PROJECT SCHEDULE - DRAINAGE RECONSTRUCTION
CONCEPCION - CAPAZ TARLAC
As of OCTOBER
NOVEMBER
ITEM ACTIVITY DURATION
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
(Days)
A. SURVEY 1.0
Survey of Existing Elevations
Site Inspection for Obstructions
B. MOBILIZATION 1.0
C. EXCAVATION 8.0
D. SLOPING 2.0
Survey for Drainage Slope
E. STEEL REINFORECEMENT FABRICATION (FLOOR/WALL) 4.0
F. GRAVEL BEDDING 2.0
G. INSTALLATION OF STEEL REINFORCEMENT (FLOOR/WALL) 6.0
H. CONCRETE POURING (DRAINAGE BASE/FLOOR) 2.0
I. FORMWORKS FABRICATION FOR DRAINAGE WALLS 6.0
J. CONCRETE POURING FOR DRAINAGE WALLS 2.0
K. REMOVAL OF DRAINAGE WALL FORMWORKS 2.0
L. STEEL REINFORCEMENT FABRICATION (FIXED AND REMOVABLE COVER) 4.0
M. CONCRETE CURING 4.0
N. FORMWORKS FABRICATION FOR FIXED COVER 4.0
O. INSTALLATION OF STEEL REINFORCEMENT (FIXED COVER) 6.0
P. CONCRETE POURING (FIXED COVER) 2.0
Q. FABRICATION OF REMOVABLE COVERS 1.0
R. CONCRETE CURING 4.0
S. REMOVAL OF FIXED COVER FORMWORKS 4.0
T. SIDEWALK GRADING 1.0
U. SIDEWALK GRAVEL BEDDING 1.0
V. FABRICATION OF REINFORCEMENTS FOR SIDEWALK 2.0
W. INSTALLATION OF SIDEWALK REINFORCEMENT 2.0
X. CONCRETE POURING (SIDEWALK) 1.0
Y. CONCRETE CURING SIDEWALK 1.0
Z. DEMOBILIZATION 1.0