Professional Documents
Culture Documents
Wipro Ltd.
Date: 23 Feb 2011
Version: 1.0
Training Manual: SAP Plant Maintenance
Table of Contents:
1. PURPOSE .......................................................................................................................................... 5
4.2 Equipment...................................................................................................................................................... 30
4.2.1 Create Equipment .......................................................................................................................................... 30
4.2.2 Change Equipment......................................................................................................................................... 35
4.2.3 Display Equipment ......................................................................................................................................... 37
Page 2 of 346
Training Manual: SAP Plant Maintenance
Page 3 of 346
Training Manual: SAP Plant Maintenance
4.16.1 Create Single Cycle Maintenance Plan (Time Based) ................................................................................. 143
4.16.2 Create Single Cycle Maintenance Plan (Performance Based) .................................................................... 147
4.16.3 Create Strategy Plan (Time or Performance Based) .................................................................................. 150
4.16.4 Schedule Maintenance Plan ...................................................................................................................... 156
4.16.5 Schedule Overview List: Maintenance Plans ............................................................................................. 158
Page 4 of 346
Training Manual: SAP Plant Maintenance
1. Purpose
The objective of this training manual is to prepare the readers to,
Page 5 of 346
Training Manual: SAP Plant Maintenance
1.1 Scope
This training manual applies to all operation & maintenance personnel involved in
performing day-to-day maintenance tasks and activities within SAP Plant Maintenance.
Page 6 of 346
Training Manual: SAP Plant Maintenance
Page 7 of 346
Training Manual: SAP Plant Maintenance
Divisions & sub-divisions of maintenance plants are considered as locations & sections.
Machines or sets of machines, which are represented in the system as pieces of
equipment or functional locations, are installed in plant locations & sections. You
indicate the place for which a maintenance task was requested with the plant section.
You can establish a contact person for Plant Maintenance using the plant section.
Page 8 of 346
Training Manual: SAP Plant Maintenance
In DGPC, some of the maintenance plant locations for each planning plant can be
summarised as follows:
Dam site
De-silting chamber
Surge shaft
Butterfly valve chamber
Underground power house
Civil structure
Auto workshop, etc.
In SAP Plant Maintenance, the various technical objects considered are as follows:
Functional Location
Equipment (Main & Sub Equipment)
Bill of Material (BOM)
Work Center
Task List
Measuring Points & Counters
Note: Each of the above technical objects is discussed in detail in “Section 4: Plant
Maintenance Master Data”, in this manual.
With this type of structuring, technical systems were subdivided into functional locations.
For example, by subdividing the hydropower plant into functional locations, we could
represent the individual functional units as functional locations in the system.
With this type of structuring, we subdivided our technical system into pieces of
equipments. A piece of equipment is an individual, physical object that is to be
maintained independently, and that can be installed in a technical system (e.g.
functional location) or part of a technical system.
2.2.3 Combination
We have combined object related structuring using pieces of equipment with functional
structuring using functional locations. In this case, the pieces of equipment were
Page 9 of 346
Training Manual: SAP Plant Maintenance
The functional location represents the site where the technical tasks are performed.
The piece of equipment represents the object with which the technical tasks are
performed.
3. SAP System
SAP means “Systems, Applications & Products” in data processing.
Page 10 of 346
Training Manual: SAP Plant Maintenance
Page 11 of 346
Training Manual: SAP Plant Maintenance
Click on the „Enter‟ button; SAP Easy Access menu screen will appear.
You can either enter the desired transaction code directly on the allocated field or select
the desired transaction via menu path provided in SAP Easy Access menu.
Page 12 of 346
Training Manual: SAP Plant Maintenance
Status Bar: The Status bar provides general information on the SAP System, the
transaction number and the task you are working on. At the left of the status bar, system
messages are displayed. The right end of the status bar contains 03 fields, one with
Server information, the other two with status information.
Menu Bar: The Menu bar allows you to find a specific transaction when you do not
know the transaction code. The menu is organized according to the task you are
performing in the SAP System.
Page 13 of 346
Training Manual: SAP Plant Maintenance
Page 14 of 346
Training Manual: SAP Plant Maintenance
Page 15 of 346
Training Manual: SAP Plant Maintenance
Page 16 of 346
Training Manual: SAP Plant Maintenance
(OR)
Page 17 of 346
Training Manual: SAP Plant Maintenance
Page 18 of 346
Training Manual: SAP Plant Maintenance
Page 19 of 346
Training Manual: SAP Plant Maintenance
Page 20 of 346
Training Manual: SAP Plant Maintenance
Page 21 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to create a functional location master
data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the „Functional location category’ and „Structure indicator’ (In this case, the
structure indicator is always „DG01‟ and the functional location category is always „M‟);
click „Enter‟ key, so that the ‘Edit mask’ appears as shown above.
Page 22 of 346
Training Manual: SAP Plant Maintenance
Click on the „Enter‟ button, to go to the following screen; enter the functional
location that you want to create as per the edit mask defined.
Enter the „Description’ of the functional location that you want to create. Entry in this
field is mandatory.
Page 23 of 346
Training Manual: SAP Plant Maintenance
Enter all the relevant details in fields as shown above. Entry in the „Start-up date’ field is
mandatory.
Note: It is a good practice to maintain all the other relevant fields in the above screen in
order to have optimum data availability in the system, for further reference and analysis.
Enter all the details in fields as shown above. Entry in the ‘Location’ & ‘Plant section’
fields is mandatory.
Enter all the details in fields as mentioned above. Entry in the ‘Cost Center’ field is
mandatory.
Page 24 of 346
Training Manual: SAP Plant Maintenance
Ensure the „SupFunctLoc.’ field is maintained for all sub-functional locations, from the
drop down list (if not maintained automatically by the system).
Ensure the „Equi-installation allwd’ check box is activated, if you need to install
equipment(s).
Page 25 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to change certain details in a functional
location master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the value in „Functional loc.’ field from the drop down list for which the master data
details need to be changed, and click „Enter‟ key.
Page 26 of 346
Training Manual: SAP Plant Maintenance
Choose the relevant field that you want to change and click “F4” key to choose the
exact data as shown above:
For example, the „Catalog profile’ field needs to be changed from ‘000000001’ to
‘PUMPS’. Select the line item called ‘PUMPS’ from the drop down menu and double-
click.
Page 27 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to display a functional location master
data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the value in „Functional loc.’ field from the drop down list for which you want to
display the master data details, and click on the „Enter‟ button.
All the details that you want to view for the above functional location can be viewed.
For example, if you want to know the „Location’ & ‘Section’ of the functional location as
shown above, then click on „Location’ tab and view the details.
Page 28 of 346
Training Manual: SAP Plant Maintenance
Note: To view the list of all the functional locations within the plant, use the following
transaction codes:
Page 29 of 346
Training Manual: SAP Plant Maintenance
4.2 Equipment
Information: The technical object, equipment is an organizational unit within logistics
that structures the maintenance objects of a plant, which is repaired / replaced /
maintained independently and installed / dismantled at a functional location.
Trigger: Perform this procedure when you need to create new equipment master.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Page 30 of 346
Training Manual: SAP Plant Maintenance
Enter the value in „Equipment category’ field from the drop down menu as shown in
screen above. Entry in this field is mandatory.
Note: The equipment number proposed by the system as shown above is temporary.
Enter all relevant details in „General’ tab as shown above. Entry in the „Start-up date’
field is mandatory.
Page 31 of 346
Training Manual: SAP Plant Maintenance
Maintain relevant fields in „Location’ tab as shown above. Entry in the „Location’ &
‘Section’ fields is mandatory.
Maintain relevant fields in „Organisation’ tab as shown above. Entry in the „Cost Center’
field is mandatory.
Page 32 of 346
Training Manual: SAP Plant Maintenance
Now you have installed the equipment to the functional location of your choice, as
shown above.
Page 33 of 346
Training Manual: SAP Plant Maintenance
In this screen, you can maintain the „Warranty’ details for the equipment and documents
such as drawings, manuals, etc. can be attached to the equipment master record. To do
this select the ‘Document type’ (ZDG) and the ‘Document number’, from the drop down
list.
Page 34 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to change certain details to an
equipment master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the equipment number as shown in the above screen and click on the „Enter‟
button, to go to the following screen.
Page 35 of 346
Training Manual: SAP Plant Maintenance
For example, change the ‘ABC indicator’ as shown in the following screen.
Note: Basically the change mode is used to enter a new value in fields which are blank
(these values are entered manually) or to change the existing values in fields to another
value (chosen from the drop down list), if required.
Page 36 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to display equipment master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the equipment number as shown in the above screen and click on the „Enter‟
button, to go to the following screen.
Page 37 of 346
Training Manual: SAP Plant Maintenance
Page 38 of 346
Training Manual: SAP Plant Maintenance
Page 39 of 346
Training Manual: SAP Plant Maintenance
Note: To view the list of all the equipments within the plant, use the following
transaction codes:
Page 40 of 346
Training Manual: SAP Plant Maintenance
Production Resources/Tools can have an additional view PRT Data, in which entries
can be made about task list usage or the status of the PRTs can be set to Locked.
Trigger: Perform this procedure when you need to create Production Resource/Tool
master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the equipment category and click on the „Enter‟ button to go to the next
screen.
Page 41 of 346
Training Manual: SAP Plant Maintenance
Enter details in the ‘Task list usage’, ‘Start reference’ & ‘End reference’ fields.
Now click on the „Save‟ button to save PRT Equipment master. The system
generates the following message.
Page 42 of 346
Training Manual: SAP Plant Maintenance
For Plant Maintenance perspective, it is the list of all raw materials, spare parts, sub-
assemblies, etc., (with their quantities and description) required to construct, overhaul,
or repair during a maintenance activity. In SAP, a BOM is used for material / spare parts
planning by assigning materials/spare parts to a maintenance order.
1. Structuring of object:
If a bill of material is available for a maintenance object, this can be used easily during
the planning of a maintenance order to plan spare parts.
Page 43 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to create Functional Location BOM
master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Choose the ‘Functional loc.’ from the drop down list; enter the „Plant’ & ‘BOM Usage’ as
shown in the above screen and click on the „Enter‟ button.
Page 44 of 346
Training Manual: SAP Plant Maintenance
Enter the „item category’ (L = stock item & N = Non stock item), „material number’ &
‘quantity’ that you want to create as a BOM for the above functional location, as shown
above.
Page 45 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to change Functional Location BOM
master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Select the ‘Functional loc.’ from the drop down list for which you want to display the
details as shown above. Now, click on the „Enter‟ button to go to the next screen.
Page 46 of 346
Training Manual: SAP Plant Maintenance
In this BOM, an additional item (item no. 0030) was added which is shown in the screen
shot above.
Now click on the „Save‟ button to save the changes to functional location BOM.
The system generates a following message.
Page 47 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to create an Equipment BOM master
data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the values in „equipment’, ‘Plant’ & ‘BOM Usage’ (Usage is always „4‟ for Plant
Maintenance use) fields, as shown above.
Note: Click on the „Check‟ button to ensure the plant entered by you is correct; if
the plant entered is incorrect as against the equipment number, then the system will
issue an error message prompting you to maintain the correct plant.
Page 48 of 346
Training Manual: SAP Plant Maintenance
Now click on the „Save‟ button. The system displays the following message.
Page 49 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to do certain changes to Equipment
BOM master data
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the values in „Equipment’, ‘Plant’ & ‘BOM Usage’ (Usage is always „4‟ for Plant
Maintenance use) fields, as shown above.
Page 50 of 346
Training Manual: SAP Plant Maintenance
In this equipment BOM, an additional item (item no. 0030) was added; moreover, the
quantity for line item 2 (item no. 0020) was changed, which is shown in screenshot
above.
Now click on the „Save‟ button to save the changes. The system displays the
following message.
Page 51 of 346
Training Manual: SAP Plant Maintenance
- Main work center in the master record for the equipment or functional location
- Main work center in a maintenance item
- Main work center in the task list header
- Performing work center in the operations for a task list
- Main work center in the order header
- Performing work center in the operations for an order
Trigger: Perform this procedure when you need to create a Work Center master data,
for plant maintenance use.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Page 52 of 346
Training Manual: SAP Plant Maintenance
Enter the values in „Plant’, ‘Work Center’ & ‘Work Center Category’ fields shown in
screenshot as above.
Page 53 of 346
Training Manual: SAP Plant Maintenance
Page 54 of 346
Training Manual: SAP Plant Maintenance
Page 55 of 346
Training Manual: SAP Plant Maintenance
Click on the „Save‟ button; the system displays the following message.
Page 56 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to create a Maintenance Strategy
master data, for Plant Maintenance use.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Page 57 of 346
Training Manual: SAP Plant Maintenance
Page 58 of 346
Training Manual: SAP Plant Maintenance
Click on the „Save‟ button; to view the details of the maintenance package that was
created by you click on the button.
4. Package Sequence
Page 59 of 346
Training Manual: SAP Plant Maintenance
In Plant Maintenance, there are three different types of task lists used. They are,
Trigger: Perform this procedure when you need to do create a General Task List
master data, for Plant Maintenance use.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Page 60 of 346
Training Manual: SAP Plant Maintenance
Enter information in the fields shown in screenshot as above. Make use of the
information furnished in the table below, while entering details in the fields.
Note: In the table below, in column “R/O/C”, “R” = Required, “O” = Optional, “C” =
Conditional.
Page 61 of 346
Training Manual: SAP Plant Maintenance
A long text
is available.
The text on
Descriptive name of the this screen
Task list task list. This is a free text Enter the description is
R
description field to enter a name for the of the task list. transferred
task list. to the first
line of the
long text
screen.
Plant in which maintenance
Planning
tasks are planned or R
plant
prepared.
Key for identifying the work
center responsible for the
Work center R Enter the work center.
completion of the
maintenance tasks.
Number which identifies
Enter the number of
Maintenance the maintenance plant.
R the maintenance
plant This is the plant that the
plant.
work center belongs to.
Usage 4 will
limit the
Indicates the area(s) where usage to
Usage R Enter usage 4
the task list can be used. only Plant
Maintenanc
e.
Key which identifies the Enter a planner group
Planner
planner group responsible R within the
group
for maintaining the task list. maintenance plant.
Indicates the processing
Status R Enter status 4.
status of the task list.
Condition of the equipment
or functional location at the
System Enter the condition, if
time the maintenance / R
condition applicable.
service tasks must be
performed.
The maintenance strategy
Maintenance that controls the sequence Enter a strategy, if
O
strategy of planned maintenance applicable.
tasks.
Set this indicator if you Enter the inspection
Inspection desire to use the task list to point field
O
points process the task on the combination. Always
basis of inspection points. „300‟ for PM use.
Page 62 of 346
Training Manual: SAP Plant Maintenance
Enter information in the fields shown in screenshot as above. Make use of the
information furnished in the table below, while entering details in the fields.
Page 63 of 346
Training Manual: SAP Plant Maintenance
Page 64 of 346
Training Manual: SAP Plant Maintenance
If one of the lines of data needs to be deleted, highlight the line and click on the ‟Delete‟
button;
Additional fields are visible in this view by scrolling to the right. Procedures for
additional fields are covered by selecting the button „Internal‟ (Internal Processing –
Shift+F5) or „External‟ (External Processing – Shift+F6).
Click on the „Selection Box‟ next to select the operation that needs to be processed;
click on the button. A screen will be displayed that will show information the
system will use in processing work orders from in-house entries such as shop labor.
Click on the „Back‟ button to return to the screen, “Create General Task List:
Operation Overview”.
Click on the selection box next to the operation that needs to be processed; further click
on the „External processing‟ button.
Page 65 of 346
Training Manual: SAP Plant Maintenance
Additional information can be added to the task list in the same way that can be done
with the PM orders. Selecting various buttons attached to the operation enters the
additional information.
: Relationship Overview
Service Package can be selected if the appropriate control key is selected for the
operation.
Page 66 of 346
Training Manual: SAP Plant Maintenance
If inspection point descriptions are assigned in the task list header, inspection
characteristics can be selected for the operation.
Page 67 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to do certain changes to an already
created General Maintenance Task List master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
By using the „Copy Reference’ function from another general, equipment, or functional
location task list, you can create a new task list.
The PM System manages all maintenance task lists within a group as one unit. It is
recommended that you divide task lists into several smaller and more manageable
groups. This reduces the volume of data processed when the group is accessed and
has a positive effect on the system response time.
Enter the values in „Group’ & ‘Group counter’ fields (if there are more than one group
counter for the group selected) that you want to change, shown in screenshot as above.
Page 68 of 346
Training Manual: SAP Plant Maintenance
Here we have added the „maintenance strategy’ field called „TEST‟ to the task list.
Page 69 of 346
Training Manual: SAP Plant Maintenance
Here, in the above screen, we can find the „maintenance package’ tab at the bottom left
corner. Click on the button, to go to the next screen.
Click on the „Save‟ button to save the task list. The system displays the following
message.
Page 70 of 346
Training Manual: SAP Plant Maintenance
Page 71 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to view details in an already created
General Maintenance Task List master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the values in ‘Group’ & ‘Group counter’ fields in the screenshot as above; click on
the „Enter‟ button to go to the next screen.
Page 72 of 346
Training Manual: SAP Plant Maintenance
The above screen displays the „maintenance package’ attached to the task list, for all
the operations.
Similarly you can display the components attached, by selecting any operation and
Similarly „Header’ data, ‘Operation’ data (Internal & External) and „Task list’ data can be
displayed by clicking on the respective buttons.
Page 73 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to create a Functional Location Task
List master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the value in ‘Functional location’ from the drop down list for which you want to
create the task list, shown in screenshot as above.
Page 74 of 346
Training Manual: SAP Plant Maintenance
Enter information in the fields shown in screenshot as above. Make use of the
information furnished in the table below, while entering details in the fields.
Page 75 of 346
Training Manual: SAP Plant Maintenance
maintenance tasks.
Usage 4 will
limit the
Indicates the area(s) where usage to
Usage R Enter usage 4.
the task list can be used. only Plant
Maintenanc
e.
Key which identifies the Enter a planner group
Planner group planner group responsible O within the
for maintaining the task list. maintenance plant.
Indicates the processing
Status R Enter status 4.
status of the task list.
Condition of the equipment
or functional location at the
System Enter the condition if
time the maintenance / R
condition applicable.
service tasks must be
performed.
The maintenance strategy
Maintenance that controls the sequence
O Enter a strategy.
strategy of planned maintenance
tasks.
Set this indicator if you
Enter the inspection
desire to use the task list to
Inspec. points O point field
process the task on the
combination.
basis of inspection points.
Page 76 of 346
Training Manual: SAP Plant Maintenance
Enter information in the fields shown in screenshot as above. Make use of the
information furnished in the table below, while entering details in the fields.
Page 77 of 346
Training Manual: SAP Plant Maintenance
plant.
If one of the lines of data needs to be deleted, highlight the line and click on the „Delete‟
button.
Page 78 of 346
Training Manual: SAP Plant Maintenance
Now revert back by clicking „Enter‟ button to go to the “Create Functional Location
Task list: Operation Overview” screen.
Page 79 of 346
Training Manual: SAP Plant Maintenance
Click on the „Save‟ button to save the task list; the system displays the following
message.
Page 80 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to do certain changes to an already
created Functional Location Task List master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter information in the fields shown in screenshot as above. Make use of the
information furnished in the table below, while entering details in the fields.
Page 81 of 346
Training Manual: SAP Plant Maintenance
Page 82 of 346
Training Manual: SAP Plant Maintenance
Page 83 of 346
Training Manual: SAP Plant Maintenance
Enter the values in „Material’ (from drop down list), „Quantity’ and the „Unit‟ fields as
shown in the above screen.
Page 84 of 346
Training Manual: SAP Plant Maintenance
Click on the „Save‟ button to save the task list; the system displays the following
message.
Page 85 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to view details in an already created
Functional Location Task List master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Select the „Functional location’ that you want to display from the drop down list; click on
the „Enter‟ button to go to the next screen.
Page 86 of 346
Training Manual: SAP Plant Maintenance
Select the „Operation 0010’ (line item 1) and click on the tab to display
the material components assigned to the operation as shown in the following screen.
Page 87 of 346
Training Manual: SAP Plant Maintenance
Page 88 of 346
Training Manual: SAP Plant Maintenance
Page 89 of 346
Training Manual: SAP Plant Maintenance
Trigger: Perform this procedure when you need to create an Equipment Task List
master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the value in „Equipment’ field that you want to display from the drop down list;
click on the „Enter‟ button to go to the next screen.
Page 90 of 346
Training Manual: SAP Plant Maintenance
Enter information in the fields shown in screenshot as above. Make use of the
information furnished in the table below, while entering details in the fields.
Page 91 of 346
Training Manual: SAP Plant Maintenance
screen.
Plant in which
Planning
maintenance tasks are R BS01
plant
planned or prepared.
Key for identifying the
work center responsible Enter the work center.
Work center R
for the completion of the MAINT
maintenance tasks.
Number which identifies
Enter the number of
Maintenance the maintenance plant.
R the maintenance
plant This is the plant that the
plant. (CH01)
work center belongs to.
Usage 4 will
limit the
Indicates the area(s)
usage to
Usage where the task list can be R Enter usage 4.
only Plant
used.
Maintenanc
e.
Key which identifies the Enter a planner group
planner group responsible within the
Planner group O
for maintaining the task maintenance plant.
list. (GAR)
Indicates the processing
Status R Enter status 4.
status of the task list.
Condition of the
equipment or functional
System Enter the condition if
location at the time the R
condition applicable.
maintenance / service
tasks must be performed.
The maintenance strategy
Maintenance that controls the sequence
O Enter a strategy.
strategy of planned maintenance
tasks.
Page 92 of 346
Training Manual: SAP Plant Maintenance
All the values are popped up from the earlier screen (Header details) as shown above.
Enter information in the fields shown in screenshot as above. Make use of the
information furnished in the table below, while entering details in the fields.
Page 93 of 346
Training Manual: SAP Plant Maintenance
Page 94 of 346
Training Manual: SAP Plant Maintenance
If one of the lines of data needs to be deleted, highlight the line and click on the „Delete‟
button.
Additional fields are visible in this view by scrolling to the right. Procedures for
additional fields are covered by selecting the buttons „Internal‟ (Internal Processing –
Shift+F5) or „External‟ (External Processing – Shift+F6).
Click on the „Selection box’ next to the operation that needs to be processed. Further,
click on the button. A screen will be displayed that will show information, the
system will use in processing work orders from in-house entries such as shop labor.
Enter information in the fields shown in screenshot as above. Make use of the
information furnished in the table below, while entering details in the fields.
Page 95 of 346
Training Manual: SAP Plant Maintenance
Page 96 of 346
Training Manual: SAP Plant Maintenance
Condition of the
equipment or functional Will default in if
System location at the time the Enter the system entered on the
R
condition maintenance / service condition. header data
tasks must be screen.
performed
Execution factor or the
number of times the
Execution
operation should be O Enter if more than one.
factor
carried out during
processing.
Specifies whether the
If selected, the
cost for externally
Fix. system will not
processed operation is
Operation O Check box as required. take the
to be calculated with or
qty (LFExt) execution factor
without regard to lot
into account.
size.
If the calculation
key is set to
Amount of total work Enter the total work of
Work O determine the
required for the activity. the operation
work duration,
leave blank.
Enter unit of measure.
Unit of measure for the Usually “H”
Un O (May default based on
work. (hours) is used.
profile).
If the calculation
key is set to
Number of capacities or
Enter the number of determine the
Number persons to perform the O
persons, or leave blank. number of
operation.
capacities, leave
blank
If the calculation
Actual duration of the
key is set to
Normal operation. Normally Enter the duration of the
O determine the
duration based on the number of operation
duration, leave
persons.
blank.
Enter unit of measure.
Unit of measure for the Usually “H”
Un R (May default based on
work duration (hours) is used.
profile).
Activity types are
Defaults from the work set up in the CO
center. Can be changed (Controlling) area
Activity type or internal
Activity if needed. Not the and need to be
cost rate for the O
type same as PM valid in the period
operation.
maintenance activity and cost center
type. used before it
can be used.
Page 97 of 346
Training Manual: SAP Plant Maintenance
Click on the „Back‟ button to return to the screen, “Create Equipment Task List:
Operation Overview”. Click on the „Selection box‟ which is next to the operations that
needs to be processed. Now click on the „External processing‟ button.
Enter information in the fields shown in screenshot as above. Make use of the
information furnished in the table below, while entering details in the fields.
Page 98 of 346
Training Manual: SAP Plant Maintenance
Page 99 of 346
Training Manual: SAP Plant Maintenance
before they
can be used.
Material
groups are
Material Material group to be used set up in the
Enter for external
group (Matl for the external operation O MM
process.
group) for analysis purposes. (Materials
Management)
area.
Reference
Section heading
options
Purchasing
groups are
Purchasing group set up in the
Purch. Enter for external
responsible for the external R MM
Group (PGr) process.
operation. (Materials
Management)
area.
Vendors are
Vendor who supplies the Enter if vendor is
Vendor R set up in the
external operation. known.
MM area.
Purchasing
Purchasing organization
Purchasing Enter purchasing Organizations
responsible for the external R
Org. (Porg) organization. are set up in
operation.
the MM area.
Outline
Outline Purchasing document
Enter outline Agreements
agrmnt number for the outline O
agreement. are set up in
(Purch doc.) agreement.
the MM area.
Outline
Outline Unique number or line item Agreement
Enter outline
agrmnt item in the purchasing O items are set
agreement item.
(Item) document. up in the MM
area.
Sort string to sub-divide the Enter an additional
Sort string O
material group if needed. sort if needed.
Purchasing info record Info records
Info record used for procuring the O Enter if known. are set up in
service from the vendor. the MM area.
Additional information can be added to the task list in the same way it can be done with
the PM orders. Selecting various buttons attached to the operation enters the additional
information.
Click on the „Save‟ button to save the task list; the system displays the following
message.
Trigger: Perform this procedure when you need to do certain changes to an already
created Equipment Task List.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the value in ‘Equipment’ field shown in the screenshot as above; click on the
„Enter‟ Button to go to the next screen.
In the above screen, assign the operations to the maintenance packages by clicking the
check boxes as shown above.
Now select „Save‟ button to save the changes made to the „Equipment task list’.
Trigger: Perform this procedure when you need to do view details in an already created
Equipment Task List master data.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the value in ‘Equipment’ field shown in the screenshot as above; click on the
„Enter‟ button to go to the next screen.
Class: The Classification system allows using characteristics, to describe all types of
objects and to group similar objects in classes to classify objects. Classes will then be
used to help user to find objects more easily, using the characteristics defined in them
as search criteria. This ensures that user can find objects with similar or identical
characteristics as quickly as possible. The classification system allows classifying all
types of object.
Procedure:
Start the transaction using the menu path or transaction code, as above.
1. Characteristics
Enter the value in „Characteristic’ & ‘Valid from’ fields, as shown above.
Then, click on the „Create‟ button to create the new characteristic, as shown above.
2. Create Characteristic
3. Change Characteristic
Click on the „Save‟ button to save the characteristic; the system displays the
following message.
Procedure:
Start the transaction using the menu path or transaction code, as above.
1. Class
Enter the value in „Class’ & ‘Valid from’ fields, as shown above.
Then, click on the „Create‟ button to create the new class, as shown above.
2. Create Class
3. Create Class
4. Create Class
Enter the value in ‘Char’ field from the drop down menu (in this case, “Energy
_Production”), as shown above.
Likewise, you can assign more than one characteristic for a class, by using the drop
down list (for example, hour meter reading, power production, temperature, etc.).
Now click on the „Save‟ button to save the class. The system displays the following
message.
4.9 Catalogs
Information: Catalogs are used to manage, uniformly define, and standardise information
(for example: object parts, damage/defect types, cause types, tasks, activities, etc,) on a
client-wide or plant-wide basis. The catalogs can help to record and subsequently evaluate
qualitative data, and to describe problems. In the catalogs, you assign each unit of
information a unique alphanumeric code and an explanatory text.
For Plant Maintenance use, catalogs are structured in the following manner:
Catalog Profile
Catalog types
Codes groups and
Codes
Note: The Catalog profile & Catalogs are predefined in the system. The Code groups for
each catalog and the Codes for each code group are those data which are created based
on the specific Plant Maintenance requirements.
Trigger: Perform this procedure when you need to do create a Code group.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Choose the „Catalog’ from the drop down list and enter „*‟ in the field ‘Code group’ as
shown above; click on the „Enter‟ button to go to the next screen.
Click on the button, to go the new entries; enter the details in the fields
shown in screenshot as above.
Now, click on the „Enter‟ button to go back to the previous screen, as shown below:
The above screenshot displays the new code groups created (in this case, newly
created code groups are 0001, 0002 & 0003).
While working in the same transaction (T Code: QS41), select the code group for which the
codes are to be created, as shown above.
After selecting the desired code group, double-click on the button to go to the
next screen as shown below:
Enter the new codes to be created for the code group „0001 Turbine‟, as shown above.
Now click on the „Save‟ button to save the codes and the code groups. The system
displays the following message.
The code groups and the codes for a code group have now been created.
Trigger: Perform this procedure when you need to do create a Measuring Point.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Note: The measuring point needs to be created as a master data prior to creating the
measurement document.
Select the „MeasPtCategory’ & ‘MeasPointObject’ values from the drop down list as
shown above. In this case, the measuring point is created for the equipment.
Enter the value in ‘Equipment’ field by selecting from the drop down list, for which the
measuring point has to be created, as shown above:
Note: The ‘measurement document number’ is assigned internally by the system. The
‘characteristic unit’ and the ‘decimal places’ are automatically proposed by the system
when the value in ‘Characteristic‟ was entered.
Now click on the „Details‟ button, to go to the next screen shown as above.
4. Additional Data
A new screen is displayed shown as above. Enter the „Upper range limit’ & ‘Lower
range limit’ in the fields shown in screenshot as below:
Trigger: Perform this procedure when you need to do create a Measuring Point
Counter.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Select the „MeasPtCategory’ & ‘MeasPointObject’ from the drop down list. In addition to
the above, activate the „Check box‟ button in „MeasPoint is Counter’ field.
In this case, the measuring point is created for the equipment. Hence, enter the
equipment number from the drop down list, for which the measuring point has to be
created, as shown above.
Note: The ‘measurement document number’ is assigned internally by the system. The
characteristic unit and the decimal places are automatically proposed by the system
based on the characteristic entered. The screen fields are different for a counter based
measuring point.
Now click on the „Save‟ button. The system displays the following message.
4.11 Permits
Information: Permits are used to ensure that special approval must be obtained before
maintenance orders are executed.
Safety precautions for the employees and surroundings: Providing ear protection for
employees, safeguarding the work area, installing a flame-proof zone, work
clearance certificate
Procedure:
Start the transaction using the menu path or transaction code, as above.
The initial screen displays the list of permits that are already created in the system, as
shown above. Click on the button, to go to the next screen.
Now click on the „Save‟ button. The system displays the following message.
4.12 Revision
Information: Revisions are used to group greater maintenance tasks together under
one number which are generally planned on a long term basis.
The revision can be entered in the order. It is thus possible to group several orders
together by using a revision number.
A default date further for the start and the end of the revision is linked to the revision
number.
The revision number can be used as a selection criterion.
Procedure:
Start the transaction using the menu path or transaction code, as above.
The initial screen displays the list of revisions that are already created in the system, as
shown above. Then, click on the button, to create a new revision.
Now click on the „Save‟ button. The system displays the following message.
Service masters are assigned to external operations within a maintenance order for
planning purposes. Once the maintenance order is released, a purchase requisition is
created automatically by the system.
Trigger: Perform this procedure when you need to do create a Service Master.
Procedure:
Start the transaction using the menu path or transaction code, as above.
1. Display Service
The initial screen displays the details of last service master, as shown above; Click on
the „Create‟ button, to create a new service master.
The screenshot as shown above displays a new screen with an activity number which is
temporary number. Do not enter any details in this field.
Now click on the „Save‟ button. The system displays the following message.
4. Display Service
Simultaneously, the system also displays the details of the service master that was
created, as shown above.
MICs are assigned to maintenance task lists which are used or calibration purposes.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the details in fields shown in screenshot as above. Click on the „Continue‟
button, to go to the next screen.
5. Tolerance Keys
6. Quantitative Data
Enter the details in fields shown in screenshot as above. Click on the „Continue‟
button, to go to the next screen.
Note: The above screen now displays the check box against
button ‘activated’.
Now click on the „Save‟ button. The system displays the following message.
Note: It is possible to create new versions (e.g. version1, version2, etc,) for the already
created MICs.
Sampling procedures are assigned to maintenance task lists (used for calibration
purposes).
Trigger: Perform this procedure when you need to do create a Sampling Procedure.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the detail in field shown in screenshot as above. Click on the „Next‟ button, to
go to the next screen.
Enter the detail in field shown in screenshot as above. Click on the „Continue‟
button, to go to the next screen.
Now click on the „Save‟ button. The system displays the following message.
The four steps involved in setting up a maintenance plan are illustrated as below:
Note: Multiple Counter Plans are not used in DGPC Plant Maintenance.
A single cycle plan is used as opposed to a strategy-based plan, for a simple and quick
way to use preventive or inspection plans, where maintenance is performed on the
same single frequency. A single-cycle plan only permits one cycle/ frequency, whereas
a strategy-based plan permits multiple frequencies. The cycle or frequency of a single
cycle plan will vary and is based on either time or performance. If a simple preventive
maintenance plan is desired and one maintenance cycle is sufficient, then a single cycle
plan is created.
The single cycle plan is either based on time or performance, depending on the
requirements of the maintenance object. In contrast to strategy based plans, no
maintenance strategies are defined or assigned for a single cycle plan. The scheduling
parameters are maintained directly in the single cycle plan. All operations in the
allocated task list will be performed at the same frequency in the single cycle plan.
The single cycle plan also includes one or more maintenance items. The maintenance
item contains the task list (list of operations or events) and the maintenance object
(functional location or equipment). It is very important to note that maintenance item(s)
(and the task lists linked in them) do not refer to a maintenance strategy. The
maintenance item is assigned a unique number and entered in the single cycle plan.
Maintenance plans cannot be scheduled without the selection of a maintenance items
from the database.
After scheduling the maintenance plan, the system will automatically generate call
objects (orders or notifications) based on the scheduling parameters in the maintenance
plan.
The various parameters which decide scheduling a maintenance plan described below:
Cycle/Unit: The maintenance cycle defines the interval after which a task becomes
due.
For a time based or performance based strategy plan, the maintenance intervals are
derived from the maintenance packages entered in the maintenance strategy.
For a single cycle plan, you can enter the maintenance interval directly.
Example: Time-based
A task is to be performed every 1000 hours. The cycle is therefore 1000 hours.
Cycle Text: You can use this text to describe a maintenance cycle.
Within a maintenance strategy, you can set out the description for a maintenance
package.
Example:
Monthly
Every 100 kilometers
You must enter an offset when the first time a maintenance package is to be
performed does not correspond with the cycle length.
In the case of multiple counter plans or maintenance cycles, you can use the offset
to perform a maintenance package once only, by maintaining the offset.
Example:
Dependency: This key is assigned internally by the system when you create the
measuring point.
Cycle start: Start date for calculating planned and call dates.
Call horizon: Determines when a maintenance call object (for example, a maintenance
order) should be generated for a waiting maintenance call.
Scheduling period: Determines the period of time, for which the system generates
planned or call dates during scheduling.
Shift factors: The shift factors for early/delayed confirmation of a maintenance task
define what percentage of the shift should be considered for the next date.
Tolerances for shift factors: The tolerances for early/delayed confirmation define the
time period, for which positive or negative differences between actual and planned
dates do not affect subsequent scheduling.
Factory calendar: For the single cycle plan, the factory calendar for the planning plant
is copied into the scheduling parameters as a default value. It can be changed for each
single cycle plan.
When you create a single cycle plan, the cycle is assigned, that is, the period until each
planned date. Orders are generated based on the planned date. However, the actual
call date - the time when the order is, in fact, generated, can differ from the planned
date.
The cycle start defines the date from which the calculation of the planned dates should
begin.
The scheduling period is one of the scheduling parameters in the maintenance plan.
The scheduling period specifies the period for which planned dates should be calculated
in advance.
The scheduling period can be used for time-based and performance-based preventive
maintenance.
The call horizon scheduling parameter is used to define when the order is actually
generated compared to the planned date.
This detailed control of order generation enables you to make a preliminary run of
planning the order before the planned date. The due maintenance task can thereby be
performed and completed punctually on the planned date.
The call horizon is specified as a percentage of the cycle: 100% means that the
order is generated exactly on the planned date. 0% would mean that the order is
generated when the maintenance plan is started.
For a call horizon of 90% and a cycle of 3 months (= 90 days), the call - the generation
of the order - would therefore occur after 81 days (= 90% of 90 days).
Important note: Specifying the call horizon is not sufficient for the order to be
generated, the maintenance plan must be scheduled for this.
The shift factor enables you to react to an early or late completion of a call object. If the
shift factor is 100%, the difference (delay/time ahead of schedule) will be added in full to
the completion date to determine the new planned date.
The next order is only created once the previous order has been technically
completed.
Trigger: Perform this procedure when you need to do create a Single Cycle
Maintenance Plan (Time Based).
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the field shown in screenshot as above; Click on the „Enter‟ button to go to
the next screen.
2. Create Maintenance Plan: Single Cycle Plan (Maintenance Plan Cycle Data)
Enter details shown in screenshot as above; scroll down to view the rest of the screen.
Note: Now, a maintenance plan for single equipment has been defined. If there is a
need for more equipment, which is similar in construction, and has similar maintenance
cycle/periodicity, then it is possible to define the same within this maintenance plan.
To do that, click on the „add more items‟ button to add more items (i.e.
equipments), as shown in screenshot below:
Note: In order to ensure that the details defined were correct while creating this
maintenance plan, it is a good practice to double check all the details entered in all the
fields.
Now click on the „Save‟ button. The system displays the following message.
Trigger: Perform this procedure when you need to do create a Single Cycle
Maintenance Plan (Performance Based).
Procedure:
Start the transaction using the menu path or transaction code, as above.
Note: Performance based single cycle maintenance plan is created when a preventive
maintenance is to be performed based on certain operational parameters.
For example, based on hours run, kilometers run, energy produced, etc. In such cases,
a measuring point counter assigned to the equipment is linked to the maintenance plan
automatically (if there is only one counter exist for an equipment) or manually (if there
exist more than one counter for an equipment).
In order for the system to schedule and generate maintenance orders at appropriate
operational frequency, it becomes mandatory to create measurement document for the
respective measuring point counter; else, system will calculate and generate
maintenance orders based on the time period.
The procedure to create a Performance Based Single Cycle Plan is similar to that of a
Time based Single Cycle Plan, except few changes.
1. Create Maintenance Plan: Single Cycle Plan (Maintenance Plan Cycle Data)
After entering the value in ‘Equipment’ field, wait for the system to propose a counter
relevant to that equipment; else, manually enter the counter number in the field (if
known) as shown in screenshot above.
Note: In order to ensure that the details defined were correct while creating this
maintenance plan, it is a good practice to double check all the details entered in all the
fields.
Now click on the „Save‟ button. The system displays the following message.
Trigger: Perform this procedure when you need to do create a Strategy based
Maintenance Plan (Time or Performance Based).
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the value in „Maint. Plan Cat.’ & ‘Strategy’ fields, shown in screenshot as above.
Click on the „Enter‟ button, to go to the next screen.
Enter the detail in ‘Maintenance plan‟ & ‘Equipment’ fields shown in screenshot as
above. Entry in these fields is mandatory. Click on the „Enter‟ button, to go to the
next screen.
Enter the value in ‘Order Type’ & ‘Counter‟ fields; Click on the „Continue‟ button, to
go to the next screen.
Note that the system has now picked up the proposed counter by you shown in
screenshot as above; also the system has generated a message for the counter
assignment, shown in screenshot as above.
Enter the value in ‘Typ’, ‘Task LstGrp’ & ‘GrpCr’ fields by clicking on the „Select Task
List‟ button. (Note that, the task list that you select from the system should have
same strategy that was entered in the maintenance plan).
Enter the „Priority’ field. Click „Enter‟ key and scroll up the screen.
The maintenance plan cycles proposed by the system based on the strategy that was
selected for the maintenance plan is now displayed shown in screenshot as above.
To do that, click on „Create More Items‟ button to add more maintenance items
(i.e. equipments), as shown in screenshot below, otherwise leave this step.
Note: In order to ensure that the details defined were correct while creating this
maintenance plan, it is a good practice to double check all the details entered in all the
fields.
Now click on the „Save‟ button. The system displays the following message.
Trigger: Perform this procedure when you need to do Schedule a Maintenance Plan.
Procedure:
Start the transaction using the menu path or transaction code, as above.
Enter the value in ‘Maintenanceplan’ field that you want to schedule, shown in
screenshot as above. Click on the „Enter‟ button.
Enter the desired „Start of Cycle’ value for the maintenance plan. Click on the
button.
System displays the list of dates (both call dates & planned dates) for the maintenance
plan based on the scheduling parameters that was defined in the maintenance plan.
Call Date = Date on which the system will generate a call object (in this case,
maintenance order).
Planned Date = Date on which the maintenance order has to be executed.
Now click on the „Save‟ button. The system displays the following message.
Trigger: Perform this procedure when you need to view the Maintenance Plan
Schedule in detail.
Procedure:
Start the transaction using the menu path or transaction code, as above.
For example, enter the ‘maintenance plan category’, ‘planning plant’ & ‘planner group’
so that the system displays the schedule list based on the search criterion shown in
screenshot as above.
The above list displays all details related to the maintenance plan, including the
maintenance order number and its planned date, etc, for equipments.
To do this, select the ‘Order number’ that you want to display in detail and click on the
„Details‟ button or double-click on the ‘Order number‟, shown in screenshot as
above.
The details related to the relevant order are displayed, shown in screenshot as above.
History R
SAP AG
Step 1: Notification of a damage or request for particular work (for example, equipment
break down).
Step 2: Creation and planning of an order based on the notification. Typical planning
tasks include creating operations, making reservations for spare parts, or planning
execution times.
Step 3: Order control with availability check, assigning the work center, printing of order
papers.
Step 4: Actual execution of the work that was requested, including withdrawal of spare
parts from the warehouse and execution of the order.
Step 5: Completion of the work that was actually performed with confirmation and
documentation of technical findings in order to record the condition of the technical
object. The order is settled in Controlling.
In SAP R/3 Plant Maintenance, there are 02 major instruments available for processing
maintenance tasks:
1. Maintenance Notification
2. Maintenance Order
Maintenance Orders are used to plan maintenance tasks and plan or track the costs
incurred. The planning functions do not necessarily have to be executed here.
Maintenance Orders can also be created as immediate orders without any planning.
Procedure:
Perform the following steps to complete notification using the information below:
Complete
Note: When completing a notification it is automatically saved and you do not need to
save the notification again.
8. Click on the „Back‟ button to return to the SAP Easy Access screen.
Different maintenance order types are used to manage the different maintenance
processes performed within DGPC.
Note: The procedure involved in processing the maintenance order types PM01, PM02
& PM06 are similar. Hence, in this manual, only PM01 order type & PM05 order type will
be discussed in detail.
Material requirements: Internal material selection is possible from the inventory list.
Planning of internal materials refers to cataloged and non-cataloged material. Cataloged
material is stock material in the system with an inventory count, whereas, non-cataloged
material is material listed in the system but will purchased every time, if the need exists
for that individual item to be consumed.
External services: Whenever the need arises to buy-in services through predefined
contracts or direct purchases of services not referencing contracts, those services could
be bought in directly through the PM Order.
Production Resource Tools (PRT's): As part of the planning phase for maintenance
orders, special tools to perform maintenance activities could be planned through the PM
Order. Special tools are sometimes required to perform duties and the assignment of
those tools to orders ensured that tool would be available for the planned activity on
time.
Permit: Permit assignment is possible for work orders when assigned to Technical
Objects. Multiple permits could be assigned to Technical Objects and the user can
select any one of them from the proposed system list at the time of order planning.
When the PM Order was generated through the Maintenance Planning cycle, the user
must assign the applicable permit to the PM Order after the work order was generated,
one of the step in the maintenance order process known as „Order Planning‟.
Internal Dates: Once the PM Order has been generated in the system the default date
could be amended to the required date when resources are available. For example,
when the procured services or materials are not available in the desired time; then the
internal dates of the PM Order must be rescheduled.
The progress of work can be monitored using maintenance orders in terms of the
statuses assigned. Depending on the nature of the maintenance work, a predetermined
sequence of statuses must be followed during the maintenance life cycle. Two forms of
statuses are included in the maintenance order. The first form is known as „System
Status‟, which is a standard SAP feature. The second form of status is a „User Status‟
which are user specific and used to control and monitor the order progress. Altogether,
the progress of a maintenance order can be identified at any time based on the statuses
as search criteria.
Maintenance orders are used to settle costs to the appropriate settlement receiver. As
manpower and materials are assigned to a maintenance order, associated costs can be
settled against the settlement receiver. The settlement rule in the maintenance order
determines where the costs are settled, which can either be a cost center or a WBS
element or internal order depending on the maintenance order type.
Trigger: Perform this procedure when you need to create maintenance order from an
already created notification.
Procedure:
Perform the following steps to create maintenance order from an already created
notification, using the information below:
Note: At least one status must be selected for the search. This search only includes the
status Outstanding as we are only looking for notifications that are to be turned into
maintenance orders.
3. To view the bottom of the screen, click on the „Down arrow‟ button located on the
vertical scroll bar.
notification.
Planner group Code that uniquely identifies Defaults from the reference
the group of employees object.
responsible for the planning of
maintenance tasks in a
particular plant.
Note: The * (asterisks) can be used as a ‘wild cards’ to search for the key word within a
field. The wildcard can be used in two ways, at the end of the string (e.g. Motor*) it will
return all entry that begin with the key word. If the wildcard is used at the beginning of
the key word (e.g. * motor) the system will return all entries that contain the key word.
5. To view the bottom of the screen, click on the „Down arrow‟ button located on the
vertical scroll bar.
Note: Enter the appropriate information to narrow down the number of records to be
shown in the list following execution.
7. To initiate the search for notifications matching the search criteria, click on the
„Execute‟ button.
Note: The notifications that match the selection criteria are displayed. If there was only
one notification that matched the search criteria, the system would automatically open
that notification record.
The report works in a similar fashion to ‘Microsoft’ Excel. If you wish to select many
consecutive rows, then click on the first record/row and drag your mouse down,
highlighting the maintenance notifications you wish to select. If you wish to select many
functional location records that are not consecutive, then click on the first record, press
the „Ctrl‟ button, and continue to click on the other maintenance notification records you
wish to select.
8. To select a notification to display, click on the box to the left of the notification number
to highlight.
To create a maintenance order for the notification, follow the menu path given below.
Create order
Object Information
If there are any notifications or orders existing with reference to the equipment in the
system, the above screen pops-up displaying the information.
planned to begin.
FunctLoc. Code that uniquely identifies Defaults from notification,
the functional location for update as required.
which the maintenance order
is raised.
Equipment Number that uniquely Defaults from notification,
identifies the equipment for update as required.
which the maintenance
request is raised
16. To assign a task list to the maintenance order, click on the „Operations‟ tab.
Note: To select a general task list for the maintenance order, follow the menu path
given below:
17. To select a task list that has been created for the technical object, follow the menu
path given below:
Note: If operations already exist in the maintenance order the user will be asked if they
want to delete the existing operation. To retain the existing operations click on the „No‟
button.
Note: If only one task list exists for the technical object the ‘Operation selection using
work center/replace work center’ screen will be displayed.
18. To select the task list to be copied, click on the box to the left of the task list number
to highlight.
19. To copy all the operations within the task list. Click on the „Copy all‟ button.
Note: A message is displayed at the bottom of the screen to confirm that the task list
has been copied into the maintenance order.
20. The following fields are copied into the maintenance order:
21. To create an operation for internal labor, click on the „Operations‟ tab.
Note: The second operation line item details are be described below:
Note: The above fields are to be completed for each new operation to be added to the
maintenance order.
23. Click on the „Enter‟ button.
Note: The system automatically calculates the duration for each activity when using
calculation key 1 in the calculation field.
25. To add long text to an operation, click on the „Create text‟ button located on the
operation line item.
Note: A message is displayed at the bottom of the screen confirming the long text has
been transferred.
28. To create an operation to procure external labor, click on the „Operations‟ tab.
30. To select the operation, click on the box the left of the operation number to highlight.
Error
Note: External labor requirements can be planned using ‘service master’ records or text
items. If there are predefined services then the appropriate service master record is
selected. If it is a once-off purchase then text is used to specify the requirements. If the
service master number is entered directly or a text item is used the price and quantity
must also be entered.
35. To select a service from a service master, click on the „Service Number‟ field to
select the correct service specification.
Activity Number
36. Double click on the „activity number‟ that you want to select.
41 To select the operation to assign materials, click on the box to the left of the
operation, to highlight.
43. To select a component from the BOM for this equipment, click on the Select
„Structural List‟ button.
44. To select a component to copy into the maintenance order, click in the check box to
the left of the material number.
Note: Non-stock, non-catalog component do not have a material master record created
in the system and no physical inventory is maintained. To procure a non-stock, non
catalog material a description of the required material is entered.
56. To add a non stock, non catalogue component to the operations, update the
following required fields:
Note: More than one non catalog component can be assigned against the operation;
the above fields must be completed for each new component.
Note: An error message is displayed, for a non catalog component a material group and
price must be entered.
48. To add a non stock component to an operation, update the following required fields:
Field Name Description Values
Material Number to uniquely identify Enter the material number.
the non stock component to
be used in the maintenance
activity.
Reqmnt qty Number that uniquely Enter material quantity.
identifies the quantity of the
material to be supplied.
52. To select the operation to assign a PRT, click on the box to the left of the operation
to highlight.
Note: To search for a PRT equipment record, the equipment category "P" for PRT can
be used.
58. To determine costs for the maintenance order, click on the „Header data‟ tab.
59. To calculate costs for the order, click on the „Determine costs‟ button.
Note: This screen shows a breakdown the order costs by key figure (grouping of costs).
The order is yet to be released therefore no actual costs will appear on the order.
61. To view a detailed cost report for this order, click on the „Report planned/actual‟
button.
Planned/actual comparison
Note: The report shows a comparison of planned versus actual costs. The costs are
broken down by cost element.
62. To return the cost overview report, click on the „Back‟ button.
Note: The scheduling of a maintenance order is based upon the Basic start and finish
dates in the order header. When the maintenance order is scheduled it looks at the
dates and tries to plan the operations based on these dates.
Note: A message appears at the bottom of the screen to confirm that the scheduling
has been performed and the scheduling log does not contain any errors.
To display the scheduling error log follow the menu path given below:
65. To check material availability for the maintenance order, follow menu path:
Availability check
66. To view the availability check log, click on the „Log‟ button.
Note: The availability check log can contain information, warning or error messages. To
display the messages click on the appropriate button.
68. To return to the availability check log, click on the „Back‟ button.
70. To issue permit for the maintenance order, click on „Header Data‟ tab.
Goto Permits
72. To select a permit to be issued, click in the check box to the left of the permit name
to select.
Note: A message appears at the bottom of the screen confirming the order will be
released after saving the order.
77. To print shop papers for the maintenance order, click on the „Header Data‟ tab.
78. To select the shop papers to print, follow the menu path given below:
Note: The shop papers to be printed need to be selected, the most common shop
papers are pre selected. To select or deselect a shop paper, click on the box the left of
the shop paper.
79. To select the document to print, click on the box to the left of the document
description to highlight.
Note: To view the document online before it is printed, click on the „Print preview‟
button. To return from the print preview screen, click on the „Back‟
button.
Note: Printing the shop papers will automatically save and close your maintenance
order. To make further changes to the order you will need to go into the change order
transaction.
82. To save the maintenance order (if order documents were not printed earlier), click
on the „Save‟ button.
84. Click on the „Back‟ button to return to the SAP Easy Access screen.
Procedure:
Note: If the maintenance order is created from a notification, the initial notification
number is displayed in the Notification field on the top right hand side of the screen.
4. To assign another notification to the same maintenance order, click on the „Objects‟
tab.
Note: The detail of the initial notification is displayed. It is possible to enter the
notification number directly if the number is known.
5. To assign a new notification, click in the first available field in the Notification column
to display the „possible entries‟ button.
Note: At least one status must be selected for the search. This search only includes the
status Outstanding as we are only looking for notifications that are to be assigned to
maintenance orders.
Note: Enter the appropriate information to narrow down the number of records to be
shown in the list following execution.
Note: The notifications that match the selection criteria are displayed. If there is only
one notification that matched the search criteria, the system would automatically default
the notification number into the maintenance order.
Click on „Details‟ button, to view the details of notification prior to copying the
notification number into the order.
9. To select a notification to be copied into the maintenance order, click on the box to
the left of the notification number to highlight.
10. To copy the notification into the order, click on the „Choose‟ button.
14. Click on the „Back‟ button to return to the SAP Easy Access screen.
Trigger: Perform this procedure when you need to maintain a settlement rule for
maintenance order.
Procedure:
Perform the following steps to maintain a settlement rule for maintenance order, using
the information below:
Note: For the majority of maintenance orders the settlement rule will be automatically
determined. Maintenance orders created for a technical object (equipment or functional
location) will use the cost center from the technical object as the cost object in the
settlement rule. If necessary (where the cost centre needs to be changed from the
default cost center, for some reasons), then the settlement rule has to be maintained
(changed).
4. To maintain the settlement rule, follow menu path: Goto Settlement Rule
Note: To create the settlement rule without the default rule, click on the „without
default‟ button.
The ‘Maintain Settlement Rule: Overview’ screen is displayed without any settlement
rules defined.
5. To create the settlement rule using the default, click on the „with default‟
button.
Note: A message is displayed at the bottom of the screen confirming the settlement rule
was created using the default.
6. To delete a settlement rule place the cursor in the first field of the settlement rule,
click on the „Delete rule‟ button.
7. To delete the second settlement rule, place the cursor in the first field of the
settlement rule, click on the „Delete rule‟ button.
10. To return to the settlement rule overview, click on the „Back‟ button.
11. To return to the maintenance order overview, click on the „Back‟ button.
Note: The system status SETC (Settlement rule created) is now displayed in the system
status field.
12. To save the maintenance order, click on the „Save‟ button.
13. The message bar displays "Order saved with number NNNNNNNNN"
14. Click on the Back button to return to the SAP Easy Access screen.
Trigger: Perform this procedure when you need to perform an individual time
confirmation for an operation within a maintenance order.
Procedure:
Perform the following steps to perform an individual time confirmation for an operation
within a maintenance order, using the information below:
Note: If only the maintenance order on the initial screen a list of operations for the order
is displayed.
To select multiple operations to confirm time, hold the ‘Ctrl key’ and click on the box to
the left of the operation number to highlight the operation.
4. To select the operations to enter a time confirmation, click on the box to the left of the
operation number to highlight.
Note: The first operation selected is displayed; enter the confirmation details for this
operation.
7. To move onto the next selected operation, click on the „Next operation‟ button.
Note: The next operation selected is displayed; enter the confirmation details for this
operation. Once the last operation has been reached, click on the Save button.
Work start Date when the actual work for Enter start date.
(first field) this operation was started.
Work start Time when the actual work for Enter start time.
(second field) this operation was started.
Work end Date when the actual work for Enter end date.
(first field) this operation was completed.
Work end Time when the actual work for Enter end time.
(second field) this operation was completed.
Reason Code that identifies why the Enter reason code.
operation has not been
completed. The code will
update the user status of the
order operation
Confirm text Additional text that can be Enter confirmation text.
entered to provide further
information regarding the
confirmation.
Note: If the operation has not been completed, the final confirmation indicator is not set.
If the operation is on hold for any reason a reason code should be selected. The reason
will update the operation use status to indicate why the operation is on hold.
11. Click on the „Back‟ button to return to the SAP Easy Access screen.
Trigger: Perform this procedure when you need to perform collective time confirmation
for operations.
Procedure:
Perform the following steps on how to enter collective time confirmations with a
selection list, using the information below:
Note: Enter the necessary selection criteria to limit the number of time confirmations
that are to be displayed.
3. To view the bottom of the screen, click on the „Down arrow‟ button located on the
vertical scroll bar.
Note: Enter the necessary selection criteria to limit the number of time confirmations
that are to be displayed.
Note: The details of the operations selected are copied into the collective confirmation
screen.
Note: The default values are copied into the time confirmation line items.
6. To select the operations to default the values from the maintenance order, click on
the box to the left of the confirmation number to highlight.
7. To copy the actual data from the maintenance order, click on the „Propose all actual
data‟ button.
Note: The actual data from the maintenance order is copied into the collective
confirmation screen for each selected operation.
8. Update the following required and optional fields for each of the operations a time
confirmation is being created for.
9. To scroll across to the right of the screen to view the additional fields for an operation,
click on the „Move right‟ button located at the bottom of the screen.
10. Update the following required and optional fields for each of the operations a time
confirmation is being created for.
12. To save the time confirmations entered, click on the „Save‟ button.
13. Click on the „Back‟ button to return to the SAP Easy Access screen.
Trigger: Perform this procedure when you need to perform technical completion of a
maintenance order.
Procedure:
Note: Before technically completing (TECO) an order, it is a good practice to review the
information displayed in system status and user status fields. This will indicate whether
all time confirmations were completed, all goods movements posted, settlement rule
created (for system status) and work completed or permit closed by operation (for User
Status) for the maintenance order.
For example, click on the „status‟ button which is found in between the system
status & the user status fields.
Complete
Note: When completing a notification it is automatically saved and you do not need to
save the notification again.
8. Click on the „Back‟ button to return to the SAP Easy Access screen.
Trigger: Perform this procedure when you need to perform business completion of a
maintenance order.
Procedure:
Note: Before performing the „Business Completion‟ of an order, the maintenance order
should have been settled for the costs transfer (from the maintenance order to the
settlement receiver, generally a cost center). This transaction (KO88) is a financial
transaction. Business completion of a maintenance order will not be possible, until and
unless the maintenance order is settled.
6. Click on the „Back‟ button to return to the SAP Easy Access screen.
Trigger: Perform this procedure when you need to maintain user status for a
maintenance order.
Procedure:
Perform the following steps to perform to maintain user status for a maintenance order,
using the information below:
4. To change the user status, click on the „Status‟ button located in the middle of
the ‘System status’ and the user status fields.
Change Status
Note: The user statuses that are available to be used at the order header are displayed.
To deselect a user status, click in the „check box‟ to the left of the user status to
deselect.
5. To set a user status, click in the check box to the left of the user status to set. In this
example; the user status CRTD for „Created‟ is displayed.
Note: The user statuses are displayed in the second half of the ‘System status’ line, the
user status PERP is included in the status line.
7. To set a user status for an operation within the order, click on the „Operations‟ tab.
8. To select an operation to change the user status, click on the box to the left of the
operation number to highlight.
9. To change the operation user status, click on the „Operation status‟ button.
Change Status
Note: The user statuses that are available to be used at the order operation are
displayed.
To deselect a user status, click in the „check box‟ to the left of the user status to
deselect.
10. To set a user status, click in the „check box‟ to the left of the user status to set. In
this example; the user status INPR for „Work In Progress‟ is selected.
14. Click on the „Back‟ button to return to the SAP Easy Access screen.
DGPC will use PM05 order type to carry out the calibration process.
The various process steps involved in a calibration order is described in detail below:
Trigger: Perform this procedure when you need to create a task list for a calibration
activity.
Procedure:
Perform the following steps to perform to create a task list for a calibration activity, using
the information below:
Note: You can also create an equipment task list. But to minimize the work you can
create a general task list and assign to any number similar equipments of same family.
Enter the valid from date a past date to avoid date clashes while scheduling a
maintenance plan for calibration.
In addition to entering the details while creating a general task list as described in
section 4.7.1, enter the inspection point number as 300.
4. Select the line item (0010) by clicking on the left side corner of the operation that
was entered.
6. Enter the „Master Inspection Characteristic No (MIC)’, ‘Version’ (if more versions
have been created) and ‘Sampling Procedure No.‟ fields.
Note: If you do not assign MIC in the operation then inspection lot will not be generated
in the calibration order.
9. Click on the „Exit‟ button to return to the SAP Easy Access Menu.
Trigger: Perform this procedure when you need to create a maintenance plan and
assign the task list that was created for the calibration activity.
Procedure:
Perform the following steps to perform to create a maintenance plan and assign the task
list that was created for the calibration activity, using the information below:
1. Start the transaction using the menu path or transaction code, as above.
Create Maintenance Plan: Single Cycle Plan (Maintenance Plan Cycle Data)
4. To assign a correct task list for this maintenance plan, click on the „Select Task
List‟ button.
5. Select the task list by placing the cursor on the line item and click on the „Choose‟
button.
The task list that was selected has been copied in the task list no filed; also the system
issues the following message;
Create Maintenance Plan: Single Cycle Plan (Maintenance Plan Additional Data)
Note: Now, a maintenance plan for single equipment has been defined. If there is a
need for more equipment, which is similar in construction, and has similar maintenance
cycle/periodicity, then it is possible to define the same within this maintenance plan.
8. To add more items within the maintenance plan, click on the „Create more items‟
button to add more items (i.e. equipments), as shown in screenshot below:
Note: In order to ensure that the details defined were correct while creating this
maintenance plan, it is a good practice to double check all the details entered in all the
fields.
9. Now click on the „Save‟ button. The system displays the following message.
Trigger: Perform this procedure when you need to do schedule a Maintenance Plan.
Procedure:
1. Start the transaction using the menu path or transaction code, as above.
Enter the maintenance plan number that you want to schedule, shown in screenshot as
above.
2. Click on the „Enter‟ button.
Enter the desired start of cycle date for the maintenance plan.
System displays the list of dates (both call dates & planned dates) for the maintenance
plan based on the scheduling parameters that was defined in the maintenance plan.
Call Date = Date on which the system will generate a call object (in this case,
maintenance order).
Now click on the „Save‟ button. The system displays the following message.
Trigger: Perform this procedure when you need to view the calibration order that was
auto generated through the maintenance plan, by using the scheduling overview list.
Procedure:
1. Start the transaction using the menu path or transaction code, as above.
Based on the scheduling parameters defined in the maintenance plan, the system
generates the call objects (i.e. calibration orders), as shown above. The order numbers
are shown against each maintenance item and maintenance plan.
3. To view the details of the calibration order, place the cursor on the order number
field and click on the „Details‟ button.
Now this order is ‘Released’ for further processing (see the system status)
7. To go back to the SAP Easy Access Menu, click on the „Back‟ button.
Trigger: Perform this procedure when you need to process the calibration order.
Procedure:
Perform the following steps to perform to process the calibration order, using the
information below:
The „inspection lot‟ button is displayed, next to order text, as shown above.
Note: Inspection lot as displayed above is applicable for PM05 order type only.
2. Click on the „inspection lot‟ button, to see the details of the inspection lot.
Trigger: Perform this procedure when you need to process the inspection lot generated
by the system through the calibration order.
Procedure:
Perform the following steps to perform to process the inspection lot that was generated
through the calibration order, using the information below:
2. To select the inspection lot with reference to the calibration order, click on the
„Dynamic Selections‟ button.
Click on the „Production‟ line item; then double-click on the „Order‟ line item so that the
Order field is displayed on the right side of the screen.
Enter the „Order‟ number for which the inspection lot needs to be processed.
Note: Before clicking on the „Execute‟ button, ensure the „Lot Creation Date‟ fields
have the correct range of dates.
4. To record the results, select the line item of the inspection lot; then click on the
„Results‟ push button as shown above, to go to the next screen.
The results recording screen for the relevant inspection lot is now displayed for entering
the actual results, as shown above.
6. To record the actual results, enter the actual data in the „Result‟ field for each line
item.
The actual results entered are stored in the „Original Value‟ fields with „Inspected Qty‟ as
1, for each line item as shown above.
7. To save the results recording, click on the „Select All‟ button and then click on the
„Save‟ button.
The system goes back to the original status; note that, now the system status has
changed after the results recording (i.e.: INSP = Inspected, RREC = Results Recorded).
8. To perform the usage decision for this inspection lot, select the line item and click on
All the actual results that were entered are now displayed in the screen as shown
above.
9. To perform the usage decision (manual) for the completed results recording, click on
the „possible entries‟ button from the „UD Code‟ field.
10. Select the correct usage decision code and click on the button; click on
the „Save‟ button.
Now the system status has changed to UD ICCO (i.e.: UD = Usage Decision ICCO =
Inspection Completed).
11. To see the inspection report, select the line item of the relevant inspection lot and
12. A new screen will appear as below, which has the inspection lot number; click on
the „Execute‟ button.
Results Printout
13. A new screen appears as below; to view the inspection report, simply click on the
„Print Preview‟ button.
15. To view the second page click on the „Next Page‟ button.
16. To go back to the SAP Easy Access Menu, click on the „Back‟ button.
Procedure:
Perform the following steps to create a document, using the information below:
Select the file from the directory and click on the „OPEN‟ button. The selected file is
copied to the DMS screen.
The above screen appears; place the cursor on the line item and right-click. The drop
don list appears as shown above. Bring the cursor down and double-click on the „Check
In‟ line item.
6. After completion of the document „check in‟, the status of the „Lock‟ is changed from
„OPEN‟ to „CLOSED‟ as shown below:
7. Click on the „additional data‟ tab and select the relevant document type. This
will become helpful while searching the document later.
8. To link the document that is being created to a technical object, click on the „object
link‟ tab, as shown below;
For example, equipment number 2000006 is linked to this document, as shown above.
9. To save the document that was created, click on the „Save‟ button.
10. To view the document that was linked to the technical object (i.e. equipment in this
case), use the T Code IE03.
Click on the „Other‟ tab. Select the line item of the document number.
10. To go back to the SAP Easy Access Menu, click on the „Back‟ button.
Procedure:
Perform the following steps to create a new version for a document, using the
information below:
Enter the document number, document type, document part & document version for
which a new version has to be created, as shown above.
If already document is assigned to SAP object, system will display object selection
screen as shown above.
5. Give necessary inputs in the respective tabs (Document data, Additional Data, Object
Links) if required.
7. To go back to the SAP Easy Access Menu, click on the „Back‟ button.
Procedure:
Perform the following steps to change a document, using the information below:
Enter document number, document type, document part & document version in fields a
shown above.
type from
the search help
Section of a document
Document which is maintained as
R
part an independent Enter the appropriate
document document
Number which identifies part & version (if any)
Document
the version of a R
version
document
3. To make other changes use tabs such as Document data, Additional Data, Object
links.
4. To change the document, click on the „Change Original‟ button, and when the
file opens up make necessary changes and „Save‟ the file.
5. Carry out the „Document Check In‟ process once again till the „Lock‟ is found in
„Locked‟ position.
7. To go back to the SAP Easy Access Menu, click on the „Back‟ button.
Procedure:
Perform the following steps to display & distribute a document, using the information
below:
Enter document number, document type, document part & document version in fields a
shown above.
3. To display the document, select the document number line item and click on the
„Display Original‟ button.
Document Display
2. To distribute the document to the SAP users, follow the path as shown in screen
shot below:
Start Distribution
Enter the receipients address, return date, confirmation receipt, distribute immediate
fields (if required).
8. To confirm the receipt of document (for example, since one of the recipient in the
above distribution list was myself), go to the SAP EASY Access Menu and click on the
„SAP Business Workplace‟ button.
Document Receipt
10. To display the document that was received, place the cursor on the number and
click on the „Document Number‟.
11. To view the document, select the line item of the document number and click on the
„Display Original‟ button.
Document Display
12. To go back to the SAP Easy Access Menu, click on the „Back‟ button.
Once the Variant & Layout is created and saved with a reference number with the user
defined field settings, the system allows the user to display the standard SAP reports
the way he/she wants.
Procedure:
Perform the following steps to create a screen variant, using the information below:
The above list is based on the standard SAP search variant, which displays the „start
date‟ as 24.11.2010 & „end data‟ as 22.02.2011. Also the „order status‟ tab displays
„outstanding‟ & „in process‟ check boxes activated.
2. Based on the above standard search criterion that is set as default by SAP, the
report output will be as follows, after clicking on the „Execute‟ button.
3. Now, a user wants to display this report based on the following search criteria:
5. After entering the above details, click on the „Save as variant‟ button. System
will go to the next screen.
Scroll down the screen so that the start date and end date fields are visible.
Variant Attributes
3. Select the „From date‟ line item; go to „Selection Variable‟ and click on the
„possible entries‟ button.
Variant Attributes
Select the line item „D: Dynamic Date Calculation‟. Click on the „Choose‟ button.
8. Go to the „Name of Variable‟ field and click on the „possible entries‟ button.
Variant Attributes
Select the „Current date +/- ??? days‟ and click „Choose‟ button.
9. System will pop up a new screen. Enter the value in the field as shown below;
10. Click on the „Copy‟ button. System will copy the data as follows;
12. To maintain the value in „To date‟ field, do the similar exercise as described in step
nos. 6, 7, 8 & 9.
Variant Attributes
Variant Attributes
13. Click on the „Save as variant‟ button. System will go to the next screen.
13. To display the report based on the variant created (i.e.: IW39_CH01), click on the
„Get Variant‟ button.
Select the IW39_CH01 variant name and click on the „Choose‟ button.
14. The system displays the similar initial screen like earlier, but with different dates,
plant and work center details. The screenshot is displayed as below:
15. To display the order details based on the search criteria that were set in variant
IW39_CH01, simply click on the „Execute‟ button.
1. To go back to the SAP Easy Access Menu, click on the „Back‟ button.
Procedure:
Perform the following steps to create a screen layout, using the information below:
Here the screen variant IW39_CH01 was selected to display the above layout report.
This layout report displays only the order number, order type, basic start date, and
description fields.
Change Layout
4. Move the field names which are in the Column Set to the Displayed Columns by
selecting the field and clicking on the „Left Arrow‟ button.
Change Layout
All the selected fields from the „Column Set‟ are moved to „Displayed Columns‟ now
as shown above.
5. Click on the „Save Layout‟ button, to save the newly created layout.
Save Layout
Enter the name of the layout and its description. Also ensure the „User-specific‟ field is
activated, as shown above. Do not activate „Default setting‟ field.
6. Click on the „Continue‟ button to see the new layout screen as below:
8. To view the report based on the newly created screen variant & layout, go back to the
SAP Easy Access Menu.
9. Enter T Code IW39. Select the screen variant IW39_CH01. Scroll down the screen till
it reaches last.
10. Enter the value in „Layout‟ field that was created by you.
11. Now click on the „Execute‟ button, to view the report of your choice based on
the screen variant & layout.
Note: The above demonstration on creating a customised screen variant & layout is
only an example. Users can create their own customised screen variant & layout based
on their need.
13. To go back to the SAP Easy Access Menu, click on the „Back‟ button.
2. Creation of accident report along with attaching the above mentioned documents.
In SAP, the various transactions involved in accident reporting process are as follows:
3. List display of accident reports (ZPM_AR3) including Save & Print out
option of the report.
Trigger: Perform this procedure when you need to create a document in DMS
(Document Management System).
Procedure:
Perform the following steps to create a document (for storing the accident evidential
documents) in DMS, using the information below:
Enter the ‘document type’ as ZPM, ‘document part’ as 000 and ‘document version’ as
00.
For information,
Please note the ‘Document Status’ field is maintained as “PR” (In Preparation) and is
“Not Released”.
3. Document Attachment
Click on ‘Open Original’ button to attach the desired document (i.e. Sample Test
Data Sheet).
Please note, upon attachment of document the ‘Secure Storage Area’ (Lock) is in
unlocked position.
4. Document Check-In
Select the line item and click on the ‘Check-In Orig.’ button or right-click the mouse
and select the line item ‘Check In’ and click on the same.
Select the ‘Storage Category’ as DMS_C1_ST (Default Storage DMS) and click on the
‘Enter’ button.
Now the document has been checked-in (see the change in the position of the lock), as
below.
5. Document Save
Note: The „Accident related evidential documents‟ are now stored in the SAP
system through DMS (Document Management System). The same can be retrieved
from the SAP system at any point in time with reference to the document number, as
mentioned above.
Trigger: Perform this procedure when you need to create a sales order.
Procedure:
Perform the following steps to create a sales order, using the information below:
Trigger: Perform this procedure when you need to display accident report.
Procedure:
Perform the following steps to display an accident report, using the information below:
Note: By clicking the „Execute‟ button, the system will display the list of all the
accident report created so for.
3. Place the cursor on the accident report number and left-click the same in order to
display the particular accident report in full.
Print:
Enter detail in ‘Output Device’ field and click on the ‘Print Preview’ button.
Print Preview:
5. Use the following functionality to ‘Save’ & ‘Print’ the accident report.