A. Certification/Payment:
1. Delay in IPC release; IPC 80 payment under SA - 71 mil EGP (ASJV letter 4114 & 4107)
2. Delay in IPC release; IPC 81A payment to ID subcontractor by 43 days – 3.2 mil EGP
(ASJV letter 4109)
3. Delay in IPC release; IPC 79 payment USD portion by 47 days – 4 mil USD (ASJV letter
4108)
4. Unjustified deductions from IPC 81 against reports that have been already submitted
(ASJV letter 4169)
5. Deductions from ID payment against works progress (ASJV letter 4046, 3902, 3891, 3742
& 2642) which is around 2.5 mil EGP each payment
6. Reduction of Aluminium works progress percent by Ehaf from 95% to 90% which
resulted in negative cash of 2.1 mil EGP
7. Remaining work including release of percent withheld by Consultant for
snagging/testing&commissioning
2. Arch/Civil variations:
CRVO 40 Additional items for new Aluminum Windows, shutters, louvers at BOH
CRVO 66 Kitchen ceiling tiles
CRVO 82 Variation for Adding Massive Oakwood Frames Pant rakes and Architraves
CRVO 86 Additional Item for New Automatic Sliding Doors – at Atrium
CRVO 87 Variation for Finishing of Exit Stairs With Epoxy Painting
CRVO 89 Variation for Supply/Install Aluminum Tiles False Ceiling
3. ID variations:
CRVO 4 Calcutta Gold - Cavity Top ST02A
CRVO 11 Zebrano Veneer on MDF Ceiling, Type (WD-12), for All Day Dining Restaurant
CRVO 10 Tensioned Fabric Structures for Lobby Entrance
CRVO 12 Fire Retardant Paint for Cladding and Ceiling for Second Fix
CRVO 13 Entrance Wall Marble in Atrium
CRVO 16 Variation Order for Mirror Glass for Bathroom Vanity Mirror
CRVO 21 Variation Order for Bridge Glass Handrail
CRVO 22 Door Type (D-117) Hand Capped Guest Room Entrance
CRVO 23 Door Type (D-118) Hand Capped Guest Room Bathroom
CRVO 25 Variation Order for Calcutta Gold Stone Threshold Type (ST-02A) at Guest Room
Entrance Door
CRVO 27 Variation Order for Door Type (D-120) Suite Bathroom Door