 413.20 13.638
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 67 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
D (m) B(m) L(m) L/B (m) α1 α2 α3 qnet (kN/m2) Se
1.00 1.00 0.14 0.08 1.00 101.12 7.783
2.00 2.00 0.14 0.08 1.00 89.81 8.534
1.0
3.00 3.00 0.14 0.08 1.00 86.04 8.817
4.00 4.00 0.14 0.08 1.00 84.15 8.965
1.50 1.00 0.14 0.08 1.00 104.35 10.668
3.00 2.00 0.14 0.08 1.00 92.68 11.697
1.5
4.50 3.00 0.14 0.08 1.00 88.79 12.085
6.00 4.00 0.14 0.08 1.00 86.84 12.288
1.0
2.00 1.00 0.14 0.08 1.00 109.62 13.707
4.00 2.00 0.14 0.08 1.00 97.36 15.029
2.0
6.00 3.00 0.14 0.08 1.00 93.27 15.527
8.00 4.00 0.14 0.08 1.00 91.23 15.788
3.00 1.00 0.14 0.08 1.00 122.18 20.292
6.00 2.00 0.14 0.08 1.00 108.52 22.249
3.0
9.00 3.00 0.14 0.08 1.00 103.96 22.986
12.00 4.00 0.14 0.08 1.00 101.68 23.373
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 68 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
D (m) B(m) L(m) L/B (m) α1 α2 α3 qnet (kN/m2) Se
1.00 1.00 0.14 0.08 1.00 198.60 15.286
2.00 2.00 0.14 0.08 1.00 176.39 16.761
1.0
3.00 3.00 0.14 0.08 1.00 168.98 17.316
4.00 4.00 0.14 0.08 1.00 165.28 17.607
1.50 1.00 0.14 0.08 1.00 193.70 19.803
3.00 2.00 0.14 0.08 1.00 172.04 21.713
1.5
4.50 3.00 0.14 0.08 1.00 164.81 22.432
6.00 4.00 0.14 0.08 1.00 161.20 22.809
2.0
2.00 1.00 0.14 0.08 1.00 194.90 24.370
4.00 2.00 0.14 0.08 1.00 173.10 26.721
2.0
6.00 3.00 0.14 0.08 1.00 165.83 27.606
8.00 4.00 0.14 0.08 1.00 162.20 28.071
3.00 1.00 0.14 0.08 1.00 203.40 33.780
6.00 2.00 0.14 0.08 1.00 180.65 37.039
3.0
9.00 3.00 0.14 0.08 1.00 173.06 38.266
12.00 4.00 0.14 0.08 1.00 169.27 38.909
Find below safe bearing pressures with limiting maximum settlement values of 25
mm using 24.89mm (highest safe computed settlement value) as a reference value.
BH 3 (Borehole 3 will be used for the new admin building/learning centre because it
is more conservative)
The table below shows computed settlements greater than allowable and the safe
bearing pressures corresponding to the limiting settlements
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 69 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Computed Computed Se Safe qnet Safe Se
D (m) B(m) L(m)
qnet (kNm2) (mm) (kNm2) (mm)
4.0 173.10 26.721 161.22 24.887
2.0 6.0 165.83 27.606 149.50 24.887
8.0 162.20 28.071 143.7 24.886
2.0 3.0 203.40 33.78 149.85 24.886
6.0 180.65 37.039 121.38 24.887
3.0
9.0 173.06 38.266 112.55 24.886
12.0 169.27 38.909 108.27 24.887
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 70 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.4 Pile Foundation
The Design Compressive Pile Resistance, Rc,d, or the ultimate compressive capacity, Qu of
piles is determined by the equation
Where,
Therefore,
Where,
The shaft resistance, Rs;d, of the pile is determined from the following equation;
Where,
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 71 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
cu = characteristics undrained shear strength of the clay along the pile shaft
α = Adhesion Factor
A factor of safety of 2.0 and 3.0 was used for shaft and base resistances of the pile
respectively to get the allowable compressive capacity. A global factor of safety of 2.5 was
also used as a combined check for both shaft and base resistance as can be seen from the
tables below.
Formular Reference
1. General
γd = γ/(1+w) Foundation Analysis and Design,
e = (Gsγw/γd)-1 5th Edition, by Joseph E. Bowles.
γsat = (Gs + e)γw/(1+e) (From Eqn 4.4)
γ' = γsul = γsat - γw
Nq = eπtanφtan2(45+φ/2)
Foundation Analysis and Design,
Nγ = (Nq - 1)tan(1.4φ) 5th Edition, by Joseph E. Bowles
(Table 4-1)
Nc = (Nq - 1)Cotφ - it is usually taken as 0.9
The Meyerhof critical Depth approach was used to compute shaft resistance for 300mm,
400mm, 600mm and 750mm diameter driven piles for Boreholes 1, 2 & 3.
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 72 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.4.1 300 mm Driven Pile Compression Capacity Computation
(Bore Hole 1)
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
12.00 8.30 9.81 1.625 15.94 28.30 2.67 0.00 12.42 1.11 17.58 7.77
Fine to medium greyish,
medium Dense sand
15.00 3.00 9.81 1.763 17.30 29.00 2.67 0.00 13.41 0.95 18.20 8.39
Fine to medium greyish, 12 8.3 0.00 0.00 0.44 25.50 0.48 8.30 7.77 64.50 99.09
medium Dense sand
15 3.00 0.00 0.00 0.43 26.25 0.49 3.00 8.39 25.16 124.24
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 73 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Fine to medium greyish,
3.70 3.70 7.27 25.36 25.36 1082.39 76.51 101.87
medium Dense, dense sand
Fine to medium greyish, 12.00 8.30 20.83 162.97 188.33 2917.04 206.19 394.52
medium Dense sand
15.00 3.00 26.13 73.87 262.20 4136.77 292.41 554.61
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 74 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
300 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 304.68 kN (from Equation 6.24)
Ha = 101.56 kN
where Mu = ultimate Moment
= σmaxZ = 633.87 kNm
σmax = F y /1.15 = 239130 kN/m 2
4
Z = π(D ) / 32D = 0.0026507 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 75 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
300 mm Driven Pile Settlement Computation
Settlement of Piles Foundation Analysis
& Design- 5th Edition
By Joseph E. Bowles
HP = H a + H Pt (from Equation 11.72)
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 76 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.4.2 400 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
12.00 8.30 9.81 1.625 15.94 28.30 2.67 0.00 12.42 1.11 17.58 7.77
Fine to medium greyish,
medium Dense sand
15.00 3.00 9.81 1.763 17.30 29.00 2.67 0.00 13.41 0.95 18.20 8.39
Fine to medium greyish, 12 8.3 0.00 0.00 0.44 25.50 0.48 8.30 7.77 64.50 99.09
medium Dense sand
15 3.00 0.00 0.00 0.43 26.25 0.49 3.00 8.39 25.16 124.24
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 77 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Fine to medium greyish,
3.70 3.70 7.27 33.82 33.82 1082.39 136.02 169.83
medium Dense, dense sand
Fine to medium greyish, 12.00 8.30 20.83 217.29 251.11 2917.04 366.57 617.67
medium Dense sand
15.00 3.00 26.13 98.50 349.60 4136.77 519.84 869.44
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 78 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
400 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 603.55 kN (from Equation 6.24)
Ha = 201.18 kN
where M u = ultimate Moment
= σmaxZ = 1502.5 kNm
σmax = F y /1.15 = 239130 kN/m 2
4
Z = π(D ) / 32D = 0.0062832 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 79 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
400 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 80 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.4.3 600 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
12.00 8.30 9.81 1.625 15.94 28.30 2.67 0.00 12.42 1.11 17.58 7.77
Fine to medium greyish,
medium Dense sand
15.00 3.00 9.81 1.763 17.30 29.00 2.67 0.00 13.41 0.95 18.20 8.39
Fine to medium greyish, 12 8.3 0.00 0.00 0.44 25.50 0.48 8.30 7.77 64.50 99.09
medium Dense sand
15 3.00 0.00 0.00 0.43 26.25 0.49 3.00 8.39 25.16 124.24
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 81 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type m m kN/m2 kN kN kN/m2 kN kN
Fine to medium greyish,
3.70 3.70 7.27 50.72 50.72 1082.39 306.04 356.76
medium Dense, dense sand
Fine to medium greyish, 12.00 8.30 20.83 325.94 376.66 2917.04 824.77 1201.43
medium Dense sand
15.00 3.00 26.13 147.74 524.40 4136.77 1169.65 1694.05
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 82 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
600 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 1559.5 kN (from Equation 6.24)
Ha = 519.82 kN
where Mu = ultimate Moment
= σmaxZ = 5070.9 kNm
2
σmax = F y /1.15 = 239130 kN/m
4
Z = π(D ) / 32D = 0.0212058 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 83 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
600 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 84 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.4.4 750 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
12.00 8.30 9.81 1.625 15.94 28.30 2.67 0.00 12.42 1.11 17.58 7.77
Fine to medium greyish,
medium Dense sand
15.00 3.00 9.81 1.763 17.30 29.00 2.67 0.00 13.41 0.95 18.20 8.39
Fine to medium greyish, 12 8.3 0.00 0.00 0.44 25.50 0.48 8.30 7.77 64.50 99.09
medium Dense sand
15 3.00 0.00 0.00 0.43 26.25 0.49 3.00 8.39 25.16 124.24
Fine to medium greyish, 12.00 8.30 20.83 407.42 470.82 2917.04 1288.71 1759.53
medium Dense sand
15.00 3.00 26.13 184.68 655.50 4136.77 1827.57 2483.07
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 85 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Application of partial safety factors for piled foundation
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 86 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
750 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 2613.6 kN (from Equation 6.24)
Ha = 871.19 kN
where Mu = ultimate Moment
= σmaxZ = 9904.2 kNm
σmax = F y /1.15 = 239130 kN/m 2
4
Z = π(D ) / 32D = 0.0414175 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 87 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
750 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 88 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.5 300 mm Driven Pile Compression Capacity Computation
(Bore Hole 2)
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose, Fine greyish sandy silt 4.60 1.90 9.81 1.627 15.96 20.20 2.63 0.00 13.28 0.94 18.04 8.23
12.00 7.40 9.81 1.792 17.58 23.40 2.67 0.00 14.25 0.84 18.72 8.91
Fine to medium greyish,
medium Dense, dense sand
15.00 3.00 9.81 1.772 17.38 32.00 2.67 0.00 13.17 0.99 18.05 8.24
Loose, Fine greyish sandy silt 4.60 1.90 7 28.00 14.72 9.00 11.19
Loose, Fine greyish sandy silt 4.60 1.90 0.300 0.07 1.79
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 89 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Fine to medium greyish,
2.70 2.70 5.23 13.32 13.32 732.82 51.80 65.12
medium Dense, dense sand
Loose, Fine greyish sandy silt 4.60 1.90 8.25 14.78 28.10 596.58 42.17 70.27
Fine to medium greyish, 12.00 7.40 22.28 155.41 183.50 2467.53 174.42 357.92
medium Dense, dense sand 15.00 3.00 27.54 77.86 261.36 3422.65 241.93 503.30
Fine to medium greyish, 12.00 7.40 155.41 183.50 25 21.21 34.11 217.61 4.00 54.40
medium Dense, dense sand
15.00 3.00 77.86 261.36 25 26.51 60.61 321.98 4.00 80.49
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 90 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
300 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 304.68 kN (from Equation 6.24)
Ha = 101.56 kN
where Mu = ultimate Moment
= σmaxZ = 633.87 kNm
σmax = F y /1.15 = 239130 kN/m 2
Z = π(D 4 ) / 32D = 0.0026507 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 91 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
300 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 92 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.5.1 400 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose, Fine greyish sandy silt 4.60 1.90 9.81 1.627 15.96 20.20 2.63 0.00 13.28 0.94 18.04 8.23
12.00 7.40 9.81 1.792 17.58 23.40 2.67 0.00 14.25 0.84 18.72 8.91
Fine to medium greyish,
medium Dense, dense sand
15.00 3.00 9.81 1.772 17.38 32.00 2.67 0.00 13.17 0.99 18.05 8.24
Loose, Fine greyish sandy silt 4.60 1.90 7 28.00 14.72 9.00 11.19
Loose, Fine greyish sandy silt 4.60 1.90 0.400 0.13 2.39
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 93 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Fine to medium greyish,
2.70 2.70 5.23 17.76 17.76 732.82 92.09 109.85
medium Dense, dense sand
Loose, Fine greyish sandy silt 4.60 1.90 8.25 19.71 37.46 596.58 74.97 112.43
Fine to medium greyish, 12.00 7.40 22.28 207.21 244.67 2467.53 310.08 554.75
medium Dense, dense sand 15.00 3.00 27.54 103.81 348.48 3422.65 430.10 778.59
Fine to medium greyish, 12.00 7.40 207.21 244.67 25 37.70 60.63 305.30 4.00 76.33
medium Dense, dense sand
15.00 3.00 103.81 348.48 25 47.12 107.76 456.24 4.00 114.06
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 94 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
400 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 603.55 kN (from Equation 6.24)
Ha = 201.18 kN
where M u = ultimate Moment
= σmaxZ = 1502.5 kNm
σmax = F y /1.15 = 239130 kN/m 2
4
Z = π(D ) / 32D = 0.0062832 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 95 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
400 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
Fine to medium greyish, 12.00 7.40 0.50 21000000 0.0011 15000.00 0.75 0.002 3.31
medium Dense, dense sand
15.00 3.00 0.50 21000000 0.0029 17500.00 0.75 0.004 6.70
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 96 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.5.2 600 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose, Fine greyish sandy silt 4.60 1.90 9.81 1.627 15.96 20.20 2.63 0.00 13.28 0.94 18.04 8.23
12.00 7.40 9.81 1.792 17.58 23.40 2.67 0.00 14.25 0.84 18.72 8.91
Fine to medium greyish,
medium Dense, dense sand
15.00 3.00 9.81 1.772 17.38 32.00 2.67 0.00 13.17 0.99 18.05 8.24
Loose, Fine greyish sandy silt 4.60 1.90 7 28.00 14.72 9.00 11.19
Loose, Fine greyish sandy silt 4.60 1.90 0.600 0.28 3.58
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 97 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Fine to medium greyish,
2.70 2.70 5.23 26.64 26.64 732.82 207.20 233.84
medium Dense, dense sand
Loose, Fine greyish sandy silt 4.60 1.90 8.25 29.56 56.20 596.58 168.68 224.87
Fine to medium greyish, 12.00 7.40 22.28 310.81 367.01 2467.53 697.68 1064.68
medium Dense, dense sand 15.00 3.00 27.54 155.72 522.73 3422.65 967.73 1490.46
Fine to medium greyish, 12.00 7.40 310.81 367.01 25 84.82 136.42 503.43 4.00 125.86
medium Dense, dense sand
15.00 3.00 155.72 522.73 25 106.03 242.45 765.18 4.00 191.29
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 98 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
600 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 1559.5 kN (from Equation 6.24)
Ha = 519.82 kN
where Mu = ultimate Moment
= σmaxZ = 5070.9 kNm
σmax = F y /1.15 = 239130 kN/m 2
4
Z = π(D ) / 32D = 0.0212058 m3
3
Hu = y3EI / (e+z f ) = 36.427 kN
Ha = 12.142 kN < 259.91 kN
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 99 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
600 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 100 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.5.3 750 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose, Fine greyish sandy silt 4.60 1.90 9.81 1.627 15.96 20.20 2.63 0.00 13.28 0.94 18.04 8.23
12.00 7.40 9.81 1.792 17.58 23.40 2.67 0.00 14.25 0.84 18.72 8.91
Fine to medium greyish,
medium Dense, dense sand
15.00 3.00 9.81 1.772 17.38 32.00 2.67 0.00 13.17 0.99 18.05 8.24
Loose, Fine greyish sandy silt 4.60 1.90 7 28.00 14.72 9.00 11.19
Loose, Fine greyish sandy silt 4.60 1.90 0.750 0.44 4.48
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 101 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Fine to medium greyish,
2.70 2.70 5.23 33.30 33.30 732.82 323.75 357.04
medium Dense, dense sand
Loose, Fine greyish sandy silt 4.60 1.90 8.25 36.95 70.25 596.58 263.56 333.80
Fine to medium greyish, 12.00 7.40 22.28 388.51 458.76 2467.53 1090.12 1548.88
medium Dense, dense sand 15.00 3.00 27.54 194.65 653.41 3422.65 1512.08 2165.49
Fine to medium greyish, 12.00 7.40 388.51 458.76 25 132.54 213.16 671.92 4.00 167.98
medium Dense, dense sand
15.00 3.00 194.65 653.41 25 165.67 378.83 1032.24 4.00 258.06
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 102 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
750 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 2613.6 kN (from Equation 6.24)
Ha = 871.19 kN
where M u = ultimate Moment
= σmaxZ = 9904.2 kNm
σmax = F y /1.15 = 239130 kN/m 2
Z = π(D 4 ) / 32D = 0.0414175 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 103 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
750 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
Fine to medium greyish, 12.00 7.40 0.50 21000000 0.0009 15000.00 0.75 0.014 15.29
medium Dense, dense sand
15.00 3.00 0.50 21000000 0.0023 17500.00 0.75 0.025 27.35
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 104 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.6 300 mm Driven Pile Compression Capacity Computation
(Bore Hole 3)
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose, Fine greyish sandy silt 4.60 1.90 9.81 1.569 15.39 48.10 2.63 0.00 10.39 1.48 16.25 6.44
12.00 7.40 9.81 1.699 16.67 22.90 2.67 0.00 13.56 0.93 18.29 8.48
Fine to medium greyish,
medium Dense sand
15.00 3.00 9.81 1.798 17.64 25.00 2.67 0.00 14.11 0.86 18.64 8.83
Loose, Fine greyish sandy silt 4.60 1.90 7 28.00 14.72 9.00 11.19
Loose, Fine greyish sandy silt 4.60 1.90 0.300 0.07 1.79
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 105 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Loose, Fine to medium greyish
2.70 2.70 4.39 11.17 11.17 351.08 24.82 35.98
sand
Loose, Fine greyish sandy silt 4.60 1.90 6.84 12.25 23.42 494.43 34.95 58.37
Fine to medium greyish, 12.00 7.40 20.23 141.08 164.49 2514.19 177.72 342.21
medium Dense sand 15.00 3.00 25.83 73.04 237.53 4089.95 289.10 526.63
Fine to medium greyish, 12.00 7.40 141.08 164.49 25 21.21 34.11 198.60 4.00 49.65
medium Dense sand
15.00 3.00 73.04 237.53 25 26.51 60.61 298.14 4.00 74.54
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 106 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
300 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 304.68 kN (from Equation 6.24)
Ha = 101.56 kN
where M u = ultimate Moment
= σmaxZ = 633.87 kNm
σmax = F y /1.15 = 239130 kN/m 2
Z = π(D 4 ) / 32D = 0.0026507 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 107 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
300 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 108 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.6.1 400 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose, Fine greyish sandy silt 4.60 1.90 9.81 1.569 15.39 48.10 2.63 0.00 10.39 1.48 16.25 6.44
12.00 7.40 9.81 1.699 16.67 22.90 2.67 0.00 13.56 0.93 18.29 8.48
Fine to medium greyish,
medium Dense sand
15.00 3.00 9.81 1.798 17.64 25.00 2.67 0.00 14.11 0.86 18.64 8.83
Loose, Fine greyish sandy silt 4.60 1.90 7 28.00 14.72 9.00 11.19
Loose, Fine greyish sandy silt 4.60 1.90 0.400 0.13 2.39
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 109 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Loose, Fine to medium greyish
2.70 2.70 4.39 14.89 14.89 351.08 44.12 59.01
sand
Loose, Fine greyish sandy silt 4.60 1.90 6.84 16.33 31.22 494.43 62.13 93.35
Fine to medium greyish, 12.00 7.40 20.23 188.10 219.32 2514.19 315.94 535.27
medium Dense sand 15.00 3.00 25.83 97.38 316.70 4089.95 513.96 830.66
Fine to medium greyish, 12.00 7.40 188.10 219.32 25 37.70 60.63 279.96 4.00 69.99
medium Dense sand
15.00 3.00 97.38 316.70 25 47.12 107.76 424.46 4.00 106.12
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 110 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
400 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
by MJ Tomlinson
Hu = 2M u / (e+z f ) = 603.55 kN (from Equation 6.24)
Ha = 201.18 kN
where M u = ultimate Moment
= σmaxZ = 1502.5 kNm
σmax = F y /1.15 = 239130 kN/m 2
Z = π(D 4 ) / 32D = 0.0062832 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 111 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
400 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 112 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.6.2 600 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m 3
Mg/m 3
kN/m 3
% - kN/m 2
kN/m 3
- kN/m 3
kN/m3
Loose, Fine to medium greyish
2.70 2.70 9.81 1.687 16.55 30.90 2.67 0.00 12.64 1.07 17.72 7.91
sand
Loose, Fine greyish sandy silt 4.60 1.90 9.81 1.569 15.39 48.10 2.63 0.00 10.39 1.48 16.25 6.44
12.00 7.40 9.81 1.699 16.67 22.90 2.67 0.00 13.56 0.93 18.29 8.48
Fine to medium greyish,
medium Dense sand
15.00 3.00 9.81 1.798 17.64 25.00 2.67 0.00 14.11 0.86 18.64 8.83
Loose, Fine greyish sandy silt 4.60 1.90 7 28.00 14.72 9.00 11.19
Loose, Fine greyish sandy silt 4.60 1.90 0.600 0.28 3.58
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 113 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Loose, Fine to medium greyish
2.70 2.70 4.39 22.33 22.33 351.08 99.26 121.60
sand
Loose, Fine greyish sandy silt 4.60 1.90 6.84 24.50 46.83 494.43 139.80 186.63
Fine to medium greyish, 12.00 7.40 20.23 282.15 328.99 2514.19 710.87 1039.86
medium Dense sand 15.00 3.00 25.83 146.07 475.06 4089.95 1156.41 1631.46
Fine to medium greyish, 12.00 7.40 282.15 328.99 25 84.82 136.42 465.41 4.00 116.35
medium Dense sand
15.00 3.00 146.07 475.06 25 106.03 242.45 717.51 4.00 179.38
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 114 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
600 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 1559.5 kN (from Equation 6.24)
Ha = 519.82 kN
where Mu = ultimate Moment
= σmaxZ = 5070.9 kNm
σmax = F y /1.15 = 239130 kN/m 2
Z = π(D 4 ) / 32D = 0.0212058 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 115 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
600 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 116 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
5.6.3 750 mm Driven Pile Compression Capacity Computation
Soil Depth Thk. γw γ γ=γt w Gs cu γd e γsat γsub
Type m m kN/m
3
Mg/m
3
kN/m
3
% - kN/m
2
kN/m
3
- kN/m
3
kN/m
3
Loose, Fine greyish sandy silt 4.60 1.90 9.81 1.569 15.39 48.10 2.63 0.00 10.39 1.48 16.25 6.44
12.00 7.40 9.81 1.699 16.67 22.90 2.67 0.00 13.56 0.93 18.29 8.48
Fine to medium greyish,
medium Dense sand
15.00 3.00 9.81 1.798 17.64 25.00 2.67 0.00 14.11 0.86 18.64 8.83
Loose, Fine greyish sandy silt 4.60 1.90 7 28.00 14.72 9.00 11.19
Loose, Fine greyish sandy silt 4.60 1.90 0.750 0.44 4.48
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 117 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
Soil Depth Thk. ƒs Qs ΣQs qb Qb Qu
Type 2 2
m m kN/m kN kN kN/m kN kN
Loose, Fine to medium greyish
2.70 2.70 4.39 27.92 27.92 351.08 155.10 183.02
sand
Loose, Fine greyish sandy silt 4.60 1.90 6.84 30.62 58.54 494.43 218.43 276.97
Fine to medium greyish, 12.00 7.40 20.23 352.69 411.23 2514.19 1110.73 1521.97
medium Dense sand 15.00 3.00 25.83 182.59 593.82 4089.95 1806.89 2400.71
Fine to medium greyish, 12.00 7.40 352.69 411.23 25 132.54 213.16 624.39 4.00 156.10
medium Dense sand
15.00 3.00 182.59 593.82 25 165.67 378.83 972.65 4.00 243.16
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 118 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
750 mm Driven Pile Lateral Capacity Computation
Laterally Loaded Piles
Pile Design and Construction
Ultimate Lateral Load on Fixed-Headed pile Practice 4th Edition
By MJ Tomlinson
Hu = 2M u / (e+z f ) = 2613.6 kN (from Equation 6.24)
Ha = 871.19 kN
where M u = ultimate Moment
= σmaxZ = 9904.2 kNm
σmax = F y /1.15 = 239130 kN/m 2
Z = π(D 4 ) / 32D = 0.0414175 m3
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 119 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
750 mm Driven Pile Settlement Computation
where Q wp = load carried at the pile point under working load condition
Q ws = load carried by frictional (skin) resistance under working load condition
Ap = area of pile cross section
L = length of pile
Ep = modulus of elasticity of the pile material
Fine to medium greyish, 12.00 7.40 0.50 21000000 0.0009 17500.00 0.75 0.012 12.74
medium Dense sand
15.00 3.00 0.50 21000000 0.0024 21500.00 0.75 0.022 24.66
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 120 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
6.0 SUMMARY
From the soil investigation report and capacity checks, the medium dense sand revealed
that between 12.0 – 15.0 m below grade level is better suited to terminate piles.
Resistance values of compressive, tensile, and lateral loads at these depths have been
established for driven Piles.
Engineering analysis carried out on shallow foundations has also been made available in
this report. The capacities of both pad and raft foundations to a maximum width of 3m and
length of 12m have been established to a satisfactory level using the Meyerhof approach.
Bore hole 12 is located in the Chiller Plant/Substation area while boreholes 1, 2 & 3 are
located in the new admin building extension area.
For the new admin building extension area, results for borehole 3 has been adopted being
the most conservative compared to boreholes 1 & 2.
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 121 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408
6.2 Deep Foundation
Pile Capacity Summary Table
LOCATION: BONNY ISLAND, NIGERIA PLANT: LNG COMPLEX PROJECT NO: 11/PDR/142
NIGERIA LNG LTD PAGE 122 OF 122 Rev A
UNIT 8002
CALCULATION OF SOIL BEARING CAPACITY DOC NO: B-35.408