Ref. No.

: BBC-PE-01-MFSCB/MHC/L/017

June 16, 2018

To : Mr. Rommel A. Ignacio


Owner Representative
Marius Holdings Corporation

Thru : Engr. Mabeth B. Ganigan


Project Management Leader
MHC Project Manager

Project : Proposed 5-Storey with Basement Commercial Building


140 Katipunan Avenue, St. Ignatius, Quezon City

Subject : Request for Approval of Materials for Electrical, Plumbing Sanitary


and Fire Protection System

Reference to the above stated subject, we would like to follow up our pending Material Request for
Approval for Electrical, Plumbing Sanitary and Fire Protection System. The delay of the Request for
Approval’s will seriously affect the schedule of procurement and delivery of the materials.
Furthermore, it will delay the progress of the project and timely accomplishments will not be followed
due to delayed installations which is caused by the delayed procurement and delivery of materials. On
time procurement and delivery of materials will help on ensuring the quality and early submission of
the project.

Herewith is the history and master list of the Materials Request for Approval for Electrical, Plumbing
Sanitary and Fire Protection System.

Thank you.

Prepared By:

NYLL JOSEPH S. MANABAT


MEPF QA/QC

Noted By:

RAUL A. BALINGIT
Project Manager
MEPF Head

MERJOHNE S. MEDENILLA
Project Manager
For and on Behalf of:
Building Beaver Corporation

MECHANICAL (GENERAL)
1. BBCPE-01-MHCCB-18/CS/RFA/M/001
2. BBCPE-01-MHCCB-18/CS/RFA/M/002

1835 E. Rodriguez Sr. Avenue, Cubao, Quezon City


Tel.: (02) 654-3911 or 654-4153 to 54  Fax: (02) 654-4605  Email buildingbeavercorp@gmail.com
April 12, 2018 – The following Request for Approvals were received by MHC PMT.
April 23, 2018 – The date required for MHC PMT to approve or disapprove on the
following Request for Approvals but there was no feedback.
June 13, 2018 – The following Request for Approvals are not still approved.
Note: BBC follows up the Request for Approvals every Coordination Meeting.

ELECTRICAL
1. BBCPE-01-MHCCB-18/CS/RFA/E/001
2. BBCPE-01-MHCCB-18/CS/RFA/E/002
3. BBCPE-01-MHCCB-18/CS/RFA/E/003
4. BBCPE-01-MHCCB-18/CS/RFA/E/004
5. BBCPE-01-MHCCB-18/CS/RFA/E/005
6. BBCPE-01-MHCCB-18/CS/RFA/E/006
7. BBCPE-01-MHCCB-18/CS/RFA/E/007

April 12, 2018 – The Request for Approval 001 to 007 were received by MHC PMT.
April 23, 2018 – The date required for MHC PMT to approve or disapprove the
Request for Approval 001 to 007 but there was no feedback.
June 16, 2018 – The Request for Approvals are not still approved.
Note: BBC follows up the Request for Approvals every Coordination Meeting.

PLUMBING SANITARY
1. BBCPE-01-MHCCB-18/CS/RFA/P/001
2. BBCPE-01-MHCCB-18/CS/RFA/P/002
3. BBCPE-01-MHCCB-18/CS/RFA/P/003
4. BBCPE-01-MHCCB-18/CS/RFA/P/004
5. BBCPE-01-MHCCB-18/CS/RFA/P/005
6. BBCPE-01-MHCCB-18/CS/RFA/P/006

April 11, 2018 – The Request for Approval 001 to 006 were received by MHC PMT.
April 20, 2018 – The date required for MHC PMT to approve or disapprove the
Request for Approval 001 to 006 there was no feedback.
June 16, 2018 – The Request for Approvals are not still approved.
Note: BBC follows up the Request for Approvals every Coordination Meeting.

FIRE PROTECTION
1. BBCPE-01-MHCCB-18/CS/RFA/FP/001
2. BBCPE-01-MHCCB-18/CS/RFA/FP/002
3. BBCPE-01-MHCCB-18/CS/RFA/FP/003
4. BBCPE-01-MHCCB-18/CS/RFA/FP/004
1835 E. Rodriguez Sr. Avenue, Cubao, Quezon City
Tel.: (02) 654-3911 or 654-4153 to 54  Fax: (02) 654-4605  Email buildingbeavercorp@gmail.com
5. BBCPE-01-MHCCB-18/CS/RFA/FP/008
6. BBCPE-01-MHCCB-18/CS/RFA/FP/009
7. BBCPE-01-MHCCB-18/CS/RFA/FP/010
8. BBCPE-01-MHCCB-18/CS/RFA/FP/011
9. BBCPE-01-MHCCB-18/CS/RFA/FP/012
10. BBCPE-01-MHCCB-18/CS/RFA/FP/013

April 11, 2018 – The Request for Approval 001 to 004 were received by MHC PMT.
April 20, 2018 – The date required for MHC PMT to approve or disapprove the
Request for Approval 001 to 004 there was no feedback.
April 30, 2018 – The Request for Approval 012 was received by MHC PMT.
May 09, 2018 – The Request for Approval 013 was received by MHC PMT.
May 10, 2018 – The date required for MHC PMT to approve or disapprove the
Request for Approval 012 but there was no feedback.
May 21, 2018 – The date required for MHC PMT to approve or disapprove the
Request for Approval 013 but there was no feedback.
June 02, 2018 – The front page of the Request for Approval 005 to 013 were scanned and
emailed to MHC PMT for their approval prior to their request.
June 12, 2018 – The following Request for Approvals are not still approved.
Note: BBC follows up the Request for Approvals every Coordination Meeting.

1835 E. Rodriguez Sr. Avenue, Cubao, Quezon City


Tel.: (02) 654-3911 or 654-4153 to 54  Fax: (02) 654-4605  Email buildingbeavercorp@gmail.com