You are on page 1of 72

CONSTRUCTION MANAGEMENT

CONSTRUCTION
PROCESS
LECTURE 2
Dr.Ananthan 2020 1
Life Cycle of a Construction Project

• 6 basic phases :
Concept and feasibility studies
Engineering and design
Procurement
Construction
Start up and implementation
Operation or utilization

Dr.Ananthan 2020 2
Dr.Ananthan 2020 3
Concept and feasibility studies

• Conceptual analyses
• Technical and economic feasibility studies
• Environmental impact report.

Dr.Ananthan 2020 4
Dr.Ananthan 2020 5
Dr.Ananthan 2020 6
Dr.Ananthan 2020 7
Dr.Ananthan 2020 8
KT DRAW BRIDGE
• The iconic drawbridge linking Kuala Terengganu City Centre to
Kuala Nerus via Seberang Takir, will be a new state landmark
when completed by end of this year. The construction work
on the RM240 million, 638m drawbridge.

• The bridge would shorten the journey from Kuala Terengganu


to the Sultan Mahmud Airport to approximately 10 minutes
via a coastal road which was be built by the state government.

Dr.Ananthan 2020 9
Dr.Ananthan 2020 10
Engineering and design
• Preliminary engineering & design
– Stresses on architectural concept
– Evaluation of technological process alternatives
– Size and capacity decision
– Comparative economic studies (choice whether
IBS or conventional) types of construction
method

Dr.Ananthan 2020 11
Engineering and design
– For example, in a high rise building:
• Determines number and spacing of the stories.
• General layout of services and occupied floor spaces.
• General functional allocations.
• Steel or reinforced concrete structure.

Dr.Ananthan 2020 12
Engineering and design

• Detailed Engineering & Design


– Process of breaking down, analyzing and
designing the structure and elements to
comply with recognized standards of safety
and performance.

– Designs will be in the form of a set of explicit


drawings and specifications that will tell the
constructors exactly how to build the structure
at site.
Dr.Ananthan 2020 13
Types of Construction Method
1. Cast in-situ method.
2. Composite method.
3. Fully pre-fabricated method.

Dr.Ananthan 2020 14
1. Cast In-situ Method
- construction on site
- formwork is used as mould where wet
concrete is poured into a temporary
system

2. Composite Method
- Partially pre-fabricated
examples:- steel roof truss, wall frames

3. Fully Pre-Fabricated method


- all elements pre-fabricated in the factory
- can involve the assembly of precast
elements such as floor slabs, in-filled
walls,
bathrooms, staircases, etc
Dr.Ananthan 2020 15
Dr.Ananthan 2020 16
Dr.Ananthan 2020 17
Dr.Ananthan 2020 18
Dr.Ananthan 2020 19
Dr.Ananthan 2020 20
Dr.Ananthan 2020 21
Dr.Ananthan 2020 22
Dr.Ananthan 2020 23
Dr.Ananthan 2020 24
Procurement
• Contracting and sub contracting.
• Obtaining materials and equipment required
to construct the project.

* Both dependent on the contractual approach


taken for the particular project.

Dr.Ananthan 2020 25
Construction
• Designer’s plans and specifications are concerted
into physical structures.

• Involves the organization & coordination of all the


resources for the project. Ex. Labor, construction
equipment, money, etc to complete the project
within __________, ____________ & ___________
specified by the designer.

Dr.Ananthan 2020 26
Start Up and Implementation

• To make sure all components function well


together as a total system.
• May involve testing, adjusting and correcting
the major electrical and mechanical systems
so that they perform at their optimum level.

Dr.Ananthan 2020 27
Operation & Utilization
• Utilisation of structure.

Dr.Ananthan 2020 28
The Construction Process
•Client identifies the need for the item of construction
Conceptual •Client appoints and briefs consultants
Stage •Consultants study the client’s requirement, propose an
outline of the design and assess the feasibility of the
project

•The concept of the project is further developed


Design Stage •Prepare the production information and contract
document
•Call tenders

Construction •Prepare production programmes


Stage •Construction carried out on the site

Operation & •The completed building or works is maintained, repaired


or altered as required, over the course of its life.
Maintenance
Stage Dr.Ananthan 2020 29
Characteristics
of a
Construction Project

Dr.Ananthan 2020 30
Management in construction
can be divided into two distinct
levels:
1. Management at the company
(corporate) level.

2. Management at project level.


Dr.Ananthan 2020 31
Nature of
Construction Industry

Dr.Ananthan 2020 32
Nature of the Construction Industry

• Management of construction projects differs from


that in other industries due to the unique nature of
the construction industry;
1. Heterogeneous and fragmented firms
2. Size of firms
3. Size of the industry
4. Regulator of the economy
5. Characteristics of projects
6. Characteristics of workforce
7. Ease of entry to the industry
8. Separation of design and production
9. Speculative demand
Dr.Ananthan 2020 33
Heterogeneous and fragmented firms

• Construction industry comprises of a group


of heterogeneous and fragmented firms,
meaning;
- there are large differences between
firms in terms of size and scope of
work, and
- within firms there is often diversity in
activities.

Dr.Ananthan 2020 34
Dr.Ananthan 2020 35
Size of firms

• The construction industry is made up of


mostly small firms.
• The small and medium sized firms however
accounts for only around
20-30 % of the total construction works.

Dr.Ananthan 2020 36
Dr.Ananthan 2020 37
Size of the industry

• The size of the construction industry is large;


- 3 to 14 % of a nation’s GDP
- employs between 5-12 % of the total workforce.
• These figures for GDP and labour employed would
be much higher if other closely related industries,
especially construction material manufacturers, are
considered. Gross Domestic Product (GDP) is the best way to
measure a country's economy. It includes everything
produced by all the people and companies that are in
the country.

Dr.Ananthan 2020 38
Dr.Ananthan 2020 39
• GDP From Construction in Malaysia decreased
to 15350 MYR Million in the first quarter of
2020 from 16575 MYR Million in the fourth
quarter of 2019.

Dr.Ananthan 2020 40
Construction industry as a regulator of the economy.

• Due to its large size and its wide influence over


other related industry, the government has very
often used the construction industry as a regulator
of the national economy.
• This done in the following ways:
- Direct intervention as a major client for the
industry.
- Indirectly through the manipulation of interest rates to
control private sector building demand

Dr.Ananthan 2020 41
Dec. 11, 2003

KUALA LUMPUR, Malaysia -- In one of its first


major economic-policy decisions, Malaysian Prime
Minister Abdullah Ahmad Badawi's government
said it plans to halt construction on a controversial
14.5 billion ringgit ($3.82 billion) railway project.

Dr.Ananthan 2020 42
KL can save $100b by dropping 3 mega projects:
Mahathir
• SHAH ALAM • The Malaysian government could reduce its
total debts by RM300 billion (S$99.5 billion) by cancelling
three mega projects started by the previous government,
Prime Minister Mahathir Mohamad said yesterday.
• These are the Kuala Lumpur-Singapore High-Speed Rail (HSR),
the East Coast Rail Line (ECRL) and the trans-Sabah gas
pipeline projects, he said at a talk show in the Selangor
capital, adding that these projects are too costly to be funded
by the government.
• Malaysia and Singapore last month signed an agreement to
postpone work on the HSR for about two years, up to May 31,
2020.
Dr.Ananthan 2020 43
Ease of entry to the industry

• There are few constraints to setting up a


contracting or property/housing
development business.
• The authorities have imposed mandatory
registration for contractors as well as
developers, but the conditions for
registration are relatively easy compared to
the consultants.

Dr.Ananthan 2020 44
Separation of design and production

• Traditionally design is separated from


production, making the management of the
construction process difficult and
complicated; reasons being:
(i) conflict of interests between the
designers and constructors,
(ii) poor communication and coordination.
*How can the above difficulties be overcome?
Dr.Ananthan 2020 45
The nature of demand

• The demand for construction projects is


called ‘derived’ demand; meaning it is
derived from the need for buildings or
infrastructure in which to live, play, work and
to manufacture, store and transport goods,
etc.

Dr.Ananthan 2020 46
Dr.Ananthan 2020 47
Dr.Ananthan 2020 48
Dr.Ananthan 2020 49
Characteristics of projects

The industry is project-based, with construction


works having the following characteristics:
• projects are large discrete units,
• works are carried out over relatively long
duration,
• projects are constructed away from where the
firms are located,
• projects undertaken by any one firm are
geographically dispersed,
• majority of projects are designed and tailor-made
to a client’s requirements,
Dr.Ananthan 2020 50
Cont’d
• there is wide variability in the types of
construction projects,
• prices for projects are established through
competitive tendering; meaning the products
are sold before they are produced,
• each individual project frequently constitutes a
significant proportion of a firm’s workload, and
• projects are built based on speculative demand.

Dr.Ananthan 2020 51
End of lecture on
Nature of Construction Industry

Dr.Ananthan 2020 52
The Contractual Relationships among the
Participants

• The contractual relationships among the parties


involved in a project depend on the procurement
method used for the project.
• Procurement methods can be broadly classified
under the following:
- Traditional approach
- Design-and-Build
- Management contracting
- Construction management
- Partnering

Dr.Ananthan 2020 53
Some models of
contractual relationship

Dr.Ananthan 2020 54
TRADITIONAL METHOD
• is based upon rigid separation of design and construction

• The promoter, usually after undertaking a feasibility study,


appoint a team of consultant (led by architect/engineer) to
under take the detail design.

• The design team prepares detailed drawing, specifications and


often Bill of Quantities.The tender documents are prepared
and the contract awarded, usually to the contractor with the
lowest bid.

Dr.Ananthan 2020 55
CONTRACTUAL AND FUNCTION RELATIONSHIP (Traditional Method)

CLIENT

DESIGN ARCHITECT ACTING AS QUANTITY


CONULTANTS DESIGN LEADER AND SURVEYOR
PROJECT MANAGER

MAIN CONTRACTOR

NOMINATED / NAMED DOMESTIC


SUBCONTRACTORS SUBCONTRACTOR

Contractual relationship

Functional relationship
Alternative relationship
Dr.Ananthan 2020 56
Dr.Ananthan 2020 57
DESIGN & BUILT METHOD

• one building contractor or a construction


company to take full responsibility and carry
sole liability for the design and construction of
a building

Dr.Ananthan 2020 58
DESIGN & BUILT METHOD

• Early delivery of project is required


• - Project is of technical complexity
• - There is the need for early start on site
• - Price certainty (usually fixed lump sum) is
required prior to production
• - Construction project is prestigious and hence
single point responsibility is required
• - Economy (time, cost, function, quality, value
for money) is required.

Dr.Ananthan 2020 59
ORGANISATION STRUCTURE (D & B)

CLIENT
CLIENT’S
AGENTS

MAIN
CONTRACTOR

CONTRACTOR’S PROJECT TEAM

QUANTITY ARCHITECT ENGINEER CONTRACTOR’S MANAGER


SURVEYOR
CONTRACTOR’S SITE TEAM

SITE SITE SITE SUPPORT


MANAGER ENGINEER SURVEYOR STAFF

Contractual relationship
Organisational relationship

Dr.Ananthan 2020 60
Dr.Ananthan 2020 61
Turnkey

THE TURNKEY CONTRACTOR IS MADE FULLY


AND TOTALLY RESPONSIBLE FOR EVERYTHING
FROM PLANNING, DESIGN, CONSTRUCTION AND
SUPERVISION.

Dr.Ananthan 2020 62
Ideal Prestige Sdn Bhd (Ideal Prestige) has signed a turnkey development
contract with the Metallurgical Corporation of China Construction Overseas
Ltd (MCC Construction) for Pacific Parade, which is poised to become
Sabah’s largest commercial development.

Dr.Ananthan 2020 63
CONSTRUCTION MANAGEMENT METHOD

• delivery of a high-quality construction product on


time at the least cost
• similar to the management contract approach except
– construction manager - consultant - employed by the
client in a purely managerial capacity
– direct contractual relationship between the various works
contractors and the client
– The design team and construction manager possess
equal professional status.
– client has direct responsibility for his or her project and
flexibility in procuring the various specialist services.

Dr.Ananthan 2020 64
ORGANISATIONAL STRUCTURE FOR CONSTRUCTION MANAGEMENT

CLIENT

DESIGN CONTRUCTION
TEAM MANAGER

WORKS CONTRACTORS

Contractual relationship

Organisational relationship
Dr.Ananthan 2020 65
ORGANISATIONAL STRUCTURE FOR CONSTRUCTION MANAGEMENT

Dr.Ananthan 2020 66
PARTNERING IN CONSTRUCTION
• Is a concept based on co-operative efforts for mutual
benefits.

• Its use is widely in other countries and in other


economic sectors.

• The application of partnering as an approach in


construction procurement may lead to improved
performance in the construction industry.

Dr.Ananthan 2020 67
PARTNERING IN CONSTRUCTION
• In partnering, efforts are made to design for
each project a problem-finding and problem-
solving team comprising of members from
both parties and recognises and honours the
objectives of all parties, thus creating
SYNERGY for project success.

Dr.Ananthan 2020 68
PARTNERING IN CONSTRUCTION
• The BRT-Sunway Line is Malaysia’s first dedicated and
elevated electric Bus Rapid Transit (BRT) system, and is
the first public-private partnership (PPP) between
Prasarana Malaysia Berhad (Prasarana) and Sunway
Berhad.

• This public transport project, operated and managed


by Prasarana, serves to enhance the connectivity,
accessibility and mobility for the communities in
Bandar Sunway, Subang Jaya and USJ. Sunway has
contributed RM123 million to the RM634 million BRT-
Sunway Line project.

Dr.Ananthan 2020 69
Dr.Ananthan 2020 70
Dr.Ananthan 2020 71
Dr.Ananthan 2020 72

You might also like