Module Name Computing Project Module Code C8-PRO-11


Week Of (Insert Date Reading Assessments - Name
Unit(s) Covered
[dd/mm/yy]) and Date [dd/mm/yy]

Week 1
(24/08/2020 to Chapter 1: Project Proposal
29/08/2020)

Week 2
(31/08/2020 to Regular class activity Refer Library/ Practice lab
05/09/2020)

Submission 1 (Blackboard)
Week 3 - Proposal - Chapter 1
(07/09/2020 to Chapter 1: Project Proposal Presentations Presentations should be
12/09/2020) done on or before 28th Aug
2020

Week 4 Submission 2 (Blackboard)-


(14/09/2020 to Chapter 2: First Review Literature Review & Project
19/09/2020) Modelling Diagram

Week 5 Submission 3 (Blackboard) -


(21/09/2020 to Regular class activity Refer Library/ Practice lab Resource Requirement &
26/09/2020) Justification - SSCC Meeting
Milestone FM-EDU-001 Rev. 001 Page 2 of 15-07-2013

Submission 4 (Blackboard) -
Week 6 Functional and Non Functional
(28/09/2020 to Regular class activity Refer Library/ Practice lab Requirement / Network
03/10/2020)
Requirements

Week 7
(05/10/2020 to Chapter 2: First Review Discussion
10/10/2020)

Submission 5 (Blackboard) -
Chapter 2 Submission on or
Week 8
before 02nd Oct 2020
(12/10/2020 to Chapter 2: First Review Submission (To include Chapter 1 also)
17/10/2020) through Black Board and
Student Feedback
Collection

Week 9
(19/10/2020 to Chapter 3: Second Review Student Feedback Collection
24/10/2020)

Week 10 Submission 6 (Blackboard)-


(26/10/2020 to Regular class activity Refer Library/ Practice lab Project Design 1 -
31/10/2020) Classroom observation

Week 11 Submission 7 (Blackboard) -


(02/11/2020 to Regular class activity Refer Library/ Practice lab Project Design 2
07/11/2020)
Milestone FM-EDU-001 Rev. 001 Page 3 of 15-07-2013

Submission 8 (Blackboard)-
Week 12
Chapter 3 Presentations
(09/11/2020 to Chapter 3: Second Review Presentations (To include Chapter 1 to Chapter 3)
14/11/2020) should be done on or before
30 Oct 2020

Week 13
(16/11/2020 to Chapter 4: Final Report
21/11/2020)

Week 14
(23/11/2020 to Regular class activity Refer Library/ Practice lab
28/11/2020)

Week 15
(30/11/2020 to Regular class activity Refer Library/ Practice lab
09/12/2020)

Week 16 Internal Mark Submission (35%)


(10/12/2020 to Regular class activity Refer Library/ Practice lab (23/11/2020)
23/12/2020)

Week 17 The submission should


(05/01/2021 to FINAL PROJECT SUBMISSION ON TURNITIN (30 Nov 2020) + include Chapter 1 to
09/01/2021) Presentation Week Chapter 4 on Turnitin
Milestone FM-EDU-001 Rev. 001 Page 4 of 15-07-2013

Week 18 Normal Result Publishing (22/12/2020)


(12/01/2021 to
16/01/2021)

Week 19
(19/01/2021 to Supplementary Support Classes
23/01/2021)

Week 20
(11/01/2021 to Supplementary Assessment Week & Turnitin Submission (11-Jan-2021)
15/01/2021)

Week 21
(19/01/2021 to Supplementary Result Publishing (22/01/2021)
23/01/2021)

Assessment Weightage
Name Weightage Type (written/practical, etc.)
Attendance / 5%
Discussion Forum Discussion Forum
Chapter 1 5% Project - Chapter 1
Chapter 2 15% Project - Chapter 2
Chapter 3 15% Project - Chapter 3
Chapter 4 35% Final Project Report - Chapter 1 to Chapter 4
Final Project
Presentation
25% Project Presentation

Supplementry Exam 100% Revised Project + Project Presentation