Professional Documents
Culture Documents
The no end of type of above equipment may vary as per site requirement
during Construction of Tunnel.
The steps to be followed for approval of each Quarry/ Borrow Area are:
2. The results of laboratory tests conducted on the materials jointly sampled with the
QA Engineer (or his designated representative) are to be summarized on the
approval form, and complete copies of all tests are to be attached to the form.
3. The Contractor shall attach to the completed “Materials Sources Data” form, his
proposed “Environmental Management Plan” for development, use and closing
down of the proposed quarry/ borrow area. Photographs of the sources site,
including access roads, etc., should be included with the proposal so that the
base line conditions of the quarry/ borrow area are clearly established.
With regard to approval of Quarries and Borrow Areas, the PM shall pay
particular attention to requirements of the Environmental Management Plan
particularly with regards to:
1. Selection of area
Borrow Areas not to be within the Project Right-of-Way
Borrow Areas preferred in non-productive, barren lands, raised
lands, waste lands, etc.
Borrow Areas to be located on agricultural land should first
have the top 150mm minimum removed and stockpiled. The
stockpiled topsoil is to be replaced and spread over the original
areas after excavation for borrow is completed.
For quarry areas, particular care is to be taken to ensure that
testing (and approval) is given only for areas to be indicated on
the plan for which the materials have homogeneous properties.
Similarly, the depth and extent of overburden to be removed
prior to quarrying is to be accurately measured and clearly
indicated.
2. Transport of Materials
All movements and access of equipment to be stationed in the
designated areas are to cause minimum compaction of the soil
(in critical areas/ situations, the PM may require that all such
equipment have tracks rather than wheels).
All transport vehicles should have covered sides and tailgates
to prevent spillage of materials.
All transport vehicles are to select appropriate routes and
delivery times, and are to adopt safe driving habits so as to
ensure minimum of inconvenience to affected village
inhabitants, and to reduce accident potential. The Contractor
is responsible for the repair/ maintenance of all roads and
facilities damaged by his transport equipment.
3. Development/ Redevelopment of Borrow Pits and Quarries
Both during and following completion of the excavation
activities in the borrow areas, the PM shall inspect the areas to
ensure that the borrow pits and access roads are properly
graded and drained to ensure minimum erosion, and to
prevent run-off from either collecting or from damaging
adjacent properties. All existing trees within the boundary of
the quarry/ borrow areas should be preserved and protected.
Temporary stockpiles of blasted quarry materials and borrow
areas soils are to be located so as to ensure smooth flow of
traffic within the areas and for access to main roads, and are to
be designed so as to minimize contamination and damage
from rainfall/ run-off etc.
Borrow Areas (except in cases where the landowner has
agreed that the borrow pit is to be excavated so as to form an
appropriate pond for agricultural purposes), will be
redeveloped by filling and providing 150mm thick layer of
preserved topsoil.
Consultant’s Q.A. Engineer shall continue to monitor the
quarry/ borrow materials both by periodic sampling and testing
of the materials as well as by “visual” assessment. As soon as
tests indicate any significant change in a material’s property, or
if a change is suspected visually, then the material properties
are to be certified by testing and if the variation(s) is
considered to be significant, then a new application for
approval of source must be lodged, and the above procedure
repeated.
It is to be noted that all field activities for the above are not to commence until
appropriate Request for Inspection Forms are completed, submitted and
approved.
5. Approval of Materials
All materials proposed by the Contractor to be used in the Project Works are
to be first approved. In general, there are four types of materials to be
approved.
(1) Natural Materials – materials with little or no processing except for perhaps
screening for oversize and removal of unsuitable particles, etc. An example of
this is soil embankment materials.
(2) Processed Materials – materials that require significant processing, including
removal of unsuitable particles, crushing, screening and perhaps, blending of
sizes. These materials are homogeneous, but with specified gradations.
(3) Manufactured Materials – especially homogeneous construction materials, like
Portland cement and admixture that are used for blending with natural
materials to obtain a concrete mix.
(4) Designed Materials – materials that involve the mixture to specific proportions
of two or more different, natural, processed or manufactured materials to obtain
a modified material giving a set of desired specific properties.
Natural materials are mined (i.e., excavated) and hence the first step,
following assurance that the material is acceptable for its intended purpose, is
to obtain approval for the Quarry.
Approval of “designed” materials for the present Project concerns those mix
designs for Portland Cement Concrete (for culverts, bridges etc). Due to the
complexity of these “mixed” materials, and the plants for producing the range
of materials sizes, final approval is deferred until completion of the following
steps:
Following approval of the job mix formula, the PM and all field support staff
shall continue to monitor both the test results of the visual characteristics of
the approved mix as placed to identify at an early stage any significant change
in the mix design that may adversely influence the adherence of the approved
mix design to the Specifications. A new mix design (or adjustment of the plant
proportioning of materials to re-establish the approved job mix formula) will be
required when it is observed that significant changes in the mix design
properties are causing the mix to no longer meet all Specification
requirements. In addition, a new mix design will be required when either the
approval of a material source or approval of one of the materials is revoked
(i.e., withdrawn). Mix /Material approved shall be revoked by the PM after due
consultation with the Consultant’s Q.A. Engineer.
The Contractor’s Q.A. Engineer shall notify in writing to the PM and the
Consultant’s / I C each time a new source, material and/ or mix design is
either approved or the approval is revoked. This information is to be included
in the Monthly Quality Control Report to be submitted with the Monthly
Progress Report.
6. Sampling of Materials
Samples collected are reduced and prepared as per Indian Standards (IS)
methods, with an additional sufficient quantity retained in appropriately sealed
bags(s) or container(s) and separately kept in the sample storage room of the
laboratory for additional testing and/ or future reference as required. Concrete
samples in particular are to be carefully cured and kept in the curing tank of
the laboratory. Access to stored samples is under the strict direct control of
the Contractor’s Q.A. Engineer. Details of all samples stored are to be kept in
a Register to be administered by the authorized engineer of the Consultant’s
Q.A. Engineer.