You are on page 1of 753

8)

Augus
t,2019
Table of Contents

A: Cost Summary

B: Notes on Cost Estimates

C: Cost of Package 1 (Segment 1 to 5)

D: Cost of Package 2 (Segment 6)

E: Cost of Package 3 (Segment 7 to 12)

F: Cost of Package 4 (Segment 13 to 16)

G: Cost of Package 5 (Segment 17 to 19)

H: Cost of Package 6 (Trunk Pipelines)

I: Cost of Package 7 (No. 1: Natun Bazar SLS, No. 2: Banasree SLS, No. 4: Bijoy Sarani SLS)

J: Cost of Package 8 (Gulshan and Banani including Gulshan SLS & Tejgaon SLS, designed by IWM)
Employer’s Cost Estimates2

A: Cost Summary

Package Nos. Packages Identity Amount in BDT


1 Sewer Network in Segment 1 to 5
2,134,671,157
2 Sewer Network in Segment 6
3,139,987,939
3 Sewer Network in Segment 7 to 12
9,307,948,688
4 Sewer Network in Segment 13 to 16
3,320,219,301
5 Sewer Network in Segment 17 to 19
7,031,459,306
6 Trunk Pipelines
643,943,792
7 Banasree, Natun Bazar,Bijoy Sarani
1,174,901,813
SLS
Gulshan & Banani SLS (By IWM)
5,066,733,950
8
Tejgaon & Gulshan SLS
909,757,344
Total Costs in BDT
32,729,623,291
Employer’s Cost Estimates3

B: Notes on Cost Estimates


The DWASA schedule of rates 2011 has been consulted for unit prices of different items of sewer network works and
updated for price level of quarter 1 of 2019. The PWD schedule of rates 2018 which is widely used has also been
considered. Further the rates of basic items as obtained from recent DWASA contract packages have also been
consulted. The basic prices of GRP pipes have been taken from vendor’s quotations and extrapolated where necessary.
The basic considerations in the rate analyses have been followed as are usually practiced in the international competitive
bidding.

Regarding the rate analyses the following explanations are to be kept in mind in order to assess the whole process of cost
estimation;

1. As it is a preliminary design for a design-build-operation procurement package, composite items of works have
been considered for cost estimation.
2. The full requirement of a particular item of works/services considered consists of a number of basic work items and
as such the breakdown of the rate analyses in terms of materials, labour and equipment were required and worked
out.
3. The rates and prices covered the full scope of works including Contractor’s equipment, overheads, profit, road
cutting permit fees where applicable, VAT & income tax as admissible, but exclusive of Custom Duties (CD, VAT).
4. For the rates of basic work items the widely used PWD schedule of rates and updated DWASA schedule of rates
have been used extensively.
5. A clear understanding of the process would require one to get through the step by step procedures of the rate
analyses and cost calculations.
6. The soft copies of the rate analyses are provided for easy reference and checking of the basic considerations and
the calculations.
Employer’s Cost Estimates4

C: Cost of Package 1 (Segment 1 to 5)


Schedule No. 1 - Pipe and Fittings Supplied from Abroad

Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 37,776.80
1.1.2 ø250 mm m 1,493.80
1.1.3 ø300 mm m 866.30
1.1.4 ø350 mm m 380.90
1.1.5 ø400 mm m 390.50
1.1.6 ø450 mm m
1.1.7 ø500 mm m 935.20
1.1.8 ø600 mm m 587.90
1.1.9 ø700 mm m 380.30
1.1.10 ø800 mm m 257.60
1.1.11 ø900 mm m
1.1.12 ø1000 mm m
1.1.13 ø1100 mm m
1.1.14 ø1300 mm m
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 76
1.2.2 ø250 mm nos. 3
1.2.3 ø300 mm nos. 2
1.2.4 ø350 mm nos. 1
1.2.5 ø400 mm nos. 1
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 2
1.2.8 ø600 mm nos. 1
1.2.9 ø700 mm nos. 1
1.2.10 ø800 mm nos. 1

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 1 of 70
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.11 ø900 mm nos.
1.2.12 ø1000 mm nos.
1.2.13 ø1100 mm nos.
1.2.14 ø1300 mm nos.
1.3 Equal and Un Equal Tee of different sizes
1.3.1 200mm x200mm nos. 76
1.3.2 250mm x250mm nos. 3
1.3.3 300mm X 300mm nos. 2
1.3.4 350mm X 350mm nos. 1
1.3.5 400mm X 400mm nos. 1
1.3.6 450mm X 450mm nos.
1.3.7 500mm X 500mm nos. 2
1.3.8 600 mm X 600mm nos. 1
1.3.9 700mm X 700mm nos. 1
1.3.10 800mm x 800mm nos. 1
1.3.11 900mm X 900mm nos.
1.3.12 1000mm X 1000mm nos.
1.3.13 250mm X250mm X 200mm nos. 3
1.3.14 300mm X 300mm X 200mm nos. 2
1.3.15 300mm X 300mm X 250mm nos. 1
1.3.16 400mm X 400mm X 200mm nos. 1
1.3.17 400mm X 400mm X 250mm nos.
1.3.18 400mm X 400mm X 300mm nos. 2
1.3.19 500mm X 500mm X 200mm nos. 1
1.3.20 500mm X 500mm X 300mm nos. 1
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos. 152

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 2 of 70
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4.2 ø250 mm nos. 6
1.4.3 ø300 mm nos. 4
1.4.4 ø350 mm nos. 2
1.4.5 ø400 mm nos. 2
1.4.6 ø450 mm nos.
1.4.7 ø500 mm nos. 4
1.4.8 ø600 mm nos. 2
1.4.9 ø700 mm nos. 2
1.4.10 ø800 mm nos. 2
1.4.11 ø900 mm nos.
1.4.12 ø1000 mm nos.
1.4.13 ø1100 mm nos.
1.4.14 ø1300 mm nos.
1.5 Flanged Adapters
1.5.1 ø200 mm nos. 19
1.5.2 ø250 mm nos. 1
1.5.3 ø300 mm nos. 1
1.5.4 ø350 mm nos.
1.5.5 ø400 mm nos. 1
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos. 1
1.5.8 ø600 mm nos.
1.5.9 ø700 mm nos.
1.5.10 ø800 mm nos. 1
1.5.11 ø900 mm nos. 1
1.5.12 ø1000 mm nos. 1
1.5.13 ø1100 mm nos.
1.5.14 ø1300 mm nos. 1

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 3 of 70
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 4 of 70
Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country

Unit Price (BDT)


Sales and other
Item Description Unit Qty. Total Unit Total Price (BDT)
Material Labour Equipment taxes (BDT)
Price (EXW)
a b c d e f g h=e+f+g i=dxh j

Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 5 of 70
Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

3.1 Design / Survey Provisions and Preliminaries


3.1.1 Insurances
3.1.1.1 For design (professional indemnity insurance) LS 1 8,385,867.11 8,385,867.11
3.1.1.2 Other Insurances (to be specified by the Tenderer) LS 1 4,192,934 4,192,933.55
Sub-total A: 12,578,800.66
3.2 Design Services (including design office and establishment)

3.2.1 Loop 501


3.2.1.1 Survey and documentation, including Survey Report LS 1 5,398,646 5,398,645.94
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.1.2 LS 1 3,299,173 3,299,172.52
Report
3.2.1.3 Design Control Services including documentation LS 1 899,774 899,774.32

3.2.2 Loop 502


3.2.2.1 Survey and documentation, including Survey Report LS 1 7,213,565 7,213,564.69
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.2.2 LS 1 4,408,290 4,408,289.53
Report
3.2.2.3 Design Control Services including documentation LS 1 1,202,261 1,202,260.78

3.2.3 Loop 503


3.2.3.1 Survey and documentation, including Survey Report LS 1 4,106,712 4,106,712.28
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.3.2 LS 1 2,509,658 2,509,657.51
Report
3.2.3.3 Design Control Services including documentation LS 1 684,452 684,452.05

3.2.4 Loop 504


3.2.4.1 Survey and documentation, including Survey Report LS 1 28,499,011 28,499,010.68
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.4.2 LS 1 17,416,062 17,416,062.08
Report
3.2.4.3 Design Control Services including documentation LS 1 4,749,835 4,749,835.11

3.2.5 Loop 505


3.2.5.1 Survey and documentation, including Survey Report LS 1 30,254,870 30,254,870.37

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 6 of 70
Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.5.2 LS 1 18,489,087 18,489,087.45
Report
3.2.5.3 Design Control Services including documentation LS 1 5,042,478 5,042,478.40

Sub-total B: 134,173,873.70
Total A+B: Sub-total 3:
146,752,674.36
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary

Name of Bidder:

Signature of Bidder:

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 7 of 70
Schedule No. 4 - Installation / Construction and Other works

Unit Price (BDT)


Item Description Unit Qty. Total Unit Total Price (BDT)
Material Labour Equipment
Price

a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 4,192,933.55 4,192,933.55
4.1.1.2 Advance Payment Guarantee LS 1 4,192,933.55 4,192,933.55
Subtotal 4.1.1 8,385,867.11
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.2 Installation All Risks Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.3 Third Party Liability Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.4 Automobile Liability Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.5 Workers' Compensation LS 1 6,289,400.33 6,289,400.33
4.1.2.6 Employer's Liability LS 1 6,289,400.33 6,289,400.33
4.1.2.7 Contractor's Equipment Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 6,289,400.33 6,289,400.33
Subtotal 4.1.2 50,315,202.64
4.1.3 Site establishment, operation and removal

Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 4,791,924.06 4,791,924.06
workshops, site access and miscellaneous services etc.

Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 4,791,924.06 4,791,924.06
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 4,791,924.06 4,791,924.06
4.1.3.4 Survey instruments LS 1 4,791,924.06 4,791,924.06
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 4,791,924.06 4,791,924.06
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 4,791,924.06 4,791,924.06
Subtotal 4.1.3 28,751,544.36
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 87,452,614.11

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 8 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.2 INSTALLATION of LOOP 101
4.2.1 Miscellaneous works during implementation
4.2.1.1 Setting-out LS 1.00 66,340.00 66,340.00
4.2.1.2 General works and site tests LS 1.00 132,680.00 132,680.00
4.2.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.2.2.1 LS 1.00 132,680.00 132,680.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction completed
4.2.2.2 LS 1.00 49,755.00 49,755.00
& acceptance certificate
4.2.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.2.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.2.2.5 Development and submission of GIS based As-built drawings LS 1.00 82,925.00 82,925.00
4.2.2.6 Post Construction modelling LS 1.00 9,951.00 9,951.00

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified below,
including fitting, fixing of all items, road cutting permission fee, temporary road
4.2.3 -
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.2.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.2.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.3.A.1.1 ø200 mm m 2,926.20 3,596.40 1,581.32 878.18 5,811.99 11,867.89 34,727,816.62


4.2.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.2.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.2.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.2.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.2.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.2.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.2.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.2.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.2.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.2.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 9 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -


4.2.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.2.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.2.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.A.2.1 ø200 mm m 390.80 3,890.84 1,719.29 901.27 5,811.99 12,323.40 4,815,983.00


4.2.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.2.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.2.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.2.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.2.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.2.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.2.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.2.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.2.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.2.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.2.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.2.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.2.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.2.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.2.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.2.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.2.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.2.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.2.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.2.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.2.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.2.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 10 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.2.3.A.2.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.2.3.A.2.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.2.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.2.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.2.3.B.1.1 ø200 mm m -
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -

4.2.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 11 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.2.11 ø900 mm m -

4.2.3.B.2.12 ø1000 mm m -

4.2.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -

4.2.3.B.3.11 ø900 mm m -

4.2.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.2.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved drawing and
specification.

4.2.4.A Normal Manhole Rectangular or circular

4.2.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.2.4.A.1.1 ø200 mm nos. 60.00 108,465.00 17,845.00 10,137.00 136,447.00 8,186,820.00


4.2.4.A.1.2 ø250 mm nos. 2.00 109,101.00 17,858.00 10,150.00 137,109.00 274,218.00
4.2.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.2.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 12 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -


4.2.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.2.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.2.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.2.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.A.2.1 ø200 mm nos. 2 133,076.00 22,507.00 12,324.00 167,907.00 335,814.00


4.2.4.A.2.2 ø250 mm nos. 2 133,713.00 22,520.00 12,338.00 168,571.00 337,142.00
4.2.4.A.2.3 ø300 mm nos. 5 134,286.00 22,521.00 12,350.00 169,157.00 845,785.00
4.2.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.2.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.2.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.2.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.2.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.2.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.2.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.2.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.2.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.2.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.2.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.2.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.2.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 13 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -


4.2.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.2.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.2.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.2.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.2.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.2.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.2.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.2.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.2.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.2.4.B Drop Manhole Rectangular or circular

4.2.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.2.4.B.1.1 ø200 mm nos. 17.00 177,870.00 34,380.00 19,812.00 232,062.00 3,945,054.00


4.2.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.2.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.2.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.2.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.2.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.2.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.2.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.2.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.2.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.2.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.2.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.2.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.2.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.2.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.2.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.2.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 14 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -


4.2.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.2.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.2.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.2.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.2.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.2.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.2.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.2.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.2.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.2.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.2.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.2.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.2.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.2.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.2.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.2.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.2.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.2.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.2.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.2.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.2.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.2.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.2.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.2.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.2.4.C Service connections Manhole Rectangular or circular -

4.2.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.2.4.C.1.1 ø200 mm nos. 163.00 108,465.00 17,845.00 10,137.00 136,447.00 22,240,861.00


4.2.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 15 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -


4.2.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.B.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.2.4.B.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.2.4.B.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.2.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.C.2.1 ø200 mm nos. 22 133,076.00 22,507.00 12,324.00 167,907.00 3,693,954.00


4.2.4.C.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.2.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.2.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.2.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.2.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.2.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.2.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.2.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.2.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.2.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.2.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.2.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.2.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.2.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 16 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -


4.2.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.2.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.2.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.2.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.2.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.2.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.2.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.2.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.2.4.B.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.2.4.B.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.2.4.B.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting, fixing
of all items, road cutting permission fee, temporary road reinstatement, dismantling
4.2.5 of existing structures, site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 277.00 40,766.88 13,972.83 8,265.14 63,004.85 17,452,343.45

4.2.5.2 ø200 mm nos. 111.00 44,627.58 15,581.46 9,230.31 69,439.35 7,707,767.85


4.2.5.3 ø250 mm nos. 111.00 51,128.58 18,290.21 10,855.56 80,274.35 8,910,452.85
4.2.5.4 ø300 mm nos. 55.00 55,471.38 20,099.71 11,941.26 87,512.35 4,813,179.25

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning, earth
4.2.6 -
cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per approved
drawing and specification.

4.2.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.6.A.1.1 ø200 mm nos. 54.00 11,079.12 3,235.25 433.10 14,747.46 796,362.84


4.2.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.2.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.2.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.2.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 17 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -


4.2.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.2.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.2.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.2.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.2.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.2.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -
4.2.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -
4.2.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.2.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.6.A.2.1 ø200 mm nos. 7.00 11,079.12 3,614.08 439.51 15,132.71 105,928.97


4.2.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.2.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.2.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.2.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.2.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.2.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.2.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.2.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.2.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.2.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.2.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.2.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.2.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.2.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.2.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.2.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.2.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.2.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 18 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -


4.2.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.2.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.2.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.2.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.2.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.2.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.2.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.2.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.2: Column 'j' to be carried forward to Schedule No. 5


. 119,969,909.84
Grand Summary

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 19 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.3 INSTALLATION of LOOP 102
4.3.1 Miscellaneous works during implementation
4.3.1.1 Setting-out LS 1.00 82,106.00 82,106.00
4.3.1.2 General works and site tests LS 1.00 164,212.00 164,212.00
4.3.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.3.2.1 LS 1.00 164,212.00 164,212.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.3.2.2 LS 1.00 61,579.50 61,579.50
completed & acceptance certificate
4.3.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.3.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.3.2.5 Development and submission of GIS based As-built drawings LS 1.00 102,632.50 102,632.50
4.3.2.6 Post Construction modelling LS 1.00 12,315.90 12,315.90

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.3.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.3.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.3.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.3.A.1.1 ø200 mm m 3,184.70 3,596.40 1,581.32 878.18 5,811.99 11,867.89 37,795,665.91


4.3.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.3.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.3.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.3.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.3.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.3.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.3.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.3.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.3.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 20 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -


4.3.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.3.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.3.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.3.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.A.2.1 ø200 mm m 673.80 3,890.84 1,719.29 901.27 5,811.99 12,323.40 8,303,503.96


4.3.3.A.2.2 ø250 mm m 219.60 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 3,007,633.47
4.3.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.2.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.3.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.3.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.3.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.3.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.3.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.3.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.2.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.2.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.3.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.3.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.3.3.A.3.3 ø300 mm m 27.20 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 786,869.23
4.3.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.3.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.3.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.3.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.3.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.3.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.3.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 21 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.3.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.3.3.A.2.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.3.3.A.2.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.3.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.3.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -

4.3.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 22 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -

4.3.3.B.2.11 ø900 mm m -

4.3.3.B.2.12 ø1000 mm m -

4.3.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -

4.3.3.B.3.11 ø900 mm m -

4.3.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.3.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.3.4.A Normal Manhole Rectangular or circular

4.3.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.A.1.1 ø200 mm nos. 134.00 108,465.00 17,845.00 10,137.00 136,447.00 18,283,898.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 23 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -


4.3.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.3.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.3.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.3.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.3.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.3.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.A.2.1 ø200 mm nos. 10 133,076.00 22,507.00 12,324.00 167,907.00 1,679,070.00


4.3.4.A.2.2 ø250 mm nos. 9 133,713.00 22,520.00 12,338.00 168,571.00 1,517,139.00
4.3.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.3.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.3.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.3.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.3.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.3.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.3.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.3.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 24 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -


4.3.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.3.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.3.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.3.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.3.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.3.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.3.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.3.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.3.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.3.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.3.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.3.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.3.4.B Drop Manhole Rectangular or circular

4.3.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.B.1.1 ø200 mm nos. 21.00 177,870.00 34,380.00 19,812.00 232,062.00 4,873,302.00


4.3.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.3.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.3.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.3.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.3.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.3.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.3.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.3.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.3.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.3.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.3.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.3.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.3.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 25 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.B.2.1 ø200 mm nos. 2 216,110.00 42,604.00 23,944.00 282,658.00 565,316.00


4.3.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.3.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.3.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.3.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.3.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.3.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.3.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.3.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.3.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.3.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.3.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.3.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.3.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.3.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.3.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.3.4.B.3.3 ø300 mm nos. 1 293,442.00 59,074.00 32,256.00 384,772.00 384,772.00
4.3.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.3.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.3.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.3.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.3.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.3.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.3.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.3.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.3.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.3.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 26 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.3.4.C Service connections Manhole Rectangular or circular -

4.3.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.3.4.C.1.1 ø200 mm nos. 177.00 108,465.00 17,845.00 10,137.00 136,447.00 24,151,119.00


4.3.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.3.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.3.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.3.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.3.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.3.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.C.2.1 ø200 mm nos. 38 133,076.00 22,507.00 12,324.00 167,907.00 6,380,466.00


4.3.4.C.2.2 ø250 mm nos. 13 133,713.00 22,520.00 12,338.00 168,571.00 2,191,423.00
4.3.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.3.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.3.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.3.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.3.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 27 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.3.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.3.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.3.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.3.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.3.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.3.4.C.3.3 ø300 mm nos. 2 183,505.00 31,840.00 16,725.00 232,070.00 464,140.00
4.3.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.3.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.3.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.3.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.3.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.3.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.3.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.3.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.3.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.3.4.C.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.3.4.C.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.3.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.3.5.1 ø150 mm nos. 343.00 40,766.88 13,972.83 8,265.14 63,004.85 21,610,663.55

4.3.5.2 ø200 mm nos. 137.00 44,627.58 15,581.46 9,230.31 69,439.35 9,513,190.95


4.3.5.3 ø250 mm nos. 137.00 51,128.58 18,290.21 10,855.56 80,274.35 10,997,585.95
4.3.5.4 ø300 mm nos. 69.00 55,471.38 20,099.71 11,941.26 87,512.35 6,038,352.15

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 28 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.3.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.3.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.6.A.1.1 ø200 mm nos. 59.00 11,079.12 3,235.25 433.10 14,747.46 870,100.14


4.3.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.3.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.3.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.3.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.3.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.3.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.3.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.3.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.3.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.3.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.3.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -
4.3.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -
4.3.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.3.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.6.A.2.1 ø200 mm nos. 13.00 11,079.12 3,614.08 439.51 15,132.71 196,725.23


4.3.6.A.2.2 ø250 mm nos. 4.00 11,597.22 3,810.28 460.57 15,868.07 63,472.28
4.3.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.3.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.3.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.3.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.3.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.3.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.3.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.3.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 29 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.3.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.3.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.3.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.3.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.3.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.3.6.A.3.3 ø300 mm nos. 1.00 12,111.88 4,863.80 496.05 17,471.72 17,471.72
4.3.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.3.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.3.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.3.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.3.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.3.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.3.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.3.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.3.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.3.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.3.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.3: Column 'j' to be carried forward to Schedule No. 5


. 160,301,437.45
Grand Summary

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 30 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 103
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 46,026.00 46,026.00
4.4.1.2 General works and site tests LS 1.00 92,052.00 92,052.00
4.4.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.4.2.1 LS 1.00 92,052.00 92,052.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.4.2.2 LS 1.00 34,519.50 34,519.50
completed & acceptance certificate
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.4.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 57,532.50 57,532.50
4.4.2.6 Post Construction modelling LS 1.00 6,903.90 6,903.90

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.3.A.1.1 ø200 mm m 1,425.30 3,596.40 1,581.32 878.18 5,811.99 11,867.89 16,915,302.11


4.4.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.4.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 31 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -


4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.4.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.4.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 682.30 3,890.84 1,719.29 901.27 5,811.99 12,323.40 8,408,252.82


4.4.3.A.2.2 ø250 mm m 86.20 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 1,180,592.01
4.4.3.A.2.3 ø300 mm m 90.30 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 1,327,171.22
4.4.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.4.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.4.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.4.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.4.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.4.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.4.3.A.3.3 ø300 mm m 17.20 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 497,579.07
4.4.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.4.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.4.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.4.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 32 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.4.3.A.3.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.4.3.A.3.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 33 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.4.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 61.00 108,465.00 17,845.00 10,137.00 136,447.00 8,323,267.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 34 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -


4.4.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.4.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.4.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 11 133,076.00 22,507.00 12,324.00 167,907.00 1,846,977.00


4.4.4.A.2.2 ø250 mm nos. 3 133,713.00 22,520.00 12,338.00 168,571.00 505,713.00
4.4.4.A.2.3 ø300 mm nos. 3 134,286.00 22,521.00 12,350.00 169,157.00 507,471.00
4.4.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.4.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.4.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.4.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 35 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -


4.4.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.4.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.4.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.4.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.4.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.4.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.4.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.4.4.B Drop Manhole Rectangular or circular

4.4.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. 13.00 177,870.00 34,380.00 19,812.00 232,062.00 3,016,806.00


4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.4.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.4.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 36 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.B.2.1 ø200 mm nos. 3 216,110.00 42,604.00 23,944.00 282,658.00 847,974.00


4.4.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.4.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.4.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.4.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.4.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.4.4.B.3.3 ø300 mm nos. 1 293,442.00 59,074.00 32,256.00 384,772.00 384,772.00
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.4.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 37 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

4.4.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.4.C.1.1 ø200 mm nos. 80.00 108,465.00 17,845.00 10,137.00 136,447.00 10,915,760.00


4.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 38 133,076.00 22,507.00 12,324.00 167,907.00 6,380,466.00


4.4.4.C.2.2 ø250 mm nos. 5 133,713.00 22,520.00 12,338.00 168,571.00 842,855.00
4.4.4.C.2.3 ø300 mm nos. 6 134,286.00 22,521.00 12,350.00 169,157.00 1,014,942.00
4.4.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.4.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 38 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.4.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.4.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.4.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.4.4.C.3.3 ø300 mm nos. 1 183,505.00 31,840.00 16,725.00 232,070.00 232,070.00
4.4.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.4.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.4.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.4.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.4.4.C.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.4.4.C.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 193.00 40,766.88 13,972.83 8,265.14 63,004.85 12,159,936.05

4.2.5.2 ø200 mm nos. 77.00 44,627.58 15,581.46 9,230.31 69,439.35 5,346,829.95


4.2.5.3 ø250 mm nos. 77.00 51,128.58 18,290.21 10,855.56 80,274.35 6,181,124.95
4.2.5.4 ø300 mm nos. 39.00 55,471.38 20,099.71 11,941.26 87,512.35 3,412,981.65

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 39 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.4.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 27.00 11,079.12 3,235.25 433.10 14,747.46 398,181.42


4.4.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.4.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -
4.4.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -
4.4.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 13.00 11,079.12 3,614.08 439.51 15,132.71 196,725.23


4.4.6.A.2.2 ø250 mm nos. 2.00 11,597.22 3,810.28 460.57 15,868.07 31,736.14
4.4.6.A.2.3 ø300 mm nos. 2.00 12,111.88 4,007.30 481.54 16,600.72 33,201.44
4.4.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.4.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.4.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 40 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.4.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.4.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.4.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.4.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.4.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.4.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.4.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.4.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.4.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.4.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.4.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.4: Column 'j' to be carried forward to Schedule No. 5


. 91,260,272.97
Grand Summary

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 41 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 104
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 314,710.00 314,710.00
4.4.1.2 General works and site tests LS 1.00 629,420.00 629,420.00
4.4.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.4.2.1 LS 1.00 629,420.00 629,420.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.4.2.2 LS 1.00 236,032.50 236,032.50
completed & acceptance certificate
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.4.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 393,387.50 393,387.50
4.4.2.6 Post Construction modelling LS 1.00 47,206.50 47,206.50

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.3.A.1.1 ø200 mm m 7,499.20 3,596.40 1,581.32 878.18 5,811.99 11,867.89 88,999,672.76


4.4.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.4.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 42 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -


4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.4.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.4.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 5,769.00 3,890.84 1,719.29 901.27 5,811.99 12,323.40 71,093,669.27


4.4.3.A.2.2 ø250 mm m 736.30 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 10,084,337.54
4.4.3.A.2.3 ø300 mm m 206.10 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 3,029,125.01
4.4.3.A.2.4 ø350 mm m 242.00 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 3,660,714.38
4.4.3.A.2.5 ø400 mm m 151.40 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 2,707,678.18
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 113.30 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 2,540,424.00
4.4.3.A.2.8 ø600 mm m 98.60 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 2,598,247.46
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.4.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.4.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.4.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.4.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.4.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.4.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 50.00 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 1,835,807.74
4.4.3.A.3.8 ø600 mm m 489.30 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 19,903,024.68
4.4.3.A.3.9 ø700 mm m 380.30 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 18,438,550.69
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 43 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.4.3.A.3.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.4.3.A.3.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 44 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.4.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 263.00 108,465.00 17,845.00 10,137.00 136,447.00 35,885,561.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 45 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -


4.4.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.4.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.4.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 128 133,076.00 22,507.00 12,324.00 167,907.00 21,492,096.00


4.4.4.A.2.2 ø250 mm nos. 16 133,713.00 22,520.00 12,338.00 168,571.00 2,697,136.00
4.4.4.A.2.3 ø300 mm nos. 5 134,286.00 22,521.00 12,350.00 169,157.00 845,785.00
4.4.4.A.2.4 ø350 mm nos. 6 134,923.00 22,534.00 12,363.00 169,820.00 1,018,920.00
4.4.4.A.2.5 ø400 mm nos. 3 135,559.00 22,547.00 12,377.00 170,483.00 511,449.00
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.A.2.7 ø500 mm nos. 4 136,776.00 22,565.00 12,402.00 171,743.00 686,972.00
4.4.4.A.2.8 ø600 mm nos. 4 138,048.00 22,591.00 12,430.00 173,069.00 692,276.00
4.4.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.4.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.4.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 46 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -


4.4.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.4.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.4.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 1 185,988 31,881 16,777 234,646.00 234,646.00
4.4.4.A.3.8 ø600 mm nos. 11 187,267 31,910 16,805 235,982.00 2,595,802.00
4.4.4.A.3.9 ø700 mm nos. 8 188,477 31,924 16,830 237,231.00 1,897,848.00
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.4.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.4.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.4.4.B Drop Manhole Rectangular or circular

4.4.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. 29.00 177,870.00 34,380.00 19,812.00 232,062.00 6,729,798.00


4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.4.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.4.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 47 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.B.2.1 ø200 mm nos. 9 216,110.00 42,604.00 23,944.00 282,658.00 2,543,922.00


4.4.4.B.2.2 ø250 mm nos. 2 216,602.00 42,630.00 23,972.00 283,204.00 566,408.00
4.4.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.4.4.B.2.5 ø400 mm nos. 2 217,952.00 42,686.00 24,050.00 284,688.00 569,376.00
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.4.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.4.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.4.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.4.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 48 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

4.4.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.4.C.1.1 ø200 mm nos. 417.00 108,465.00 17,845.00 10,137.00 136,447.00 56,898,399.00


4.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 321 133,076.00 22,507.00 12,324.00 167,907.00 53,898,147.00


4.4.4.C.2.2 ø250 mm nos. 41 133,713.00 22,520.00 12,338.00 168,571.00 6,911,411.00
4.4.4.C.2.3 ø300 mm nos. 12 134,286.00 22,521.00 12,350.00 169,157.00 2,029,884.00
4.4.4.C.2.4 ø350 mm nos. 14 134,923.00 22,534.00 12,363.00 169,820.00 2,377,480.00
4.4.4.C.2.5 ø400 mm nos. 9 135,559.00 22,547.00 12,377.00 170,483.00 1,534,347.00
4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.C.2.7 ø500 mm nos. 7 136,776.00 22,565.00 12,402.00 171,743.00 1,202,201.00
4.4.4.C.2.8 ø600 mm nos. 6 138,048.00 22,591.00 12,430.00 173,069.00 1,038,414.00
4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 49 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.4.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.4.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.4.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.4.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.4.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.4.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 3 185,988.00 31,881.00 16,777.00 234,646.00 703,938.00
4.4.4.C.3.8 ø600 mm nos. 28 187,267.00 31,910.00 16,805.00 235,982.00 6,607,496.00
4.4.4.C.3.9 ø700 mm nos. 22 188,477.00 31,924.00 16,830.00 237,231.00 5,219,082.00
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.4.4.C.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.4.4.C.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 1,312.00 40,766.88 13,972.83 8,265.14 63,004.85 82,662,363.20

4.2.5.2 ø200 mm nos. 525.00 44,627.58 15,581.46 9,230.31 69,439.35 36,455,658.75


4.2.5.3 ø250 mm nos. 525.00 51,128.58 18,290.21 10,855.56 80,274.35 42,144,033.75
4.2.5.4 ø300 mm nos. 262.00 55,471.38 20,099.71 11,941.26 87,512.35 22,928,235.70

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 50 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.4.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 139.00 11,079.12 3,235.25 433.10 14,747.46 2,049,896.94


4.4.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.4.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -
4.4.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -
4.4.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 107.00 11,079.12 3,614.08 439.51 15,132.71 1,619,199.97


4.4.6.A.2.2 ø250 mm nos. 14.00 11,597.22 3,810.28 460.57 15,868.07 222,152.98
4.4.6.A.2.3 ø300 mm nos. 4.00 12,111.88 4,007.30 481.54 16,600.72 66,402.88
4.4.6.A.2.4 ø350 mm nos. 5.00 12,575.47 4,195.03 500.60 17,271.10 86,355.50
4.4.6.A.2.5 ø400 mm nos. 3.00 13,090.13 4,395.42 521.95 18,007.50 54,022.50
4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. 2.00 14,177.39 4,798.62 565.97 19,541.98 39,083.96
4.4.6.A.2.8 ø600 mm nos. 2.00 15,264.65 5,206.67 610.38 21,081.70 42,163.40
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 51 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.4.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.4.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.4.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.4.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.4.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.4.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.4.6.A.3.7 ø500 mm nos. 1.00 14,177.39 5,852.76 583.83 20,613.98 20,613.98
4.4.6.A.3.8 ø600 mm nos. 9.00 15,264.65 6,359.64 629.91 22,254.20 200,287.80
4.4.6.A.3.9 ø700 mm nos. 7.00 16,460.93 6,881.60 679.59 24,022.12 168,154.84
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.4.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.4.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.4: Column 'j' to be carried forward to Schedule No. 5


. 633,311,348.36
Grand Summary

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 52 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.5 INSTALLATION of LOOP 105
4.5.1 Miscellaneous works during implementation
4.5.1.1 Setting-out LS 1.00 352,204.00 352,204.00
4.5.1.2 General works and site tests LS 1.00 704,408.00 704,408.00
4.5.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.5.2.1 LS 1.00 704,408.00 704,408.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.5.2.2 LS 1.00 264,153.00 264,153.00
completed & acceptance certificate
4.5.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.5.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.5.2.5 Development and submission of GIS based As-built drawings LS 1.00 440,255.00 440,255.00
4.5.2.6 Post Construction modelling LS 1.00 52,830.60 52,830.60

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.5.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.5.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.3.A.1.1 ø200 mm m 12,668.00 3,596.40 1,581.32 878.18 5,811.99 11,867.89 150,342,417.12


4.5.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.5.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.5.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.5.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.5.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.5.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.5.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.5.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.5.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 53 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -


4.5.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.5.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.5.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.5.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.A.2.1 ø200 mm m 2,557.50 3,890.84 1,719.29 901.27 5,811.99 12,323.40 31,517,084.27


4.5.3.A.2.2 ø250 mm m 451.70 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 6,186,466.48
4.5.3.A.2.3 ø300 mm m 426.20 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 6,264,013.01
4.5.3.A.2.4 ø350 mm m 138.90 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 2,101,129.04
4.5.3.A.2.5 ø400 mm m 239.10 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 4,276,128.49
4.5.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.5.3.A.2.7 ø500 mm m 373.60 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 8,376,896.79
4.5.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.5.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.5.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.5.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.5.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.5.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.5.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.5.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.5.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.5.3.A.3.3 ø300 mm m 99.30 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 2,872,651.28
4.5.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.5.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.5.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.5.3.A.3.7 ø500 mm m 398.30 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 14,624,044.44
4.5.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.5.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.5.3.A.3.10 ø800 mm m 257.60 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 14,006,879.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 54 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.5.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.5.3.A.3.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.5.3.A.3.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.5.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.5.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -

4.5.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 55 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -

4.5.3.B.2.11 ø900 mm m -

4.5.3.B.2.12 ø1000 mm m -

4.5.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -

4.5.3.B.3.11 ø900 mm m -

4.5.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.5.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.5.4.A Normal Manhole Rectangular or circular

4.5.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.A.1.1 ø200 mm nos. 305.00 108,465.00 17,845.00 10,137.00 136,447.00 41,616,335.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 56 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.1.2 ø250 mm nos. 2.00 109,101.00 17,858.00 10,150.00 137,109.00 274,218.00


4.5.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.A.1.5 ø400 mm nos. 1.00 110,948.00 17,886.00 10,189.00 139,023.00 139,023.00
4.5.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.5.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.5.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.5.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.A.2.1 ø200 mm nos. 30 133,076.00 22,507.00 12,324.00 167,907.00 5,037,210.00


4.5.4.A.2.2 ø250 mm nos. 9 133,713.00 22,520.00 12,338.00 168,571.00 1,517,139.00
4.5.4.A.2.3 ø300 mm nos. 12 134,286.00 22,521.00 12,350.00 169,157.00 2,029,884.00
4.5.4.A.2.4 ø350 mm nos. 3 134,923.00 22,534.00 12,363.00 169,820.00 509,460.00
4.5.4.A.2.5 ø400 mm nos. 8 135,559.00 22,547.00 12,377.00 170,483.00 1,363,864.00
4.5.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.5.4.A.2.7 ø500 mm nos. 13 136,776.00 22,565.00 12,402.00 171,743.00 2,232,659.00
4.5.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.5.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.5.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.5.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.A.3.1 ø200 mm nos. 1 182,295 31,825 16,700 230,820.00 230,820.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 57 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -


4.5.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.5.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.5.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.5.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.5.4.A.3.7 ø500 mm nos. 7 185,988 31,881 16,777 234,646.00 1,642,522.00
4.5.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.5.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.5.4.A.3.10 ø800 mm nos. 6 189,750 31,950 16,858 238,558.00 1,431,348.00

4.5.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.5.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.5.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.5.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.5.4.B Drop Manhole Rectangular or circular

4.5.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.B.1.1 ø200 mm nos. 50.00 177,870.00 34,380.00 19,812.00 232,062.00 11,603,100.00


4.5.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.5.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.5.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.5.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.5.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.5.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.5.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.5.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.5.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.5.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.5.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.5.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.5.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 58 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.B.2.1 ø200 mm nos. 3 216,110.00 42,604.00 23,944.00 282,658.00 847,974.00


4.5.4.B.2.2 ø250 mm nos. 1 216,602.00 42,630.00 23,972.00 283,204.00 283,204.00
4.5.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00
4.5.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.5.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.5.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.5.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.5.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.5.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.5.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.5.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.5.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.5.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.5.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.5.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.5.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.5.4.B.3.3 ø300 mm nos. 1 293,442.00 59,074.00 32,256.00 384,772.00 384,772.00
4.5.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.5.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.5.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.5.4.B.3.7 ø500 mm nos. 1 295,284.00 59,156.00 32,362.00 386,802.00 386,802.00
4.5.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.5.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.5.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.5.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.5.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.5.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 59 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.5.4.C Service connections Manhole Rectangular or circular -

4.5.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.5.4.C.1.1 ø200 mm nos. 704.00 108,465.00 17,845.00 10,137.00 136,447.00 96,058,688.00


4.5.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.5.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.5.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.5.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.5.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.C.2.1 ø200 mm nos. 143 133,076.00 22,507.00 12,324.00 167,907.00 24,010,701.00


4.5.4.C.2.2 ø250 mm nos. 26 133,713.00 22,520.00 12,338.00 168,571.00 4,382,846.00
4.5.4.C.2.3 ø300 mm nos. 24 134,286.00 22,521.00 12,350.00 169,157.00 4,059,768.00
4.5.4.C.2.4 ø350 mm nos. 8 134,923.00 22,534.00 12,363.00 169,820.00 1,358,560.00
4.5.4.C.2.5 ø400 mm nos. 14 135,559.00 22,547.00 12,377.00 170,483.00 2,386,762.00
4.5.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.5.4.C.2.7 ø500 mm nos. 21 136,776.00 22,565.00 12,402.00 171,743.00 3,606,603.00
4.5.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 60 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.5.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.5.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.5.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.5.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.5.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.5.4.C.3.3 ø300 mm nos. 6 183,505.00 31,840.00 16,725.00 232,070.00 1,392,420.00
4.5.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.5.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.5.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.5.4.C.3.7 ø500 mm nos. 23 185,988.00 31,881.00 16,777.00 234,646.00 5,396,858.00
4.5.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.5.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.5.4.C.3.10 ø800 mm nos. 15 189,750.00 31,950.00 16,858.00 238,558.00 3,578,370.00

4.5.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.5.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.5.4.C.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.5.4.C.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.5.5.1 ø150 mm nos. 1,468.00 40,766.88 13,972.83 8,265.14 63,004.85 92,491,119.80

4.5.5.2 ø200 mm nos. 587.00 44,627.58 15,581.46 9,230.31 69,439.35 40,760,898.45


4.5.5.3 ø250 mm nos. 587.00 51,128.58 18,290.21 10,855.56 80,274.35 47,121,043.45
4.5.5.4 ø300 mm nos. 294.00 55,471.38 20,099.71 11,941.26 87,512.35 25,728,630.90

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 61 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.5.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.5.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.6.A.1.1 ø200 mm nos. 235.00 11,079.12 3,235.25 433.10 14,747.46 3,465,653.10


4.5.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.5.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.5.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.5.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.5.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.5.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.5.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.5.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.5.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.5.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.5.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -
4.5.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -
4.5.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.5.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.6.A.2.1 ø200 mm nos. 48.00 11,079.12 3,614.08 439.51 15,132.71 726,370.08


4.5.6.A.2.2 ø250 mm nos. 9.00 11,597.22 3,810.28 460.57 15,868.07 142,812.63
4.5.6.A.2.3 ø300 mm nos. 8.00 12,111.88 4,007.30 481.54 16,600.72 132,805.76
4.5.6.A.2.4 ø350 mm nos. 3.00 12,575.47 4,195.03 500.60 17,271.10 51,813.30
4.5.6.A.2.5 ø400 mm nos. 5.00 13,090.13 4,395.42 521.95 18,007.50 90,037.50
4.5.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.5.6.A.2.7 ø500 mm nos. 7.00 14,177.39 4,798.62 565.97 19,541.98 136,793.86
4.5.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.5.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.5.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 62 of 70
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.5.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.5.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.5.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.5.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.5.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.5.6.A.3.3 ø300 mm nos. 2.00 12,111.88 4,863.80 496.05 17,471.72 34,943.44
4.5.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.5.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.5.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.5.6.A.3.7 ø500 mm nos. 8.00 14,177.39 5,852.76 583.83 20,613.98 164,911.84
4.5.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.5.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.5.6.A.3.10 ø800 mm nos. 5.00 17,602.69 7,398.46 727.66 25,728.81 128,644.05

4.5.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.5.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.5.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.5.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.5: Column 'j' to be carried forward to Schedule No. 5


. 672,330,452.67
Grand Summary

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 63 of 70
Schedule No. 5 - Grand Summary

Schedule No. Title


Total Price (BDT)

1 Schedule No. 1 - Pipe and Fittings Supplied from Abroad


2 Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
3 Schedule No. 3 - Design Services 146752674
4 Schedule No. 4 - Installation / Construction and Other works
4.1 Implementation Provisions and Preliminaries for all Loops 87452614
4.2 Installation/ Construction of all Loops (Schedule 4)
4.2.1 INSTALLATION of LOOP 101 119969910
4.2.2 INSTALLATION of LOOP 102 160301437
4.2.3 INSTALLATION of LOOP 103 91260273
4.2.4 INSTALLATION of LOOP 104 633311348
4.2.5 INSTALLATION of LOOP 105 672330453
Sub total 4.2: Installation/ Construction of all Loops (Schedule 4) 1677173421
5 Provisional Sum
5.1 Provisional sum for Physical Contingencies 83858671
5.2 Provisional Sum for Price Contingencies 80050168
5.3 Provisional Sum for alleviations program, refer to SCC, Sub-Clause xxxxxx 4791924
Sub-Total 5: Provisional Sum 168700764
6 Recommended spare parts 10874513
7 Day work 3466235
8 O&M - 40250936
. Grand Total (1+3+4.1+4.2+5+6+7+8) to be carried forward to Letter of Bid 2134671157

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 64 of 70
Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh

Recommended Spare Parts


6.1 GRP Sewer Pipe (Dia in mm)
6.1.1 160 meter 50.00 1,770.40 1,770.40 88,520.00
6.1.2 200 meter 50.00 2,213.00 2,213.00 110,650.00
6.1.3 250 meter 50.00 2,923.00 2,923.00 146,150.00
6.1.4 300 meter 50.00 3,315.00 3,315.00 165,750.00
6.1.5 350 meter 70.00 4,292.00 4,292.00 300,440.00
6.1.6 400 meter 70.00 5,043.00 5,043.00 353,010.00
6.1.7 500 meter 70.00 7,807.00 7,807.00 546,490.00
6.1.8 600 meter 50.00 10,104.00 10,104.00 505,200.00
6.1.9 700 meter 50.00 15,281.00 15,281.00 764,050.00
6.1.10 800 meter 50.00 18,120.00 18,120.00 906,000.00
6.1.11 900 meter 50.00 16,711.99 16,711.99 835,599.33
6.1.12 1000 meter 50.00 18,462.01 18,462.01 923,100.67
6.2 Coupler/Coller
6.2.1 160 Pcs. 10.00 2,655.60 2,655.60 26,556.00
6.2.2 200 Pcs. 10.00 3,319.50 3,319.50 33,195.00
6.2.3 250 Pcs. 10.00 4,384.50 4,384.50 43,845.00
6.2.4 300 Pcs. 10.00 4,972.50 4,972.50 49,725.00
6.2.5 350 Pcs. 10.00 6,438.00 6,438.00 64,380.00
6.2.6 400 Pcs. 10.00 7,564.50 7,564.50 75,645.00
6.2.7 500 Pcs. 10.00 11,710.50 11,710.50 117,105.00
6.2.8 600 Pcs. 10.00 15,156.00 15,156.00 151,560.00
6.2.9 700 Pcs. 10.00 22,921.50 22,921.50 229,215.00
6.2.10 800 Pcs. 10.00 27,180.00 27,180.00 271,800.00
6.2.11 900 Pcs. 10.00 25,067.98 25,067.98 250,679.80
6.2.12 1000 Pcs. 10.00 27,693.02 27,693.02 276,930.20
6.3 Flange Adapter
6.3.1 160 Pcs. 10.00 885.20 885.20 8,852.00
6.3.2 200 Pcs. 10.00 1,106.50 1,106.50 11,065.00
6.3.3 250 Pcs. 10.00 1,461.50 1,461.50 14,615.00
6.3.4 300 Pcs. 10.00 1,657.50 1,657.50 16,575.00
6.3.5 350 Pcs. 10.00 2,146.00 2,146.00 21,460.00
6.3.6 400 Pcs. 10.00 2,521.50 2,521.50 25,215.00
6.3.7 500 Pcs. 10.00 3,903.50 3,903.50 39,035.00
6.3.8 600 Pcs. 10.00 5,052.00 5,052.00 50,520.00
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 65 of 70
Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh
6.3.9 700 Pcs. 10.00 7,640.50 7,640.50 76,405.00
6.3.10 800 Pcs. 10.00 9,060.00 9,060.00 90,600.00
6.3.11 900 Pcs. 10.00 8,355.99 8,355.99 83,559.93
6.3.12 1000 Pcs. 10.00 9,231.01 9,231.01 92,310.07
6.4 Tee/Wye
6.4.1 160 Pcs. 10.00 2,655.60 2,655.60 26,556.00
6.4.2 200 Pcs. 10.00 3,319.50 3,319.50 33,195.00
6.4.3 250 Pcs. 10.00 4,384.50 4,384.50 43,845.00
6.4.4 300 Pcs. 10.00 4,972.50 4,972.50 49,725.00
6.4.5 350 Pcs. 10.00 6,438.00 6,438.00 64,380.00
6.4.6 400 Pcs. 10.00 10,086.00 10,086.00 100,860.00
6.4.7 500 Pcs. 10.00 15,614.00 15,614.00 156,140.00
6.4.8 600 Pcs. 10.00 20,208.00 20,208.00 202,080.00
6.4.9 700 Pcs. 10.00 30,562.00 30,562.00 305,620.00
6.4.10 800 Pcs. 10.00 36,240.00 36,240.00 362,400.00
6.4.11 900 Pcs. 10.00 33,423.97 33,423.97 334,239.73
6.4.12 1000 Pcs. 10.00 36,924.03 36,924.03 369,240.27
6.5 Elbow (30/60/90 degrees)
6.5.1 160 Pcs. 10.00 1,770.40 1,770.40 17,704.00
6.5.2 200 Pcs. 10.00 2,213.00 2,213.00 22,130.00
6.5.3 250 Pcs. 10.00 2,923.00 2,923.00 29,230.00
6.5.4 300 Pcs. 10.00 3,315.00 3,315.00 33,150.00
6.5.5 350 Pcs. 10.00 4,292.00 4,292.00 42,920.00
6.5.6 400 Pcs. 10.00 5,043.00 5,043.00 50,430.00
6.5.7 500 Pcs. 10.00 7,807.00 7,807.00 78,070.00
6.5.8 600 Pcs. 10.00 10,104.00 10,104.00 101,040.00
6.5.9 700 Pcs. 10.00 15,281.00 15,281.00 152,810.00
6.5.10 800 Pcs. 10.00 18,120.00 18,120.00 181,200.00
6.5.11 900 Pcs. 10.00 16,711.99 16,711.99 167,119.87
6.5.12 1000 Pcs. 10.00 18,462.01 18,462.01 184,620.13
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 10,874,513.00

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 66 of 70
Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.1 Equipment
7.1.1 Micro Tunneling Machine with complete set hrs. 50 6,000.00 6,000.00 300,000.00
7.1.2 Hydraulic HDD Unit hrs. 30 4,000.00 4,000.00 120,000.00
7.1.3 Excavator, face shovel, or dragline:
7.1.3.1 Up to and including 1 m3 hrs. 30 2,000.00 2,000.00 60,000.00
7.1.3.2 Over 1 m3 to 2 m3 hrs. 40 3,000.00 3,000.00 120,000.00
7.1.3.3 Over 2 m3 hrs. 30 3,510.00 3,510.00 105,300.00
7.1.4 Tractor, including bull or angle dozer:
7.1.4.1 Up to and including 150 kW hrs. 50 1,000.00 1,000.00 50,000.00
7.1.4.2 Over 150 kW to 200 kW hrs. 50 1,500.00 1,500.00 75,000.00
7.1.4.3 Over 200 kW to 250 kW hrs. 50 2,000.00 2,000.00 100,000.00
7.1.5 Tractor with ripper:
7.1.5.1 Up to and including 200 kW hrs. 50 1,500.00 1,500.00 75,000.00
7.1.5.2 Over 200 kW to 250 kW hrs. 50 2,000.00 2,000.00 100,000.00
7.1.6 Portable concrete mixer - 0.4m3 hrs. 70 500.00 500.00 35,000.00
7.1.7 Hydraulic Excavator – 1 m3 hrs. 50 3,000.00 3,000.00 150,000.00
7.1.8 4-tool compressor including tools and hoses hrs. 50 2,000.00 2,000.00 100,000.00
7.1.9 10 tonne lorry-mounted crane hrs. 50 5,000.00 5,000.00 250,000.00
7.1.10 750 Kg crane hrs. 50 2,000.00 2,000.00 100,000.00
7.1.11 0.5 m3 dumper hrs. 50 1,000.00 1,000.00 50,000.00
7.1.12 1 m3 dumper hrs. 50 1,500.00 1,500.00 75,000.00
7.1.13 7 m3 tipper lorry hrs. 50 2,000.00 2,000.00 100,000.00
7.1.14 15 m3 lorry hrs. 50 2,000.00 2,000.00 100,000.00
7.1.15 4 wheel drive pick-up or van hrs. 50 500.00 500.00 25,000.00
7.1.16 Vibrating plate compactor hrs. 50 500.00 500.00 25,000.00
7.1.17 8-10 tonne roller hrs. 50 2,000.00 2,000.00 100,000.00
7.1.18 Scaffolding, 10 sqm day 10 2,025.00 2,025.00 20,250.00
7.1.19 5-Ton capacity truck-fare in Dhaka city i/c loading, unloading hrs. 70 456.50 456.50 31,955.00
7.1.20 Concrete mixer machine -1 bag capacity hrs. 40 537.50 537.50 21,500.00
7.1.21 Concrete vibrator-40mm dia hrs. 40 423.00 423.00 16,920.00
7.1.22 Diesel operated 1 cusec pump hrs. 70 505.00 505.00 35,350.00
7.1.23 Electricity operated 1 cusec pump hrs. 50 329.00 329.00 16,450.00
7.1.24 Road cutting Equipment hrs. 50 1,097.00 1,097.00 54,850.00
7.1.25 Backhoe Loader, wheel operated hrs. 30 3,510.00 3,510.00 105,300.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 67 of 70
Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh

7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 20 675.00 675.00 13,500.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 20 607.50 607.50 12,150.00
clinker): 50kg bag
7.2.3 White Cement kg 50 54.00 54.00 2,700.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 0.50 86,400.00 86,400.00 43,200.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 0.50 87,750.00 87,750.00 43,875.00
7.2.6 MS Sheet M Ton 0.50 114,750.00 114,750.00 57,375.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 1,110 10,800.00 10,800.00 11,988.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 1,110 12,150.00 12,150.00 13,486.50
7.2.9 Imported Earth m3 20 572.50 572.50 11,450.00
7.2.10 Sand (F.M. 0.8) m3 20 525.00 525.00 10,500.00
7.2.11 Sand (F.M. 1.2) m3 10 810.50 810.50 8,105.00
7.2.12 Sand (F.M. 2.5) m3 10 2,384.00 2,384.00 23,840.00
7.2.13 Viti/Filling Sand m3 20 524.50 524.50 10,490.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 68 of 70
Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.3 Labor
-
7.3.1 Contract Manager day 10 15,000.00 15,000.00 150,000.00
7.3.2 Office Assistant day 10 500.00 500.00 5,000.00
7.3.3 Contract / Legal Advisor day 10 5,000.00 5,000.00 50,000.00
7.3.4 Financial Advisor day 10 5,000.00 5,000.00 50,000.00
7.3.5 Quantity Engineer day 10 3,000.00 3,000.00 30,000.00
7.3.6 Designer day 10 10,000.00 10,000.00 100,000.00
7.3.7 Field Engineer day 10 3,000.00 3,000.00 30,000.00
7.3.8 Draft Person day 10 2,000.00 2,000.00 20,000.00
7.3.9 Ordinary/casual Labour day 50 600.00 600.00 30,000.00
7.3.10 Skilled labour day 30 945.00 945.00 28,350.00
7.3.11 Head Operator/Ganger day 10 1,080.00 1,080.00 10,800.00
7.3.12 Asstt. Operator/Ganger day 10 945.00 945.00 9,450.00
7.3.13 Head Mason day 10 1,080.00 1,080.00 10,800.00
7.3.14 Mud Operator day 10 945.00 945.00 9,450.00
7.3.15 Field Supervisor/Manager day 10 3,375.00 3,375.00 33,750.00
7.3.16 Field/Maintenance Engineer day 10 2,700.00 2,700.00 27,000.00
7.3.17 Skilled technician/Plumber/Mason/Steel work Erector/ day 10 800.00 800.00 8,000.00
7.3.18 Semi Skilled technician day 30 700.00 700.00 21,000.00
7.3.19 Site security day 10 600.00 600.00 6,000.00
7.3.20 Driver day 10 1,100.00 1,100.00 11,000.00
7.3.21 Sweeper for Odd Job day 10 1,000.00 1,000.00 10,000.00
7.3.22 Surveyor day 10 1,080.00 1,080.00 10,800.00
7.3.23 Asstt. Surveyor day 30 810.00 810.00 24,300.00
7.3.24 Carpenter

Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 3,466,234.50

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 69 of 70
Schedule No. 8 - O&M Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price
a b c d e f g h=e+f+g i=dxh
8 O&M Services and Documentation

8.1 One year O&M (5 Loops in Segments 1-5)


8.1.1 O&M Services in Loop 101 km 3.32 934,330.00 3,101,975.60
8.1.2 O&M Services in Loop 102 km 4.11 934,330.00 3,840,096.30
8.1.3 O&M Services in Loop 103 km 2.3 934,330.00 2,148,959.00
8.1.4 O&M Services in Loop 104 km 15.74 934,330.00 14,706,354.20
8.1.5 O&M Services in Loop 105 km 17.61 934,330.00 16,453,551.30
43.08
Sub-total 8.1: Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 40,250,936.40

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 70 of 70
Employer’s Cost Estimates5

D: Cost of Package 2 (Segment 6)


Schedule No. 1 - Pipe and Fittings Supplied from Abroad

Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 57,080.60
1.1.2 ø250 mm m 2,797.70
1.1.3 ø300 mm m 1,720.90
1.1.4 ø350 mm m 1,672.30
1.1.5 ø400 mm m 960.10
1.1.6 ø450 mm m 415.10
1.1.7 ø500 mm m 219.20
1.1.8 ø600 mm m 261.30
1.1.9 ø700 mm m 80.60
1.1.10 ø800 mm m
1.1.11 ø900 mm m
1.1.12 ø1000 mm m
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 114
1.2.2 ø250 mm nos. 6
1.2.3 ø300 mm nos. 3
1.2.4 ø350 mm nos. 3
1.2.5 ø400 mm nos. 2
1.2.6 ø450 mm nos. 1
1.2.7 ø500 mm nos. 1
1.2.8 ø600 mm nos. 1
1.2.9 ø700 mm nos. 1

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 1 of 176
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.10 ø800 mm nos.
1.2.11 ø900 mm nos.
1.2.12 ø1000 mm nos.
Equal and Un Equal Tee
1.3
of different sizes
1.3.1 200mm x200mm nos. 114
1.3.2 250mm x250mm nos. 6
1.3.3 300mm X 300mm nos. 3
1.3.4 350mm X 350mm nos. 3
1.3.5 400mm X 400mm nos. 2
1.3.6 450mm X 450mm nos. 1
1.3.7 500mm X 500mm nos. 1
1.3.8 600 mm X 600mm nos. 1
1.3.9 700mm X 700mm nos. 1
1.3.10 800mm x 800mm nos.
1.3.11 900mm X 900mm nos.
1.3.12 1000mm X 1000mm nos.
1.3.13 250mm X250mm X 200mm nos. 6
1.3.14 300mm X 300mm X 200mm nos. 3
1.3.15 300mm X 300mm X 250mm nos. 3
1.3.16 400mm X 400mm X 200mm nos. 2
1.3.17 400mm X 400mm X 250mm nos. 2
1.3.18 400mm X 400mm X 300mm nos. 2
1.3.19 500mm X 500mm X 200mm nos. 1
1.3.20 500mm X 500mm X 300mm nos. 1

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 2 of 176
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos. 228
1.4.2 ø250 mm nos. 12
1.4.3 ø300 mm nos. 6
1.4.4 ø350 mm nos. 6
1.4.5 ø400 mm nos. 4
1.4.6 ø450 mm nos. 2
1.4.7 ø500 mm nos. 2
1.4.8 ø600 mm nos. 2
1.4.9 ø700 mm nos. 2
1.4.10 ø800 mm nos.
1.4.11 ø900 mm nos.
1.4.12 ø1000 mm nos.
1.5 Flanged Adapters
1.5.1 ø200 mm nos. 29
1.5.2 ø250 mm nos. 2
1.5.3 ø300 mm nos. 1
1.5.4 ø350 mm nos. 1
1.5.5 ø400 mm nos. 1
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos. 1
1.5.8 ø600 mm nos. 1
1.5.9 ø700 mm nos. 1
1.5.10 ø800 mm nos.

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 3 of 176
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.5.11 ø900 mm nos.
1.5.12 ø1000 mm nos.

Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 4 of 176
Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country

Unit Price (BDT) Total Sales and


Item Description Unit Qty. Total Unit Price other taxes
Material Labour Equipment (BDT) (BDT)
Price (EXW)
a b c d e f g h=e+f+g i=dxh j

Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 5 of 176
Schedule No. 3 - Design Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment (BDT)
Price

a b c d e f g h=e+f+g i=dxh

3.1 Design / Survey Provisions and Preliminaries


3.1.1 Insurances
3.1.1.1 For design (professional indemnity insurance) LS 1 12,195,308.50 12,195,308.50
3.1.1.2 Other Insurances (to be specified by the Tenderer) LS 1 6,097,654.25 6,097,654.25
Sub-total A: 18,292,962.75
3.2 Design Services (including design office and establishment)

3.2.1 Loop 201


3.2.1.1 Survey and documentation, including Survey Report LS 1 2,171,245.68 2,171,245.68
Detailed designs, Specifications and documentation, including Quality
3.2.1.2 LS 1 1,326,872.36 1,326,872.36
Assurance and Design Report
3.2.1.3 Design Control Services including documentation LS 1 361,874.28 361,874.28

3.2.2 Loop 202


3.2.2.1 Survey and documentation, including Survey Report LS 1 3,340,780.03 3,340,780.03
Detailed designs, Specifications and documentation, including Quality
3.2.2.2 LS 1 2,041,587.80 2,041,587.80
Assurance and Design Report
3.2.2.3 Design Control Services including documentation LS 1 556,796.67 556,796.67

3.2.3 Loop 203A


3.2.3.1 Survey and documentation, including Survey Report LS 1 2,087,254.65 2,087,254.65
Detailed designs, Specifications and documentation, including Quality
3.2.3.2 LS 1 1,275,544.51 1,275,544.51
Assurance and Design Report
3.2.3.3 Design Control Services including documentation LS 1 347,875.78 347,875.78

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 6 of 176
Schedule No. 3 - Design Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment (BDT)
Price

a b c d e f g h=e+f+g i=dxh

3.2.4 Loop 203B


3.2.4.1 Survey and documentation, including Survey Report LS 1 4,590,016.77 4,590,016.77
Detailed designs, Specifications and documentation, including Quality
3.2.4.2 LS 1 2,805,010.25 2,805,010.25
Assurance and Design Report
3.2.4.3 Design Control Services including documentation LS 1 765,002.80 765,002.80

3.2.5 Loop 204


3.2.5.1 Survey and documentation, including Survey Report LS 1 6,620,883.37 6,620,883.37
Detailed designs, Specifications and documentation, including Quality
3.2.5.2 LS 1 4,046,095.39 4,046,095.39
Assurance and Design Report
3.2.5.3 Design Control Services including documentation LS 1 1,103,480.56 1,103,480.56

3.2.6 Loop 205


3.2.6.1 Survey and documentation, including Survey Report LS 1 6,692,392.67 6,692,392.67
Detailed designs, Specifications and documentation, including Quality
3.2.6.2 LS 1 4,089,795.52 4,089,795.52
Assurance and Design Report
3.2.6.3 Design Control Services including documentation LS 1 1,115,398.78 1,115,398.78

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 7 of 176
Schedule No. 3 - Design Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment (BDT)
Price

a b c d e f g h=e+f+g i=dxh

3.2.7 Loop 206


3.2.7.1 Survey and documentation, including Survey Report LS 1 6,963,908.01 6,963,908.01
Detailed designs, Specifications and documentation, including Quality
3.2.7.2 LS 1 4,255,721.56 4,255,721.56
Assurance and Design Report
3.2.7.3 Design Control Services including documentation LS 1 1,160,651.34 1,160,651.34

3.2.8 Loop 207


3.2.8.1 Survey and documentation, including Survey Report LS 1 18,138,518.96 18,138,518.96
Detailed designs, Specifications and documentation, including Quality
3.2.8.2 LS 1 11,084,650.47 11,084,650.47
Assurance and Design Report
3.2.8.3 Design Control Services including documentation LS 1 3,023,086.49 3,023,086.49

3.2.9 Loop 208


3.2.9.1 Survey and documentation, including Survey Report LS 1 24,395,224.37 24,395,224.37
Detailed designs, Specifications and documentation, including Quality
3.2.9.2 LS 1 14,908,192.67 14,908,192.67
Assurance and Design Report
3.2.9.3 Design Control Services including documentation LS 1 4,065,870.73 4,065,870.73

3.2.10 Loop 209


3.2.10.1 Survey and documentation, including Survey Report LS 1 8,631,155.12 8,631,155.12
Detailed designs, Specifications and documentation, including Quality
3.2.10.2 LS 1 5,274,594.79 5,274,594.79
Assurance and Design Report
3.2.10.3 Design Control Services including documentation LS 1 1,438,525.85 1,438,525.85

3.2.11 Loop 210

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 8 of 176
Schedule No. 3 - Design Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment (BDT)
Price

a b c d e f g h=e+f+g i=dxh

3.2.11.1 Survey and documentation, including Survey Report LS 1 11,640,194.96 11,640,194.96


Detailed designs, Specifications and documentation, including Quality
3.2.11.2 LS 1 7,113,452.48 7,113,452.48
Assurance and Design Report
3.2.11.3 Design Control Services including documentation LS 1 1,940,032.49 1,940,032.49

3.2.12 Loop 211


3.2.12.1 Survey and documentation, including Survey Report LS 1 14,486,201.92 14,486,201.92
Detailed designs, Specifications and documentation, including Quality
3.2.12.2 LS 1 8,852,678.95 8,852,678.95
Assurance and Design Report
3.2.12.3 Design Control Services including documentation LS 1 2,414,366.99 2,414,366.99

Sub-total B: 195,124,936.04
Total A+B: Sub-total 3:
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 213,417,898.79
Grand Summary

Name of Bidder:

Signature of Bidder:

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 9 of 176
Schedule No. 4 - Installation / Construction and Other works

Unit Price (BDT)


Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment (BDT)
Price

a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 6,097,654.25 6,097,654.25
4.1.1.2 Advance Payment Guarantee LS 1 6,097,654.25 6,097,654.25
Subtotal 4.1.1 12,195,308.50
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.2 Installation All Risks Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.3 Third Party Liability Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.4 Automobile Liability Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.5 Workers' Compensation LS 1 9,146,481.38 9,146,481.38
4.1.2.6 Employer's Liability LS 1 9,146,481.38 9,146,481.38
4.1.2.7 Contractor's Equipment Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 9,146,481.38 9,146,481.38
Subtotal 4.1.2 73,171,851.01
4.1.3 Site establishment, operation and removal

Supply and erect signboard, establish Contractor´s main site offices, welfare
4.1.3.1 LS 1 6,968,747.72 6,968,747.72
facilities, workshops, site access and miscellaneous services etc.

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 10 of 176
Schedule No. 4 - Installation / Construction and Other works

Unit Price (BDT)


Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment (BDT)
Price

a b c d e f g h=e+f+g i=dxh

Manage generally the site and the above facilities during the implementation
4.1.3.2 LS 1 6,968,747.72 6,968,747.72
period including health, safety and security measures

4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 6,968,747.72 6,968,747.72
4.1.3.4 Survey instruments LS 1 6,968,747.72 6,968,747.72
The Project Manager's / Engineers Office with all operational facilities, operation
4.1.3.5 LS 1 6,968,747.72 6,968,747.72
and maintenance

Removal at the completion of the works of all the established facilities and site
4.1.3.6 LS 1 6,968,747.72 6,968,747.72
restoration

Subtotal 4.1.3 41,812,486.29


Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 127,179,645.80

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 11 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.2 INSTALLATION of LOOP 201
4.2.1 Miscellaneous works during implementation
4.2.1.1 Setting-out LS 1.00 27,854.00 27,854.00
4.2.1.2 General works and site tests LS 1.00 55,708.00 55,708.00
4.2.2 Commissioning and final inspection /Tests
Pre-commissioning with necessary arrangement on
4.2.2.1 completion of installation, construction, documentation, LS 1.00 55,708.00 55,708.00
reporting etc.

Commissioning and final inspection / testing before


4.2.2.2 LS 1.00 20,890.50 20,890.50
issuing construction completed & acceptance certificate

Training of Employer's staff on operation and


4.2.2.3 LS 1.00 15,000.00 15,000.00
maintenance

Development and submission of Operation and


4.2.2.4 LS 1.00 7,500.00 7,500.00
Maintenance manuals
Development and submission of GIS based As-built
4.2.2.5 LS 1.00 34,817.50 34,817.50
drawings
4.2.2.6 Post Construction modelling LS 1.00 4,178.10 4,178.10

Supply and Installation of GRP pipes in accordance with


the technical specification and the standard detail
drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting
4.2.3 permission fee, temporary road reinstatement, -
dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting as per approved drawing and
specification.

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 12 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.2.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.3.A.1.1 ø200 mm m 1,331.10 3,596.40 1,581.32 878.18 5,811.99 11,867.89 15,797,346.97


4.2.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.2.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.2.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.2.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.2.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.2.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.2.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.2.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.2.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.2.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.2.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.2.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.A.2.1 ø200 mm m 41.30 3,890.84 1,719.29 901.27 5,811.99 12,323.40 508,956.24


4.2.3.A.2.2 ø250 mm m 20.30 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 278,028.05
4.2.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.2.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.2.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.2.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.2.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 13 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -


4.2.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.2.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.2.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.2.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.2.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.2.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.2.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.2.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.2.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.2.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.2.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.2.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.2.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.2.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.2.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.2.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.2.3.B.1.1 ø200 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 14 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -

4.2.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 15 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.2.11 ø900 mm m -

4.2.3.B.2.12 ø1000 mm m -

4.2.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -

4.2.3.B.3.11 ø900 mm m -

4.2.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in


accordance with the technical specification and the
standard detailed drawings, of any diameter/ size and to
the depths specified below, including fitting, fixing of all
items, road cutting permission fee, temporary road
4.2.4
reinstatement, dismantling of existing structures, site
cleaning, earth cutting, sand filling, earth refilling , coarse
materials/ khoa filling, concreting, Approved brand CI
Manhole cover, as per approved drawing and
specification.

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 16 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A Normal Manhole Rectangular or circular

Manhole invert depth less than equal


4.2.4.A.1
to 3m ( ≤ 3m)
4.2.4.A.1.1 ø200 mm nos. 25.00 108,465.00 17,845.00 10,137.00 136,447.00 3,411,175.00
4.2.4.A.1.2 ø250 mm nos. 2.00 109,101.00 17,858.00 10,150.00 137,109.00 274,218.00
4.2.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.2.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.2.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.A.2.1 ø200 mm nos. 133,076.00 22,507.00 12,324.00 167,907.00 -


4.2.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.2.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.2.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.2.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.2.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 17 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -


4.2.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.2.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.2.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.2.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.2.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.2.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.2.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.2.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.2.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.2.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.2.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.2.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.2.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.2.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.2.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.2.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.2.4.B Drop Manhole Rectangular or circular

Manhole invert depth less than equal


4.2.4.B.1
to 3m ( ≤ 3m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 18 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.1.1 ø200 mm nos. - 177,870.00 34,380.00 19,812.00 232,062.00 -


4.2.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.2.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.2.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.2.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.2.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.2.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.2.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.2.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.2.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.2.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.2.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.2.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.2.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.2.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.2.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.2.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.2.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.2.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.2.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.2.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 19 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.2.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.2.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.2.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.2.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.2.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.2.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.2.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.2.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.2.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.2.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.2.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.2.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.2.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.2.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.2.4.C Service connections Manhole Rectangular or circular -

S/C Manhole invert depth less than equal to 3m ( ≤


4.2.4.C.1 -
3m)

4.2.4.C.1.1 ø200 mm nos. 74.00 108,465.00 17,845.00 10,137.00 136,447.00 10,097,078.00


4.2.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 20 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -


4.2.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.B.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.2.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.C.2.1 ø200 mm nos. 3 133,076.00 22,507.00 12,324.00 167,907.00 503,721.00


4.2.4.C.2.2 ø250 mm nos. 2 133,713.00 22,520.00 12,338.00 168,571.00 337,142.00
4.2.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.2.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.2.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.2.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.2.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.2.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.2.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 21 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.2.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.2.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.2.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.2.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.2.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.2.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.2.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.2.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.2.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.2.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.2.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.2.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.2.4.B.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP


pipes including fitting, fixing of all items, road cutting
permission fee, temporary road reinstatement,
dismantling of existing structures, site cleaning, earth
4.2.5
cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection
pit, average length of 10m as per approved drawing and
specification.

4.2.5.1 ø150 mm nos. 117.00 40,766.88 13,972.83 8,265.14 63,004.85 7,371,567.45

4.2.5.2 ø200 mm nos. 47.00 44,627.58 15,581.46 9,230.31 69,439.35 3,263,649.45

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 22 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.5.3 ø250 mm nos. 47.00 51,128.58 18,290.21 10,855.56 80,274.35 3,772,894.45


4.2.5.4 ø300 mm nos. 23.00 55,471.38 20,099.71 11,941.26 87,512.35 2,012,784.05

Construction of concrete thrust blocks including road


cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth -
cutting, sand filling, earth refilling , coarse material s/
khoa filling, as per approved drawing and specification.

4.2.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.6.A.1.1 ø200 mm nos. 25.00 11,079.12 3,235.25 433.10 14,747.46 368,686.50


4.2.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.2.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.2.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.2.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.2.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.2.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.2.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.2.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.2.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.2.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.2.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.2.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.6.A.2.1 ø200 mm nos. 1.00 11,079.12 3,614.08 439.51 15,132.71 15,132.71


4.2.6.A.2.2 ø250 mm nos. 1.00 11,597.22 3,810.28 460.57 15,868.07 15,868.07
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 23 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -


4.2.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.2.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.2.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.2.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.2.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.2.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.2.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.2.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.2.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.2.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.2.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.2.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.2.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.2.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.2.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.2.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.2.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.2.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.2.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.2.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 24 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.2: Column 'j' to be carried forward to


. 48,249,904.04
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 25 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.3 INSTALLATION of LOOP 202
4.3.1 Miscellaneous works during implementation
4.3.1.1 Setting-out LS 1.00 41,120.00 41,120.00
4.3.1.2 General works and site tests LS 1.00 82,240.00 82,240.00
4.3.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.3.2.1 LS 1.00 82,240.00 82,240.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.3.2.2 LS 1.00 30,840.00 30,840.00
construction completed & acceptance certificate

4.3.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.3.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.3.2.5 Development and submission of GIS based As-built drawings LS 1.00 51,400.00 51,400.00
4.3.2.6 Post Construction modelling LS 1.00 6,168.00 6,168.00

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing
4.3.3 of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse material s/ khoa
filling, concreting as per approved drawing and specification.

4.3.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.3.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.3.A.1.1 ø200 mm m 1,388.80 3,596.40 1,581.32 878.18 5,811.99 11,867.89 16,482,124.16


4.3.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 26 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -


4.3.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.3.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.3.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.3.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.3.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.3.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.3.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.3.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.3.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.3.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.A.2.1 ø200 mm m 667 3,890.84 1,719.29 901.27 5,811.99 12,323.40 8,222,169.55


4.3.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.3.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.2.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.3.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.3.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.3.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.3.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.3.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.3.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 27 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.3.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.3.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.3.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.3.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.3.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.3.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.3.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.3.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.3.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.3.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.3.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.3.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.3.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 28 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -

4.3.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -

4.3.3.B.2.11 ø900 mm m -

4.3.3.B.2.12 ø1000 mm m -

4.3.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 29 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -

4.3.3.B.3.11 ø900 mm m -

4.3.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary
4.3.4
road reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per
approved drawing and specification.

4.3.4.A Normal Manhole Rectangular or circular

4.3.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.A.1.1 ø200 mm nos. 40.00 108,465.00 17,845.00 10,137.00 136,447.00 5,457,880.00


4.3.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 30 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -


4.3.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.3.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.A.2.1 ø200 mm nos. 12 133,076.00 22,507.00 12,324.00 167,907.00 2,014,884.00


4.3.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.3.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.3.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.3.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.3.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.3.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.3.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.3.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.3.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.3.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.3.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 31 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -


4.3.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.3.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.3.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.3.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.3.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.3.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.3.4.B Drop Manhole Rectangular or circular

4.3.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.B.1.1 ø200 mm nos. - 177,870.00 34,380.00 19,812.00 232,062.00 -


4.3.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.3.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.3.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.3.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.3.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.3.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.3.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.3.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.3.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.3.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.3.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.3.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 32 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -


4.3.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.3.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.3.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.3.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.3.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.3.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.3.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.3.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.3.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.3.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.3.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.3.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.3.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.3.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.3.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.3.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.3.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.3.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.3.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.3.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.3.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 33 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.3.4.C Service connections Manhole Rectangular or circular -

4.3.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.3.4.C.1.1 ø200 mm nos. 78.00 108,465.00 17,845.00 10,137.00 136,447.00 10,642,866.00


4.3.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.3.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.3.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.3.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.C.2.1 ø200 mm nos. 38 133,076.00 22,507.00 12,324.00 167,907.00 6,380,466.00


4.3.4.C.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.3.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.3.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.3.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 34 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -


4.3.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.3.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.3.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.3.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.3.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.3.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.3.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.3.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.3.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.3.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.3.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.3.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.3.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.3.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 35 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures,
4.3.5 site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection
pit, average length of 10m as per approved drawing and
specification.

4.3.5.1 ø150 mm nos. 172.00 40,766.88 13,972.83 8,265.14 63,004.85 10,836,834.20

4.3.5.2 ø200 mm nos. 69.00 44,627.58 15,581.46 9,230.31 69,439.35 4,791,315.15


4.3.5.3 ø250 mm nos. 69.00 51,128.58 18,290.21 10,855.56 80,274.35 5,538,930.15
4.3.5.4 ø300 mm nos. 34.00 55,471.38 20,099.71 11,941.26 87,512.35 2,975,419.90

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.3.6 existing structures, site cleaning, earth cutting, sand filling, earth -
refilling , coarse material s/ khoa filling, as per approved drawing
and specification.

4.3.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.6.A.1.1 ø200 mm nos. 26.00 11,079.12 3,235.25 433.10 14,747.46 383,433.96


4.3.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.3.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.3.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.3.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.3.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.3.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.3.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.3.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 36 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.3.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.3.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.3.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.6.A.2.1 ø200 mm nos. 13.00 11,079.12 3,614.08 439.51 15,132.71 196,725.23


4.3.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.3.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.3.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.3.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.3.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.3.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.3.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.3.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.3.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.3.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.3.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.3.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.3.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.3.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.3.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.3.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.3.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 37 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -


4.3.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.3.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.3.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.3.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.3.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.3: Column 'j' to be carried forward to


. 74,239,556.30
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 38 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 203A
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 26,550.00 26,550.00
4.4.1.2 General works and site tests LS 1.00 53,100.00 53,100.00
4.4.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.4.2.1 LS 1.00 53,100.00 53,100.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.4.2.2 LS 1.00 19,912.50 19,912.50
construction completed & acceptance certificate
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

Development and submission of Operation and Maintenance


4.4.2.4 LS 1.00 7,500.00 7,500.00
manuals

4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 33,187.50 33,187.50
4.4.2.6 Post Construction modelling LS 1.00 3,982.50 3,982.50

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing
4.4.3 of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse material s/ khoa
filling, concreting as per approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.3.A.1.1 ø200 mm m 1,294.80 3,596.40 1,581.32 878.18 5,811.99 11,867.89 15,366,542.60


4.4.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.4.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 39 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -


4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.4.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 33 3,890.84 1,719.29 901.27 5,811.99 12,323.40 402,975.04


4.4.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.4.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.4.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.4.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.4.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 40 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.4.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.4.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.4.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.4.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.4.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.4.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.4.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 41 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 42 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary
4.4.4
road reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per
approved drawing and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 32.00 108,465.00 17,845.00 10,137.00 136,447.00 4,366,304.00


4.4.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 43 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -


4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 133,076.00 22,507.00 12,324.00 167,907.00 -


4.4.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.4.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.4.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.4.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.4.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.4.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.4.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.4.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 44 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -


4.4.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.4.4.B Drop Manhole Rectangular or circular

4.4.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. - 177,870.00 34,380.00 19,812.00 232,062.00 -


4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.4.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.4.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 45 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -


4.4.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.4.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 46 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.4.C.1.1 ø200 mm nos. 72.00 108,465.00 17,845.00 10,137.00 136,447.00 9,824,184.00


4.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 2 133,076.00 22,507.00 12,324.00 167,907.00 335,814.00


4.4.4.C.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.4.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.4.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.4.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 47 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.4.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.4.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.4.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.4.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.4.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.4.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures,
4.4.5 site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection
pit, average length of 10m as per approved drawing and
specification.

4.2.5.1 ø150 mm nos. 111.00 40,766.88 13,972.83 8,265.14 63,004.85 6,993,538.35

4.2.5.2 ø200 mm nos. 44.00 44,627.58 15,581.46 9,230.31 69,439.35 3,055,331.40

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 48 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.5.3 ø250 mm nos. 44.00 51,128.58 18,290.21 10,855.56 80,274.35 3,532,071.40


4.2.5.4 ø300 mm nos. 22.00 55,471.38 20,099.71 11,941.26 87,512.35 1,925,271.70

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.4.6 existing structures, site cleaning, earth cutting, sand filling, earth -
refilling , coarse material s/ khoa filling, as per approved drawing
and specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 24.00 11,079.12 3,235.25 433.10 14,747.46 353,939.04


4.4.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.4.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 1.00 11,079.12 3,614.08 439.51 15,132.71 15,132.71


4.4.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.4.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.4.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 49 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -


4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.4.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.4.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.4.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.4.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.4.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.4.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.4.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.4.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.4: Column 'j' to be carried forward to


. 46,383,436.74
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 50 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 203B
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 55,340.00 55,340.00
4.4.1.2 General works and site tests LS 1.00 110,680.00 110,680.00
4.4.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.4.2.1 LS 1.00 110,680.00 110,680.00
installation, construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing
4.4.2.2 LS 1.00 41,505.00 41,505.00
construction completed & acceptance certificate
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

Development and submission of Operation and Maintenance


4.4.2.4 LS 1.00 7,500.00 7,500.00
manuals

4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 69,175.00 69,175.00
4.4.2.6 Post Construction modelling LS 1.00 8,301.00 8,301.00

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing of
4.4.3 all items, road cutting permission fee, temporary road reinstatement, -
dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.3.A.1.1 ø200 mm m 2,355.30 3,596.40 1,581.32 878.18 5,811.99 11,867.89 27,952,438.83


4.4.3.A.1.2 ø250 mm m 33.10 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 438,118.94

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 51 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.3 ø300 mm m 57.70 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 818,853.29


4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.4.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 135 3,890.84 1,719.29 901.27 5,811.99 12,323.40 1,663,658.41


4.4.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.4.3.A.2.3 ø300 mm m 66 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 972,964.95
4.4.3.A.2.4 ø350 mm m 94 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 1,421,930.38
4.4.3.A.2.5 ø400 mm m 26 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 459,625.69
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.4.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 52 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.4.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.4.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.4.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.4.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.4.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.4.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.4.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 53 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 54 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.4.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 85.00 108,465.00 17,845.00 10,137.00 136,447.00 11,597,995.00


4.4.4.A.1.2 ø250 mm nos. 1.00 109,101.00 17,858.00 10,150.00 137,109.00 137,109.00
4.4.4.A.1.3 ø300 mm nos. 3.00 109,675.00 17,860.00 10,162.00 137,697.00 413,091.00
4.4.4.A.1.4 ø350 mm nos. 1.00 110,311.00 17,873.00 10,176.00 138,360.00 138,360.00
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 55 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -


4.4.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 133,076.00 22,507.00 12,324.00 167,907.00 -


4.4.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.4.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.4.4.A.2.4 ø350 mm nos. 1 134,923.00 22,534.00 12,363.00 169,820.00 169,820.00
4.4.4.A.2.5 ø400 mm nos. 1 135,559.00 22,547.00 12,377.00 170,483.00 170,483.00
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.4.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.4.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 56 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -


4.4.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.4.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.4.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.4.4.B Drop Manhole Rectangular or circular

4.4.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. - 177,870.00 34,380.00 19,812.00 232,062.00 -


4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 57 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.4.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.4.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.4.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.4.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 58 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

4.4.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.4.C.1.1 ø200 mm nos. 131.00 108,465.00 17,845.00 10,137.00 136,447.00 17,874,557.00


4.4.C.1.2 ø250 mm nos. 2.00 109,101.00 17,858.00 10,150.00 137,109.00 274,218.00
4.4.C.1.3 ø300 mm nos. 4.00 109,675.00 17,860.00 10,162.00 137,697.00 550,788.00
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 8 133,076.00 22,507.00 12,324.00 167,907.00 1,343,256.00


4.4.4.C.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.4.4.C.2.3 ø300 mm nos. 4 134,286.00 22,521.00 12,350.00 169,157.00 676,628.00
4.4.4.C.2.4 ø350 mm nos. 6 134,923.00 22,534.00 12,363.00 169,820.00 1,018,920.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 59 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.2.5 ø400 mm nos. 2 135,559.00 22,547.00 12,377.00 170,483.00 340,966.00


4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.4.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.4.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.4.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.4.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.4.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.4.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 60 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.4.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 231.00 40,766.88 13,972.83 8,265.14 63,004.85 14,554,120.35

4.2.5.2 ø200 mm nos. 92.00 44,627.58 15,581.46 9,230.31 69,439.35 6,388,420.20


4.2.5.3 ø250 mm nos. 92.00 51,128.58 18,290.21 10,855.56 80,274.35 7,385,240.20
4.2.5.4 ø300 mm nos. 46.00 55,471.38 20,099.71 11,941.26 87,512.35 4,025,568.10

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.4.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 44.00 11,079.12 3,235.25 433.10 14,747.46 648,888.24


4.4.6.A.1.2 ø250 mm nos. 1.00 11,597.22 3,408.39 453.76 15,459.37 15,459.37
4.4.6.A.1.3 ø300 mm nos. 1.00 12,111.88 3,579.06 474.29 16,165.22 16,165.22
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 61 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 3.00 11,079.12 3,614.08 439.51 15,132.71 45,398.13


4.4.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.4.6.A.2.3 ø300 mm nos. 1.00 12,111.88 4,007.30 481.54 16,600.72 16,600.72
4.4.6.A.2.4 ø350 mm nos. 2.00 12,575.47 4,195.03 500.60 17,271.10 34,542.20
4.4.6.A.2.5 ø400 mm nos. 1.00 13,090.13 4,395.42 521.95 18,007.50 18,007.50
4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.4.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.4.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.4.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.4.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.4.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 62 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -


4.4.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.4.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.4.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.4: Column 'j' to be carried forward to Schedule


. 102,000,372.71
No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 63 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi
4.5 INSTALLATION of LOOP 204
4.5.1 Miscellaneous works during implementation
4.5.1.1 Setting-out LS 1.00 79,110.00 79,110.00
4.5.1.2 General works and site tests LS 1.00 158,220.00 158,220.00
4.5.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.5.2.1 LS 1.00 158,220.00 158,220.00
installation, construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing
4.5.2.2 LS 1.00 59,332.50 59,332.50
construction completed & acceptance certificate
4.5.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

4.5.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00

4.5.2.5 Development and submission of GIS based As-built drawings LS 1.00 98,887.50 98,887.50
4.5.2.6 Post Construction modelling LS 1.00 11,866.50 11,866.50

Supply and Installation of GRP pipes in accordance with the technical


specification and the standard detail drawing, of any diameter and to
the depths specified below, including fitting, fixing of all items, road
4.5.3 cutting permission fee, temporary road reinstatement, dismantling of -
existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.5.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.5.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.3.A.1.1 ø200 mm m 2,644.50 3,596.40 1,581.32 878.18 5,811.99 11,867.89 31,384,632.31


4.5.3.A.1.2 ø250 mm m 250.10 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 3,310,379.07

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 64 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.1.3 ø300 mm m 91.00 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 1,291,432.40


4.5.3.A.1.4 ø350 mm m 26.10 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 382,044.90
4.5.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.5.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.5.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.5.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.5.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.5.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.5.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.5.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.5.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.A.2.1 ø200 mm m 214 3,890.84 1,719.29 901.27 5,811.99 12,323.40 2,631,044.96


4.5.3.A.2.2 ø250 mm m 88 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 1,198,396.76
4.5.3.A.2.3 ø300 mm m 190 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 2,792,497.59
4.5.3.A.2.4 ø350 mm m 400 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 6,056,818.33
4.5.3.A.2.5 ø400 mm m 41 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 733,254.99
4.5.3.A.2.6 ø450 mm m 11 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 211,254.01
4.5.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.5.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.5.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.5.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.5.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.5.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 65 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.5.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.5.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.5.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.5.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.5.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.5.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.5.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.5.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.5.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.5.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.5.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.5.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.5.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 66 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -

4.5.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -

4.5.3.B.2.11 ø900 mm m -

4.5.3.B.2.12 ø1000 mm m -

4.5.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 67 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -

4.5.3.B.3.11 ø900 mm m -

4.5.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.5.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.5.4.A Normal Manhole Rectangular or circular

4.5.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.A.1.1 ø200 mm nos. 74.00 108,465.00 17,845.00 10,137.00 136,447.00 10,097,078.00


4.5.4.A.1.2 ø250 mm nos. 2.00 109,101.00 17,858.00 10,150.00 137,109.00 274,218.00
4.5.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 68 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -


4.5.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.5.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.A.2.1 ø200 mm nos. 17 133,076.00 22,507.00 12,324.00 167,907.00 2,854,419.00


4.5.4.A.2.2 ø250 mm nos. 1 133,713.00 22,520.00 12,338.00 168,571.00 168,571.00
4.5.4.A.2.3 ø300 mm nos. 5 134,286.00 22,521.00 12,350.00 169,157.00 845,785.00
4.5.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.5.4.A.2.5 ø400 mm nos. 1 135,559.00 22,547.00 12,377.00 170,483.00 170,483.00
4.5.4.A.2.6 ø450 mm nos. 1 136,195.00 22,560.00 12,391.00 171,146.00 171,146.00
4.5.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.5.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.5.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.5.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.5.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 69 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -


4.5.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.5.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.5.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.5.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.5.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.5.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.5.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.5.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.5.4.B Drop Manhole Rectangular or circular

4.5.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.B.1.1 ø200 mm nos. 9.00 177,870.00 34,380.00 19,812.00 232,062.00 2,088,558.00


4.5.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.5.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.5.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.5.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.5.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.5.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.5.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.5.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.5.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.5.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.5.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 70 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.5.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.5.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.5.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.5.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.5.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.5.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.5.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.5.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.5.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.5.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.5.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.5.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.5.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.5.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.5.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.5.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.5.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.5.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.5.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.5.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 71 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.5.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.5.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.5.4.C Service connections Manhole Rectangular or circular -

4.5.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.5.4.C.1.1 ø200 mm nos. 147.00 108,465.00 17,845.00 10,137.00 136,447.00 20,057,709.00


4.5.4.C.1.2 ø250 mm nos. 14.00 109,101.00 17,858.00 10,150.00 137,109.00 1,919,526.00
4.5.4.C.1.3 ø300 mm nos. 6.00 109,675.00 17,860.00 10,162.00 137,697.00 826,182.00
4.5.4.C.1.4 ø350 mm nos. 2.00 110,311.00 17,873.00 10,176.00 138,360.00 276,720.00
4.5.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.5.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.C.2.1 ø200 mm nos. 12 133,076.00 22,507.00 12,324.00 167,907.00 2,014,884.00


4.5.4.C.2.2 ø250 mm nos. 5 133,713.00 22,520.00 12,338.00 168,571.00 842,855.00
4.5.4.C.2.3 ø300 mm nos. 11 134,286.00 22,521.00 12,350.00 169,157.00 1,860,727.00
4.5.4.C.2.4 ø350 mm nos. 23 134,923.00 22,534.00 12,363.00 169,820.00 3,905,860.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 72 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.2.5 ø400 mm nos. 3 135,559.00 22,547.00 12,377.00 170,483.00 511,449.00


4.5.4.C.2.6 ø450 mm nos. 1 136,195.00 22,560.00 12,391.00 171,146.00 171,146.00
4.5.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.5.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.5.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.5.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.5.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.5.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.5.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.5.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.5.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.5.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.5.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.5.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.5.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.5.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.5.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 73 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.2.6
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.5.5.1 ø150 mm nos. 330.00 40,766.88 13,972.83 8,265.14 63,004.85 20,791,600.50

4.5.5.2 ø200 mm nos. 132.00 44,627.58 15,581.46 9,230.31 69,439.35 9,165,994.20


4.5.5.3 ø250 mm nos. 132.00 51,128.58 18,290.21 10,855.56 80,274.35 10,596,214.20
4.5.5.4 ø300 mm nos. 66.00 55,471.38 20,099.71 11,941.26 87,512.35 5,775,815.10

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.5.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.5.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.6.A.1.1 ø200 mm nos. 49.00 11,079.12 3,235.25 433.10 14,747.46 722,625.54


4.5.6.A.1.2 ø250 mm nos. 5.00 11,597.22 3,408.39 453.76 15,459.37 77,296.85
4.5.6.A.1.3 ø300 mm nos. 2.00 12,111.88 3,579.06 474.29 16,165.22 32,330.44
4.5.6.A.1.4 ø350 mm nos. 1.00 12,575.47 3,742.23 492.96 16,810.66 16,810.66
4.5.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.5.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.5.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.5.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.5.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 74 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.5.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.5.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.5.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.6.A.2.1 ø200 mm nos. 4.00 11,079.12 3,614.08 439.51 15,132.71 60,530.84


4.5.6.A.2.2 ø250 mm nos. 2.00 11,597.22 3,810.28 460.57 15,868.07 31,736.14
4.5.6.A.2.3 ø300 mm nos. 4.00 12,111.88 4,007.30 481.54 16,600.72 66,402.88
4.5.6.A.2.4 ø350 mm nos. 8.00 12,575.47 4,195.03 500.60 17,271.10 138,168.80
4.5.6.A.2.5 ø400 mm nos. 1.00 13,090.13 4,395.42 521.95 18,007.50 18,007.50
4.5.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.5.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.5.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.5.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.5.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.5.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.5.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.5.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.5.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.5.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.5.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.5.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.5.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 75 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -


4.5.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.5.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.5.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.5.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.5.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.5: Column 'j' to be carried forward to Schedule


. 147,130,741.47
No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 76 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.6 INSTALLATION of LOOP 205
4.6.1 Miscellaneous works during implementation
4.6.1.1 Setting-out LS 1.00 81,650.00 81,650.00
4.6.1.2 General works and site tests LS 1.00 163,300.00 163,300.00
4.6.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion


4.6.2.1 LS 1.00 163,300.00 163,300.00
of installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.6.2.2 LS 1.00 61,237.50 61,237.50
construction completed & acceptance certificate
4.6.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

Development and submission of Operation and Maintenance


4.6.2.4 LS 1.00 7,500.00 7,500.00
manuals

4.6.2.5 Development and submission of GIS based As-built drawings LS 1.00 102,062.50 102,062.50

4.6.2.6 Post Construction modelling LS 1.00 12,247.50 12,247.50

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting,
4.6.3 fixing of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse material s/ khoa
filling, concreting as per approved drawing and specification.

4.6.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.6.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 77 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.3.A.1.1 ø200 mm m 2,124.10 3,596.40 1,581.32 878.18 5,811.99 11,867.89 25,208,582.90


4.6.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.6.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.6.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.6.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.6.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.6.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.6.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.6.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.6.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.6.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.6.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.6.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.6.3.A.2.1 ø200 mm m 1,958.40 3,890.84 1,719.29 901.27 5,811.99 12,323.40 24,134,137.96


4.6.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.6.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.6.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.6.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.6.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.6.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.6.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.6.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 78 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.6.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.6.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.6.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.6.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.6.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.6.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.6.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.6.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.6.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.6.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.6.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.6.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.6.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.6.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.6.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.6.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.6.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.6.3.B.1.1 ø200 mm m -
4.6.3.B.1.2 ø250 mm m -
4.6.3.B.1.3 ø300 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 79 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.3.B.1.4 ø350 mm m -
4.6.3.B.1.5 ø400 mm m -
4.6.3.B.1.6 ø450 mm m -
4.6.3.B.1.7 ø500 mm m -
4.6.3.B.1.8 ø600 mm m -
4.6.3.B.1.9 ø700 mm m -
4.6.3.B.1.10 ø800 mm m -
4.6.3.B.1.11 ø900 mm m -
4.6.3.B.1.12 ø1000 mm m -

4.6.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.6.3.B.2.1 ø200 mm m -
4.6.3.B.2.2 ø250 mm m -
4.6.3.B.2.3 ø300 mm m -
4.6.3.B.2.4 ø350 mm m -
4.6.3.B.2.5 ø400 mm m -
4.6.3.B.2.6 ø450 mm m -
4.6.3.B.2.7 ø500 mm m -
4.6.3.B.2.8 ø600 mm m -
4.6.3.B.2.9 ø700 mm m -
4.6.3.B.2.10 ø800 mm m -

4.6.3.B.2.11 ø900 mm m -

4.6.3.B.2.12 ø1000 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 80 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.6.3.B.3.1 ø200 mm m -
4.6.3.B.3.2 ø250 mm m -
4.6.3.B.3.3 ø300 mm m -
4.6.3.B.3.4 ø350 mm m -
4.6.3.B.3.5 ø400 mm m -
4.6.3.B.3.6 ø450 mm m -
4.6.3.B.3.7 ø500 mm m -
4.6.3.B.3.8 ø600 mm m -
4.6.3.B.3.9 ø700 mm m -
4.6.3.B.3.10 ø800 mm m -

4.6.3.B.3.11 ø900 mm m -

4.6.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in


accordance with the technical specification and the standard
detailed drawings, of any diameter/ size and to the depths
specified below, including fitting, fixing of all items, road cutting
4.6.4 permission fee, temporary road reinstatement, dismantling of
existing structures, site cleaning, earth cutting, sand filling,
earth refilling , coarse materials/ khoa filling, concreting,
Approved brand CI Manhole cover, as per approved drawing
and specification.

4.6.4.A Normal Manhole Rectangular or circular

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 81 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.6.4.A.1.1 ø200 mm nos. 57.00 108,465.00 17,845.00 10,137.00 136,447.00 7,777,479.00


4.6.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.6.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.6.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.6.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.6.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.6.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.6.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.6.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.6.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.6.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.6.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.6.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.6.4.A.2.1 ø200 mm nos. 33 133,076.00 22,507.00 12,324.00 167,907.00 5,540,931.00


4.6.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.6.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.6.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.6.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.6.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.6.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.6.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 82 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -


4.6.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.6.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.6.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.6.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.6.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.6.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.6.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.6.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.6.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.6.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.6.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.6.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.6.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.6.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.6.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.6.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.6.4.B Drop Manhole Rectangular or circular

4.6.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.6.4.B.1.1 ø200 mm nos. - 177,870.00 34,380.00 19,812.00 232,062.00 -


4.6.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.6.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 83 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -


4.6.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.6.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.6.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.6.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.6.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.6.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.6.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.6.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.6.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.6.4.B.2.1 ø200 mm nos. 5 216,110.00 42,604.00 23,944.00 282,658.00 1,413,290.00


4.6.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.6.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.6.4.B.2.4 ø350 mm nos. 1 217,460.00 42,660.00 24,022.00 284,142.00 284,142.00
4.6.4.B.2.5 ø400 mm nos. 1 217,952.00 42,686.00 24,050.00 284,688.00 284,688.00
4.6.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.6.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.6.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.6.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.6.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.6.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.6.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 84 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.6.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.6.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.6.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.6.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.6.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.6.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.6.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.6.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.6.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.6.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.6.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.6.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.6.4.C Service connections Manhole Rectangular or circular -

4.6.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.6.4.C.1.1 ø200 mm nos. 119.00 108,465.00 17,845.00 10,137.00 136,447.00 16,237,193.00


4.6.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.6.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.6.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.6.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.6.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 85 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -


4.6.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.6.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.6.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.6.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.6.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.6.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.6.4.C.2.1 ø200 mm nos. 109 133,076.00 22,507.00 12,324.00 167,907.00 18,301,863.00


4.6.4.C.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.6.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.6.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.6.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.6.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.6.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.6.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.6.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.6.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.6.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.6.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.6.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.6.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.6.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 86 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -


4.6.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.6.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.6.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.6.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.6.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.6.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.6.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.6.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.6.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing
4.6.5 structures, site cleaning, earth cutting, sand filling, earth refilling
, coarse material s/ khoa filling, concreting, individual house
hold inspection pit, average length of 10m as per approved
drawing and specification.

4.6.5.1 ø150 mm nos. 341.00 40,766.88 13,972.83 8,265.14 63,004.85 21,484,653.85

4.6.5.2 ø200 mm nos. 136.00 44,627.58 15,581.46 9,230.31 69,439.35 9,443,751.60


4.6.5.3 ø250 mm nos. 136.00 51,128.58 18,290.21 10,855.56 80,274.35 10,917,311.60
4.6.5.4 ø300 mm nos. 68.00 55,471.38 20,099.71 11,941.26 87,512.35 5,950,839.80

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 87 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.6.6 existing structures, site cleaning, earth cutting, sand filling, -
earth refilling , coarse material s/ khoa filling, as per approved
drawing and specification.

4.6.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.6.6.A.1.1 ø200 mm nos. 40.00 11,079.12 3,235.25 433.10 14,747.46 589,898.40


4.6.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.6.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.6.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.6.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.6.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.6.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.6.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.6.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.6.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.6.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.6.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.6.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.6.6.A.2.1 ø200 mm nos. 36.00 11,079.12 3,614.08 439.51 15,132.71 544,777.56


4.6.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.6.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.6.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 88 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.6.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -


4.6.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.6.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.6.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.6.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.6.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.6.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.6.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.6.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.6.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.6.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.6.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.6.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.6.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.6.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.6.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.6.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.6.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.6.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.6.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.6.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 89 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Sub-total 4.6: Column 'j' to be carried forward to


. 148,719,837.17
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 90 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.7 INSTALLATION of LOOP 206
4.7.1 Miscellaneous works during implementation
4.7.1.1 Setting-out LS 1.00 84,066.00 84,066.00
4.7.1.2 General works and site tests LS 1.00 168,132.00 168,132.00
4.7.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.7.2.1 LS 1.00 168,132.00 168,132.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.7.2.2 LS 1.00 63,049.50 63,049.50
construction completed & acceptance certificate
4.7.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.7.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.7.2.5 Development and submission of GIS based As-built drawings LS 1.00 105,082.50 105,082.50
4.7.2.6 Post Construction modelling LS 1.00 12,609.90 12,609.90

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing of
4.7.3 all items, road cutting permission fee, temporary road reinstatement, -
dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.7.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.7.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.7.3.A.1.1 ø200 mm m 2,380.60 3,596.40 1,581.32 878.18 5,811.99 11,867.89 28,252,696.42


4.7.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.7.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.7.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.7.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 91 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -


4.7.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.7.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.7.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.7.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.7.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.7.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.7.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.7.3.A.2.1 ø200 mm m 1,504.50 3,890.84 1,719.29 901.27 5,811.99 12,323.40 18,540,548.69


4.7.3.A.2.2 ø250 mm m 44.30 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 606,731.16
4.7.3.A.2.3 ø300 mm m 121.80 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 1,790,137.93
4.7.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.7.3.A.2.5 ø400 mm m 87.30 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 1,561,296.60
4.7.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.7.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.7.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.7.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.7.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.7.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.7.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.7.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.7.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.7.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.7.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.7.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 92 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.3.A.3.5 ø400 mm m 52 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 1,668,423.40


4.7.3.A.3.6 ø450 mm m 13 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 423,240.87
4.7.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.7.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.7.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.7.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.7.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.7.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.7.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.7.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.7.3.B.1.1 ø200 mm m -
4.7.3.B.1.2 ø250 mm m -
4.7.3.B.1.3 ø300 mm m -
4.7.3.B.1.4 ø350 mm m -
4.7.3.B.1.5 ø400 mm m -
4.7.3.B.1.6 ø450 mm m -
4.7.3.B.1.7 ø500 mm m -
4.7.3.B.1.8 ø600 mm m -
4.7.3.B.1.9 ø700 mm m -
4.7.3.B.1.10 ø800 mm m -
4.7.3.B.1.11 ø900 mm m -
4.7.3.B.1.12 ø1000 mm m -

4.7.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.7.3.B.2.1 ø200 mm m -
4.7.3.B.2.2 ø250 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 93 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.3.B.2.3 ø300 mm m -
4.7.3.B.2.4 ø350 mm m -
4.7.3.B.2.5 ø400 mm m -
4.7.3.B.2.6 ø450 mm m -
4.7.3.B.2.7 ø500 mm m -
4.7.3.B.2.8 ø600 mm m -
4.7.3.B.2.9 ø700 mm m -
4.7.3.B.2.10 ø800 mm m -

4.7.3.B.2.11 ø900 mm m -

4.7.3.B.2.12 ø1000 mm m -

4.7.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.7.3.B.3.1 ø200 mm m -
4.7.3.B.3.2 ø250 mm m -
4.7.3.B.3.3 ø300 mm m -
4.7.3.B.3.4 ø350 mm m -
4.7.3.B.3.5 ø400 mm m -
4.7.3.B.3.6 ø450 mm m -
4.7.3.B.3.7 ø500 mm m -
4.7.3.B.3.8 ø600 mm m -
4.7.3.B.3.9 ø700 mm m -
4.7.3.B.3.10 ø800 mm m -

4.7.3.B.3.11 ø900 mm m -

4.7.3.B.3.12 ø1000 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 94 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.7.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.7.4.A Normal Manhole Rectangular or circular

4.7.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.7.4.A.1.1 ø200 mm nos. 68.00 108,465.00 17,845.00 10,137.00 136,447.00 9,278,396.00


4.7.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.7.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.7.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.7.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.7.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.7.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.7.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.7.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.7.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.7.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.7.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.7.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.7.4.A.2.1 ø200 mm nos. 14 133,076.00 22,507.00 12,324.00 167,907.00 2,350,698.00


4.7.4.A.2.2 ø250 mm nos. 1 133,713.00 22,520.00 12,338.00 168,571.00 168,571.00
4.7.4.A.2.3 ø300 mm nos. 3 134,286.00 22,521.00 12,350.00 169,157.00 507,471.00
4.7.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 95 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.4.A.2.5 ø400 mm nos. 3 135,559.00 22,547.00 12,377.00 170,483.00 511,449.00


4.7.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.7.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.7.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.7.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.7.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.7.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.7.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.7.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.7.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.7.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.7.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.7.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.7.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.7.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.7.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.7.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.7.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.7.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.7.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -


4.7.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.7.4.B Drop Manhole Rectangular or circular

4.7.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.7.4.B.1.1 ø200 mm nos. - 177,870.00 34,380.00 19,812.00 232,062.00 -


4.7.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 96 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -


4.7.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.7.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.7.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.7.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.7.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.7.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.7.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.7.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.7.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.7.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.7.4.B.2.1 ø200 mm nos. 7 216,110.00 42,604.00 23,944.00 282,658.00 1,978,606.00


4.7.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.7.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.7.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.7.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.7.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.7.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.7.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.7.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.7.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.7.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.7.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.7.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.7.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 97 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -


4.7.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.7.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.7.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.7.4.B.3.6 ø450 mm nos. 1 294,918.00 59,152.00 32,338.00 386,408.00 386,408.00
4.7.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.7.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.7.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.7.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.7.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.7.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.7.4.C Service connections Manhole Rectangular or circular -

4.7.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.7.4.C.1.1 ø200 mm nos. 133.00 108,465.00 17,845.00 10,137.00 136,447.00 18,147,451.00


4.7.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.7.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.7.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.7.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.7.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.7.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.7.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.7.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.7.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.7.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.7.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 98 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.7.4.C.2.1 ø200 mm nos. 84 133,076.00 22,507.00 12,324.00 167,907.00 14,104,188.00


4.7.4.C.2.2 ø250 mm nos. 3 133,713.00 22,520.00 12,338.00 168,571.00 505,713.00
4.7.4.C.2.3 ø300 mm nos. 7 134,286.00 22,521.00 12,350.00 169,157.00 1,184,099.00
4.7.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.7.4.C.2.5 ø400 mm nos. 5 135,559.00 22,547.00 12,377.00 170,483.00 852,415.00
4.7.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.7.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.7.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.7.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.7.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.7.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.7.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.7.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.7.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.7.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.7.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.7.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.7.4.C.3.5 ø400 mm nos. 3 184,778.00 31,866.00 16,752.00 233,396.00 700,188.00
4.7.4.C.3.6 ø450 mm nos. 1 185,414.00 31,879.00 16,766.00 234,059.00 234,059.00
4.7.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.7.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.7.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.7.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 99 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.7.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.7.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.7.5.1 ø150 mm nos. 351.00 40,766.88 13,972.83 8,265.14 63,004.85 22,114,702.35

4.7.5.2 ø200 mm nos. 140.00 44,627.58 15,581.46 9,230.31 69,439.35 9,721,509.00


4.7.5.3 ø250 mm nos. 140.00 51,128.58 18,290.21 10,855.56 80,274.35 11,238,409.00
4.7.5.4 ø300 mm nos. 70.00 55,471.38 20,099.71 11,941.26 87,512.35 6,125,864.50

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.7.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.7.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.7.6.A.1.1 ø200 mm nos. 44.00 11,079.12 3,235.25 433.10 14,747.46 648,888.24


4.7.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.7.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.7.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.7.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.7.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.7.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.7.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.7.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 100 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.7.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.7.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.7.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.7.6.A.2.1 ø200 mm nos. 28.00 11,079.12 3,614.08 439.51 15,132.71 423,715.88


4.7.6.A.2.2 ø250 mm nos. 1.00 11,597.22 3,810.28 460.57 15,868.07 15,868.07
4.7.6.A.2.3 ø300 mm nos. 2.00 12,111.88 4,007.30 481.54 16,600.72 33,201.44
4.7.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.7.6.A.2.5 ø400 mm nos. 2.00 13,090.13 4,395.42 521.95 18,007.50 36,015.00
4.7.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.7.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.7.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.7.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.7.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.7.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.7.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.7.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.7.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.7.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.7.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.7.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.7.6.A.3.5 ø400 mm nos. 1.00 13,090.13 5,350.74 538.14 18,979.00 18,979.00
4.7.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.7.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.7.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 101 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.7.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -


4.7.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.7.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.7.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.7: Column 'j' to be carried forward to Schedule


. 154,753,511.44
No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 102 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi
4.8 INSTALLATION of LOOP 207
4.8.1 Miscellaneous works during implementation
4.8.1.1 Setting-out LS 1.00 206,958.00 206,958.00
4.8.1.2 General works and site tests LS 1.00 413,916.00 413,916.00
4.8.2 Commissioning and final inspection /Tests
Pre-commissioning with necessary arrangement on
4.8.2.1 completion of installation, construction, documentation, LS 1.00 413,916.00 413,916.00
reporting etc.

Commissioning and final inspection / testing before issuing


4.8.2.2 LS 1.00 155,218.50 155,218.50
construction completed & acceptance certificate

4.8.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

Development and submission of Operation and


4.8.2.4 LS 1.00 7,500.00 7,500.00
Maintenance manuals
Development and submission of GIS based As-built
4.8.2.5 LS 1.00 258,697.50 258,697.50
drawings
4.8.2.6 Post Construction modelling LS 1.00 31,043.70 31,043.70

Supply and Installation of GRP pipes in accordance with


the technical specification and the standard detail drawing,
of any diameter and to the depths specified below,
including fitting, fixing of all items, road cutting permission
4.8.3 -
fee, temporary road reinstatement, dismantling of existing
structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.8.3.A Sewer Pipelines of Grade-A using GRP Pipes -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 103 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.8.3.A.1.1 ø200 mm m 4,656.40 3,596.40 1,581.32 878.18 5,811.99 11,867.89 55,261,638.07


4.8.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.8.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.8.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.8.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.8.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.8.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.8.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.8.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.8.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.8.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.8.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.8.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.8.3.A.2.1 ø200 mm m 4,005.90 3,890.84 1,719.29 901.27 5,811.99 12,323.40 49,366,290.47


4.8.3.A.2.2 ø250 mm m 372.00 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 5,094,898.23
4.8.3.A.2.3 ø300 mm m 178.90 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 2,629,356.94
4.8.3.A.2.4 ø350 mm m 76.80 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 1,161,747.37
4.8.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.8.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.8.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 104 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -


4.8.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.8.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.8.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.8.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.8.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.8.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.8.3.A.3.2 ø250 mm m 64 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 1,785,463.03
4.8.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.8.3.A.3.4 ø350 mm m 558 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 16,375,051.53
4.8.3.A.3.5 ø400 mm m 338 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 10,868,862.25
4.8.3.A.3.6 ø450 mm m 76 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 2,506,635.83
4.8.3.A.3.7 ø500 mm m 21 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 785,725.71
4.8.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.8.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.8.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.8.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.8.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.8.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.8.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.8.3.B.1.1 ø200 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 105 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.3.B.1.2 ø250 mm m -
4.8.3.B.1.3 ø300 mm m -
4.8.3.B.1.4 ø350 mm m -
4.8.3.B.1.5 ø400 mm m -
4.8.3.B.1.6 ø450 mm m -
4.8.3.B.1.7 ø500 mm m -
4.8.3.B.1.8 ø600 mm m -
4.8.3.B.1.9 ø700 mm m -
4.8.3.B.1.10 ø800 mm m -
4.8.3.B.1.11 ø900 mm m -
4.8.3.B.1.12 ø1000 mm m -

4.8.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.8.3.B.2.1 ø200 mm m -
4.8.3.B.2.2 ø250 mm m -
4.8.3.B.2.3 ø300 mm m -
4.8.3.B.2.4 ø350 mm m -
4.8.3.B.2.5 ø400 mm m -
4.8.3.B.2.6 ø450 mm m -
4.8.3.B.2.7 ø500 mm m -
4.8.3.B.2.8 ø600 mm m -
4.8.3.B.2.9 ø700 mm m -
4.8.3.B.2.10 ø800 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 106 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.3.B.2.11 ø900 mm m -

4.8.3.B.2.12 ø1000 mm m -

4.8.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.8.3.B.3.1 ø200 mm m -
4.8.3.B.3.2 ø250 mm m -
4.8.3.B.3.3 ø300 mm m -
4.8.3.B.3.4 ø350 mm m -
4.8.3.B.3.5 ø400 mm m -
4.8.3.B.3.6 ø450 mm m -
4.8.3.B.3.7 ø500 mm m -
4.8.3.B.3.8 ø600 mm m -
4.8.3.B.3.9 ø700 mm m -
4.8.3.B.3.10 ø800 mm m -

4.8.3.B.3.11 ø900 mm m -

4.8.3.B.3.12 ø1000 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 107 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of RCC Manholes chambers in


accordance with the technical specification and the
standard detailed drawings, of any diameter/ size and to
the depths specified below, including fitting, fixing of all
items, road cutting permission fee, temporary road
4.8.4
reinstatement, dismantling of existing structures, site
cleaning, earth cutting, sand filling, earth refilling , coarse
materials/ khoa filling, concreting, Approved brand CI
Manhole cover, as per approved drawing and
specification.

4.8.4.A Normal Manhole Rectangular or circular

4.8.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.8.4.A.1.1 ø200 mm nos. 119.00 108,465.00 17,845.00 10,137.00 136,447.00 16,237,193.00


4.8.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.8.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.8.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.8.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.8.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.8.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.8.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.8.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.8.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.8.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.8.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 108 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.8.4.A.2.1 ø200 mm nos. 73 133,076.00 22,507.00 12,324.00 167,907.00 12,257,211.00


4.8.4.A.2.2 ø250 mm nos. 8 133,713.00 22,520.00 12,338.00 168,571.00 1,348,568.00
4.8.4.A.2.3 ø300 mm nos. 3 134,286.00 22,521.00 12,350.00 169,157.00 507,471.00
4.8.4.A.2.4 ø350 mm nos. 6 134,923.00 22,534.00 12,363.00 169,820.00 1,018,920.00
4.8.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.8.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.8.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.8.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.8.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.8.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.8.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.8.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.8.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.8.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.8.4.A.3.2 ø250 mm nos. 1 182,932 31,838 16,713 231,483.00 231,483.00
4.8.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.8.4.A.3.4 ø350 mm nos. 10 184,142 31,853 16,738 232,733.00 2,327,330.00
4.8.4.A.3.5 ø400 mm nos. 6 184,778 31,866 16,752 233,396.00 1,400,376.00
4.8.4.A.3.6 ø450 mm nos. 2 185,414 31,879 16,766 234,059.00 468,118.00
4.8.4.A.3.7 ø500 mm nos. 1 185,988 31,881 16,777 234,646.00 234,646.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 109 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -


4.8.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.8.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.8.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.8.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.8.4.B Drop Manhole Rectangular or circular

4.8.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.8.4.B.1.1 ø200 mm nos. 4.00 177,870.00 34,380.00 19,812.00 232,062.00 928,248.00


4.8.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.8.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.8.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.8.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.8.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.8.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.8.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.8.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.8.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.8.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.8.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.8.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.8.4.B.2.1 ø200 mm nos. 2 216,110.00 42,604.00 23,944.00 282,658.00 565,316.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 110 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -


4.8.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00
4.8.4.B.2.4 ø350 mm nos. 1 217,460.00 42,660.00 24,022.00 284,142.00 284,142.00
4.8.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.8.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.8.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.8.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.8.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.8.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.8.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.8.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.8.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.8.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.8.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.8.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.8.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.8.4.B.3.5 ø400 mm nos. 1 294,426.00 59,126.00 32,310.00 385,862.00 385,862.00
4.8.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.8.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.8.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.8.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 111 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.8.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.8.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.8.4.C Service connections Manhole Rectangular or circular -

S/C Manhole invert depth less than equal to


4.8.4.C.1 -
3m ( ≤ 3m)
4.8.4.C.1.1 ø200 mm nos. 259.00 108,465.00 17,845.00 10,137.00 136,447.00 35,339,773.00
4.8.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.8.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.8.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.8.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.8.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.8.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.8.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.8.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.8.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.8.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.8.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.8.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.8.4.C.2.1 ø200 mm nos. 223 133,076.00 22,507.00 12,324.00 167,907.00 37,443,261.00


4.8.4.C.2.2 ø250 mm nos. 21 133,713.00 22,520.00 12,338.00 168,571.00 3,539,991.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 112 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.4.C.2.3 ø300 mm nos. 10 134,286.00 22,521.00 12,350.00 169,157.00 1,691,570.00


4.8.4.C.2.4 ø350 mm nos. 5 134,923.00 22,534.00 12,363.00 169,820.00 849,100.00
4.8.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.8.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.8.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.8.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.8.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.8.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.8.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.8.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.8.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.8.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.8.4.C.3.2 ø250 mm nos. 4 182,932.00 31,838.00 16,713.00 231,483.00 925,932.00
4.8.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.8.4.C.3.4 ø350 mm nos. 31 184,142.00 31,853.00 16,738.00 232,733.00 7,214,723.00
4.8.4.C.3.5 ø400 mm nos. 19 184,778.00 31,866.00 16,752.00 233,396.00 4,434,524.00
4.8.4.C.3.6 ø450 mm nos. 5 185,414.00 31,879.00 16,766.00 234,059.00 1,170,295.00
4.8.4.C.3.7 ø500 mm nos. 2 185,988.00 31,881.00 16,777.00 234,646.00 469,292.00
4.8.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.8.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.8.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 113 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.8.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP


pipes including fitting, fixing of all items, road cutting
permission fee, temporary road reinstatement, dismantling
4.8.5 of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling,
concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.8.5.1 ø150 mm nos. 864.00 40,766.88 13,972.83 8,265.14 63,004.85 54,436,190.40

4.8.5.2 ø200 mm nos. 345.00 44,627.58 15,581.46 9,230.31 69,439.35 23,956,575.75


4.8.5.3 ø250 mm nos. 345.00 51,128.58 18,290.21 10,855.56 80,274.35 27,694,650.75
4.8.5.4 ø300 mm nos. 173.00 55,471.38 20,099.71 11,941.26 87,512.35 15,139,636.55

Construction of concrete thrust blocks including road


cutting permission fee, temporary road reinstatement,
4.8.6 dismantling of existing structures, site cleaning, earth -
cutting, sand filling, earth refilling , coarse material s/ khoa
filling, as per approved drawing and specification.

4.8.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.8.6.A.1.1 ø200 mm nos. 86.00 11,079.12 3,235.25 433.10 14,747.46 1,268,281.56


4.8.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.8.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.8.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.8.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 114 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -


4.8.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.8.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.8.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.8.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.8.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.8.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.8.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.8.6.A.2.1 ø200 mm nos. 74.00 11,079.12 3,614.08 439.51 15,132.71 1,119,820.54


4.8.6.A.2.2 ø250 mm nos. 7.00 11,597.22 3,810.28 460.57 15,868.07 111,076.49
4.8.6.A.2.3 ø300 mm nos. 3.00 12,111.88 4,007.30 481.54 16,600.72 49,802.16
4.8.6.A.2.4 ø350 mm nos. 2.00 12,575.47 4,195.03 500.60 17,271.10 34,542.20
4.8.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.8.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.8.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.8.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.8.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.8.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.8.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.8.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.8.6.A.3 Pipe invert depth greater than 5m ( > 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 115 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.8.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.8.6.A.3.2 ø250 mm nos. 1.00 11,597.22 4,617.36 474.24 16,688.82 16,688.82
4.8.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.8.6.A.3.4 ø350 mm nos. 10.00 12,575.47 5,100.93 515.95 18,192.35 181,923.50
4.8.6.A.3.5 ø400 mm nos. 6.00 13,090.13 5,350.74 538.14 18,979.00 113,874.00
4.8.6.A.3.6 ø450 mm nos. 2.00 13,662.73 5,606.32 562.02 19,831.08 39,662.16
4.8.6.A.3.7 ø500 mm nos. 1.00 14,177.39 5,852.76 583.83 20,613.98 20,613.98
4.8.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.8.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.8.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.8.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.8.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.8: Column 'j' to be carried forward to


. 403,078,199.00
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 116 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.9 INSTALLATION of LOOP 208
4.9.1 Miscellaneous works during implementation
4.9.1.1 Setting-out LS 1.00 283,304.00 283,304.00
4.9.1.2 General works and site tests LS 1.00 566,608.00 566,608.00
4.9.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.9.2.1 LS 1.00 566,608.00 566,608.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.9.2.2 LS 1.00 212,478.00 212,478.00
construction completed & acceptance certificate
4.9.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

4.9.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00

4.9.2.5 Development and submission of GIS based As-built drawings LS 1.00 354,130.00 354,130.00
4.9.2.6 Post Construction modelling LS 1.00 42,495.60 42,495.60

Supply and Installation of GRP pipes in accordance with the technical


specification and the standard detail drawing, of any diameter and to
the depths specified below, including fitting, fixing of all items, road
4.9.3 cutting permission fee, temporary road reinstatement, dismantling of -
existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.9.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.9.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.9.3.A.1.1 ø200 mm m 7,344.20 3,596.40 1,581.32 878.18 5,811.99 11,867.89 87,160,149.97


4.9.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 117 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -


4.9.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.9.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.9.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.9.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.9.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.9.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.9.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.9.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.9.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.9.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.9.3.A.2.1 ø200 mm m 4,343 3,890.84 1,719.29 901.27 5,811.99 12,323.40 53,521,739.47


4.9.3.A.2.2 ø250 mm m 844 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 11,559,392.75
4.9.3.A.2.3 ø300 mm m 510 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 7,501,530.36
4.9.3.A.2.4 ø350 mm m 97 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 1,461,260.37
4.9.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.9.3.A.2.6 ø450 mm m 162 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 2,998,324.45
4.9.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.9.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.9.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.9.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.9.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.9.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 118 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.9.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.9.3.A.3.2 ø250 mm m 177 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 4,943,500.77
4.9.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.9.3.A.3.4 ø350 mm m 34 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 1,009,501.38
4.9.3.A.3.5 ø400 mm m 117 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 3,761,185.70
4.9.3.A.3.6 ø450 mm m 38 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 1,250,036.98
4.9.3.A.3.7 ø500 mm m 157 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 5,746,078.22
4.9.3.A.3.8 ø600 mm m 261 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 10,628,776.52
4.9.3.A.3.9 ø700 mm m 81 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 3,907,828.52
4.9.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.9.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.9.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.9.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.9.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.9.3.B.1.1 ø200 mm m -
4.9.3.B.1.2 ø250 mm m -
4.9.3.B.1.3 ø300 mm m -
4.9.3.B.1.4 ø350 mm m -
4.9.3.B.1.5 ø400 mm m -
4.9.3.B.1.6 ø450 mm m -
4.9.3.B.1.7 ø500 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 119 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.3.B.1.8 ø600 mm m -
4.9.3.B.1.9 ø700 mm m -
4.9.3.B.1.10 ø800 mm m -
4.9.3.B.1.11 ø900 mm m -
4.9.3.B.1.12 ø1000 mm m -

4.9.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.9.3.B.2.1 ø200 mm m -
4.9.3.B.2.2 ø250 mm m -
4.9.3.B.2.3 ø300 mm m -
4.9.3.B.2.4 ø350 mm m -
4.9.3.B.2.5 ø400 mm m -
4.9.3.B.2.6 ø450 mm m -
4.9.3.B.2.7 ø500 mm m -
4.9.3.B.2.8 ø600 mm m -
4.9.3.B.2.9 ø700 mm m -
4.9.3.B.2.10 ø800 mm m -

4.9.3.B.2.11 ø900 mm m -

4.9.3.B.2.12 ø1000 mm m -

4.9.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.9.3.B.3.1 ø200 mm m -
4.9.3.B.3.2 ø250 mm m -
4.9.3.B.3.3 ø300 mm m -
4.9.3.B.3.4 ø350 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 120 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.3.B.3.5 ø400 mm m -
4.9.3.B.3.6 ø450 mm m -
4.9.3.B.3.7 ø500 mm m -
4.9.3.B.3.8 ø600 mm m -
4.9.3.B.3.9 ø700 mm m -
4.9.3.B.3.10 ø800 mm m -

4.9.3.B.3.11 ø900 mm m -

4.9.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including fitting,
fixing of all items, road cutting permission fee, temporary road
4.9.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.9.4.A Normal Manhole Rectangular or circular

4.9.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.9.4.A.1.1 ø200 mm nos. 200.00 108,465.00 17,845.00 10,137.00 136,447.00 27,289,400.00


4.9.4.A.1.2 ø250 mm nos. 3.00 109,101.00 17,858.00 10,150.00 137,109.00 411,327.00
4.9.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.9.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.9.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.9.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 121 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -


4.9.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.9.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.9.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.9.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.9.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.9.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.9.4.A.2.1 ø200 mm nos. 58 133,076.00 22,507.00 12,324.00 167,907.00 9,738,606.00


4.9.4.A.2.2 ø250 mm nos. 16 133,713.00 22,520.00 12,338.00 168,571.00 2,697,136.00
4.9.4.A.2.3 ø300 mm nos. 10 134,286.00 22,521.00 12,350.00 169,157.00 1,691,570.00
4.9.4.A.2.4 ø350 mm nos. 4 134,923.00 22,534.00 12,363.00 169,820.00 679,280.00
4.9.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.9.4.A.2.6 ø450 mm nos. 5 136,195.00 22,560.00 12,391.00 171,146.00 855,730.00
4.9.4.A.2.7 ø500 mm nos. 2 136,776.00 22,565.00 12,402.00 171,743.00 343,486.00
4.9.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.9.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.9.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.9.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.9.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.9.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.9.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.9.4.A.3.2 ø250 mm nos. 2 182,932 31,838 16,713 231,483.00 462,966.00
4.9.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 122 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -


4.9.4.A.3.5 ø400 mm nos. 3 184,778 31,866 16,752 233,396.00 700,188.00
4.9.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.9.4.A.3.7 ø500 mm nos. 3 185,988 31,881 16,777 234,646.00 703,938.00
4.9.4.A.3.8 ø600 mm nos. 6 187,267 31,910 16,805 235,982.00 1,415,892.00
4.9.4.A.3.9 ø700 mm nos. 1 188,477 31,924 16,830 237,231.00 237,231.00
4.9.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.9.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.9.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.9.4.B Drop Manhole Rectangular or circular

4.9.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.9.4.B.1.1 ø200 mm nos. 4.00 177,870.00 34,380.00 19,812.00 232,062.00 928,248.00


4.9.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.9.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.9.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.9.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.9.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.9.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.9.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.9.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.9.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.9.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.9.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 123 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.9.4.B.2.1 ø200 mm nos. 4 216,110.00 42,604.00 23,944.00 282,658.00 1,130,632.00


4.9.4.B.2.2 ø250 mm nos. 2 216,602.00 42,630.00 23,972.00 283,204.00 566,408.00
4.9.4.B.2.3 ø300 mm nos. 2 216,968.00 42,634.00 23,994.00 283,596.00 567,192.00
4.9.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.9.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.9.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.9.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.9.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.9.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.9.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.9.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.9.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.9.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.9.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.9.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.9.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.9.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.9.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.9.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.9.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.9.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.9.4.B.3.9 ø700 mm nos. 1 297,140.00 59,244.00 32,466.00 388,850.00 388,850.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 124 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.9.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.9.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.9.4.C Service connections Manhole Rectangular or circular -

4.9.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.9.4.C.1.1 ø200 mm nos. 409.00 108,465.00 17,845.00 10,137.00 136,447.00 55,806,823.00


4.9.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.9.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.9.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.9.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.9.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.9.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.9.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.9.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.9.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.9.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.9.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.9.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.9.4.C.2.1 ø200 mm nos. 242 133,076.00 22,507.00 12,324.00 167,907.00 40,633,494.00


4.9.4.C.2.2 ø250 mm nos. 47 133,713.00 22,520.00 12,338.00 168,571.00 7,922,837.00
4.9.4.C.2.3 ø300 mm nos. 29 134,286.00 22,521.00 12,350.00 169,157.00 4,905,553.00
4.9.4.C.2.4 ø350 mm nos. 6 134,923.00 22,534.00 12,363.00 169,820.00 1,018,920.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 125 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -


4.9.4.C.2.6 ø450 mm nos. 9 136,195.00 22,560.00 12,391.00 171,146.00 1,540,314.00
4.9.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.9.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.9.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.9.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.9.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.9.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.9.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.9.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.9.4.C.3.2 ø250 mm nos. 10 182,932.00 31,838.00 16,713.00 231,483.00 2,314,830.00
4.9.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.9.4.C.3.4 ø350 mm nos. 2 184,142.00 31,853.00 16,738.00 232,733.00 465,466.00
4.9.4.C.3.5 ø400 mm nos. 7 184,778.00 31,866.00 16,752.00 233,396.00 1,633,772.00
4.9.4.C.3.6 ø450 mm nos. 3 185,414.00 31,879.00 16,766.00 234,059.00 702,177.00
4.9.4.C.3.7 ø500 mm nos. 9 185,988.00 31,881.00 16,777.00 234,646.00 2,111,814.00
4.9.4.C.3.8 ø600 mm nos. 15 187,267.00 31,910.00 16,805.00 235,982.00 3,539,730.00
4.9.4.C.3.9 ø700 mm nos. 5 188,477.00 31,924.00 16,830.00 237,231.00 1,186,155.00
4.9.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.9.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.9.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 126 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.9.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.9.5.1 ø150 mm nos. 1,182.00 40,766.88 13,972.83 8,265.14 63,004.85 74,471,732.70

4.9.5.2 ø200 mm nos. 473.00 44,627.58 15,581.46 9,230.31 69,439.35 32,844,812.55


4.9.5.3 ø250 mm nos. 473.00 51,128.58 18,290.21 10,855.56 80,274.35 37,969,767.55
4.9.5.4 ø300 mm nos. 236.00 55,471.38 20,099.71 11,941.26 87,512.35 20,652,914.60

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.9.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.9.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.9.6.A.1.1 ø200 mm nos. 136.00 11,079.12 3,235.25 433.10 14,747.46 2,005,654.56


4.9.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.9.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.9.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.9.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.9.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.9.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.9.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.9.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 127 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.9.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.9.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.9.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.9.6.A.2.1 ø200 mm nos. 81.00 11,079.12 3,614.08 439.51 15,132.71 1,225,749.51


4.9.6.A.2.2 ø250 mm nos. 16.00 11,597.22 3,810.28 460.57 15,868.07 253,889.12
4.9.6.A.2.3 ø300 mm nos. 10.00 12,111.88 4,007.30 481.54 16,600.72 166,007.20
4.9.6.A.2.4 ø350 mm nos. 2.00 12,575.47 4,195.03 500.60 17,271.10 34,542.20
4.9.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.9.6.A.2.6 ø450 mm nos. 3.00 13,662.73 4,601.59 545.00 18,809.33 56,427.99
4.9.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.9.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.9.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.9.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.9.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.9.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.9.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.9.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.9.6.A.3.2 ø250 mm nos. 3.00 11,597.22 4,617.36 474.24 16,688.82 50,066.46
4.9.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.9.6.A.3.4 ø350 mm nos. 1.00 12,575.47 5,100.93 515.95 18,192.35 18,192.35
4.9.6.A.3.5 ø400 mm nos. 2.00 13,090.13 5,350.74 538.14 18,979.00 37,958.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 128 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.6.A.3.6 ø450 mm nos. 1.00 13,662.73 5,606.32 562.02 19,831.08 19,831.08


4.9.6.A.3.7 ø500 mm nos. 3.00 14,177.39 5,852.76 583.83 20,613.98 61,841.94
4.9.6.A.3.8 ø600 mm nos. 5.00 15,264.65 6,359.64 629.91 22,254.20 111,271.00
4.9.6.A.3.9 ø700 mm nos. 2.00 16,460.93 6,881.60 679.59 24,022.12 48,044.24
4.9.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.9.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.9.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.9: Column 'j' to be carried forward to Schedule


. 542,116,097.10
No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 129 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.10 INSTALLATION of LOOP 209
4.10.1 Miscellaneous works during implementation
4.10.1.1 Setting-out LS 1.00 105,976.00 105,976.00
4.10.1.2 General works and site tests LS 1.00 211,952.00 211,952.00
4.10.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.10.2.1 LS 1.00 211,952.00 211,952.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.10.2.2 LS 1.00 79,482.00 79,482.00
construction completed & acceptance certificate
4.10.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

Development and submission of Operation and Maintenance


4.10.2.4 LS 1.00 7,500.00 7,500.00
manuals

4.10.2.5 Development and submission of GIS based As-built drawings LS 1.00 132,470.00 132,470.00
4.10.2.6 Post Construction modelling LS 1.00 15,896.40 15,896.40

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing
4.10.3 of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse material s/ khoa
filling, concreting as per approved drawing and specification.

4.10.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.10.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.10.3.A.1.1 ø200 mm m 3,687.60 3,596.40 1,581.32 878.18 5,811.99 11,867.89 43,764,027.26


4.10.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 130 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -


4.10.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.10.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.10.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.10.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.10.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.10.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.10.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.10.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.10.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.10.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.10.3.A.2.1 ø200 mm m 991.70 3,890.84 1,719.29 901.27 5,811.99 12,323.40 12,221,111.43


4.10.3.A.2.2 ø250 mm m 143.50 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 1,965,370.69
4.10.3.A.2.3 ø300 mm m 393.30 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 5,780,470.00
4.10.3.A.2.4 ø350 mm m 54.80 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 828,955.16
4.10.3.A.2.5 ø400 mm m 27.90 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 498,971.08
4.10.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.10.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.10.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.10.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.10.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.10.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.10.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 131 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.10.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.10.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.10.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.10.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.10.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.10.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.10.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.10.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.10.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.10.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.10.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.10.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.10.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.10.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.10.3.B.1.1 ø200 mm m -
4.10.3.B.1.2 ø250 mm m -
4.10.3.B.1.3 ø300 mm m -
4.10.3.B.1.4 ø350 mm m -
4.10.3.B.1.5 ø400 mm m -
4.10.3.B.1.6 ø450 mm m -
4.10.3.B.1.7 ø500 mm m -
4.10.3.B.1.8 ø600 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 132 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.3.B.1.9 ø700 mm m -
4.10.3.B.1.10 ø800 mm m -
4.10.3.B.1.11 ø900 mm m -
4.10.3.B.1.12 ø1000 mm m -

4.10.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.10.3.B.2.1 ø200 mm m -
4.10.3.B.2.2 ø250 mm m -
4.10.3.B.2.3 ø300 mm m -
4.10.3.B.2.4 ø350 mm m -
4.10.3.B.2.5 ø400 mm m -
4.10.3.B.2.6 ø450 mm m -
4.10.3.B.2.7 ø500 mm m -
4.10.3.B.2.8 ø600 mm m -
4.10.3.B.2.9 ø700 mm m -
4.10.3.B.2.10 ø800 mm m -

4.10.3.B.2.11 ø900 mm m -

4.10.3.B.2.12 ø1000 mm m -

4.10.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.10.3.B.3.1 ø200 mm m -
4.10.3.B.3.2 ø250 mm m -
4.10.3.B.3.3 ø300 mm m -
4.10.3.B.3.4 ø350 mm m -
4.10.3.B.3.5 ø400 mm m -
4.10.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 133 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.3.B.3.7 ø500 mm m -
4.10.3.B.3.8 ø600 mm m -
4.10.3.B.3.9 ø700 mm m -
4.10.3.B.3.10 ø800 mm m -

4.10.3.B.3.11 ø900 mm m -

4.10.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary
4.10.4
road reinstatement, dismantling of existing structures, site
cleaning, earth cutting, sand filling, earth refilling , coarse
materials/ khoa filling, concreting, Approved brand CI Manhole
cover, as per approved drawing and specification.

4.10.4.A Normal Manhole Rectangular or circular

4.10.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.10.4.A.1.1 ø200 mm nos. 89.00 108,465.00 17,845.00 10,137.00 136,447.00 12,143,783.00


4.10.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.10.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.10.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.10.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.10.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.10.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.10.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.10.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 134 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -


4.10.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.10.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.10.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.10.4.A.2.1 ø200 mm nos. 9 133,076.00 22,507.00 12,324.00 167,907.00 1,511,163.00


4.10.4.A.2.2 ø250 mm nos. 4 133,713.00 22,520.00 12,338.00 168,571.00 674,284.00
4.10.4.A.2.3 ø300 mm nos. 8 134,286.00 22,521.00 12,350.00 169,157.00 1,353,256.00
4.10.4.A.2.4 ø350 mm nos. 2 134,923.00 22,534.00 12,363.00 169,820.00 339,640.00
4.10.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.10.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.10.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.10.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.10.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.10.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.10.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.10.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.10.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.10.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.10.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.10.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.10.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.10.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.10.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 135 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -


4.10.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.10.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.10.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.10.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.10.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.10.4.B Drop Manhole Rectangular or circular

4.10.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.10.4.B.1.1 ø200 mm nos. 9.00 177,870.00 34,380.00 19,812.00 232,062.00 2,088,558.00


4.10.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.10.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.10.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.10.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.10.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.10.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.10.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.10.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.10.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.10.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.10.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.10.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.10.4.B.2.1 ø200 mm nos. 1 216,110.00 42,604.00 23,944.00 282,658.00 282,658.00


4.10.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 136 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00


4.10.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.10.4.B.2.5 ø400 mm nos. 1 217,952.00 42,686.00 24,050.00 284,688.00 284,688.00
4.10.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.10.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.10.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.10.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.10.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.10.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.10.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.10.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.10.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.10.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.10.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.10.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.10.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.10.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.10.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.10.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.10.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.10.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.10.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.10.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 137 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.4.C Service connections Manhole Rectangular or circular -

4.10.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.10.4.C.1.1 ø200 mm nos. 205.00 108,465.00 17,845.00 10,137.00 136,447.00 27,971,635.00


4.10.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.10.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.10.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.10.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.10.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.10.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.10.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.10.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.10.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.10.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.10.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.10.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.10.4.C.2.1 ø200 mm nos. 56 133,076.00 22,507.00 12,324.00 167,907.00 9,402,792.00


4.10.4.C.2.2 ø250 mm nos. 8 133,713.00 22,520.00 12,338.00 168,571.00 1,348,568.00
4.10.4.C.2.3 ø300 mm nos. 22 134,286.00 22,521.00 12,350.00 169,157.00 3,721,454.00
4.10.4.C.2.4 ø350 mm nos. 4 134,923.00 22,534.00 12,363.00 169,820.00 679,280.00
4.10.4.C.2.5 ø400 mm nos. 2 135,559.00 22,547.00 12,377.00 170,483.00 340,966.00
4.10.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.10.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.10.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 138 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -


4.10.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.10.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.10.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.10.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.10.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.10.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.10.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.10.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.10.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.10.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.10.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.10.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.10.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.10.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.10.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.10.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures,
4.10.5 site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection
pit, average length of 10m as per approved drawing and
specification.

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 139 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.5.1 ø150 mm nos. 442.00 40,766.88 13,972.83 8,265.14 63,004.85 27,848,143.70

4.10.5.2 ø200 mm nos. 177.00 44,627.58 15,581.46 9,230.31 69,439.35 12,290,764.95


4.10.5.3 ø250 mm nos. 177.00 51,128.58 18,290.21 10,855.56 80,274.35 14,208,559.95
4.10.5.4 ø300 mm nos. 88.00 55,471.38 20,099.71 11,941.26 87,512.35 7,701,086.80

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.10.6 existing structures, site cleaning, earth cutting, sand filling, earth -
refilling , coarse material s/ khoa filling, as per approved drawing
and specification.

4.10.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.10.6.A.1.1 ø200 mm nos. 68.00 11,079.12 3,235.25 433.10 14,747.46 1,002,827.28


4.10.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.10.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.10.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.10.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.10.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.10.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.10.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.10.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.10.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.10.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.10.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.10.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.10.6.A.2.1 ø200 mm nos. 19.00 11,079.12 3,614.08 439.51 15,132.71 287,521.49


4.10.6.A.2.2 ø250 mm nos. 3.00 11,597.22 3,810.28 460.57 15,868.07 47,604.21
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 140 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.10.6.A.2.3 ø300 mm nos. 7.00 12,111.88 4,007.30 481.54 16,600.72 116,205.04


4.10.6.A.2.4 ø350 mm nos. 1.00 12,575.47 4,195.03 500.60 17,271.10 17,271.10
4.10.6.A.2.5 ø400 mm nos. 1.00 13,090.13 4,395.42 521.95 18,007.50 18,007.50
4.10.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.10.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.10.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.10.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.10.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.10.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.10.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.10.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.10.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.10.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.10.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.10.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.10.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.10.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.10.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.10.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.10.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.10.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.10.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.10.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 141 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Sub-total 4.10: Column 'j' to be carried forward to


. 191,803,447.04
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 142 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi
4.11 INSTALLATION of LOOP 210
4.11.1 Miscellaneous works during implementation
4.11.1.1 Setting-out LS 1.00 141,102.00 141,102.00
4.11.1.2 General works and site tests LS 1.00 282,204.00 282,204.00
4.11.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.11.2.1 LS 1.00 282,204.00 282,204.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.11.2.2 LS 1.00 105,826.50 105,826.50
construction completed & acceptance certificate
4.11.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.11.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.11.2.5 Development and submission of GIS based As-built drawings LS 1.00 176,377.50 176,377.50
4.11.2.6 Post Construction modelling LS 1.00 21,165.30 21,165.30

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing of
4.11.3 all items, road cutting permission fee, temporary road reinstatement, -
dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.11.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.11.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.11.3.A.1.1 ø200 mm m 5,378.70 3,596.40 1,581.32 878.18 5,811.99 11,867.89 63,833,814.25


4.11.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.11.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 143 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -


4.11.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.11.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.11.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.11.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.11.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.11.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.11.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.11.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.11.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.11.23.A.2.1 ø200 mm m 721 3,890.84 1,719.29 901.27 5,811.99 12,323.40 8,888,865.25


4.11.23.A.2.2 ø250 mm m 464 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 6,357,666.01
4.11.23.A.2.3 ø300 mm m 58 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 845,097.95
4.11.23.A.2.4 ø350 mm m 185 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 2,801,505.38
4.11.23.A.2.5 ø400 mm m 139 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 2,489,490.11
4.11.23.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.11.23.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.11.23.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.11.23.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.11.23.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.11.23.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.11.23.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.11.3.A.3 Pipe invert depth greater than 5m ( > 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 144 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.11.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.11.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.11.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.11.3.A.3.5 ø400 mm m 93 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 2,986,445.74
4.11.3.A.3.6 ø450 mm m 16 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 528,230.85
4.11.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.11.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.11.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.11.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.11.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.11.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.11.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.11.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.11.3.B.1.1 ø200 mm m -
4.11.3.B.1.2 ø250 mm m -
4.11.3.B.1.3 ø300 mm m -
4.11.3.B.1.4 ø350 mm m -
4.11.3.B.1.5 ø400 mm m -
4.11.3.B.1.6 ø450 mm m -
4.11.3.B.1.7 ø500 mm m -
4.11.3.B.1.8 ø600 mm m -
4.11.3.B.1.9 ø700 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 145 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.3.B.1.10 ø800 mm m -
4.11.3.B.1.11 ø900 mm m -
4.11.3.B.1.12 ø1000 mm m -

4.11.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.11.3.B.2.1 ø200 mm m -
4.11.3.B.2.2 ø250 mm m -
4.11.3.B.2.3 ø300 mm m -
4.11.3.B.2.4 ø350 mm m -
4.11.3.B.2.5 ø400 mm m -
4.11.3.B.2.6 ø450 mm m -
4.11.3.B.2.7 ø500 mm m -
4.11.3.B.2.8 ø600 mm m -
4.11.3.B.2.9 ø700 mm m -
4.11.3.B.2.10 ø800 mm m -

4.11.3.B.2.11 ø900 mm m -

4.11.3.B.2.12 ø1000 mm m -

4.11.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.11.3.B.3.1 ø200 mm m -
4.11.3.B.3.2 ø250 mm m -
4.11.3.B.3.3 ø300 mm m -
4.11.3.B.3.4 ø350 mm m -
4.11.3.B.3.5 ø400 mm m -
4.11.3.B.3.6 ø450 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 146 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.3.B.3.7 ø500 mm m -
4.11.3.B.3.8 ø600 mm m -
4.11.3.B.3.9 ø700 mm m -
4.11.3.B.3.10 ø800 mm m -

4.11.3.B.3.11 ø900 mm m -

4.11.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.11.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.11.4.A Normal Manhole Rectangular or circular

4.11.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.11.4.A.1.1 ø200 mm nos. 121.00 108,465.00 17,845.00 10,137.00 136,447.00 16,510,087.00


4.11.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.11.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.11.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.11.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.11.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.11.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.11.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 147 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -


4.11.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.11.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.11.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.11.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.11.4.A.2.1 ø200 mm nos. 14 133,076.00 22,507.00 12,324.00 167,907.00 2,350,698.00


4.11.4.A.2.2 ø250 mm nos. 5 133,713.00 22,520.00 12,338.00 168,571.00 842,855.00
4.11.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.11.4.A.2.4 ø350 mm nos. 5 134,923.00 22,534.00 12,363.00 169,820.00 849,100.00
4.11.4.A.2.5 ø400 mm nos. 6 135,559.00 22,547.00 12,377.00 170,483.00 1,022,898.00
4.11.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.11.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.11.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.11.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.11.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.11.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.11.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.11.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.11.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.11.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.11.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.11.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.11.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 148 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -


4.11.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.11.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.11.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.11.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.11.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.11.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.11.4.B Drop Manhole Rectangular or circular

4.11.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.11.4.B.1.1 ø200 mm nos. 16.00 177,870.00 34,380.00 19,812.00 232,062.00 3,712,992.00


4.11.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.11.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.11.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.11.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.11.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.11.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.11.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.11.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.11.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.11.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.11.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.11.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.11.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 149 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.4.B.2.2 ø250 mm nos. 2 216,602.00 42,630.00 23,972.00 283,204.00 566,408.00


4.11.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00
4.11.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.11.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.11.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.11.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.11.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.11.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.11.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.11.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.11.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.11.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.11.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.11.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.11.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.11.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.11.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.11.4.B.3.6 ø450 mm nos. 1 294,918.00 59,152.00 32,338.00 386,408.00 386,408.00
4.11.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.11.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.11.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.11.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.11.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 150 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.11.4.C Service connections Manhole Rectangular or circular -

4.11.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.11.4.C.1.1 ø200 mm nos. 299.00 108,465.00 17,845.00 10,137.00 136,447.00 40,797,653.00


4.11.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.11.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.11.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.11.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.11.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.11.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.11.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.11.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.11.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.11.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.11.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.11.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.11.4.C.2.1 ø200 mm nos. 41 133,076.00 22,507.00 12,324.00 167,907.00 6,884,187.00


4.11.4.C.2.2 ø250 mm nos. 26 133,713.00 22,520.00 12,338.00 168,571.00 4,382,846.00
4.11.4.C.2.3 ø300 mm nos. 4 134,286.00 22,521.00 12,350.00 169,157.00 676,628.00
4.11.4.C.2.4 ø350 mm nos. 11 134,923.00 22,534.00 12,363.00 169,820.00 1,868,020.00
4.11.4.C.2.5 ø400 mm nos. 8 135,559.00 22,547.00 12,377.00 170,483.00 1,363,864.00
4.11.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.11.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 151 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -


4.11.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.11.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.11.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.11.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.11.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.11.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.11.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.11.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.11.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.11.4.C.3.5 ø400 mm nos. 6 184,778.00 31,866.00 16,752.00 233,396.00 1,400,376.00
4.11.4.C.3.6 ø450 mm nos. 1 185,414.00 31,879.00 16,766.00 234,059.00 234,059.00
4.11.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.11.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.11.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.11.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.11.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.11.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 152 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.11.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.11.5.1 ø150 mm nos. 589.00 40,766.88 13,972.83 8,265.14 63,004.85 37,109,856.65

4.11.5.2 ø200 mm nos. 236.00 44,627.58 15,581.46 9,230.31 69,439.35 16,387,686.60


4.11.5.3 ø250 mm nos. 236.00 51,128.58 18,290.21 10,855.56 80,274.35 18,944,746.60
4.11.5.4 ø300 mm nos. 118.00 55,471.38 20,099.71 11,941.26 87,512.35 10,326,457.30

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.2.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.11.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.11.6.A.1.1 ø200 mm nos. 100.00 11,079.12 3,235.25 433.10 14,747.46 1,474,746.00


4.11.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.11.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.11.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.11.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.11.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.11.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.11.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.11.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 153 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.11.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.11.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.11.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.11.6.A.2.1 ø200 mm nos. 14.00 11,079.12 3,614.08 439.51 15,132.71 211,857.94


4.11.6.A.2.2 ø250 mm nos. 9.00 11,597.22 3,810.28 460.57 15,868.07 142,812.63
4.11.6.A.2.3 ø300 mm nos. 1.00 12,111.88 4,007.30 481.54 16,600.72 16,600.72
4.11.6.A.2.4 ø350 mm nos. 4.00 12,575.47 4,195.03 500.60 17,271.10 69,084.40
4.11.6.A.2.5 ø400 mm nos. 3.00 13,090.13 4,395.42 521.95 18,007.50 54,022.50
4.11.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.11.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.11.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.11.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.11.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.11.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.11.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.11.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.11.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.11.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.11.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.11.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.11.6.A.3.5 ø400 mm nos. 2.00 13,090.13 5,350.74 538.14 18,979.00 37,958.00
4.11.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 154 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Road Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment Cutting (BDT)
Price
Fees
a b c d e f g h i = e+f+g+h j=dxi

4.11.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -


4.11.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.11.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.11.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.11.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.11.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.11: Column 'j' to be carried forward to


. 258,670,999.20
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 155 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.12 INSTALLATION of LOOP 211
4.12.1 Miscellaneous works during implementation
4.12.1.1 Setting-out LS 1.00 171,126.00 171,126.00
4.12.1.2 General works and site tests LS 1.00 342,252.00 342,252.00
4.12.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.12.2.1 LS 1.00 342,252.00 342,252.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.12.2.2 LS 1.00 128,344.50 128,344.50
construction completed & acceptance certificate
4.12.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.12.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.12.2.5 Development and submission of GIS based As-built drawings LS 1.00 213,907.50 213,907.50
4.12.2.6 Post Construction modelling LS 1.00 25,668.90 25,668.90

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing
4.12.3 of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse material s/ khoa filling,
concreting as per approved drawing and specification.

4.12.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.12.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.12.3.A.1.1 ø200 mm m 3,923.70 3,596.40 1,581.32 878.18 5,811.99 11,867.89 46,566,035.84


4.12.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 156 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -


4.12.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.12.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.12.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.12.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.12.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.12.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.12.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.12.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.12.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.12.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.12.3.A.2.1 ø200 mm m 3,776 3,890.84 1,719.29 901.27 5,811.99 12,323.40 46,533,141.82


4.12.3.A.2.2 ø250 mm m 241 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 3,293,879.10
4.12.3.A.2.3 ø300 mm m 54 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 795,126.94
4.12.3.A.2.4 ø350 mm m 146 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 2,208,530.16
4.12.3.A.2.5 ø400 mm m 39 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 699,274.88
4.12.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.12.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.12.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.12.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.12.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.12.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.12.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 157 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.12.3.A.3.1 ø200 mm m 180 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 4,779,594.06


4.12.3.A.3.2 ø250 mm m 57 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 1,590,178.01
4.12.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.12.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.12.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.12.3.A.3.6 ø450 mm m 98 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 3,228,441.96
4.12.3.A.3.7 ø500 mm m 41 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 1,516,377.19
4.12.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.12.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.12.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.12.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.12.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.12.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.12.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.12.3.B.1.1 ø200 mm m -
4.12.3.B.1.2 ø250 mm m -
4.12.3.B.1.3 ø300 mm m -
4.12.3.B.1.4 ø350 mm m -
4.12.3.B.1.5 ø400 mm m -
4.12.3.B.1.6 ø450 mm m -
4.12.3.B.1.7 ø500 mm m -
4.12.3.B.1.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 158 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.3.B.1.9 ø700 mm m -
4.12.3.B.1.10 ø800 mm m -
4.12.3.B.1.11 ø900 mm m -
4.12.3.B.1.12 ø1000 mm m -

4.12.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.12.3.B.2.1 ø200 mm m -
4.12.3.B.2.2 ø250 mm m -
4.12.3.B.2.3 ø300 mm m -
4.12.3.B.2.4 ø350 mm m -
4.12.3.B.2.5 ø400 mm m -
4.12.3.B.2.6 ø450 mm m -
4.12.3.B.2.7 ø500 mm m -
4.12.3.B.2.8 ø600 mm m -
4.12.3.B.2.9 ø700 mm m -
4.12.3.B.2.10 ø800 mm m -

4.12.3.B.2.11 ø900 mm m -

4.12.3.B.2.12 ø1000 mm m -

4.12.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.12.3.B.3.1 ø200 mm m -
4.12.3.B.3.2 ø250 mm m -
4.12.3.B.3.3 ø300 mm m -
4.12.3.B.3.4 ø350 mm m -
4.12.3.B.3.5 ø400 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 159 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.3.B.3.6 ø450 mm m -
4.12.3.B.3.7 ø500 mm m -
4.12.3.B.3.8 ø600 mm m -
4.12.3.B.3.9 ø700 mm m -
4.12.3.B.3.10 ø800 mm m -

4.12.3.B.3.11 ø900 mm m -

4.12.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary
4.12.4
road reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per
approved drawing and specification.

4.12.4.A Normal Manhole Rectangular or circular

4.12.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.12.4.A.1.1 ø200 mm nos. 100.00 108,465.00 17,845.00 10,137.00 136,447.00 13,644,700.00


4.12.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.12.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.12.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.12.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.12.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.12.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 160 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -


4.12.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.12.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.12.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.12.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.12.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.12.4.A.2.1 ø200 mm nos. 74 133,076.00 22,507.00 12,324.00 167,907.00 12,425,118.00


4.12.4.A.2.2 ø250 mm nos. 7 133,713.00 22,520.00 12,338.00 168,571.00 1,179,997.00
4.12.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.12.4.A.2.4 ø350 mm nos. 3 134,923.00 22,534.00 12,363.00 169,820.00 509,460.00
4.12.4.A.2.5 ø400 mm nos. 1 135,559.00 22,547.00 12,377.00 170,483.00 170,483.00
4.12.4.A.2.6 ø450 mm nos. 1 136,195.00 22,560.00 12,391.00 171,146.00 171,146.00
4.12.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.12.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.12.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.12.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.12.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.12.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.12.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.12.4.A.3.1 ø200 mm nos. 3 182,295 31,825 16,700 230,820.00 692,460.00


4.12.4.A.3.2 ø250 mm nos. 1 182,932 31,838 16,713 231,483.00 231,483.00
4.12.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.12.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 161 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -


4.12.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.12.4.A.3.7 ø500 mm nos. 1 185,988 31,881 16,777 234,646.00 234,646.00
4.12.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.12.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.12.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.12.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.12.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.12.4.B Drop Manhole Rectangular or circular

4.12.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.12.4.B.1.1 ø200 mm nos. 3.00 177,870.00 34,380.00 19,812.00 232,062.00 696,186.00


4.12.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.12.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.12.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.12.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.12.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.12.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.12.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.12.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.12.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.12.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.12.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.12.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 162 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.B.2.1 ø200 mm nos. 2 216,110.00 42,604.00 23,944.00 282,658.00 565,316.00


4.12.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.12.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.12.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.12.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.12.4.B.2.6 ø450 mm nos. 1 218,444.00 42,712.00 24,076.00 285,232.00 285,232.00
4.12.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.12.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.12.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.12.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.12.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.12.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.12.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.12.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.12.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.12.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.12.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.12.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.12.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.12.4.B.3.7 ø500 mm nos. 1 295,284.00 59,156.00 32,362.00 386,802.00 386,802.00
4.12.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.12.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.12.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 163 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.12.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.12.4.C Service connections Manhole Rectangular or circular -

4.12.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.12.4.C.1.1 ø200 mm nos. 218.00 108,465.00 17,845.00 10,137.00 136,447.00 29,745,446.00


4.12.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.12.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.12.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.12.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.12.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.12.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.12.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.12.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.12.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.12.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.12.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.12.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.12.4.C.2.1 ø200 mm nos. 210 133,076.00 22,507.00 12,324.00 167,907.00 35,260,470.00


4.12.4.C.2.2 ø250 mm nos. 14 133,713.00 22,520.00 12,338.00 168,571.00 2,359,994.00
4.12.4.C.2.3 ø300 mm nos. 4 134,286.00 22,521.00 12,350.00 169,157.00 676,628.00
4.12.4.C.2.4 ø350 mm nos. 9 134,923.00 22,534.00 12,363.00 169,820.00 1,528,380.00
4.12.4.C.2.5 ø400 mm nos. 3 135,559.00 22,547.00 12,377.00 170,483.00 511,449.00
4.12.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 164 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -


4.12.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.12.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.12.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.12.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.12.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.12.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.12.4.C.3.1 ø200 mm nos. 11 182,295.00 31,825.00 16,700.00 230,820.00 2,539,020.00


4.12.4.C.3.2 ø250 mm nos. 4 182,932.00 31,838.00 16,713.00 231,483.00 925,932.00
4.12.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.12.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.12.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.12.4.C.3.6 ø450 mm nos. 6 185,414.00 31,879.00 16,766.00 234,059.00 1,404,354.00
4.12.4.C.3.7 ø500 mm nos. 3 185,988.00 31,881.00 16,777.00 234,646.00 703,938.00
4.12.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.12.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.12.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.12.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.12.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 165 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures,
4.12.5 site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection
pit, average length of 10m as per approved drawing and
specification.

4.12.5.1 ø150 mm nos. 714.00 40,766.88 13,972.83 8,265.14 63,004.85 44,985,462.90

4.12.5.2 ø200 mm nos. 285.00 44,627.58 15,581.46 9,230.31 69,439.35 19,790,214.75


4.12.5.3 ø250 mm nos. 285.00 51,128.58 18,290.21 10,855.56 80,274.35 22,878,189.75
4.12.5.4 ø300 mm nos. 143.00 55,471.38 20,099.71 11,941.26 87,512.35 12,514,266.05

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.12.6 existing structures, site cleaning, earth cutting, sand filling, earth -
refilling , coarse material s/ khoa filling, as per approved drawing
and specification.

4.12.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.12.6.A.1.1 ø200 mm nos. 73.00 11,079.12 3,235.25 433.10 14,747.46 1,076,564.58


4.12.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.12.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.12.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.12.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.12.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.12.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.12.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.12.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 166 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.12.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.12.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.12.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.12.6.A.2.1 ø200 mm nos. 70.00 11,079.12 3,614.08 439.51 15,132.71 1,059,289.70


4.12.6.A.2.2 ø250 mm nos. 5.00 11,597.22 3,810.28 460.57 15,868.07 79,340.35
4.12.6.A.2.3 ø300 mm nos. 1.00 12,111.88 4,007.30 481.54 16,600.72 16,600.72
4.12.6.A.2.4 ø350 mm nos. 3.00 12,575.47 4,195.03 500.60 17,271.10 51,813.30
4.12.6.A.2.5 ø400 mm nos. 1.00 13,090.13 4,395.42 521.95 18,007.50 18,007.50
4.12.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.12.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.12.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.12.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.12.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.12.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.12.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.12.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.12.6.A.3.1 ø200 mm nos. 4.00 11,079.12 4,371.74 452.35 15,903.21 63,612.84


4.12.6.A.3.2 ø250 mm nos. 1.00 11,597.22 4,617.36 474.24 16,688.82 16,688.82
4.12.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.12.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.12.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.12.6.A.3.6 ø450 mm nos. 2.00 13,662.73 5,606.32 562.02 19,831.08 39,662.16
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 167 of 176
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.6.A.3.7 ø500 mm nos. 1.00 14,177.39 5,852.76 583.83 20,613.98 20,613.98


4.12.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.12.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.12.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.12.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.12.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.12: Column 'j' to be carried forward to


. 321,915,598.27
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 168 of 176
Schedule No. 5 - Grand Summary

Schedule No. Title


Total Price (BDT)

1 Schedule No. 1 - Pipe and Fittings Supplied from Abroad


2 Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
3 Schedule No. 3 - Design Services 213417899
4 Schedule No. 4 - Installation / Construction and Other works
4.1 Implementation Provisions and Preliminaries for all Loops 127179646
4.2 Installation/ Construction of all Loops (Schedule 4)
4.2.1 INSTALLATION of LOOP 201 48249904
4.2.2 INSTALLATION of LOOP 202 74239556
4.2.3 INSTALLATION of LOOP 203A 46383437
4.2.4 INSTALLATION of LOOP 203B 102000373
4.2.5 INSTALLATION of LOOP 204 147130741
4.2.6 INSTALLATION of LOOP 205 148719837
4.2.7 INSTALLATION of LOOP 206 154753511
4.2.8 INSTALLATION of LOOP 207 403078199
4.2.9 INSTALLATION of LOOP 208 542116097
4.2.10 INSTALLATION of LOOP 209 191803447
4.2.11 INSTALLATION of LOOP 210 258670999
4.2.12 INSTALLATION of LOOP 211 321915598
Sub total 4.2: Installation/ Construction of all Loops (Schedule 4) 2439061700
5 Provisional Sum
5.1 Provisional sum for Physical Contingencies 121953085
5.2 Provisional Sum for Price Contingencies 117749548
5.3 Provisional Sum for alleviations program, refer to SCC, Sub-Clause xxxxxx 6968748
Sub-Total 5: Provisional Sum 246671380
6 Recommended spare parts 38664764
7 Day work 14046204
8 O&M - 60946346
. Grand Total (1+3+4.1+4.2+5+6+7+8) to be carried forward to Letter of Bid 3139987939

Name of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 169 of 176
Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 170 of 176
Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh

Recommended Spare Parts


6.1 GRP Sewer Pipe (Dia in mm)
6.1.1 160 meter 250.00 1,770.40 1,770.40 442,600.00
6.1.2 200 meter 250.00 2,213.00 2,213.00 553,250.00
6.1.3 250 meter 250.00 2,923.00 2,923.00 730,750.00
6.1.4 300 meter 250.00 3,315.00 3,315.00 828,750.00
6.1.5 350 meter 300.00 4,292.00 4,292.00 1,287,600.00
6.1.6 400 meter 300.00 5,043.00 5,043.00 1,512,900.00
6.1.7 500 meter 300.00 7,807.00 7,807.00 2,342,100.00
6.1.8 600 meter 200.00 10,104.00 10,104.00 2,020,800.00
6.1.9 700 meter 200.00 15,281.00 15,281.00 3,056,200.00
6.1.10 800 meter 200.00 18,120.00 18,120.00 3,624,000.00
6.1.11 900 meter 200.00 16,711.99 16,711.99 3,342,397.33
6.1.12 1000 meter 200.00 18,462.01 18,462.01 3,692,402.67
6.2 Coupler/Coller
6.2.1 160 Pcs. 50.00 2,655.60 2,655.60 132,780.00
6.2.2 200 Pcs. 50.00 3,319.50 3,319.50 165,975.00
6.2.3 250 Pcs. 50.00 4,384.50 4,384.50 219,225.00
6.2.4 300 Pcs. 50.00 4,972.50 4,972.50 248,625.00
6.2.5 350 Pcs. 50.00 6,438.00 6,438.00 321,900.00
6.2.6 400 Pcs. 50.00 7,564.50 7,564.50 378,225.00
6.2.7 500 Pcs. 50.00 11,710.50 11,710.50 585,525.00
6.2.8 600 Pcs. 50.00 15,156.00 15,156.00 757,800.00
6.2.9 700 Pcs. 50.00 22,921.50 22,921.50 1,146,075.00
6.2.10 800 Pcs. 50.00 27,180.00 27,180.00 1,359,000.00
6.2.11 900 Pcs. 50.00 25,067.98 25,067.98 1,253,399.00
6.2.12 1000 Pcs. 50.00 27,693.02 27,693.02 1,384,651.00
6.3 Flange Adapter
6.3.1 160 Pcs. 20.00 885.20 885.20 17,704.00
6.3.2 200 Pcs. 20.00 1,106.50 1,106.50 22,130.00
6.3.3 250 Pcs. 20.00 1,461.50 1,461.50 29,230.00
6.3.4 300 Pcs. 20.00 1,657.50 1,657.50 33,150.00
6.3.5 350 Pcs. 20.00 2,146.00 2,146.00 42,920.00
6.3.6 400 Pcs. 20.00 2,521.50 2,521.50 50,430.00
6.3.7 500 Pcs. 20.00 3,903.50 3,903.50 78,070.00
6.3.8 600 Pcs. 20.00 5,052.00 5,052.00 101,040.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 171 of 176
Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh
6.3.9 700 Pcs. 20.00 7,640.50 7,640.50 152,810.00
6.3.10 800 Pcs. 20.00 9,060.00 9,060.00 181,200.00
6.3.11 900 Pcs. 20.00 8,355.99 8,355.99 167,119.87
6.3.12 1000 Pcs. 20.00 9,231.01 9,231.01 184,620.13
6.4 Tee/Wye
6.4.1 160 Pcs. 20.00 2,655.60 2,655.60 53,112.00
6.4.2 200 Pcs. 20.00 3,319.50 3,319.50 66,390.00
6.4.3 250 Pcs. 20.00 4,384.50 4,384.50 87,690.00
6.4.4 300 Pcs. 20.00 4,972.50 4,972.50 99,450.00
6.4.5 350 Pcs. 20.00 6,438.00 6,438.00 128,760.00
6.4.6 400 Pcs. 20.00 10,086.00 10,086.00 201,720.00
6.4.7 500 Pcs. 20.00 15,614.00 15,614.00 312,280.00
6.4.8 600 Pcs. 20.00 20,208.00 20,208.00 404,160.00
6.4.9 700 Pcs. 20.00 30,562.00 30,562.00 611,240.00
6.4.10 800 Pcs. 20.00 36,240.00 36,240.00 724,800.00
6.4.11 900 Pcs. 20.00 33,423.97 33,423.97 668,479.47
6.4.12 1000 Pcs. 20.00 36,924.03 36,924.03 738,480.53
6.5 Elbow (30/60/90 degrees)
6.5.1 160 Pcs. 20.00 1,770.40 1,770.40 35,408.00
6.5.2 200 Pcs. 20.00 2,213.00 2,213.00 44,260.00
6.5.3 250 Pcs. 20.00 2,923.00 2,923.00 58,460.00
6.5.4 300 Pcs. 20.00 3,315.00 3,315.00 66,300.00
6.5.5 350 Pcs. 20.00 4,292.00 4,292.00 85,840.00
6.5.6 400 Pcs. 20.00 5,043.00 5,043.00 100,860.00
6.5.7 500 Pcs. 20.00 7,807.00 7,807.00 156,140.00
6.5.8 600 Pcs. 20.00 10,104.00 10,104.00 202,080.00
6.5.9 700 Pcs. 20.00 15,281.00 15,281.00 305,620.00
6.5.10 800 Pcs. 20.00 18,120.00 18,120.00 362,400.00
6.5.11 900 Pcs. 20.00 16,711.99 16,711.99 334,239.73
6.5.12 1000 Pcs. 20.00 18,462.01 18,462.01 369,240.27
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 38,664,764.00

Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 172 of 176
Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.1 Equipment
7.1.1 Micro Tunneling Machine with complete set hrs. 240 6,000.00 6,000.00 1,440,000.00
7.1.2 Hydraulic HDD Unit hrs. 144 4,000.00 4,000.00 576,000.00
7.1.3 Excavator, face shovel, or dragline: -
7.1.3.1 Up to and including 1 m3 hrs. 144 2,000.00 2,000.00 288,000.00
7.1.3.2 Over 1 m3 to 2 m3 hrs. 180 3,000.00 3,000.00 540,000.00
7.1.3.3 Over 2 m3 hrs. 120 3,510.00 3,510.00 421,200.00
7.1.4 Tractor, including bull or angle dozer: -
7.1.4.1 Up to and including 150 kW hrs. 200 1,000.00 1,000.00 200,000.00
7.1.4.2 Over 150 kW to 200 kW hrs. 200 1,500.00 1,500.00 300,000.00
7.1.4.3 Over 200 kW to 250 kW hrs. 200 2,000.00 2,000.00 400,000.00
7.1.5 Tractor with ripper: -
7.1.5.1 Up to and including 200 kW hrs. 200 1,500.00 1,500.00 300,000.00
7.1.5.2 Over 200 kW to 250 kW hrs. 200 2,000.00 2,000.00 400,000.00
7.1.6 Portable concrete mixer - 0.4m3 hrs. 300 500.00 500.00 150,000.00
7.1.7 Hydraulic Excavator – 1 m3 hrs. 200 3,000.00 3,000.00 600,000.00
7.1.8 4-tool compressor including tools and hoses hrs. 200 2,000.00 2,000.00 400,000.00
7.1.9 10 tonne lorry-mounted crane hrs. 200 5,000.00 5,000.00 1,000,000.00
7.1.10 750 Kg crane hrs. 200 2,000.00 2,000.00 400,000.00
7.1.11 0.5 m3 dumper hrs. 200 1,000.00 1,000.00 200,000.00
7.1.12 1 m3 dumper hrs. 200 1,500.00 1,500.00 300,000.00
7.1.13 7 m3 tipper lorry hrs. 200 2,000.00 2,000.00 400,000.00
7.1.14 15 m3 lorry hrs. 200 2,000.00 2,000.00 400,000.00
7.1.15 4 wheel drive pick-up or van hrs. 200 500.00 500.00 100,000.00
7.1.16 Vibrating plate compactor hrs. 200 500.00 500.00 100,000.00
7.1.17 8-10 tonne roller hrs. 200 2,000.00 2,000.00 400,000.00
7.1.18 Scaffolding, 10 sqm day 36 2,025.00 2,025.00 72,900.00
7.1.19 5-Ton capacity truck-fare in Dhaka city i/c loading, unloading hrs. 300 456.50 456.50 136,950.00
7.1.20 Concrete mixer machine -1 bag capacity hrs. 168 537.50 537.50 90,300.00
7.1.21 Concrete vibrator-40mm dia hrs. 168 423.00 423.00 71,064.00
7.1.22 Diesel operated 1 cusec pump hrs. 288 505.00 505.00 145,440.00
7.1.23 Electricity operated 1 cusec pump hrs. 240 329.00 329.00 78,960.00
7.1.24 Road cutting Equipment hrs. 240 1,097.00 1,097.00 263,280.00
7.1.25 Backhoe Loader, wheel operated hrs. 144 3,510.00 3,510.00 505,440.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 173 of 176
Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh

7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 100 675.00 675.00 67,500.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 100 607.50 607.50 60,750.00
clinker): 50kg bag
7.2.3 White Cement kg 250 54.00 54.00 13,500.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 1 86,400.00 86,400.00 86,400.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 1 87,750.00 87,750.00 87,750.00
7.2.6 MS Sheet M Ton 1 114,750.00 114,750.00 57,375.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 5,000 10,800.00 10,800.00 54,000.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 5,000 12,150.00 12,150.00 60,750.00
7.2.9 Imported Earth m3 100 572.50 572.50 57,250.00
7.2.10 Sand (F.M. 0.8) m3 100 525.00 525.00 52,500.00
7.2.11 Sand (F.M. 1.2) m3 50 810.50 810.50 40,525.00
7.2.12 Sand (F.M. 2.5) m3 50 2,384.00 2,384.00 119,200.00
7.2.13 Viti/Filling Sand m3 100 524.50 524.50 52,450.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 174 of 176
Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.3 Labor
-
7.3.1 Contract Manager day 36 15,000.00 15,000.00 540,000.00
7.3.2 Office Assistant day 72 500.00 500.00 36,000.00
7.3.3 Contract / Legal Advisor day 24 5,000.00 5,000.00 120,000.00
7.3.4 Financial Advisor day 24 5,000.00 5,000.00 120,000.00
7.3.5 Quantity Engineer day 36 3,000.00 3,000.00 108,000.00
7.3.6 Designer day 24 10,000.00 10,000.00 240,000.00
7.3.7 Field Engineer day 36 3,000.00 3,000.00 108,000.00
7.3.8 Draft Person day 24 2,000.00 2,000.00 48,000.00
7.3.9 Ordinary/casual Labour day 240 600.00 600.00 144,000.00
7.3.10 Skilled labour day 120 945.00 945.00 113,400.00
7.3.11 Head Operator/Ganger day 36 1,080.00 1,080.00 38,880.00
7.3.12 Asstt. Operator/Ganger day 72 945.00 945.00 68,040.00
7.3.13 Head Mason day 36 1,080.00 1,080.00 38,880.00
7.3.14 Mud Operator day 36 945.00 945.00 34,020.00
7.3.15 Field Supervisor/Manager day 36 3,375.00 3,375.00 121,500.00
7.3.16 Field/Maintenance Engineer day 72 2,700.00 2,700.00 194,400.00
7.3.17 Skilled technician/Plumber/Mason/Steel work Erector/ day 72 800.00 800.00 57,600.00
7.3.18 Semi Skilled technician day 120 700.00 700.00 84,000.00
7.3.19 Site security day 48 600.00 600.00 28,800.00
7.3.20 Driver day 72 1,100.00 1,100.00 79,200.00
7.3.21 Sweeper for Odd Job day 72 1,000.00 1,000.00 72,000.00
7.3.22 Surveyor day 60 1,080.00 1,080.00 64,800.00
7.3.23 Asstt. Surveyor day 120 810.00 810.00 97,200.00
7.3.24 Carpenter

Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 14,046,204.00

Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 175 of 176
Schedule No. 8 - O&M Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price
a b c d e f g h=e+f+g i=dxh
8 O&M Services and Documentation

8.1 One year O&M (12 Loops in Segment 6)


8.1.1 O&M Services in Loop 201 km 1.39 934,330.00 1,298,718.70
8.1.2 O&M Services in Loop 202 km 2.06 934,330.00 1,924,719.80
8.1.3 O&M Services in Loop 203A km 1.33 934,330.00 1,242,658.90
8.1.4 O&M Services in Loop 203B km 2.77 934,330.00 2,588,094.10
8.1.5 O&M Services in Loop 204 km 3.96 934,330.00 3,699,946.80
8.1.6 O&M Services in Loop 205 km 4.08 934,330.00 3,812,066.40
8.1.7 O&M Services in Loop 206 km 4.20 934,330.00 3,924,186.00
8.1.8 O&M Services in Loop 207 km 10.35 934,330.00 9,670,315.50
8.1.9 O&M Services in Loop 208 km 14.17 934,330.00 13,239,456.10
8.1.10 O&M Services in Loop 209 km 5.30 934,330.00 4,951,949.00
8.1.11 O&M Services in Loop 210 km 7.06 934,330.00 6,596,369.80
8.1.12 O&M Services in Loop 211 km 8.56 934,330.00 7,997,864.80
65.23
Sub-total 8.1: Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 60,946,345.90

Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 176 of 176
Employer’s Cost Estimates6

E: Cost of Package 3 (Segment 7 to 12)


Schedule No. 1 - Pipe and Fittings Supplied from Abroad

Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 140,169.40
1.1.2 ø250 mm m 7,564.20
1.1.3 ø300 mm m 4,851.90
1.1.4 ø350 mm m 4,182.20
1.1.5 ø400 mm m 3,142.20
1.1.6 ø450 mm m 173.90
1.1.7 ø500 mm m 3,882.10
1.1.8 ø600 mm m 4,263.80
1.1.9 ø700 mm m 3,847.20
1.1.10 ø800 mm m 742.30
1.1.11 ø900 mm m 580.20
1.1.12 ø1000 mm m 451.20
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 280
1.2.2 ø250 mm nos. 15
1.2.3 ø300 mm nos. 10
1.2.4 ø350 mm nos. 8
1.2.5 ø400 mm nos. 6
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 9
1.2.8 ø600 mm nos. 9
1.2.9 ø700 mm nos. 9

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 1 of 199
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.10 ø800 mm nos. 1
1.2.11 ø900 mm nos. 1
1.2.12 ø1000 mm nos. 1
1.3 Equal and Un Equal Tee of different sizes
1.3.1 200mm x200mm nos. 280
1.3.2 250mm x250mm nos. 15
1.3.3 300mm X 300mm nos. 10
1.3.4 350mm X 350mm nos. 8
1.3.5 400mm X 400mm nos. 6
1.3.6 450mm X 450mm nos.
1.3.7 500mm X 500mm nos. 9
1.3.8 600 mm X 600mm nos. 9
1.3.9 700mm X 700mm nos. 9
1.3.10 800mm x 800mm nos. 1
1.3.11 900mm X 900mm nos. 1
1.3.12 1000mm X 1000mm nos. 1
1.3.13 250mm X250mm X 200mm nos. 15
1.3.14 300mm X 300mm X 200mm nos. 10
1.3.15 300mm X 300mm X 250mm nos. 10
1.3.16 400mm X 400mm X 200mm nos. 6
1.3.17 400mm X 400mm X 250mm nos. 6
1.3.18 400mm X 400mm X 300mm nos. 6
1.3.19 500mm X 500mm X 200mm nos. 9
1.3.20 500mm X 500mm X 300mm nos. 9

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 2 of 199
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos. 560
1.4.2 ø250 mm nos. 30
1.4.3 ø300 mm nos. 20
1.4.4 ø350 mm nos. 16
1.4.5 ø400 mm nos. 12
1.4.6 ø450 mm nos.
1.4.7 ø500 mm nos. 18
1.4.8 ø600 mm nos. 18
1.4.9 ø700 mm nos. 18
1.4.10 ø800 mm nos. 2
1.4.11 ø900 mm nos. 2
1.4.12 ø1000 mm nos. 2
1.5 Flanged Adapters
1.5.1 ø200 mm nos. 70
1.5.2 ø250 mm nos. 4
1.5.3 ø300 mm nos. 3
1.5.4 ø350 mm nos. 2
1.5.5 ø400 mm nos. 2
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos. 3
1.5.8 ø600 mm nos. 3
1.5.9 ø700 mm nos. 3
1.5.10 ø800 mm nos.

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 3 of 199
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.5.11 ø900 mm nos.
1.5.12 ø1000 mm nos.

Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 4 of 199
Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country

Unit Price (BDT)


Total Price Sales and other
Item Description Unit Qty. Total Unit
Material Labour Equipment (BDT) taxes (BDT)
Price (EXW)
a b c d e f g h=e+f+g i=dxh j

Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 5 of 199
Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

3.1 Design / Survey Provisions and Preliminaries


3.1.1 Insurances
3.1.1.1 For design (professional indemnity insurance) LS 1 36,661,491.48 36,661,491.48
3.1.1.2 Other Insurances (to be specified by the Tenderer) LS 1 18,330,746 18,330,745.74
Sub-total A: 54,992,237.21
3.2 Design Services (including design office and establishment)

3.2.1 Loop 301


3.2.1.1 Survey and documentation, including Survey Report LS 1 17,111,220 17,111,219.59
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.1.2 LS 1 10,456,856 10,456,856.42
Design Report
3.2.1.3 Design Control Services including documentation LS 1 2,851,870 2,851,869.93

3.2.2 Loop 302


3.2.2.1 Survey and documentation, including Survey Report LS 1 11,174,801 11,174,801.13
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.2.2 LS 1 6,829,045 6,829,045.14
Design Report
3.2.2.3 Design Control Services including documentation LS 1 1,862,467 1,862,466.86

3.2.3 Loop 303


3.2.3.1 Survey and documentation, including Survey Report LS 1 17,099,605 17,099,605.26

Detailed designs, Specifications and documentation, including Quality Assurance and


3.2.3.2 LS 1 10,449,759 10,449,758.77
Design Report
3.2.3.3 Design Control Services including documentation LS 1 2,849,934 2,849,934.21

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 6 of 199
Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

3.2.4 Loop 304


3.2.4.1 Survey and documentation, including Survey Report LS 1 7,853,349 7,853,349.40
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.4.2 LS 1 4,799,269 4,799,269.08
Design Report
3.2.4.3 Design Control Services including documentation LS 1 1,308,892 1,308,891.57

3.2.5 Loop 305


3.2.5.1 Survey and documentation, including Survey Report LS 1 12,120,952 12,120,952.28
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.5.2 LS 1 7,407,249 7,407,248.61
Design Report
3.2.5.3 Design Control Services including documentation LS 1 2,020,159 2,020,158.71

3.2.6 Loop 306


3.2.6.1 Survey and documentation, including Survey Report LS 1 8,988,245 8,988,244.79
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.6.2 LS 1 5,492,816 5,492,816.26
Design Report
3.2.6.3 Design Control Services including documentation LS 1 1,498,041 1,498,040.80

3.2.7 Loop 307


3.2.7.1 Survey and documentation, including Survey Report LS 1 35,153,681 35,153,681.12
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.7.2 LS 1 21,482,805 21,482,805.13
Design Report
3.2.7.3 Design Control Services including documentation LS 1 5,858,947 5,858,946.85

3.2.8 Loop 308


3.2.8.1 Survey and documentation, including Survey Report LS 1 5,869,055 5,869,055.11
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.8.2 LS 1 3,586,645 3,586,644.79
Design Report

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 7 of 199
Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

3.2.8.3 Design Control Services including documentation LS 1 978,176 978,175.85

3.2.9 Loop 309


3.2.9.1 Survey and documentation, including Survey Report LS 1 20,609,023 20,609,022.81
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.9.2 LS 1 12,594,403 12,594,402.83
Design Report
3.2.9.3 Design Control Services including documentation LS 1 3,434,837 3,434,837.13

3.2.10 Loop 310


3.2.10.1 Survey and documentation, including Survey Report LS 1 32,957,759 32,957,758.96
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.10.2 LS 1 20,140,853 20,140,852.70
Design Report
3.2.10.3 Design Control Services including documentation LS 1 5,492,960 5,492,959.83

3.2.11 Loop 311


3.2.11.1 Survey and documentation, including Survey Report LS 1 32,594,560 32,594,560.33
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.11.2 LS 1 19,918,898 19,918,897.98
Design Report
3.2.11.3 Design Control Services including documentation LS 1 5,432,427 5,432,426.72

3.2.12 Loop 312


3.2.12.1 Survey and documentation, including Survey Report LS 1 42,408,328 42,408,327.65

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 8 of 199
Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

Detailed designs, Specifications and documentation, including Quality Assurance and


3.2.12.2 LS 1 25,916,200 25,916,200.23
Design Report
3.2.12.3 Design Control Services including documentation LS 1 7,068,055 7,068,054.61

3.2.13 Loop 313


3.2.13.1 Survey and documentation, including Survey Report LS 1 62,914,656 62,914,656.31
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.13.2 LS 1 38,447,846 38,447,845.52
Design Report
3.2.13.3 Design Control Services including documentation LS 1 10,485,776 10,485,776.05

3.2.14 Loop 314


3.2.14.1 Survey and documentation, including Survey Report LS 1 23,098,189 23,098,188.54
Detailed designs, Specifications and documentation, including Quality Assurance and
3.2.14.2 LS 1 14,115,560 14,115,559.67
Design Report
3.2.14.3 Design Control Services including documentation LS 1 3,849,698 3,849,698.09

Sub-total B: 586,583,863.61
Total A+B: Sub-total 3:
641,576,100.82
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary

Name of Bidder:

Signature of Bidder:

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 9 of 199
Schedule No. 4 - Installation / Construction and Other works

Unit Price (BDT)


Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment (BDT)
Price

a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 18,330,745.74 18,330,745.74
4.1.1.2 Advance Payment Guarantee LS 1 18,330,745.74 18,330,745.74
Subtotal 4.1.1 36,661,491.48
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.2 Installation All Risks Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.3 Third Party Liability Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.4 Automobile Liability Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.5 Workers' Compensation LS 1 27,496,118.61 27,496,118.61
4.1.2.6 Employer's Liability LS 1 27,496,118.61 27,496,118.61
4.1.2.7 Contractor's Equipment Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 27,496,118.61 27,496,118.61
Subtotal 4.1.2 219,968,948.86
4.1.3 Site establishment, operation and removal

Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 20,949,423.70 20,949,423.70
workshops, site access and miscellaneous services etc.

Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 20,949,423.70 20,949,423.70
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 20,949,423.70 20,949,423.70
4.1.3.4 Survey instruments LS 1 20,949,423.70 20,949,423.70
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 20,949,423.70 20,949,423.70
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 10 of 199
Schedule No. 4 - Installation / Construction and Other works

Unit Price (BDT)


Total Price
Item Description Unit Qty. Total Unit
Material Labour Equipment (BDT)
Price

a b c d e f g h=e+f+g i=dxh
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 20,949,423.70 20,949,423.70
Subtotal 4.1.3 125,696,542.20
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 382,326,982.54

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 11 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.2 INSTALLATION of LOOP 301
4.2.1 Miscellaneous works during implementation
4.2.1.1 Setting-out LS 1.00 181,494.00 181,494.00
4.2.1.2 General works and site tests LS 1.00 362,988.00 362,988.00
4.2.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.2.2.1 LS 1.00 362,988.00 362,988.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.2.2.2 LS 1.00 136,120.50 136,120.50
construction completed & acceptance certificate
4.2.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

4.2.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00

4.2.2.5 Development and submission of GIS based As-built drawings LS 1.00 226,867.50 226,867.50
4.2.2.6 Post Construction modelling LS 1.00 27,224.10 27,224.10

Supply and Installation of GRP pipes in accordance with the technical


specification and the standard detail drawing, of any diameter and to
the depths specified below, including fitting, fixing of all items, road
4.2.3 cutting permission fee, temporary road reinstatement, dismantling of -
existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.2.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.2.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.3.A.1.1 ø200 mm m 3,288.50 3,596.40 1,581.32 878.18 5,811.99 11,867.89 39,027,552.79


4.2.3.A.1.2 ø250 mm m 41.50 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 549,303.20
4.2.3.A.1.3 ø300 mm m 94.60 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 1,342,522.04

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 12 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -


4.2.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.2.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.2.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.2.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.2.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.2.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.2.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.2.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.2.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.A.2.1 ø200 mm m 3,926.40 3,890.84 1,719.29 901.27 5,811.99 12,323.40 48,386,580.52


4.2.3.A.2.2 ø250 mm m 122.30 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 1,675,016.27
4.2.3.A.2.3 ø300 mm m 242.40 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 3,562,639.03
4.2.3.A.2.4 ø350 mm m 101.00 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 1,527,818.81
4.2.3.A.2.5 ø400 mm m 60.60 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 1,083,786.64
4.2.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.2.3.A.2.7 ø500 mm m 310.10 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 6,953,093.40
4.2.3.A.2.8 ø600 mm m 318.30 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 8,387,648.75
4.2.3.A.2.9 ø700 mm m 31.10 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 1,060,607.90
4.2.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.2.3.A.3 Pipe invert depth greater than 5m ( > 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 13 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.2.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.2.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.2.3.A.3.4 ø350 mm m 97.20 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 2,852,428.33
4.2.3.A.3.5 ø400 mm m 37.50 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 1,205,508.24
4.2.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.2.3.A.3.7 ø500 mm m 154.30 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 5,665,302.68
4.2.3.A.3.8 ø600 mm m 133.70 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 5,438,451.67
4.2.3.A.3.9 ø700 mm m 115.20 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 5,585,382.70
4.2.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.2.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.2.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.2.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.2.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.2.3.B.1.1 ø200 mm m -
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 14 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -

4.2.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -

4.2.3.B.2.11 ø900 mm m -

4.2.3.B.2.12 ø1000 mm m -

4.2.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 15 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -

4.2.3.B.3.11 ø900 mm m -

4.2.3.B.3.12 ø1000 mm m -
Supply and Installation of RCC Manholes chambers in accordance
with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.2.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.
4.2.4.A Normal Manhole Rectangular or circular

4.2.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.2.4.A.1.1 ø200 mm nos. 98.00 108,465.00 17,845.00 10,137.00 136,447.00 13,371,806.00


4.2.4.A.1.2 ø250 mm nos. 4.00 109,101.00 17,858.00 10,150.00 137,109.00 548,436.00
4.2.4.A.1.3 ø300 mm nos. 6.00 109,675.00 17,860.00 10,162.00 137,697.00 826,182.00
4.2.4.A.1.4 ø350 mm nos. 1.00 110,311.00 17,873.00 10,176.00 138,360.00 138,360.00
4.2.4.A.1.5 ø400 mm nos. 1.00 110,948.00 17,886.00 10,189.00 139,023.00 139,023.00
4.2.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.A.1.8 ø600 mm nos. 9.00 113,437.00 17,929.00 10,242.00 141,608.00 1,274,472.00
4.2.4.A.1.9 ø700 mm nos. 11.00 114,647.00 17,944.00 10,267.00 142,858.00 1,571,438.00
4.2.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 16 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -


4.2.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.2.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.A.2.1 ø200 mm nos. 86 133,076.00 22,507.00 12,324.00 167,907.00 14,440,002.00


4.2.4.A.2.2 ø250 mm nos. 13 133,713.00 22,520.00 12,338.00 168,571.00 2,191,423.00
4.2.4.A.2.3 ø300 mm nos. 18 134,286.00 22,521.00 12,350.00 169,157.00 3,044,826.00
4.2.4.A.2.4 ø350 mm nos. 14 134,923.00 22,534.00 12,363.00 169,820.00 2,377,480.00
4.2.4.A.2.5 ø400 mm nos. 22 135,559.00 22,547.00 12,377.00 170,483.00 3,750,626.00
4.2.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.A.2.7 ø500 mm nos. 1 136,776.00 22,565.00 12,402.00 171,743.00 171,743.00
4.2.4.A.2.8 ø600 mm nos. 2 138,048.00 22,591.00 12,430.00 173,069.00 346,138.00
4.2.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.2.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.2.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.2.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.A.3.1 ø200 mm nos. 5 182,295 31,825 16,700 230,820.00 1,154,100.00


4.2.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.2.4.A.3.3 ø300 mm nos. 2 183,505 31,840 16,725 232,070.00 464,140.00
4.2.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.2.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.2.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.2.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 17 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.3.8 ø600 mm nos. 5 187,267 31,910 16,805 235,982.00 1,179,910.00


4.2.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.2.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.2.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.2.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.2.4.B Drop Manhole Rectangular or circular

4.2.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.2.4.B.1.1 ø200 mm nos. 19.00 177,870.00 34,380.00 19,812.00 232,062.00 4,409,178.00


4.2.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.2.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.2.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.2.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.2.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.2.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.2.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.2.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.2.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.2.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.2.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.2.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.B.2.1 ø200 mm nos. 6 216,110.00 42,604.00 23,944.00 282,658.00 1,695,948.00


4.2.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.2.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 18 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -


4.2.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.2.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.2.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.2.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.2.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.2.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.2.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.2.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.2.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.2.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.2.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.2.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.2.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.2.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.2.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.2.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.2.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.2.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.2.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.2.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.2.4.C Service connections Manhole Rectangular or circular -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 19 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.2.4.C.1.1 ø200 mm nos. 183.00 108,465.00 17,845.00 10,137.00 136,447.00 24,969,801.00


4.2.4.C.1.2 ø250 mm nos. 3.00 109,101.00 17,858.00 10,150.00 137,109.00 411,327.00
4.2.4.C.1.3 ø300 mm nos. 6.00 109,675.00 17,860.00 10,162.00 137,697.00 826,182.00
4.2.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.B.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.2.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.C.2.1 ø200 mm nos. 219 133,076.00 22,507.00 12,324.00 167,907.00 36,771,633.00


4.2.4.C.2.2 ø250 mm nos. 7 133,713.00 22,520.00 12,338.00 168,571.00 1,179,997.00
4.2.4.C.2.3 ø300 mm nos. 14 134,286.00 22,521.00 12,350.00 169,157.00 2,368,198.00
4.2.4.C.2.4 ø350 mm nos. 6 134,923.00 22,534.00 12,363.00 169,820.00 1,018,920.00
4.2.4.C.2.5 ø400 mm nos. 4 135,559.00 22,547.00 12,377.00 170,483.00 681,932.00
4.2.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.C.2.7 ø500 mm nos. 18 136,776.00 22,565.00 12,402.00 171,743.00 3,091,374.00
4.2.4.C.2.8 ø600 mm nos. 18 138,048.00 22,591.00 12,430.00 173,069.00 3,115,242.00
4.2.4.C.2.9 ø700 mm nos. 2 139,258.00 22,605.00 12,455.00 174,318.00 348,636.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 20 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.2.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.2.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.2.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.2.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.2.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.2.4.C.3.4 ø350 mm nos. 6 184,142.00 31,853.00 16,738.00 232,733.00 1,396,398.00
4.2.4.C.3.5 ø400 mm nos. 3 184,778.00 31,866.00 16,752.00 233,396.00 700,188.00
4.2.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.2.4.C.3.7 ø500 mm nos. 9 185,988.00 31,881.00 16,777.00 234,646.00 2,111,814.00
4.2.4.C.3.8 ø600 mm nos. 8 187,267.00 31,910.00 16,805.00 235,982.00 1,887,856.00
4.2.4.C.3.9 ø700 mm nos. 7 188,477.00 31,924.00 16,830.00 237,231.00 1,660,617.00
4.2.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.2.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.2.4.B.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.2.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 757.00 40,766.88 13,972.83 8,265.14 63,004.85 47,694,671.45

4.2.5.2 ø200 mm nos. 303.00 44,627.58 15,581.46 9,230.31 69,439.35 21,040,123.05

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 21 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.5.3 ø250 mm nos. 303.00 51,128.58 18,290.21 10,855.56 80,274.35 24,323,128.05


4.2.5.4 ø300 mm nos. 151.00 55,471.38 20,099.71 11,941.26 87,512.35 13,214,364.85

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.2.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.2.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.6.A.1.1 ø200 mm nos. 61.00 11,079.12 3,235.25 433.10 14,747.46 899,595.06


4.2.6.A.1.2 ø250 mm nos. 1.00 11,597.22 3,408.39 453.76 15,459.37 15,459.37
4.2.6.A.1.3 ø300 mm nos. 2.00 12,111.88 3,579.06 474.29 16,165.22 32,330.44
4.2.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.2.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.2.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.2.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.2.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.2.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.2.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.2.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.2.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.2.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.6.A.2.1 ø200 mm nos. 73.00 11,079.12 3,614.08 439.51 15,132.71 1,104,687.83


4.2.6.A.2.2 ø250 mm nos. 2.00 11,597.22 3,810.28 460.57 15,868.07 31,736.14
4.2.6.A.2.3 ø300 mm nos. 5.00 12,111.88 4,007.30 481.54 16,600.72 83,003.60

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 22 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.2.4 ø350 mm nos. 2.00 12,575.47 4,195.03 500.60 17,271.10 34,542.20


4.2.6.A.2.5 ø400 mm nos. 1.00 13,090.13 4,395.42 521.95 18,007.50 18,007.50
4.2.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.2.6.A.2.7 ø500 mm nos. 6.00 14,177.39 4,798.62 565.97 19,541.98 117,251.88
4.2.6.A.2.8 ø600 mm nos. 6.00 15,264.65 5,206.67 610.38 21,081.70 126,490.20
4.2.6.A.2.9 ø700 mm nos. 1.00 16,460.93 5,629.81 658.39 22,749.12 22,749.12
4.2.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.2.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.2.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.2.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.2.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.2.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.2.6.A.3.4 ø350 mm nos. 2.00 12,575.47 5,100.93 515.95 18,192.35 36,384.70
4.2.6.A.3.5 ø400 mm nos. 1.00 13,090.13 5,350.74 538.14 18,979.00 18,979.00
4.2.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.2.6.A.3.7 ø500 mm nos. 3.00 14,177.39 5,852.76 583.83 20,613.98 61,841.94
4.2.6.A.3.8 ø600 mm nos. 3.00 15,264.65 6,359.64 629.91 22,254.20 66,762.60
4.2.6.A.3.9 ø700 mm nos. 2.00 16,460.93 6,881.60 679.59 24,022.12 48,044.24
4.2.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.2.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.2.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 23 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Sub-total 4.2: Column 'j' to be carried forward to Schedule


. 380,249,324.28
No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 24 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.3 INSTALLATION of LOOP 302
4.3.1 Miscellaneous works during implementation
4.3.1.1 Setting-out LS 1.00 126,930.00 126,930.00
4.3.1.2 General works and site tests LS 1.00 253,860.00 253,860.00
4.3.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.3.2.1 LS 1.00 253,860.00 253,860.00
installation, construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing
4.3.2.2 LS 1.00 95,197.50 95,197.50
construction completed & acceptance certificate
4.3.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

4.3.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00

4.3.2.5 Development and submission of GIS based As-built drawings LS 1.00 158,662.50 158,662.50
4.3.2.6 Post Construction modelling LS 1.00 19,039.50 19,039.50

Supply and Installation of GRP pipes in accordance with the technical


specification and the standard detail drawing, of any diameter and to
the depths specified below, including fitting, fixing of all items, road
4.3.3 cutting permission fee, temporary road reinstatement, dismantling of -
existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.3.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.3.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.3.A.1.1 ø200 mm m 2,678.70 3,596.40 1,581.32 878.18 5,811.99 11,867.89 31,790,514.11


4.3.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.3.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 25 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -


4.3.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.3.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.3.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.3.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.3.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.3.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.3.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.3.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.3.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.A.2.1 ø200 mm m 2,617 3,890.84 1,719.29 901.27 5,811.99 12,323.40 32,255,255.67


4.3.3.A.2.2 ø250 mm m 292 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 4,004,699.57
4.3.3.A.2.3 ø300 mm m 103 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 1,507,948.70
4.2.3.A.2.4 ø350 mm m 409 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 6,185,397.14
4.3.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.3.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.3.3.A.2.7 ø500 mm m 195 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 4,370,067.41
4.3.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.3.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.3.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.3.3.A.3 Pipe invert depth greater than 5m ( > 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 26 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.3.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.3.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.3.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.3.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.3.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.3.3.A.3.7 ø500 mm m 52 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 1,894,553.58
4.3.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.3.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.3.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.3.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.3.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.3.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.3.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 27 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -

4.3.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -

4.3.3.B.2.11 ø900 mm m -

4.3.3.B.2.12 ø1000 mm m -

4.3.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 28 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -

4.3.3.B.3.11 ø900 mm m -

4.3.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.3.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.3.4.A Normal Manhole Rectangular or circular

4.3.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.A.1.1 ø200 mm nos. 117.00 108,465.00 17,845.00 10,137.00 136,447.00 15,964,299.00


4.3.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.A.1.7 ø500 mm nos. 1.00 112,164.00 17,903.00 10,215.00 140,282.00 140,282.00
4.3.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 29 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -


4.3.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.3.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.A.2.1 ø200 mm nos. 55 133,076.00 22,507.00 12,324.00 167,907.00 9,234,885.00


4.3.4.A.2.2 ø250 mm nos. 10 133,713.00 22,520.00 12,338.00 168,571.00 1,685,710.00
4.3.4.A.2.3 ø300 mm nos. 5 134,286.00 22,521.00 12,350.00 169,157.00 845,785.00
4.3.4.A.2.4 ø350 mm nos. 9 134,923.00 22,534.00 12,363.00 169,820.00 1,528,380.00
4.3.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.A.2.7 ø500 mm nos. 8 136,776.00 22,565.00 12,402.00 171,743.00 1,373,944.00
4.3.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.3.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.3.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.A.3.1 ø200 mm nos. 1 182,295 31,825 16,700 230,820.00 230,820.00


4.3.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.3.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.3.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.3.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 30 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -


4.3.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.3.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.3.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.3.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.3.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.3.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.3.4.B Drop Manhole Rectangular or circular

4.3.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.B.1.1 ø200 mm nos. 12.00 177,870.00 34,380.00 19,812.00 232,062.00 2,784,744.00


4.3.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.3.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.3.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.3.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.3.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.3.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.3.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.3.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.3.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.3.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.3.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.3.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.B.2.1 ø200 mm nos. 1 216,110.00 42,604.00 23,944.00 282,658.00 282,658.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 31 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.2.2 ø250 mm nos. 2 216,602.00 42,630.00 23,972.00 283,204.00 566,408.00


4.3.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.3.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.3.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.3.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.3.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.3.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.3.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.3.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.3.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.3.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.3.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.3.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.3.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.3.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.3.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.3.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.3.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.3.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.3.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.3.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.3.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 32 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.3.4.C Service connections Manhole Rectangular or circular -

4.3.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.3.4.C.1.1 ø200 mm nos. 149.00 108,465.00 17,845.00 10,137.00 136,447.00 20,330,603.00


4.3.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.3.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.3.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.3.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.C.2.1 ø200 mm nos. 146 133,076.00 22,507.00 12,324.00 167,907.00 24,514,422.00


4.3.4.C.2.2 ø250 mm nos. 17 133,713.00 22,520.00 12,338.00 168,571.00 2,865,707.00
4.3.4.C.2.3 ø300 mm nos. 6 134,286.00 22,521.00 12,350.00 169,157.00 1,014,942.00
4.3.4.C.2.4 ø350 mm nos. 23 134,923.00 22,534.00 12,363.00 169,820.00 3,905,860.00
4.3.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.C.2.7 ø500 mm nos. 11 136,776.00 22,565.00 12,402.00 171,743.00 1,889,173.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 33 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -


4.3.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.3.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.3.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.3.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.3.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.3.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.3.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.3.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.3.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.3.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.3.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.3.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.3.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.3.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 34 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.3.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.3.5.1 ø150 mm nos. 530.00 40,766.88 13,972.83 8,265.14 63,004.85 33,392,570.50

4.3.5.2 ø200 mm nos. 212.00 44,627.58 15,581.46 9,230.31 69,439.35 14,721,142.20


4.3.5.3 ø250 mm nos. 212.00 51,128.58 18,290.21 10,855.56 80,274.35 17,018,162.20
4.3.5.4 ø300 mm nos. 106.00 55,471.38 20,099.71 11,941.26 87,512.35 9,276,309.10

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.3.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.3.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.6.A.1.1 ø200 mm nos. 50.00 11,079.12 3,235.25 433.10 14,747.46 737,373.00


4.3.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.3.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.3.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.3.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.3.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.3.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.3.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.3.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 35 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.3.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.3.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.3.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.6.A.2.1 ø200 mm nos. 49.00 11,079.12 3,614.08 439.51 15,132.71 741,502.79


4.3.6.A.2.2 ø250 mm nos. 6.00 11,597.22 3,810.28 460.57 15,868.07 95,208.42
4.3.6.A.2.3 ø300 mm nos. 2.00 12,111.88 4,007.30 481.54 16,600.72 33,201.44
4.3.6.A.2.4 ø350 mm nos. 8.00 12,575.47 4,195.03 500.60 17,271.10 138,168.80
4.3.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.3.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.3.6.A.2.7 ø500 mm nos. 4.00 14,177.39 4,798.62 565.97 19,541.98 78,167.92
4.3.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.3.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.3.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.3.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.3.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.3.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.3.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.3.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.3.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.3.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.3.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 36 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -


4.3.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.3.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.3.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.3.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.3.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.3: Column 'j' to be carried forward to Schedule


. 248,328,914.06
No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 37 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 303
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 171,278.00 171,278.00
4.4.1.2 General works and site tests LS 1.00 342,556.00 342,556.00
4.4.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.4.2.1 LS 1.00 342,556.00 342,556.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.4.2.2 LS 1.00 128,458.50 128,458.50
construction completed & acceptance certificate

4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

Development and submission of Operation and Maintenance


4.4.2.4 LS 1.00 7,500.00 7,500.00
manuals

4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 214,097.50 214,097.50
4.4.2.6 Post Construction modelling LS 1.00 25,691.70 25,691.70

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing of
4.4.3 all items, road cutting permission fee, temporary road reinstatement, -
dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as
per approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.3.A.1.1 ø200 mm m 2,817.10 3,596.40 1,581.32 878.18 5,811.99 11,867.89 33,433,029.94


4.4.3.A.1.2 ø250 mm m 259.00 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 3,428,181.44

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 38 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -


4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.4.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 3,738 3,890.84 1,719.29 901.27 5,811.99 12,323.40 46,061,155.77


4.4.3.A.2.2 ø250 mm m 162 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 2,222,854.79
4.4.3.A.2.3 ø300 mm m 87 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 1,278,669.95
4.4.3.A.2.4 ø350 mm m 200 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 3,028,409.17
4.4.3.A.2.5 ø400 mm m 289 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 5,161,399.76
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 113 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 2,538,181.79
4.4.3.A.2.8 ø600 mm m 216 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 5,694,536.27
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 39 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.4.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.4.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.4.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.4.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.4.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.4.3.A.3.9 ø700 mm m 683 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 33,100,180.26
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.4.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 40 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 41 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.4.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 168.00 108,465.00 17,845.00 10,137.00 136,447.00 22,923,096.00


4.4.4.A.1.2 ø250 mm nos. 12.00 109,101.00 17,858.00 10,150.00 137,109.00 1,645,308.00
4.4.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 42 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -


4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 72 133,076.00 22,507.00 12,324.00 167,907.00 12,089,304.00


4.4.4.A.2.2 ø250 mm nos. 5 133,713.00 22,520.00 12,338.00 168,571.00 842,855.00
4.4.4.A.2.3 ø300 mm nos. 2 134,286.00 22,521.00 12,350.00 169,157.00 338,314.00
4.4.4.A.2.4 ø350 mm nos. 7 134,923.00 22,534.00 12,363.00 169,820.00 1,188,740.00
4.4.4.A.2.5 ø400 mm nos. 8 135,559.00 22,547.00 12,377.00 170,483.00 1,363,864.00
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.A.2.7 ø500 mm nos. 5 136,776.00 22,565.00 12,402.00 171,743.00 858,715.00
4.4.4.A.2.8 ø600 mm nos. 6 138,048.00 22,591.00 12,430.00 173,069.00 1,038,414.00
4.4.4.A.2.9 ø700 mm nos. 7 139,258.00 22,605.00 12,455.00 174,318.00 1,220,226.00
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.4.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.4.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.4.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 43 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -


4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.4.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.4.4.A.3.9 ø700 mm nos. 23 188,477 31,924 16,830 237,231.00 5,456,313.00
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.4.4.B Drop Manhole Rectangular or circular

4.4.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. 36.00 177,870.00 34,380.00 19,812.00 232,062.00 8,354,232.00


4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 44 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.2.1 ø200 mm nos. 14 216,110.00 42,604.00 23,944.00 282,658.00 3,957,212.00


4.4.4.B.2.2 ø250 mm nos. 1 216,602.00 42,630.00 23,972.00 283,204.00 283,204.00
4.4.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.4.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.4.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 45 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

4.4.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.4.C.1.1 ø200 mm nos. 157.00 108,465.00 17,845.00 10,137.00 136,447.00 21,422,179.00


4.4.C.1.2 ø250 mm nos. 15.00 109,101.00 17,858.00 10,150.00 137,109.00 2,056,635.00
4.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 208 133,076.00 22,507.00 12,324.00 167,907.00 34,924,656.00


4.4.4.C.2.2 ø250 mm nos. 10 133,713.00 22,520.00 12,338.00 168,571.00 1,685,710.00
4.4.4.C.2.3 ø300 mm nos. 5 134,286.00 22,521.00 12,350.00 169,157.00 845,785.00
4.4.4.C.2.4 ø350 mm nos. 12 134,923.00 22,534.00 12,363.00 169,820.00 2,037,840.00
4.4.4.C.2.5 ø400 mm nos. 17 135,559.00 22,547.00 12,377.00 170,483.00 2,898,211.00
4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 46 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.2.7 ø500 mm nos. 7 136,776.00 22,565.00 12,402.00 171,743.00 1,202,201.00


4.4.4.C.2.8 ø600 mm nos. 13 138,048.00 22,591.00 12,430.00 173,069.00 2,249,897.00
4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.4.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.4.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.4.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.4.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.4.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.4.4.C.3.9 ø700 mm nos. 38 188,477.00 31,924.00 16,830.00 237,231.00 9,014,778.00
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 47 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.4.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 714.00 40,766.88 13,972.83 8,265.14 63,004.85 44,985,462.90

4.2.5.2 ø200 mm nos. 286.00 44,627.58 15,581.46 9,230.31 69,439.35 19,859,654.10


4.2.5.3 ø250 mm nos. 286.00 51,128.58 18,290.21 10,855.56 80,274.35 22,958,464.10
4.2.5.4 ø300 mm nos. 143.00 55,471.38 20,099.71 11,941.26 87,512.35 12,514,266.05

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.4.6 existing structures, site cleaning, earth cutting, sand filling, earth -
refilling , coarse material s/ khoa filling, as per approved drawing and
specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 52.00 11,079.12 3,235.25 433.10 14,747.46 766,867.92


4.4.6.A.1.2 ø250 mm nos. 5.00 11,597.22 3,408.39 453.76 15,459.37 77,296.85
4.4.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 48 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 69.00 11,079.12 3,614.08 439.51 15,132.71 1,044,156.99


4.4.6.A.2.2 ø250 mm nos. 3.00 11,597.22 3,810.28 460.57 15,868.07 47,604.21
4.4.6.A.2.3 ø300 mm nos. 2.00 12,111.88 4,007.30 481.54 16,600.72 33,201.44
4.4.6.A.2.4 ø350 mm nos. 4.00 12,575.47 4,195.03 500.60 17,271.10 69,084.40
4.4.6.A.2.5 ø400 mm nos. 6.00 13,090.13 4,395.42 521.95 18,007.50 108,045.00
4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. 2.00 14,177.39 4,798.62 565.97 19,541.98 39,083.96
4.4.6.A.2.8 ø600 mm nos. 4.00 15,264.65 5,206.67 610.38 21,081.70 84,326.80
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.4.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.4.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.4.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.4.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 49 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -


4.4.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.4.6.A.3.9 ø700 mm nos. 13.00 16,460.93 6,881.60 679.59 24,022.12 312,287.56
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.4: Column 'j' to be carried forward to Schedule


. 379,991,228.11
No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 50 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 304
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 86,430.00 86,430.00
4.4.1.2 General works and site tests LS 1.00 172,860.00 172,860.00
4.4.2 Commissioning and final inspection /Tests
Pre-commissioning with necessary arrangement on
4.4.2.1 completion of installation, construction, documentation, LS 1.00 172,860.00 172,860.00
reporting etc.
Commissioning and final inspection / testing before issuing
4.4.2.2 LS 1.00 64,822.50 64,822.50
construction completed & acceptance certificate

4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

Development and submission of Operation and Maintenance


4.4.2.4 LS 1.00 7,500.00 7,500.00
manuals

Development and submission of GIS based As-built


4.4.2.5 LS 1.00 108,037.50 108,037.50
drawings

4.4.2.6 Post Construction modelling LS 1.00 12,964.50 12,964.50

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of
any diameter and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee,
4.4.3 -
temporary road reinstatement, dismantling of existing
structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 51 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.1 ø200 mm m 3,051.30 3,596.40 1,581.32 878.18 5,811.99 11,867.89 36,212,489.53


4.4.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.4.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.4.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 614 3,890.84 1,719.29 901.27 5,811.99 12,323.40 7,571,494.26


4.4.3.A.2.2 ø250 mm m 103 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 1,406,575.40
4.4.3.A.2.3 ø300 mm m 169 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 2,482,383.38
4.4.3.A.2.4 ø350 mm m 62 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 942,407.05
4.4.3.A.2.5 ø400 mm m 110 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 1,970,846.34
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.4.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 52 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.4.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.4.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.4.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.4.3.A.3.5 ø400 mm m 182 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 5,847,518.62
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 30 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 1,094,141.41
4.4.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.4.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.4.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 53 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 54 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in


accordance with the technical specification and the standard
detailed drawings, of any diameter/ size and to the depths
specified below, including fitting, fixing of all items, road
4.4.4 cutting permission fee, temporary road reinstatement,
dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per
approved drawing and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 125.00 108,465.00 17,845.00 10,137.00 136,447.00 17,055,875.00


4.4.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 55 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -


4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 11 133,076.00 22,507.00 12,324.00 167,907.00 1,846,977.00


4.4.4.A.2.2 ø250 mm nos. 3 133,713.00 22,520.00 12,338.00 168,571.00 505,713.00
4.4.4.A.2.3 ø300 mm nos. 7 134,286.00 22,521.00 12,350.00 169,157.00 1,184,099.00
4.4.4.A.2.4 ø350 mm nos. 3 134,923.00 22,534.00 12,363.00 169,820.00 509,460.00
4.4.4.A.2.5 ø400 mm nos. 6 135,559.00 22,547.00 12,377.00 170,483.00 1,022,898.00
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.4.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.4.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.4.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 56 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.3.5 ø400 mm nos. 5 184,778 31,866 16,752 233,396.00 1,166,980.00


4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 2 185,988 31,881 16,777 234,646.00 469,292.00
4.4.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.4.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.4.4.B Drop Manhole Rectangular or circular

Manhole invert depth less than equal to


4.4.4.B.1
3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. 15.00 177,870.00 34,380.00 19,812.00 232,062.00 3,480,930.00


4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 57 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.2.1 ø200 mm nos. 2 216,110.00 42,604.00 23,944.00 282,658.00 565,316.00


4.4.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.4.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.4.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.4.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -


2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 58 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

S/C Manhole invert depth less than equal to


4.4.4.C.1 -
3m ( ≤ 3m)
4.4.C.1.1 ø200 mm nos. 170.00 108,465.00 17,845.00 10,137.00 136,447.00 23,195,990.00
4.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 35 133,076.00 22,507.00 12,324.00 167,907.00 5,876,745.00


4.4.4.C.2.2 ø250 mm nos. 6 133,713.00 22,520.00 12,338.00 168,571.00 1,011,426.00
4.4.4.C.2.3 ø300 mm nos. 10 134,286.00 22,521.00 12,350.00 169,157.00 1,691,570.00
4.4.4.C.2.4 ø350 mm nos. 4 134,923.00 22,534.00 12,363.00 169,820.00 679,280.00
4.4.4.C.2.5 ø400 mm nos. 7 135,559.00 22,547.00 12,377.00 170,483.00 1,193,381.00
4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 59 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -


4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.4.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.4.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.4.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.4.4.C.3.5 ø400 mm nos. 11 184,778.00 31,866.00 16,752.00 233,396.00 2,567,356.00
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 2 185,988.00 31,881.00 16,777.00 234,646.00 469,292.00
4.4.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.4.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 60 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP


pipes including fitting, fixing of all items, road cutting
permission fee, temporary road reinstatement, dismantling of
4.4.5 existing structures, site cleaning, earth cutting, sand filling,
earth refilling , coarse material s/ khoa filling, concreting,
individual house hold inspection pit, average length of 10m
as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 361.00 40,766.88 13,972.83 8,265.14 63,004.85 22,744,750.85

4.2.5.2 ø200 mm nos. 144.00 44,627.58 15,581.46 9,230.31 69,439.35 9,999,266.40


4.2.5.3 ø250 mm nos. 144.00 51,128.58 18,290.21 10,855.56 80,274.35 11,559,506.40
4.2.5.4 ø300 mm nos. 72.00 55,471.38 20,099.71 11,941.26 87,512.35 6,300,889.20

Construction of concrete thrust blocks including road


cutting permission fee, temporary road reinstatement,
4.4.6 dismantling of existing structures, site cleaning, earth -
cutting, sand filling, earth refilling , coarse material s/ khoa
filling, as per approved drawing and specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 57.00 11,079.12 3,235.25 433.10 14,747.46 840,605.22


4.4.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.4.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 61 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 12.00 11,079.12 3,614.08 439.51 15,132.71 181,592.52


4.4.6.A.2.2 ø250 mm nos. 2.00 11,597.22 3,810.28 460.57 15,868.07 31,736.14
4.4.6.A.2.3 ø300 mm nos. 3.00 12,111.88 4,007.30 481.54 16,600.72 49,802.16
4.4.6.A.2.4 ø350 mm nos. 1.00 12,575.47 4,195.03 500.60 17,271.10 17,271.10
4.4.6.A.2.5 ø400 mm nos. 2.00 13,090.13 4,395.42 521.95 18,007.50 36,015.00
4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.4.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.4.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.4.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.4.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.4.6.A.3.5 ø400 mm nos. 4.00 13,090.13 5,350.74 538.14 18,979.00 75,916.00
4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 62 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.3.7 ø500 mm nos. 1.00 14,177.39 5,852.76 583.83 20,613.98 20,613.98


4.4.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.4.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.4: Column 'j' to be carried forward to


. 174,518,875.46
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 63 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.5 INSTALLATION of LOOP 305
4.5.1 Miscellaneous works during implementation
4.5.1.1 Setting-out LS 1.00 131,044.00 131,044.00
4.5.1.2 General works and site tests LS 1.00 262,088.00 262,088.00
4.5.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.5.2.1 LS 1.00 262,088.00 262,088.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.5.2.2 LS 1.00 98,283.00 98,283.00
construction completed & acceptance certificate

4.5.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.5.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.5.2.5 Development and submission of GIS based As-built drawings LS 1.00 163,805.00 163,805.00
4.5.2.6 Post Construction modelling LS 1.00 19,656.60 19,656.60

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing
4.5.3 of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse material s/ khoa filling,
concreting as per approved drawing and specification.

4.5.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.5.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.3.A.1.1 ø200 mm m 3,360.70 3,596.40 1,581.32 878.18 5,811.99 11,867.89 39,884,414.37


4.5.3.A.1.2 ø250 mm m 135.30 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 1,790,860.81
4.5.3.A.1.3 ø300 mm m 61.50 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 872,781.24

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 64 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.1.4 ø350 mm m 65.70 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 961,699.24


4.5.3.A.1.5 ø400 mm m 314.80 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 5,454,985.54
4.5.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.5.3.A.1.7 ø500 mm m 147.10 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 3,209,102.76
4.5.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.5.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.5.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.5.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.5.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.5.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.A.2.1 ø200 mm m 1,158 3,890.84 1,719.29 901.27 5,811.99 12,323.40 14,274,189.13


4.5.3.A.2.2 ø250 mm m 51 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 695,754.92
4.5.3.A.2.3 ø300 mm m 316 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 4,644,364.41
4.5.3.A.2.4 ø350 mm m 281 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 4,250,664.21
4.5.3.A.2.5 ø400 mm m 67 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 1,189,303.83
4.5.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.5.3.A.2.7 ø500 mm m 9 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 190,587.86
4.5.3.A.2.8 ø600 mm m 227 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 5,987,036.74
4.5.3.A.2.9 ø700 mm m 299 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 10,179,789.63
4.5.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.5.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.5.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.5.3.A.3 Pipe invert depth greater than 5m ( > 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 65 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.5.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.5.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.5.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.5.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.5.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.5.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.5.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.5.3.A.3.9 ø700 mm m 60 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 2,923,598.75
4.5.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.5.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.5.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.5.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.5.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 66 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -

4.5.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -

4.5.3.B.2.11 ø900 mm m -

4.5.3.B.2.12 ø1000 mm m -

4.5.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 67 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -

4.5.3.B.3.11 ø900 mm m -

4.5.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.5.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.5.4.A Normal Manhole Rectangular or circular

4.5.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.A.1.1 ø200 mm nos. 110.00 108,465.00 17,845.00 10,137.00 136,447.00 15,009,170.00


4.5.4.A.1.2 ø250 mm nos. 5.00 109,101.00 17,858.00 10,150.00 137,109.00 685,545.00
4.5.4.A.1.3 ø300 mm nos. 3.00 109,675.00 17,860.00 10,162.00 137,697.00 413,091.00
4.5.4.A.1.4 ø350 mm nos. 3.00 110,311.00 17,873.00 10,176.00 138,360.00 415,080.00
4.5.4.A.1.5 ø400 mm nos. 17.00 110,948.00 17,886.00 10,189.00 139,023.00 2,363,391.00
4.5.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.A.1.7 ø500 mm nos. 6.00 112,164.00 17,903.00 10,215.00 140,282.00 841,692.00
4.5.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 68 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -


4.5.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.5.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.A.2.1 ø200 mm nos. 20 133,076.00 22,507.00 12,324.00 167,907.00 3,358,140.00


4.5.4.A.2.2 ø250 mm nos. 1 133,713.00 22,520.00 12,338.00 168,571.00 168,571.00
4.5.4.A.2.3 ø300 mm nos. 8 134,286.00 22,521.00 12,350.00 169,157.00 1,353,256.00
4.5.4.A.2.4 ø350 mm nos. 9 134,923.00 22,534.00 12,363.00 169,820.00 1,528,380.00
4.5.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.5.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.5.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.5.4.A.2.8 ø600 mm nos. 5 138,048.00 22,591.00 12,430.00 173,069.00 865,345.00
4.5.4.A.2.9 ø700 mm nos. 11 139,258.00 22,605.00 12,455.00 174,318.00 1,917,498.00
4.5.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.5.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.5.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.5.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.5.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.5.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 69 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -


4.5.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.5.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.5.4.A.3.9 ø700 mm nos. 2 188,477 31,924 16,830 237,231.00 474,462.00
4.5.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.5.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.5.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.5.4.B Drop Manhole Rectangular or circular

4.5.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.B.1.1 ø200 mm nos. 24.00 177,870.00 34,380.00 19,812.00 232,062.00 5,569,488.00


4.5.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.5.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.5.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.5.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.5.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.5.4.B.1.7 ø500 mm nos. 1.00 180,584.00 34,496.00 19,968.00 235,048.00 235,048.00
4.5.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.5.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.5.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.5.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.5.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.5.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.B.2.1 ø200 mm nos. 7 216,110.00 42,604.00 23,944.00 282,658.00 1,978,606.00


2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 70 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -


4.5.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.5.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.5.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.5.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.5.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.5.4.B.2.8 ø600 mm nos. 1 219,808.00 42,772.00 24,154.00 286,734.00 286,734.00
4.5.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.5.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.5.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.5.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.5.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.5.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.5.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.5.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.5.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.5.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.5.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.5.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.5.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.5.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.5.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 71 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.5.4.C Service connections Manhole Rectangular or circular -

4.5.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.5.4.C.1.1 ø200 mm nos. 187.00 108,465.00 17,845.00 10,137.00 136,447.00 25,515,589.00


4.5.4.C.1.2 ø250 mm nos. 8.00 109,101.00 17,858.00 10,150.00 137,109.00 1,096,872.00
4.5.4.C.1.3 ø300 mm nos. 4.00 109,675.00 17,860.00 10,162.00 137,697.00 550,788.00
4.5.4.C.1.4 ø350 mm nos. 4.00 110,311.00 17,873.00 10,176.00 138,360.00 553,440.00
4.5.4.C.1.5 ø400 mm nos. 18.00 110,948.00 17,886.00 10,189.00 139,023.00 2,502,414.00
4.5.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.C.1.7 ø500 mm nos. 9.00 112,164.00 17,903.00 10,215.00 140,282.00 1,262,538.00
4.5.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.5.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.C.2.1 ø200 mm nos. 65 133,076.00 22,507.00 12,324.00 167,907.00 10,913,955.00


4.5.4.C.2.2 ø250 mm nos. 3 133,713.00 22,520.00 12,338.00 168,571.00 505,713.00
4.5.4.C.2.3 ø300 mm nos. 18 134,286.00 22,521.00 12,350.00 169,157.00 3,044,826.00
4.5.4.C.2.4 ø350 mm nos. 16 134,923.00 22,534.00 12,363.00 169,820.00 2,717,120.00
4.5.4.C.2.5 ø400 mm nos. 4 135,559.00 22,547.00 12,377.00 170,483.00 681,932.00
4.5.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.5.4.C.2.7 ø500 mm nos. 1 136,776.00 22,565.00 12,402.00 171,743.00 171,743.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 72 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.2.8 ø600 mm nos. 13 138,048.00 22,591.00 12,430.00 173,069.00 2,249,897.00


4.5.4.C.2.9 ø700 mm nos. 17 139,258.00 22,605.00 12,455.00 174,318.00 2,963,406.00
4.5.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.5.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.5.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.5.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.5.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.5.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.5.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.5.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.5.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.5.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.5.4.C.3.9 ø700 mm nos. 4 188,477.00 31,924.00 16,830.00 237,231.00 948,924.00
4.5.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.5.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.5.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.2.6
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 73 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.5.1 ø150 mm nos. 547.00 40,766.88 13,972.83 8,265.14 63,004.85 34,463,652.95

4.5.5.2 ø200 mm nos. 219.00 44,627.58 15,581.46 9,230.31 69,439.35 15,207,217.65


4.5.5.3 ø250 mm nos. 219.00 51,128.58 18,290.21 10,855.56 80,274.35 17,580,082.65
4.5.5.4 ø300 mm nos. 109.00 55,471.38 20,099.71 11,941.26 87,512.35 9,538,846.15

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.5.6 existing structures, site cleaning, earth cutting, sand filling, earth -
refilling , coarse material s/ khoa filling, as per approved drawing
and specification.

4.5.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.6.A.1.1 ø200 mm nos. 62.00 11,079.12 3,235.25 433.10 14,747.46 914,342.52


4.5.6.A.1.2 ø250 mm nos. 3.00 11,597.22 3,408.39 453.76 15,459.37 46,378.11
4.5.6.A.1.3 ø300 mm nos. 1.00 12,111.88 3,579.06 474.29 16,165.22 16,165.22
4.5.6.A.1.4 ø350 mm nos. 1.00 12,575.47 3,742.23 492.96 16,810.66 16,810.66
4.5.6.A.1.5 ø400 mm nos. 6.00 13,090.13 3,917.76 513.86 17,521.75 105,130.50
4.5.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.5.6.A.1.7 ø500 mm nos. 3.00 14,177.39 4,271.54 557.05 19,005.98 57,017.94
4.5.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.5.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.5.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.5.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.5.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.5.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.6.A.2.1 ø200 mm nos. 22.00 11,079.12 3,614.08 439.51 15,132.71 332,919.62

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 74 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.2.2 ø250 mm nos. 1.00 11,597.22 3,810.28 460.57 15,868.07 15,868.07


4.5.6.A.2.3 ø300 mm nos. 6.00 12,111.88 4,007.30 481.54 16,600.72 99,604.32
4.5.6.A.2.4 ø350 mm nos. 5.00 12,575.47 4,195.03 500.60 17,271.10 86,355.50
4.5.6.A.2.5 ø400 mm nos. 1.00 13,090.13 4,395.42 521.95 18,007.50 18,007.50
4.5.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.5.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.5.6.A.2.8 ø600 mm nos. 4.00 15,264.65 5,206.67 610.38 21,081.70 84,326.80
4.5.6.A.2.9 ø700 mm nos. 6.00 16,460.93 5,629.81 658.39 22,749.12 136,494.72
4.5.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.5.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.5.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.5.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.5.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.5.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.5.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.5.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.5.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.5.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.5.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.5.6.A.3.9 ø700 mm nos. 1.00 16,460.93 6,881.60 679.59 24,022.12 24,022.12
4.5.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.5.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 75 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.5: Column 'j' to be carried forward to


. 269,354,495.04
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 76 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.6 INSTALLATION of LOOP 306
4.6.1 Miscellaneous works during implementation
4.6.1.1 Setting-out LS 1.00 105,214.00 105,214.00
4.6.1.2 General works and site tests LS 1.00 210,428.00 210,428.00
4.6.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.6.2.1 LS 1.00 210,428.00 210,428.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.6.2.2 LS 1.00 78,910.50 78,910.50
construction completed & acceptance certificate
4.6.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.6.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.6.2.5 Development and submission of GIS based As-built drawings LS 1.00 131,517.50 131,517.50
4.6.2.6 Post Construction modelling LS 1.00 15,782.10 15,782.10

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing
4.6.3 of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse material s/ khoa
filling, concreting as per approved drawing and specification.

4.6.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.6.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.6.3.A.1.1 ø200 mm m 3,932.70 3,596.40 1,581.32 878.18 5,811.99 11,867.89 46,672,846.84


4.6.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 77 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -


4.6.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.6.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.6.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.6.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.6.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.6.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.6.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.6.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.6.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.6.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.6.3.A.2.1 ø200 mm m 433.40 3,890.84 1,719.29 901.27 5,811.99 12,323.40 5,340,959.66


4.6.3.A.2.2 ø250 mm m 202.50 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 2,773,432.50
4.6.3.A.2.3 ø300 mm m 214.20 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 3,148,173.60
4.6.3.A.2.4 ø350 mm m 119.80 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 1,812,204.89
4.6.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.6.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.6.3.A.2.7 ø500 mm m 343.90 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 7,710,960.41
4.6.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.6.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.6.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.6.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.6.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 78 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.6.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.6.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.6.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.6.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.6.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.6.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.6.3.A.3.7 ø500 mm m 14 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 521,369.40
4.6.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.6.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.6.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.6.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.6.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.6.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.6.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.6.3.B.1.1 ø200 mm m -
4.6.3.B.1.2 ø250 mm m -
4.6.3.B.1.3 ø300 mm m -
4.6.3.B.1.4 ø350 mm m -
4.6.3.B.1.5 ø400 mm m -
4.6.3.B.1.6 ø450 mm m -
4.6.3.B.1.7 ø500 mm m -
4.6.3.B.1.8 ø600 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 79 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.3.B.1.9 ø700 mm m -
4.6.3.B.1.10 ø800 mm m -
4.6.3.B.1.11 ø900 mm m -
4.6.3.B.1.12 ø1000 mm m -

4.6.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.6.3.B.2.1 ø200 mm m -
4.6.3.B.2.2 ø250 mm m -
4.6.3.B.2.3 ø300 mm m -
4.6.3.B.2.4 ø350 mm m -
4.6.3.B.2.5 ø400 mm m -
4.6.3.B.2.6 ø450 mm m -
4.6.3.B.2.7 ø500 mm m -
4.6.3.B.2.8 ø600 mm m -
4.6.3.B.2.9 ø700 mm m -
4.6.3.B.2.10 ø800 mm m -

4.6.3.B.2.11 ø900 mm m -

4.6.3.B.2.12 ø1000 mm m -

4.6.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.6.3.B.3.1 ø200 mm m -
4.6.3.B.3.2 ø250 mm m -
4.6.3.B.3.3 ø300 mm m -
4.6.3.B.3.4 ø350 mm m -
4.6.3.B.3.5 ø400 mm m -
4.6.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 80 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.3.B.3.7 ø500 mm m -
4.6.3.B.3.8 ø600 mm m -
4.6.3.B.3.9 ø700 mm m -
4.6.3.B.3.10 ø800 mm m -

4.6.3.B.3.11 ø900 mm m -

4.6.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in


accordance with the technical specification and the standard
detailed drawings, of any diameter/ size and to the depths
specified below, including fitting, fixing of all items, road cutting
4.6.4
permission fee, temporary road reinstatement, dismantling of
existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse materials/ khoa filling, concreting, Approved brand
CI Manhole cover, as per approved drawing and specification.

4.6.4.A Normal Manhole Rectangular or circular

4.6.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.6.4.A.1.1 ø200 mm nos. 113.00 108,465.00 17,845.00 10,137.00 136,447.00 15,418,511.00


4.6.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.6.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.6.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.6.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.6.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.6.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.6.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.6.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 81 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -


4.6.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.6.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.6.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.6.4.A.2.1 ø200 mm nos. 6 133,076.00 22,507.00 12,324.00 167,907.00 1,007,442.00


4.6.4.A.2.2 ø250 mm nos. 5 133,713.00 22,520.00 12,338.00 168,571.00 842,855.00
4.6.4.A.2.3 ø300 mm nos. 8 134,286.00 22,521.00 12,350.00 169,157.00 1,353,256.00
4.6.4.A.2.4 ø350 mm nos. 3 134,923.00 22,534.00 12,363.00 169,820.00 509,460.00
4.6.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.6.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.6.4.A.2.7 ø500 mm nos. 11 136,776.00 22,565.00 12,402.00 171,743.00 1,889,173.00
4.6.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.6.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.6.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.6.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.6.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.6.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.6.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.6.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.6.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.6.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.6.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.6.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 82 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -


4.6.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.6.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.6.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.6.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.6.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.6.4.B Drop Manhole Rectangular or circular

4.6.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.6.4.B.1.1 ø200 mm nos. 15.00 177,870.00 34,380.00 19,812.00 232,062.00 3,480,930.00


4.6.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.6.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.6.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.6.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.6.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.6.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.6.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.6.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.6.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.6.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.6.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.6.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.6.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.6.4.B.2.2 ø250 mm nos. 1 216,602.00 42,630.00 23,972.00 283,204.00 283,204.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 83 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -


4.6.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.6.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.6.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.6.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.6.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.6.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.6.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.6.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.6.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.6.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.6.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.6.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.6.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.6.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.6.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.6.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.6.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.6.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.6.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.6.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.6.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.6.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 84 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.4.C Service connections Manhole Rectangular or circular -

S/C Manhole invert depth less than equal to


4.6.4.C.1 -
3m ( ≤ 3m)
4.6.4.C.1.1 ø200 mm nos. 219.00 108,465.00 17,845.00 10,137.00 136,447.00 29,881,893.00
4.6.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.6.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.6.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.6.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.6.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.6.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.6.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.6.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.6.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.6.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.6.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.6.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.6.4.C.2.1 ø200 mm nos. 25 133,076.00 22,507.00 12,324.00 167,907.00 4,197,675.00


4.6.4.C.2.2 ø250 mm nos. 12 133,713.00 22,520.00 12,338.00 168,571.00 2,022,852.00
4.6.4.C.2.3 ø300 mm nos. 12 134,286.00 22,521.00 12,350.00 169,157.00 2,029,884.00
4.6.4.C.2.4 ø350 mm nos. 7 134,923.00 22,534.00 12,363.00 169,820.00 1,188,740.00
4.6.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.6.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.6.4.C.2.7 ø500 mm nos. 20 136,776.00 22,565.00 12,402.00 171,743.00 3,434,860.00
4.6.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 85 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -


4.6.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.6.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.6.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.6.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.6.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.6.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.6.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.6.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.6.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.6.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.6.4.C.3.7 ø500 mm nos. 1 185,988.00 31,881.00 16,777.00 234,646.00 234,646.00
4.6.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.6.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.6.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.6.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.6.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures,
4.6.5 site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection
pit, average length of 10m as per approved drawing and
specification.

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 86 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.5.1 ø150 mm nos. 439.00 40,766.88 13,972.83 8,265.14 63,004.85 27,659,129.15

4.6.5.2 ø200 mm nos. 176.00 44,627.58 15,581.46 9,230.31 69,439.35 12,221,325.60


4.6.5.3 ø250 mm nos. 176.00 51,128.58 18,290.21 10,855.56 80,274.35 14,128,285.60
4.6.5.4 ø300 mm nos. 88.00 55,471.38 20,099.71 11,941.26 87,512.35 7,701,086.80

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.6.6 existing structures, site cleaning, earth cutting, sand filling, earth -
refilling , coarse material s/ khoa filling, as per approved drawing
and specification.

4.6.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.6.6.A.1.1 ø200 mm nos. 73.00 11,079.12 3,235.25 433.10 14,747.46 1,076,564.58


4.6.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.6.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.6.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.6.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.6.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.6.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.6.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.6.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.6.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.6.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.6.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.6.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.6.6.A.2.1 ø200 mm nos. 8.00 11,079.12 3,614.08 439.51 15,132.71 121,061.68


4.6.6.A.2.2 ø250 mm nos. 4.00 11,597.22 3,810.28 460.57 15,868.07 63,472.28
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 87 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.6.6.A.2.3 ø300 mm nos. 4.00 12,111.88 4,007.30 481.54 16,600.72 66,402.88


4.6.6.A.2.4 ø350 mm nos. 2.00 12,575.47 4,195.03 500.60 17,271.10 34,542.20
4.6.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.6.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.6.6.A.2.7 ø500 mm nos. 7.00 14,177.39 4,798.62 565.97 19,541.98 136,793.86
4.6.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.6.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.6.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.6.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.6.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.6.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.6.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.6.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.6.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.6.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.6.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.6.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.6.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.6.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.6.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.6.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.6.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.6.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 88 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Sub-total 4.6: Column 'j' to be carried forward to


. 199,738,773.02
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 89 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.7 INSTALLATION of LOOP 307
4.7.1 Miscellaneous works during implementation
4.7.1.1 Setting-out LS 1.00 388,136.00 388,136.00
4.7.1.2 General works and site tests LS 1.00 776,272.00 776,272.00
4.7.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.7.2.1 LS 1.00 776,272.00 776,272.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.7.2.2 LS 1.00 291,102.00 291,102.00
construction completed & acceptance certificate
4.7.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.7.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.7.2.5 Development and submission of GIS based As-built drawings LS 1.00 485,170.00 485,170.00
4.7.2.6 Post Construction modelling LS 1.00 58,220.40 58,220.40

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing
4.7.3 of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse material s/ khoa filling,
concreting as per approved drawing and specification.

4.7.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.7.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.7.3.A.1.1 ø200 mm m 14,610.50 3,596.40 1,581.32 878.18 5,811.99 11,867.89 173,395,791.39


4.7.3.A.1.2 ø250 mm m 347.70 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 4,602,234.31
4.7.3.A.1.3 ø300 mm m 35.80 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 508,058.02
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 90 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.3.A.1.4 ø350 mm m 153.60 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 2,248,356.21


4.7.3.A.1.5 ø400 mm m 6.90 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 119,566.07
4.7.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.7.3.A.1.7 ø500 mm m 117.80 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 2,569,900.10
4.7.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.7.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.7.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.7.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.7.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.7.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.7.3.A.2.1 ø200 mm m 1,436.00 3,890.84 1,719.29 901.27 5,811.99 12,323.40 17,696,396.09


4.7.3.A.2.2 ø250 mm m 229.80 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 3,147,332.29
4.7.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.7.3.A.2.4 ø350 mm m 94.30 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 1,426,468.45
4.7.3.A.2.5 ø400 mm m 41.40 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 740,408.70
4.7.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.7.3.A.2.7 ø500 mm m 760.70 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 17,056,491.95
4.7.3.A.2.8 ø600 mm m 487.80 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 12,854,210.05
4.7.3.A.2.9 ø700 mm m 322.70 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 11,005,085.81
4.7.3.A.2.10 ø800 mm m 338.20 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 13,539,549.27

4.7.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.7.3.A.2.12 ø1000 mm m 155.90 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 6,583,085.52

4.7.3.A.3 Pipe invert depth greater than 5m ( > 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 91 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.7.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.7.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.7.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.7.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.7.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.7.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.7.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.7.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.7.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.7.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.7.3.A.3.12 ø1000 mm m 268 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 15,156,945.28

4.7.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.7.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.7.3.B.1.1 ø200 mm m -
4.7.3.B.1.2 ø250 mm m -
4.7.3.B.1.3 ø300 mm m -
4.7.3.B.1.4 ø350 mm m -
4.7.3.B.1.5 ø400 mm m -
4.7.3.B.1.6 ø450 mm m -
4.7.3.B.1.7 ø500 mm m -
4.7.3.B.1.8 ø600 mm m -
4.7.3.B.1.9 ø700 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 92 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.3.B.1.10 ø800 mm m -
4.7.3.B.1.11 ø900 mm m -
4.7.3.B.1.12 ø1000 mm m -

4.7.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.7.3.B.2.1 ø200 mm m -
4.7.3.B.2.2 ø250 mm m -
4.7.3.B.2.3 ø300 mm m -
4.7.3.B.2.4 ø350 mm m -
4.7.3.B.2.5 ø400 mm m -
4.7.3.B.2.6 ø450 mm m -
4.7.3.B.2.7 ø500 mm m -
4.7.3.B.2.8 ø600 mm m -
4.7.3.B.2.9 ø700 mm m -
4.7.3.B.2.10 ø800 mm m -

4.7.3.B.2.11 ø900 mm m -

4.7.3.B.2.12 ø1000 mm m -

4.7.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.7.3.B.3.1 ø200 mm m -
4.7.3.B.3.2 ø250 mm m -
4.7.3.B.3.3 ø300 mm m -
4.7.3.B.3.4 ø350 mm m -
4.7.3.B.3.5 ø400 mm m -
4.7.3.B.3.6 ø450 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 93 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.3.B.3.7 ø500 mm m -
4.7.3.B.3.8 ø600 mm m -
4.7.3.B.3.9 ø700 mm m -
4.7.3.B.3.10 ø800 mm m -

4.7.3.B.3.11 ø900 mm m -

4.7.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.7.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.7.4.A Normal Manhole Rectangular or circular

4.7.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.7.4.A.1.1 ø200 mm nos. 481.00 108,465.00 17,845.00 10,137.00 136,447.00 65,631,007.00


4.7.4.A.1.2 ø250 mm nos. 14.00 109,101.00 17,858.00 10,150.00 137,109.00 1,919,526.00
4.7.4.A.1.3 ø300 mm nos. 2.00 109,675.00 17,860.00 10,162.00 137,697.00 275,394.00
4.7.4.A.1.4 ø350 mm nos. 7.00 110,311.00 17,873.00 10,176.00 138,360.00 968,520.00
4.7.4.A.1.5 ø400 mm nos. 1.00 110,948.00 17,886.00 10,189.00 139,023.00 139,023.00
4.7.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.7.4.A.1.7 ø500 mm nos. 8.00 112,164.00 17,903.00 10,215.00 140,282.00 1,122,256.00
4.7.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 94 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -


4.7.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.7.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.7.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.7.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.7.4.A.2.1 ø200 mm nos. 17 133,076.00 22,507.00 12,324.00 167,907.00 2,854,419.00


4.7.4.A.2.2 ø250 mm nos. 6 133,713.00 22,520.00 12,338.00 168,571.00 1,011,426.00
4.7.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.7.4.A.2.4 ø350 mm nos. 2 134,923.00 22,534.00 12,363.00 169,820.00 339,640.00
4.7.4.A.2.5 ø400 mm nos. 4 135,559.00 22,547.00 12,377.00 170,483.00 681,932.00
4.7.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.7.4.A.2.7 ø500 mm nos. 19 136,776.00 22,565.00 12,402.00 171,743.00 3,263,117.00
4.7.4.A.2.8 ø600 mm nos. 15 138,048.00 22,591.00 12,430.00 173,069.00 2,596,035.00
4.7.4.A.2.9 ø700 mm nos. 10 139,258.00 22,605.00 12,455.00 174,318.00 1,743,180.00
4.7.4.A.2.10 ø800 mm nos. 12 140,531.00 22,632.00 12,483.00 175,646.00 2,107,752.00

4.7.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.7.4.A.2.12 ø1000 mm nos. 8 143,020.00 22,675.00 12,535.00 178,230.00 1,425,840.00

4.7.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.7.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.7.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.7.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.7.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.7.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 95 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -


4.7.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.7.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.7.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.7.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.7.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.7.4.A.3.12 ø1000 mm nos. 5 192,239 31,994 16,910 241,143.00 1,205,715.00

4.7.4.B Drop Manhole Rectangular or circular

4.7.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.7.4.B.1.1 ø200 mm nos. 68.00 177,870.00 34,380.00 19,812.00 232,062.00 15,780,216.00


4.7.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.7.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.7.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.7.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.7.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.7.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.7.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.7.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.7.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.7.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.7.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.7.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.7.4.B.2.1 ø200 mm nos. 6 216,110.00 42,604.00 23,944.00 282,658.00 1,695,948.00


2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 96 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.4.B.2.2 ø250 mm nos. 2 216,602.00 42,630.00 23,972.00 283,204.00 566,408.00


4.7.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.7.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.7.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.7.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.7.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.7.4.B.2.8 ø600 mm nos. 1 219,808.00 42,772.00 24,154.00 286,734.00 286,734.00
4.7.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.7.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.7.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.7.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.7.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.7.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.7.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.7.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.7.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.7.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.7.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.7.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.7.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.7.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.7.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.7.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 97 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.7.4.C Service connections Manhole Rectangular or circular -

4.7.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.7.4.C.1.1 ø200 mm nos. 812.00 108,465.00 17,845.00 10,137.00 136,447.00 110,794,964.00


4.7.4.C.1.2 ø250 mm nos. 20.00 109,101.00 17,858.00 10,150.00 137,109.00 2,742,180.00
4.7.4.C.1.3 ø300 mm nos. 2.00 109,675.00 17,860.00 10,162.00 137,697.00 275,394.00
4.7.4.C.1.4 ø350 mm nos. 9.00 110,311.00 17,873.00 10,176.00 138,360.00 1,245,240.00
4.7.4.C.1.5 ø400 mm nos. 1.00 110,948.00 17,886.00 10,189.00 139,023.00 139,023.00
4.7.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.7.4.C.1.7 ø500 mm nos. 7.00 112,164.00 17,903.00 10,215.00 140,282.00 981,974.00
4.7.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.7.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.7.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.7.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.7.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.7.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.7.4.C.2.1 ø200 mm nos. 80 133,076.00 22,507.00 12,324.00 167,907.00 13,432,560.00


4.7.4.C.2.2 ø250 mm nos. 13 133,713.00 22,520.00 12,338.00 168,571.00 2,191,423.00
4.7.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.7.4.C.2.4 ø350 mm nos. 6 134,923.00 22,534.00 12,363.00 169,820.00 1,018,920.00
4.7.4.C.2.5 ø400 mm nos. 3 135,559.00 22,547.00 12,377.00 170,483.00 511,449.00
4.7.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.7.4.C.2.7 ø500 mm nos. 43 136,776.00 22,565.00 12,402.00 171,743.00 7,384,949.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 98 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.4.C.2.8 ø600 mm nos. 28 138,048.00 22,591.00 12,430.00 173,069.00 4,845,932.00


4.7.4.C.2.9 ø700 mm nos. 18 139,258.00 22,605.00 12,455.00 174,318.00 3,137,724.00
4.7.4.C.2.10 ø800 mm nos. 19 140,531.00 22,632.00 12,483.00 175,646.00 3,337,274.00

4.7.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.7.4.C.2.12 ø1000 mm nos. 9 143,020.00 22,675.00 12,535.00 178,230.00 1,604,070.00

4.7.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.7.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.7.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.7.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.7.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.7.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.7.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.7.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.7.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.7.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.7.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.7.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.7.4.C.3.12 ø1000 mm nos. 15 192,239.00 31,994.00 16,910.00 241,143.00 3,617,145.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 99 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures,
4.7.5 site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection
pit, average length of 10m as per approved drawing and
specification.

4.7.5.1 ø150 mm nos. 1,618.00 40,766.88 13,972.83 8,265.14 63,004.85 101,941,847.30

4.7.5.2 ø200 mm nos. 647.00 44,627.58 15,581.46 9,230.31 69,439.35 44,927,259.45


4.7.5.3 ø250 mm nos. 647.00 51,128.58 18,290.21 10,855.56 80,274.35 51,937,504.45
4.7.5.4 ø300 mm nos. 324.00 55,471.38 20,099.71 11,941.26 87,512.35 28,354,001.40

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.7.6 existing structures, site cleaning, earth cutting, sand filling, earth -
refilling , coarse material s/ khoa filling, as per approved drawing
and specification.

4.7.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.7.6.A.1.1 ø200 mm nos. 271.00 11,079.12 3,235.25 433.10 14,747.46 3,996,561.66


4.7.6.A.1.2 ø250 mm nos. 7.00 11,597.22 3,408.39 453.76 15,459.37 108,215.59
4.7.6.A.1.3 ø300 mm nos. 1.00 12,111.88 3,579.06 474.29 16,165.22 16,165.22
4.7.6.A.1.4 ø350 mm nos. 3.00 12,575.47 3,742.23 492.96 16,810.66 50,431.98
4.7.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.7.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.7.6.A.1.7 ø500 mm nos. 2.00 14,177.39 4,271.54 557.05 19,005.98 38,011.96
4.7.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.7.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 100 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.7.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.7.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.7.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.7.6.A.2.1 ø200 mm nos. 27.00 11,079.12 3,614.08 439.51 15,132.71 408,583.17


4.7.6.A.2.2 ø250 mm nos. 4.00 11,597.22 3,810.28 460.57 15,868.07 63,472.28
4.7.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.7.6.A.2.4 ø350 mm nos. 2.00 12,575.47 4,195.03 500.60 17,271.10 34,542.20
4.7.6.A.2.5 ø400 mm nos. 1.00 13,090.13 4,395.42 521.95 18,007.50 18,007.50
4.7.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.7.6.A.2.7 ø500 mm nos. 14.00 14,177.39 4,798.62 565.97 19,541.98 273,587.72
4.7.6.A.2.8 ø600 mm nos. 9.00 15,264.65 5,206.67 610.38 21,081.70 189,735.30
4.7.6.A.2.9 ø700 mm nos. 6.00 16,460.93 5,629.81 658.39 22,749.12 136,494.72
4.7.6.A.2.10 ø800 mm nos. 6.00 17,602.69 6,047.83 704.78 24,355.31 146,131.86

4.7.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.7.6.A.2.12 ø1000 mm nos. 3.00 20,104.25 6,918.91 805.17 27,828.33 83,484.99

4.7.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.7.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.7.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.7.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.7.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.7.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.7.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 101 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.7.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -


4.7.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.7.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.7.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.7.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.7.6.A.3.12 ø1000 mm nos. 5.00 20,104.25 8,467.18 831.39 29,402.83 147,014.15

Sub-total 4.7: Column 'j' to be carried forward to


. 781,192,913.83
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 102 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.8 INSTALLATION of LOOP 308
4.8.1 Miscellaneous works during implementation
4.8.1.1 Setting-out LS 1.00 67,626.00 67,626.00
4.8.1.2 General works and site tests LS 1.00 135,252.00 135,252.00
4.8.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.8.2.1 LS 1.00 135,252.00 135,252.00
installation, construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing
4.8.2.2 LS 1.00 50,719.50 50,719.50
construction completed & acceptance certificate
4.8.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.8.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.8.2.5 Development and submission of GIS based As-built drawings LS 1.00 84,532.50 84,532.50
4.8.2.6 Post Construction modelling LS 1.00 10,143.90 10,143.90

Supply and Installation of GRP pipes in accordance with the technical


specification and the standard detail drawing, of any diameter and to
the depths specified below, including fitting, fixing of all items, road
4.8.3 cutting permission fee, temporary road reinstatement, dismantling of -
existing structures, site cleaning, earth cutting, sand filling, earth refilling
, coarse material s/ khoa filling, concreting as per approved drawing and
specification.

4.8.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.8.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.8.3.A.1.1 ø200 mm m 2,561.80 3,596.40 1,581.32 878.18 5,811.99 11,867.89 30,403,157.89


4.8.3.A.1.2 ø250 mm m 281.80 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 3,729,967.30
4.8.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.8.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 103 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -


4.8.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.8.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.8.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.8.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.8.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.8.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.8.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.8.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.8.3.A.2.1 ø200 mm m 172.20 3,890.84 1,719.29 901.27 5,811.99 12,323.40 2,122,088.72


4.8.3.A.2.2 ø250 mm m 54.10 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 740,951.60
4.8.3.A.2.3 ø300 mm m 56.70 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 833,340.07
4.8.3.A.2.4 ø350 mm m 187.60 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 2,837,809.99
4.8.3.A.2.5 ø400 mm m 34.90 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 624,160.96
4.8.3.A.2.6 ø450 mm m 32.20 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 596,699.92
4.8.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.8.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.8.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.8.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.8.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.8.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.8.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.8.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 104 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -


4.8.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.8.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.8.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.8.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.8.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.8.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.8.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.8.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.8.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.8.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.8.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.8.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.8.3.B.1.1 ø200 mm m -
4.8.3.B.1.2 ø250 mm m -
4.8.3.B.1.3 ø300 mm m -
4.8.3.B.1.4 ø350 mm m -
4.8.3.B.1.5 ø400 mm m -
4.8.3.B.1.6 ø450 mm m -
4.8.3.B.1.7 ø500 mm m -
4.8.3.B.1.8 ø600 mm m -
4.8.3.B.1.9 ø700 mm m -
4.8.3.B.1.10 ø800 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 105 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.3.B.1.11 ø900 mm m -
4.8.3.B.1.12 ø1000 mm m -

4.8.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.8.3.B.2.1 ø200 mm m -
4.8.3.B.2.2 ø250 mm m -
4.8.3.B.2.3 ø300 mm m -
4.8.3.B.2.4 ø350 mm m -
4.8.3.B.2.5 ø400 mm m -
4.8.3.B.2.6 ø450 mm m -
4.8.3.B.2.7 ø500 mm m -
4.8.3.B.2.8 ø600 mm m -
4.8.3.B.2.9 ø700 mm m -
4.8.3.B.2.10 ø800 mm m -

4.8.3.B.2.11 ø900 mm m -

4.8.3.B.2.12 ø1000 mm m -

4.8.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.8.3.B.3.1 ø200 mm m -
4.8.3.B.3.2 ø250 mm m -
4.8.3.B.3.3 ø300 mm m -
4.8.3.B.3.4 ø350 mm m -
4.8.3.B.3.5 ø400 mm m -
4.8.3.B.3.6 ø450 mm m -
4.8.3.B.3.7 ø500 mm m -
4.8.3.B.3.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 106 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.3.B.3.9 ø700 mm m -
4.8.3.B.3.10 ø800 mm m -

4.8.3.B.3.11 ø900 mm m -

4.8.3.B.3.12 ø1000 mm m -
Supply and Installation of RCC Manholes chambers in accordance with
the technical specification and the standard detailed drawings, of any
diameter/ size and to the depths specified below, including fitting,
fixing of all items, road cutting permission fee, temporary road
4.8.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.
4.8.4.A Normal Manhole Rectangular or circular

4.8.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.8.4.A.1.1 ø200 mm nos. 71.00 108,465.00 17,845.00 10,137.00 136,447.00 9,687,737.00


4.8.4.A.1.2 ø250 mm nos. 10.00 109,101.00 17,858.00 10,150.00 137,109.00 1,371,090.00
4.8.4.A.1.3 ø300 mm nos. 1.00 109,675.00 17,860.00 10,162.00 137,697.00 137,697.00
4.8.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.8.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.8.4.A.1.6 ø450 mm nos. 1.00 111,584.00 17,899.00 10,203.00 139,686.00 139,686.00
4.8.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.8.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.8.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.8.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.8.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.8.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 107 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.8.4.A.2.1 ø200 mm nos. 1 133,076.00 22,507.00 12,324.00 167,907.00 167,907.00


4.8.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.8.4.A.2.3 ø300 mm nos. 1 134,286.00 22,521.00 12,350.00 169,157.00 169,157.00
4.8.4.A.2.4 ø350 mm nos. 8 134,923.00 22,534.00 12,363.00 169,820.00 1,358,560.00
4.8.4.A.2.5 ø400 mm nos. 1 135,559.00 22,547.00 12,377.00 170,483.00 170,483.00
4.8.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.8.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.8.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.8.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.8.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.8.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.8.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.8.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.8.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.8.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.8.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.8.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.8.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.8.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.8.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.8.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.8.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 108 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.8.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.8.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.8.4.B Drop Manhole Rectangular or circular

4.8.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.8.4.B.1.1 ø200 mm nos. 24.00 177,870.00 34,380.00 19,812.00 232,062.00 5,569,488.00


4.8.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.8.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.8.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.8.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.8.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.8.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.8.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.8.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.8.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.8.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.8.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.8.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.8.4.B.2.1 ø200 mm nos. 4 216,110.00 42,604.00 23,944.00 282,658.00 1,130,632.00


4.8.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.8.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.8.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.8.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 109 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.4.B.2.6 ø450 mm nos. 1 218,444.00 42,712.00 24,076.00 285,232.00 285,232.00


4.8.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.8.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.8.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.8.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.8.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.8.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.8.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.8.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.8.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.8.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.8.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.8.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.8.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.8.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.8.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.8.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.8.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.8.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.8.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.8.4.C Service connections Manhole Rectangular or circular -

4.8.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.8.4.C.1.1 ø200 mm nos. 143.00 108,465.00 17,845.00 10,137.00 136,447.00 19,511,921.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 110 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.4.C.1.2 ø250 mm nos. 16.00 109,101.00 17,858.00 10,150.00 137,109.00 2,193,744.00


4.8.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.8.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.8.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.8.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.8.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.8.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.8.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.8.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.8.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.8.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.8.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.8.4.C.2.1 ø200 mm nos. 10 133,076.00 22,507.00 12,324.00 167,907.00 1,679,070.00


4.8.4.C.2.2 ø250 mm nos. 4 133,713.00 22,520.00 12,338.00 168,571.00 674,284.00
4.8.4.C.2.3 ø300 mm nos. 4 134,286.00 22,521.00 12,350.00 169,157.00 676,628.00
4.8.4.C.2.4 ø350 mm nos. 11 134,923.00 22,534.00 12,363.00 169,820.00 1,868,020.00
4.8.4.C.2.5 ø400 mm nos. 2 135,559.00 22,547.00 12,377.00 170,483.00 340,966.00
4.8.4.C.2.6 ø450 mm nos. 2 136,195.00 22,560.00 12,391.00 171,146.00 342,292.00
4.8.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.8.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.8.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.8.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.8.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 111 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.8.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.8.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.8.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.8.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.8.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.8.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.8.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.8.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.8.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.8.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.8.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.8.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.8.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes including


fitting, fixing of all items, road cutting permission fee, temporary road
reinstatement, dismantling of existing structures, site cleaning, earth
4.8.5
cutting, sand filling, earth refilling , coarse material s/ khoa filling,
concreting, individual house hold inspection pit, average length of 10m
as per approved drawing and specification.

4.8.5.1 ø150 mm nos. 282.00 40,766.88 13,972.83 8,265.14 63,004.85 17,767,367.70

4.8.5.2 ø200 mm nos. 113.00 44,627.58 15,581.46 9,230.31 69,439.35 7,846,646.55


4.8.5.3 ø250 mm nos. 113.00 51,128.58 18,290.21 10,855.56 80,274.35 9,071,001.55
4.8.5.4 ø300 mm nos. 56.00 55,471.38 20,099.71 11,941.26 87,512.35 4,900,691.60

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 112 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.8.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.8.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.8.6.A.1.1 ø200 mm nos. 48.00 11,079.12 3,235.25 433.10 14,747.46 707,878.08


4.8.6.A.1.2 ø250 mm nos. 5.00 11,597.22 3,408.39 453.76 15,459.37 77,296.85
4.8.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.8.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.8.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.8.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.8.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.8.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.8.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.8.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.8.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.8.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.8.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.8.6.A.2.1 ø200 mm nos. 3.00 11,079.12 3,614.08 439.51 15,132.71 45,398.13


4.8.6.A.2.2 ø250 mm nos. 1.00 11,597.22 3,810.28 460.57 15,868.07 15,868.07
4.8.6.A.2.3 ø300 mm nos. 1.00 12,111.88 4,007.30 481.54 16,600.72 16,600.72
4.8.6.A.2.4 ø350 mm nos. 4.00 12,575.47 4,195.03 500.60 17,271.10 69,084.40
4.8.6.A.2.5 ø400 mm nos. 1.00 13,090.13 4,395.42 521.95 18,007.50 18,007.50
4.8.6.A.2.6 ø450 mm nos. 1.00 13,662.73 4,601.59 545.00 18,809.33 18,809.33

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 113 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.8.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -


4.8.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.8.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.8.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.8.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.8.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.8.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.8.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.8.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.8.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.8.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.8.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.8.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.8.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.8.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.8.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.8.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.8.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.8.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.8: Column 'j' to be carried forward to Schedule


. 130,423,446.82
No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 114 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.9 INSTALLATION of LOOP 309
4.9.1 Miscellaneous works during implementation
4.9.1.1 Setting-out LS 1.00 200,400.00 200,400.00
4.9.1.2 General works and site tests LS 1.00 400,800.00 400,800.00
4.9.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.9.2.1 LS 1.00 400,800.00 400,800.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.9.2.2 LS 1.00 150,300.00 150,300.00
construction completed & acceptance certificate

4.9.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

4.9.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00

4.9.2.5 Development and submission of GIS based As-built drawings LS 1.00 250,500.00 250,500.00
4.9.2.6 Post Construction modelling LS 1.00 30,060.00 30,060.00

Supply and Installation of GRP pipes in accordance with the technical


specification and the standard detail drawing, of any diameter and to
the depths specified below, including fitting, fixing of all items, road
4.9.3 cutting permission fee, temporary road reinstatement, dismantling of -
existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.9.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.9.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.9.3.A.1.1 ø200 mm m 2,789.50 3,596.40 1,581.32 878.18 5,811.99 11,867.89 33,105,476.20


4.9.3.A.1.2 ø250 mm m 147.80 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 1,956,313.58

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 115 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -


4.9.3.A.1.4 ø350 mm m 122.90 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 1,798,977.73
4.9.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.9.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.9.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.9.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.9.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.9.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.9.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.9.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.9.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.9.3.A.2.1 ø200 mm m 4,180 3,890.84 1,719.29 901.27 5,811.99 12,323.40 51,506,864.29


4.9.3.A.2.2 ø250 mm m 302 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 4,129,332.84
4.9.3.A.2.3 ø300 mm m 209 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 3,070,277.61
4.9.3.A.2.4 ø350 mm m 95 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 1,432,519.22
4.9.3.A.2.5 ø400 mm m 86 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 1,530,893.35
4.9.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.9.3.A.2.7 ø500 mm m 144 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 3,231,024.70
4.9.3.A.2.8 ø600 mm m 361 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 9,518,123.56
4.9.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.9.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.9.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.9.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 116 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.9.3.A.3.1 ø200 mm m 127 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 3,368,526.33


4.9.3.A.3.2 ø250 mm m 129 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 3,601,613.71
4.9.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.9.3.A.3.4 ø350 mm m 109 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 3,198,710.78
4.9.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.9.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.9.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.9.3.A.3.8 ø600 mm m 389 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 15,819,101.37
4.9.3.A.3.9 ø700 mm m 790 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 38,321,931.27
4.9.3.A.3.10 ø800 mm m 40 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 2,164,106.30

4.9.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.9.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.9.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.9.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.9.3.B.1.1 ø200 mm m -
4.9.3.B.1.2 ø250 mm m -
4.9.3.B.1.3 ø300 mm m -
4.9.3.B.1.4 ø350 mm m -
4.9.3.B.1.5 ø400 mm m -
4.9.3.B.1.6 ø450 mm m -
4.9.3.B.1.7 ø500 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 117 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.3.B.1.8 ø600 mm m -
4.9.3.B.1.9 ø700 mm m -
4.9.3.B.1.10 ø800 mm m -
4.9.3.B.1.11 ø900 mm m -
4.9.3.B.1.12 ø1000 mm m -

4.9.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.9.3.B.2.1 ø200 mm m -
4.9.3.B.2.2 ø250 mm m -
4.9.3.B.2.3 ø300 mm m -
4.9.3.B.2.4 ø350 mm m -
4.9.3.B.2.5 ø400 mm m -
4.9.3.B.2.6 ø450 mm m -
4.9.3.B.2.7 ø500 mm m -
4.9.3.B.2.8 ø600 mm m -
4.9.3.B.2.9 ø700 mm m -
4.9.3.B.2.10 ø800 mm m -

4.9.3.B.2.11 ø900 mm m -

4.9.3.B.2.12 ø1000 mm m -

4.9.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.9.3.B.3.1 ø200 mm m -
4.9.3.B.3.2 ø250 mm m -
4.9.3.B.3.3 ø300 mm m -
4.9.3.B.3.4 ø350 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 118 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.3.B.3.5 ø400 mm m -
4.9.3.B.3.6 ø450 mm m -
4.9.3.B.3.7 ø500 mm m -
4.9.3.B.3.8 ø600 mm m -
4.9.3.B.3.9 ø700 mm m -
4.9.3.B.3.10 ø800 mm m -

4.9.3.B.3.11 ø900 mm m -

4.9.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including fitting,
fixing of all items, road cutting permission fee, temporary road
4.9.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.9.4.A Normal Manhole Rectangular or circular

4.9.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.9.4.A.1.1 ø200 mm nos. 127.00 108,465.00 17,845.00 10,137.00 136,447.00 17,328,769.00


4.9.4.A.1.2 ø250 mm nos. 6.00 109,101.00 17,858.00 10,150.00 137,109.00 822,654.00
4.9.4.A.1.3 ø300 mm nos. 1.00 109,675.00 17,860.00 10,162.00 137,697.00 137,697.00
4.9.4.A.1.4 ø350 mm nos. 5.00 110,311.00 17,873.00 10,176.00 138,360.00 691,800.00
4.9.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.9.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 119 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -


4.9.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.9.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.9.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.9.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.9.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.9.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.9.4.A.2.1 ø200 mm nos. 73 133,076.00 22,507.00 12,324.00 167,907.00 12,257,211.00


4.9.4.A.2.2 ø250 mm nos. 11 133,713.00 22,520.00 12,338.00 168,571.00 1,854,281.00
4.9.4.A.2.3 ø300 mm nos. 5 134,286.00 22,521.00 12,350.00 169,157.00 845,785.00
4.9.4.A.2.4 ø350 mm nos. 4 134,923.00 22,534.00 12,363.00 169,820.00 679,280.00
4.9.4.A.2.5 ø400 mm nos. 5 135,559.00 22,547.00 12,377.00 170,483.00 852,415.00
4.9.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.9.4.A.2.7 ø500 mm nos. 4 136,776.00 22,565.00 12,402.00 171,743.00 686,972.00
4.9.4.A.2.8 ø600 mm nos. 18 138,048.00 22,591.00 12,430.00 173,069.00 3,115,242.00
4.9.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.9.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.9.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.9.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.9.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.9.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.9.4.A.3.2 ø250 mm nos. 3 182,932 31,838 16,713 231,483.00 694,449.00
4.9.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 120 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.A.3.4 ø350 mm nos. 1 184,142 31,853 16,738 232,733.00 232,733.00


4.9.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.9.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.9.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.9.4.A.3.8 ø600 mm nos. 8 187,267 31,910 16,805 235,982.00 1,887,856.00
4.9.4.A.3.9 ø700 mm nos. 21 188,477 31,924 16,830 237,231.00 4,981,851.00
4.9.4.A.3.10 ø800 mm nos. 1 189,750 31,950 16,858 238,558.00 238,558.00

4.9.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.9.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.9.4.B Drop Manhole Rectangular or circular

4.9.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.9.4.B.1.1 ø200 mm nos. 37.00 177,870.00 34,380.00 19,812.00 232,062.00 8,586,294.00


4.9.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.9.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.9.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.9.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.9.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.9.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.9.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.9.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.9.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.9.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.9.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 121 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.9.4.B.2.1 ø200 mm nos. 16 216,110.00 42,604.00 23,944.00 282,658.00 4,522,528.00


4.9.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.9.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.9.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.9.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.9.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.9.4.B.2.7 ø500 mm nos. 1 218,824.00 42,720.00 24,100.00 285,644.00 285,644.00
4.9.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.9.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.9.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.9.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.9.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.9.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.9.4.B.3.1 ø200 mm nos. 3 292,584.00 59,046.00 32,206.00 383,836.00 1,151,508.00


4.9.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.9.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.9.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.9.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.9.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.9.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.9.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.9.4.B.3.9 ø700 mm nos. 1 297,140.00 59,244.00 32,466.00 388,850.00 388,850.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 122 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.9.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.9.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.9.4.C Service connections Manhole Rectangular or circular -

4.9.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.9.4.C.1.1 ø200 mm nos. 155.00 108,465.00 17,845.00 10,137.00 136,447.00 21,149,285.00


4.9.4.C.1.2 ø250 mm nos. 9.00 109,101.00 17,858.00 10,150.00 137,109.00 1,233,981.00
4.9.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.9.4.C.1.4 ø350 mm nos. 7.00 110,311.00 17,873.00 10,176.00 138,360.00 968,520.00
4.9.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.9.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.9.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.9.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.9.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.9.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.9.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.9.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.9.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.9.4.C.2.1 ø200 mm nos. 233 133,076.00 22,507.00 12,324.00 167,907.00 39,122,331.00


4.9.4.C.2.2 ø250 mm nos. 17 133,713.00 22,520.00 12,338.00 168,571.00 2,865,707.00
4.9.4.C.2.3 ø300 mm nos. 12 134,286.00 22,521.00 12,350.00 169,157.00 2,029,884.00
4.9.4.C.2.4 ø350 mm nos. 6 134,923.00 22,534.00 12,363.00 169,820.00 1,018,920.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 123 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.4.C.2.5 ø400 mm nos. 5 135,559.00 22,547.00 12,377.00 170,483.00 852,415.00


4.9.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.9.4.C.2.7 ø500 mm nos. 9 136,776.00 22,565.00 12,402.00 171,743.00 1,545,687.00
4.9.4.C.2.8 ø600 mm nos. 21 138,048.00 22,591.00 12,430.00 173,069.00 3,634,449.00
4.9.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.9.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.9.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.9.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.9.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.9.4.C.3.1 ø200 mm nos. 8 182,295.00 31,825.00 16,700.00 230,820.00 1,846,560.00


4.9.4.C.3.2 ø250 mm nos. 8 182,932.00 31,838.00 16,713.00 231,483.00 1,851,864.00
4.9.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.9.4.C.3.4 ø350 mm nos. 7 184,142.00 31,853.00 16,738.00 232,733.00 1,629,131.00
4.9.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.9.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.9.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.9.4.C.3.8 ø600 mm nos. 22 187,267.00 31,910.00 16,805.00 235,982.00 5,191,604.00
4.9.4.C.3.9 ø700 mm nos. 44 188,477.00 31,924.00 16,830.00 237,231.00 10,438,164.00
4.9.4.C.3.10 ø800 mm nos. 3 189,750.00 31,950.00 16,858.00 238,558.00 715,674.00

4.9.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.9.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 124 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.9.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.9.5.1 ø150 mm nos. 836.00 40,766.88 13,972.83 8,265.14 63,004.85 52,672,054.60

4.9.5.2 ø200 mm nos. 334.00 44,627.58 15,581.46 9,230.31 69,439.35 23,192,742.90


4.9.5.3 ø250 mm nos. 334.00 51,128.58 18,290.21 10,855.56 80,274.35 26,811,632.90
4.9.5.4 ø300 mm nos. 167.00 55,471.38 20,099.71 11,941.26 87,512.35 14,614,562.45

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.9.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.9.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.9.6.A.1.1 ø200 mm nos. 52.00 11,079.12 3,235.25 433.10 14,747.46 766,867.92


4.9.6.A.1.2 ø250 mm nos. 3.00 11,597.22 3,408.39 453.76 15,459.37 46,378.11
4.9.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.9.6.A.1.4 ø350 mm nos. 2.00 12,575.47 3,742.23 492.96 16,810.66 33,621.32
4.9.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.9.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.9.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.9.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.9.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 125 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.9.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.9.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.9.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.9.6.A.2.1 ø200 mm nos. 78.00 11,079.12 3,614.08 439.51 15,132.71 1,180,351.38


4.9.6.A.2.2 ø250 mm nos. 6.00 11,597.22 3,810.28 460.57 15,868.07 95,208.42
4.9.6.A.2.3 ø300 mm nos. 4.00 12,111.88 4,007.30 481.54 16,600.72 66,402.88
4.9.6.A.2.4 ø350 mm nos. 2.00 12,575.47 4,195.03 500.60 17,271.10 34,542.20
4.9.6.A.2.5 ø400 mm nos. 2.00 13,090.13 4,395.42 521.95 18,007.50 36,015.00
4.9.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.9.6.A.2.7 ø500 mm nos. 3.00 14,177.39 4,798.62 565.97 19,541.98 58,625.94
4.9.6.A.2.8 ø600 mm nos. 7.00 15,264.65 5,206.67 610.38 21,081.70 147,571.90
4.9.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.9.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.9.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.9.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.9.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.9.6.A.3.1 ø200 mm nos. 3.00 11,079.12 4,371.74 452.35 15,903.21 47,709.63


4.9.6.A.3.2 ø250 mm nos. 3.00 11,597.22 4,617.36 474.24 16,688.82 50,066.46
4.9.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.9.6.A.3.4 ø350 mm nos. 2.00 12,575.47 5,100.93 515.95 18,192.35 36,384.70
4.9.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.9.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 126 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.9.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -


4.9.6.A.3.8 ø600 mm nos. 7.00 15,264.65 6,359.64 629.91 22,254.20 155,779.40
4.9.6.A.3.9 ø700 mm nos. 15.00 16,460.93 6,881.60 679.59 24,022.12 360,331.80
4.9.6.A.3.10 ø800 mm nos. 1.00 17,602.69 7,398.46 727.66 25,728.81 25,728.81

4.9.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.9.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.9: Column 'j' to be carried forward to Schedule


. 457,978,284.56
No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 127 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.10 INSTALLATION of LOOP 310
4.10.1 Miscellaneous works during implementation
4.10.1.1 Setting-out LS 1.00 332,354.00 332,354.00
4.10.1.2 General works and site tests LS 1.00 664,708.00 664,708.00
4.10.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.10.2.1 LS 1.00 664,708.00 664,708.00
installation, construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing
4.10.2.2 LS 1.00 249,265.50 249,265.50
construction completed & acceptance certificate
4.10.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.10.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.10.2.5 Development and submission of GIS based As-built drawings LS 1.00 415,442.50 415,442.50
4.10.2.6 Post Construction modelling LS 1.00 49,853.10 49,853.10

Supply and Installation of GRP pipes in accordance with the technical


specification and the standard detail drawing, of any diameter and to
the depths specified below, including fitting, fixing of all items, road
4.10.3 cutting permission fee, temporary road reinstatement, dismantling of -
existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.10.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.10.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.10.3.A.1.1 ø200 mm m 7,859.70 3,596.40 1,581.32 878.18 5,811.99 11,867.89 93,278,046.72


4.10.3.A.1.2 ø250 mm m 300.00 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 3,970,866.53
4.10.3.A.1.3 ø300 mm m 215.60 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 3,059,701.39
4.10.3.A.1.4 ø350 mm m 45.30 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 663,089.43

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 128 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -


4.10.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.10.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.10.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.10.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.10.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.10.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.10.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.10.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.10.3.A.2.1 ø200 mm m 4,140.10 3,890.84 1,719.29 901.27 5,811.99 12,323.40 51,020,090.16


4.10.3.A.2.2 ø250 mm m 579.80 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 7,940,919.33
4.10.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.10.3.A.2.4 ø350 mm m 396.60 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 5,999,336.04
4.10.3.A.2.5 ø400 mm m 195.90 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 3,503,528.11
4.10.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.10.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.10.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.10.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.10.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.10.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.10.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.10.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.10.3.A.3.1 ø200 mm m 48 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 1,273,143.81

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 129 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.3.A.3.2 ø250 mm m 59 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 1,645,973.73


4.10.3.A.3.3 ø300 mm m 462 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 13,373,884.04
4.10.3.A.3.4 ø350 mm m 150 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 4,410,699.36
4.10.3.A.3.5 ø400 mm m 479 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 15,401,573.22
4.10.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.10.3.A.3.7 ø500 mm m 946 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 34,718,795.93
4.10.3.A.3.8 ø600 mm m 418 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 16,998,720.65
4.10.3.A.3.9 ø700 mm m 323 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 15,636,162.49
4.10.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.10.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.10.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.10.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.10.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.10.3.B.1.1 ø200 mm m -
4.10.3.B.1.2 ø250 mm m -
4.10.3.B.1.3 ø300 mm m -
4.10.3.B.1.4 ø350 mm m -
4.10.3.B.1.5 ø400 mm m -
4.10.3.B.1.6 ø450 mm m -
4.10.3.B.1.7 ø500 mm m -
4.10.3.B.1.8 ø600 mm m -
4.10.3.B.1.9 ø700 mm m -
4.10.3.B.1.10 ø800 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 130 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.3.B.1.11 ø900 mm m -
4.10.3.B.1.12 ø1000 mm m -

4.10.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.10.3.B.2.1 ø200 mm m -
4.10.3.B.2.2 ø250 mm m -
4.10.3.B.2.3 ø300 mm m -
4.10.3.B.2.4 ø350 mm m -
4.10.3.B.2.5 ø400 mm m -
4.10.3.B.2.6 ø450 mm m -
4.10.3.B.2.7 ø500 mm m -
4.10.3.B.2.8 ø600 mm m -
4.10.3.B.2.9 ø700 mm m -
4.10.3.B.2.10 ø800 mm m -

4.10.3.B.2.11 ø900 mm m -

4.10.3.B.2.12 ø1000 mm m -

4.10.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.10.3.B.3.1 ø200 mm m -
4.10.3.B.3.2 ø250 mm m -
4.10.3.B.3.3 ø300 mm m -
4.10.3.B.3.4 ø350 mm m -
4.10.3.B.3.5 ø400 mm m -
4.10.3.B.3.6 ø450 mm m -
4.10.3.B.3.7 ø500 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 131 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.3.B.3.8 ø600 mm m -
4.10.3.B.3.9 ø700 mm m -
4.10.3.B.3.10 ø800 mm m -

4.10.3.B.3.11 ø900 mm m -

4.10.3.B.3.12 ø1000 mm m -
Supply and Installation of RCC Manholes chambers in accordance
with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.10.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.
4.10.4.A Normal Manhole Rectangular or circular

4.10.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.10.4.A.1.1 ø200 mm nos. 275.00 108,465.00 17,845.00 10,137.00 136,447.00 37,522,925.00


4.10.4.A.1.2 ø250 mm nos. 13.00 109,101.00 17,858.00 10,150.00 137,109.00 1,782,417.00
4.10.4.A.1.3 ø300 mm nos. 6.00 109,675.00 17,860.00 10,162.00 137,697.00 826,182.00
4.10.4.A.1.4 ø350 mm nos. 1.00 110,311.00 17,873.00 10,176.00 138,360.00 138,360.00
4.10.4.A.1.5 ø400 mm nos. 1.00 110,948.00 17,886.00 10,189.00 139,023.00 139,023.00
4.10.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.10.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.10.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.10.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.10.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.10.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 132 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.10.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.10.4.A.2.1 ø200 mm nos. 82 133,076.00 22,507.00 12,324.00 167,907.00 13,768,374.00


4.10.4.A.2.2 ø250 mm nos. 22 133,713.00 22,520.00 12,338.00 168,571.00 3,708,562.00
4.10.4.A.2.3 ø300 mm nos. 2 134,286.00 22,521.00 12,350.00 169,157.00 338,314.00
4.10.4.A.2.4 ø350 mm nos. 11 134,923.00 22,534.00 12,363.00 169,820.00 1,868,020.00
4.10.4.A.2.5 ø400 mm nos. 11 135,559.00 22,547.00 12,377.00 170,483.00 1,875,313.00
4.10.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.10.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.10.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.10.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.10.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.10.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.10.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.10.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.10.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.10.4.A.3.2 ø250 mm nos. 2 182,932 31,838 16,713 231,483.00 462,966.00
4.10.4.A.3.3 ø300 mm nos. 18 183,505 31,840 16,725 232,070.00 4,177,260.00
4.10.4.A.3.4 ø350 mm nos. 5 184,142 31,853 16,738 232,733.00 1,163,665.00
4.10.4.A.3.5 ø400 mm nos. 13 184,778 31,866 16,752 233,396.00 3,034,148.00
4.10.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.10.4.A.3.7 ø500 mm nos. 25 185,988 31,881 16,777 234,646.00 5,866,150.00
4.10.4.A.3.8 ø600 mm nos. 16 187,267 31,910 16,805 235,982.00 3,775,712.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 133 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.4.A.3.9 ø700 mm nos. 11 188,477 31,924 16,830 237,231.00 2,609,541.00


4.10.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.10.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.10.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.10.4.B Drop Manhole Rectangular or circular

4.10.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.10.4.B.1.1 ø200 mm nos. 71.00 177,870.00 34,380.00 19,812.00 232,062.00 16,476,402.00


4.10.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.10.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.10.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.10.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.10.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.10.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.10.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.10.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.10.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.10.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.10.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.10.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.10.4.B.2.1 ø200 mm nos. 14 216,110.00 42,604.00 23,944.00 282,658.00 3,957,212.00


4.10.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.10.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.10.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 134 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -


4.10.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.10.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.10.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.10.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.10.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.10.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.10.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.10.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.10.4.B.3.1 ø200 mm nos. 1 292,584.00 59,046.00 32,206.00 383,836.00 383,836.00


4.10.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.10.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.10.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.10.4.B.3.5 ø400 mm nos. 1 294,426.00 59,126.00 32,310.00 385,862.00 385,862.00
4.10.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.10.4.B.3.7 ø500 mm nos. 2 295,284.00 59,156.00 32,362.00 386,802.00 773,604.00
4.10.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.10.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.10.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.10.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.10.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.10.4.C Service connections Manhole Rectangular or circular -

4.10.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -


2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 135 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.4.C.1.1 ø200 mm nos. 437.00 108,465.00 17,845.00 10,137.00 136,447.00 59,627,339.00


4.10.4.C.1.2 ø250 mm nos. 17.00 109,101.00 17,858.00 10,150.00 137,109.00 2,330,853.00
4.10.4.C.1.3 ø300 mm nos. 12.00 109,675.00 17,860.00 10,162.00 137,697.00 1,652,364.00
4.10.4.C.1.4 ø350 mm nos. 3.00 110,311.00 17,873.00 10,176.00 138,360.00 415,080.00
4.10.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.10.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.10.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.10.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.10.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.10.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.10.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.10.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.10.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.10.4.C.2.1 ø200 mm nos. 231 133,076.00 22,507.00 12,324.00 167,907.00 38,786,517.00


4.10.4.C.2.2 ø250 mm nos. 33 133,713.00 22,520.00 12,338.00 168,571.00 5,562,843.00
4.10.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.10.4.C.2.4 ø350 mm nos. 23 134,923.00 22,534.00 12,363.00 169,820.00 3,905,860.00
4.10.4.C.2.5 ø400 mm nos. 11 135,559.00 22,547.00 12,377.00 170,483.00 1,875,313.00
4.10.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.10.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.10.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.10.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.10.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 136 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.10.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.10.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.10.4.C.3.1 ø200 mm nos. 3 182,295.00 31,825.00 16,700.00 230,820.00 692,460.00


4.10.4.C.3.2 ø250 mm nos. 4 182,932.00 31,838.00 16,713.00 231,483.00 925,932.00
4.10.4.C.3.3 ø300 mm nos. 26 183,505.00 31,840.00 16,725.00 232,070.00 6,033,820.00
4.10.4.C.3.4 ø350 mm nos. 9 184,142.00 31,853.00 16,738.00 232,733.00 2,094,597.00
4.10.4.C.3.5 ø400 mm nos. 27 184,778.00 31,866.00 16,752.00 233,396.00 6,301,692.00
4.10.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.10.4.C.3.7 ø500 mm nos. 53 185,988.00 31,881.00 16,777.00 234,646.00 12,436,238.00
4.10.4.C.3.8 ø600 mm nos. 24 187,267.00 31,910.00 16,805.00 235,982.00 5,663,568.00
4.10.4.C.3.9 ø700 mm nos. 18 188,477.00 31,924.00 16,830.00 237,231.00 4,270,158.00
4.10.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.10.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.10.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.10.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.10.5.1 ø150 mm nos. 1,386.00 40,766.88 13,972.83 8,265.14 63,004.85 87,324,722.10

4.10.5.2 ø200 mm nos. 554.00 44,627.58 15,581.46 9,230.31 69,439.35 38,469,399.90


4.10.5.3 ø250 mm nos. 554.00 51,128.58 18,290.21 10,855.56 80,274.35 44,471,989.90

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 137 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.5.4 ø300 mm nos. 277.00 55,471.38 20,099.71 11,941.26 87,512.35 24,240,920.95

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.10.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.10.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.10.6.A.1.1 ø200 mm nos. 146.00 11,079.12 3,235.25 433.10 14,747.46 2,153,129.16


4.10.6.A.1.2 ø250 mm nos. 6.00 11,597.22 3,408.39 453.76 15,459.37 92,756.22
4.10.6.A.1.3 ø300 mm nos. 4.00 12,111.88 3,579.06 474.29 16,165.22 64,660.88
4.10.6.A.1.4 ø350 mm nos. 1.00 12,575.47 3,742.23 492.96 16,810.66 16,810.66
4.10.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.10.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.10.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.10.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.10.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.10.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.10.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.10.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.10.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.10.6.A.2.1 ø200 mm nos. 77.00 11,079.12 3,614.08 439.51 15,132.71 1,165,218.67


4.10.6.A.2.2 ø250 mm nos. 11.00 11,597.22 3,810.28 460.57 15,868.07 174,548.77
4.10.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.10.6.A.2.4 ø350 mm nos. 8.00 12,575.47 4,195.03 500.60 17,271.10 138,168.80

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 138 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.10.6.A.2.5 ø400 mm nos. 4.00 13,090.13 4,395.42 521.95 18,007.50 72,030.00


4.10.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.10.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.10.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.10.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.10.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.10.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.10.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.10.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.10.6.A.3.1 ø200 mm nos. 1.00 11,079.12 4,371.74 452.35 15,903.21 15,903.21


4.10.6.A.3.2 ø250 mm nos. 1.00 11,597.22 4,617.36 474.24 16,688.82 16,688.82
4.10.6.A.3.3 ø300 mm nos. 9.00 12,111.88 4,863.80 496.05 17,471.72 157,245.48
4.10.6.A.3.4 ø350 mm nos. 3.00 12,575.47 5,100.93 515.95 18,192.35 54,577.05
4.10.6.A.3.5 ø400 mm nos. 9.00 13,090.13 5,350.74 538.14 18,979.00 170,811.00
4.10.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.10.6.A.3.7 ø500 mm nos. 18.00 14,177.39 5,852.76 583.83 20,613.98 371,051.64
4.10.6.A.3.8 ø600 mm nos. 8.00 15,264.65 6,359.64 629.91 22,254.20 178,033.60
4.10.6.A.3.9 ø700 mm nos. 6.00 16,460.93 6,881.60 679.59 24,022.12 144,132.72
4.10.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.10.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.10.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.10: Column 'j' to be carried forward to


. 732,394,643.59
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 139 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.11 INSTALLATION of LOOP 311
4.11.1 Miscellaneous works during implementation
4.11.1.1 Setting-out LS 1.00 335,690.00 335,690.00
4.11.1.2 General works and site tests LS 1.00 671,380.00 671,380.00
4.11.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.11.2.1 LS 1.00 671,380.00 671,380.00
installation, construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing
4.11.2.2 LS 1.00 251,767.50 251,767.50
construction completed & acceptance certificate
4.11.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00

4.11.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00

4.11.2.5 Development and submission of GIS based As-built drawings LS 1.00 419,612.50 419,612.50
4.11.2.6 Post Construction modelling LS 1.00 50,353.50 50,353.50

Supply and Installation of GRP pipes in accordance with the technical


specification and the standard detail drawing, of any diameter and to
the depths specified below, including fitting, fixing of all items, road
4.11.3 cutting permission fee, temporary road reinstatement, dismantling of -
existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.11.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.11.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.11.3.A.1.1 ø200 mm m 7,896.20 3,596.40 1,581.32 878.18 5,811.99 11,867.89 93,711,224.67


4.11.3.A.1.2 ø250 mm m 210.10 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 2,780,930.20
4.11.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.11.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 140 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -


4.11.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.11.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.11.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.11.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.11.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.11.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.11.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.11.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.11.23.A.2.1 ø200 mm m 5,123 3,890.84 1,719.29 901.27 5,811.99 12,323.40 63,132,755.71


4.11.23.A.2.2 ø250 mm m 448 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 6,128,943.43
4.11.23.A.2.3 ø300 mm m 483 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 7,101,762.28
4.11.23.A.2.4 ø350 mm m 312 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 4,725,649.47
4.11.23.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.11.23.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.11.23.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.11.23.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.11.23.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.11.23.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.11.23.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.11.23.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.11.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.11.3.A.3.1 ø200 mm m 30 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 782,452.97

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 141 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -


4.11.3.A.3.3 ø300 mm m 186 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 5,389,475.66
4.11.3.A.3.4 ø350 mm m 274 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 8,029,057.52
4.11.3.A.3.5 ø400 mm m 761 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 24,463,780.46
4.11.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.11.3.A.3.7 ø500 mm m 116 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 4,240,715.87
4.11.3.A.3.8 ø600 mm m 836 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 33,989,306.00
4.11.3.A.3.9 ø700 mm m 111 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 5,362,355.26
4.11.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.11.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.11.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.11.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.11.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.11.3.B.1.1 ø200 mm m -
4.11.3.B.1.2 ø250 mm m -
4.11.3.B.1.3 ø300 mm m -
4.11.3.B.1.4 ø350 mm m -
4.11.3.B.1.5 ø400 mm m -
4.11.3.B.1.6 ø450 mm m -
4.11.3.B.1.7 ø500 mm m -
4.11.3.B.1.8 ø600 mm m -
4.11.3.B.1.9 ø700 mm m -
4.11.3.B.1.10 ø800 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 142 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.3.B.1.11 ø900 mm m -
4.11.3.B.1.12 ø1000 mm m -

4.11.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.11.3.B.2.1 ø200 mm m -
4.11.3.B.2.2 ø250 mm m -
4.11.3.B.2.3 ø300 mm m -
4.11.3.B.2.4 ø350 mm m -
4.11.3.B.2.5 ø400 mm m -
4.11.3.B.2.6 ø450 mm m -
4.11.3.B.2.7 ø500 mm m -
4.11.3.B.2.8 ø600 mm m -
4.11.3.B.2.9 ø700 mm m -
4.11.3.B.2.10 ø800 mm m -

4.11.3.B.2.11 ø900 mm m -

4.11.3.B.2.12 ø1000 mm m -

4.11.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.11.3.B.3.1 ø200 mm m -
4.11.3.B.3.2 ø250 mm m -
4.11.3.B.3.3 ø300 mm m -
4.11.3.B.3.4 ø350 mm m -
4.11.3.B.3.5 ø400 mm m -
4.11.3.B.3.6 ø450 mm m -
4.11.3.B.3.7 ø500 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 143 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.3.B.3.8 ø600 mm m -
4.11.3.B.3.9 ø700 mm m -
4.11.3.B.3.10 ø800 mm m -

4.11.3.B.3.11 ø900 mm m -

4.11.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.11.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.11.4.A Normal Manhole Rectangular or circular

4.11.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.11.4.A.1.1 ø200 mm nos. 328.00 108,465.00 17,845.00 10,137.00 136,447.00 44,754,616.00


4.11.4.A.1.2 ø250 mm nos. 9.00 109,101.00 17,858.00 10,150.00 137,109.00 1,233,981.00
4.11.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.11.4.A.1.4 ø350 mm nos. 1.00 110,311.00 17,873.00 10,176.00 138,360.00 138,360.00
4.11.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.11.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.11.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.11.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.11.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.11.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 144 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -


4.11.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.11.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.11.4.A.2.1 ø200 mm nos. 107 133,076.00 22,507.00 12,324.00 167,907.00 17,966,049.00


4.11.4.A.2.2 ø250 mm nos. 14 133,713.00 22,520.00 12,338.00 168,571.00 2,359,994.00
4.11.4.A.2.3 ø300 mm nos. 21 134,286.00 22,521.00 12,350.00 169,157.00 3,552,297.00
4.11.4.A.2.4 ø350 mm nos. 14 134,923.00 22,534.00 12,363.00 169,820.00 2,377,480.00
4.11.4.A.2.5 ø400 mm nos. 4 135,559.00 22,547.00 12,377.00 170,483.00 681,932.00
4.11.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.11.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.11.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.11.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.11.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.11.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.11.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.11.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.11.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.11.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.11.4.A.3.3 ø300 mm nos. 4 183,505 31,840 16,725 232,070.00 928,280.00
4.11.4.A.3.4 ø350 mm nos. 5 184,142 31,853 16,738 232,733.00 1,163,665.00
4.11.4.A.3.5 ø400 mm nos. 20 184,778 31,866 16,752 233,396.00 4,667,920.00
4.11.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.11.4.A.3.7 ø500 mm nos. 5 185,988 31,881 16,777 234,646.00 1,173,230.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 145 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.4.A.3.8 ø600 mm nos. 29 187,267 31,910 16,805 235,982.00 6,843,478.00


4.11.4.A.3.9 ø700 mm nos. 4 188,477 31,924 16,830 237,231.00 948,924.00
4.11.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.11.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.11.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.11.4.B Drop Manhole Rectangular or circular

4.11.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.11.4.B.1.1 ø200 mm nos. 53.00 177,870.00 34,380.00 19,812.00 232,062.00 12,299,286.00


4.11.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.11.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.11.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.11.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.11.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.11.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.11.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.11.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.11.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.11.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.11.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.11.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.11.4.B.2.1 ø200 mm nos. 20 216,110.00 42,604.00 23,944.00 282,658.00 5,653,160.00


4.11.4.B.2.2 ø250 mm nos. 1 216,602.00 42,630.00 23,972.00 283,204.00 283,204.00
4.11.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 146 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -


4.11.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.11.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.11.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.11.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.11.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.11.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.11.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.11.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.11.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.11.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.11.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.11.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.11.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.11.4.B.3.5 ø400 mm nos. 1 294,426.00 59,126.00 32,310.00 385,862.00 385,862.00
4.11.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.11.4.B.3.7 ø500 mm nos. 1 295,284.00 59,156.00 32,362.00 386,802.00 386,802.00
4.11.4.B.3.8 ø600 mm nos. 1 296,282.00 59,214.00 32,416.00 387,912.00 387,912.00
4.11.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.11.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.11.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.11.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.11.4.C Service connections Manhole Rectangular or circular -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 147 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.11.4.C.1.1 ø200 mm nos. 439.00 108,465.00 17,845.00 10,137.00 136,447.00 59,900,233.00


4.11.4.C.1.2 ø250 mm nos. 12.00 109,101.00 17,858.00 10,150.00 137,109.00 1,645,308.00
4.11.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.11.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.11.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.11.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.11.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.11.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.11.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.11.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.11.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.11.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.11.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.11.4.C.2.1 ø200 mm nos. 285 133,076.00 22,507.00 12,324.00 167,907.00 47,853,495.00


4.11.4.C.2.2 ø250 mm nos. 25 133,713.00 22,520.00 12,338.00 168,571.00 4,214,275.00
4.11.4.C.2.3 ø300 mm nos. 27 134,286.00 22,521.00 12,350.00 169,157.00 4,567,239.00
4.11.4.C.2.4 ø350 mm nos. 18 134,923.00 22,534.00 12,363.00 169,820.00 3,056,760.00
4.11.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.11.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.11.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.11.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.11.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 148 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.11.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.11.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.11.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.11.4.C.3.1 ø200 mm nos. 2 182,295.00 31,825.00 16,700.00 230,820.00 461,640.00


4.11.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.11.4.C.3.3 ø300 mm nos. 11 183,505.00 31,840.00 16,725.00 232,070.00 2,552,770.00
4.11.4.C.3.4 ø350 mm nos. 16 184,142.00 31,853.00 16,738.00 232,733.00 3,723,728.00
4.11.4.C.3.5 ø400 mm nos. 43 184,778.00 31,866.00 16,752.00 233,396.00 10,036,028.00
4.11.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.11.4.C.3.7 ø500 mm nos. 7 185,988.00 31,881.00 16,777.00 234,646.00 1,642,522.00
4.11.4.C.3.8 ø600 mm nos. 47 187,267.00 31,910.00 16,805.00 235,982.00 11,091,154.00
4.11.4.C.3.9 ø700 mm nos. 7 188,477.00 31,924.00 16,830.00 237,231.00 1,660,617.00
4.11.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.11.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.11.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.11.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.11.5.1 ø150 mm nos. 1,400.00 40,766.88 13,972.83 8,265.14 63,004.85 88,206,790.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 149 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.5.2 ø200 mm nos. 560.00 44,627.58 15,581.46 9,230.31 69,439.35 38,886,036.00


4.11.5.3 ø250 mm nos. 560.00 51,128.58 18,290.21 10,855.56 80,274.35 44,953,636.00
4.11.5.4 ø300 mm nos. 280.00 55,471.38 20,099.71 11,941.26 87,512.35 24,503,458.00

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.2.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.11.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.11.6.A.1.1 ø200 mm nos. 146.00 11,079.12 3,235.25 433.10 14,747.46 2,153,129.16


4.11.6.A.1.2 ø250 mm nos. 4.00 11,597.22 3,408.39 453.76 15,459.37 61,837.48
4.11.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.11.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.11.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.11.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.11.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.11.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.11.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.11.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.11.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.11.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.11.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.11.6.A.2.1 ø200 mm nos. 95.00 11,079.12 3,614.08 439.51 15,132.71 1,437,607.45


4.11.6.A.2.2 ø250 mm nos. 8.00 11,597.22 3,810.28 460.57 15,868.07 126,944.56

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 150 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.11.6.A.2.3 ø300 mm nos. 9.00 12,111.88 4,007.30 481.54 16,600.72 149,406.48


4.11.6.A.2.4 ø350 mm nos. 6.00 12,575.47 4,195.03 500.60 17,271.10 103,626.60
4.11.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.11.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.11.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.11.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.11.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.11.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.11.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.11.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.11.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.11.6.A.3.1 ø200 mm nos. 1.00 11,079.12 4,371.74 452.35 15,903.21 15,903.21


4.11.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.11.6.A.3.3 ø300 mm nos. 4.00 12,111.88 4,863.80 496.05 17,471.72 69,886.88
4.11.6.A.3.4 ø350 mm nos. 5.00 12,575.47 5,100.93 515.95 18,192.35 90,961.75
4.11.6.A.3.5 ø400 mm nos. 14.00 13,090.13 5,350.74 538.14 18,979.00 265,706.00
4.11.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.11.6.A.3.7 ø500 mm nos. 2.00 14,177.39 5,852.76 583.83 20,613.98 41,227.96
4.11.6.A.3.8 ø600 mm nos. 16.00 15,264.65 6,359.64 629.91 22,254.20 356,067.20
4.11.6.A.3.9 ø700 mm nos. 2.00 16,460.93 6,881.60 679.59 24,022.12 48,044.24
4.11.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.11.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.11.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 151 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Total Unit
Material Labour Equipment (BDT)
Cutting Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Sub-total 4.11: Column 'j' to be carried forward to


. 724,323,562.97
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 152 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.12 INSTALLATION of LOOP 312
4.12.1 Miscellaneous works during implementation
4.12.1.1 Setting-out LS 1.00 428,014.00 428,014.00
4.12.1.2 General works and site tests LS 1.00 856,028.00 856,028.00
4.12.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.12.2.1 LS 1.00 856,028.00 856,028.00
installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.12.2.2 LS 1.00 321,010.50 321,010.50
construction completed & acceptance certificate
4.12.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.12.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.12.2.5 Development and submission of GIS based As-built drawings LS 1.00 535,017.50 535,017.50
4.12.2.6 Post Construction modelling LS 1.00 64,202.10 64,202.10

Supply and Installation of GRP pipes in accordance with the technical


specification and the standard detail drawing, of any diameter and to
the depths specified below, including fitting, fixing of all items, road
4.12.3 cutting permission fee, temporary road reinstatement, dismantling of -
existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.12.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.12.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.12.3.A.1.1 ø200 mm m 6,002.30 3,596.40 1,581.32 878.18 5,811.99 11,867.89 71,234,629.80


4.12.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.12.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 153 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -


4.12.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.12.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.12.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.12.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.12.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.12.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.12.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.12.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.12.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.12.3.A.2.1 ø200 mm m 10,334 3,890.84 1,719.29 901.27 5,811.99 12,323.40 127,348,737.88


4.12.3.A.2.2 ø250 mm m 918 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 12,571,524.42
4.12.3.A.2.3 ø300 mm m 421 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 6,184,647.29
4.12.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.12.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.12.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.12.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.12.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.12.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.12.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.12.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.12.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.12.3.A.3 Pipe invert depth greater than 5m ( > 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 154 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.3.A.3.1 ø200 mm m 1,165 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 30,902,913.64


4.12.3.A.3.2 ø250 mm m 514 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 14,345,079.55
4.12.3.A.3.3 ø300 mm m 489 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 14,152,074.57
4.12.3.A.3.4 ø350 mm m 231 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 6,770,115.39
4.12.3.A.3.5 ø400 mm m 86 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 2,774,276.29
4.12.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.12.3.A.3.7 ø500 mm m 99 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 3,638,570.94
4.12.3.A.3.8 ø600 mm m 399 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 16,246,204.90
4.12.3.A.3.9 ø700 mm m 742 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 35,965,597.95
4.12.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.12.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.12.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.12.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.12.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.12.3.B.1.1 ø200 mm m -
4.12.3.B.1.2 ø250 mm m -
4.12.3.B.1.3 ø300 mm m -
4.12.3.B.1.4 ø350 mm m -
4.12.3.B.1.5 ø400 mm m -
4.12.3.B.1.6 ø450 mm m -
4.12.3.B.1.7 ø500 mm m -
4.12.3.B.1.8 ø600 mm m -
4.12.3.B.1.9 ø700 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 155 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.3.B.1.10 ø800 mm m -
4.12.3.B.1.11 ø900 mm m -
4.12.3.B.1.12 ø1000 mm m -

4.12.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.12.3.B.2.1 ø200 mm m -
4.12.3.B.2.2 ø250 mm m -
4.12.3.B.2.3 ø300 mm m -
4.12.3.B.2.4 ø350 mm m -
4.12.3.B.2.5 ø400 mm m -
4.12.3.B.2.6 ø450 mm m -
4.12.3.B.2.7 ø500 mm m -
4.12.3.B.2.8 ø600 mm m -
4.12.3.B.2.9 ø700 mm m -
4.12.3.B.2.10 ø800 mm m -

4.12.3.B.2.11 ø900 mm m -

4.12.3.B.2.12 ø1000 mm m -

4.12.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.12.3.B.3.1 ø200 mm m -
4.12.3.B.3.2 ø250 mm m -
4.12.3.B.3.3 ø300 mm m -
4.12.3.B.3.4 ø350 mm m -
4.12.3.B.3.5 ø400 mm m -
4.12.3.B.3.6 ø450 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 156 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.3.B.3.7 ø500 mm m -
4.12.3.B.3.8 ø600 mm m -
4.12.3.B.3.9 ø700 mm m -
4.12.3.B.3.10 ø800 mm m -

4.12.3.B.3.11 ø900 mm m -

4.12.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance


with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.12.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.

4.12.4.A Normal Manhole Rectangular or circular

4.12.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.12.4.A.1.1 ø200 mm nos. 278.00 108,465.00 17,845.00 10,137.00 136,447.00 37,932,266.00


4.12.4.A.1.2 ø250 mm nos. 1.00 109,101.00 17,858.00 10,150.00 137,109.00 137,109.00
4.12.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.12.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.12.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.12.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.12.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.12.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 157 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -


4.12.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.12.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.12.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.12.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.12.4.A.2.1 ø200 mm nos. 264 133,076.00 22,507.00 12,324.00 167,907.00 44,327,448.00


4.12.4.A.2.2 ø250 mm nos. 29 133,713.00 22,520.00 12,338.00 168,571.00 4,888,559.00
4.12.4.A.2.3 ø300 mm nos. 16 134,286.00 22,521.00 12,350.00 169,157.00 2,706,512.00
4.12.4.A.2.4 ø350 mm nos. 3 134,923.00 22,534.00 12,363.00 169,820.00 509,460.00
4.12.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.12.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.12.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.12.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.12.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.12.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.12.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.12.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.12.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.12.4.A.3.1 ø200 mm nos. 31 182,295 31,825 16,700 230,820.00 7,155,420.00


4.12.4.A.3.2 ø250 mm nos. 15 182,932 31,838 16,713 231,483.00 3,472,245.00
4.12.4.A.3.3 ø300 mm nos. 8 183,505 31,840 16,725 232,070.00 1,856,560.00
4.12.4.A.3.4 ø350 mm nos. 4 184,142 31,853 16,738 232,733.00 930,932.00
4.12.4.A.3.5 ø400 mm nos. 2 184,778 31,866 16,752 233,396.00 466,792.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 158 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -


4.12.4.A.3.7 ø500 mm nos. 3 185,988 31,881 16,777 234,646.00 703,938.00
4.12.4.A.3.8 ø600 mm nos. 16 187,267 31,910 16,805 235,982.00 3,775,712.00
4.12.4.A.3.9 ø700 mm nos. 26 188,477 31,924 16,830 237,231.00 6,168,006.00
4.12.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.12.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.12.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.12.4.B Drop Manhole Rectangular or circular

4.12.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.12.4.B.1.1 ø200 mm nos. 37.00 177,870.00 34,380.00 19,812.00 232,062.00 8,586,294.00


4.12.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.12.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.12.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.12.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.12.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.12.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.12.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.12.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.12.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.12.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.12.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.12.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.12.4.B.2.1 ø200 mm nos. 34 216,110.00 42,604.00 23,944.00 282,658.00 9,610,372.00


2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 159 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.B.2.2 ø250 mm nos. 2 216,602.00 42,630.00 23,972.00 283,204.00 566,408.00


4.12.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00
4.12.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.12.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.12.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.12.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.12.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.12.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.12.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.12.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.12.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.12.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.12.4.B.3.1 ø200 mm nos. 3 292,584.00 59,046.00 32,206.00 383,836.00 1,151,508.00


4.12.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.12.4.B.3.3 ø300 mm nos. 2 293,442.00 59,074.00 32,256.00 384,772.00 769,544.00
4.12.4.B.3.4 ø350 mm nos. 1 293,934.00 59,100.00 32,284.00 385,318.00 385,318.00
4.12.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.12.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.12.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.12.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.12.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.12.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.12.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 160 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.12.4.C Service connections Manhole Rectangular or circular -

4.12.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.12.4.C.1.1 ø200 mm nos. 334.00 108,465.00 17,845.00 10,137.00 136,447.00 45,573,298.00


4.12.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.12.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.12.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.12.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.12.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.12.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.12.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.12.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.12.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.12.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.12.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.12.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.12.4.C.2.1 ø200 mm nos. 575 133,076.00 22,507.00 12,324.00 167,907.00 96,546,525.00


4.12.4.C.2.2 ø250 mm nos. 51 133,713.00 22,520.00 12,338.00 168,571.00 8,597,121.00
4.12.4.C.2.3 ø300 mm nos. 24 134,286.00 22,521.00 12,350.00 169,157.00 4,059,768.00
4.12.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.12.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.12.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.12.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 161 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -


4.12.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.12.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.12.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.12.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.12.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.12.4.C.3.1 ø200 mm nos. 65 182,295.00 31,825.00 16,700.00 230,820.00 15,003,300.00


4.12.4.C.3.2 ø250 mm nos. 29 182,932.00 31,838.00 16,713.00 231,483.00 6,713,007.00
4.12.4.C.3.3 ø300 mm nos. 28 183,505.00 31,840.00 16,725.00 232,070.00 6,497,960.00
4.12.4.C.3.4 ø350 mm nos. 13 184,142.00 31,853.00 16,738.00 232,733.00 3,025,529.00
4.12.4.C.3.5 ø400 mm nos. 5 184,778.00 31,866.00 16,752.00 233,396.00 1,166,980.00
4.12.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.12.4.C.3.7 ø500 mm nos. 6 185,988.00 31,881.00 16,777.00 234,646.00 1,407,876.00
4.12.4.C.3.8 ø600 mm nos. 23 187,267.00 31,910.00 16,805.00 235,982.00 5,427,586.00
4.12.4.C.3.9 ø700 mm nos. 42 188,477.00 31,924.00 16,830.00 237,231.00 9,963,702.00
4.12.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.12.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.12.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 162 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures, site
4.12.5
cleaning, earth cutting, sand filling, earth refilling , coarse material s/
khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.12.5.1 ø150 mm nos. 1,784.00 40,766.88 13,972.83 8,265.14 63,004.85 112,400,652.40

4.12.5.2 ø200 mm nos. 714.00 44,627.58 15,581.46 9,230.31 69,439.35 49,579,695.90


4.12.5.3 ø250 mm nos. 714.00 51,128.58 18,290.21 10,855.56 80,274.35 57,315,885.90
4.12.5.4 ø300 mm nos. 357.00 55,471.38 20,099.71 11,941.26 87,512.35 31,241,908.95

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of existing
4.12.6 structures, site cleaning, earth cutting, sand filling, earth refilling , -
coarse material s/ khoa filling, as per approved drawing and
specification.

4.12.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.12.6.A.1.1 ø200 mm nos. 111.00 11,079.12 3,235.25 433.10 14,747.46 1,636,968.06


4.12.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.12.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.12.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.12.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.12.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.12.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.12.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.12.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 163 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.12.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.12.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.12.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.12.6.A.2.1 ø200 mm nos. 192.00 11,079.12 3,614.08 439.51 15,132.71 2,905,480.32


4.12.6.A.2.2 ø250 mm nos. 17.00 11,597.22 3,810.28 460.57 15,868.07 269,757.19
4.12.6.A.2.3 ø300 mm nos. 8.00 12,111.88 4,007.30 481.54 16,600.72 132,805.76
4.12.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.12.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.12.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.12.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.12.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.12.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.12.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.12.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.12.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.12.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.12.6.A.3.1 ø200 mm nos. 22.00 11,079.12 4,371.74 452.35 15,903.21 349,870.62


4.12.6.A.3.2 ø250 mm nos. 10.00 11,597.22 4,617.36 474.24 16,688.82 166,888.20
4.12.6.A.3.3 ø300 mm nos. 9.00 12,111.88 4,863.80 496.05 17,471.72 157,245.48
4.12.6.A.3.4 ø350 mm nos. 4.00 12,575.47 5,100.93 515.95 18,192.35 72,769.40
4.12.6.A.3.5 ø400 mm nos. 2.00 13,090.13 5,350.74 538.14 18,979.00 37,958.00
4.12.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 164 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.12.6.A.3.7 ø500 mm nos. 2.00 14,177.39 5,852.76 583.83 20,613.98 41,227.96


4.12.6.A.3.8 ø600 mm nos. 8.00 15,264.65 6,359.64 629.91 22,254.20 178,033.60
4.12.6.A.3.9 ø700 mm nos. 14.00 16,460.93 6,881.60 679.59 24,022.12 336,309.68
4.12.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.12.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.12.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.12: Column 'j' to be carried forward to


. 942,407,281.13
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 165 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.13 INSTALLATION of LOOP 313
4.13.1 Miscellaneous works during implementation
4.13.1.1 Setting-out LS 1.00 694,340.00 694,340.00
4.13.1.2 General works and site tests LS 1.00 1,388,680.00 1,388,680.00
4.13.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion


4.13.2.1 LS 1.00 1,388,680.00 1,388,680.00
of installation, construction, documentation, reporting etc.

Commissioning and final inspection / testing before issuing


4.13.2.2 LS 1.00 520,755.00 520,755.00
construction completed & acceptance certificate
4.13.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.13.2.4 LS 1.00 7,500.00 7,500.00
manuals

4.13.2.5 Development and submission of GIS based As-built drawings LS 1.00 867,925.00 867,925.00

4.13.2.6 Post Construction modelling LS 1.00 104,151.00 104,151.00

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting,
4.13.3 fixing of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse material s/ khoa
filling, concreting as per approved drawing and specification.

4.13.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.13.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.13.3.A.1.1 ø200 mm m 19,127.40 3,596.40 1,581.32 878.18 5,811.99 11,867.89 227,001,858.96


4.13.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 166 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -


4.13.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.13.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.13.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.13.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.13.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.13.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.13.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.13.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.13.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.13.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.13.3.A.2.1 ø200 mm m 11,239.30 3,890.84 1,719.29 901.27 5,811.99 12,323.40 138,506,340.27


4.13.3.A.2.2 ø250 mm m 834.60 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 11,430,650.70
4.13.3.A.2.3 ø300 mm m 151.50 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 2,226,649.39
4.13.3.A.2.4 ø350 mm m - 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.13.3.A.2.5 ø400 mm m 307.10 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 5,492,258.72
4.13.3.A.2.6 ø450 mm m - 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.13.3.A.2.7 ø500 mm m 289.60 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 6,493,440.34
4.13.3.A.2.8 ø600 mm m 122.40 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 3,225,410.64
4.13.3.A.2.9 ø700 mm m - 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.13.3.A.2.10 ø800 mm m - 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.13.3.A.2.11 ø900 mm m - 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.13.3.A.2.12 ø1000 mm m - 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 167 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.13.3.A.3.1 ø200 mm m 181.30 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 4,808,770.27


4.13.3.A.3.2 ø250 mm m 161.20 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 4,497,135.01
4.13.3.A.3.3 ø300 mm m 315.30 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 9,121,318.71
4.13.3.A.3.4 ø350 mm m 288.50 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 8,466,312.48
4.13.3.A.3.5 ø400 mm m - 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.13.3.A.3.6 ø450 mm m - 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.13.3.A.3.7 ø500 mm m - 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.13.3.A.3.8 ø600 mm m 355.30 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 14,452,370.06
4.13.3.A.3.9 ø700 mm m 371.40 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 18,007,041.09
4.13.3.A.3.10 ø800 mm m 364.30 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 19,808,641.38

4.13.3.A.3.11 ø900 mm m 580.20 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 30,979,585.93

4.13.3.A.3.12 ø1000 mm m 27.60 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 1,562,688.42

4.13.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.13.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.13.3.B.1.1 ø200 mm m -
4.13.3.B.1.2 ø250 mm m -
4.13.3.B.1.3 ø300 mm m -
4.13.3.B.1.4 ø350 mm m -
4.13.3.B.1.5 ø400 mm m -
4.13.3.B.1.6 ø450 mm m -
4.13.3.B.1.7 ø500 mm m -
4.13.3.B.1.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 168 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.3.B.1.9 ø700 mm m -
4.13.3.B.1.10 ø800 mm m -
4.13.3.B.1.11 ø900 mm m -
4.13.3.B.1.12 ø1000 mm m -

4.13.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.13.3.B.2.1 ø200 mm m -
4.13.3.B.2.2 ø250 mm m -
4.13.3.B.2.3 ø300 mm m -
4.13.3.B.2.4 ø350 mm m -
4.13.3.B.2.5 ø400 mm m -
4.13.3.B.2.6 ø450 mm m -
4.13.3.B.2.7 ø500 mm m -
4.13.3.B.2.8 ø600 mm m -
4.13.3.B.2.9 ø700 mm m -
4.13.3.B.2.10 ø800 mm m -

4.13.3.B.2.11 ø900 mm m -

4.13.3.B.2.12 ø1000 mm m -

4.13.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.13.3.B.3.1 ø200 mm m -
4.13.3.B.3.2 ø250 mm m -
4.13.3.B.3.3 ø300 mm m -
4.13.3.B.3.4 ø350 mm m -
4.13.3.B.3.5 ø400 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 169 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.3.B.3.6 ø450 mm m -
4.13.3.B.3.7 ø500 mm m -
4.13.3.B.3.8 ø600 mm m -
4.13.3.B.3.9 ø700 mm m -
4.13.3.B.3.10 ø800 mm m -

4.13.3.B.3.11 ø900 mm m -

4.13.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in


accordance with the technical specification and the standard
detailed drawings, of any diameter/ size and to the depths
specified below, including fitting, fixing of all items, road cutting
4.13.4 permission fee, temporary road reinstatement, dismantling of
existing structures, site cleaning, earth cutting, sand filling,
earth refilling , coarse materials/ khoa filling, concreting,
Approved brand CI Manhole cover, as per approved drawing
and specification.

4.13.4.A Normal Manhole Rectangular or circular

4.13.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.13.4.A.1.1 ø200 mm nos. 567.00 108,465.00 17,845.00 10,137.00 136,447.00 77,365,449.00


4.13.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.13.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.13.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.13.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.13.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.13.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 170 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -


4.13.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.13.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.13.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.13.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.13.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.13.4.A.2.1 ø200 mm nos. 245 133,076.00 22,507.00 12,324.00 167,907.00 41,137,215.00


4.13.4.A.2.2 ø250 mm nos. 33 133,713.00 22,520.00 12,338.00 168,571.00 5,562,843.00
4.13.4.A.2.3 ø300 mm nos. 9 134,286.00 22,521.00 12,350.00 169,157.00 1,522,413.00
4.13.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.13.4.A.2.5 ø400 mm nos. 9 135,559.00 22,547.00 12,377.00 170,483.00 1,534,347.00
4.13.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.13.4.A.2.7 ø500 mm nos. 9 136,776.00 22,565.00 12,402.00 171,743.00 1,545,687.00
4.13.4.A.2.8 ø600 mm nos. 5 138,048.00 22,591.00 12,430.00 173,069.00 865,345.00
4.13.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.13.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.13.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.13.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.13.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.13.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.13.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.13.4.A.3.3 ø300 mm nos. 7 183,505 31,840 16,725 232,070.00 1,624,490.00
4.13.4.A.3.4 ø350 mm nos. 10 184,142 31,853 16,738 232,733.00 2,327,330.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 171 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -


4.13.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.13.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.13.4.A.3.8 ø600 mm nos. 9 187,267 31,910 16,805 235,982.00 2,123,838.00
4.13.4.A.3.9 ø700 mm nos. 14 188,477 31,924 16,830 237,231.00 3,321,234.00
4.13.4.A.3.10 ø800 mm nos. 12 189,750 31,950 16,858 238,558.00 2,862,696.00

4.13.4.A.3.11 ø900 mm nos. 18 190,967 31,968 16,883 239,818.00 4,316,724.00

4.13.4.A.3.12 ø1000 mm nos. 1 192,239 31,994 16,910 241,143.00 241,143.00

4.13.4.B Drop Manhole Rectangular or circular

4.13.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.13.4.B.1.1 ø200 mm nos. 62.00 177,870.00 34,380.00 19,812.00 232,062.00 14,387,844.00


4.13.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.13.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.13.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.13.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.13.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.13.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.13.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.13.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.13.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.13.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.13.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.13.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 172 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.4.B.2.1 ø200 mm nos. 18 216,110.00 42,604.00 23,944.00 282,658.00 5,087,844.00


4.13.4.B.2.2 ø250 mm nos. 2 216,602.00 42,630.00 23,972.00 283,204.00 566,408.00
4.13.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00
4.13.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.13.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.13.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.13.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.13.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.13.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.13.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.13.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.13.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.13.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.13.4.B.3.1 ø200 mm nos. 2 292,584.00 59,046.00 32,206.00 383,836.00 767,672.00


4.13.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.13.4.B.3.3 ø300 mm nos. 1 293,442.00 59,074.00 32,256.00 384,772.00 384,772.00
4.13.4.B.3.4 ø350 mm nos. 1 293,934.00 59,100.00 32,284.00 385,318.00 385,318.00
4.13.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.13.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.13.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.13.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.13.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.13.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 173 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.13.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.13.4.C Service connections Manhole Rectangular or circular -

S/C Manhole invert depth less than equal


4.13.4.C.1 -
to 3m ( ≤ 3m)
4.13.4.C.1.1 ø200 mm nos. 1,063.00 108,465.00 17,845.00 10,137.00 136,447.00 145,043,161.00
4.13.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.13.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.13.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.13.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.13.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.13.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.13.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.13.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.13.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.13.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.13.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.13.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.13.4.C.2.1 ø200 mm nos. 625.00 133,076.00 22,507.00 12,324.00 167,907.00 104,941,875.00


4.13.4.C.2.2 ø250 mm nos. 47.00 133,713.00 22,520.00 12,338.00 168,571.00 7,922,837.00
4.13.4.C.2.3 ø300 mm nos. 9.00 134,286.00 22,521.00 12,350.00 169,157.00 1,522,413.00
4.13.4.C.2.4 ø350 mm nos. - 134,923.00 22,534.00 12,363.00 169,820.00 -
4.13.4.C.2.5 ø400 mm nos. 18.00 135,559.00 22,547.00 12,377.00 170,483.00 3,068,694.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 174 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.4.C.2.6 ø450 mm nos. - 136,195.00 22,560.00 12,391.00 171,146.00 -


4.13.4.C.2.7 ø500 mm nos. 17.00 136,776.00 22,565.00 12,402.00 171,743.00 2,919,631.00
4.13.4.C.2.8 ø600 mm nos. 7.00 138,048.00 22,591.00 12,430.00 173,069.00 1,211,483.00
4.13.4.C.2.9 ø700 mm nos. - 139,258.00 22,605.00 12,455.00 174,318.00 -
4.13.4.C.2.10 ø800 mm nos. - 140,531.00 22,632.00 12,483.00 175,646.00 -

4.13.4.C.2.11 ø900 mm nos. - 141,748.00 22,649.00 12,508.00 176,905.00 -

4.13.4.C.2.12 ø1000 mm nos. - 143,020.00 22,675.00 12,535.00 178,230.00 -

4.13.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.13.4.C.3.1 ø200 mm nos. 11.00 182,295.00 31,825.00 16,700.00 230,820.00 2,539,020.00


4.13.4.C.3.2 ø250 mm nos. 9.00 182,932.00 31,838.00 16,713.00 231,483.00 2,083,347.00
4.13.4.C.3.3 ø300 mm nos. 18.00 183,505.00 31,840.00 16,725.00 232,070.00 4,177,260.00
4.13.4.C.3.4 ø350 mm nos. 17.00 184,142.00 31,853.00 16,738.00 232,733.00 3,956,461.00
4.13.4.C.3.5 ø400 mm nos. - 184,778.00 31,866.00 16,752.00 233,396.00 -
4.13.4.C.3.6 ø450 mm nos. - 185,414.00 31,879.00 16,766.00 234,059.00 -
4.13.4.C.3.7 ø500 mm nos. - 185,988.00 31,881.00 16,777.00 234,646.00 -
4.13.4.C.3.8 ø600 mm nos. 20.00 187,267.00 31,910.00 16,805.00 235,982.00 4,719,640.00
4.13.4.C.3.9 ø700 mm nos. 21.00 188,477.00 31,924.00 16,830.00 237,231.00 4,981,851.00
4.13.4.C.3.10 ø800 mm nos. 21.00 189,750.00 31,950.00 16,858.00 238,558.00 5,009,718.00

4.13.4.C.3.11 ø900 mm nos. 33.00 190,967.00 31,968.00 16,883.00 239,818.00 7,913,994.00

4.13.4.C.3.12 ø1000 mm nos. 2.00 192,239.00 31,994.00 16,910.00 241,143.00 482,286.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 175 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes


including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing
4.13.5 structures, site cleaning, earth cutting, sand filling, earth refilling
, coarse material s/ khoa filling, concreting, individual house
hold inspection pit, average length of 10m as per approved
drawing and specification.

4.13.5.1 ø150 mm nos. 2,894.00 40,766.88 13,972.83 8,265.14 63,004.85 182,336,035.90

4.13.5.2 ø200 mm nos. 1,157.00 44,627.58 15,581.46 9,230.31 69,439.35 80,341,327.95


4.13.5.3 ø250 mm nos. 1,157.00 51,128.58 18,290.21 10,855.56 80,274.35 92,877,422.95
4.13.5.4 ø300 mm nos. 579.00 55,471.38 20,099.71 11,941.26 87,512.35 50,669,650.65

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.13.6 existing structures, site cleaning, earth cutting, sand filling, -
earth refilling , coarse material s/ khoa filling, as per approved
drawing and specification.

4.13.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.13.6.A.1.1 ø200 mm nos. 354.00 11,079.12 3,235.25 433.10 14,747.46 5,220,600.84


4.13.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.13.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.13.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.13.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.13.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.13.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.13.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.13.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 176 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -


4.13.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.13.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.13.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.13.6.A.2.1 ø200 mm nos. 208.00 11,079.12 3,614.08 439.51 15,132.71 3,147,603.68


4.13.6.A.2.2 ø250 mm nos. 16.00 11,597.22 3,810.28 460.57 15,868.07 253,889.12
4.13.6.A.2.3 ø300 mm nos. 3.00 12,111.88 4,007.30 481.54 16,600.72 49,802.16
4.13.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.13.6.A.2.5 ø400 mm nos. 6.00 13,090.13 4,395.42 521.95 18,007.50 108,045.00
4.13.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.13.6.A.2.7 ø500 mm nos. 6.00 14,177.39 4,798.62 565.97 19,541.98 117,251.88
4.13.6.A.2.8 ø600 mm nos. 2.00 15,264.65 5,206.67 610.38 21,081.70 42,163.40
4.13.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.13.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.13.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.13.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.13.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.13.6.A.3.1 ø200 mm nos. 4.00 11,079.12 4,371.74 452.35 15,903.21 63,612.84


4.13.6.A.3.2 ø250 mm nos. 3.00 11,597.22 4,617.36 474.24 16,688.82 50,066.46
4.13.6.A.3.3 ø300 mm nos. 6.00 12,111.88 4,863.80 496.05 17,471.72 104,830.32
4.13.6.A.3.4 ø350 mm nos. 6.00 12,575.47 5,100.93 515.95 18,192.35 109,154.10
4.13.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.13.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 177 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.13.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -


4.13.6.A.3.8 ø600 mm nos. 7.00 15,264.65 6,359.64 629.91 22,254.20 155,779.40
4.13.6.A.3.9 ø700 mm nos. 7.00 16,460.93 6,881.60 679.59 24,022.12 168,154.84
4.13.6.A.3.10 ø800 mm nos. 7.00 17,602.69 7,398.46 727.66 25,728.81 180,101.67

4.13.6.A.3.11 ø900 mm nos. 11.00 18,853.47 7,930.39 779.34 27,563.20 303,195.20

4.13.6.A.3.12 ø1000 mm nos. 1.00 20,104.25 8,467.18 831.39 29,402.83 29,402.83

Sub-total 4.13: Column 'j' to be carried forward to


. 1,398,103,473.55
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 178 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi
4.14 INSTALLATION of LOOP 314
4.14.1 Miscellaneous works during implementation
4.14.1.1 Setting-out LS 1.00 228,062.00 228,062.00
4.14.1.2 General works and site tests LS 1.00 456,124.00 456,124.00
4.14.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of


4.14.2.1 LS 1.00 456,124.00 456,124.00
installation, construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing
4.14.2.2 LS 1.00 171,046.50 171,046.50
construction completed & acceptance certificate
4.14.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.14.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.14.2.5 Development and submission of GIS based As-built drawings LS 1.00 285,077.50 285,077.50
4.14.2.6 Post Construction modelling LS 1.00 34,209.30 34,209.30

Supply and Installation of GRP pipes in accordance with the


technical specification and the standard detail drawing, of any
diameter and to the depths specified below, including fitting, fixing
4.14.3 of all items, road cutting permission fee, temporary road -
reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse material s/ khoa
filling, concreting as per approved drawing and specification.

4.14.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.14.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.14.3.A.1.1 ø200 mm m 3,274.10 3,596.40 1,581.32 878.18 5,811.99 11,867.89 38,856,655.19


4.14.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.14.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.14.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 179 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -


4.14.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.14.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.14.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.14.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.14.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.14.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -
4.14.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.14.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.14.3.A.2.1 ø200 mm m 5,215.70 3,890.84 1,719.29 901.27 5,811.99 12,323.40 64,275,134.48


4.14.3.A.2.2 ø250 mm m 276.70 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 3,789,672.96
4.14.3.A.2.3 ø300 mm m 161.10 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 2,367,744.01
4.14.3.A.2.4 ø350 mm m 258.50 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 3,910,308.54
4.14.3.A.2.5 ø400 mm m 18.50 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 330,858.96
4.14.3.A.2.6 ø450 mm m - 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.14.3.A.2.7 ø500 mm m - 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.14.3.A.2.8 ø600 mm m - 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.14.3.A.2.9 ø700 mm m - 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.14.3.A.2.10 ø800 mm m - 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.14.3.A.2.11 ø900 mm m - 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.14.3.A.2.12 ø1000 mm m - 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.14.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.14.3.A.3.1 ø200 mm m 1,040.60 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 27,600,696.88

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 180 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.3.A.3.2 ø250 mm m 402.60 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 11,231,678.39


4.14.3.A.3.3 ø300 mm m 378.00 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 10,935,168.00
4.14.3.A.3.4 ø350 mm m 128.10 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 3,759,218.82
4.14.3.A.3.5 ø400 mm m 65.40 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 2,102,406.36
4.14.3.A.3.6 ø450 mm m 141.70 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 4,649,087.66
4.14.3.A.3.7 ø500 mm m 42.10 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 1,545,750.11
4.14.3.A.3.8 ø600 mm m - 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.14.3.A.3.9 ø700 mm m - 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.14.3.A.3.10 ø800 mm m - 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.14.3.A.3.11 ø900 mm m - 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.14.3.A.3.12 ø1000 mm m - 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.14.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.14.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.14.3.B.1.1 ø200 mm m -
4.14.3.B.1.2 ø250 mm m -
4.14.3.B.1.3 ø300 mm m -
4.14.3.B.1.4 ø350 mm m -
4.14.3.B.1.5 ø400 mm m -
4.14.3.B.1.6 ø450 mm m -
4.14.3.B.1.7 ø500 mm m -
4.14.3.B.1.8 ø600 mm m -
4.14.3.B.1.9 ø700 mm m -
4.14.3.B.1.10 ø800 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 181 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.3.B.1.11 ø900 mm m -
4.14.3.B.1.12 ø1000 mm m -

4.14.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.14.3.B.2.1 ø200 mm m -
4.14.3.B.2.2 ø250 mm m -
4.14.3.B.2.3 ø300 mm m -
4.14.3.B.2.4 ø350 mm m -
4.14.3.B.2.5 ø400 mm m -
4.14.3.B.2.6 ø450 mm m -
4.14.3.B.2.7 ø500 mm m -
4.14.3.B.2.8 ø600 mm m -
4.14.3.B.2.9 ø700 mm m -
4.14.3.B.2.10 ø800 mm m -

4.14.3.B.2.11 ø900 mm m -

4.14.3.B.2.12 ø1000 mm m -

4.14.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.14.3.B.3.1 ø200 mm m -
4.14.3.B.3.2 ø250 mm m -
4.14.3.B.3.3 ø300 mm m -
4.14.3.B.3.4 ø350 mm m -
4.14.3.B.3.5 ø400 mm m -
4.14.3.B.3.6 ø450 mm m -
4.14.3.B.3.7 ø500 mm m -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 182 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.3.B.3.8 ø600 mm m -
4.14.3.B.3.9 ø700 mm m -
4.14.3.B.3.10 ø800 mm m -

4.14.3.B.3.11 ø900 mm m -

4.14.3.B.3.12 ø1000 mm m -
Supply and Installation of RCC Manholes chambers in accordance
with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary
4.14.4
road reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per
approved drawing and specification.
4.14.4.A Normal Manhole Rectangular or circular

4.14.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.14.4.A.1.1 ø200 mm nos. 146.00 108,465.00 17,845.00 10,137.00 136,447.00 19,921,262.00


4.14.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.14.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.14.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.14.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.14.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.14.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.14.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.14.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.14.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.14.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 183 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.14.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.14.4.A.2.1 ø200 mm nos. 158 133,076.00 22,507.00 12,324.00 167,907.00 26,529,306.00


4.14.4.A.2.2 ø250 mm nos. 12 133,713.00 22,520.00 12,338.00 168,571.00 2,022,852.00
4.14.4.A.2.3 ø300 mm nos. 7 134,286.00 22,521.00 12,350.00 169,157.00 1,184,099.00
4.14.4.A.2.4 ø350 mm nos. 13 134,923.00 22,534.00 12,363.00 169,820.00 2,207,660.00
4.14.4.A.2.5 ø400 mm nos. 3 135,559.00 22,547.00 12,377.00 170,483.00 511,449.00
4.14.4.A.2.6 ø450 mm nos. 1 136,195.00 22,560.00 12,391.00 171,146.00 171,146.00
4.14.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.14.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.14.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.14.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.14.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.14.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.14.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.14.4.A.3.1 ø200 mm nos. 37 182,295 31,825 16,700 230,820.00 8,540,340.00


4.14.4.A.3.2 ø250 mm nos. 11 182,932 31,838 16,713 231,483.00 2,546,313.00
4.14.4.A.3.3 ø300 mm nos. 6 183,505 31,840 16,725 232,070.00 1,392,420.00
4.14.4.A.3.4 ø350 mm nos. 2 184,142 31,853 16,738 232,733.00 465,466.00
4.14.4.A.3.5 ø400 mm nos. 1 184,778 31,866 16,752 233,396.00 233,396.00
4.14.4.A.3.6 ø450 mm nos. 3 185,414 31,879 16,766 234,059.00 702,177.00
4.14.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.14.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 184 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -


4.14.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.14.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.14.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.14.4.B Drop Manhole Rectangular or circular

4.14.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.14.4.B.1.1 ø200 mm nos. 40.00 177,870.00 34,380.00 19,812.00 232,062.00 9,282,480.00


4.14.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.14.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.14.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.14.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.14.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.14.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.14.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.14.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.14.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.14.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.14.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.14.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.14.4.B.2.1 ø200 mm nos. 46 216,110.00 42,604.00 23,944.00 282,658.00 13,002,268.00


4.14.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.14.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.14.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 185 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -


4.14.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.14.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.14.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.14.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.14.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.14.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.14.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.14.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.14.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.14.4.B.3.2 ø250 mm nos. 2 293,074.00 59,072.00 32,234.00 384,380.00 768,760.00
4.14.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.14.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.14.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.14.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.14.4.B.3.7 ø500 mm nos. 1 295,284.00 59,156.00 32,362.00 386,802.00 386,802.00
4.14.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.14.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.14.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.14.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.14.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.14.4.C Service connections Manhole Rectangular or circular -

4.14.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -


2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 186 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.4.C.1.1 ø200 mm nos. 182.00 108,465.00 17,845.00 10,137.00 136,447.00 24,833,354.00


4.14.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.14.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.14.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.14.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.14.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.14.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.14.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.14.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.14.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.14.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.14.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.14.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.14.4.C.2.1 ø200 mm nos. 290 133,076.00 22,507.00 12,324.00 167,907.00 48,693,030.00


4.14.4.C.2.2 ø250 mm nos. 16 133,713.00 22,520.00 12,338.00 168,571.00 2,697,136.00
4.14.4.C.2.3 ø300 mm nos. 9 134,286.00 22,521.00 12,350.00 169,157.00 1,522,413.00
4.14.4.C.2.4 ø350 mm nos. 15 134,923.00 22,534.00 12,363.00 169,820.00 2,547,300.00
4.14.4.C.2.5 ø400 mm nos. 2 135,559.00 22,547.00 12,377.00 170,483.00 340,966.00
4.14.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.14.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.14.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.14.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.14.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 187 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.14.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.14.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.14.4.C.3.1 ø200 mm nos. 58 182,295.00 31,825.00 16,700.00 230,820.00 13,387,560.00


4.14.4.C.3.2 ø250 mm nos. 23 182,932.00 31,838.00 16,713.00 231,483.00 5,324,109.00
4.14.4.C.3.3 ø300 mm nos. 21 183,505.00 31,840.00 16,725.00 232,070.00 4,873,470.00
4.14.4.C.3.4 ø350 mm nos. 8 184,142.00 31,853.00 16,738.00 232,733.00 1,861,864.00
4.14.4.C.3.5 ø400 mm nos. 4 184,778.00 31,866.00 16,752.00 233,396.00 933,584.00
4.14.4.C.3.6 ø450 mm nos. 8 185,414.00 31,879.00 16,766.00 234,059.00 1,872,472.00
4.14.4.C.3.7 ø500 mm nos. 3 185,988.00 31,881.00 16,777.00 234,646.00 703,938.00
4.14.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.14.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.14.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.14.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.14.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


Supply and Installation of service connections with GRP pipes
including fitting, fixing of all items, road cutting permission fee,
temporary road reinstatement, dismantling of existing structures,
4.14.5 site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection
pit, average length of 10m as per approved drawing and
specification.
4.14.5.1 ø150 mm nos. 951 40,766.88 13,972.83 8,265.14 63,004.85 59,917,612.35

4.14.5.2 ø200 mm nos. 380 44,627.58 15,581.46 9,230.31 69,439.35 26,414,728.74


4.14.5.3 ø250 mm nos. 380 51,128.58 18,290.21 10,855.56 80,274.35 30,536,362.74

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 188 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.5.4 ø300 mm nos. 190 55,471.38 20,099.71 11,941.26 87,512.35 16,644,848.97

Construction of concrete thrust blocks including road cutting


permission fee, temporary road reinstatement, dismantling of
4.14.6 existing structures, site cleaning, earth cutting, sand filling, earth -
refilling , coarse material s/ khoa filling, as per approved drawing
and specification.

4.2.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.14.6.A.1.1 ø200 mm nos. 61.00 11,079.12 3,235.25 433.10 14,747.46 899,595.06


4.14.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.14.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.14.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.14.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.14.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.14.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.14.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.14.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.14.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.14.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.14.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.14.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.14.6.A.2.1 ø200 mm nos. 97.00 11,079.12 3,614.08 439.51 15,132.71 1,467,872.87


4.14.6.A.2.2 ø250 mm nos. 5.00 11,597.22 3,810.28 460.57 15,868.07 79,340.35
4.14.6.A.2.3 ø300 mm nos. 3.00 12,111.88 4,007.30 481.54 16,600.72 49,802.16
4.14.6.A.2.4 ø350 mm nos. 5.00 12,575.47 4,195.03 500.60 17,271.10 86,355.50

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 189 of 199
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Total Price
Item Description Unit Qty. Road Cutting Total Unit
Material Labour Equipment (BDT)
Fees Price

a b c d e f g h i = e+f+g+h j=dxi

4.14.6.A.2.5 ø400 mm nos. 1.00 13,090.13 4,395.42 521.95 18,007.50 18,007.50


4.14.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.14.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.14.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.14.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.14.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.14.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.14.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.14.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.14.6.A.3.1 ø200 mm nos. 19.00 11,079.12 4,371.74 452.35 15,903.21 302,160.99


4.14.6.A.3.2 ø250 mm nos. 8.00 11,597.22 4,617.36 474.24 16,688.82 133,510.56
4.14.6.A.3.3 ø300 mm nos. 7.00 12,111.88 4,863.80 496.05 17,471.72 122,302.04
4.14.6.A.3.4 ø350 mm nos. 3.00 12,575.47 5,100.93 515.95 18,192.35 54,577.05
4.14.6.A.3.5 ø400 mm nos. 1.00 13,090.13 5,350.74 538.14 18,979.00 18,979.00
4.14.6.A.3.6 ø450 mm nos. 3.00 13,662.73 5,606.32 562.02 19,831.08 59,493.24
4.14.6.A.3.7 ø500 mm nos. 1.00 14,177.39 5,852.76 583.83 20,613.98 20,613.98
4.14.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.14.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.14.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.14.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.14.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.14: Column 'j' to be carried forward to


. 513,293,078.76
Schedule No. 5 Grand Summary

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 190 of 199
Schedule No. 5 - Grand Summary

Schedule No. Title


Total Price (BDT)

1 Schedule No. 1 - Pipe and Fittings Supplied from Abroad


2 Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
3 Schedule No. 3 - Design Services 641576101
4 Schedule No. 4 - Installation / Construction and Other works
4.1 Implementation Provisions and Preliminaries for all Loops 382326983
4.2 Installation/ Construction of all Loops (Schedule 4)
4.2.1 INSTALLATION of LOOP 301 380249324
4.2.2 INSTALLATION of LOOP 302 248328914
4.2.3 INSTALLATION of LOOP 303 379991228
4.2.4 INSTALLATION of LOOP 304 174518875
4.2.5 INSTALLATION of LOOP 305 269354495
4.2.6 INSTALLATION of LOOP 306 199738773
4.2.7 INSTALLATION of LOOP 307 781192914
4.2.8 INSTALLATION of LOOP 308 130423447
4.2.9 INSTALLATION of LOOP 309 457978285
4.2.10 INSTALLATION of LOOP 310 732394644
4.2.11 INSTALLATION of LOOP 311 724323563
4.2.12 INSTALLATION of LOOP 312 942407281
4.2.12 INSTALLATION of LOOP 313 1398103474
4.2.13 INSTALLATION of LOOP 314 513293079
Sub total 4.2: Installation/ Construction of all Loops (Schedule 4) 7332298295
5 Provisional Sum
5.1 Provisional sum for Physical Contingencies 366614915
5.2 Provisional Sum for Price Contingencies 349048076
5.3 Provisional Sum for alleviations program, refer to SCC, Sub-Clause xxxxxx 20949424
Sub-Total 5: Provisional Sum 736612414
6 Recommended spare parts 38664764
7 Day work 14046204
8 O&M - 162423927
. Grand Total (1+3+4.1+4.2+5+6+7+8) to be carried forward to Letter of Bid 9307948688

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 191 of 199
Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 192 of 199
Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Price Total Price (BDT)
Quantity Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh

Recommended Spare Parts


6.1 GRP Sewer Pipe (Dia in mm)
6.1.1 160 meter 250.00 1,770.40 1,770.40 442,600.00
6.1.2 200 meter 250.00 2,213.00 2,213.00 553,250.00
6.1.3 250 meter 250.00 2,923.00 2,923.00 730,750.00
6.1.4 300 meter 250.00 3,315.00 3,315.00 828,750.00
6.1.5 350 meter 300.00 4,292.00 4,292.00 1,287,600.00
6.1.6 400 meter 300.00 5,043.00 5,043.00 1,512,900.00
6.1.7 500 meter 300.00 7,807.00 7,807.00 2,342,100.00
6.1.8 600 meter 200.00 10,104.00 10,104.00 2,020,800.00
6.1.9 700 meter 200.00 15,281.00 15,281.00 3,056,200.00
6.1.10 800 meter 200.00 18,120.00 18,120.00 3,624,000.00
6.1.11 900 meter 200.00 16,711.99 16,711.99 3,342,397.33
6.1.12 1000 meter 200.00 18,462.01 18,462.01 3,692,402.67
6.2 Coupler/Coller
6.2.1 160 Pcs. 50.00 2,655.60 2,655.60 132,780.00
6.2.2 200 Pcs. 50.00 3,319.50 3,319.50 165,975.00
6.2.3 250 Pcs. 50.00 4,384.50 4,384.50 219,225.00
6.2.4 300 Pcs. 50.00 4,972.50 4,972.50 248,625.00
6.2.5 350 Pcs. 50.00 6,438.00 6,438.00 321,900.00
6.2.6 400 Pcs. 50.00 7,564.50 7,564.50 378,225.00
6.2.7 500 Pcs. 50.00 11,710.50 11,710.50 585,525.00
6.2.8 600 Pcs. 50.00 15,156.00 15,156.00 757,800.00
6.2.9 700 Pcs. 50.00 22,921.50 22,921.50 1,146,075.00
6.2.10 800 Pcs. 50.00 27,180.00 27,180.00 1,359,000.00
6.2.11 900 Pcs. 50.00 25,067.98 25,067.98 1,253,399.00
6.2.12 1000 Pcs. 50.00 27,693.02 27,693.02 1,384,651.00
6.3 Flange Adapter
6.3.1 160 Pcs. 20.00 885.20 885.20 17,704.00
6.3.2 200 Pcs. 20.00 1,106.50 1,106.50 22,130.00
6.3.3 250 Pcs. 20.00 1,461.50 1,461.50 29,230.00
6.3.4 300 Pcs. 20.00 1,657.50 1,657.50 33,150.00
6.3.5 350 Pcs. 20.00 2,146.00 2,146.00 42,920.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 193 of 199
Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Price Total Price (BDT)
Quantity Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh
6.3.6 400 Pcs. 20.00 2,521.50 2,521.50 50,430.00
6.3.7 500 Pcs. 20.00 3,903.50 3,903.50 78,070.00
6.3.8 600 Pcs. 20.00 5,052.00 5,052.00 101,040.00
6.3.9 700 Pcs. 20.00 7,640.50 7,640.50 152,810.00
6.3.10 800 Pcs. 20.00 9,060.00 9,060.00 181,200.00
6.3.11 900 Pcs. 20.00 8,355.99 8,355.99 167,119.87
6.3.12 1000 Pcs. 20.00 9,231.01 9,231.01 184,620.13
6.4 Tee/Wye
6.4.1 160 Pcs. 20.00 2,655.60 2,655.60 53,112.00
6.4.2 200 Pcs. 20.00 3,319.50 3,319.50 66,390.00
6.4.3 250 Pcs. 20.00 4,384.50 4,384.50 87,690.00
6.4.4 300 Pcs. 20.00 4,972.50 4,972.50 99,450.00
6.4.5 350 Pcs. 20.00 6,438.00 6,438.00 128,760.00
6.4.6 400 Pcs. 20.00 10,086.00 10,086.00 201,720.00
6.4.7 500 Pcs. 20.00 15,614.00 15,614.00 312,280.00
6.4.8 600 Pcs. 20.00 20,208.00 20,208.00 404,160.00
6.4.9 700 Pcs. 20.00 30,562.00 30,562.00 611,240.00
6.4.10 800 Pcs. 20.00 36,240.00 36,240.00 724,800.00
6.4.11 900 Pcs. 20.00 33,423.97 33,423.97 668,479.47
6.4.12 1000 Pcs. 20.00 36,924.03 36,924.03 738,480.53
6.5 Elbow (30/60/90 degrees)
6.5.1 160 Pcs. 20.00 1,770.40 1,770.40 35,408.00
6.5.2 200 Pcs. 20.00 2,213.00 2,213.00 44,260.00
6.5.3 250 Pcs. 20.00 2,923.00 2,923.00 58,460.00
6.5.4 300 Pcs. 20.00 3,315.00 3,315.00 66,300.00
6.5.5 350 Pcs. 20.00 4,292.00 4,292.00 85,840.00
6.5.6 400 Pcs. 20.00 5,043.00 5,043.00 100,860.00
6.5.7 500 Pcs. 20.00 7,807.00 7,807.00 156,140.00
6.5.8 600 Pcs. 20.00 10,104.00 10,104.00 202,080.00
6.5.9 700 Pcs. 20.00 15,281.00 15,281.00 305,620.00
6.5.10 800 Pcs. 20.00 18,120.00 18,120.00 362,400.00
6.5.11 900 Pcs. 20.00 16,711.99 16,711.99 334,239.73
6.5.12 1000 Pcs. 20.00 18,462.01 18,462.01 369,240.27
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 38,664,764.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 194 of 199
Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Price Total Price (BDT)
Quantity Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh
Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 195 of 199
Schedule No. 7 - Day Work

Unit Price (BDT) Total Price


Nominal
Item Description Unit Total Unit
Quantity Material Labour Equipment (BDT)
Price
a b c d e f g h=e+f+g i=dxh
7.1 Equipment

7.1.1 Micro Tunneling Machine with complete set hrs. 240 6,000.00 6,000.00 1,440,000.00
7.1.2 Hydraulic HDD Unit hrs. 144 4,000.00 4,000.00 576,000.00
7.1.3 Excavator, face shovel, or dragline:
7.1.3.1 Up to and including 1 m3 hrs. 144 2,000.00 2,000.00 288,000.00
7.1.3.2 Over 1 m3 to 2 m3 hrs. 180 3,000.00 3,000.00 540,000.00
7.1.3.3 Over 2 m3 hrs. 120 3,510.00 3,510.00 421,200.00
7.1.4 Tractor, including bull or angle dozer:
7.1.4.1 Up to and including 150 kW hrs. 200 1,000.00 1,000.00 200,000.00
7.1.4.2 Over 150 kW to 200 kW hrs. 200 1,500.00 1,500.00 300,000.00
7.1.4.3 Over 200 kW to 250 kW hrs. 200 2,000.00 2,000.00 400,000.00
7.1.5 Tractor with ripper:
7.1.5.1 Up to and including 200 kW hrs. 200 1,500.00 1,500.00 300,000.00
7.1.5.2 Over 200 kW to 250 kW hrs. 200 2,000.00 2,000.00 400,000.00
7.1.6 Portable concrete mixer - 0.4m3 hrs. 300 500.00 500.00 150,000.00
7.1.7 Hydraulic Excavator – 1 m3 hrs. 200 3,000.00 3,000.00 600,000.00
7.1.8 4-tool compressor including tools and hoses hrs. 200 2,000.00 2,000.00 400,000.00
7.1.9 10 tonne lorry-mounted crane hrs. 200 5,000.00 5,000.00 1,000,000.00
7.1.10 750 Kg crane hrs. 200 2,000.00 2,000.00 400,000.00
7.1.11 0.5 m3 dumper hrs. 200 1,000.00 1,000.00 200,000.00
7.1.12 1 m3 dumper hrs. 200 1,500.00 1,500.00 300,000.00
7.1.13 7 m3 tipper lorry hrs. 200 2,000.00 2,000.00 400,000.00
7.1.14 15 m3 lorry hrs. 200 2,000.00 2,000.00 400,000.00
7.1.15 4 wheel drive pick-up or van hrs. 200 500.00 500.00 100,000.00
7.1.16 Vibrating plate compactor hrs. 200 500.00 500.00 100,000.00
7.1.17 8-10 tonne roller hrs. 200 2,000.00 2,000.00 400,000.00
7.1.18 Scaffolding, 10 sqm day 36 2,025.00 2,025.00 72,900.00
7.1.19 5-Ton capacity truck-fare in Dhaka city i/c loading, unloading hrs. 300 456.50 456.50 136,950.00
7.1.20 Concrete mixer machine -1 bag capacity hrs. 168 537.50 537.50 90,300.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 196 of 199
Schedule No. 7 - Day Work

Unit Price (BDT) Total Price


Nominal
Item Description Unit Total Unit
Quantity Material Labour Equipment (BDT)
Price
a b c d e f g h=e+f+g i=dxh
7.1.21 Concrete vibrator-40mm dia hrs. 168 423.00 423.00 71,064.00
7.1.22 Diesel operated 1 cusec pump hrs. 288 505.00 505.00 145,440.00
7.1.23 Electricity operated 1 cusec pump hrs. 240 329.00 329.00 78,960.00
7.1.24 Road cutting Equipment hrs. 240 1,097.00 1,097.00 263,280.00
7.1.25 Backhoe Loader, wheel operated hrs. 144 3,510.00 3,510.00 505,440.00

7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1 (32.5-
7.2.1 bag 100 675.00 675.00 67,500.00
42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 100 607.50 607.50 60,750.00
clinker): 50kg bag
7.2.3 White Cement kg 250 54.00 54.00 13,500.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 1 86,400.00 86,400.00 86,400.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 1 87,750.00 87,750.00 87,750.00
7.2.6 MS Sheet M Ton 1 114,750.00 114,750.00 57,375.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 5,000 10,800.00 10,800.00 54,000.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 5,000 12,150.00 12,150.00 60,750.00
7.2.9 Imported Earth m3 100 572.50 572.50 57,250.00
7.2.10 Sand (F.M. 0.8) m3 100 525.00 525.00 52,500.00
7.2.11 Sand (F.M. 1.2) m3 50 810.50 810.50 40,525.00
7.2.12 Sand (F.M. 2.5) m3 50 2,384.00 2,384.00 119,200.00
7.2.13 Viti/Filling Sand m3 100 524.50 524.50 52,450.00
7.3 Labor
-
7.3.1 Contract Manager day 36 15,000.00 15,000.00 540,000.00
7.3.2 Office Assistant day 72 500.00 500.00 36,000.00

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 197 of 199
Schedule No. 7 - Day Work

Unit Price (BDT) Total Price


Nominal
Item Description Unit Total Unit
Quantity Material Labour Equipment (BDT)
Price
a b c d e f g h=e+f+g i=dxh
7.3.3 Contract / Legal Advisor day 24 5,000.00 5,000.00 120,000.00
7.3.4 Financial Advisor day 24 5,000.00 5,000.00 120,000.00
7.3.5 Quantity Engineer day 36 3,000.00 3,000.00 108,000.00
7.3.6 Designer day 24 10,000.00 10,000.00 240,000.00
7.3.7 Field Engineer day 36 3,000.00 3,000.00 108,000.00
7.3.8 Draft Person day 24 2,000.00 2,000.00 48,000.00
7.3.9 Ordinary/casual Labour day 240 600.00 600.00 144,000.00
7.3.10 Skilled labour day 120 945.00 945.00 113,400.00
7.3.11 Head Operator/Ganger day 36 1,080.00 1,080.00 38,880.00
7.3.12 Asstt. Operator/Ganger day 72 945.00 945.00 68,040.00
7.3.13 Head Mason day 36 1,080.00 1,080.00 38,880.00
7.3.14 Mud Operator day 36 945.00 945.00 34,020.00
7.3.15 Field Supervisor/Manager day 36 3,375.00 3,375.00 121,500.00
7.3.16 Field/Maintenance Engineer day 72 2,700.00 2,700.00 194,400.00
7.3.17 Skilled technician/Plumber/Mason/Steel work Erector/ day 72 800.00 800.00 57,600.00
7.3.18 Semi Skilled technician day 120 700.00 700.00 84,000.00
7.3.19 Site security day 48 600.00 600.00 28,800.00
7.3.20 Driver day 72 1,100.00 1,100.00 79,200.00
7.3.21 Sweeper for Odd Job day 72 1,000.00 1,000.00 72,000.00
7.3.22 Surveyor day 60 1,080.00 1,080.00 64,800.00
7.3.23 Asstt. Surveyor day 120 810.00 810.00 97,200.00
7.3.24 Carpenter

Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 14,046,204.00

Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 198 of 199
Schedule No. 8 - O&M Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price
a b c d e f g h=e+f+g i=dxh
8 O&M Services and Documentation

8.1 One year O&M (14 Loops in Segments 7-12)


8.1.1 O&M Services in Loop 301 km 9.07 934,330.00 8,474,373.10
8.1.2 O&M Services in Loop 302 km 6.35 934,330.00 5,932,995.50
8.1.3 O&M Services in Loop 303 km 8.56 934,330.00 7,997,864.80
8.1.4 O&M Services in Loop 304 km 4.32 934,330.00 4,036,305.60
8.1.5 O&M Services in Loop 305 km 6.55 934,330.00 6,119,861.50
8.1.6 O&M Services in Loop 306 km 5.26 934,330.00 4,914,575.80
8.1.7 O&M Services in Loop 307 km 19.41 934,330.00 18,135,345.30
8.1.8 O&M Services in Loop 308 km 3.38 934,330.00 3,158,035.40
8.1.9 O&M Services in Loop 309 km 10.02 934,330.00 9,361,986.60
8.1.10 O&M Services in Loop 310 km 16.62 934,330.00 15,528,564.60
8.1.11 O&M Services in Loop 311 km 16.78 934,330.00 15,678,057.40
8.1.12 O&M Services in Loop 312 km 21.4 934,330.00 19,994,662.00
8.1.13 O&M Services in Loop 313 km 34.72 934,330.00 32,439,937.60
8.1.14 O&M Services in Loop 314 km 11.4 934,330.00 10,651,362.00
173.84
Sub-total 8.1: Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 162,423,927.20

Name of Bidder

Signature of Bidder

2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 199 of 199
Employer’s Cost Estimates7

F: Cost of Package 4 (Segment 13 to 16)


Schedule No. 1 - Pipe and Fittings Supplied from Abroad

Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 53,518.80
1.1.2 ø250 mm m 1,751.70
1.1.3 ø300 mm m 1,978.50
1.1.4 ø350 mm m 1,391.90
1.1.5 ø400 mm m 1,824.40
1.1.6 ø450 mm m
1.1.7 ø500 mm m 1,932.00
1.1.8 ø600 mm m 1,234.30
1.1.9 ø700 mm m 232.70
1.1.10 ø800 mm m 28.90
1.1.11 ø900 mm m
1.1.12 ø1000 mm m
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 107
1.2.2 ø250 mm nos. 4
1.2.3 ø300 mm nos. 4
1.2.4 ø350 mm nos. 3
1.2.5 ø400 mm nos. 4
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 5
1.2.8 ø600 mm nos. 2
1.2.9 ø700 mm nos. 1
1.2.10 ø800 mm nos.

Dasherkandi Sewerage Project, Cost Estimate for Package 4 1 of 65 2018


Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.11 ø900 mm nos.
1.2.12 ø1000 mm nos.
1.3 Equal and Un Equal Tee of different sizes
1.3.1 200mm x200mm nos. 107
1.3.2 250mm x250mm nos. 4
1.3.3 300mm X 300mm nos. 4
1.3.4 350mm X 350mm nos. 3
1.3.5 400mm X 400mm nos. 4
1.3.6 450mm X 450mm nos.
1.3.7 500mm X 500mm nos. 5
1.3.8 600 mm X 600mm nos. 2
1.3.9 700mm X 700mm nos. 1
1.3.10 800mm x 800mm nos.
1.3.11 900mm X 900mm nos.
1.3.12 1000mm X 1000mm nos.
1.3.13 250mm X250mm X 200mm nos. 4
1.3.14 300mm X 300mm X 200mm nos. 4
1.3.15 300mm X 300mm X 250mm nos. 4
1.3.16 400mm X 400mm X 200mm nos. 4
1.3.17 400mm X 400mm X 250mm nos. 4
1.3.18 400mm X 400mm X 300mm nos. 4
1.3.19 500mm X 500mm X 200mm nos. 5
1.3.20 500mm X 500mm X 300mm nos. 2
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos. 214

Dasherkandi Sewerage Project, Cost Estimate for Package 4 2 of 65 2018


Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4.2 ø250 mm nos. 8
1.4.3 ø300 mm nos. 8
1.4.4 ø350 mm nos. 6
1.4.5 ø400 mm nos. 8
1.4.6 ø450 mm nos.
1.4.7 ø500 mm nos. 10
1.4.8 ø600 mm nos. 4
1.4.9 ø700 mm nos. 2
1.4.10 ø800 mm nos.
1.4.11 ø900 mm nos.
1.4.12 ø1000 mm nos.
1.5 Flanged Adapters
1.5.1 ø200 mm nos. 27
1.5.2 ø250 mm nos. 1
1.5.3 ø300 mm nos. 1
1.5.4 ø350 mm nos. 1
1.5.5 ø400 mm nos. 1
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos. 2
1.5.8 ø600 mm nos. 2
1.5.9 ø700 mm nos. 1
1.5.10 ø800 mm nos.
1.5.11 ø900 mm nos.
1.5.12 ø1000 mm nos.

Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 4 3 of 65 2018


Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 4 4 of 65 2018


Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country

Unit Price (BDT)


Sales and other
Item Description Unit Qty. Total Unit Total Price (BDT)
Material Labour Equipment taxes (BDT)
Price (EXW)
a b c d e f g h=e+f+g i=dxh j

Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 4 5 of 65 2018


Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

3.1 Design / Survey Provisions and Preliminaries


3.1.1 Insurances
3.1.1.1 For design (professional indemnity insurance) LS 1 13,066,349.98 13,066,349.98
3.1.1.2 Other Insurances (to be specified by the Tenderer) LS 1 6,533,175 6,533,174.99
Sub-total A: 19,599,524.98
3.2 Design Services (including design office and establishment)

3.2.1 Loop 401


3.2.1.1 Survey and documentation, including Survey Report LS 1 10,635,070 10,635,069.60
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.1.2 LS 1 6,499,209 6,499,209.20
Report
3.2.1.3 Design Control Services including documentation LS 1 1,772,512 1,772,511.60

3.2.2 Loop 402


3.2.2.1 Survey and documentation, including Survey Report LS 1 30,411,689 30,411,688.85
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.2.2 LS 1 18,584,921 18,584,920.96
Report
3.2.2.3 Design Control Services including documentation LS 1 5,068,615 5,068,614.81

3.2.3 Loop 403


3.2.3.1 Survey and documentation, including Survey Report LS 1 18,087,513 18,087,512.73
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.3.2 LS 1 11,053,480 11,053,480.00
Report
3.2.3.3 Design Control Services including documentation LS 1 3,014,585 3,014,585.46

3.2.4 Loop 404


3.2.4.1 Survey and documentation, including Survey Report LS 1 32,552,774 32,552,774.07
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.4.2 LS 1 19,893,362 19,893,361.93
Report
3.2.4.3 Design Control Services including documentation LS 1 5,425,462 5,425,462.35

3.2.5 Loop 405


3.2.5.1 Survey and documentation, including Survey Report LS 1 25,910,105 25,910,104.61

Dasherkandi Sewerage Project, Cost Estimate for Package 4 6 of 65 2018


Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.5.2 LS 1 15,833,953 15,833,952.82
Report
3.2.5.3 Design Control Services including documentation LS 1 4,318,351 4,318,350.77

Sub-total B: 209,061,599.75
Total A+B: Sub-total 3:
228,661,124.73
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary

Name of Bidder:

Signature of Bidder:

Dasherkandi Sewerage Project, Cost Estimate for Package 4 7 of 65 2018


Schedule No. 4 - Installation / Construction and Other works

Unit Price (BDT)


Item Description Unit Qty. Total Unit Total Price (BDT)
Material Labour Equipment
Price

a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 6,533,174.99 6,533,174.99
4.1.1.2 Advance Payment Guarantee LS 1 6,533,174.99 6,533,174.99
Subtotal 4.1.1 13,066,349.98
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.2 Installation All Risks Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.3 Third Party Liability Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.4 Automobile Liability Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.5 Workers' Compensation LS 1 9,799,762.49 9,799,762.49
4.1.2.6 Employer's Liability LS 1 9,799,762.49 9,799,762.49
4.1.2.7 Contractor's Equipment Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 9,799,762.49 9,799,762.49
Subtotal 4.1.2 78,398,099.90
4.1.3 Site establishment, operation and removal

Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 7,466,485.71 7,466,485.71
workshops, site access and miscellaneous services etc.

Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 7,466,485.71 7,466,485.71
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 7,466,485.71 7,466,485.71
4.1.3.4 Survey instruments LS 1 7,466,485.71 7,466,485.71
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 7,466,485.71 7,466,485.71
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 7,466,485.71 7,466,485.71
Subtotal 4.1.3 44,798,914.23
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 136,263,364.11

Dasherkandi Sewerage Project, Cost Estimate for Package 4 8 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.2 INSTALLATION of LOOP 401
4.2.1 Miscellaneous works during implementation
4.2.1.1 Setting-out LS 1.00 123,288.00 123,288.00
4.2.1.2 General works and site tests LS 1.00 246,576.00 246,576.00
4.2.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.2.2.1 LS 1.00 246,576.00 246,576.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction completed
4.2.2.2 LS 1.00 92,466.00 92,466.00
& acceptance certificate
4.2.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.2.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.2.2.5 Development and submission of GIS based As-built drawings LS 1.00 154,110.00 154,110.00
4.2.2.6 Post Construction modelling LS 1.00 18,493.20 18,493.20

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified below,
including fitting, fixing of all items, road cutting permission fee, temporary road
4.2.3 -
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.2.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.2.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.3.A.1.1 ø200 mm m 4,789.40 3,596.40 1,581.32 878.18 5,811.99 11,867.89 56,840,067.30


4.2.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.2.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.2.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.2.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.2.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.2.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.2.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.2.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.2.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.2.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 9 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.2.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.A.2.1 ø200 mm m 357.80 3,890.84 1,719.29 901.27 5,811.99 12,323.40 4,409,310.95


4.2.3.A.2.2 ø250 mm m 105.80 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 1,449,032.88
4.2.3.A.2.3 ø300 mm m 159.80 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 2,348,637.44
4.2.3.A.2.4 ø350 mm m 265.00 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 4,008,633.51
4.2.3.A.2.5 ø400 mm m 219.60 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 3,927,385.26
4.2.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.2.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.2.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.2.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.2.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.2.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.2.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.2.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.2.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.2.3.A.3.5 ø400 mm m 267.00 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 8,583,218.64
4.2.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.2.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.2.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.2.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.2.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.2.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.2.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.2.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.2.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

Dasherkandi Sewerage Project, Cost Estimate for Package 4 10 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.1.1 ø200 mm m -
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -

4.2.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -

4.2.3.B.2.11 ø900 mm m -

4.2.3.B.2.12 ø1000 mm m -

4.2.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 11 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -

4.2.3.B.3.11 ø900 mm m -

4.2.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.2.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved drawing and
specification.

4.2.4.A Normal Manhole Rectangular or circular

4.2.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.2.4.A.1.1 ø200 mm nos. 117.00 108,465.00 17,845.00 10,137.00 136,447.00 15,964,299.00


4.2.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.2.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.2.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.2.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.A.2.1 ø200 mm nos. 5 133,076.00 22,507.00 12,324.00 167,907.00 839,535.00


4.2.4.A.2.2 ø250 mm nos. 4 133,713.00 22,520.00 12,338.00 168,571.00 674,284.00

Dasherkandi Sewerage Project, Cost Estimate for Package 4 12 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.2.3 ø300 mm nos. 6 134,286.00 22,521.00 12,350.00 169,157.00 1,014,942.00


4.2.4.A.2.4 ø350 mm nos. 10 134,923.00 22,534.00 12,363.00 169,820.00 1,698,200.00
4.2.4.A.2.5 ø400 mm nos. 8 135,559.00 22,547.00 12,377.00 170,483.00 1,363,864.00
4.2.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.2.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.2.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.2.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.2.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.2.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.2.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.2.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.2.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.2.4.A.3.5 ø400 mm nos. 6 184,778 31,866 16,752 233,396.00 1,400,376.00
4.2.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.2.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.2.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.2.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.2.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.2.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.2.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.2.4.B Drop Manhole Rectangular or circular

4.2.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.2.4.B.1.1 ø200 mm nos. 27.00 177,870.00 34,380.00 19,812.00 232,062.00 6,265,674.00


4.2.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.2.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.2.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.2.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 13 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -


4.2.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.2.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.2.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.2.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.2.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.2.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.2.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.2.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.2.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.2.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.2.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.2.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.2.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.2.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.2.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.2.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.2.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.2.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.2.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.2.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.2.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.2.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.2.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.2.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.2.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.2.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.2.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 14 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.2.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.2.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.2.4.C Service connections Manhole Rectangular or circular -

4.2.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.2.4.C.1.1 ø200 mm nos. 267.00 108,465.00 17,845.00 10,137.00 136,447.00 36,431,349.00


4.2.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.2.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.2.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.B.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.2.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.C.2.1 ø200 mm nos. 20 133,076.00 22,507.00 12,324.00 167,907.00 3,358,140.00


4.2.4.C.2.2 ø250 mm nos. 6 133,713.00 22,520.00 12,338.00 168,571.00 1,011,426.00
4.2.4.C.2.3 ø300 mm nos. 9 134,286.00 22,521.00 12,350.00 169,157.00 1,522,413.00
4.2.4.C.2.4 ø350 mm nos. 15 134,923.00 22,534.00 12,363.00 169,820.00 2,547,300.00
4.2.4.C.2.5 ø400 mm nos. 13 135,559.00 22,547.00 12,377.00 170,483.00 2,216,279.00
4.2.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.2.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.2.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.2.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 15 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.2.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.2.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.2.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.2.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.2.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.2.4.C.3.5 ø400 mm nos. 15 184,778.00 31,866.00 16,752.00 233,396.00 3,500,940.00
4.2.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.2.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.2.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.2.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.2.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.2.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.2.4.B.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes including fitting, fixing
of all items, road cutting permission fee, temporary road reinstatement, dismantling
4.2.5 of existing structures, site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 515.00 40,766.88 13,972.83 8,265.14 63,004.85 32,447,497.75

4.2.5.2 ø200 mm nos. 206.00 44,627.58 15,581.46 9,230.31 69,439.35 14,304,506.10


4.2.5.3 ø250 mm nos. 206.00 51,128.58 18,290.21 10,855.56 80,274.35 16,536,516.10
4.2.5.4 ø300 mm nos. 103.00 55,471.38 20,099.71 11,941.26 87,512.35 9,013,772.05

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning, earth
4.2.6 -
cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per approved
drawing and specification.

4.2.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.6.A.1.1 ø200 mm nos. 89.00 11,079.12 3,235.25 433.10 14,747.46 1,312,523.94


4.2.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.2.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 16 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -


4.2.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.2.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.2.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.2.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.2.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.2.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.2.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.2.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.2.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.6.A.2.1 ø200 mm nos. 7.00 11,079.12 3,614.08 439.51 15,132.71 105,928.97


4.2.6.A.2.2 ø250 mm nos. 2.00 11,597.22 3,810.28 460.57 15,868.07 31,736.14
4.2.6.A.2.3 ø300 mm nos. 3.00 12,111.88 4,007.30 481.54 16,600.72 49,802.16
4.2.6.A.2.4 ø350 mm nos. 5.00 12,575.47 4,195.03 500.60 17,271.10 86,355.50
4.2.6.A.2.5 ø400 mm nos. 4.00 13,090.13 4,395.42 521.95 18,007.50 72,030.00
4.2.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.2.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.2.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.2.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.2.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.2.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.2.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.2.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.2.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.2.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.2.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.2.6.A.3.5 ø400 mm nos. 5.00 13,090.13 5,350.74 538.14 18,979.00 94,895.00
4.2.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.2.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 17 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -


4.2.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.2.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.2.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.2.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.2: Column 'j' to be carried forward to Schedule No. 5


. 236,334,879.90
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 4 18 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.3 INSTALLATION of LOOP 402
4.3.1 Miscellaneous works during implementation
4.3.1.1 Setting-out LS 1.00 322,504.00 322,504.00
4.3.1.2 General works and site tests LS 1.00 645,008.00 645,008.00
4.3.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.3.2.1 LS 1.00 645,008.00 645,008.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.3.2.2 LS 1.00 241,878.00 241,878.00
completed & acceptance certificate
4.3.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.3.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.3.2.5 Development and submission of GIS based As-built drawings LS 1.00 403,130.00 403,130.00
4.3.2.6 Post Construction modelling LS 1.00 48,375.60 48,375.60

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.3.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.3.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.3.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.3.A.1.1 ø200 mm m 10,304.30 3,596.40 1,581.32 878.18 5,811.99 11,867.89 122,290,288.03


4.3.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.3.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.3.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.3.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.3.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.3.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.3.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.3.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.3.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 19 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -


4.3.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.3.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.A.2.1 ø200 mm m 3,123 3,890.84 1,719.29 901.27 5,811.99 12,323.40 38,479,802.79


4.3.3.A.2.2 ø250 mm m 419 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 5,737,238.89
4.3.3.A.2.3 ø300 mm m 336 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 4,938,311.52
4.2.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.3.3.A.2.5 ø400 mm m 80 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 1,436,106.72
4.3.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.3.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.3.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.3.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.3.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.3.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.A.3.1 ø200 mm m 44 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 1,169,700.88


4.3.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.3.3.A.3.3 ø300 mm m 257 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 7,437,649.98
4.3.3.A.3.4 ø350 mm m 50 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 1,467,298.52
4.3.3.A.3.5 ø400 mm m 197 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 6,332,936.60
4.3.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.3.3.A.3.7 ø500 mm m 765 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 28,080,515.15
4.3.3.A.3.8 ø600 mm m 521 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 21,204,673.55
4.3.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.3.3.A.3.10 ø800 mm m 29 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 1,571,423.92

4.3.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.3.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.3.3.B Sewer Pipelines of Grade-B using GRP Pipes

Dasherkandi Sewerage Project, Cost Estimate for Package 4 20 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -

4.3.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -

4.3.3.B.2.11 ø900 mm m -

4.3.3.B.2.12 ø1000 mm m -

4.3.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 21 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -

4.3.3.B.3.11 ø900 mm m -

4.3.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.3.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.3.4.A Normal Manhole Rectangular or circular

4.3.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.A.1.1 ø200 mm nos. 289.00 108,465.00 17,845.00 10,137.00 136,447.00 39,433,183.00


4.3.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.3.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.3.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 22 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.A.2.1 ø200 mm nos. 96 133,076.00 22,507.00 12,324.00 167,907.00 16,119,072.00


4.3.4.A.2.2 ø250 mm nos. 16 133,713.00 22,520.00 12,338.00 168,571.00 2,697,136.00
4.3.4.A.2.3 ø300 mm nos. 10 134,286.00 22,521.00 12,350.00 169,157.00 1,691,570.00
4.3.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.3.4.A.2.5 ø400 mm nos. 4 135,559.00 22,547.00 12,377.00 170,483.00 681,932.00
4.3.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.3.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.3.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.3.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.3.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.3.4.A.3.3 ø300 mm nos. 7 183,505 31,840 16,725 232,070.00 1,624,490.00
4.3.4.A.3.4 ø350 mm nos. 2 184,142 31,853 16,738 232,733.00 465,466.00
4.3.4.A.3.5 ø400 mm nos. 3 184,778 31,866 16,752 233,396.00 700,188.00
4.3.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.3.4.A.3.7 ø500 mm nos. 23 185,988 31,881 16,777 234,646.00 5,396,858.00
4.3.4.A.3.8 ø600 mm nos. 16 187,267 31,910 16,805 235,982.00 3,775,712.00
4.3.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.3.4.A.3.10 ø800 mm nos. 1 189,750 31,950 16,858 238,558.00 238,558.00

4.3.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.3.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.3.4.B Drop Manhole Rectangular or circular

4.3.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.B.1.1 ø200 mm nos. 109.00 177,870.00 34,380.00 19,812.00 232,062.00 25,294,758.00

Dasherkandi Sewerage Project, Cost Estimate for Package 4 23 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -


4.3.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.3.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.3.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.3.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.3.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.3.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.3.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.3.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.3.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.3.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.3.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.3.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.3.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00
4.3.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.3.4.B.2.5 ø400 mm nos. 1 217,952.00 42,686.00 24,050.00 284,688.00 284,688.00
4.3.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.3.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.3.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.3.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.3.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.3.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.3.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.3.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.3.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.3.4.B.3.3 ø300 mm nos. 1 293,442.00 59,074.00 32,256.00 384,772.00 384,772.00
4.3.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.3.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 24 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -


4.3.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.3.4.B.3.8 ø600 mm nos. 1 296,282.00 59,214.00 32,416.00 387,912.00 387,912.00
4.3.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.3.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.3.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.3.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.3.4.C Service connections Manhole Rectangular or circular -

4.3.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.3.4.C.1.1 ø200 mm nos. 573.00 108,465.00 17,845.00 10,137.00 136,447.00 78,184,131.00


4.3.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.3.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.3.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.3.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.C.2.1 ø200 mm nos. 174 133,076.00 22,507.00 12,324.00 167,907.00 29,215,818.00


4.3.4.C.2.2 ø250 mm nos. 24 133,713.00 22,520.00 12,338.00 168,571.00 4,045,704.00
4.3.4.C.2.3 ø300 mm nos. 19 134,286.00 22,521.00 12,350.00 169,157.00 3,213,983.00
4.3.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.3.4.C.2.5 ø400 mm nos. 5 135,559.00 22,547.00 12,377.00 170,483.00 852,415.00
4.3.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 25 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -


4.3.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.3.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.3.4.C.3.1 ø200 mm nos. 3 182,295.00 31,825.00 16,700.00 230,820.00 692,460.00


4.3.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.3.4.C.3.3 ø300 mm nos. 15 183,505.00 31,840.00 16,725.00 232,070.00 3,481,050.00
4.3.4.C.3.4 ø350 mm nos. 3 184,142.00 31,853.00 16,738.00 232,733.00 698,199.00
4.3.4.C.3.5 ø400 mm nos. 11 184,778.00 31,866.00 16,752.00 233,396.00 2,567,356.00
4.3.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.3.4.C.3.7 ø500 mm nos. 43 185,988.00 31,881.00 16,777.00 234,646.00 10,089,778.00
4.3.4.C.3.8 ø600 mm nos. 29 187,267.00 31,910.00 16,805.00 235,982.00 6,843,478.00
4.3.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.3.4.C.3.10 ø800 mm nos. 2 189,750.00 31,950.00 16,858.00 238,558.00 477,116.00

4.3.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.3.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.3.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.3.5.1 ø150 mm nos. 1,345.00 40,766.88 13,972.83 8,265.14 63,004.85 84,741,523.25

4.3.5.2 ø200 mm nos. 538.00 44,627.58 15,581.46 9,230.31 69,439.35 37,358,370.30


4.3.5.3 ø250 mm nos. 538.00 51,128.58 18,290.21 10,855.56 80,274.35 43,187,600.30
4.3.5.4 ø300 mm nos. 269.00 55,471.38 20,099.71 11,941.26 87,512.35 23,540,822.15

Dasherkandi Sewerage Project, Cost Estimate for Package 4 26 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.3.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.3.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.6.A.1.1 ø200 mm nos. 191.00 11,079.12 3,235.25 433.10 14,747.46 2,816,764.86


4.3.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.3.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.3.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.3.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.3.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.3.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.3.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.3.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.3.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.3.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.3.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.3.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.6.A.2.1 ø200 mm nos. 58.00 11,079.12 3,614.08 439.51 15,132.71 877,697.18


4.3.6.A.2.2 ø250 mm nos. 8.00 11,597.22 3,810.28 460.57 15,868.07 126,944.56
4.3.6.A.2.3 ø300 mm nos. 6.00 12,111.88 4,007.30 481.54 16,600.72 99,604.32
4.3.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.3.6.A.2.5 ø400 mm nos. 2.00 13,090.13 4,395.42 521.95 18,007.50 36,015.00
4.3.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.3.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.3.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.3.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.3.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.3.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 27 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.3.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.6.A.3.1 ø200 mm nos. 1.00 11,079.12 4,371.74 452.35 15,903.21 15,903.21


4.3.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.3.6.A.3.3 ø300 mm nos. 5.00 12,111.88 4,863.80 496.05 17,471.72 87,358.60
4.3.6.A.3.4 ø350 mm nos. 1.00 12,575.47 5,100.93 515.95 18,192.35 18,192.35
4.3.6.A.3.5 ø400 mm nos. 4.00 13,090.13 5,350.74 538.14 18,979.00 75,916.00
4.3.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.3.6.A.3.7 ø500 mm nos. 14.00 14,177.39 5,852.76 583.83 20,613.98 288,595.72
4.3.6.A.3.8 ø600 mm nos. 10.00 15,264.65 6,359.64 629.91 22,254.20 222,542.00
4.3.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.3.6.A.3.10 ø800 mm nos. 1.00 17,602.69 7,398.46 727.66 25,728.81 25,728.81

4.3.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.3.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.3: Column 'j' to be carried forward to Schedule No. 5


. 675,815,307.77
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 4 28 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 403
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 197,524.00 197,524.00
4.4.1.2 General works and site tests LS 1.00 395,048.00 395,048.00
4.4.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.4.2.1 LS 1.00 395,048.00 395,048.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.4.2.2 LS 1.00 148,143.00 148,143.00
completed & acceptance certificate
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.4.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 246,905.00 246,905.00
4.4.2.6 Post Construction modelling LS 1.00 29,628.60 29,628.60

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.3.A.1.1 ø200 mm m 5,422.90 3,596.40 1,581.32 878.18 5,811.99 11,867.89 64,358,374.95


4.4.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.4.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 29 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -


4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 2,840 3,890.84 1,719.29 901.27 5,811.99 12,323.40 34,998,443.53


4.4.3.A.2.2 ø250 mm m 143 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 1,958,522.71
4.4.3.A.2.3 ø300 mm m 74 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 1,087,604.32
4.4.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.4.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.4.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.4.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.4.3.A.3.3 ø300 mm m 70 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 2,019,245.31
4.4.3.A.3.4 ø350 mm m 225 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 6,596,974.16
4.4.3.A.3.5 ø400 mm m 223 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 7,162,326.26
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 616 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 22,602,464.86
4.4.3.A.3.8 ø600 mm m 263 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 10,710,129.57
4.4.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.4.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

Dasherkandi Sewerage Project, Cost Estimate for Package 4 30 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 31 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.4.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 152.00 108,465.00 17,845.00 10,137.00 136,447.00 20,739,944.00


4.4.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 32 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 35 133,076.00 22,507.00 12,324.00 167,907.00 5,876,745.00


4.4.4.A.2.2 ø250 mm nos. 4 133,713.00 22,520.00 12,338.00 168,571.00 674,284.00
4.4.4.A.2.3 ø300 mm nos. 3 134,286.00 22,521.00 12,350.00 169,157.00 507,471.00
4.4.4.A.2.4 ø350 mm nos. 1 134,923.00 22,534.00 12,363.00 169,820.00 169,820.00
4.4.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.4.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.4.4.A.3.3 ø300 mm nos. 1 183,505 31,840 16,725 232,070.00 232,070.00
4.4.4.A.3.4 ø350 mm nos. 5 184,142 31,853 16,738 232,733.00 1,163,665.00
4.4.4.A.3.5 ø400 mm nos. 6 184,778 31,866 16,752 233,396.00 1,400,376.00
4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 16 185,988 31,881 16,777 234,646.00 3,754,336.00
4.4.4.A.3.8 ø600 mm nos. 8 187,267 31,910 16,805 235,982.00 1,887,856.00
4.4.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.4.4.B Drop Manhole Rectangular or circular

4.4.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. 10.00 177,870.00 34,380.00 19,812.00 232,062.00 2,320,620.00

Dasherkandi Sewerage Project, Cost Estimate for Package 4 33 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -


4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.B.2.1 ø200 mm nos. 11 216,110.00 42,604.00 23,944.00 282,658.00 3,109,238.00


4.4.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.4.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.4.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.4.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 34 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -


4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

4.4.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.4.C.1.1 ø200 mm nos. 302.00 108,465.00 17,845.00 10,137.00 136,447.00 41,206,994.00


4.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 158 133,076.00 22,507.00 12,324.00 167,907.00 26,529,306.00


4.4.4.C.2.2 ø250 mm nos. 8 133,713.00 22,520.00 12,338.00 168,571.00 1,348,568.00
4.4.4.C.2.3 ø300 mm nos. 5 134,286.00 22,521.00 12,350.00 169,157.00 845,785.00
4.4.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.4.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 35 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -


4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.4.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.4.4.C.3.3 ø300 mm nos. 4 183,505.00 31,840.00 16,725.00 232,070.00 928,280.00
4.4.4.C.3.4 ø350 mm nos. 13 184,142.00 31,853.00 16,738.00 232,733.00 3,025,529.00
4.4.4.C.3.5 ø400 mm nos. 13 184,778.00 31,866.00 16,752.00 233,396.00 3,034,148.00
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 35 185,988.00 31,881.00 16,777.00 234,646.00 8,212,610.00
4.4.4.C.3.8 ø600 mm nos. 15 187,267.00 31,910.00 16,805.00 235,982.00 3,539,730.00
4.4.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 824.00 40,766.88 13,972.83 8,265.14 63,004.85 51,915,996.40

4.2.5.2 ø200 mm nos. 329.00 44,627.58 15,581.46 9,230.31 69,439.35 22,845,546.15


4.2.5.3 ø250 mm nos. 329.00 51,128.58 18,290.21 10,855.56 80,274.35 26,410,261.15
4.2.5.4 ø300 mm nos. 165.00 55,471.38 20,099.71 11,941.26 87,512.35 14,439,537.75

Dasherkandi Sewerage Project, Cost Estimate for Package 4 36 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.4.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 101.00 11,079.12 3,235.25 433.10 14,747.46 1,489,493.46


4.4.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.4.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 53.00 11,079.12 3,614.08 439.51 15,132.71 802,033.63


4.4.6.A.2.2 ø250 mm nos. 3.00 11,597.22 3,810.28 460.57 15,868.07 47,604.21
4.4.6.A.2.3 ø300 mm nos. 2.00 12,111.88 4,007.30 481.54 16,600.72 33,201.44
4.4.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.4.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.4.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 37 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.4.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.4.6.A.3.3 ø300 mm nos. 1.00 12,111.88 4,863.80 496.05 17,471.72 17,471.72
4.4.6.A.3.4 ø350 mm nos. 4.00 12,575.47 5,100.93 515.95 18,192.35 72,769.40
4.4.6.A.3.5 ø400 mm nos. 4.00 13,090.13 5,350.74 538.14 18,979.00 75,916.00
4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.4.6.A.3.7 ø500 mm nos. 12.00 14,177.39 5,852.76 583.83 20,613.98 247,367.76
4.4.6.A.3.8 ø600 mm nos. 5.00 15,264.65 6,359.64 629.91 22,254.20 111,271.00
4.4.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.4: Column 'j' to be carried forward to Schedule No. 5


. 401,944,727.34
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 4 38 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 404
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 350,682.00 350,682.00
4.4.1.2 General works and site tests LS 1.00 701,364.00 701,364.00
4.4.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.4.2.1 LS 1.00 701,364.00 701,364.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.4.2.2 LS 1.00 263,011.50 263,011.50
completed & acceptance certificate
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.4.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 438,352.50 438,352.50
4.4.2.6 Post Construction modelling LS 1.00 52,602.30 52,602.30

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.3.A.1.1 ø200 mm m 8,137.90 3,596.40 1,581.32 878.18 5,811.99 11,867.89 96,579,693.42


4.4.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.4.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 39 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -


4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 7,137 3,890.84 1,719.29 901.27 5,811.99 12,323.40 87,948,377.44


4.4.3.A.2.2 ø250 mm m 320 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 4,382,708.15
4.4.3.A.2.3 ø300 mm m 210 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 3,083,505.23
4.4.3.A.2.4 ø350 mm m 60 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 901,564.37
4.4.3.A.2.5 ø400 mm m 215 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 3,846,906.06
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.4.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.A.3.1 ø200 mm m 115 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 3,052,892.76


4.4.3.A.3.2 ø250 mm m 243 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 6,776,390.17
4.4.3.A.3.3 ø300 mm m 251 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 7,255,397.18
4.4.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.4.3.A.3.5 ø400 mm m 58 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 1,851,660.65
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 301 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 11,051,562.58
4.4.3.A.3.8 ø600 mm m 450 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 18,292,234.21
4.4.3.A.3.9 ø700 mm m 38 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 1,837,552.12
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.4.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

Dasherkandi Sewerage Project, Cost Estimate for Package 4 40 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 41 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.4.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 249.00 108,465.00 17,845.00 10,137.00 136,447.00 33,975,303.00


4.4.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 42 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 176 133,076.00 22,507.00 12,324.00 167,907.00 29,551,632.00


4.4.4.A.2.2 ø250 mm nos. 11 133,713.00 22,520.00 12,338.00 168,571.00 1,854,281.00
4.4.4.A.2.3 ø300 mm nos. 7 134,286.00 22,521.00 12,350.00 169,157.00 1,184,099.00
4.4.4.A.2.4 ø350 mm nos. 2 134,923.00 22,534.00 12,363.00 169,820.00 339,640.00
4.4.4.A.2.5 ø400 mm nos. 9 135,559.00 22,547.00 12,377.00 170,483.00 1,534,347.00
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.A.2.7 ø500 mm nos. 1 136,776.00 22,565.00 12,402.00 171,743.00 171,743.00
4.4.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 2 182,295 31,825 16,700 230,820.00 461,640.00


4.4.4.A.3.2 ø250 mm nos. 3 182,932 31,838 16,713 231,483.00 694,449.00
4.4.4.A.3.3 ø300 mm nos. 5 183,505 31,840 16,725 232,070.00 1,160,350.00
4.4.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.4.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 7 185,988 31,881 16,777 234,646.00 1,642,522.00
4.4.4.A.3.8 ø600 mm nos. 14 187,267 31,910 16,805 235,982.00 3,303,748.00
4.4.4.A.3.9 ø700 mm nos. 2 188,477 31,924 16,830 237,231.00 474,462.00
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.4.4.B Drop Manhole Rectangular or circular

4.4.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. 106.00 177,870.00 34,380.00 19,812.00 232,062.00 24,598,572.00

Dasherkandi Sewerage Project, Cost Estimate for Package 4 43 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -


4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.B.2.1 ø200 mm nos. 20 216,110.00 42,604.00 23,944.00 282,658.00 5,653,160.00


4.4.4.B.2.2 ø250 mm nos. 2 216,602.00 42,630.00 23,972.00 283,204.00 566,408.00
4.4.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00
4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.4.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.4.4.B.3.3 ø300 mm nos. 1 293,442.00 59,074.00 32,256.00 384,772.00 384,772.00
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 44 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -


4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

4.4.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.4.C.1.1 ø200 mm nos. 453.00 108,465.00 17,845.00 10,137.00 136,447.00 61,810,491.00


4.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 397 133,076.00 22,507.00 12,324.00 167,907.00 66,659,079.00


4.4.4.C.2.2 ø250 mm nos. 18 133,713.00 22,520.00 12,338.00 168,571.00 3,034,278.00
4.4.4.C.2.3 ø300 mm nos. 12 134,286.00 22,521.00 12,350.00 169,157.00 2,029,884.00
4.4.4.C.2.4 ø350 mm nos. 4 134,923.00 22,534.00 12,363.00 169,820.00 679,280.00
4.4.4.C.2.5 ø400 mm nos. 12 135,559.00 22,547.00 12,377.00 170,483.00 2,045,796.00
4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 45 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -


4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 7 182,295.00 31,825.00 16,700.00 230,820.00 1,615,740.00


4.4.4.C.3.2 ø250 mm nos. 14 182,932.00 31,838.00 16,713.00 231,483.00 3,240,762.00
4.4.4.C.3.3 ø300 mm nos. 14 183,505.00 31,840.00 16,725.00 232,070.00 3,248,980.00
4.4.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.4.4.C.3.5 ø400 mm nos. 4 184,778.00 31,866.00 16,752.00 233,396.00 933,584.00
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 17 185,988.00 31,881.00 16,777.00 234,646.00 3,988,982.00
4.4.4.C.3.8 ø600 mm nos. 25 187,267.00 31,910.00 16,805.00 235,982.00 5,899,550.00
4.4.4.C.3.9 ø700 mm nos. 3 188,477.00 31,924.00 16,830.00 237,231.00 711,693.00
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 1,462.00 40,766.88 13,972.83 8,265.14 63,004.85 92,113,090.70

4.2.5.2 ø200 mm nos. 585.00 44,627.58 15,581.46 9,230.31 69,439.35 40,622,019.75


4.2.5.3 ø250 mm nos. 585.00 51,128.58 18,290.21 10,855.56 80,274.35 46,960,494.75
4.2.5.4 ø300 mm nos. 292.00 55,471.38 20,099.71 11,941.26 87,512.35 25,553,606.20

Dasherkandi Sewerage Project, Cost Estimate for Package 4 46 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.4.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 151.00 11,079.12 3,235.25 433.10 14,747.46 2,226,866.46


4.4.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.4.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 132.00 11,079.12 3,614.08 439.51 15,132.71 1,997,517.72


4.4.6.A.2.2 ø250 mm nos. 6.00 11,597.22 3,810.28 460.57 15,868.07 95,208.42
4.4.6.A.2.3 ø300 mm nos. 4.00 12,111.88 4,007.30 481.54 16,600.72 66,402.88
4.4.6.A.2.4 ø350 mm nos. 1.00 12,575.47 4,195.03 500.60 17,271.10 17,271.10
4.4.6.A.2.5 ø400 mm nos. 4.00 13,090.13 4,395.42 521.95 18,007.50 72,030.00
4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.4.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 47 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. 2.00 11,079.12 4,371.74 452.35 15,903.21 31,806.42


4.4.6.A.3.2 ø250 mm nos. 5.00 11,597.22 4,617.36 474.24 16,688.82 83,444.10
4.4.6.A.3.3 ø300 mm nos. 5.00 12,111.88 4,863.80 496.05 17,471.72 87,358.60
4.4.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.4.6.A.3.5 ø400 mm nos. 1.00 13,090.13 5,350.74 538.14 18,979.00 18,979.00
4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.4.6.A.3.7 ø500 mm nos. 6.00 14,177.39 5,852.76 583.83 20,613.98 123,683.88
4.4.6.A.3.8 ø600 mm nos. 8.00 15,264.65 6,359.64 629.91 22,254.20 178,033.60
4.4.6.A.3.9 ø700 mm nos. 1.00 16,460.93 6,881.60 679.59 24,022.12 24,022.12
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.4: Column 'j' to be carried forward to Schedule No. 5


. 723,394,979.35
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 4 48 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.5 INSTALLATION of LOOP 405
4.5.1 Miscellaneous works during implementation
4.5.1.1 Setting-out LS 1.00 283,866.00 283,866.00
4.5.1.2 General works and site tests LS 1.00 567,732.00 567,732.00
4.5.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.5.2.1 LS 1.00 567,732.00 567,732.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.5.2.2 LS 1.00 212,899.50 212,899.50
completed & acceptance certificate
4.5.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.5.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.5.2.5 Development and submission of GIS based As-built drawings LS 1.00 354,832.50 354,832.50
4.5.2.6 Post Construction modelling LS 1.00 42,579.90 42,579.90

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.5.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.5.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.3.A.1.1 ø200 mm m 8,838.10 3,596.40 1,581.32 878.18 5,811.99 11,867.89 104,889,589.26


4.5.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.5.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.5.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.5.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.5.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.5.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.5.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.5.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.5.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 49 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.1.11 ø900 mm m - 19,017.29 2,714.29 5,263.12 11,301.09 38,295.79 -


4.5.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -

4.5.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.A.2.1 ø200 mm m 2,410 3,890.84 1,719.29 901.27 5,811.99 12,323.40 29,699,383.42


4.5.3.A.2.2 ø250 mm m 521 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 7,136,966.31
4.5.3.A.2.3 ø300 mm m 531 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 7,808,705.09
4.5.3.A.2.4 ø350 mm m 443 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 6,707,275.85
4.5.3.A.2.5 ø400 mm m 482 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 8,616,640.35
4.5.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.5.3.A.2.7 ø500 mm m 106 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 2,378,984.88
4.5.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.5.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.5.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.5.3.A.2.11 ø900 mm m 19,362.05 3,072.21 5,292.51 11,301.09 39,027.86 -

4.5.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -

4.5.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.5.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.5.3.A.3.3 ø300 mm m 90 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 2,600,718.53
4.5.3.A.3.4 ø350 mm m 349 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 10,244,678.29
4.5.3.A.3.5 ø400 mm m 83 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 2,674,620.94
4.5.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.5.3.A.3.7 ø500 mm m 145 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 5,305,484.36
4.5.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.5.3.A.3.9 ø700 mm m 195 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 9,444,726.99
4.5.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.5.3.A.3.11 ø900 mm m 31,348.01 4,425.66 6,319.90 11,301.09 53,394.67 -

4.5.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -

4.5.3.B Sewer Pipelines of Grade-B using GRP Pipes

Dasherkandi Sewerage Project, Cost Estimate for Package 4 50 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -

4.5.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -

4.5.3.B.2.11 ø900 mm m -

4.5.3.B.2.12 ø1000 mm m -

4.5.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 51 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -

4.5.3.B.3.11 ø900 mm m -

4.5.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.5.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.5.4.A Normal Manhole Rectangular or circular

4.5.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.A.1.1 ø200 mm nos. 298.00 108,465.00 17,845.00 10,137.00 136,447.00 40,661,206.00


4.5.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.5.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 52 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.A.2.1 ø200 mm nos. 42 133,076.00 22,507.00 12,324.00 167,907.00 7,052,094.00


4.5.4.A.2.2 ø250 mm nos. 18 133,713.00 22,520.00 12,338.00 168,571.00 3,034,278.00
4.5.4.A.2.3 ø300 mm nos. 14 134,286.00 22,521.00 12,350.00 169,157.00 2,368,198.00
4.5.4.A.2.4 ø350 mm nos. 16 134,923.00 22,534.00 12,363.00 169,820.00 2,717,120.00
4.5.4.A.2.5 ø400 mm nos. 16 135,559.00 22,547.00 12,377.00 170,483.00 2,727,728.00
4.5.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.5.4.A.2.7 ø500 mm nos. 8 136,776.00 22,565.00 12,402.00 171,743.00 1,373,944.00
4.5.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.5.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.5.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.5.4.A.3.3 ø300 mm nos. 1 183,505 31,840 16,725 232,070.00 232,070.00
4.5.4.A.3.4 ø350 mm nos. 11 184,142 31,853 16,738 232,733.00 2,560,063.00
4.5.4.A.3.5 ø400 mm nos. 2 184,778 31,866 16,752 233,396.00 466,792.00
4.5.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.5.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.5.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.5.4.A.3.9 ø700 mm nos. 5 188,477 31,924 16,830 237,231.00 1,186,155.00
4.5.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.5.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.5.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -

4.5.4.B Drop Manhole Rectangular or circular

4.5.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.B.1.1 ø200 mm nos. 72.00 177,870.00 34,380.00 19,812.00 232,062.00 16,708,464.00

Dasherkandi Sewerage Project, Cost Estimate for Package 4 53 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -


4.5.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.5.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.5.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.5.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.5.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.5.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.5.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.5.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.5.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.5.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -

4.5.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.B.2.1 ø200 mm nos. 10 216,110.00 42,604.00 23,944.00 282,658.00 2,826,580.00


4.5.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.5.4.B.2.3 ø300 mm nos. 1 216,968.00 42,634.00 23,994.00 283,596.00 283,596.00
4.5.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.5.4.B.2.5 ø400 mm nos. 1 217,952.00 42,686.00 24,050.00 284,688.00 284,688.00
4.5.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.5.4.B.2.7 ø500 mm nos. 1 218,824.00 42,720.00 24,100.00 285,644.00 285,644.00
4.5.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.5.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.5.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.5.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.5.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -

4.5.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.5.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.5.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.5.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.5.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 54 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -


4.5.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.5.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.5.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.5.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.5.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.5.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -

4.5.4.C Service connections Manhole Rectangular or circular -

4.5.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.5.4.C.1.1 ø200 mm nos. 492.00 108,465.00 17,845.00 10,137.00 136,447.00 67,131,924.00


4.5.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.5.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -

4.5.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.C.2.1 ø200 mm nos. 134 133,076.00 22,507.00 12,324.00 167,907.00 22,499,538.00


4.5.4.C.2.2 ø250 mm nos. 29 133,713.00 22,520.00 12,338.00 168,571.00 4,888,559.00
4.5.4.C.2.3 ø300 mm nos. 30 134,286.00 22,521.00 12,350.00 169,157.00 5,074,710.00
4.5.4.C.2.4 ø350 mm nos. 25 134,923.00 22,534.00 12,363.00 169,820.00 4,245,500.00
4.5.4.C.2.5 ø400 mm nos. 27 135,559.00 22,547.00 12,377.00 170,483.00 4,603,041.00
4.5.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.5.4.C.2.7 ø500 mm nos. 6 136,776.00 22,565.00 12,402.00 171,743.00 1,030,458.00

Dasherkandi Sewerage Project, Cost Estimate for Package 4 55 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -


4.5.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -

4.5.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.5.4.C.3.1 ø200 mm nos. 182,295.00 31,825.00 16,700.00 230,820.00 -


4.5.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.5.4.C.3.3 ø300 mm nos. 5 183,505.00 31,840.00 16,725.00 232,070.00 1,160,350.00
4.5.4.C.3.4 ø350 mm nos. 20 184,142.00 31,853.00 16,738.00 232,733.00 4,654,660.00
4.5.4.C.3.5 ø400 mm nos. 5 184,778.00 31,866.00 16,752.00 233,396.00 1,166,980.00
4.5.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.5.4.C.3.7 ø500 mm nos. 9 185,988.00 31,881.00 16,777.00 234,646.00 2,111,814.00
4.5.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.5.4.C.3.9 ø700 mm nos. 11 188,477.00 31,924.00 16,830.00 237,231.00 2,609,541.00
4.5.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.5.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.5.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.5.5.1 ø150 mm nos. 1,184.00 40,766.88 13,972.83 8,265.14 63,004.85 74,597,742.40

4.5.5.2 ø200 mm nos. 473.00 44,627.58 15,581.46 9,230.31 69,439.35 32,844,812.55


4.5.5.3 ø250 mm nos. 473.00 51,128.58 18,290.21 10,855.56 80,274.35 37,969,767.55
4.5.5.4 ø300 mm nos. 237.00 55,471.38 20,099.71 11,941.26 87,512.35 20,740,426.95

Dasherkandi Sewerage Project, Cost Estimate for Package 4 56 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.5.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.5.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.6.A.1.1 ø200 mm nos. 164.00 11,079.12 3,235.25 433.10 14,747.46 2,418,583.44


4.5.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.5.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.5.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.5.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.5.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.5.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.5.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.5.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.5.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.5.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.5.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

4.5.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.6.A.2.1 ø200 mm nos. 45.00 11,079.12 3,614.08 439.51 15,132.71 680,971.95


4.5.6.A.2.2 ø250 mm nos. 10.00 11,597.22 3,810.28 460.57 15,868.07 158,680.70
4.5.6.A.2.3 ø300 mm nos. 10.00 12,111.88 4,007.30 481.54 16,600.72 166,007.20
4.5.6.A.2.4 ø350 mm nos. 8.00 12,575.47 4,195.03 500.60 17,271.10 138,168.80
4.5.6.A.2.5 ø400 mm nos. 9.00 13,090.13 4,395.42 521.95 18,007.50 162,067.50
4.5.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.5.6.A.2.7 ø500 mm nos. 2.00 14,177.39 4,798.62 565.97 19,541.98 39,083.96
4.5.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.5.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.5.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.5.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

Dasherkandi Sewerage Project, Cost Estimate for Package 4 57 of 65 2018


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -

4.5.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.5.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.5.6.A.3.3 ø300 mm nos. 2.00 12,111.88 4,863.80 496.05 17,471.72 34,943.44
4.5.6.A.3.4 ø350 mm nos. 7.00 12,575.47 5,100.93 515.95 18,192.35 127,346.45
4.5.6.A.3.5 ø400 mm nos. 2.00 13,090.13 5,350.74 538.14 18,979.00 37,958.00
4.5.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.5.6.A.3.7 ø500 mm nos. 3.00 14,177.39 5,852.76 583.83 20,613.98 61,841.94
4.5.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.5.6.A.3.9 ø700 mm nos. 4.00 16,460.93 6,881.60 679.59 24,022.12 96,088.48
4.5.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.5.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.5.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -

Sub-total 4.5: Column 'j' to be carried forward to Schedule No. 5


. 575,780,102.47
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 4 58 of 65 2018


Schedule No. 5 - Grand Summary

Schedule No. Title


Total Price (BDT)

1 Schedule No. 1 - Pipe and Fittings Supplied from Abroad


2 Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
3 Schedule No. 3 - Design Services 228661125
4 Schedule No. 4 - Installation / Construction and Other works
4.1 Implementation Provisions and Preliminaries for all Loops 136263364
4.2 Installation/ Construction of all Loops (Schedule 4)
4.2.1 INSTALLATION of LOOP 401 236334880
4.2.2 INSTALLATION of LOOP 402 675815308
4.2.3 INSTALLATION of LOOP 403 401944727
4.2.4 INSTALLATION of LOOP 404 723394979
4.2.5 INSTALLATION of LOOP 405 575780102
Sub total 4.2: Installation/ Construction of all Loops (Schedule 4) 2613269997
5 Provisional Sum
5.1 Provisional sum for Physical Contingencies 130663500
5.2 Provisional Sum for Price Contingencies 124508224
5.3 Provisional Sum for alleviations program, refer to SCC, Sub-Clause xxxxxx 7466486
Sub-Total 5: Provisional Sum 262638209
6 Recommended spare parts 14859631
7 Day work 4832632
8 O&M - 59694344
. Grand Total (1+3+4.1+4.2+5+6+7+8) to be carried forward to Letter of Bid 3320219301

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 4 59 of 65 2018


Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh

Recommended Spare Parts


6.1 GRP Sewer Pipe (Dia in mm)
6.1.1 160 meter 80.00 1,770.40 1,770.40 141,632.00
6.1.2 200 meter 80.00 2,213.00 2,213.00 177,040.00
6.1.3 250 meter 80.00 2,923.00 2,923.00 233,840.00
6.1.4 300 meter 80.00 3,315.00 3,315.00 265,200.00
6.1.5 350 meter 100.00 4,292.00 4,292.00 429,200.00
6.1.6 400 meter 100.00 5,043.00 5,043.00 504,300.00
6.1.7 500 meter 100.00 7,807.00 7,807.00 780,700.00
6.1.8 600 meter 70.00 10,104.00 10,104.00 707,280.00
6.1.9 700 meter 70.00 15,281.00 15,281.00 1,069,670.00
6.1.10 800 meter 70.00 18,120.00 18,120.00 1,268,400.00
6.1.11 900 meter 70.00 16,711.99 16,711.99 1,169,839.07
6.1.12 1000 meter 70.00 18,462.01 18,462.01 1,292,340.93
6.2 Coupler/Coller
6.2.1 160 Pcs. 20.00 2,655.60 2,655.60 53,112.00
6.2.2 200 Pcs. 20.00 3,319.50 3,319.50 66,390.00
6.2.3 250 Pcs. 20.00 4,384.50 4,384.50 87,690.00
6.2.4 300 Pcs. 20.00 4,972.50 4,972.50 99,450.00
6.2.5 350 Pcs. 20.00 6,438.00 6,438.00 128,760.00
6.2.6 400 Pcs. 20.00 7,564.50 7,564.50 151,290.00
6.2.7 500 Pcs. 20.00 11,710.50 11,710.50 234,210.00
6.2.8 600 Pcs. 20.00 15,156.00 15,156.00 303,120.00
6.2.9 700 Pcs. 20.00 22,921.50 22,921.50 458,430.00
6.2.10 800 Pcs. 20.00 27,180.00 27,180.00 543,600.00
6.2.11 900 Pcs. 20.00 25,067.98 25,067.98 501,359.60
6.2.12 1000 Pcs. 20.00 27,693.02 27,693.02 553,860.40
6.3 Flange Adapter
6.3.1 160 Pcs. 10.00 885.20 885.20 8,852.00
6.3.2 200 Pcs. 10.00 1,106.50 1,106.50 11,065.00
6.3.3 250 Pcs. 10.00 1,461.50 1,461.50 14,615.00
6.3.4 300 Pcs. 10.00 1,657.50 1,657.50 16,575.00
6.3.5 350 Pcs. 10.00 2,146.00 2,146.00 21,460.00
6.3.6 400 Pcs. 10.00 2,521.50 2,521.50 25,215.00
6.3.7 500 Pcs. 10.00 3,903.50 3,903.50 39,035.00
6.3.8 600 Pcs. 10.00 5,052.00 5,052.00 50,520.00

Dasherkandi Sewerage Project, Cost Estimate for Package 4 60 of 65 2018


Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh
6.3.9 700 Pcs. 10.00 7,640.50 7,640.50 76,405.00
6.3.10 800 Pcs. 10.00 9,060.00 9,060.00 90,600.00
6.3.11 900 Pcs. 10.00 8,355.99 8,355.99 83,559.93
6.3.12 1000 Pcs. 10.00 9,231.01 9,231.01 92,310.07
6.4 Tee/Wye
6.4.1 160 Pcs. 10.00 2,655.60 2,655.60 26,556.00
6.4.2 200 Pcs. 10.00 3,319.50 3,319.50 33,195.00
6.4.3 250 Pcs. 10.00 4,384.50 4,384.50 43,845.00
6.4.4 300 Pcs. 10.00 4,972.50 4,972.50 49,725.00
6.4.5 350 Pcs. 10.00 6,438.00 6,438.00 64,380.00
6.4.6 400 Pcs. 10.00 10,086.00 10,086.00 100,860.00
6.4.7 500 Pcs. 10.00 15,614.00 15,614.00 156,140.00
6.4.8 600 Pcs. 10.00 20,208.00 20,208.00 202,080.00
6.4.9 700 Pcs. 10.00 30,562.00 30,562.00 305,620.00
6.4.10 800 Pcs. 10.00 36,240.00 36,240.00 362,400.00
6.4.11 900 Pcs. 10.00 33,423.97 33,423.97 334,239.73
6.4.12 1000 Pcs. 10.00 36,924.03 36,924.03 369,240.27
6.5 Elbow (30/60/90 degrees)
6.5.1 160 Pcs. 10.00 1,770.40 1,770.40 17,704.00
6.5.2 200 Pcs. 10.00 2,213.00 2,213.00 22,130.00
6.5.3 250 Pcs. 10.00 2,923.00 2,923.00 29,230.00
6.5.4 300 Pcs. 10.00 3,315.00 3,315.00 33,150.00
6.5.5 350 Pcs. 10.00 4,292.00 4,292.00 42,920.00
6.5.6 400 Pcs. 10.00 5,043.00 5,043.00 50,430.00
6.5.7 500 Pcs. 10.00 7,807.00 7,807.00 78,070.00
6.5.8 600 Pcs. 10.00 10,104.00 10,104.00 101,040.00
6.5.9 700 Pcs. 10.00 15,281.00 15,281.00 152,810.00
6.5.10 800 Pcs. 10.00 18,120.00 18,120.00 181,200.00
6.5.11 900 Pcs. 10.00 16,711.99 16,711.99 167,119.87
6.5.12 1000 Pcs. 10.00 18,462.01 18,462.01 184,620.13
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 14,859,631.00

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 4 61 of 65 2018


Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.1 Equipment
7.1.1 Micro Tunneling Machine with complete set hrs. 80 6,000.00 6,000.00 480,000.00
7.1.2 Hydraulic HDD Unit hrs. 50 4,000.00 4,000.00 200,000.00
7.1.3 Excavator, face shovel, or dragline:
7.1.3.1 Up to and including 1 m3 hrs. 50 2,000.00 2,000.00 100,000.00
7.1.3.2 Over 1 m3 to 2 m3 hrs. 60 3,000.00 3,000.00 180,000.00
7.1.3.3 Over 2 m3 hrs. 40 3,510.00 3,510.00 140,400.00
7.1.4 Tractor, including bull or angle dozer:
7.1.4.1 Up to and including 150 kW hrs. 70 1,000.00 1,000.00 70,000.00
7.1.4.2 Over 150 kW to 200 kW hrs. 70 1,500.00 1,500.00 105,000.00
7.1.4.3 Over 200 kW to 250 kW hrs. 70 2,000.00 2,000.00 140,000.00
7.1.5 Tractor with ripper:
7.1.5.1 Up to and including 200 kW hrs. 70 1,500.00 1,500.00 105,000.00
7.1.5.2 Over 200 kW to 250 kW hrs. 70 2,000.00 2,000.00 140,000.00
7.1.6 Portable concrete mixer - 0.4m3 hrs. 100 500.00 500.00 50,000.00
7.1.7 Hydraulic Excavator – 1 m3 hrs. 70 3,000.00 3,000.00 210,000.00
7.1.8 4-tool compressor including tools and hoses hrs. 70 2,000.00 2,000.00 140,000.00
7.1.9 10 tonne lorry-mounted crane hrs. 70 5,000.00 5,000.00 350,000.00
7.1.10 750 Kg crane hrs. 70 2,000.00 2,000.00 140,000.00
7.1.11 0.5 m3 dumper hrs. 70 1,000.00 1,000.00 70,000.00
7.1.12 1 m3 dumper hrs. 70 1,500.00 1,500.00 105,000.00
7.1.13 7 m3 tipper lorry hrs. 70 2,000.00 2,000.00 140,000.00
7.1.14 15 m3 lorry hrs. 70 2,000.00 2,000.00 140,000.00
7.1.15 4 wheel drive pick-up or van hrs. 70 500.00 500.00 35,000.00
7.1.16 Vibrating plate compactor hrs. 70 500.00 500.00 35,000.00
7.1.17 8-10 tonne roller hrs. 70 2,000.00 2,000.00 140,000.00
7.1.18 Scaffolding, 10 sqm day 10 2,025.00 2,025.00 20,250.00
7.1.19 5-Ton capacity truck-fare in Dhaka city i/c loading, unloading hrs. 100 456.50 456.50 45,650.00
7.1.20 Concrete mixer machine -1 bag capacity hrs. 60 537.50 537.50 32,250.00
7.1.21 Concrete vibrator-40mm dia hrs. 60 423.00 423.00 25,380.00
7.1.22 Diesel operated 1 cusec pump hrs. 100 505.00 505.00 50,500.00
7.1.23 Electricity operated 1 cusec pump hrs. 80 329.00 329.00 26,320.00
7.1.24 Road cutting Equipment hrs. 80 1,097.00 1,097.00 87,760.00
7.1.25 Backhoe Loader, wheel operated hrs. 50 3,510.00 3,510.00 175,500.00

Dasherkandi Sewerage Project, Cost Estimate for Package 4 62 of 65 2018


Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh

7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 30 675.00 675.00 20,250.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 30 607.50 607.50 18,225.00
clinker): 50kg bag
7.2.3 White Cement kg 80 54.00 54.00 4,320.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 0.50 86,400.00 86,400.00 43,200.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 0.50 87,750.00 87,750.00 43,875.00
7.2.6 MS Sheet M Ton 0.50 114,750.00 114,750.00 57,375.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 1,670 10,800.00 10,800.00 18,036.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 1,670 12,150.00 12,150.00 20,290.50
7.2.9 Imported Earth m3 30 572.50 572.50 17,175.00
7.2.10 Sand (F.M. 0.8) m3 30 525.00 525.00 15,750.00
7.2.11 Sand (F.M. 1.2) m3 20 810.50 810.50 16,210.00
7.2.12 Sand (F.M. 2.5) m3 20 2,384.00 2,384.00 47,680.00
7.2.13 Viti/Filling Sand m3 30 524.50 524.50 15,735.00

Dasherkandi Sewerage Project, Cost Estimate for Package 4 63 of 65 2018


Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.3 Labor
-
7.3.1 Contract Manager day 10 15,000.00 15,000.00 150,000.00
7.3.2 Office Assistant day 20 500.00 500.00 10,000.00
7.3.3 Contract / Legal Advisor day 10 5,000.00 5,000.00 50,000.00
7.3.4 Financial Advisor day 10 5,000.00 5,000.00 50,000.00
7.3.5 Quantity Engineer day 10 3,000.00 3,000.00 30,000.00
7.3.6 Designer day 10 10,000.00 10,000.00 100,000.00
7.3.7 Field Engineer day 10 3,000.00 3,000.00 30,000.00
7.3.8 Draft Person day 10 2,000.00 2,000.00 20,000.00
7.3.9 Ordinary/casual Labour day 80 600.00 600.00 48,000.00
7.3.10 Skilled labour day 40 945.00 945.00 37,800.00
7.3.11 Head Operator/Ganger day 10 1,080.00 1,080.00 10,800.00
7.3.12 Asstt. Operator/Ganger day 20 945.00 945.00 18,900.00
7.3.13 Head Mason day 10 1,080.00 1,080.00 10,800.00
7.3.14 Mud Operator day 10 945.00 945.00 9,450.00
7.3.15 Field Supervisor/Manager day 10 3,375.00 3,375.00 33,750.00
7.3.16 Field/Maintenance Engineer day 20 2,700.00 2,700.00 54,000.00
7.3.17 Skilled technician/Plumber/Mason/Steel work Erector/ day 20 800.00 800.00 16,000.00
7.3.18 Semi Skilled technician day 40 700.00 700.00 28,000.00
7.3.19 Site security day 20 600.00 600.00 12,000.00
7.3.20 Driver day 20 1,100.00 1,100.00 22,000.00
7.3.21 Sweeper for Odd Job day 20 1,000.00 1,000.00 20,000.00
7.3.22 Surveyor day 20 1,080.00 1,080.00 21,600.00
7.3.23 Asstt. Surveyor day 40 810.00 810.00 32,400.00
7.3.24 Carpenter

Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 4,832,631.50

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 4 64 of 65 2018


Schedule No. 8 - O&M Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price
a b c d e f g h=e+f+g i=dxh
8 O&M Services and Documentation

8.1 One year O&M (5 Loops in Segments 13-16)


8.1.1 O&M Services in Loop 401 km 6.16 934,330.00 5,755,472.80
8.1.2 O&M Services in Loop 402 km 16.13 934,330.00 15,070,742.90
8.1.3 O&M Services in Loop 403 km 9.88 934,330.00 9,231,180.40
8.1.4 O&M Services in Loop 404 km 17.53 934,330.00 16,378,804.90
8.1.5 O&M Services in Loop 405 km 14.19 934,330.00 13,258,142.70
63.89
Sub-total 8.1: Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 59,694,343.70

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 4 65 of 65 2018


Employer’s Cost Estimates8

G: Cost of Package 5 (Segment 17 to 19)


Schedule No. 1 - Pipe and Fittings Supplied from Abroad

Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 121,902.50
1.1.2 ø250 mm m 1,310.60
1.1.3 ø300 mm m 1,768.60
1.1.4 ø350 mm m 1,528.50
1.1.5 ø400 mm m 555.30
1.1.6 ø450 mm m
1.1.7 ø500 mm m 826.70
1.1.8 ø600 mm m 1,392.90
1.1.9 ø700 mm m 1,569.50
1.1.10 ø800 mm m 176.60
1.1.11 ø900 mm m
1.1.12 ø1000 mm m 554.30
1.1.13 ø1100 mm m 1,823.80
1.1.14 ø1300 mm m 188.10
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 244
1.2.2 ø250 mm nos. 3
1.2.3 ø300 mm nos. 4
1.2.4 ø350 mm nos. 3
1.2.5 ø400 mm nos. 1
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 2
1.2.8 ø600 mm nos. 3
1.2.9 ø700 mm nos. 3

Dasherkandi Sewerage Project, Cost Estimate for Package 5 1 of 101


Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.10 ø800 mm nos.

Dasherkandi Sewerage Project, Cost Estimate for Package 5 2 of 101


Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.11 ø900 mm nos.
1.2.12 ø1000 mm nos. 1
1.2.13 ø1100 mm nos. 4
1.2.14 ø1300 mm nos.
1.3 Equal and Un Equal Tee of different sizes
1.3.1 200mm x200mm nos. 244
1.3.2 250mm x250mm nos. 3
1.3.3 300mm X 300mm nos. 4
1.3.4 350mm X 350mm nos. 3
1.3.5 400mm X 400mm nos. 1
1.3.6 450mm X 450mm nos.
1.3.7 500mm X 500mm nos. 2
1.3.8 600 mm X 600mm nos. 3
1.3.9 700mm X 700mm nos. 3
1.3.10 800mm x 800mm nos.
1.3.11 900mm X 900mm nos.
1.3.12 1000mm X 1000mm nos. 1
1.3.13 250mm X250mm X 200mm nos. 3
1.3.14 300mm X 300mm X 200mm nos. 4
1.3.15 300mm X 300mm X 250mm nos. 3
1.3.16 400mm X 400mm X 200mm nos. 1
1.3.17 400mm X 400mm X 250mm nos.
1.3.18 400mm X 400mm X 300mm nos. 2
1.3.19 500mm X 500mm X 200mm nos. 3
1.3.20 500mm X 500mm X 300mm nos. 3
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos. 488

Dasherkandi Sewerage Project, Cost Estimate for Package 5 3 of 101


Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4.2 ø250 mm nos. 6
1.4.3 ø300 mm nos. 8
1.4.4 ø350 mm nos. 6
1.4.5 ø400 mm nos. 2
1.4.6 ø450 mm nos.
1.4.7 ø500 mm nos. 4
1.4.8 ø600 mm nos. 6
1.4.9 ø700 mm nos. 6
1.4.10 ø800 mm nos.
1.4.11 ø900 mm nos.
1.4.12 ø1000 mm nos. 2
1.4.13 ø1100 mm nos. 8
1.4.14 ø1300 mm nos.
1.5 Flanged Adapters
1.5.1 ø200 mm nos. 61
1.5.2 ø250 mm nos. 1
1.5.3 ø300 mm nos. 1
1.5.4 ø350 mm nos. 1
1.5.5 ø400 mm nos. 1
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos. 1
1.5.8 ø600 mm nos. 1
1.5.9 ø700 mm nos. 1
1.5.10 ø800 mm nos. 1
1.5.11 ø900 mm nos. 1
1.5.12 ø1000 mm nos. 1
1.5.13 ø1100 mm nos. 1
1.5.14 ø1300 mm nos. 1

Dasherkandi Sewerage Project, Cost Estimate for Package 5 4 of 101


Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)

Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 5 5 of 101


Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country

Unit Price (BDT)


Sales and other
Item Description Unit Qty. Total Unit Total Price (BDT)
Material Labour Equipment taxes (BDT)
Price (EXW)
a b c d e f g h=e+f+g i=dxh j

Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 5 6 of 101


Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

3.1 Design / Survey Provisions and Preliminaries


3.1.1 Insurances
3.1.1.1 For design (professional indemnity insurance) LS 1 27,687,918.53 27,687,918.53
3.1.1.2 Other Insurances (to be specified by the Tenderer) LS 1 13,843,959 13,843,959.26
Sub-total A: 41,531,877.79
3.2 Design Services (including design office and establishment)

3.2.1 Loop 501


3.2.1.1 Survey and documentation, including Survey Report LS 1 39,660,150 39,660,150.21
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.1.2 LS 1 24,236,758 24,236,758.46
Report
3.2.1.3 Design Control Services including documentation LS 1 6,610,025 6,610,025.04

3.2.2 Loop 502


3.2.2.1 Survey and documentation, including Survey Report LS 1 18,128,377 18,128,376.57
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.2.2 LS 1 11,078,452 11,078,452.35
Report
3.2.2.3 Design Control Services including documentation LS 1 3,021,396 3,021,396.10

3.2.3 Loop 503


3.2.3.1 Survey and documentation, including Survey Report LS 1 35,212,855 35,212,855.17

Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.3.2 LS 1 21,518,967 21,518,967.05
Report
3.2.3.3 Design Control Services including documentation LS 1 5,868,809 5,868,809.19

3.2.4 Loop 504


3.2.4.1 Survey and documentation, including Survey Report LS 1 13,271,358 13,271,357.63
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.4.2 LS 1 8,110,274 8,110,274.11
Report
3.2.4.3 Design Control Services including documentation LS 1 2,211,893 2,211,892.94

3.2.5 Loop 505


3.2.5.1 Survey and documentation, including Survey Report LS 1 57,121,669 57,121,668.57

Dasherkandi Sewerage Project, Cost Estimate for Package 5 7 of 101


Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.5.2 LS 1 34,907,686 34,907,686.35
Report
3.2.5.3 Design Control Services including documentation LS 1 9,520,278 9,520,278.10

3.2.6 Loop 506


3.2.6.1 Survey and documentation, including Survey Report LS 1 33,480,358 33,480,358.28
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.6.2 LS 1 20,460,219 20,460,218.95
Report
3.2.6.3 Design Control Services including documentation LS 1 5,580,060 5,580,059.71

3.2.7 Loop 507


3.2.7.1 Survey and documentation, including Survey Report LS 1 52,316,500 52,316,500.33
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.7.2 LS 1 31,971,195 31,971,194.65
Report
3.2.7.3 Design Control Services including documentation LS 1 8,719,417 8,719,416.72

Sub-total B: 443,006,696.48
Total A+B: Sub-total 3:
484,538,574.27
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary

Name of Bidder:

Signature of Bidder:

Dasherkandi Sewerage Project, Cost Estimate for Package 5 8 of 101


Schedule No. 4 - Installation / Construction and Other works

Unit Price (BDT)


Item Description Unit Qty. Total Unit Total Price (BDT)
Material Labour Equipment
Price

a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 13,843,959.26 13,843,959.26
4.1.1.2 Advance Payment Guarantee LS 1 13,843,959.26 13,843,959.26
Subtotal 4.1.1 27,687,918.53
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.2 Installation All Risks Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.3 Third Party Liability Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.4 Automobile Liability Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.5 Workers' Compensation LS 1 20,765,938.90 20,765,938.90
4.1.2.6 Employer's Liability LS 1 20,765,938.90 20,765,938.90
4.1.2.7 Contractor's Equipment Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 20,765,938.90 20,765,938.90
Subtotal 4.1.2 166,127,511.18
4.1.3 Site establishment, operation and removal

Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 15,821,667.73 15,821,667.73
workshops, site access and miscellaneous services etc.

Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 15,821,667.73 15,821,667.73
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 15,821,667.73 15,821,667.73
4.1.3.4 Survey instruments LS 1 15,821,667.73 15,821,667.73
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 15,821,667.73 15,821,667.73
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 15,821,667.73 15,821,667.73
Subtotal 4.1.3 94,930,006.39

Dasherkandi Sewerage Project, Cost Estimate for Package 5 9 of 101


Schedule No. 4 - Installation / Construction and Other works

Unit Price (BDT)


Item Description Unit Qty. Total Unit Total Price (BDT)
Material Labour Equipment
Price

a b c d e f g h=e+f+g i=dxh
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 288,745,436.10

Dasherkandi Sewerage Project, Cost Estimate for Package 5 10 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.2 INSTALLATION of LOOP 501
4.2.1 Miscellaneous works during implementation
4.2.1.1 Setting-out LS 1.00 432,356.00 432,356.00
4.2.1.2 General works and site tests LS 1.00 864,712.00 864,712.00
4.2.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.2.2.1 LS 1.00 864,712.00 864,712.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction completed
4.2.2.2 LS 1.00 324,267.00 324,267.00
& acceptance certificate
4.2.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.2.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.2.2.5 Development and submission of GIS based As-built drawings LS 1.00 540,445.00 540,445.00
4.2.2.6 Post Construction modelling LS 1.00 64,853.40 64,853.40

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified below,
including fitting, fixing of all items, road cutting permission fee, temporary road
4.2.3 -
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.2.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.2.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.3.A.1.1 ø200 mm m 13,974.80 3,596.40 1,581.32 878.18 5,811.99 11,867.89 165,851,374.39


4.2.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.2.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.2.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.2.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.2.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.2.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.2.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.2.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.2.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 11 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -


4.2.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.2.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.2.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.2.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.A.2.1 ø200 mm m 3,981.50 3,890.84 1,719.29 901.27 5,811.99 12,323.40 49,065,599.62


4.2.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.2.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.2.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.2.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.2.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.2.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.2.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.2.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.2.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.2.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.2.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.2.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.A.3.1 ø200 mm m 3,661.50 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 97,117,001.38


4.2.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.2.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.2.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.2.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.2.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.2.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.2.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.2.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 12 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.2.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.2.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.2.3.A.2.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.2.3.A.2.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.2.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.2.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.2.3.B.1.1 ø200 mm m -
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -

4.2.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 13 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -

4.2.3.B.2.11 ø900 mm m -

4.2.3.B.2.12 ø1000 mm m -

4.2.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -

4.2.3.B.3.11 ø900 mm m -

4.2.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.2.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved drawing and
specification.

4.2.4.A Normal Manhole Rectangular or circular

Dasherkandi Sewerage Project, Cost Estimate for Package 5 14 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.2.4.A.1.1 ø200 mm nos. 451.00 108,465.00 17,845.00 10,137.00 136,447.00 61,537,597.00


4.2.4.A.1.2 ø250 mm nos. 2.00 109,101.00 17,858.00 10,150.00 137,109.00 274,218.00
4.2.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.2.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.2.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.2.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.2.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.A.2.1 ø200 mm nos. 97 133,076.00 22,507.00 12,324.00 167,907.00 16,286,979.00


4.2.4.A.2.2 ø250 mm nos. 13 133,713.00 22,520.00 12,338.00 168,571.00 2,191,423.00
4.2.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.2.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.2.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.2.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.2.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.2.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.2.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.2.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.2.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 15 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.2.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.A.3.1 ø200 mm nos. 13 182,295 31,825 16,700 230,820.00 3,000,660.00


4.2.4.A.3.2 ø250 mm nos. 18 182,932 31,838 16,713 231,483.00 4,166,694.00
4.2.4.A.3.3 ø300 mm nos. 13 183,505 31,840 16,725 232,070.00 3,016,910.00
4.2.4.A.3.4 ø350 mm nos. 5 184,142 31,853 16,738 232,733.00 1,163,665.00
4.2.4.A.3.5 ø400 mm nos. 20 184,778 31,866 16,752 233,396.00 4,667,920.00
4.2.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.2.4.A.3.7 ø500 mm nos. 27 185,988 31,881 16,777 234,646.00 6,335,442.00
4.2.4.A.3.8 ø600 mm nos. 17 187,267 31,910 16,805 235,982.00 4,011,694.00
4.2.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.2.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.2.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.2.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.2.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.2.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.2.4.B Drop Manhole Rectangular or circular

4.2.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.2.4.B.1.1 ø200 mm nos. 37.00 177,870.00 34,380.00 19,812.00 232,062.00 8,586,294.00


4.2.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.2.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.2.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.2.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.2.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.2.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.2.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.2.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.2.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.2.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 16 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -


4.2.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.2.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.2.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.B.2.1 ø200 mm nos. 5 216,110.00 42,604.00 23,944.00 282,658.00 1,413,290.00


4.2.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.2.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.2.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.2.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.2.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.2.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.2.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.2.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.2.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.2.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.2.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.2.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.2.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.2.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.2.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.2.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.2.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.2.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.2.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.2.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.2.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.2.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.2.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 17 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.2.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.2.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.2.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.2.4.C Service connections Manhole Rectangular or circular -

4.2.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.2.4.C.1.1 ø200 mm nos. 777.00 108,465.00 17,845.00 10,137.00 136,447.00 106,019,319.00


4.2.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.2.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.2.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.B.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.2.4.B.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.2.4.B.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.2.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.C.2.1 ø200 mm nos. 222 133,076.00 22,507.00 12,324.00 167,907.00 37,275,354.00


4.2.4.C.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.2.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.2.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.2.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.2.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.2.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 18 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -


4.2.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.2.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.2.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.2.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.2.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.2.4.C.3.1 ø200 mm nos. 204 182,295.00 31,825.00 16,700.00 230,820.00 47,087,280.00


4.2.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.2.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.2.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.2.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.2.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.2.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.2.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.2.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.2.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.2.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

4.2.4.B.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.2.4.B.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.2.4.B.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting, fixing
of all items, road cutting permission fee, temporary road reinstatement, dismantling
4.2.5 of existing structures, site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 1,803.00 40,766.88 13,972.83 8,265.14 63,004.85 113,597,744.55

4.2.5.2 ø200 mm nos. 721.00 44,627.58 15,581.46 9,230.31 69,439.35 50,065,771.35


4.2.5.3 ø250 mm nos. 721.00 51,128.58 18,290.21 10,855.56 80,274.35 57,877,806.35

Dasherkandi Sewerage Project, Cost Estimate for Package 5 19 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.5.4 ø300 mm nos. 361.00 55,471.38 20,099.71 11,941.26 87,512.35 31,591,958.35

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning, earth
4.2.6 -
cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per approved
drawing and specification.

4.2.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.6.A.1.1 ø200 mm nos. 259.00 11,079.12 3,235.25 433.10 14,747.46 3,819,592.14


4.2.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.2.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.2.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.2.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.2.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.2.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.2.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.2.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.2.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.2.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.2.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -
4.2.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -
4.2.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.2.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.6.A.2.1 ø200 mm nos. 74.00 11,079.12 3,614.08 439.51 15,132.71 1,119,820.54


4.2.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.2.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.2.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.2.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.2.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.2.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.2.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 20 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -


4.2.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.2.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.2.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.2.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.2.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.2.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.6.A.3.1 ø200 mm nos. 68.00 11,079.12 4,371.74 452.35 15,903.21 1,081,418.28


4.2.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.2.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.2.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.2.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.2.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.2.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.2.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.2.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.2.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.2.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.2.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.2.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.2.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.2: Column 'j' to be carried forward to Schedule No. 5


. 881,336,671.35
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 5 21 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.3 INSTALLATION of LOOP 502
4.3.1 Miscellaneous works during implementation
4.3.1.1 Setting-out LS 1.00 176,156.00 176,156.00
4.3.1.2 General works and site tests LS 1.00 352,312.00 352,312.00
4.3.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.3.2.1 LS 1.00 352,312.00 352,312.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.3.2.2 LS 1.00 132,117.00 132,117.00
completed & acceptance certificate
4.3.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.3.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.3.2.5 Development and submission of GIS based As-built drawings LS 1.00 220,195.00 220,195.00
4.3.2.6 Post Construction modelling LS 1.00 26,423.40 26,423.40

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.3.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.3.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.3.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.3.A.1.1 ø200 mm m 5,476.70 3,596.40 1,581.32 878.18 5,811.99 11,867.89 64,996,867.37


4.3.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.3.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.3.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.3.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.3.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.3.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.3.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.3.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 22 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -


4.3.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -
4.3.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.3.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.3.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.3.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.A.2.1 ø200 mm m 911.30 3,890.84 1,719.29 901.27 5,811.99 12,323.40 11,230,310.42


4.3.3.A.2.2 ø250 mm m 91.40 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 1,251,811.02
4.3.3.A.2.3 ø300 mm m 393.50 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 5,783,409.48
4.2.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.3.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.3.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.3.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.3.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.3.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.3.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.2.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.2.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.3.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.A.3.1 ø200 mm m 29.90 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 793,062.50


4.3.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.3.3.A.3.3 ø300 mm m 114.50 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 3,312,372.32
4.3.3.A.3.4 ø350 mm m 163.40 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 4,795,131.58
4.3.3.A.3.5 ø400 mm m 363.40 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 11,682,178.48
4.3.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.3.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 23 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -


4.3.3.A.3.9 ø700 mm m 1,134.80 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 55,019,898.29
4.3.3.A.3.10 ø800 mm m 96.80 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 5,263,454.53

4.3.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.3.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.3.3.A.2.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.3.3.A.2.14 ø1300 mm m 32.10 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 2,025,070.25

4.3.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.3.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -

4.3.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 24 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -

4.3.3.B.2.11 ø900 mm m -

4.3.3.B.2.12 ø1000 mm m -

4.3.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -

4.3.3.B.3.11 ø900 mm m -

4.3.3.B.3.12 ø1000 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 25 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.3.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.3.4.A Normal Manhole Rectangular or circular

4.3.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.A.1.1 ø200 mm nos. 199.00 108,465.00 17,845.00 10,137.00 136,447.00 27,152,953.00


4.3.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.3.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.3.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.3.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.3.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.3.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.A.2.1 ø200 mm nos. 19 133,076.00 22,507.00 12,324.00 167,907.00 3,190,233.00


4.3.4.A.2.2 ø250 mm nos. 3 133,713.00 22,520.00 12,338.00 168,571.00 505,713.00
4.3.4.A.2.3 ø300 mm nos. 15 134,286.00 22,521.00 12,350.00 169,157.00 2,537,355.00
4.3.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.3.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 26 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -


4.3.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.3.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.3.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.3.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.3.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.3.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.3.4.A.3.3 ø300 mm nos. 2 183,505 31,840 16,725 232,070.00 464,140.00
4.3.4.A.3.4 ø350 mm nos. 5 184,142 31,853 16,738 232,733.00 1,163,665.00
4.3.4.A.3.5 ø400 mm nos. 8 184,778 31,866 16,752 233,396.00 1,867,168.00
4.3.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.3.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.3.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.3.4.A.3.9 ø700 mm nos. 27 188,477 31,924 16,830 237,231.00 6,405,237.00
4.3.4.A.3.10 ø800 mm nos. 4 189,750 31,950 16,858 238,558.00 954,232.00

4.3.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.3.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.3.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.3.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.3.4.B Drop Manhole Rectangular or circular

4.3.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.B.1.1 ø200 mm nos. 14.00 177,870.00 34,380.00 19,812.00 232,062.00 3,248,868.00


4.3.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.3.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 27 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -


4.3.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.3.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.3.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.3.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.3.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.3.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.3.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.3.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.3.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.3.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.3.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.B.2.1 ø200 mm nos. 1 216,110.00 42,604.00 23,944.00 282,658.00 282,658.00


4.3.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.3.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.3.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.3.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.3.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.3.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.3.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.3.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.3.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.3.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.3.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.3.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.3.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.3.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 28 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -


4.3.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.3.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.3.4.B.3.5 ø400 mm nos. 1 294,426.00 59,126.00 32,310.00 385,862.00 385,862.00
4.3.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.3.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.3.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.3.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.3.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.3.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.3.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.3.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.3.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.3.4.C Service connections Manhole Rectangular or circular -

4.3.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.3.4.C.1.1 ø200 mm nos. 305.00 108,465.00 17,845.00 10,137.00 136,447.00 41,616,335.00


4.3.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.3.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.3.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.3.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 29 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.3.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.C.2.1 ø200 mm nos. 51 133,076.00 22,507.00 12,324.00 167,907.00 8,563,257.00


4.3.4.C.2.2 ø250 mm nos. 6 133,713.00 22,520.00 12,338.00 168,571.00 1,011,426.00
4.3.4.C.2.3 ø300 mm nos. 22 134,286.00 22,521.00 12,350.00 169,157.00 3,721,454.00
4.3.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.3.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.3.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.3.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.3.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.3.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.3.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.3.4.C.3.1 ø200 mm nos. 2 182,295.00 31,825.00 16,700.00 230,820.00 461,640.00


4.3.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.3.4.C.3.3 ø300 mm nos. 7 183,505.00 31,840.00 16,725.00 232,070.00 1,624,490.00
4.3.4.C.3.4 ø350 mm nos. 10 184,142.00 31,853.00 16,738.00 232,733.00 2,327,330.00
4.3.4.C.3.5 ø400 mm nos. 21 184,778.00 31,866.00 16,752.00 233,396.00 4,901,316.00
4.3.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.3.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.3.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.3.4.C.3.9 ø700 mm nos. 64 188,477.00 31,924.00 16,830.00 237,231.00 15,182,784.00
4.3.4.C.3.10 ø800 mm nos. 6 189,750.00 31,950.00 16,858.00 238,558.00 1,431,348.00

4.3.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 30 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.3.4.C.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.3.4.C.3.14 ø1300 mm nos. 2 196,001.00 32,064.00 16,991.00 245,056.00 490,112.00

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.3.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.3.5.1 ø150 mm nos. 735.00 40,766.88 13,972.83 8,265.14 63,004.85 46,308,564.75

4.3.5.2 ø200 mm nos. 294.00 44,627.58 15,581.46 9,230.31 69,439.35 20,415,168.90


4.3.5.3 ø250 mm nos. 294.00 51,128.58 18,290.21 10,855.56 80,274.35 23,600,658.90
4.3.5.4 ø300 mm nos. 147.00 55,471.38 20,099.71 11,941.26 87,512.35 12,864,315.45

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.3.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.3.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.6.A.1.1 ø200 mm nos. 102.00 11,079.12 3,235.25 433.10 14,747.46 1,504,240.92


4.3.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.3.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.3.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.3.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.3.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.3.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.3.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.3.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.3.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.3.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.3.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 31 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -


4.3.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.3.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.6.A.2.1 ø200 mm nos. 17.00 11,079.12 3,614.08 439.51 15,132.71 257,256.07


4.3.6.A.2.2 ø250 mm nos. 2.00 11,597.22 3,810.28 460.57 15,868.07 31,736.14
4.3.6.A.2.3 ø300 mm nos. 7.00 12,111.88 4,007.30 481.54 16,600.72 116,205.04
4.3.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.3.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.3.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.3.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.3.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.3.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.3.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.3.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.3.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.3.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.3.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.3.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.6.A.3.1 ø200 mm nos. 1.00 11,079.12 4,371.74 452.35 15,903.21 15,903.21


4.3.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.3.6.A.3.3 ø300 mm nos. 2.00 12,111.88 4,863.80 496.05 17,471.72 34,943.44
4.3.6.A.3.4 ø350 mm nos. 3.00 12,575.47 5,100.93 515.95 18,192.35 54,577.05
4.3.6.A.3.5 ø400 mm nos. 7.00 13,090.13 5,350.74 538.14 18,979.00 132,853.00
4.3.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.3.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.3.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.3.6.A.3.9 ø700 mm nos. 21.00 16,460.93 6,881.60 679.59 24,022.12 504,464.52
4.3.6.A.3.10 ø800 mm nos. 2.00 17,602.69 7,398.46 727.66 25,728.81 51,457.62

Dasherkandi Sewerage Project, Cost Estimate for Package 5 32 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.3.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.3.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.3.6.A.3.14 ø1300 mm nos. 1.00 24,183.62 10,127.67 998.77 35,310.06 35,310.06

Sub-total 4.3: Column 'j' to be carried forward to Schedule No. 5


. 402,852,812.69
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 5 33 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 503
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 388,606.00 388,606.00
4.4.1.2 General works and site tests LS 1.00 777,212.00 777,212.00
4.4.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.4.2.1 LS 1.00 777,212.00 777,212.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.4.2.2 LS 1.00 291,454.50 291,454.50
completed & acceptance certificate
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.4.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 485,757.50 485,757.50
4.4.2.6 Post Construction modelling LS 1.00 58,290.90 58,290.90

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.3.A.1.1 ø200 mm m 13,901.80 3,596.40 1,581.32 878.18 5,811.99 11,867.89 164,985,018.50


4.4.3.A.1.2 ø250 mm m 68.40 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 905,357.57
4.4.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 34 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -


4.4.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -
4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.4.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.4.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 2,683.20 3,890.84 1,719.29 901.27 5,811.99 12,323.40 33,066,135.10


4.4.3.A.2.2 ø250 mm m 608.30 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 8,331,254.28
4.4.3.A.2.3 ø300 mm m 427.20 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 6,278,710.36
4.4.3.A.2.4 ø350 mm m 274.50 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 4,152,339.24
4.4.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.4.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.4.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.4.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.A.3.1 ø200 mm m 256.50 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 6,803,362.24


4.4.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.4.3.A.3.3 ø300 mm m 169.60 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 4,906,361.09
4.4.3.A.3.4 ø350 mm m 187.30 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 5,496,500.27
4.4.3.A.3.5 ø400 mm m 191.90 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 6,168,987.48
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 351.70 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 12,913,071.62

Dasherkandi Sewerage Project, Cost Estimate for Package 5 35 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.3.8 ø600 mm m 309.90 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 12,605,655.73


4.4.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.4.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.4.3.A.3.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.4.3.A.3.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 36 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 37 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.4.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 565.00 108,465.00 17,845.00 10,137.00 136,447.00 77,092,555.00


4.4.4.A.1.2 ø250 mm nos. 4.00 109,101.00 17,858.00 10,150.00 137,109.00 548,436.00
4.4.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.4.A.1.8 ø600 mm nos. 2.00 113,437.00 17,929.00 10,242.00 141,608.00 283,216.00
4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.4.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.4.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 63 133,076.00 22,507.00 12,324.00 167,907.00 10,578,141.00


4.4.4.A.2.2 ø250 mm nos. 21 133,713.00 22,520.00 12,338.00 168,571.00 3,539,991.00
4.4.4.A.2.3 ø300 mm nos. 8 134,286.00 22,521.00 12,350.00 169,157.00 1,353,256.00
4.4.4.A.2.4 ø350 mm nos. 9 134,923.00 22,534.00 12,363.00 169,820.00 1,528,380.00
4.4.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 38 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -


4.4.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.4.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.4.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 6 182,295 31,825 16,700 230,820.00 1,384,920.00


4.4.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.4.4.A.3.3 ø300 mm nos. 3 183,505 31,840 16,725 232,070.00 696,210.00
4.4.4.A.3.4 ø350 mm nos. 4 184,142 31,853 16,738 232,733.00 930,932.00
4.4.4.A.3.5 ø400 mm nos. 6 184,778 31,866 16,752 233,396.00 1,400,376.00
4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 10 185,988 31,881 16,777 234,646.00 2,346,460.00
4.4.4.A.3.8 ø600 mm nos. 9 187,267 31,910 16,805 235,982.00 2,123,838.00
4.4.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.4.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.4.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.4.4.B Drop Manhole Rectangular or circular

4.4.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. 46.00 177,870.00 34,380.00 19,812.00 232,062.00 10,674,852.00


4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 39 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -


4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.4.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.4.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.B.2.1 ø200 mm nos. 6 216,110.00 42,604.00 23,944.00 282,658.00 1,695,948.00


4.4.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.4.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.4.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.4.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.4.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 1 292,584.00 59,046.00 32,206.00 383,836.00 383,836.00

Dasherkandi Sewerage Project, Cost Estimate for Package 5 40 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -


4.4.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.4.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.4.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

4.4.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.4.C.1.1 ø200 mm nos. 773.00 108,465.00 17,845.00 10,137.00 136,447.00 105,473,531.00


4.4.C.1.2 ø250 mm nos. 4.00 109,101.00 17,858.00 10,150.00 137,109.00 548,436.00
4.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 41 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 150 133,076.00 22,507.00 12,324.00 167,907.00 25,186,050.00


4.4.4.C.2.2 ø250 mm nos. 34 133,713.00 22,520.00 12,338.00 168,571.00 5,731,414.00
4.4.4.C.2.3 ø300 mm nos. 24 134,286.00 22,521.00 12,350.00 169,157.00 4,059,768.00
4.4.4.C.2.4 ø350 mm nos. 16 134,923.00 22,534.00 12,363.00 169,820.00 2,717,120.00
4.4.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.4.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.4.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 15 182,295.00 31,825.00 16,700.00 230,820.00 3,462,300.00


4.4.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.4.4.C.3.3 ø300 mm nos. 10 183,505.00 31,840.00 16,725.00 232,070.00 2,320,700.00
4.4.4.C.3.4 ø350 mm nos. 11 184,142.00 31,853.00 16,738.00 232,733.00 2,560,063.00
4.4.4.C.3.5 ø400 mm nos. 11 184,778.00 31,866.00 16,752.00 233,396.00 2,567,356.00
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 20 185,988.00 31,881.00 16,777.00 234,646.00 4,692,920.00
4.4.4.C.3.8 ø600 mm nos. 18 187,267.00 31,910.00 16,805.00 235,982.00 4,247,676.00
4.4.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 42 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.4.4.C.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.4.4.C.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 1,620.00 40,766.88 13,972.83 8,265.14 63,004.85 102,067,857.00

4.2.5.2 ø200 mm nos. 648.00 44,627.58 15,581.46 9,230.31 69,439.35 44,996,698.80


4.2.5.3 ø250 mm nos. 648.00 51,128.58 18,290.21 10,855.56 80,274.35 52,017,778.80
4.2.5.4 ø300 mm nos. 324.00 55,471.38 20,099.71 11,941.26 87,512.35 28,354,001.40

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.4.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 258.00 11,079.12 3,235.25 433.10 14,747.46 3,804,844.68


4.4.6.A.1.2 ø250 mm nos. 1.00 11,597.22 3,408.39 453.76 15,459.37 15,459.37
4.4.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 43 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -


4.4.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 50.00 11,079.12 3,614.08 439.51 15,132.71 756,635.50


4.4.6.A.2.2 ø250 mm nos. 11.00 11,597.22 3,810.28 460.57 15,868.07 174,548.77
4.4.6.A.2.3 ø300 mm nos. 8.00 12,111.88 4,007.30 481.54 16,600.72 132,805.76
4.4.6.A.2.4 ø350 mm nos. 5.00 12,575.47 4,195.03 500.60 17,271.10 86,355.50
4.4.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.4.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.4.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.4.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. 5.00 11,079.12 4,371.74 452.35 15,903.21 79,516.05


4.4.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.4.6.A.3.3 ø300 mm nos. 3.00 12,111.88 4,863.80 496.05 17,471.72 52,415.16
4.4.6.A.3.4 ø350 mm nos. 4.00 12,575.47 5,100.93 515.95 18,192.35 72,769.40
4.4.6.A.3.5 ø400 mm nos. 4.00 13,090.13 5,350.74 538.14 18,979.00 75,916.00
4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.4.6.A.3.7 ø500 mm nos. 7.00 14,177.39 5,852.76 583.83 20,613.98 144,297.86
4.4.6.A.3.8 ø600 mm nos. 6.00 15,264.65 6,359.64 629.91 22,254.20 133,525.20
4.4.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 44 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.4.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.4.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.4: Column 'j' to be carried forward to Schedule No. 5


. 782,507,892.64
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 5 45 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 504
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 148,538.00 148,538.00
4.4.1.2 General works and site tests LS 1.00 297,076.00 297,076.00
4.4.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.4.2.1 LS 1.00 297,076.00 297,076.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.4.2.2 LS 1.00 111,403.50 111,403.50
completed & acceptance certificate
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.4.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 185,672.50 185,672.50
4.4.2.6 Post Construction modelling LS 1.00 22,280.70 22,280.70

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.4.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.4.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.3.A.1.1 ø200 mm m 5,391.80 3,596.40 1,581.32 878.18 5,811.99 11,867.89 63,989,283.60


4.4.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.4.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.4.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.4.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.4.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.4.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.4.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.4.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 46 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -


4.4.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -
4.4.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.4.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.4.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.4.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.A.2.1 ø200 mm m 1,477.60 3,890.84 1,719.29 901.27 5,811.99 12,323.40 18,209,049.35


4.4.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.4.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.4.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.4.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.4.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.4.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.4.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.4.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.4.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.4.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.4.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.4.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.4.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.42.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.A.3.1 ø200 mm m 435.50 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 11,551,127.71


4.4.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.4.3.A.3.3 ø300 mm m 10.00 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 289,290.16
4.4.3.A.3.4 ø350 mm m 112.00 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 3,286,748.69
4.4.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.4.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.4.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 47 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -


4.4.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.4.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.4.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.4.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.4.3.A.3.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.4.3.A.3.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.4.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.4.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -

4.4.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 48 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -

4.4.3.B.2.11 ø900 mm m -

4.4.3.B.2.12 ø1000 mm m -

4.4.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -

4.4.3.B.3.11 ø900 mm m -

4.4.3.B.3.12 ø1000 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 49 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.4.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.4.4.A Normal Manhole Rectangular or circular

4.4.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.A.1.1 ø200 mm nos. 236.00 108,465.00 17,845.00 10,137.00 136,447.00 32,201,492.00


4.4.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.4.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.4.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.4.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.A.2.1 ø200 mm nos. 33 133,076.00 22,507.00 12,324.00 167,907.00 5,540,931.00


4.4.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.4.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.4.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.4.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 50 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -


4.4.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.4.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.4.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.4.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.A.3.1 ø200 mm nos. 7 182,295 31,825 16,700 230,820.00 1,615,740.00


4.4.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.4.4.A.3.3 ø300 mm nos. 1 183,505 31,840 16,725 232,070.00 232,070.00
4.4.4.A.3.4 ø350 mm nos. 5 184,142 31,853 16,738 232,733.00 1,163,665.00
4.4.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.4.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.4.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.4.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.4.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.4.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.4.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.4.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.4.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.4.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.4.4.B Drop Manhole Rectangular or circular

4.4.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.4.4.B.1.1 ø200 mm nos. 15.00 177,870.00 34,380.00 19,812.00 232,062.00 3,480,930.00


4.4.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.4.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 51 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -


4.4.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.4.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.4.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.4.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.4.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.4.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.4.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.4.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.4.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.4.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.4.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.B.2.1 ø200 mm nos. 1 216,110.00 42,604.00 23,944.00 282,658.00 282,658.00


4.4.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.4.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.4.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.4.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.4.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.4.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.4.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.4.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.4.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.4.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.4.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.4.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.4.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.4.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.4.4.B.3.1 ø200 mm nos. 1 292,584.00 59,046.00 32,206.00 383,836.00 383,836.00

Dasherkandi Sewerage Project, Cost Estimate for Package 5 52 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -


4.4.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.4.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.4.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.4.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.4.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.4.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.4.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.4.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.4.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.4.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.4.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.4.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.4.4.C Service connections Manhole Rectangular or circular -

4.4.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.4.C.1.1 ø200 mm nos. 300.00 108,465.00 17,845.00 10,137.00 136,447.00 40,934,100.00


4.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 53 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.4.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.4.4.C.2.1 ø200 mm nos. 83 133,076.00 22,507.00 12,324.00 167,907.00 13,936,281.00


4.4.4.C.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.4.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.4.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.4.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.4.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.4.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.4.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.4.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.4.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.4.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.4.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.4.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.4.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.4.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.4.4.C.3.1 ø200 mm nos. 25 182,295.00 31,825.00 16,700.00 230,820.00 5,770,500.00


4.4.4.C.3.2 ø250 mm nos. 182,932.00 31,838.00 16,713.00 231,483.00 -
4.4.4.C.3.3 ø300 mm nos. 1 183,505.00 31,840.00 16,725.00 232,070.00 232,070.00
4.4.4.C.3.4 ø350 mm nos. 7 184,142.00 31,853.00 16,738.00 232,733.00 1,629,131.00
4.4.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.4.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.4.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.4.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.4.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.4.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.4.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 54 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.4.4.C.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.4.4.C.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 620.00 40,766.88 13,972.83 8,265.14 63,004.85 39,063,007.00

4.2.5.2 ø200 mm nos. 248.00 44,627.58 15,581.46 9,230.31 69,439.35 17,220,958.80


4.2.5.3 ø250 mm nos. 248.00 51,128.58 18,290.21 10,855.56 80,274.35 19,908,038.80
4.2.5.4 ø300 mm nos. 124.00 55,471.38 20,099.71 11,941.26 87,512.35 10,851,531.40

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.4.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.4.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.4.6.A.1.1 ø200 mm nos. 100.00 11,079.12 3,235.25 433.10 14,747.46 1,474,746.00


4.4.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.4.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.4.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.4.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.4.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.4.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.4.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.4.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.4.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.4.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.4.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 55 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -


4.4.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.4.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.4.6.A.2.1 ø200 mm nos. 28.00 11,079.12 3,614.08 439.51 15,132.71 423,715.88


4.4.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.4.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.4.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.4.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.4.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.4.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.4.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.4.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.4.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.4.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.4.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.4.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.4.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.4.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.4.6.A.3.1 ø200 mm nos. 8.00 11,079.12 4,371.74 452.35 15,903.21 127,225.68


4.4.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.4.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.4.6.A.3.4 ø350 mm nos. 2.00 12,575.47 5,100.93 515.95 18,192.35 36,384.70
4.4.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.4.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.4.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.4.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.4.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.4.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 56 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.4.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.4.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.4.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.4.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.4: Column 'j' to be carried forward to Schedule No. 5


. 294,919,058.47
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 5 57 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.5 INSTALLATION of LOOP 505
4.5.1 Miscellaneous works during implementation
4.5.1.1 Setting-out LS 1.00 599,466.00 599,466.00
4.5.1.2 General works and site tests LS 1.00 1,198,932.00 1,198,932.00
4.5.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.5.2.1 LS 1.00 1,198,932.00 1,198,932.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.5.2.2 LS 1.00 449,599.50 449,599.50
completed & acceptance certificate
4.5.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.5.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.5.2.5 Development and submission of GIS based As-built drawings LS 1.00 749,332.50 749,332.50
4.5.2.6 Post Construction modelling LS 1.00 89,919.90 89,919.90

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.5.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.5.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.3.A.1.1 ø200 mm m 18,988.50 3,596.40 1,581.32 878.18 5,811.99 11,867.89 225,353,409.18


4.5.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.5.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.5.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.5.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.5.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.5.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.5.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.5.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 58 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -


4.5.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -
4.5.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.5.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.5.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.5.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.A.2.1 ø200 mm m 6,749.10 3,890.84 1,719.29 901.27 5,811.99 12,323.40 83,171,829.31


4.5.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.5.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.5.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.5.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.5.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.5.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.5.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.5.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.5.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.5.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.5.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.5.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.5.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.5.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.A.3.1 ø200 mm m 1,427.60 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 37,865,418.86


4.5.3.A.3.2 ø250 mm m 274.00 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 7,644,013.61
4.5.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.5.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.5.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.5.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.5.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 59 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -


4.5.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.5.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.5.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.5.3.A.3.12 ø1000 mm m 554.30 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 31,383,992.41


4.5.3.A.3.13 ø1100 mm m 1,823.80 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 108,164,338.61
4.5.3.A.3.14 ø1300 mm m 156.00 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 9,841,462.92

4.5.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.5.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -

4.5.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 60 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -

4.5.3.B.2.11 ø900 mm m -

4.5.3.B.2.12 ø1000 mm m -

4.5.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -

4.5.3.B.3.11 ø900 mm m -

4.5.3.B.3.12 ø1000 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 61 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.5.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.5.4.A Normal Manhole Rectangular or circular

4.5.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.A.1.1 ø200 mm nos. 604.00 108,465.00 17,845.00 10,137.00 136,447.00 82,413,988.00


4.5.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.5.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.5.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.5.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.5.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.A.2.1 ø200 mm nos. 150 133,076.00 22,507.00 12,324.00 167,907.00 25,186,050.00


4.5.4.A.2.2 ø250 mm nos. 1 133,713.00 22,520.00 12,338.00 168,571.00 168,571.00
4.5.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.5.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.5.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.5.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 62 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -


4.5.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.5.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.5.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.5.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.A.3.1 ø200 mm nos. 31 182,295 31,825 16,700 230,820.00 7,155,420.00


4.5.4.A.3.2 ø250 mm nos. 4 182,932 31,838 16,713 231,483.00 925,932.00
4.5.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.5.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.5.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.5.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.5.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.5.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.5.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.5.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.5.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.5.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.5.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.5.4.A.3.14 ø1300 mm nos. 5 196,001 32,064 16,991 245,056.00 1,225,280.00

4.5.4.B Drop Manhole Rectangular or circular

4.5.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.B.1.1 ø200 mm nos. 64.00 177,870.00 34,380.00 19,812.00 232,062.00 14,851,968.00


4.5.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.5.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 63 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -


4.5.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.5.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.5.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.5.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.5.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.5.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.5.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.5.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.5.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.5.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.5.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.B.2.1 ø200 mm nos. 16 216,110.00 42,604.00 23,944.00 282,658.00 4,522,528.00


4.5.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.5.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.5.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.5.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.5.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.5.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.5.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.5.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.5.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.5.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.5.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.5.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.5.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.5.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.B.3.1 ø200 mm nos. 3 292,584.00 59,046.00 32,206.00 383,836.00 1,151,508.00

Dasherkandi Sewerage Project, Cost Estimate for Package 5 64 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.3.2 ø250 mm nos. 2 293,074.00 59,072.00 32,234.00 384,380.00 768,760.00


4.5.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.5.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.5.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.5.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.5.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.5.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.5.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.5.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.5.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.5.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.5.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.5.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.5.4.C Service connections Manhole Rectangular or circular -

4.5.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.5.4.C.1.1 ø200 mm nos. 1,055.00 108,465.00 17,845.00 10,137.00 136,447.00 143,951,585.00


4.5.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.5.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.5.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 65 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.5.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.C.2.1 ø200 mm nos. 375 133,076.00 22,507.00 12,324.00 167,907.00 62,965,125.00


4.5.4.C.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.5.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.5.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.5.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.5.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.5.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.5.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.5.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.5.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.5.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.5.4.C.3.1 ø200 mm nos. 80 182,295.00 31,825.00 16,700.00 230,820.00 18,465,600.00


4.5.4.C.3.2 ø250 mm nos. 16 182,932.00 31,838.00 16,713.00 231,483.00 3,703,728.00
4.5.4.C.3.3 ø300 mm nos. 183,505.00 31,840.00 16,725.00 232,070.00 -
4.5.4.C.3.4 ø350 mm nos. 184,142.00 31,853.00 16,738.00 232,733.00 -
4.5.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.5.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.5.4.C.3.7 ø500 mm nos. 185,988.00 31,881.00 16,777.00 234,646.00 -
4.5.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.5.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.5.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.5.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 66 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.3.12 ø1000 mm nos. 31 192,239.00 31,994.00 16,910.00 241,143.00 7,475,433.00


4.5.4.C.3.13 ø1100 mm nos. 102 193,512.00 32,020.00 16,938.00 242,470.00 24,731,940.00
4.5.4.C.3.14 ø1300 mm nos. 9 196,001.00 32,064.00 16,991.00 245,056.00 2,205,504.00

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.5.5.1 ø150 mm nos. 2,498.00 40,766.88 13,972.83 8,265.14 63,004.85 157,386,115.30

4.5.5.2 ø200 mm nos. 999.00 44,627.58 15,581.46 9,230.31 69,439.35 69,369,910.65


4.5.5.3 ø250 mm nos. 999.00 51,128.58 18,290.21 10,855.56 80,274.35 80,194,075.65
4.5.5.4 ø300 mm nos. 500.00 55,471.38 20,099.71 11,941.26 87,512.35 43,756,175.00

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.5.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.5.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.6.A.1.1 ø200 mm nos. 352.00 11,079.12 3,235.25 433.10 14,747.46 5,191,105.92


4.5.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.5.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.5.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.5.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.5.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.5.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.5.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.5.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.5.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.5.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.5.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 67 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -


4.5.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.5.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.6.A.2.1 ø200 mm nos. 125.00 11,079.12 3,614.08 439.51 15,132.71 1,891,588.75


4.5.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.5.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.5.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.5.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.5.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.5.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.5.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.5.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.5.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.5.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.5.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.5.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.5.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.5.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.6.A.3.1 ø200 mm nos. 27.00 11,079.12 4,371.74 452.35 15,903.21 429,386.67


4.5.6.A.3.2 ø250 mm nos. 5.00 11,597.22 4,617.36 474.24 16,688.82 83,444.10
4.5.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.5.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.5.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.5.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.5.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.5.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.5.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.5.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 68 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.5.6.A.3.12 ø1000 mm nos. 10.00 20,104.25 8,467.18 831.39 29,402.83 294,028.30


4.5.6.A.3.13 ø1100 mm nos. 34.00 21,464.04 9,019.06 887.06 31,370.16 1,066,585.44
4.5.6.A.3.14 ø1300 mm nos. 3.00 24,183.62 10,127.67 998.77 35,310.06 105,930.18

Sub-total 4.5: Column 'j' to be carried forward to Schedule No. 5


. 1,269,370,412.76
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 5 69 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.5 INSTALLATION of LOOP 506
4.5.1 Miscellaneous works during implementation
4.5.1.1 Setting-out LS 1.00 371,056.00 371,056.00
4.5.1.2 General works and site tests LS 1.00 742,112.00 742,112.00
4.5.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.5.2.1 LS 1.00 742,112.00 742,112.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.5.2.2 LS 1.00 278,292.00 278,292.00
completed & acceptance certificate
4.5.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.5.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.5.2.5 Development and submission of GIS based As-built drawings LS 1.00 463,820.00 463,820.00
4.5.2.6 Post Construction modelling LS 1.00 55,658.40 55,658.40

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.5.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.5.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.3.A.1.1 ø200 mm m 12,399.60 3,596.40 1,581.32 878.18 5,811.99 11,867.89 147,157,075.73


4.5.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.5.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.5.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.5.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.5.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.5.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.5.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.5.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 70 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -


4.5.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -
4.5.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.5.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.5.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.5.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.A.2.1 ø200 mm m 4,568.30 3,890.84 1,719.29 901.27 5,811.99 12,323.40 56,296,968.16


4.5.3.A.2.2 ø250 mm m 12.30 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 168,460.34
4.5.3.A.2.3 ø300 mm m 271.90 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 3,996,211.02
4.5.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.5.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.5.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.5.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.5.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.5.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.5.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.5.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.5.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.5.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.5.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.5.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.A.3.1 ø200 mm m 503.80 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 13,362,705.26


4.5.3.A.3.2 ø250 mm m 110.00 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 3,068,764.59
4.5.3.A.3.3 ø300 mm m 236.10 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 6,830,140.65
4.5.3.A.3.4 ø350 mm m 350.90 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 10,297,501.04
4.5.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.5.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.5.3.A.3.7 ø500 mm m 99.90 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 3,667,943.86

Dasherkandi Sewerage Project, Cost Estimate for Package 5 71 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -


4.5.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.5.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.5.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.5.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.5.3.A.3.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.5.3.A.3.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.5.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.5.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -

4.5.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 72 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -

4.5.3.B.2.11 ø900 mm m -

4.5.3.B.2.12 ø1000 mm m -

4.5.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -

4.5.3.B.3.11 ø900 mm m -

4.5.3.B.3.12 ø1000 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 73 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.5.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.5.4.A Normal Manhole Rectangular or circular

4.5.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.A.1.1 ø200 mm nos. 486.00 108,465.00 17,845.00 10,137.00 136,447.00 66,313,242.00


4.5.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.5.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.5.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.5.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.5.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.A.2.1 ø200 mm nos. 132 133,076.00 22,507.00 12,324.00 167,907.00 22,163,724.00


4.5.4.A.2.2 ø250 mm nos. 4 133,713.00 22,520.00 12,338.00 168,571.00 674,284.00
4.5.4.A.2.3 ø300 mm nos. 16 134,286.00 22,521.00 12,350.00 169,157.00 2,706,512.00
4.5.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.5.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.5.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 74 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -


4.5.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.5.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.5.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.5.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.A.3.1 ø200 mm nos. 3 182,295 31,825 16,700 230,820.00 692,460.00


4.5.4.A.3.2 ø250 mm nos. 1 182,932 31,838 16,713 231,483.00 231,483.00
4.5.4.A.3.3 ø300 mm nos. 5 183,505 31,840 16,725 232,070.00 1,160,350.00
4.5.4.A.3.4 ø350 mm nos. 18 184,142 31,853 16,738 232,733.00 4,189,194.00
4.5.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.5.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.5.4.A.3.7 ø500 mm nos. 6 185,988 31,881 16,777 234,646.00 1,407,876.00
4.5.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.5.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.5.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.5.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.5.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.5.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.5.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.5.4.B Drop Manhole Rectangular or circular

4.5.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.B.1.1 ø200 mm nos. 58.00 177,870.00 34,380.00 19,812.00 232,062.00 13,459,596.00


4.5.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.5.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 75 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -


4.5.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.5.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.5.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.5.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.5.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.5.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.5.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.5.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.5.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.5.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.5.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.B.2.1 ø200 mm nos. 8 216,110.00 42,604.00 23,944.00 282,658.00 2,261,264.00


4.5.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.5.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.5.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.5.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.5.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.5.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.5.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.5.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.5.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.5.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.5.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.5.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.5.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.5.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.B.3.1 ø200 mm nos. 4 292,584.00 59,046.00 32,206.00 383,836.00 1,535,344.00

Dasherkandi Sewerage Project, Cost Estimate for Package 5 76 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -


4.5.4.B.3.3 ø300 mm nos. 1 293,442.00 59,074.00 32,256.00 384,772.00 384,772.00
4.5.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.5.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.5.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.5.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.5.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.5.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.5.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.5.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.5.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.5.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.5.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.5.4.C Service connections Manhole Rectangular or circular -

4.5.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.5.4.C.1.1 ø200 mm nos. 689.00 108,465.00 17,845.00 10,137.00 136,447.00 94,011,983.00


4.5.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.5.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.5.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 77 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.5.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.C.2.1 ø200 mm nos. 254 133,076.00 22,507.00 12,324.00 167,907.00 42,648,378.00


4.5.4.C.2.2 ø250 mm nos. 1 133,713.00 22,520.00 12,338.00 168,571.00 168,571.00
4.5.4.C.2.3 ø300 mm nos. 16 134,286.00 22,521.00 12,350.00 169,157.00 2,706,512.00
4.5.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.5.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.5.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.5.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.5.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.5.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.5.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.5.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.5.4.C.3.1 ø200 mm nos. 28 182,295.00 31,825.00 16,700.00 230,820.00 6,462,960.00


4.5.4.C.3.2 ø250 mm nos. 7 182,932.00 31,838.00 16,713.00 231,483.00 1,620,381.00
4.5.4.C.3.3 ø300 mm nos. 14 183,505.00 31,840.00 16,725.00 232,070.00 3,248,980.00
4.5.4.C.3.4 ø350 mm nos. 20 184,142.00 31,853.00 16,738.00 232,733.00 4,654,660.00
4.5.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.5.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.5.4.C.3.7 ø500 mm nos. 6 185,988.00 31,881.00 16,777.00 234,646.00 1,407,876.00
4.5.4.C.3.8 ø600 mm nos. 187,267.00 31,910.00 16,805.00 235,982.00 -
4.5.4.C.3.9 ø700 mm nos. 188,477.00 31,924.00 16,830.00 237,231.00 -
4.5.4.C.3.10 ø800 mm nos. 189,750.00 31,950.00 16,858.00 238,558.00 -

4.5.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 78 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.5.4.C.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.5.4.C.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.5.5.1 ø150 mm nos. 1,547.00 40,766.88 13,972.83 8,265.14 63,004.85 97,468,502.95

4.5.5.2 ø200 mm nos. 619.00 44,627.58 15,581.46 9,230.31 69,439.35 42,982,957.65


4.5.5.3 ø250 mm nos. 619.00 51,128.58 18,290.21 10,855.56 80,274.35 49,689,822.65
4.5.5.4 ø300 mm nos. 309.00 55,471.38 20,099.71 11,941.26 87,512.35 27,041,316.15

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.5.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.5.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.6.A.1.1 ø200 mm nos. 230.00 11,079.12 3,235.25 433.10 14,747.46 3,391,915.80


4.5.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.5.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.5.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.5.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.5.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.5.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.5.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.5.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.5.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.5.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.5.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 79 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -


4.5.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.5.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.6.A.2.1 ø200 mm nos. 85.00 11,079.12 3,614.08 439.51 15,132.71 1,286,280.35


4.5.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.5.6.A.2.3 ø300 mm nos. 5.00 12,111.88 4,007.30 481.54 16,600.72 83,003.60
4.5.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.5.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.5.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.5.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.5.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.5.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.5.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.5.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.5.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.5.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.5.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.5.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.6.A.3.1 ø200 mm nos. 9.00 11,079.12 4,371.74 452.35 15,903.21 143,128.89


4.5.6.A.3.2 ø250 mm nos. 2.00 11,597.22 4,617.36 474.24 16,688.82 33,377.64
4.5.6.A.3.3 ø300 mm nos. 5.00 12,111.88 4,863.80 496.05 17,471.72 87,358.60
4.5.6.A.3.4 ø350 mm nos. 7.00 12,575.47 5,100.93 515.95 18,192.35 127,346.45
4.5.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.5.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.5.6.A.3.7 ø500 mm nos. 2.00 14,177.39 5,852.76 583.83 20,613.98 41,227.96
4.5.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.5.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.5.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 80 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.5.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.5.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.5.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.5: Column 'j' to be carried forward to Schedule No. 5


. 744,007,961.74
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 5 81 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.5 INSTALLATION of LOOP 507
4.5.1 Miscellaneous works during implementation
4.5.1.1 Setting-out LS 1.00 555,770.00 555,770.00
4.5.1.2 General works and site tests LS 1.00 1,111,540.00 1,111,540.00
4.5.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.5.2.1 LS 1.00 1,111,540.00 1,111,540.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.5.2.2 LS 1.00 416,827.50 416,827.50
completed & acceptance certificate
4.5.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.5.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.5.2.5 Development and submission of GIS based As-built drawings LS 1.00 694,712.50 694,712.50
4.5.2.6 Post Construction modelling LS 1.00 83,365.50 83,365.50

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.5.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.5.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.3.A.1.1 ø200 mm m 15,430.80 3,596.40 1,581.32 878.18 5,811.99 11,867.89 183,131,020.69


4.5.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.5.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.5.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.5.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.5.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.5.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.5.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.5.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 82 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -


4.5.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -
4.5.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.5.3.A.1.13 ø1100 mm m - 22,621.75 2,922.16 6,288.05 12,269.76 44,101.71 -
4.5.3.A.1.14 ø1300 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -

4.5.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.A.2.1 ø200 mm m 8,685.70 3,890.84 1,719.29 901.27 5,811.99 12,323.40 107,037,317.24


4.5.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.5.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.5.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.5.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.5.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.5.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.5.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.5.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.5.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.5.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.5.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.5.3.A.2.13 ø1100 mm m 22,975.39 3,334.53 6,319.05 12,269.76 44,898.73 -
4.5.3.A.2.14 ø1300 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -

4.5.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.A.3.1 ø200 mm m 967.00 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 25,648,543.04


4.5.3.A.3.2 ø250 mm m 146.20 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 4,078,667.11
4.5.3.A.3.3 ø300 mm m 145.80 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 4,217,850.51
4.5.3.A.3.4 ø350 mm m 440.40 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 12,923,965.40
4.5.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.5.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.5.3.A.3.7 ø500 mm m 375.10 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 13,772,229.65

Dasherkandi Sewerage Project, Cost Estimate for Package 5 83 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.A.3.8 ø600 mm m 1,083.00 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 44,052,678.79


4.5.3.A.3.9 ø700 mm m 434.70 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 21,076,092.51
4.5.3.A.3.10 ø800 mm m 79.80 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 4,339,087.52

4.5.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.5.3.A.3.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.5.3.A.3.13 ø1100 mm m 34,907.71 4,788.45 7,341.21 12,269.76 59,307.13 -
4.5.3.A.3.14 ø1300 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -

4.5.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.5.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -

4.5.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 84 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -

4.5.3.B.2.11 ø900 mm m -

4.5.3.B.2.12 ø1000 mm m -

4.5.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -

4.5.3.B.3.11 ø900 mm m -

4.5.3.B.3.12 ø1000 mm m -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 85 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.5.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.5.4.A Normal Manhole Rectangular or circular

4.5.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.A.1.1 ø200 mm nos. 553.00 108,465.00 17,845.00 10,137.00 136,447.00 75,455,191.00


4.5.4.A.1.2 ø250 mm nos. 1.00 109,101.00 17,858.00 10,150.00 137,109.00 137,109.00
4.5.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.A.1.4 ø350 mm nos. 1.00 110,311.00 17,873.00 10,176.00 138,360.00 138,360.00
4.5.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.A.1.7 ø500 mm nos. 8.00 112,164.00 17,903.00 10,215.00 140,282.00 1,122,256.00
4.5.4.A.1.8 ø600 mm nos. 27.00 113,437.00 17,929.00 10,242.00 141,608.00 3,823,416.00
4.5.4.A.1.9 ø700 mm nos. 10.00 114,647.00 17,944.00 10,267.00 142,858.00 1,428,580.00
4.5.4.A.1.10 ø800 mm nos. 1.00 115,920.00 17,970.00 10,295.00 144,185.00 144,185.00
4.5.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.5.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.5.4.A.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.5.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.A.2.1 ø200 mm nos. 181 133,076.00 22,507.00 12,324.00 167,907.00 30,391,167.00


4.5.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.5.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.5.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.5.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.5.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 86 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.A.2.7 ø500 mm nos. 3 136,776.00 22,565.00 12,402.00 171,743.00 515,229.00


4.5.4.A.2.8 ø600 mm nos. 8 138,048.00 22,591.00 12,430.00 173,069.00 1,384,552.00
4.5.4.A.2.9 ø700 mm nos. 1 139,258.00 22,605.00 12,455.00 174,318.00 174,318.00
4.5.4.A.2.10 ø800 mm nos. 1 140,531.00 22,632.00 12,483.00 175,646.00 175,646.00

4.5.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.5.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.5.4.A.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.5.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.A.3.1 ø200 mm nos. 83 182,295 31,825 16,700 230,820.00 19,158,060.00


4.5.4.A.3.2 ø250 mm nos. 2 182,932 31,838 16,713 231,483.00 462,966.00
4.5.4.A.3.3 ø300 mm nos. 4 183,505 31,840 16,725 232,070.00 928,280.00
4.5.4.A.3.4 ø350 mm nos. 10 184,142 31,853 16,738 232,733.00 2,327,330.00
4.5.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.5.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.5.4.A.3.7 ø500 mm nos. 7 185,988 31,881 16,777 234,646.00 1,642,522.00
4.5.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.5.4.A.3.9 ø700 mm nos. 2 188,477 31,924 16,830 237,231.00 474,462.00
4.5.4.A.3.10 ø800 mm nos. 1 189,750 31,950 16,858 238,558.00 238,558.00

4.5.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.5.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.5.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.5.4.A.3.14 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -

4.5.4.B Drop Manhole Rectangular or circular

4.5.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.5.4.B.1.1 ø200 mm nos. 50.00 177,870.00 34,380.00 19,812.00 232,062.00 11,603,100.00


4.5.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.5.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 87 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -


4.5.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.5.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.5.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.5.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.5.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.5.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.5.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.5.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.5.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.5.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.5.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.B.2.1 ø200 mm nos. 20 216,110.00 42,604.00 23,944.00 282,658.00 5,653,160.00


4.5.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.5.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.5.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.5.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.5.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.5.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.5.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.5.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.5.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.5.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.5.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.5.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.5.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.5.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.5.4.B.3.1 ø200 mm nos. 1 292,584.00 59,046.00 32,206.00 383,836.00 383,836.00

Dasherkandi Sewerage Project, Cost Estimate for Package 5 88 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -


4.5.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.5.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.5.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.5.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.5.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.5.4.B.3.8 ø600 mm nos. 1 296,282.00 59,214.00 32,416.00 387,912.00 387,912.00
4.5.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.5.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.5.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.5.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.5.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.5.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.5.4.C Service connections Manhole Rectangular or circular -

4.5.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.5.4.C.1.1 ø200 mm nos. 858.00 108,465.00 17,845.00 10,137.00 136,447.00 117,071,526.00


4.5.4.C.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.5.4.C.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.5.4.C.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.5.4.C.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.5.4.C.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.5.4.C.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.5.4.C.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.5.4.C.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.5.4.C.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.5.4.C.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.5.4.C.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.5.4.C.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 89 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.1.14 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -

4.5.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.5.4.C.2.1 ø200 mm nos. 483 133,076.00 22,507.00 12,324.00 167,907.00 81,099,081.00


4.5.4.C.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.5.4.C.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.5.4.C.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.5.4.C.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.5.4.C.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.5.4.C.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.5.4.C.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.5.4.C.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.5.4.C.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.5.4.C.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.5.4.C.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.5.4.C.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.5.4.C.2.14 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -

4.5.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.5.4.C.3.1 ø200 mm nos. 54 182,295.00 31,825.00 16,700.00 230,820.00 12,464,280.00


4.5.4.C.3.2 ø250 mm nos. 9 182,932.00 31,838.00 16,713.00 231,483.00 2,083,347.00
4.5.4.C.3.3 ø300 mm nos. 9 183,505.00 31,840.00 16,725.00 232,070.00 2,088,630.00
4.5.4.C.3.4 ø350 mm nos. 25 184,142.00 31,853.00 16,738.00 232,733.00 5,818,325.00
4.5.4.C.3.5 ø400 mm nos. 184,778.00 31,866.00 16,752.00 233,396.00 -
4.5.4.C.3.6 ø450 mm nos. 185,414.00 31,879.00 16,766.00 234,059.00 -
4.5.4.C.3.7 ø500 mm nos. 21 185,988.00 31,881.00 16,777.00 234,646.00 4,927,566.00
4.5.4.C.3.8 ø600 mm nos. 61 187,267.00 31,910.00 16,805.00 235,982.00 14,394,902.00
4.5.4.C.3.9 ø700 mm nos. 25 188,477.00 31,924.00 16,830.00 237,231.00 5,930,775.00
4.5.4.C.3.10 ø800 mm nos. 5 189,750.00 31,950.00 16,858.00 238,558.00 1,192,790.00

4.5.4.C.3.11 ø900 mm nos. 190,967.00 31,968.00 16,883.00 239,818.00 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 90 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.4.C.3.12 ø1000 mm nos. 192,239.00 31,994.00 16,910.00 241,143.00 -


4.5.4.C.3.13 ø1100 mm nos. 193,512.00 32,020.00 16,938.00 242,470.00 -
4.5.4.C.3.14 ø1300 mm nos. 196,001.00 32,064.00 16,991.00 245,056.00 -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.5.5.1 ø150 mm nos. 2,316.00 40,766.88 13,972.83 8,265.14 63,004.85 145,919,232.60

4.5.5.2 ø200 mm nos. 926.00 44,627.58 15,581.46 9,230.31 69,439.35 64,300,838.10


4.5.5.3 ø250 mm nos. 926.00 51,128.58 18,290.21 10,855.56 80,274.35 74,334,048.10
4.5.5.4 ø300 mm nos. 463.00 55,471.38 20,099.71 11,941.26 87,512.35 40,518,218.05

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.5.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.5.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.5.6.A.1.1 ø200 mm nos. 286.00 11,079.12 3,235.25 433.10 14,747.46 4,217,773.56


4.5.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.5.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.5.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.5.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.5.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.5.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.5.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.5.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.5.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.5.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.5.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -

Dasherkandi Sewerage Project, Cost Estimate for Package 5 91 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -


4.5.6.A.1.14 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -

4.5.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.5.6.A.2.1 ø200 mm nos. 161.00 11,079.12 3,614.08 439.51 15,132.71 2,436,366.31


4.5.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.5.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.5.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.5.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.5.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.5.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.5.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.5.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.5.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.5.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.5.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.5.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.5.6.A.2.14 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -

4.5.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.5.6.A.3.1 ø200 mm nos. 18.00 11,079.12 4,371.74 452.35 15,903.21 286,257.78


4.5.6.A.3.2 ø250 mm nos. 3.00 11,597.22 4,617.36 474.24 16,688.82 50,066.46
4.5.6.A.3.3 ø300 mm nos. 3.00 12,111.88 4,863.80 496.05 17,471.72 52,415.16
4.5.6.A.3.4 ø350 mm nos. 8.00 12,575.47 5,100.93 515.95 18,192.35 145,538.80
4.5.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.5.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.5.6.A.3.7 ø500 mm nos. 7.00 14,177.39 5,852.76 583.83 20,613.98 144,297.86
4.5.6.A.3.8 ø600 mm nos. 20.00 15,264.65 6,359.64 629.91 22,254.20 445,084.00
4.5.6.A.3.9 ø700 mm nos. 8.00 16,460.93 6,881.60 679.59 24,022.12 192,176.96
4.5.6.A.3.10 ø800 mm nos. 2.00 17,602.69 7,398.46 727.66 25,728.81 51,457.62

Dasherkandi Sewerage Project, Cost Estimate for Package 5 92 of 101


Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.5.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.5.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.5.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.5.6.A.3.14 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -

Sub-total 4.5: Column 'j' to be carried forward to Schedule No. 5


. 1,162,588,896.33
Grand Summary

Dasherkandi Sewerage Project, Cost Estimate for Package 5 93 of 101


Schedule No. 5 - Grand Summary

Schedule No. Title


Total Price (BDT)

1 Schedule No. 1 - Pipe and Fittings Supplied from Abroad


2 Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
3 Schedule No. 3 - Design Services 484538574
4 Schedule No. 4 - Installation / Construction and Other works
4.1 Implementation Provisions and Preliminaries for all Loops 288745436
4.2 Installation/ Construction of all Loops (Schedule 4)
4.2.1 INSTALLATION of LOOP 501 881336671
4.2.2 INSTALLATION of LOOP 502 402852813
4.2.3 INSTALLATION of LOOP 503 782507893
4.2.4 INSTALLATION of LOOP 504 294919058
4.2.5 INSTALLATION of LOOP 505 1269370413
4.2.6 INSTALLATION of LOOP 506 744007962
4.2.7 INSTALLATION of LOOP 507 1162588896
Sub total 4.2: Installation/ Construction of all Loops (Schedule 4) 5537583706
5 Provisional Sum
5.1 Provisional sum for Physical Contingencies 276879185
5.2 Provisional Sum for Price Contingencies 263679724
5.3 Provisional Sum for alleviations program, refer to SCC, Sub-Clause xxxxxx 15821668
Sub-Total 5: Provisional Sum 556380577
6 Recommended spare parts 29719262
7 Day work 9665263
8 O&M - 124826488
. Grand Total (1+3+4.1+4.2+5+6+7+8) to be carried forward to Letter of Bid 7031459306

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 5 94 of 101


Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh

Recommended Spare Parts


6.1 GRP Sewer Pipe (Dia in mm)
6.1.1 160 meter 160.00 1,770.40 1,770.40 283,264.00
6.1.2 200 meter 160.00 2,213.00 2,213.00 354,080.00
6.1.3 250 meter 160.00 2,923.00 2,923.00 467,680.00
6.1.4 300 meter 160.00 3,315.00 3,315.00 530,400.00
6.1.5 350 meter 200.00 4,292.00 4,292.00 858,400.00
6.1.6 400 meter 200.00 5,043.00 5,043.00 1,008,600.00
6.1.7 500 meter 200.00 7,807.00 7,807.00 1,561,400.00
6.1.8 600 meter 140.00 10,104.00 10,104.00 1,414,560.00
6.1.9 700 meter 140.00 15,281.00 15,281.00 2,139,340.00
6.1.10 800 meter 140.00 18,120.00 18,120.00 2,536,800.00
6.1.11 900 meter 140.00 16,711.99 16,711.99 2,339,678.13
6.1.12 1000 meter 140.00 18,462.01 18,462.01 2,584,681.87
6.2 Coupler/Coller
6.2.1 160 Pcs. 40.00 2,655.60 2,655.60 106,224.00
6.2.2 200 Pcs. 40.00 3,319.50 3,319.50 132,780.00
6.2.3 250 Pcs. 40.00 4,384.50 4,384.50 175,380.00
6.2.4 300 Pcs. 40.00 4,972.50 4,972.50 198,900.00
6.2.5 350 Pcs. 40.00 6,438.00 6,438.00 257,520.00
6.2.6 400 Pcs. 40.00 7,564.50 7,564.50 302,580.00
6.2.7 500 Pcs. 40.00 11,710.50 11,710.50 468,420.00
6.2.8 600 Pcs. 40.00 15,156.00 15,156.00 606,240.00
6.2.9 700 Pcs. 40.00 22,921.50 22,921.50 916,860.00
6.2.10 800 Pcs. 40.00 27,180.00 27,180.00 1,087,200.00
6.2.11 900 Pcs. 40.00 25,067.98 25,067.98 1,002,719.20
6.2.12 1000 Pcs. 40.00 27,693.02 27,693.02 1,107,720.80
6.3 Flange Adapter
6.3.1 160 Pcs. 20.00 885.20 885.20 17,704.00
6.3.2 200 Pcs. 20.00 1,106.50 1,106.50 22,130.00
6.3.3 250 Pcs. 20.00 1,461.50 1,461.50 29,230.00
6.3.4 300 Pcs. 20.00 1,657.50 1,657.50 33,150.00
6.3.5 350 Pcs. 20.00 2,146.00 2,146.00 42,920.00
6.3.6 400 Pcs. 20.00 2,521.50 2,521.50 50,430.00

Dasherkandi Sewerage Project, Cost Estimate for Package 5 95 of 101


Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh
6.3.7 500 Pcs. 20.00 3,903.50 3,903.50 78,070.00
6.3.8 600 Pcs. 20.00 5,052.00 5,052.00 101,040.00
6.3.9 700 Pcs. 20.00 7,640.50 7,640.50 152,810.00
6.3.10 800 Pcs. 20.00 9,060.00 9,060.00 181,200.00
6.3.11 900 Pcs. 20.00 8,355.99 8,355.99 167,119.87
6.3.12 1000 Pcs. 20.00 9,231.01 9,231.01 184,620.13
6.4 Tee/Wye
6.4.1 160 Pcs. 20.00 2,655.60 2,655.60 53,112.00
6.4.2 200 Pcs. 20.00 3,319.50 3,319.50 66,390.00
6.4.3 250 Pcs. 20.00 4,384.50 4,384.50 87,690.00
6.4.4 300 Pcs. 20.00 4,972.50 4,972.50 99,450.00
6.4.5 350 Pcs. 20.00 6,438.00 6,438.00 128,760.00
6.4.6 400 Pcs. 20.00 10,086.00 10,086.00 201,720.00
6.4.7 500 Pcs. 20.00 15,614.00 15,614.00 312,280.00
6.4.8 600 Pcs. 20.00 20,208.00 20,208.00 404,160.00
6.4.9 700 Pcs. 20.00 30,562.00 30,562.00 611,240.00
6.4.10 800 Pcs. 20.00 36,240.00 36,240.00 724,800.00
6.4.11 900 Pcs. 20.00 33,423.97 33,423.97 668,479.47
6.4.12 1000 Pcs. 20.00 36,924.03 36,924.03 738,480.53
6.5 Elbow (30/60/90 degrees)
6.5.1 160 Pcs. 20.00 1,770.40 1,770.40 35,408.00
6.5.2 200 Pcs. 20.00 2,213.00 2,213.00 44,260.00
6.5.3 250 Pcs. 20.00 2,923.00 2,923.00 58,460.00
6.5.4 300 Pcs. 20.00 3,315.00 3,315.00 66,300.00
6.5.5 350 Pcs. 20.00 4,292.00 4,292.00 85,840.00
6.5.6 400 Pcs. 20.00 5,043.00 5,043.00 100,860.00
6.5.7 500 Pcs. 20.00 7,807.00 7,807.00 156,140.00
6.5.8 600 Pcs. 20.00 10,104.00 10,104.00 202,080.00
6.5.9 700 Pcs. 20.00 15,281.00 15,281.00 305,620.00
6.5.10 800 Pcs. 20.00 18,120.00 18,120.00 362,400.00
6.5.11 900 Pcs. 20.00 16,711.99 16,711.99 334,239.73
6.5.12 1000 Pcs. 20.00 18,462.01 18,462.01 369,240.27
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 29,719,262.00

Name of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 5 96 of 101


Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh
Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 5 97 of 101


Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.1 Equipment
7.1.1 Micro Tunneling Machine with complete set hrs. 160 6,000.00 6,000.00 960,000.00
7.1.2 Hydraulic HDD Unit hrs. 100 4,000.00 4,000.00 400,000.00
7.1.3 Excavator, face shovel, or dragline:
7.1.3.1 Up to and including 1 m3 hrs. 100 2,000.00 2,000.00 200,000.00
7.1.3.2 Over 1 m3 to 2 m3 hrs. 120 3,000.00 3,000.00 360,000.00
7.1.3.3 Over 2 m3 hrs. 80 3,510.00 3,510.00 280,800.00
7.1.4 Tractor, including bull or angle dozer:
7.1.4.1 Up to and including 150 kW hrs. 140 1,000.00 1,000.00 140,000.00
7.1.4.2 Over 150 kW to 200 kW hrs. 140 1,500.00 1,500.00 210,000.00
7.1.4.3 Over 200 kW to 250 kW hrs. 140 2,000.00 2,000.00 280,000.00
7.1.5 Tractor with ripper:
7.1.5.1 Up to and including 200 kW hrs. 140 1,500.00 1,500.00 210,000.00
7.1.5.2 Over 200 kW to 250 kW hrs. 140 2,000.00 2,000.00 280,000.00
7.1.6 Portable concrete mixer - 0.4m3 hrs. 200 500.00 500.00 100,000.00
7.1.7 Hydraulic Excavator – 1 m3 hrs. 140 3,000.00 3,000.00 420,000.00
7.1.8 4-tool compressor including tools and hoses hrs. 140 2,000.00 2,000.00 280,000.00
7.1.9 10 tonne lorry-mounted crane hrs. 140 5,000.00 5,000.00 700,000.00
7.1.10 750 Kg crane hrs. 140 2,000.00 2,000.00 280,000.00
7.1.11 0.5 m3 dumper hrs. 140 1,000.00 1,000.00 140,000.00
7.1.12 1 m3 dumper hrs. 140 1,500.00 1,500.00 210,000.00
7.1.13 7 m3 tipper lorry hrs. 140 2,000.00 2,000.00 280,000.00
7.1.14 15 m3 lorry hrs. 140 2,000.00 2,000.00 280,000.00
7.1.15 4 wheel drive pick-up or van hrs. 140 500.00 500.00 70,000.00
7.1.16 Vibrating plate compactor hrs. 140 500.00 500.00 70,000.00
7.1.17 8-10 tonne roller hrs. 140 2,000.00 2,000.00 280,000.00
7.1.18 Scaffolding, 10 sqm day 20 2,025.00 2,025.00 40,500.00
7.1.19 5-Ton capacity truck-fare in Dhaka city i/c loading, unloading hrs. 200 456.50 456.50 91,300.00
7.1.20 Concrete mixer machine -1 bag capacity hrs. 120 537.50 537.50 64,500.00
7.1.21 Concrete vibrator-40mm dia hrs. 120 423.00 423.00 50,760.00
7.1.22 Diesel operated 1 cusec pump hrs. 200 505.00 505.00 101,000.00
7.1.23 Electricity operated 1 cusec pump hrs. 160 329.00 329.00 52,640.00
7.1.24 Road cutting Equipment hrs. 160 1,097.00 1,097.00 175,520.00

Dasherkandi Sewerage Project, Cost Estimate for Package 5 98 of 101


Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.1.25 Backhoe Loader, wheel operated hrs. 100 3,510.00 3,510.00 351,000.00

7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 60 675.00 675.00 40,500.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 60 607.50 607.50 36,450.00
clinker): 50kg bag
7.2.3 White Cement kg 160 54.00 54.00 8,640.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 1.00 86,400.00 86,400.00 86,400.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 1.00 87,750.00 87,750.00 87,750.00
7.2.6 MS Sheet M Ton 1.00 114,750.00 114,750.00 114,750.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 3,340 10,800.00 10,800.00 36,072.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 3,340 12,150.00 12,150.00 40,581.00
7.2.9 Imported Earth m3 60 572.50 572.50 34,350.00
7.2.10 Sand (F.M. 0.8) m3 60 525.00 525.00 31,500.00
7.2.11 Sand (F.M. 1.2) m3 40 810.50 810.50 32,420.00
7.2.12 Sand (F.M. 2.5) m3 40 2,384.00 2,384.00 95,360.00
7.2.13 Viti/Filling Sand m3 60 524.50 524.50 31,470.00

Dasherkandi Sewerage Project, Cost Estimate for Package 5 99 of 101


Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.3 Labor
-
7.3.1 Contract Manager day 20 15,000.00 15,000.00 300,000.00
7.3.2 Office Assistant day 40 500.00 500.00 20,000.00
7.3.3 Contract / Legal Advisor day 20 5,000.00 5,000.00 100,000.00
7.3.4 Financial Advisor day 20 5,000.00 5,000.00 100,000.00
7.3.5 Quantity Engineer day 20 3,000.00 3,000.00 60,000.00
7.3.6 Designer day 20 10,000.00 10,000.00 200,000.00
7.3.7 Field Engineer day 20 3,000.00 3,000.00 60,000.00
7.3.8 Draft Person day 20 2,000.00 2,000.00 40,000.00
7.3.9 Ordinary/casual Labour day 160 600.00 600.00 96,000.00
7.3.10 Skilled labour day 80 945.00 945.00 75,600.00
7.3.11 Head Operator/Ganger day 20 1,080.00 1,080.00 21,600.00
7.3.12 Asstt. Operator/Ganger day 40 945.00 945.00 37,800.00
7.3.13 Head Mason day 20 1,080.00 1,080.00 21,600.00
7.3.14 Mud Operator day 20 945.00 945.00 18,900.00
7.3.15 Field Supervisor/Manager day 20 3,375.00 3,375.00 67,500.00
7.3.16 Field/Maintenance Engineer day 40 2,700.00 2,700.00 108,000.00
7.3.17 Skilled technician/Plumber/Mason/Steel work Erector/ day 40 800.00 800.00 32,000.00
7.3.18 Semi Skilled technician day 80 700.00 700.00 56,000.00
7.3.19 Site security day 40 600.00 600.00 24,000.00
7.3.20 Driver day 40 1,100.00 1,100.00 44,000.00
7.3.21 Sweeper for Odd Job day 40 1,000.00 1,000.00 40,000.00
7.3.22 Surveyor day 40 1,080.00 1,080.00 43,200.00
7.3.23 Asstt. Surveyor day 80 810.00 810.00 64,800.00
7.3.24 Carpenter

Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 9,665,263.00

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 5 100 of 101


Schedule No. 8 - O&M Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price
a b c d e f g h=e+f+g i=dxh
8 O&M Services and Documentation

8.1 One year O&M (5 Loops in Segments 17-19)


8.1.1 O&M Services in Loop 401 km 21.62 934,330.00 20,200,214.60
8.1.2 O&M Services in Loop 402 km 8.81 934,330.00 8,231,447.30
8.1.3 O&M Services in Loop 403 km 19.43 934,330.00 18,154,031.90
8.1.4 O&M Services in Loop 404 km 7.43 934,330.00 6,942,071.90
8.1.5 O&M Services in Loop 405 km 29.97 934,330.00 28,001,870.10
8.1.6 O&M Services in Loop 406 km 18.55 934,330.00 17,331,821.50
8.1.7 O&M Services in Loop 407 km 27.79 934,330.00 25,965,030.70
133.60
Sub-total 8.1: Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 124,826,488.00

Name of Bidder

Signature of Bidder

Dasherkandi Sewerage Project, Cost Estimate for Package 5 101 of 101


Employer’s Cost Estimates9

H: Cost of Package 6 (Trunk Pipelines)


Schedule No. 1 - Pipe and Fittings Supplied from Abroad

Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m
1.1.2 ø250 mm m
1.1.3 ø300 mm m
1.1.4 ø350 mm m
1.1.5 ø400 mm m
1.1.6 ø450 mm m
1.1.7 ø500 mm m 608.30
1.1.8 ø600 mm m 403.50
1.1.9 ø700 mm m
1.1.10 ø800 mm m 254.50
1.1.11 ø900 mm m
1.1.12 ø1000 mm m 259.90
1.1.13 ø1100 mm m
1.1.14 ø1200 mm m 175.00
1.1.15 ø1300 mm m 1,254.20
1.1.16 ø1400 mm m 96.40
1.1.17 ø1500 mm m
1.1.18 ø1600 mm m 1,102.90
1.1.19 ø1700 mm m 506.70
1.1.20 ø1800 mm m 719.10
1.1.21 ø1900 mm m 733.20
1.1.22 ø2000 mm m 117.00
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos.
1.2.2 ø250 mm nos.
1.2.3 ø300 mm nos.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 1 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.4 ø350 mm nos.
1.2.5 ø400 mm nos.
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 1
1.2.8 ø600 mm nos. 1
1.2.9 ø700 mm nos.
1.2.10 ø800 mm nos. 1

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 2 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.11 ø900 mm nos.
1.2.12 ø1000 mm nos. 1
1.2.13 ø1100 mm nos.
1.2.14 ø1200 mm nos.
1.2.15 ø1300 mm nos. 3
1.2.16 ø1400 mm nos.
1.2.17 ø1500 mm nos.
1.2.18 ø1600 mm nos. 2
1.2.19 ø1700 mm nos. 1
1.2.20 ø1800 mm nos. 1
1.2.21 ø1900 mm nos. 1
1.2.22 ø2000 mm nos.
1.3 Equal and Un Equal Tee of different sizes
1.3.1 200mm x200mm nos.
1.3.2 250mm x250mm nos.
1.3.3 300mm X 300mm nos.
1.3.4 350mm X 350mm nos.
1.3.5 400mm X 400mm nos.
1.3.6 450mm X 450mm nos.
1.3.7 500mm X 500mm nos. 1
1.3.8 600 mm X 600mm nos. 1
1.3.9 700mm X 700mm nos.
1.3.10 800mm x 800mm nos. 1
1.3.11 900mm X 900mm nos.
1.3.12 1000mm X 1000mm nos. 1
1.3.13 250mm X250mm X 200mm nos.
1.3.14 300mm X 300mm X 200mm nos.
1.3.15 300mm X 300mm X 250mm nos.
1.3.16 400mm X 400mm X 200mm nos.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 3 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.3.17 400mm X 400mm X 250mm nos.
1.3.18 400mm X 400mm X 300mm nos.
1.3.19 500mm X 500mm X 200mm nos. 1
1.3.20 500mm X 500mm X 300mm nos. 1
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos.

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 4 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4.2 ø250 mm nos.
1.4.3 ø300 mm nos.
1.4.4 ø350 mm nos.
1.4.5 ø400 mm nos.
1.4.6 ø450 mm nos.
1.4.7 ø500 mm nos. 2
1.4.8 ø600 mm nos. 2
1.4.9 ø700 mm nos.
1.4.10 ø800 mm nos. 2
1.4.11 ø900 mm nos.
1.4.12 ø1000 mm nos. 2
1.4.13 ø1100 mm nos.
1.4.14 ø1200 mm nos.
1.4.15 ø1300 mm nos. 6
1.4.16 ø1400 mm nos.
1.4.17 ø1500 mm nos.
1.4.18 ø1600 mm nos. 4
1.4.19 ø1700 mm nos. 2
1.4.20 ø1800 mm nos. 2
1.4.21 ø1900 mm nos. 2
1.4.22 ø2000 mm nos.
1.5 Flanged Adapters
1.5.1 ø200 mm nos.
1.5.2 ø250 mm nos.
1.5.3 ø300 mm nos.
1.5.4 ø350 mm nos.
1.5.5 ø400 mm nos. 1
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 5 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.5.8 ø600 mm nos.
1.5.9 ø700 mm nos.
1.5.10 ø800 mm nos. 1
1.5.11 ø900 mm nos. 1
1.5.12 ø1000 mm nos. 1
1.5.13 ø1100 mm nos.
1.5.14 ø1200 mm nos. 1
1.5.15 ø1300 mm nos. 2
1.5.16 ø1400 mm nos. 1
1.5.17 ø1500 mm nos. 1
1.5.18 ø1600 mm nos. 2
1.5.19 ø1700 mm nos. 1
1.5.20 ø1800 mm nos. 1
1.5.21 ø1900 mm nos. 1
1.5.22 ø2000 mm nos. 1

Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 6 of 42
Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country

Unit Price (BDT)


Sales and other
Item Description Unit Qty. Total Unit Total Price (BDT)
Material Labour Equipment taxes (BDT)
Price (EXW)
a b c d e f g h=e+f+g i=dxh j

Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 7 of 42
Schedule No. 3 - Design Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price

a b c d e f g h=e+f+g i=dxh

3.1 Design / Survey Provisions and Preliminaries


3.1.1 Insurances
3.1.1.1 For design (professional indemnity insurance) LS 1 2,550,382.49 2,550,382.49
3.1.1.2 Other Insurances (to be specified by the Tenderer) LS 1 1,275,191 1,275,191.24
Sub-total A: 3,825,573.73
3.2 Design Services (including design office and establishment)

3.2.1 Loop 601


3.2.1.1 Survey and documentation, including Survey Report LS 1 4,494,473 4,494,472.75
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.1.2 LS 1 2,746,622 2,746,622.24
Report
3.2.1.3 Design Control Services including documentation LS 1 749,079 749,078.79

3.2.2 Loop 602


3.2.2.1 Survey and documentation, including Survey Report LS 1 18,458,970 18,458,969.64
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.2.2 LS 1 11,280,481 11,280,481.45
Report
3.2.2.3 Design Control Services including documentation LS 1 3,076,495 3,076,494.94

Sub-total B: 40,806,119.80
Total A+B: Sub-total 3:
44,631,693.53
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary

Name of Bidder:

Signature of Bidder:

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 8 of 42
Schedule No. 4 - Installation / Construction and Other works

Unit Price (BDT)


Item Description Unit Qty. Total Unit Total Price (BDT)
Material Labour Equipment
Price

a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 1,275,191.24 1,275,191.24
4.1.1.2 Advance Payment Guarantee LS 1 1,275,191.24 1,275,191.24
Subtotal 4.1.1 2,550,382.49
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.2 Installation All Risks Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.3 Third Party Liability Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.4 Automobile Liability Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.5 Workers' Compensation LS 1 1,912,786.87 1,912,786.87
4.1.2.6 Employer's Liability LS 1 1,912,786.87 1,912,786.87
4.1.2.7 Contractor's Equipment Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 1,912,786.87 1,912,786.87
Subtotal 4.1.2 15,302,294.93
4.1.3 Site establishment, operation and removal

Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 1,457,361.42 1,457,361.42
workshops, site access and miscellaneous services etc.

Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 1,457,361.42 1,457,361.42
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 1,457,361.42 1,457,361.42
4.1.3.4 Survey instruments LS 1 1,457,361.42 1,457,361.42
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 1,457,361.42 1,457,361.42
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 1,457,361.42 1,457,361.42
Subtotal 4.1.3 8,744,168.53
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 26,596,845.95

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 9 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.2 INSTALLATION of LOOP 601
4.2.1 Miscellaneous works during implementation
4.2.1.1 Setting-out LS 1.00 5,090.00 5,090.00
4.2.1.2 General works and site tests LS 1.00 10,180.00 10,180.00
4.2.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.2.2.1 LS 1.00 10,180.00 10,180.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction completed
4.2.2.2 LS 1.00 3,817.50 3,817.50
& acceptance certificate
4.2.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.2.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.2.2.5 Development and submission of GIS based As-built drawings LS 1.00 6,362.50 6,362.50
4.2.2.6 Post Construction modelling LS 1.00 763.50 763.50

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified below,
including fitting, fixing of all items, road cutting permission fee, temporary road
4.2.3 -
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.

4.2.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.2.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.3.A.1.1 ø200 mm m - 3,596.40 1,581.32 878.18 5,811.99 11,867.89 -


4.2.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.2.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.2.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.2.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.2.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.2.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.2.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.2.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.2.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -
4.2.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 10 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -


4.2.3.A.1.13 ø1100 mm m - 22,694.44 2,965.83 6,308.08 12,592.65 44,561.00 -
4.2.3.A.1.14 ø1200 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -
4.2.3.A.1.15 ø1300 mm m - 26,426.35 3,229.53 7,368.05 13,884.20 50,908.14 -
4.2.3.A.1.16 ø1400 mm m - 28,262.76 3,342.84 7,889.95 14,529.98 54,025.53 -
4.2.3.A.1.17 ø1500 mm m - 30,101.88 3,454.24 8,412.60 15,175.75 57,144.47 -
4.2.3.A.1.18 ø1600 mm m - 31,943.69 3,563.80 8,935.99 15,821.53 60,265.01 -
4.2.3.A.1.19 ø1700 mm m - 32,108.07 3,646.38 8,981.28 16,467.31 61,203.03 -
4.2.3.A.1.20 ø1800 mm m - 32,275.15 3,727.25 9,027.31 17,113.08 62,142.80 -
4.2.3.A.1.21 ø1900 mm m - 32,444.93 3,806.51 9,074.10 17,758.86 63,084.39 -
4.2.3.A.1.22 ø2000 mm m - 32,617.42 3,884.23 9,121.62 18,404.64 64,027.90 -

4.2.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.A.2.1 ø200 mm m 3,890.84 1,719.29 901.27 5,811.99 12,323.40 -


4.2.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.2.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.2.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.2.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.2.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.2.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.2.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.2.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.2.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.2.3.A.2.13 ø1100 mm m 23,051.04 3,358.21 6,338.27 12,592.65 45,340.17 -
4.2.3.A.2.14 ø1200 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -
4.2.3.A.2.15 ø1300 mm m 26,794.79 3,782.37 7,403.55 13,884.20 51,864.91 -
4.2.3.A.2.16 ø1400 mm m 28,637.12 3,979.89 7,928.29 14,529.98 55,075.27 -
4.2.3.A.2.17 ø1500 mm m 30,482.15 4,177.20 8,453.83 15,175.75 58,288.93 -
4.2.3.A.2.18 ø1600 mm m 32,329.89 4,367.92 8,979.94 15,821.53 61,499.28 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 11 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.2.19 ø1700 mm m 32,500.19 4,410.78 9,023.57 16,467.31 62,401.85 -


4.2.3.A.2.20 ø1800 mm m 32,673.19 4,452.06 9,067.94 17,113.08 63,306.27 -
4.2.3.A.2.21 ø1900 mm m 32,848.89 4,491.85 9,113.05 17,758.86 64,212.65 -
4.2.3.A.2.22 ø2000 mm m 33,027.30 4,530.24 9,158.91 18,404.64 65,121.08 -

4.2.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.2.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.2.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.2.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.2.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.2.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.2.3.A.3.7 ø500 mm m 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 -
4.2.3.A.3.8 ø600 mm m 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 -
4.2.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.2.3.A.3.10 ø800 mm m 254.50 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 13,838,317.95

4.2.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.2.3.A.2.12 ø1000 mm m 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 -


4.2.3.A.2.13 ø1100 mm m 34,966.34 4,817.96 7,358.16 12,592.65 59,735.10 -
4.2.3.A.2.14 ø1200 mm m 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 -
4.2.3.A.2.14 ø1300 mm m 38,635.64 5,440.66 8,417.60 13,884.20 66,378.10 -
4.2.3.A.2.15 ø1400 mm m 40,443.63 5,735.80 8,939.73 14,529.98 69,649.15 -
4.2.3.A.2.16 ø1500 mm m 42,254.33 6,031.95 9,462.69 15,175.75 72,924.73 -
4.2.3.A.2.17 ø1600 mm m 44,067.74 6,318.31 9,986.14 15,821.53 76,193.72 -
4.2.3.A.2.18 ø1700 mm m 44,203.70 6,374.05 10,025.19 16,467.31 77,070.24 -
4.2.3.A.2.19 ø1800 mm m 44,342.36 6,428.34 10,064.98 17,113.08 77,948.77 -
4.2.3.A.2.20 ø1900 mm m 44,483.73 6,481.29 10,105.52 17,758.86 78,829.39 -
4.2.3.A.2.21 ø2000 mm m 44,627.80 6,533.01 10,146.80 18,404.64 79,712.24 -

4.2.3.B Sewer Pipelines of Grade-B using GRP Pipes

4.2.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.2.3.B.1.1 ø200 mm m -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 12 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -

4.2.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -

4.2.3.B.2.11 ø900 mm m -

4.2.3.B.2.12 ø1000 mm m -

4.2.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.2.3.B.3.1 ø200 mm m -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 13 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -

4.2.3.B.3.11 ø900 mm m -

4.2.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.2.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved drawing and
specification.

4.2.4.A Normal Manhole Rectangular or circular

4.2.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.2.4.A.1.1 ø200 mm nos. - 108,465.00 17,845.00 10,137.00 136,447.00 -


4.2.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.2.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.2.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 14 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -


4.2.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.2.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.2.4.A.1.14 ø1200 mm nos. - 120,898.00 18,057.00 10,400.00 149,355.00 -
4.2.4.A.1.15 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -
4.2.4.A.1.16 ø1400 mm nos. - 123,381.00 18,098.00 10,453.00 151,932.00 -
4.2.4.A.1.17 ø1500 mm nos. - 124,661.00 18,127.00 10,481.00 153,269.00 -
4.2.4.A.1.18 ø1600 mm nos. - 125,870.00 18,142.00 10,506.00 154,518.00 -
4.2.4.A.1.19 ø1700 mm nos. - 127,143.00 18,168.00 10,533.00 155,844.00 -
4.2.4.A.1.20 ø1800 mm nos. - 128,353.00 18,182.00 10,559.00 157,094.00 -
4.2.4.A.1.21 ø1900 mm nos. - 129,633.00 18,211.00 10,586.00 158,430.00 -
4.2.4.A.1.22 ø2000 mm nos. - 130,842.00 18,226.00 10,611.00 159,679.00 -

4.2.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.A.2.1 ø200 mm nos. 133,076.00 22,507.00 12,324.00 167,907.00 -


4.2.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.2.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.2.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.2.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.2.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.2.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.2.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.2.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.2.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.2.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.2.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.2.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.2.4.A.2.14 ø1200 mm nos. 145,510.00 22,719.00 12,588.00 180,817.00 -
4.2.4.A.2.15 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -
4.2.4.A.2.16 ø1400 mm nos. 147,992.00 22,760.00 12,641.00 183,393.00 -
4.2.4.A.2.17 ø1500 mm nos. 149,272.00 22,789.00 12,668.00 184,729.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 15 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.A.2.18 ø1600 mm nos. 150,482.00 22,803.00 12,694.00 185,979.00 -


4.2.4.A.2.19 ø1700 mm nos. 151,754.00 22,829.00 12,721.00 187,304.00 -
4.2.4.A.2.20 ø1800 mm nos. 152,964.00 22,844.00 12,746.00 188,554.00 -
4.2.4.A.2.21 ø1900 mm nos. 154,244.00 22,873.00 12,774.00 189,891.00 -
4.2.4.A.2.22 ø2000 mm nos. 155,454.00 22,887.00 12,799.00 191,140.00 -

4.2.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.2.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.2.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.2.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.2.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.2.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.2.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.2.4.A.3.7 ø500 mm nos. 185,988 31,881 16,777 234,646.00 -
4.2.4.A.3.8 ø600 mm nos. 187,267 31,910 16,805 235,982.00 -
4.2.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.2.4.A.3.10 ø800 mm nos. 4 189,750 31,950 16,858 238,558.00 954,232.00

4.2.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.2.4.A.3.12 ø1000 mm nos. 192,239 31,994 16,910 241,143.00 -


4.2.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.2.4.A.3.14 ø1200 mm nos. 194,729 32,038 16,963 243,730.00 -
4.2.4.A.3.15 ø1300 mm nos. 196,001 32,064 16,991 245,056.00 -
4.2.4.A.3.16 ø1400 mm nos. 197,211 32,078 17,016 246,305.00 -
4.2.4.A.3.17 ø1500 mm nos. 198,491 32,107 17,043 247,641.00 -
4.2.4.A.3.18 ø1600 mm nos. 199,701 32,122 17,069 248,892.00 -
4.2.4.A.3.19 ø1700 mm nos. 200,973 32,148 17,096 250,217.00 -
4.2.4.A.3.20 ø1800 mm nos. 202,183 32,163 17,121 251,467.00 -
4.2.4.A.3.21 ø1900 mm nos. 203,463 32,192 17,149 252,804.00 -
4.2.4.A.3.22 ø2000 mm nos. 204,673 32,206 17,174 254,053.00 -

4.2.4.B Drop Manhole Rectangular or circular

4.2.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 16 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.1.1 ø200 mm nos. - 177,870.00 34,380.00 19,812.00 232,062.00 -


4.2.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.2.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.2.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.2.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.2.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.2.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.2.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.2.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.2.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.2.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.2.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.2.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.2.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.2.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.2.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.2.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.2.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.2.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.2.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.2.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.2.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.2.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.2.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.2.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

4.2.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.2.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.2.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.2.4.B.3 Manhole invert depth greater than 5m ( > 5m)

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 17 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.2.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.2.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.2.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.2.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.2.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.2.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.2.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.2.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.2.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.2.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.2.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.2.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.2.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.2.4.C Service connections Manhole Rectangular or circular -

4.2.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.2.4.C.1.1 ø200 mm nos. 108,465.00 17,845.00 10,137.00 136,447.00 -


4.2.4.C.1.2 ø250 mm nos. 109,101.00 17,858.00 10,150.00 137,109.00 -
4.2.4.C.1.3 ø300 mm nos. 109,675.00 17,860.00 10,162.00 137,697.00 -
4.2.4.C.1.4 ø350 mm nos. 110,311.00 17,873.00 10,176.00 138,360.00 -
4.2.4.C.1.5 ø400 mm nos. 110,948.00 17,886.00 10,189.00 139,023.00 -
4.2.4.C.1.6 ø450 mm nos. 111,584.00 17,899.00 10,203.00 139,686.00 -
4.2.4.C.1.7 ø500 mm nos. 112,164.00 17,903.00 10,215.00 140,282.00 -
4.2.4.C.1.8 ø600 mm nos. 113,437.00 17,929.00 10,242.00 141,608.00 -
4.2.4.C.1.9 ø700 mm nos. 114,647.00 17,944.00 10,267.00 142,858.00 -
4.2.4.C.1.10 ø800 mm nos. 115,920.00 17,970.00 10,295.00 144,185.00 -
4.2.4.C.1.11 ø900 mm nos. 117,136.00 17,988.00 10,320.00 145,444.00 -
4.2.4.B.1.12 ø1000 mm nos. 118,409.00 18,014.00 10,348.00 146,771.00 -
4.2.4.B.1.13 ø1100 mm nos. 119,682.00 18,040.00 10,375.00 148,097.00 -
4.2.4.B.1.14 ø1300 mm nos. 120,898.00 18,057.00 10,400.00 149,355.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 18 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.2.4.C.2.1 ø200 mm nos. 125,870.00 18,142.00 10,506.00 154,518.00 -


4.2.4.C.2.2 ø250 mm nos. 127,143.00 18,168.00 10,533.00 155,844.00 -
4.2.4.C.2.3 ø300 mm nos. 128,353.00 18,182.00 10,559.00 157,094.00 -
4.2.4.C.2.4 ø350 mm nos. 129,633.00 18,211.00 10,586.00 158,430.00 -
4.2.4.C.2.5 ø400 mm nos. 130,842.00 18,226.00 10,611.00 159,679.00 -
4.2.4.C.2.6 ø450 mm nos. - -
4.2.4.C.2.7 ø500 mm nos. - -
4.2.4.C.2.8 ø600 mm nos. - -
4.2.4.C.2.9 ø700 mm nos. 133,076.00 22,507.00 12,324.00 167,907.00 -
4.2.4.C.2.10 ø800 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -

4.2.4.C.2.11 ø900 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -

4.2.4.C.2.12 ø1000 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -


4.2.4.C.2.13 ø1100 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.2.4.C.2.14 ø1300 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -

4.2.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.2.4.C.3.1 ø200 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -


4.2.4.C.3.2 ø250 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -
4.2.4.C.3.3 ø300 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -
4.2.4.C.3.4 ø350 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.2.4.C.3.5 ø400 mm nos. 145,510.00 22,719.00 12,588.00 180,817.00 -
4.2.4.C.3.6 ø450 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -
4.2.4.C.3.7 ø500 mm nos. 147,992.00 22,760.00 12,641.00 183,393.00 -
4.2.4.C.3.8 ø600 mm nos. 149,272.00 22,789.00 12,668.00 184,729.00 -
4.2.4.C.3.9 ø700 mm nos. 150,482.00 22,803.00 12,694.00 185,979.00 -
4.2.4.C.3.10 ø800 mm nos. 151,754.00 22,829.00 12,721.00 187,304.00 -

4.2.4.C.3.11 ø900 mm nos. 152,964.00 22,844.00 12,746.00 188,554.00 -

4.2.4.B.3.12 ø1000 mm nos. 154,244.00 22,873.00 12,774.00 189,891.00 -


4.2.4.B.3.13 ø1100 mm nos. 155,454.00 22,887.00 12,799.00 191,140.00 -
4.2.4.B.3.14 ø1300 mm nos. - -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 19 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

Supply and Installation of service connections with GRP pipes including fitting, fixing
of all items, road cutting permission fee, temporary road reinstatement, dismantling
4.2.5 of existing structures, site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.

4.2.5.1 ø150 mm nos. 40,766.88 13,972.83 8,265.14 63,004.85 -

4.2.5.2 ø200 mm nos. 44,627.58 15,581.46 9,230.31 69,439.35 -


4.2.5.3 ø250 mm nos. 51,128.58 18,290.21 10,855.56 80,274.35 -
4.2.5.4 ø300 mm nos. 55,471.38 20,099.71 11,941.26 87,512.35 -

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning, earth
4.2.6 -
cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per approved
drawing and specification.

4.2.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.2.6.A.1.1 ø200 mm nos. - 11,079.12 3,235.25 433.10 14,747.46 -


4.2.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.2.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.2.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.2.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.2.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.2.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.2.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.2.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.2.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -
4.2.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -
4.2.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -
4.2.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -
4.2.6.A.1.14 ø1200 mm nos. - 22,769.33 6,946.93 896.75 30,613.01 -
4.2.6.A.1.15 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -
4.2.6.A.1.16 ø1400 mm nos. - 25,597.92 7,779.01 1,007.43 34,384.35 -
4.2.6.A.1.17 ø1500 mm nos. - 27,121.22 8,212.55 1,066.57 36,400.34 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 20 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.1.18 ø1600 mm nos. - 28,590.02 8,640.99 1,124.09 38,355.10 -


4.2.6.A.1.19 ø1700 mm nos. - 30,167.83 9,084.51 1,185.22 40,437.56 -
4.2.6.A.1.20 ø1800 mm nos. - 31,745.64 9,532.88 1,246.73 42,525.26 -
4.2.6.A.1.21 ø1900 mm nos. - 33,432.47 9,996.34 1,311.85 44,740.66 -
4.2.6.A.1.22 ø2000 mm nos. - 35,064.78 10,454.69 1,375.36 46,894.83 -

4.2.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.2.6.A.2.1 ø200 mm nos. - 11,079.12 3,614.08 439.51 15,132.71 -


4.2.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.2.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.2.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.2.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.2.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.2.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.2.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.2.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.2.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.2.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.2.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.2.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.2.6.A.2.14 ø1200 mm nos. - 22,769.33 7,819.90 911.54 31,500.76 -
4.2.6.A.2.15 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -
4.2.6.A.2.16 ø1400 mm nos. - 25,597.92 8,750.79 1,023.89 35,372.60 -
4.2.6.A.2.17 ø1500 mm nos. - 27,121.22 9,233.76 1,083.86 37,438.84 -
4.2.6.A.2.18 ø1600 mm nos. - 28,590.02 9,711.60 1,142.22 39,443.85 -
4.2.6.A.2.19 ø1700 mm nos. - 30,167.83 10,204.54 1,204.19 41,576.56 -
4.2.6.A.2.20 ø1800 mm nos. - 31,745.64 10,702.33 1,266.54 43,714.51 -
4.2.6.A.2.21 ø1900 mm nos. - 33,432.47 11,215.20 1,332.50 45,980.16 -
4.2.6.A.2.22 ø2000 mm nos. - 35,064.78 11,722.96 1,396.84 48,184.58 -

4.2.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.2.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 21 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -


4.2.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.2.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.2.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.2.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.2.6.A.3.7 ø500 mm nos. - 14,177.39 5,852.76 583.83 20,613.98 -
4.2.6.A.3.8 ø600 mm nos. - 15,264.65 6,359.64 629.91 22,254.20 -
4.2.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.2.6.A.3.10 ø800 mm nos. 1.00 17,602.69 7,398.46 727.66 25,728.81 25,728.81

4.2.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.2.6.A.3.12 ø1000 mm nos. - 20,104.25 8,467.18 831.39 29,402.83 -


4.2.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.2.6.A.3.14 ø1200 mm nos. - 22,769.33 9,565.82 941.11 33,276.26 -
4.2.6.A.3.15 ø1300 mm nos. - 24,183.62 10,127.67 998.77 35,310.06 -
4.2.6.A.3.16 ø1400 mm nos. - 25,597.92 10,694.37 1,056.81 37,349.10 -
4.2.6.A.3.17 ø1500 mm nos. - 27,121.22 11,276.16 1,118.46 39,515.84 -
4.2.6.A.3.18 ø1600 mm nos. - 28,590.02 11,852.83 1,178.49 41,621.35 -
4.2.6.A.3.19 ø1700 mm nos. - 30,167.83 12,444.59 1,242.14 43,854.56 -
4.2.6.A.3.20 ø1800 mm nos. - 31,745.64 13,041.21 1,306.16 46,093.01 -
4.2.6.A.3.21 ø1900 mm nos. - 33,432.47 13,652.91 1,373.79 48,459.16 -
4.2.6.A.3.22 ø2000 mm nos. - 35,064.78 14,259.49 1,439.81 50,764.08 -

Supply and Installation of sewerline in canal crossing through pipe jacking using
hydraulic jacks in accordance with the technical specification and the standard
detail drawing, of any diameter and to the depths in any kind of soils, including
construction of thrust and reception pits at manhole positions incorporating headwall
4.2.7 and seal assembly, construction of thrust wall/structural framework and piling if
necessary, fitting, fixing of all items, road cutting permission fee, temporary road
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse materials/ khoa filling, concreting as per approved
drawing and specification.

4.2.7.1 Diameter and depth as specified in the drawing m 74.00 1,148,648.65 85,000,000.00

Sub-total 4.2: Column 'j' to be carried forward to Schedule No. 5


. 99,877,172.26
Grand Summary

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 22 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi
4.3 INSTALLATION of LOOP 602
4.3.1 Miscellaneous works during implementation
4.3.1.1 Setting-out LS 1.00 119,524.00 119,524.00
4.3.1.2 General works and site tests LS 1.00 239,048.00 239,048.00
4.3.2 Commissioning and final inspection /Tests

Pre-commissioning with necessary arrangement on completion of installation,


4.3.2.1 LS 1.00 239,048.00 239,048.00
construction, documentation, reporting etc.
Commissioning and final inspection / testing before issuing construction
4.3.2.2 LS 1.00 89,643.00 89,643.00
completed & acceptance certificate
4.3.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.3.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.3.2.5 Development and submission of GIS based As-built drawings LS 1.00 149,405.00 149,405.00
4.3.2.6 Post Construction modelling LS 1.00 17,928.60 17,928.60

Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.3.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.

4.3.3.A Sewer Pipelines of Grade-A using GRP Pipes -

4.3.3.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.3.A.1.1 ø200 mm m - 3,596.40 1,581.32 878.18 5,811.99 11,867.89 -


4.3.3.A.1.2 ø250 mm m - 4,359.43 1,646.76 1,095.15 6,134.88 13,236.22 -
4.3.3.A.1.3 ø300 mm m - 4,805.13 1,706.98 1,221.68 6,457.77 14,191.56 -
4.3.3.A.1.4 ø350 mm m - 4,859.51 1,760.89 1,236.68 6,780.66 14,637.74 -
4.3.3.A.1.5 ø400 mm m - 6,642.57 1,837.96 1,744.34 7,103.54 17,328.42 -
4.3.3.A.1.6 ø450 mm m - 6,832.70 1,892.84 1,798.01 7,426.43 17,949.99 -
4.3.3.A.1.7 ø500 mm m - 9,518.71 1,984.76 2,563.00 7,749.32 21,815.79 -
4.3.3.A.1.8 ø600 mm m - 11,930.56 2,119.95 3,249.31 8,395.10 25,694.92 -
4.3.3.A.1.9 ø700 mm m - 17,249.23 2,307.31 4,763.78 9,040.87 33,361.19 -
4.3.3.A.1.10 ø800 mm m - 20,400.63 2,628.39 5,658.98 10,655.32 39,343.31 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 23 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.A.1.11 ø900 mm m - 20,636.63 2,738.58 5,724.63 11,301.09 40,400.94 -


4.3.3.A.1.12 ø1000 mm m - 20,869.59 2,848.10 5,789.36 11,946.87 41,453.92 -
4.3.3.A.1.13 ø1100 mm m - 22,694.44 2,965.83 6,308.08 12,592.65 44,561.00 -
4.3.3.A.1.14 ø1200 mm m - 24,592.64 3,114.27 6,846.90 13,238.42 47,792.23 -
4.3.3.A.1.15 ø1300 mm m - 26,426.35 3,229.53 7,368.05 13,884.20 50,908.14 -
4.3.3.A.1.16 ø1400 mm m - 28,262.76 3,342.84 7,889.95 14,529.98 54,025.53 -
4.3.3.A.1.17 ø1500 mm m - 30,101.88 3,454.24 8,412.60 15,175.75 57,144.47 -
4.3.3.A.1.18 ø1600 mm m - 31,943.69 3,563.80 8,935.99 15,821.53 60,265.01 -
4.3.3.A.1.19 ø1700 mm m - 32,108.07 3,646.38 8,981.28 16,467.31 61,203.03 -
4.3.3.A.1.20 ø1800 mm m - 32,275.15 3,727.25 9,027.31 17,113.08 62,142.80 -
4.3.3.A.1.21 ø1900 mm m - 32,444.93 3,806.51 9,074.10 17,758.86 63,084.39 -
4.3.3.A.1.22 ø2000 mm m - 32,617.42 3,884.23 9,121.62 18,404.64 64,027.90 -

4.3.3.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.A.2.1 ø200 mm m 3,890.84 1,719.29 901.27 5,811.99 12,323.40 -


4.3.3.A.2.2 ø250 mm m 4,656.83 1,786.06 1,118.20 6,134.88 13,695.96 -
4.3.3.A.2.3 ø300 mm m 5,105.49 1,887.95 1,246.15 6,457.77 14,697.36 -
4.2.3.A.2.4 ø350 mm m 5,162.83 1,923.06 1,260.37 6,780.66 15,126.92 -
4.3.3.A.2.5 ø400 mm m 6,948.85 2,061.70 1,770.18 7,103.54 17,884.27 -
4.3.3.A.2.6 ø450 mm m 7,141.94 2,138.14 1,824.54 7,426.43 18,531.05 -
4.3.3.A.2.7 ø500 mm m 9,830.91 2,251.66 2,590.21 7,749.32 22,422.10 -
4.3.3.A.2.8 ø600 mm m 12,248.68 2,429.72 3,277.89 8,395.10 26,351.39 -
4.3.3.A.2.9 ø700 mm m 17,573.27 2,694.07 4,794.93 9,040.87 34,103.15 -
4.3.3.A.2.10 ø800 mm m 20,739.47 2,952.01 5,687.36 10,655.32 40,034.15 -

4.2.3.A.2.11 ø900 mm m 20,981.39 3,096.50 5,754.02 11,301.09 41,133.01 -

4.2.3.A.2.12 ø1000 mm m 21,220.27 3,239.48 5,819.72 11,946.87 42,226.33 -


4.2.3.A.2.13 ø1100 mm m 23,051.04 3,358.21 6,338.27 12,592.65 45,340.17 -
4.2.3.A.2.14 ø1200 mm m 24,955.16 3,570.08 6,879.09 13,238.42 48,642.75 -
4.2.3.A.2.15 ø1300 mm m 26,794.79 3,782.37 7,403.55 13,884.20 51,864.91 -
4.2.3.A.2.16 ø1400 mm m 28,637.12 3,979.89 7,928.29 14,529.98 55,075.27 -
4.2.3.A.2.17 ø1500 mm m 30,482.15 4,177.20 8,453.83 15,175.75 58,288.93 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 24 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.2.3.A.2.18 ø1600 mm m 451.00 32,329.89 4,367.92 8,979.94 15,821.53 61,499.28 27,736,176.73


4.2.3.A.2.19 ø1700 mm m 115.90 32,500.19 4,410.78 9,023.57 16,467.31 62,401.85 7,232,374.07
4.2.3.A.2.20 ø1800 mm m 32,673.19 4,452.06 9,067.94 17,113.08 63,306.27 -
4.2.3.A.2.21 ø1900 mm m 32,848.89 4,491.85 9,113.05 17,758.86 64,212.65 -
4.2.3.A.2.22 ø2000 mm m 33,027.30 4,530.24 9,158.91 18,404.64 65,121.08 -

4.3.3.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.A.3.1 ø200 mm m 16,168.88 2,584.29 1,958.66 5,811.99 26,523.83 -


4.3.3.A.3.2 ø250 mm m 16,918.15 2,671.15 2,173.68 6,134.88 27,897.86 -
4.3.3.A.3.3 ø300 mm m 17,350.09 2,820.81 2,300.36 6,457.77 28,929.02 -
4.3.3.A.3.4 ø350 mm m 17,390.70 2,862.27 2,312.34 6,780.66 29,345.97 -
4.3.3.A.3.5 ø400 mm m 19,160.00 3,062.14 2,821.20 7,103.54 32,146.89 -
4.3.3.A.3.6 ø450 mm m 19,336.37 3,172.60 2,873.97 7,426.43 32,809.37 -
4.3.3.A.3.7 ø500 mm m 608.30 22,008.61 3,320.17 3,638.06 7,749.32 36,716.15 22,334,436.93
4.3.3.A.3.8 ø600 mm m 403.50 24,392.93 3,565.94 4,322.56 8,395.10 40,676.53 16,412,978.66
4.3.3.A.3.9 ø700 mm m 29,682.00 3,924.57 5,836.78 9,040.87 48,484.22 -
4.3.3.A.3.10 ø800 mm m 32,761.77 4,239.13 6,718.32 10,655.32 54,374.53 -

4.3.3.A.3.11 ø900 mm m 32,967.36 4,449.95 6,781.41 11,301.09 55,499.82 -

4.3.3.A.2.12 ø1000 mm m 259.90 33,169.60 4,659.17 6,843.50 11,946.87 56,619.15 14,715,315.94


4.3.3.A.2.13 ø1100 mm m 34,966.34 4,817.96 7,358.16 12,592.65 59,735.10 -
4.3.3.A.2.14 ø1200 mm m 175.00 36,830.35 5,121.98 7,895.55 13,238.42 63,086.30 11,040,102.64
4.3.3.A.2.14 ø1300 mm m 1,254.20 38,635.64 5,440.66 8,417.60 13,884.20 66,378.10 83,251,415.70
4.3.3.A.2.15 ø1400 mm m 96.40 40,443.63 5,735.80 8,939.73 14,529.98 69,649.15 6,714,177.82
4.3.3.A.2.16 ø1500 mm m 42,254.33 6,031.95 9,462.69 15,175.75 72,924.73 -
4.3.3.A.2.17 ø1600 mm m 651.90 44,067.74 6,318.31 9,986.14 15,821.53 76,193.72 49,670,687.61
4.3.3.A.2.18 ø1700 mm m 390.80 44,203.70 6,374.05 10,025.19 16,467.31 77,070.24 30,119,051.61
4.3.3.A.2.19 ø1800 mm m 719.10 44,342.36 6,428.34 10,064.98 17,113.08 77,948.77 56,052,957.89
4.3.3.A.2.20 ø1900 mm m 733.20 44,483.73 6,481.29 10,105.52 17,758.86 78,829.39 57,797,711.39
4.3.3.A.2.21 ø2000 mm m 117.00 44,627.80 6,533.01 10,146.80 18,404.64 79,712.24 9,326,332.44

4.3.3.B Sewer Pipelines of Grade-B using GRP Pipes

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 25 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.1 Pipe invert depth less than equal to 3m ( ≤ 3m)

4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -

4.3.3.B.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -

4.3.3.B.2.11 ø900 mm m -

4.3.3.B.2.12 ø1000 mm m -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 26 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.3.B.3 Pipe invert depth greater than 5m ( > 5m)

4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -

4.3.3.B.3.11 ø900 mm m -

4.3.3.B.3.12 ø1000 mm m -

Supply and Installation of RCC Manholes chambers in accordance with the


technical specification and the standard detailed drawings, of any diameter/ size
and to the depths specified below, including fitting, fixing of all items, road cutting
4.3.4 permission fee, temporary road reinstatement, dismantling of existing structures,
site cleaning, earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per approved drawing
and specification.

4.3.4.A Normal Manhole Rectangular or circular

4.3.4.A.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.A.1.1 ø200 mm nos. - 108,465.00 17,845.00 10,137.00 136,447.00 -


4.3.4.A.1.2 ø250 mm nos. - 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.A.1.3 ø300 mm nos. - 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.A.1.4 ø350 mm nos. - 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.A.1.5 ø400 mm nos. - 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.A.1.6 ø450 mm nos. - 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.A.1.7 ø500 mm nos. - 112,164.00 17,903.00 10,215.00 140,282.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 27 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.1.8 ø600 mm nos. - 113,437.00 17,929.00 10,242.00 141,608.00 -


4.3.4.A.1.9 ø700 mm nos. - 114,647.00 17,944.00 10,267.00 142,858.00 -
4.3.4.A.1.10 ø800 mm nos. - 115,920.00 17,970.00 10,295.00 144,185.00 -
4.3.4.A.1.11 ø900 mm nos. - 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.A.1.12 ø1000 mm nos. - 118,409.00 18,014.00 10,348.00 146,771.00 -
4.3.4.A.1.13 ø1100 mm nos. - 119,682.00 18,040.00 10,375.00 148,097.00 -
4.3.4.A.1.14 ø1200 mm nos. - 120,898.00 18,057.00 10,400.00 149,355.00 -
4.3.4.A.1.15 ø1300 mm nos. - 122,171.00 18,083.00 10,428.00 150,682.00 -
4.3.4.A.1.16 ø1400 mm nos. - 123,381.00 18,098.00 10,453.00 151,932.00 -
4.3.4.A.1.17 ø1500 mm nos. - 124,661.00 18,127.00 10,481.00 153,269.00 -
4.3.4.A.1.18 ø1600 mm nos. - 125,870.00 18,142.00 10,506.00 154,518.00 -
4.3.4.A.1.19 ø1700 mm nos. - 127,143.00 18,168.00 10,533.00 155,844.00 -
4.3.4.A.1.20 ø1800 mm nos. - 128,353.00 18,182.00 10,559.00 157,094.00 -
4.3.4.A.1.21 ø1900 mm nos. - 129,633.00 18,211.00 10,586.00 158,430.00 -
4.3.4.A.1.22 ø2000 mm nos. - 130,842.00 18,226.00 10,611.00 159,679.00 -

4.3.4.A.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.A.2.1 ø200 mm nos. 133,076.00 22,507.00 12,324.00 167,907.00 -


4.3.4.A.2.2 ø250 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -
4.3.4.A.2.3 ø300 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -
4.3.4.A.2.4 ø350 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -
4.3.4.A.2.5 ø400 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.A.2.6 ø450 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -
4.3.4.A.2.7 ø500 mm nos. 136,776.00 22,565.00 12,402.00 171,743.00 -
4.3.4.A.2.8 ø600 mm nos. 138,048.00 22,591.00 12,430.00 173,069.00 -
4.3.4.A.2.9 ø700 mm nos. 139,258.00 22,605.00 12,455.00 174,318.00 -
4.3.4.A.2.10 ø800 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -

4.3.4.A.2.11 ø900 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -

4.3.4.A.2.12 ø1000 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -


4.3.4.A.2.13 ø1100 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.3.4.A.2.14 ø1200 mm nos. 145,510.00 22,719.00 12,588.00 180,817.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 28 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.2.15 ø1300 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -


4.3.4.A.2.16 ø1400 mm nos. 147,992.00 22,760.00 12,641.00 183,393.00 -
4.3.4.A.2.17 ø1500 mm nos. 149,272.00 22,789.00 12,668.00 184,729.00 -
4.3.4.A.2.18 ø1600 mm nos. 9 150,482.00 22,803.00 12,694.00 185,979.00 1,673,811.00
4.3.4.A.2.19 ø1700 mm nos. 2 151,754.00 22,829.00 12,721.00 187,304.00 374,608.00
4.3.4.A.2.20 ø1800 mm nos. 152,964.00 22,844.00 12,746.00 188,554.00 -
4.3.4.A.2.21 ø1900 mm nos. 1 154,244.00 22,873.00 12,774.00 189,891.00 189,891.00
4.3.4.A.2.22 ø2000 mm nos. 155,454.00 22,887.00 12,799.00 191,140.00 -

4.3.4.A.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.A.3.1 ø200 mm nos. 182,295 31,825 16,700 230,820.00 -


4.3.4.A.3.2 ø250 mm nos. 182,932 31,838 16,713 231,483.00 -
4.3.4.A.3.3 ø300 mm nos. 183,505 31,840 16,725 232,070.00 -
4.3.4.A.3.4 ø350 mm nos. 184,142 31,853 16,738 232,733.00 -
4.3.4.A.3.5 ø400 mm nos. 184,778 31,866 16,752 233,396.00 -
4.3.4.A.3.6 ø450 mm nos. 185,414 31,879 16,766 234,059.00 -
4.3.4.A.3.7 ø500 mm nos. 7 185,988 31,881 16,777 234,646.00 1,642,522.00
4.3.4.A.3.8 ø600 mm nos. 4 187,267 31,910 16,805 235,982.00 943,928.00
4.3.4.A.3.9 ø700 mm nos. 188,477 31,924 16,830 237,231.00 -
4.3.4.A.3.10 ø800 mm nos. 189,750 31,950 16,858 238,558.00 -

4.3.4.A.3.11 ø900 mm nos. 190,967 31,968 16,883 239,818.00 -

4.3.4.A.3.12 ø1000 mm nos. 3 192,239 31,994 16,910 241,143.00 723,429.00


4.3.4.A.3.13 ø1100 mm nos. 193,512 32,020 16,938 242,470.00 -
4.3.4.A.3.14 ø1200 mm nos. 2 194,729 32,038 16,963 243,730.00 487,460.00
4.3.4.A.3.15 ø1300 mm nos. 14 196,001 32,064 16,991 245,056.00 3,430,784.00
4.3.4.A.3.16 ø1400 mm nos. 2 197,211 32,078 17,016 246,305.00 492,610.00
4.3.4.A.3.17 ø1500 mm nos. 198,491 32,107 17,043 247,641.00 -
4.3.4.A.3.18 ø1600 mm nos. 3 199,701 32,122 17,069 248,892.00 746,676.00
4.3.4.A.3.19 ø1700 mm nos. 3 200,973 32,148 17,096 250,217.00 750,651.00
4.3.4.A.3.20 ø1800 mm nos. 8 202,183 32,163 17,121 251,467.00 2,011,736.00
4.3.4.A.3.21 ø1900 mm nos. 8 203,463 32,192 17,149 252,804.00 2,022,432.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 29 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.A.3.22 ø2000 mm nos. 2 204,673 32,206 17,174 254,053.00 508,106.00

4.3.4.B Drop Manhole Rectangular or circular

4.3.4.B.1 Manhole invert depth less than equal to 3m ( ≤ 3m)

4.3.4.B.1.1 ø200 mm nos. - 177,870.00 34,380.00 19,812.00 232,062.00 -


4.3.4.B.1.2 ø250 mm nos. - 178,362.00 34,406.00 19,840.00 232,608.00 -
4.3.4.B.1.3 ø300 mm nos. - 178,728.00 34,410.00 19,862.00 233,000.00 -
4.3.4.B.1.4 ø350 mm nos. - 179,220.00 34,436.00 19,890.00 233,546.00 -
4.3.4.B.1.5 ø400 mm nos. - 179,712.00 34,462.00 19,918.00 234,092.00 -
4.3.4.B.1.6 ø450 mm nos. - 180,204.00 34,488.00 19,946.00 234,638.00 -
4.3.4.B.1.7 ø500 mm nos. - 180,584.00 34,496.00 19,968.00 235,048.00 -
4.3.4.B.1.8 ø600 mm nos. - 181,568.00 34,548.00 20,022.00 236,138.00 -
4.3.4.B.1.9 ø700 mm nos. - 182,426.00 34,578.00 20,074.00 237,078.00 -
4.3.4.B.1.10 ø800 mm nos. - 183,410.00 34,630.00 20,128.00 238,168.00 -
4.3.4.B.1.11 ø900 mm nos. - 184,282.00 34,664.00 20,178.00 239,124.00 -
4.3.4.B.1.12 ø1000 mm nos. - 185,266.00 34,718.00 20,234.00 240,218.00 -
4.3.4.B.1.13 ø1100 mm nos. - 186,250.00 34,770.00 20,288.00 241,308.00 -
4.3.4.B.1.14 ø1300 mm nos. - 188,106.00 34,856.00 20,394.00 243,356.00 -

4.3.4.B.2 Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.B.2.1 ø200 mm nos. 216,110.00 42,604.00 23,944.00 282,658.00 -


4.3.4.B.2.2 ø250 mm nos. 216,602.00 42,630.00 23,972.00 283,204.00 -
4.3.4.B.2.3 ø300 mm nos. 216,968.00 42,634.00 23,994.00 283,596.00 -
4.3.4.B.2.4 ø350 mm nos. 217,460.00 42,660.00 24,022.00 284,142.00 -
4.3.4.B.2.5 ø400 mm nos. 217,952.00 42,686.00 24,050.00 284,688.00 -
4.3.4.B.2.6 ø450 mm nos. 218,444.00 42,712.00 24,076.00 285,232.00 -
4.3.4.B.2.7 ø500 mm nos. 218,824.00 42,720.00 24,100.00 285,644.00 -
4.3.4.B.2.8 ø600 mm nos. 219,808.00 42,772.00 24,154.00 286,734.00 -
4.3.4.B.2.9 ø700 mm nos. 220,666.00 42,802.00 24,204.00 287,672.00 -
4.3.4.B.2.10 ø800 mm nos. 221,650.00 42,854.00 24,260.00 288,764.00 -

4.3.4.B.2.11 ø900 mm nos. 222,522.00 42,890.00 24,310.00 289,722.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 30 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.B.2.12 ø1000 mm nos. 223,506.00 42,942.00 24,366.00 290,814.00 -


4.3.4.B.2.13 ø1100 mm nos. 224,490.00 42,994.00 24,420.00 291,904.00 -
4.3.4.B.2.14 ø1300 mm nos. 226,346.00 43,082.00 24,526.00 293,954.00 -

4.3.4.B.3 Manhole invert depth greater than 5m ( > 5m)

4.3.4.B.3.1 ø200 mm nos. 292,584.00 59,046.00 32,206.00 383,836.00 -


4.3.4.B.3.2 ø250 mm nos. 293,074.00 59,072.00 32,234.00 384,380.00 -
4.3.4.B.3.3 ø300 mm nos. 293,442.00 59,074.00 32,256.00 384,772.00 -
4.3.4.B.3.4 ø350 mm nos. 293,934.00 59,100.00 32,284.00 385,318.00 -
4.3.4.B.3.5 ø400 mm nos. 294,426.00 59,126.00 32,310.00 385,862.00 -
4.3.4.B.3.6 ø450 mm nos. 294,918.00 59,152.00 32,338.00 386,408.00 -
4.3.4.B.3.7 ø500 mm nos. 295,284.00 59,156.00 32,362.00 386,802.00 -
4.3.4.B.3.8 ø600 mm nos. 296,282.00 59,214.00 32,416.00 387,912.00 -
4.3.4.B.3.9 ø700 mm nos. 297,140.00 59,244.00 32,466.00 388,850.00 -
4.3.4.B.3.10 ø800 mm nos. 298,124.00 59,296.00 32,522.00 389,942.00 -

4.3.4.B.3.11 ø900 mm nos. 298,996.00 59,330.00 32,572.00 390,898.00 -

4.3.4.B.3.12 ø1000 mm nos. 299,980.00 59,382.00 32,628.00 391,990.00 -


4.3.4.B.3.13 ø1100 mm nos. 300,964.00 59,434.00 32,682.00 393,080.00 -
4.3.4.B.3.14 ø1300 mm nos. 302,820.00 59,522.00 32,788.00 395,130.00 -

4.3.4.C Service connections Manhole Rectangular or circular -

4.3.4.C.1 S/C Manhole invert depth less than equal to 3m ( ≤ 3m) -

4.3.4.C.1.1 ø200 mm nos. 108,465.00 17,845.00 10,137.00 136,447.00 -


4.3.4.C.1.2 ø250 mm nos. 109,101.00 17,858.00 10,150.00 137,109.00 -
4.3.4.C.1.3 ø300 mm nos. 109,675.00 17,860.00 10,162.00 137,697.00 -
4.3.4.C.1.4 ø350 mm nos. 110,311.00 17,873.00 10,176.00 138,360.00 -
4.3.4.C.1.5 ø400 mm nos. 110,948.00 17,886.00 10,189.00 139,023.00 -
4.3.4.C.1.6 ø450 mm nos. 111,584.00 17,899.00 10,203.00 139,686.00 -
4.3.4.C.1.7 ø500 mm nos. 112,164.00 17,903.00 10,215.00 140,282.00 -
4.3.4.C.1.8 ø600 mm nos. 113,437.00 17,929.00 10,242.00 141,608.00 -
4.3.4.C.1.9 ø700 mm nos. 114,647.00 17,944.00 10,267.00 142,858.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 31 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.C.1.10 ø800 mm nos. 115,920.00 17,970.00 10,295.00 144,185.00 -


4.3.4.C.1.11 ø900 mm nos. 117,136.00 17,988.00 10,320.00 145,444.00 -
4.3.4.C.1.12 ø1000 mm nos. 118,409.00 18,014.00 10,348.00 146,771.00 -
4.3.4.C.1.13 ø1100 mm nos. 119,682.00 18,040.00 10,375.00 148,097.00 -
4.3.4.C.1.14 ø1300 mm nos. 120,898.00 18,057.00 10,400.00 149,355.00 -

4.3.4.C.2 S/C Manhole invert depth 3 m to 5m ( > 3m to 5m)

4.3.4.C.2.1 ø200 mm nos. 125,870.00 18,142.00 10,506.00 154,518.00 -


4.3.4.C.2.2 ø250 mm nos. 127,143.00 18,168.00 10,533.00 155,844.00 -
4.3.4.C.2.3 ø300 mm nos. 128,353.00 18,182.00 10,559.00 157,094.00 -
4.3.4.C.2.4 ø350 mm nos. 129,633.00 18,211.00 10,586.00 158,430.00 -
4.3.4.C.2.5 ø400 mm nos. 130,842.00 18,226.00 10,611.00 159,679.00 -
4.3.4.C.2.6 ø450 mm nos. - -
4.3.4.C.2.7 ø500 mm nos. - -
4.3.4.C.2.8 ø600 mm nos. - -
4.3.4.C.2.9 ø700 mm nos. 133,076.00 22,507.00 12,324.00 167,907.00 -
4.3.4.C.2.10 ø800 mm nos. 133,713.00 22,520.00 12,338.00 168,571.00 -

4.3.4.C.2.11 ø900 mm nos. 134,286.00 22,521.00 12,350.00 169,157.00 -

4.3.4.C.2.12 ø1000 mm nos. 134,923.00 22,534.00 12,363.00 169,820.00 -


4.3.4.C.2.13 ø1100 mm nos. 135,559.00 22,547.00 12,377.00 170,483.00 -
4.3.4.C.2.14 ø1300 mm nos. 136,195.00 22,560.00 12,391.00 171,146.00 -

4.3.4.C.3 S/C Manhole invert depth greater than 5m ( > 5m)

4.3.4.C.3.1 ø200 mm nos. 140,531.00 22,632.00 12,483.00 175,646.00 -


4.3.4.C.3.2 ø250 mm nos. 141,748.00 22,649.00 12,508.00 176,905.00 -
4.3.4.C.3.3 ø300 mm nos. 143,020.00 22,675.00 12,535.00 178,230.00 -
4.3.4.C.3.4 ø350 mm nos. 144,293.00 22,701.00 12,563.00 179,557.00 -
4.3.4.C.3.5 ø400 mm nos. 145,510.00 22,719.00 12,588.00 180,817.00 -
4.3.4.C.3.6 ø450 mm nos. 146,782.00 22,745.00 12,616.00 182,143.00 -
4.3.4.C.3.7 ø500 mm nos. 147,992.00 22,760.00 12,641.00 183,393.00 -
4.3.4.C.3.8 ø600 mm nos. 149,272.00 22,789.00 12,668.00 184,729.00 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 32 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.4.C.3.9 ø700 mm nos. 150,482.00 22,803.00 12,694.00 185,979.00 -


4.3.4.C.3.10 ø800 mm nos. 151,754.00 22,829.00 12,721.00 187,304.00 -

4.3.4.C.3.11 ø900 mm nos. 152,964.00 22,844.00 12,746.00 188,554.00 -

4.3.4.C.3.12 ø1000 mm nos. 154,244.00 22,873.00 12,774.00 189,891.00 -


4.3.4.C.3.13 ø1100 mm nos. 155,454.00 22,887.00 12,799.00 191,140.00 -
4.3.4.C.3.14 ø1300 mm nos. - -

Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.3.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.

4.3.5.1 ø150 mm nos. 40,766.88 13,972.83 8,265.14 63,004.85 -

4.3.5.2 ø200 mm nos. 44,627.58 15,581.46 9,230.31 69,439.35 -


4.3.5.3 ø250 mm nos. 51,128.58 18,290.21 10,855.56 80,274.35 -
4.3.5.4 ø300 mm nos. 55,471.38 20,099.71 11,941.26 87,512.35 -

Construction of concrete thrust blocks including road cutting permission fee,


temporary road reinstatement, dismantling of existing structures, site cleaning,
4.3.6 -
earth cutting, sand filling, earth refilling , coarse material s/ khoa filling, as per
approved drawing and specification.

4.3.6.A.1 Pipe invert depth less than equal to 3m ( ≤ 3m) -

4.3.6.A.1.1 ø200 mm nos. - 11,079.12 3,235.25 433.10 14,747.46 -


4.3.6.A.1.2 ø250 mm nos. - 11,597.22 3,408.39 453.76 15,459.37 -
4.3.6.A.1.3 ø300 mm nos. - 12,111.88 3,579.06 474.29 16,165.22 -
4.3.6.A.1.4 ø350 mm nos. - 12,575.47 3,742.23 492.96 16,810.66 -
4.3.6.A.1.5 ø400 mm nos. - 13,090.13 3,917.76 513.86 17,521.75 -
4.3.6.A.1.6 ø450 mm nos. - 13,662.73 4,100.87 536.52 18,300.13 -
4.3.6.A.1.7 ø500 mm nos. - 14,177.39 4,271.54 557.05 19,005.98 -
4.3.6.A.1.8 ø600 mm nos. - 15,264.65 4,630.19 600.61 20,495.45 -
4.3.6.A.1.9 ø700 mm nos. - 16,460.93 5,003.91 647.78 22,112.62 -
4.3.6.A.1.10 ø800 mm nos. - 17,602.69 5,372.52 693.34 23,668.56 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 33 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.1.11 ø900 mm nos. - 18,853.47 5,756.22 742.51 25,352.20 -


4.3.6.A.1.12 ø1000 mm nos. - 20,104.25 6,144.77 792.06 27,041.08 -
4.3.6.A.1.13 ø1100 mm nos. - 21,464.04 6,548.41 845.21 28,857.66 -
4.3.6.A.1.14 ø1200 mm nos. - 22,769.33 6,946.93 896.75 30,613.01 -
4.3.6.A.1.15 ø1300 mm nos. - 24,183.62 7,360.54 951.90 32,496.06 -
4.3.6.A.1.16 ø1400 mm nos. - 25,597.92 7,779.01 1,007.43 34,384.35 -
4.3.6.A.1.17 ø1500 mm nos. - 27,121.22 8,212.55 1,066.57 36,400.34 -
4.3.6.A.1.18 ø1600 mm nos. - 28,590.02 8,640.99 1,124.09 38,355.10 -
4.3.6.A.1.19 ø1700 mm nos. - 30,167.83 9,084.51 1,185.22 40,437.56 -
4.3.6.A.1.20 ø1800 mm nos. - 31,745.64 9,532.88 1,246.73 42,525.26 -
4.3.6.A.1.21 ø1900 mm nos. - 33,432.47 9,996.34 1,311.85 44,740.66 -
4.3.6.A.1.22 ø2000 mm nos. - 35,064.78 10,454.69 1,375.36 46,894.83 -

4.3.6.A.2 Pipe invert depth 3 m to 5m ( > 3m to 5m)

4.3.6.A.2.1 ø200 mm nos. - 11,079.12 3,614.08 439.51 15,132.71 -


4.3.6.A.2.2 ø250 mm nos. - 11,597.22 3,810.28 460.57 15,868.07 -
4.3.6.A.2.3 ø300 mm nos. - 12,111.88 4,007.30 481.54 16,600.72 -
4.3.6.A.2.4 ø350 mm nos. - 12,575.47 4,195.03 500.60 17,271.10 -
4.3.6.A.2.5 ø400 mm nos. - 13,090.13 4,395.42 521.95 18,007.50 -
4.3.6.A.2.6 ø450 mm nos. - 13,662.73 4,601.59 545.00 18,809.33 -
4.3.6.A.2.7 ø500 mm nos. - 14,177.39 4,798.62 565.97 19,541.98 -
4.3.6.A.2.8 ø600 mm nos. - 15,264.65 5,206.67 610.38 21,081.70 -
4.3.6.A.2.9 ø700 mm nos. - 16,460.93 5,629.81 658.39 22,749.12 -
4.3.6.A.2.10 ø800 mm nos. - 17,602.69 6,047.83 704.78 24,355.31 -

4.3.6.A.2.11 ø900 mm nos. - 18,853.47 6,480.94 754.78 26,089.20 -

4.3.6.A.2.12 ø1000 mm nos. - 20,104.25 6,918.91 805.17 27,828.33 -


4.3.6.A.2.13 ø1100 mm nos. - 21,464.04 7,371.96 859.16 29,695.16 -
4.3.6.A.2.14 ø1200 mm nos. - 22,769.33 7,819.90 911.54 31,500.76 -
4.3.6.A.2.15 ø1300 mm nos. - 24,183.62 8,282.92 967.52 33,434.06 -
4.3.6.A.2.16 ø1400 mm nos. - 25,597.92 8,750.79 1,023.89 35,372.60 -
4.3.6.A.2.17 ø1500 mm nos. - 27,121.22 9,233.76 1,083.86 37,438.84 -

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 34 of 42
Schedule No. 4 - Installation and Other Services

Unit Price (BDT)


Item Description Unit Qty. Road Cutting Total Unit Total Price (BDT)
Material Labour Equipment
Fees Price
a b c d e f g h i = e+f+g+h j=dxi

4.3.6.A.2.18 ø1600 mm nos. 3.00 28,590.02 9,711.60 1,142.22 39,443.85 118,331.55


4.3.6.A.2.19 ø1700 mm nos. 1.00 30,167.83 10,204.54 1,204.19 41,576.56 41,576.56
4.3.6.A.2.20 ø1800 mm nos. - 31,745.64 10,702.33 1,266.54 43,714.51 -
4.3.6.A.2.21 ø1900 mm nos. - 33,432.47 11,215.20 1,332.50 45,980.16 -
4.3.6.A.2.22 ø2000 mm nos. - 35,064.78 11,722.96 1,396.84 48,184.58 -

4.3.6.A.3 Pipe invert depth greater than 5m ( > 5m)

4.3.6.A.3.1 ø200 mm nos. - 11,079.12 4,371.74 452.35 15,903.21 -


4.3.6.A.3.2 ø250 mm nos. - 11,597.22 4,617.36 474.24 16,688.82 -
4.3.6.A.3.3 ø300 mm nos. - 12,111.88 4,863.80 496.05 17,471.72 -
4.3.6.A.3.4 ø350 mm nos. - 12,575.47 5,100.93 515.95 18,192.35 -
4.3.6.A.3.5 ø400 mm nos. - 13,090.13 5,350.74 538.14 18,979.00 -
4.3.6.A.3.6 ø450 mm nos. - 13,662.73 5,606.32 562.02 19,831.08 -
4.3.6.A.3.7 ø500 mm nos. 2.00 14,177.39 5,852.76 583.83 20,613.98 41,227.96
4.3.6.A.3.8 ø600 mm nos. 1.00 15,264.65 6,359.64 629.91 22,254.20 22,254.20
4.3.6.A.3.9 ø700 mm nos. - 16,460.93 6,881.60 679.59 24,022.12 -
4.3.6.A.3.10 ø800 mm nos. - 17,602.69 7,398.46 727.66 25,728.81 -

4.3.6.A.3.11 ø900 mm nos. - 18,853.47 7,930.39 779.34 27,563.20 -

4.3.6.A.3.12 ø1000 mm nos. 1.00 20,104.25 8,467.18 831.39 29,402.83 29,402.83


4.3.6.A.3.13 ø1100 mm nos. - 21,464.04 9,019.06 887.06 31,370.16 -
4.3.6.A.3.14 ø1200 mm nos. 1.00 22,769.33 9,565.82 941.11 33,276.26 33,276.26
4.3.6.A.3.15 ø1300 mm nos. 5.00 24,183.62 10,127.67 998.77 35,310.06 176,550.30
4.3.6.A.3.16 ø1400 mm nos. 1.00 25,597.92 10,694.37 1,056.81 37,349.10 37,349.10
4.3.6.A.3.17 ø1500 mm nos. - 27,121.22 11,276.16 1,118.46 39,515.84 -
4.3.6.A.3.18 ø1600 mm nos. 1.00 28,590.02 11,852.83 1,178.49 41,621.35 41,621.35
4.3.6.A.3.19 ø1700 mm nos. 1.00 30,167.83 12,444.59 1,242.14 43,854.56 43,854.56
4.3.6.A.3.20 ø1800 mm nos. 3.00 31,745.64 13,041.21 1,306.16 46,093.01 138,279.03
4.3.6.A.3.21 ø1900 mm nos. 3.00 33,432.47 13,652.91 1,373.79 48,459.16 145,377.48
4.3.6.A.3.22 ø2000 mm nos. 1.00 35,064.78 14,259.49 1,439.81 50,764.08 50,764.08

Sub-total 4.3: Column 'j' to be carried forward to Schedule No. 5


. 410,199,325.30
Grand Summary

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 35 of 42
Schedule No. 5 - Grand Summary

Schedule No. Title


Total Price (BDT)

1 Schedule No. 1 - Pipe and Fittings Supplied from Abroad


2 Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
3 Schedule No. 3 - Design Services 44631694
4 Schedule No. 4 - Installation / Construction and Other works
4.1 Implementation Provisions and Preliminaries for all Loops 26596846
4.2 Installation/ Construction of all Loops (Schedule 4)
4.2.1 INSTALLATION of LOOP 601 99877172
4.2.2 INSTALLATION of LOOP 602 410199325
Sub total 4.2: Installation/ Construction of all Loops (Schedule 4) 510076498
5 Provisional Sum
5.1 Provisional sum for Physical Contingencies 25503825
5.2 Provisional Sum for Price Contingencies 24147892
5.3 Provisional Sum for alleviations program, refer to SCC, Sub-Clause xxxxxx 1457361
Sub-Total 5: Provisional Sum 51109079
6 Recommended spare parts 5206420
7 Day work 502381
8 O&M - 5820876
. Grand Total (1+3+4.1+4.2+5+6+7+8) to be carried forward to Letter of Bid 643943792

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 36 of 42
Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh

Recommended Spare Parts


6.1 GRP Sewer Pipe (Dia in mm)
6.1.1 900 meter 8.00 18,190.00 18,190.00 145,520.00
6.1.2 1000 meter 8.00 18,250.80 18,250.80 146,006.40
6.1.3 1100 meter 8.00 22,557.07 22,557.07 180,456.56
6.1.4 1200 meter 8.00 24,823.24 24,823.24 198,585.92
6.1.5 1300 meter 10.00 27,089.41 27,089.41 270,894.10
6.1.6 1400 meter 10.00 29,355.58 29,355.58 293,555.80
6.1.7 1500 meter 10.00 31,621.75 31,621.75 316,217.50
6.1.8 1600 meter 7.00 33,887.93 33,887.93 237,215.51
6.1.9 1700 meter 7.00 36,154.10 36,154.10 253,078.70
6.1.10 1800 meter 7.00 38,420.27 38,420.27 268,941.89
6.1.11 1900 meter 7.00 40,686.44 40,686.44 284,805.08
6.1.12 2000 meter 7.00 42,952.61 42,952.61 300,668.27
6.2 Coupler/Coller
6.2.1 900 Pcs. 2.00 27,285.00 27,285.00 54,570.00
6.2.2 1000 Pcs. 2.00 27,376.20 27,376.20 54,752.40
6.2.3 1100 Pcs. 2.00 33,835.61 33,835.61 67,671.21
6.2.4 1200 Pcs. 2.00 37,234.86 37,234.86 74,469.72
6.2.5 1300 Pcs. 2.00 40,634.12 40,634.12 81,268.23
6.2.6 1400 Pcs. 2.00 44,033.37 44,033.37 88,066.74
6.2.7 1500 Pcs. 2.00 47,432.63 47,432.63 94,865.25
6.2.8 1600 Pcs. 2.00 50,831.90 50,831.90 101,663.79
6.2.9 1700 Pcs. 2.00 54,231.15 54,231.15 108,462.30
6.2.10 1800 Pcs. 2.00 57,630.41 57,630.41 115,260.81
6.2.11 1900 Pcs. 2.00 61,029.66 61,029.66 122,059.32
6.2.12 2000 Pcs. 2.00 64,428.92 64,428.92 128,857.83
6.3 Flange Adapter
6.3.1 900 Pcs. 1.00 9,095.00 9,095.00 9,095.00
6.3.2 1000 Pcs. 1.00 9,125.40 9,125.40 9,125.40
6.3.3 1100 Pcs. 1.00 11,278.54 11,278.54 11,278.54
6.3.4 1200 Pcs. 1.00 12,411.62 12,411.62 12,411.62
6.3.5 1300 Pcs. 1.00 13,544.71 13,544.71 13,544.71
6.3.6 1400 Pcs. 1.00 14,677.79 14,677.79 14,677.79
6.3.7 1500 Pcs. 1.00 15,810.88 15,810.88 15,810.88
6.3.8 1600 Pcs. 1.00 16,943.97 16,943.97 16,943.97
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 37 of 42
Schedule No. 6 - Recommended Spare Parts

Unit Price (BDT)


Item Description Unit Nominal Quantity Total Unit Price Total Price (BDT)
Material Labour Equipment
(EXW/CIP)
a b c d e f g h=e+f+g i=dxh
6.3.9 1700 Pcs. 1.00 18,077.05 18,077.05 18,077.05
6.3.10 1800 Pcs. 1.00 19,210.14 19,210.14 19,210.14
6.3.11 1900 Pcs. 1.00 20,343.22 20,343.22 20,343.22
6.3.12 2000 Pcs. 1.00 21,476.31 21,476.31 21,476.31
6.4 Tee/Wye
6.4.1 900 Pcs. 1.00 27,285.00 27,285.00 27,285.00
6.4.2 1000 Pcs. 1.00 27,376.20 27,376.20 27,376.20
6.4.3 1100 Pcs. 1.00 33,835.61 33,835.61 33,835.61
6.4.4 1200 Pcs. 1.00 37,234.86 37,234.86 37,234.86
6.4.5 1300 Pcs. 1.00 40,634.12 40,634.12 40,634.12
6.4.6 1400 Pcs. 1.00 58,711.16 58,711.16 58,711.16
6.4.7 1500 Pcs. 1.00 63,243.50 63,243.50 63,243.50
6.4.8 1600 Pcs. 1.00 67,775.86 67,775.86 67,775.86
6.4.9 1700 Pcs. 1.00 72,308.20 72,308.20 72,308.20
6.4.10 1800 Pcs. 1.00 76,840.54 76,840.54 76,840.54
6.4.11 1900 Pcs. 1.00 81,372.88 81,372.88 81,372.88
6.4.12 2000 Pcs. 1.00 85,905.22 85,905.22 85,905.22
6.5 Elbow (30/60/90 degrees)
6.5.1 900 Pcs. 1.00 18,190.00 18,190.00 18,190.00
6.5.2 1000 Pcs. 1.00 18,250.80 18,250.80 18,250.80
6.5.3 1100 Pcs. 1.00 22,557.07 22,557.07 22,557.07
6.5.4 1200 Pcs. 1.00 24,823.24 24,823.24 24,823.24
6.5.5 1300 Pcs. 1.00 27,089.41 27,089.41 27,089.41
6.5.6 1400 Pcs. 1.00 29,355.58 29,355.58 29,355.58
6.5.7 1500 Pcs. 1.00 31,621.75 31,621.75 31,621.75
6.5.8 1600 Pcs. 1.00 33,887.93 33,887.93 33,887.93
6.5.9 1700 Pcs. 1.00 36,154.10 36,154.10 36,154.10
6.5.10 1800 Pcs. 1.00 38,420.27 38,420.27 38,420.27
6.5.11 1900 Pcs. 1.00 40,686.44 40,686.44 40,686.44
6.5.12 2000 Pcs. 1.00 42,952.61 42,952.61 42,952.61
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 5,206,420.27

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 38 of 42
Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.1 Equipment
7.1.1 Micro Tunneling Machine with complete set hrs. 8 6,000.00 6,000.00 48,000.00
7.1.2 Hydraulic HDD Unit hrs. 5 4,000.00 4,000.00 20,000.00
7.1.3 Excavator, face shovel, or dragline:
7.1.3.1 Up to and including 1 m3 hrs. 5 2,000.00 2,000.00 10,000.00
7.1.3.2 Over 1 m3 to 2 m3 hrs. 6 3,000.00 3,000.00 18,000.00
7.1.3.3 Over 2 m3 hrs. 4 3,510.00 3,510.00 14,040.00
7.1.4 Tractor, including bull or angle dozer:
7.1.4.1 Up to and including 150 kW hrs. 7 1,000.00 1,000.00 7,000.00
7.1.4.2 Over 150 kW to 200 kW hrs. 7 1,500.00 1,500.00 10,500.00
7.1.4.3 Over 200 kW to 250 kW hrs. 7 2,000.00 2,000.00 14,000.00
7.1.5 Tractor with ripper:
7.1.5.1 Up to and including 200 kW hrs. 7 1,500.00 1,500.00 10,500.00
7.1.5.2 Over 200 kW to 250 kW hrs. 7 2,000.00 2,000.00 14,000.00
7.1.6 Portable concrete mixer - 0.4m3 hrs. 10 500.00 500.00 5,000.00
7.1.7 Hydraulic Excavator – 1 m3 hrs. 7 3,000.00 3,000.00 21,000.00
7.1.8 4-tool compressor including tools and hoses hrs. 7 2,000.00 2,000.00 14,000.00
7.1.9 10 tonne lorry-mounted crane hrs. 7 5,000.00 5,000.00 35,000.00
7.1.10 750 Kg crane hrs. 7 2,000.00 2,000.00 14,000.00
7.1.11 0.5 m3 dumper hrs. 7 1,000.00 1,000.00 7,000.00
7.1.12 1 m3 dumper hrs. 7 1,500.00 1,500.00 10,500.00
7.1.13 7 m3 tipper lorry hrs. 7 2,000.00 2,000.00 14,000.00
7.1.14 15 m3 lorry hrs. 7 2,000.00 2,000.00 14,000.00
7.1.15 4 wheel drive pick-up or van hrs. 7 500.00 500.00 3,500.00
7.1.16 Vibrating plate compactor hrs. 7 500.00 500.00 3,500.00
7.1.17 8-10 tonne roller hrs. 7 2,000.00 2,000.00 14,000.00
7.1.18 Scaffolding, 10 sqm day 1 2,025.00 2,025.00 2,025.00
7.1.19 5-Ton capacity truck-fare in Dhaka city i/c loading, unloading hrs. 10 456.50 456.50 4,565.00
7.1.20 Concrete mixer machine -1 bag capacity hrs. 6 537.50 537.50 3,225.00
7.1.21 Concrete vibrator-40mm dia hrs. 6 423.00 423.00 2,538.00
7.1.22 Diesel operated 1 cusec pump hrs. 10 505.00 505.00 5,050.00
7.1.23 Electricity operated 1 cusec pump hrs. 8 329.00 329.00 2,632.00
7.1.24 Road cutting Equipment hrs. 8 1,097.00 1,097.00 8,776.00
7.1.25 Backhoe Loader, wheel operated hrs. 5 3,510.00 3,510.00 17,550.00

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 39 of 42
Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh

7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 3 675.00 675.00 2,025.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 3 607.50 607.50 1,822.50
clinker): 50kg bag
7.2.3 White Cement kg 8 54.00 54.00 432.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 0.05 86,400.00 86,400.00 4,320.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 0.05 87,750.00 87,750.00 4,387.50
7.2.6 MS Sheet M Ton 0.05 114,750.00 114,750.00 5,737.50
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 1,000 10,800.00 10,800.00 10,800.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 1,000 12,150.00 12,150.00 12,150.00
7.2.9 Imported Earth m3 3 572.50 572.50 1,717.50
7.2.10 Sand (F.M. 0.8) m3 3 525.00 525.00 1,575.00
7.2.11 Sand (F.M. 1.2) m3 2 810.50 810.50 1,621.00
7.2.12 Sand (F.M. 2.5) m3 2 2,384.00 2,384.00 4,768.00
7.2.13 Viti/Filling Sand m3 3 524.50 524.50 1,573.50

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 40 of 42
Schedule No. 7 - Day Work

Unit Price (BDT)


Nominal
Item Description Unit Total Unit Total Price (BDT)
Quantity Material Labour Equipment
Price
a b c d e f g h=e+f+g i=dxh
7.3 Labor
-
7.3.1 Contract Manager day 1 15,000.00 15,000.00 15,000.00
7.3.2 Office Assistant day 2 500.00 500.00 1,000.00
7.3.3 Contract / Legal Advisor day 1 5,000.00 5,000.00 5,000.00
7.3.4 Financial Advisor day 1 5,000.00 5,000.00 5,000.00
7.3.5 Quantity Engineer day 1 3,000.00 3,000.00 3,000.00
7.3.6 Designer day 1 10,000.00 10,000.00 10,000.00
7.3.7 Field Engineer day 1 3,000.00 3,000.00 3,000.00
7.3.8 Draft Person day 1 2,000.00 2,000.00 2,000.00
7.3.9 Ordinary/casual Labour day 8 600.00 600.00 4,800.00
7.3.10 Skilled labour day 4 945.00 945.00 3,780.00
7.3.11 Head Operator/Ganger day 1 1,080.00 1,080.00 1,080.00
7.3.12 Asstt. Operator/Ganger day 2 945.00 945.00 1,890.00
7.3.13 Head Mason day 1 1,080.00 1,080.00 1,080.00
7.3.14 Mud Operator day 1 945.00 945.00 945.00
7.3.15 Field Supervisor/Manager day 1 3,375.00 3,375.00 3,375.00
7.3.16 Field/Maintenance Engineer day 2 2,700.00 2,700.00 5,400.00
7.3.17 Skilled technician/Plumber/Mason/Steel work Erector/ day 2 800.00 800.00 1,600.00
7.3.18 Semi Skilled technician day 4 700.00 700.00 2,800.00
7.3.19 Site security day 2 600.00 600.00 1,200.00
7.3.20 Driver day 2 1,100.00 1,100.00 2,200.00
7.3.21 Sweeper for Odd Job day 2 1,000.00 1,000.00 2,000.00
7.3.22 Surveyor day 2 1,080.00 1,080.00 2,160.00
7.3.23 Asstt. Surveyor day 4 810.00 810.00 3,240.00
7.3.24 Carpenter

Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 502,380.50

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 41 of 42
Schedule No. 8 - O&M Services

Unit Price (BDT)


Item Description Unit Qty. Total Price (BDT)
Material Labour Equipment Total Unit Price
a b c d e f g h=e+f+g i=dxh
8 O&M Services and Documentation

8.1
One year O&M (2 Loops in Segments 1-5 and in 7-16)
8.1.1 O&M Services in Loop 601 km 0.25 934,330.00 233,582.50
8.1.2 O&M Services in Loop 602 km 5.98 934,330.00 5,587,293.40
6.23
Sub-total 8.1: Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 5,820,875.90

Name of Bidder

Signature of Bidder

2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 42 of 42
Employer’s Cost Estimates10

I: Cost of Package 7

(No. 1: Natun Bazar SLS, No. 2: Banasree SLS,

No. 4: Bijoy Sarani SLS)


Package 7 (1)

Equipment Estimated Cost - No.1 Natunbazar SLS

Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit Rates Amount

Part-A : Mechanical Equipment

Grate interval 25mm,mounting angle 75o


1 Rotary coarse screen Set 2 12,600,000 25,200,000
H=8.75m,N=1.5kW
2 Screw conveyor Q=7.5m3/h, L=10m, N=3kW Set 1 4,200,000 4,200,000

LxBxH=1500x700x800,
3 Slag bucket Set 1 420,000 420,000
Material: SS304
DN1500, H=7.7m
4 Electrical sluice gate Set 1 1,680,000 1,680,000
N=1.5kW
BxH=1.2x1.2,H=7.85m
5 Electrical sluice gate Set 2 1,680,000 3,360,000
N=3kW
BxH=1.2x1.2,H=8.15m
6 Electrical sluice gate Set 2 1,680,000 3,360,000
N=3kW
DN1500,H=5.05m
7 Electrical sluice gate Set 1 1,680,000 1,680,000
N=2kW
BxH=2.5x2.5, H=9.89m
8 Electrical sluice gate Set 1 1,680,000 1,680,000
N=3kW
DN1000,H= 4.65m,
9 Electrical sluice gate Set 2 1,680,000 3,360,000
N=2kW
duty-2, Standby-2,
10 Submersible sewage pump Q=0.926m3/s, H=7.04m,N=90kW Set 4 8,400,000 33,600,000
VFD Control

11 Portable submersible pump Q=55m3/h, H=16m, N=4.2kW Set 2 504,000 1,008,000

12 Pipeline self-control valve/Check Valve DN800 Set 4 1,260,000 5,040,000

13 Pressure balanced Expansion Joint DN800 Set 4 420,000 1,680,000


Gn=10t, Lk=7.6m, height: 18m
14 Overhead crane Set 2 2,520,000 5,040,000
N=16.2kW

15 Axial flow fan Q=9300m3/h, P=190Pa, N=0.75kW Set 2 420,000 840,000

Part-B: Electrical Equipment - -

1 Frequency Converter (VFD) 90kW Pump motor matching frequency Set 4 630,000 2,520,000

Dasherkandi Sewerage Project, Cost Estimate for Package 7 1/13


Equipment Estimated Cost - No.1 Natunbazar SLS

Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit Rates Amount

Part-A : Mechanical Equipment including incoming and


2 HV incoming and outgoing lines cabinet KYN28-12, (H2200xW1500xD800) Set 2 1,150,800 2,301,600
outgoing wire cabinet
3 High-voltage metering cabinet KYN28-12 Set 1 378,000 378,000

4 High-voltage PT cabinet KYN28-12 Set 1 1,150,800 1,150,800

5 Transformer Dry type, SCB10-500kVA, 11kV/.44kV Set 1 1,680,000 1,680,000


including incoming
cabinet, contact cabinet
6 LV incoming and outgoing lines cabinet Set 8 546,000 4,368,000
GCK(2200x1000x800) and outgoing wire
cabinet
Low-voltage capacitance
7 Capacitance compensation cabinet 200Kvar, GCK(2200x800x1000) Set 1 546,000 546,000
compensation cabinet
8 230VDC power supply cabinet 63AH Set 1 546,000 546,000

9 0.44kV generator set 500kW diesel generator Set 1 8,400,000 8,400,000

10 Diesel Storage Tank Set 1 420,000 420,000


SYNC dual power automatic transfer switch board,
11 Dual power conversion cabinet Set 1 546,000 546,000
1600A

Part-C : Automatic Monitoring Control System - -

I Monitoring Equipment - -

Intel core i5, 3G, memory 8G DDR4 2400 MHz,


1 Industrial Personal Computer Set 3 168,000 504,000
Hard disk 1T
2 Workstation According to Intel corei5 processor Set 1 420,000 420,000
Rack server; CPU: Intel Xeon, E5 2600 V4 series;
3 Communication Server Set 1 336,000 336,000
core:16, 3G
4 Exchange 100M/24 interfaces Set 1 84,000 84,000

print speed-not less than 18 pages per minute;


5 Laser Printer Set 1 168,000 168,000
reslution- 600x600dpi; cache >= 8MB; page: A3

6 UPS Power Supply 2kVA/6h Set 1 840,000 840,000

7 Control Console 1910*670*750, Five linkage console Set 1 84,000 84,000

Dasherkandi Sewerage Project, Cost Estimate for Package 7 2/13


Equipment Estimated Cost - No.1 Natunbazar SLS

Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit Rates Amount

8
Part-A Server
: Mechanical cabinet and KVM
Equipment Height 2.2m Set 1 1,680,000 1,680,000

II Software system - -

1 Monitoring management software Set 1 1,680,000 1,680,000

2 Operating system Windows server 2012 Set 1 84,000 84,000

3 Data base SQL server 2012 Set 1 126,000 126,000

III PLC cabinet - -

1 PLC control cabinet minimum S7-400 Set 1 1,260,000 1,260,000

IV Instrumentation - -

1 Electromagnetic Flow Meter Proline Promag L400 Set 1 869,400 869,400

2 Ultrasonic level transmitter Prosonic M FMU 44 Set 3 420,000 1,260,000

3 Ultrasonic level detector Turbimax CUS71D Set 3 420,000 1,260,000

4 Ultrasonic level difference transmitter Prosonic M FMU 44 Set 2 420,000 840,000

5 Ultrasonic level difference detector Turbimax CUS71D Set 2 420,000 840,000

6 H2S Meter E2608-H2S Set 2 420,000 840,000

7 Water pressure monitor PMP51-AA21JA1P Set 1 420,000 420,000


Stainless steel outdoor box (containing distribution
8 600x800x300 Set 8 84,000 672,000
system)
9 Mounting bracket of stainless steel outdoor box ø90x1.2m Set 10 84,000 840,000

10 Mounting bracket with fixing seat of sensor Set 14 84,000 1,176,000

V Video surveillance equipment - -

1 Video computer PRO 3000MT Set 1 168,000 168,000

2 Decoder XTE200G-YC Set 6 25,200 151,200

Dasherkandi Sewerage Project, Cost Estimate for Package 7 3/13


Equipment Estimated Cost - No.1 Natunbazar SLS

Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit Rates Amount

3
Part-A : Mechanical
Line-by-line
Equipment HD monitor LED Set 6 42,000 252,000

4 Constant speed network intelligence dome XT-DL480B Set 6 840,000 5,040,000

5 Lightning protection device of power supply LKX-M220/2/10 Set 6 84,000 504,000

6 Fiber optic transceiver CY-96110SA-2 Pair 6 42,000 252,000

Sum of Equipment L.S 1 137,655,000

7 Installation Cost, 30% of Equipment Price L.S 1 41,296,500 41,296,500

8 Total Sum L.S 1 178,951,500

Dasherkandi Sewerage Project, Cost Estimate for Package 7 4/13


1.Major Equipment
1.1 Lifting Pump Station (Natunbazar)
1.1.1 Mechanical Equipment

a) Submersible Sewage Pumps

S/N Description Unit Specification Remark


Technical
A
Parameters
1 Rated flow m3/hr 3335 0.926m3/sec
2 Rated Pump head m 7
3 Efficiency % 81
4 Actual diameter of impeller mm 616
5 Maximum particle size mm 135
6 Cooling jacket Yes
B Material
Nodular cast iron
1 Pump Case/Impeller
EN-JS1050/AISI 80-55-06
2 Main shaft seal SiC-SiC
3 Secondary shaft seal SiC-Graphite
C Installation
o
1 Maximum ambient temperature C 40
2 Standards of flange DIN
3 Pressure stage PN 10
D Electric Data
1 Rated power kW 110 See Note
2 Rated current A 275
4 Supply frequency Hz 50
5 Rotation speed rpm 495

Dasherkandi Sewerage Project, Cost Estimate for Package 7 5/13


Phase : 3ф
6 Power Supply Rated voltage : 0.4 kV
Frequency : 50Hz
7 Starting method VFD(Variable Frequency Drive)
Maximum number of starts
8 6
per hour
Motor efficiency
% 94
at full load
9 % 94
at 3/4 load
% 93
at 1/2 load
10 Protection class (IEC 34-5) IP68
11 Insulation class (IEC 85) F
E Others
Capacitive sensor detecting
1 Water content sensor with oil
liquid impurity
2 Net weight kg 3900

b) Rotary Coarse Screen

S/N Description Unit Specification


Technical
A
Parameters
1 Width of channel mm 2500
2 Width of screen mm 2400
3 Depth of channel mm 8500
4 Bar spacing mm 25
o
5 Angle of installation 75
6 Unloading height mm 800
7 Flow of passing screen m3/h 1218
8 Power of electric motor kW 1.5
9 Protection class (IEC 34-5) IP65
10 Insulation class (IEC 85) F

Dasherkandi Sewerage Project, Cost Estimate for Package 7 6/13


24-hour continuous operation
11 Work system
intermittent operation
B Material
1 Frame Stainless Steel 304
2 Hood Stainless Steel 304
3 Screen bar Stainless Steel 304
4 Trash rack Stainless Steel 304
5 Drag chain Stainless Steel 304
6 Transmission shaft Stainless Steel 304
7 All fasteners, fittings Stainless Steel 304
8 On-site control box body Stainless Steel 304
C Others
Designed for operation
1 hour ≥ 8000
without faults
The normal service life of the
2 year ≥ 10
complete machine

1.1.2 Electrical Equipment

a) Transformers

S/N Description Unit Specification Remark


1 Type Dry type
2 Rated Power kVA 630
3 Voltage kV 11/04
4 Tap Range % ±2x2.5
5 Number of Phases phase 3
6 Frequency Hz 50
7 Impedance Voltage % 4
8 Vector Group Dyn11
9 Insulation class F
10 No-load Loss W 1510
11 Load loss (75°C) W 5100
Dasherkandi Sewerage Project, Cost Estimate for Package 7 7/13
12 No-load Current % 0.6
13 Protection class IP20

AN/AF(natural air cooling under


14 Cooling Method normal conditions and forced air
cooling under high temperature)

15 Sound level dB less than 50


16 Overall dimensions mm 1380X860X1265
17 Weight kg 2345

b) Diesel Generators

S/N Description Unit Specification Remark


1 Type designation
IEC 34-1, IEC 34-5
Design Standard IEC 34-6, JEC 114
JEC 139
2 Rated voltage V 440/230
3 Rated frequency Hz 50
Rated continuous output at
4 kW 650
generator terminal
5 Rated power factor 0.8
6 Permissible overload, during 1 hour % 10
7 Starting time, maximum sec less than 30
8 Frequency adjusting range % ±5
Frequency regulation accuracy (at
9 % ± 0.25
set load)
10 Voltage adjusting range % ± 10
11 Voltage regulation accuracy % ± 0.5
12 Generator insulation class F
13 Telephone harmonic factor (THF) % less than 2

Dasherkandi Sewerage Project, Cost Estimate for Package 7 8/13


Maximum noise level
14 dB(A) 110
(7m far from the desel, outdoor)

c) Variable Frequency Driver

S/N Description Unit Specification Remark


1 Type designation
IEC 61800-5-1
IEC 61800-3
EN 55011
2 Motor Power kW 110
3 Apparent Power kVA 135
4 Input Voltage Range V 380~415
5 Output frequency Hz 0.1~200
6 Starting Torque & Torque Boost % 150~170
7 Cooling Method Air cooling
8 Protection Class IP54

d) HV Circuit Breaker

S/N Description Unit Specification Remark


1 Type designation Vacuum circuit breaker
2 Rated Voltage kV 12
3 Rated Current A 1250
4 Rated short-circuit breaking current kA 25
5 Frequency Hz 50
Short-time power frequency
6 kV/min 42/1
withstand voltage
7 Lightning impulse withstand voltage kV 75

Dasherkandi Sewerage Project, Cost Estimate for Package 7 9/13


e) Air Circuit Breaker

S/N Description Unit Specification Remark


1 Type designation Air circuit breaker
2 Rated Voltage V 690
3 Rated Current A 2500
4 Rated short-circuit breaking current kA 40
5 Frequency Hz 50

f) Moulded Case Circuit Breaker

S/N Description Unit Specification Remark


1 Type designation Moudle Case Circuit Breaker
2 Rated Voltage V 690
3 Rated Current A 630
4 Rated short-circuit breaking current kA 40
5 Frequency Hz 50

Note:
0.163×1×55.56×7
Pump Output Power= ×1.15=90kW
0.81
90
Motor Rated Power= =95.75kW~110kW
0.94

Dasherkandi Sewerage Project, Cost Estimate for Package 7 10/13


Load Calculation for Natunbazar SLS
NOS of Equipment Equipment capacity Power Load Calculation

total Power Demand


SL.NO. Name installed working power for working Active Reactive Apparent
installed Factor coefficient
number number single power power Power Power
power
nos nos kW kW kW kW kVar kVA

Submersible sewage
1 4 2 110.00 440.00 220.00 0.83 0.95 209.00 140.45 251.81
pump

2 Coarse screen machine 2 2 1.50 3.00 3.00 0.80 0.75 2.25 1.69 2.81

3 Screw conveyor 1 1 3.00 3.00 3.00 0.80 0.75 2.25 1.69 2.81

4 Electric crane 2 2 16.20 32.40 32.40 0.82 0.10 3.24 2.26 3.95

Electrical Sluice
5 2 2 3.00 6.00 6.00 0.80 0.10 0.60 0.45 0.75
gate(rectangle)

Electrical Sluice
6 2 2 3.00 6.00 6.00 0.80 0.10 0.60 0.45 0.75
gate(rectangle)

Electrical Sluice
7 1 1 3.00 3.00 3.00 0.80 0.10 0.30 0.23 0.38
gate(rectangle)

Electrical Sluice
8 1 1 1.50 1.50 1.50 0.80 0.10 0.15 0.11 0.19
gate(circular)

Electrical Sluice
9 1 1 2.00 2.00 2.00 0.80 0.10 0.20 0.15 0.25
gate(circular)

Electrical Sluice
10 2 2 2.00 4.00 4.00 0.80 0.10 0.40 0.30 0.50
gate(circular)

Submersible sewage
11 2 2 4.20 8.40 8.40 0.80 0.20 1.68 1.26 2.10
pump

12 Axial flow fan 2 2 0.75 1.50 1.50 0.80 0.20 0.30 0.23 0.38

14 Maintenance power box 3 1 5.00 15.00 5.00 0.80 0.10 0.50 0.38 0.63

Dasherkandi Sewerage Project, Cost Estimate for Package 7 11/13


15 Power of PLC 1 1 5.00 5.00 5.00 0.80 1.00 5.00 3.75 6.25

16 Lighting+HVAC 1 1 30.00 30.00 30.00 0.90 0.80 24.00 11.62 26.67

17 Consent Power 1 1 5.00 5.00 5.00 0.80 0.50 2.50 1.88 3.13

Total
Sum 565.80 335.80 252.97 166.88 303.34
(kW)

Total 565.80 335.80 252.97 166.88 303.34


multiply simultaneity
factor KSp=0.85or 0.80 215.02 158.54 267.15
KSq=0.95
reactive power
-100.00 -96.00
compensation
total after compensation 0.96 215.02 58.54 222.85
transformer loss
DPb=0.01Sjs 2.23
DQb=0.05Sjs 11.14
total 565.80 335.80 0.95 0.65 217.25 69.68 228.15

Dasherkandi Sewerage Project, Cost Estimate for Package 7 12/13


Natunbazar SLS- HVAC and Lighting Load Calculation
Length Width Area Lighting HVAC Total Power
Utility Name
(m) (m) (m2) (kW) (kW) (kW)
Coarse Screen Room 13.65 7.94 108.38 1.63 1.63
Lifting Pump Station Room 9.00 10.06 90.54 1.36 1.36
Electric Room 8.68 4.65 40.36 0.61 4.04 4.64
Toilet 1.70 3.56 6.05 0.09 0.61 0.70
Prayer Room 1.86 4.65 8.65 0.13 0.86 0.99
Office Room 2.75 4.65 12.79 0.19 1.28 1.47
Control Room 5.62 4.65 26.13 0.39 2.61 3.01
Transformer+Generator+Fuel
12.40 4.00 63.60 0.95 6.36 7.31
Storage Room
Total 5.35 15.76 21.11

Note:

■For lighting-15W/m2
■For HVAC-100W/m2

Dasherkandi Sewerage Project, Cost Estimate for Package 7 13/13


Package 7 (2)
Equipment Estimated Cost - No.2 Banasree SLS
Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit rate Amount
Part-A : Mechanical Equipment

Grate interval 25mm,mounting angle 75o


1 Rotary coarse screen Set 1 12,600,000.00 12,600,000.00
H=8.605m,N=1.5kW
2 Screw conveyor Q=5m3/h, L=2m, N=1.5kW Set 1 4,200,000.00 4,200,000.00

LxBxH=1500x700x800,
3 Slag bucket Set 1 420,000.00 420,000.00
Material: SS304
DN800, H=7.905m
4 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=1.5kW
BxH=1x1,H=7.9m
5 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=3kW
BxH=1x1,H=7.6m
6 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=3kW
DN800,H=4.458m
7 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=2kW
DN500,H= 4.65m,
8 Electrical sluice gate Set 2 1,680,000.00 3,360,000.00
N=2kW
duty-2, Standby-1,
9 Submersible sewage pump Q=0.202m3/s, H=5.5m,N=22kW Set 3 3,360,000.00 10,080,000.00
VFD Control

10 Portable submersible pump Q=55m3/h, H=16m, N=4.2kW Set 2 504,000.00 1,008,000.00

Gn=10t, Lk=7.6m, height: 18m


11 Overhead crane Set 1 2,520,000.00 2,520,000.00
N=16.2kW

12 Overhead crane Gn=5t, N=7.85kW Set 1 1,680,000.00 1,680,000.00

13 Check valve DN600 Set 3 1,260,000.00 3,780,000.00

14 Pressure balanced expansion joint DN600 Set 3 420,000.00 1,260,000.00

15 Axial flow fan Q=2000m3/h, P=190Pa, N=0.75kW Set 2 420,000.00 840,000.00

Part-B: Electrical Equipment

1 Frequency Converter (VFD) 22kW Pump motor matching frequency Set 3 336,000 1,008,000

including incoming and


2 HV incoming and outgoing lines cabinet KYN28-12, (H2200xW800xD1000) Set 2 1,260,000 2,520,000
outgoing wire cabinet

3 High-voltage metering cabinet KYN28-12 Set 1 378,000 378,000

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 1 of 12


Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit rate Amount
4 High-voltage PT cabinet KYN28-12 Set 1 1,260,000 1,260,000

5 Transformer Dry type, SCB10-160kVA, 11kV/.44kV Set 1 672,000 672,000


including incoming cabinet,
6 LV incoming and outgoing lines cabinet GCK(2200x1000x800) Set 7 252,000 1,764,000 contact cabinet and outgoing
wire cabinet
Low-voltage capacitance
7 Capacitance compensation cabinet 40Kvar, GCK(2200x800x1000) Set 1 252,000 252,000
compensation cabinet
8 230VDC power supply cabinet 63AH Set 1 252,000 252,000

9 0.44kV generator set 160kW diesel generator Set 1 2,940,000 2,940,000

10 Diesel Storage Tank Set 1 252,000 252,000

SYNC dual power automatic transfer switch board,


11 Dual power conversion cabinet Set 1 252,000 252,000
1600A

Part-C : Automatic Monitoring Control System

I Monitoring Equipment
Intel core i5, 3G, memory 8G DDR4 2400 MHz, Hard
1 Industrial Personal Computer Set 3 168,000 504,000
disk 1T
2 Workstation According to Intel corei5 processor Set 1 420,000 420,000
Rack server; CPU: Intel Xeon, E5 2600 V4 series;
3 Communication Server Set 1 336,000 336,000
core:16, 3G
4 Exchange 100M/24 interfaces Set 1 84,000 84,000

print speed-not less than 18 pages per minute; reslution-


5 Laser Printer Set 1 168,000 168,000
600x600dpi; cache >= 8MB; page: A3

6 UPS Power Supply 2kVA/6h Set 1 840,000 840,000

7 Control Console 1910*670*750, Five linkage console Set 1 84,000 84,000

8 Server cabinet and KVM Height 2.2m Set 1 1,680,000 1,680,000

II Software system - -

1 Monitoring management software Set 1 1,680,000 1,680,000

2 Operating system Windows server 2012 Set 1 84,000 84,000

3 Data base SQL server 2012 Set 1 126,000 126,000

III PLC cabinet - -

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 2 of 12


Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit rate Amount
1 PLC control cabinet minimum S7-400 Set 1 1,260,000 1,260,000

IV Instrumentation - -

1 Electromagnetic Flow Meter Proline Promag L400 Set 1 869,400 869,400

2 Ultrasonic level transmitter Prosonic M FMU 44 Set 3 420,000 1,260,000

3 Ultrasonic level detector Turbimax CUS71D Set 3 420,000 1,260,000

4 Ultrasonic level difference transmitter Prosonic M FMU 44 Set 1 420,000 420,000

5 Ultrasonic level difference detector Turbimax CUS71D Set 1 420,000 420,000

6 H2S Meter E2608-H2S Set 4 420,000 1,680,000

7 Water pressure monitor PMP51-AA21JA1P Set 1 420,000 420,000


Stainless steel outdoor box (containing
8 600x800x300 Set 8 84,000 672,000
distribution system)
Mounting bracket of stainless steel outdoor
9 ø90x1.2m Set 10 84,000 840,000
box
10 Mounting bracket with fixing seat of sensor Set 14 84,000 1,176,000

V Video surveillance equipment - -

1 Video computer PRO 3000MT Set 1 168,000 168,000

2 Decoder XTE200G-YC Set 6 25,200 151,200

3 Line-by-line HD monitor LED Set 6 42,000 252,000

4 Constant speed network intelligence dome XT-DL480B Set 6 840,000 5,040,000

5 Lightning protection device of power supply LKX-M220/2/10 Set 6 84,000 504,000

6 Fiber optic transceiver CY-96110SA-2 Pair 6 42,000 252,000

Sum of Equipment L.S 1 82,416,600

7 Installation Cost, 30% of Equipment Price L.S 1 24,724,980 24,724,980

8 Total Sum L.S 1 107,141,580

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 3 of 12


Major Equipment Specification
No.2: Banasree SLS
1.1 Mechanical Equipment

a) Submersible Sewage Pumps

S/N Description Unit Specification Remark


Technical
A
Parameters
1 Rated flow m3/hr 727.2 0.202m3/sec
2 Rated Pump head m 5.5
3 Efficiency % 70
4 Actual diameter of impeller mm
5 Maximum particle size mm
6 Cooling jacket Yes
B Material
Nodular cast iron
1 Pump Case/Impeller
EN-JS1050/AISI 80-55-06
2 Main shaft seal SiC-SiC
3 Secondary shaft seal SiC-Graphite
C Installation
o
1 Maximum ambient temperature C 40
2 Standards of flange DIN
3 Pressure stage PN 10
D Electric Data
1 Rated power kW 18.5
2 Rated current A
4 Supply frequency Hz 50
5 Rotation speed rpm 495

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 4 of 12


Phase : 3ф
6 Power Supply Rated voltage : 0.4 kV
Frequency : 50Hz
7 Starting method VFD(Variable Frequency Drive)
Maximum number of starts
8 6
per hour
Motor efficiency
% 94
at full load
9 % 94
at 3/4 load
% 93
at 1/2 load
10 Protection class (IEC 34-5) IP68
11 Insulation class (IEC 85) F
E Others
Capacitive sensor detecting
1 Water content sensor with oil
liquid impurity
2 Net weight kg 3900

b) Rotary Coarse Screen

S/N Description Unit Specification


Technical
A
Parameters
1 Width of channel mm 1500
2 Width of screen mm 1400
3 Depth of channel mm 8600
4 Bar spacing mm 25
o
5 Angle of installation 75
6 Unloading height mm 800
7 Flow of passing screen m3/h 1218
8 Power of electric motor kW 1.5
Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 5 of 12
9 Protection class (IEC 34-5) IP65
10 Insulation class (IEC 85) F
24-hour continuous operation
11 Work system
intermittent operation
B Material
1 Frame Stainless Steel 304
2 Hood Stainless Steel 304
3 Screen bar Stainless Steel 304
4 Trash rack Stainless Steel 304
5 Drag chain Stainless Steel 304
6 Transmission shaft Stainless Steel 304
7 All fasteners, fittings Stainless Steel 304
8 On-site control box body Stainless Steel 304
C Others
Designed for operation
1 hour ≥ 8000
without faults
The normal service life of the
2 year ≥ 10
complete machine

1.2 Electrical Equipment

a) Transformers

S/N Description Unit Specification Remark


1 Type Dry type
2 Rated Power kVA 500
3 Voltage kV 11/04
4 Tap Range % ±2x2.5
5 Number of Phases phase 3
6 Frequency Hz 50
7 Impedance Voltage % 4
8 Vector Group Dyn11
9 Insulation class F
Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 6 of 12
10 No-load Loss W 1510
11 Load loss (75°C) W 5100
12 No-load Current % 0.6
13 Protection class IP20

AN/AF(natural air cooling under


14 Cooling Method normal conditions and forced air
cooling under high temperature)

15 Sound level dB less than 50


16 Overall dimensions mm 1380X860X1265
17 Weight kg 2345

b) Diesel Generators

S/N Description Unit Specification Remark


1 Type designation
IEC 34-1, IEC 34-5
Design Standard IEC 34-6, JEC 114
JEC 139
2 Rated voltage V 440/230
3 Rated frequency Hz 50
Rated continuous output at
4 kW 500
generator terminal
5 Rated power factor 0.8
6 Permissible overload, during 1 hour % 10
7 Starting time, maximum sec less than 30
8 Frequency adjusting range % ±5
Frequency regulation accuracy (at
9 % ± 0.25
set load)
10 Voltage adjusting range % ± 10
11 Voltage regulation accuracy % ± 0.5

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 7 of 12


12 Generator insulation class F
13 Telephone harmonic factor (THF) % less than 2
Maximum noise level
14 dB(A) 110
(7m far from the desel, outdoor)

c) Variable Frequency Driver

S/N Description Unit Specification Remark


1 Type designation
IEC 61800-5-1
IEC 61800-3
EN 55011
2 Motor Power kW 90
3 Apparent Power kVA 113
4 Input Voltage Range V 380~415
5 Output frequency Hz 0.1~200
6 Starting Torque & Torque Boost % 150~170
7 Cooling Method Air cooling
8 Protection Class IP54

d) HV Circuit Breaker

S/N Description Unit Specification Remark


1 Type designation Vacuum circuit breaker
2 Rated Voltage kV 12
3 Rated Current A 1250
4 Rated short-circuit breaking current kA 25
5 Frequency Hz 50
Short-time power frequency
6 kV/min 42/1
withstand voltage

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 8 of 12


7 Lightning impulse withstand voltage kV 75

e) Air Circuit Breaker

S/N Description Unit Specification Remark


1 Type designation Air circuit breaker
2 Rated Voltage V 690
3 Rated Current A 2500
4 Rated short-circuit breaking current kA 40
5 Frequency Hz 50

f) Moulded Case Circuit Breaker

S/N Description Unit Specification Remark


1 Type designation Moudle Case Circuit Breaker
2 Rated Voltage V 690
3 Rated Current A 630
4 Rated short-circuit breaking current kA 40
5 Frequency Hz 50

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 9 of 12


Electrical Power Load List & Calculation
No.2: Banasree SLS
NOS of Equipment Equipment capacity Power Load Calculation

total Power Demand


SL.NO. Name installed working power for working Active Reactive Apparent
installed Factor coefficient
number number single power power Power Power
power
nos nos kW kW kW kW kVar kVA

Submersible sewage
1 3 2 90.00 270.00 180.00 0.83 0.95 171.00 114.91 206.02
pump

2 Coarse screen machine 1 2 1.50 1.50 3.00 0.80 0.75 2.25 1.69 2.81

3 Screw conveyor 1 1 3.00 3.00 3.00 0.80 0.75 2.25 1.69 2.81

4 Electric crane 2 2 16.20 32.40 32.40 0.82 0.10 3.24 2.26 3.95

Electrical Sluice
5 2 2 3.00 6.00 6.00 0.80 0.10 0.60 0.45 0.75
gate(rectangle)

Electrical Sluice
6 2 2 3.00 6.00 6.00 0.80 0.10 0.60 0.45 0.75
gate(rectangle)

Electrical Sluice
7 1 1 3.00 3.00 3.00 0.80 0.10 0.30 0.23 0.38
gate(rectangle)

Electrical Sluice
8 1 1 1.50 1.50 1.50 0.80 0.10 0.15 0.11 0.19
gate(circular)

Electrical Sluice
9 1 1 2.00 2.00 2.00 0.80 0.10 0.20 0.15 0.25
gate(circular)

Electrical Sluice
10 2 2 2.00 4.00 4.00 0.80 0.10 0.40 0.30 0.50
gate(circular)

Submersible sewage
11 2 2 4.20 8.40 8.40 0.80 0.20 1.68 1.26 2.10
pump

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 10 of 12


12 Axial flow fan 2 2 0.75 1.50 1.50 0.80 0.20 0.30 0.23 0.38

14 Maintenance power box 3 1 5.00 15.00 5.00 0.80 0.10 0.50 0.38 0.63

15 Power of PLC 1 1 5.00 5.00 5.00 0.80 1.00 5.00 3.75 6.25

16 Lighting 2 2 5.00 10.00 10.00 0.90 0.80 8.00 3.87 8.89

17 HVAC 2 2 10.00 20.00 20.00 0.90 0.80 16.00 7.75 17.78

18 Potable Water Pump 1 1 3.00 3.00 3.00 0.80 0.80 2.40 1.80 3.00

18 Spare 1 1 5.00 5.00 5.00 0.80 0.50 2.50 1.88 3.13

Total
Sum 397.30 298.80 217.37 143.15 260.55
(kW)

Total 397.30 298.80 217.37 143.15 260.55


multiply simultaneity
factor KSp=0.85or 0.81 184.76 135.99 229.41
KSq=0.95
reactive power
-100.00
compensation
total after compensation 0.98 184.76 35.99 188.24
transformer loss
DPb=0.01Sjs 1.88
DQb=0.05Sjs 9.41
total 397.30 298.80 0.97 0.62 186.65 45.40 192.09

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 11 of 12


HVAC and Lighting Load Calculation
No.2: Banasree SLS
Length Width Area Lighting HVAC Total Power
Sl. No. Utility Name
(m) (m) (m2) (kW) (kW) (kW)
1 Coarse Screen Room 7.50 1.35 10.09 0.15 0.15
2 Lifting Pump Station Room 9.00 7.09 63.81 0.96 0.96
3 Electric Room 8.68 4.65 40.36 0.61 4.84 5.45
4 Toilet 1.70 3.56 6.05 0.09 0.61 0.70
5 Prayer Room 1.86 4.65 8.65 0.13 0.86 0.99
6 Office Room 2.75 4.65 12.79 0.19 1.28 1.47
7 Control Room 5.62 4.65 26.13 0.39 2.61 3.01
Transformer+Generator+Fuel
8 12.40 4.00 63.60 0.95 7.63 8.59
Storage Room
9 Storage Building 7.00 4.00 35.20 0.53 0.53
10 Corridor 10.24 2.00 20.48 0.31 0.31
11 Street 1.00 1.00
Total 5.31 17.84 23.15

Note:
2
■For lighting-15W/m
2
■For HVAC-100W/m
2
■For Electric Room, Transformer & Generator HVAC-120W/m

Dasherkandi Sewerage Project, Cost Estimate for Package 7 Page 12 of 12


Package 7 (3)
Equipment Estimated Cost - No.4 Bijoy Sarani SLS

Total BDT Remarks


S.No Items Main Specification Unit
Quantity Unit rate Total amount

Part-A : Mechanical Equipment

1 Rotary coarse screen Grate interval 25mm,mounting angle 75o Set 1 12,600,000.00 12,600,000.00
H=8.540m,N=1.5kW
3
2 Screw conveyor Q=5m /h, L=2m, N=1.5kW Set 1 4,200,000.00 4,200,000.00

LxBxH=1500x700x800,
3 Slag bucket Set 1 420,000.00 420,000.00
Material: SS304
DN600, H=7.940m
4 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=1.5kW
BxH=1x1,H=7.74m
5 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=3kW
BxH=1x1,H=8.54m
6 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=3kW
DN600,H=6m
7 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=2kW

8 Electrical sluice gate DN500,H=5.05m,N=2kW Set 2 1,680,000.00 3,360,000.00


duty-1, Standby-1,
8 Submersible sewage pump Q=0.19m3/s, H=3m,N=11kW Set 2 1,680,000.00 3,360,000.00 VFD Control

9 Portable submersible pump Q=55m3/h, H=16m, N=4.2kW Set 2 504,000.00 1,008,000.00

10 Check valve DN600 Set 2 1,260,000.00 2,520,000.00

11 Pressure balanced expansion joint DN600 Set 2 420,000.00 840,000.00

Gn=5t, Lk=7.6m, height: 18m


10 Overhead crane Set 2 1,680,000.00 3,360,000.00
N=7.85kW
3
12 Axial flow fan Q=2000m /h, P=190Pa, N=0.75kW Set 2 420,000.00 840,000.00

Part-B: Electrical Equipment

1 Frequency Converter (VFD) 11kW Pump motor matching frequency Set 2 252,000 504,000
including incoming and
2 HV incoming and outgoing lines cabinet KYN28-12, (H2200xW800xD1000) Set 2 1,092,000 2,184,000
outgoing wire cabinet

3 High-voltage metering cabinet KYN28-12 Set 1 378,000 378,000

Dasherkandi Sewerage Project, Cost Estimate for Package 7 1/12


Total BDT Remarks
S.No Items Main Specification Unit
Quantity Unit rate Total amount

4 High-voltage PT cabinet KYN28-12 Set 1 1,092,000 1,092,000

5 Transformer Dry type, SCB10-80kVA, 11kV/.44kV Set 1 378,000 378,000


including incoming
GCK(2200x800x800)-4 cabinet, contact cabinet
6 LV incoming and outgoing lines cabinet Set 6 210,000 1,260,000
GCK(2200x1000x800)-4 and outgoing wire
cabinet
Low-voltage
7 Capacitance compensation cabinet 20Kvar, GCK(2200x800x1000) Set 1 210,000 210,000 capacitance
compensation cabinet
8 230VDC power supply cabinet 63AH Set 1 210,000 210,000

9 0.44kV generator set 80kW diesel generator Set 1 2,352,000 2,352,000

10 Diesel Storage Tank Set 1 210,000 210,000

SYNC dual power automatic transfer switch board,


11 Dual power conversion cabinet Set 1 210,000 210,000
1600A

Part-C : Automatic Monitoring Control System

I Monitoring Equipment
Intel core i5, 3G, memory 8G DDR4 2400 MHz, Hard
1 Industrial Personal Computer Set 3 168,000 504,000
disk 1T
2 Workstation According to Intel corei5 processor Set 1 420,000 420,000
Rack server; CPU: Intel Xeon, E5 2600 V4 series;
3 Communication Server Set 1 336,000 336,000
core:16, 3G
4 Exchange 100M/24 interfaces Set 1 84,000 84,000

print speed-not less than 18 pages per minute; reslution-


5 Laser Printer Set 1 168,000 168,000
600x600dpi; cache >= 8MB; page: A3

6 UPS Power Supply 2kVA/6h Set 1 840,000 840,000

7 Control Console 1910*670*750, Five linkage console Set 1 84,000 84,000

8 Server cabinet and KVM Height 2.2m Set 1 1,680,000 1,680,000

II Software system - -

1 Monitoring management software Set 1 1,680,000 1,680,000

2 Operating system Windows server 2012 Set 1 84,000 84,000

Dasherkandi Sewerage Project, Cost Estimate for Package 7 2/12


Total BDT Remarks
S.No Items Main Specification Unit
Quantity Unit rate Total amount

3 Data base SQL server 2012 Set 1 126,000 126,000

III PLC cabinet - -

1 PLC control cabinet minimum S7-400 Set 1 1,260,000 1,260,000

IV Instrumentation - -

1 Electromagnetic Flow Meter Proline Promag L400 Set 1 869,400 869,400

2 Ultrasonic level transmitter Prosonic M FMU 44 Set 3 420,000 1,260,000

3 Ultrasonic level detector Turbimax CUS71D Set 3 420,000 1,260,000

4 Ultrasonic level difference transmitter Prosonic M FMU 44 Set 1 420,000 420,000

5 Ultrasonic level difference detector Turbimax CUS71D Set 1 420,000 420,000

6 H2S Meter E2608-H2S Set 1 420,000 420,000

7 Water pressure monitor PMP51-AA21JA1P Set 1 420,000 420,000


Stainless steel outdoor box (containing
8 600x800x300 Set 8 84,000 672,000
distribution system)
Mounting bracket of stainless steel outdoor
9 ø90x1.2m Set 10 84,000 840,000
box
10 Mounting bracket with fixing seat of sensor Set 14 84,000 1,176,000

V Video surveillance equipment - -

1 Video computer PRO 3000MT Set 1 168,000 168,000

2 Decoder XTE200G-YC Set 6 25,200 151,200

3 Line-by-line HD monitor LED Set 6 42,000 252,000

4 Constant speed network intelligence dome XT-DL480B Set 6 840,000 5,040,000

5 Lightning protection device of power supply LKX-M220/2/10 Set 6 84,000 504,000

6 Fiber optic transceiver CY-96110SA-2 Pair 6 42,000 252,000

Sum of Equipment L.S 1 69,354,600

7 Installation Cost, 30% of Equipment Price L.S 1 20,806,380 20,806,380

8 Total Sum L.S 1 90,160,980

Dasherkandi Sewerage Project, Cost Estimate for Package 7 3/12


Major Equipment Specification
No. 4: Bijoy Sarani SLS
1.1 Mechanical Equipment

a) Submersible Sewage Pumps

S/N Description Unit Specification Remark


Technical
A
Parameters
1 Rated flow m3/hr 698.4 0.194m3/sec
2 Rated Pump head m 3
3 Efficiency % 65
4 Actual diameter of impeller mm
5 Maximum particle size mm
6 Cooling jacket Yes
B Material
Nodular cast iron
1 Pump Case/Impeller
EN-JS1050/AISI 80-55-06
2 Main shaft seal SiC-SiC
3 Secondary shaft seal SiC-Graphite
C Installation
o
1 Maximum ambient temperature C 40
2 Standards of flange DIN
3 Pressure stage PN 10
D Electric Data
1 Rated power kW 11 See Note
2 Rated current A
4 Supply frequency Hz 50
5 Rotation speed rpm 495

Dasherkandi Sewerage Project, Cost Estimate for Package 7 4/12


Phase : 3ф
6 Power Supply Rated voltage : 0.4 kV
Frequency : 50Hz
7 Starting method VFD(Variable Frequency Drive)
Maximum number of starts
8 6
per hour
Motor efficiency
% 94
at full load
9 % 94
at 3/4 load
% 93
at 1/2 load
10 Protection class (IEC 34-5) IP68
11 Insulation class (IEC 85) F
E Others
Capacitive sensor detecting
1 Water content sensor with oil
liquid impurity
2 Net weight kg 3900

b) Rotary Coarse Screen

S/N Description Unit Specification


Technical
A
Parameters
1 Width of channel mm 1500
2 Width of screen mm 1400
3 Depth of channel mm 8600
4 Bar spacing mm 25
o
5 Angle of installation 75
6 Unloading height mm 800
7 Flow of passing screen m3/h 1218
Dasherkandi Sewerage Project, Cost Estimate for Package 7 5/12
8 Power of electric motor kW 1.5
9 Protection class (IEC 34-5) IP65
10 Insulation class (IEC 85) F
24-hour continuous operation
11 Work system
intermittent operation
B Material
1 Frame Stainless Steel 304
2 Hood Stainless Steel 304
3 Screen bar Stainless Steel 304
4 Trash rack Stainless Steel 304
5 Drag chain Stainless Steel 304
6 Transmission shaft Stainless Steel 304
7 All fasteners, fittings Stainless Steel 304
8 On-site control box body Stainless Steel 304
C Others
Designed for operation
1 hour ≥ 8000
without faults
The normal service life of the
2 year ≥ 10
complete machine

1.2 Electrical Equipment

a) Transformers

S/N Description Unit Specification Remark


1 Type Dry type
2 Rated Power kVA 80
3 Voltage kV 11/04
4 Tap Range % ±2x2.5
5 Number of Phases phase 3
6 Frequency Hz 50
7 Impedance Voltage % 4
8 Vector Group Dyn11
Dasherkandi Sewerage Project, Cost Estimate for Package 7 6/12
9 Insulation class F
10 No-load Loss W 1510
11 Load loss (75°C) W 5100
12 No-load Current % 0.6
13 Protection class IP20

AN/AF(natural air cooling under


14 Cooling Method normal conditions and forced air
cooling under high temperature)

15 Sound level dB less than 50


16 Overall dimensions mm 1380X860X1265
17 Weight kg 2345

b) Diesel Generators

S/N Description Unit Specification Remark


1 Type designation
IEC 34-1, IEC 34-5
Design Standard IEC 34-6, JEC 114
JEC 139
2 Rated voltage V 440/230
3 Rated frequency Hz 50
Rated continuous output at
4 kW 80
generator terminal
5 Rated power factor 0.8
6 Permissible overload, during 1 hour % 10
7 Starting time, maximum sec less than 30
8 Frequency adjusting range % ±5
Frequency regulation accuracy (at
9 % ± 0.25
set load)
10 Voltage adjusting range % ± 10

Dasherkandi Sewerage Project, Cost Estimate for Package 7 7/12


11 Voltage regulation accuracy % ± 0.5
12 Generator insulation class F
13 Telephone harmonic factor (THF) % less than 2

Maximum noise level


14 dB(A) 110
(7m far from the desel, outdoor)

c) Variable Frequency Driver

S/N Description Unit Specification Remark


1 Type designation
IEC 61800-5-1
IEC 61800-3
EN 55011
2 Motor Power kW 90
3 Apparent Power kVA 113
4 Input Voltage Range V 380~415
5 Output frequency Hz 0.1~200
6 Starting Torque & Torque Boost % 150~170
7 Cooling Method Air cooling
8 Protection Class IP54

d) HV Circuit Breaker

S/N Description Unit Specification Remark


1 Type designation Vacuum circuit breaker
2 Rated Voltage kV 12
3 Rated Current A 1250
4 Rated short-circuit breaking current kA 25

Dasherkandi Sewerage Project, Cost Estimate for Package 7 8/12


5 Frequency Hz 50
Short-time power frequency
6 kV/min 42/1
withstand voltage
7 Lightning impulse withstand voltage kV 75

e) Air Circuit Breaker

S/N Description Unit Specification Remark


1 Type designation Air circuit breaker
2 Rated Voltage V 690
3 Rated Current A 2500
4 Rated short-circuit breaking current kA 40
5 Frequency Hz 50

f) Moulded Case Circuit Breaker

S/N Description Unit Specification Remark


1 Type designation Moudle Case Circuit Breaker
2 Rated Voltage V 690
3 Rated Current A 630
4 Rated short-circuit breaking current kA 40
5 Frequency Hz 50
Note:
0.163×1×11.64×3
Pump Output Power= ×1.15=10.07kW
0.65

Dasherkandi Sewerage Project, Cost Estimate for Package 7 9/12


Electrical Power Load List & Calculation
No.4: Bijoysarani SLS
NOS of Equipment Equipment capacity Power Load Calculation

total Power Demand


SL.NO. Name installed working power for working Active Reactive Apparent
installed Factor coefficient
number number single power power Power Power
power
nos nos kW kW kW kW kVar kVA

Submersible sewage
1 2 1 11.00 22.00 11.00 0.83 0.95 10.45 7.02 12.59
pump

2 Coarse screen machine 1 1 1.50 1.50 1.50 0.80 0.75 1.13 0.84 1.41

3 Screw conveyor 1 1 1.50 1.50 1.50 0.80 0.75 1.13 0.84 1.41

4 Electric crane 2 2 7.85 15.70 15.70 0.82 0.10 1.57 1.10 1.91

Electrical Sluice
5 1 1 3.00 3.00 3.00 0.80 0.10 0.30 0.23 0.38
gate(rectangle)

Electrical Sluice
6 1 1 3.00 3.00 3.00 0.80 0.10 0.30 0.23 0.38
gate(rectangle)

Electrical Sluice
7 1 1 1.50 1.50 1.50 0.80 0.10 0.15 0.11 0.19
gate(circular)

Electrical Sluice
8 1 1 2.00 2.00 2.00 0.80 0.10 0.20 0.15 0.25
gate(circular)

Submersible sewage
9 2 2 4.20 8.40 8.40 0.80 0.20 1.68 1.26 2.10
pump

10 Axial flow fan 2 2 0.75 1.50 1.50 0.80 0.20 0.30 0.23 0.38

11 Maintenance power box 3 1 5.00 15.00 5.00 0.80 0.10 0.50 0.38 0.63

Dasherkandi Sewerage Project, Cost Estimate for Package 7 10/12


12 Power of PLC 1 1 5.00 5.00 5.00 0.80 1.00 5.00 3.75 6.25

13 Lighting 2 2 5.00 10.00 10.00 0.90 0.80 8.00 3.87 8.89

14 HVAC 2 2 10.00 20.00 20.00 0.90 0.80 16.00 7.75 17.78

15 Potable Water Pump 1 1 3.00 3.00 3.00 0.80 0.80 2.40 1.80 3.00

16 Spare 1 1 5.00 5.00 5.00 0.80 0.50 2.50 1.88 3.13

Total
Sum 118.10 97.10 51.60 31.43 60.65
(kW)

Total 118.10 97.10 51.60 31.43 60.65


multiply simultaneity
factor KSp=0.85or 0.83 43.86 29.86 53.06
KSq=0.95
reactive power
-20.00
compensation
total after compensation 0.98 43.86 9.86 44.95
transformer loss
DPb=0.01Sjs 0.45
DQb=0.05Sjs 2.25
total 118.10 97.10 0.96 0.46 44.31 12.10 45.93

Dasherkandi Sewerage Project, Cost Estimate for Package 7 11/12


HVAC and Lighting Load Calculation
No.4: Bijoy Sarani SLS
Length Width Area Lighting HVAC Total Power
Sl. No. Utility Name
(m) (m) (m2) (kW) (kW) (kW)
1 Coarse Screen Room 13.65 7.94 108.38 1.63 1.63
2 Lifting Pump Station Room 9.00 10.06 90.54 1.36 1.36
3 Electric Room 8.68 4.65 40.36 0.61 4.84 5.45
4 Toilet 1.70 3.56 6.05 0.09 0.61 0.70
5 Prayer Room 1.86 4.65 8.65 0.13 0.86 0.99
6 Office Room 2.75 4.65 12.79 0.19 1.28 1.47
7 Control Room 5.62 4.65 26.13 0.39 2.61 3.01
Transformer+Generator+Fuel
8 12.40 4.00 63.60 0.95 7.63 8.59
Storage Room
9 Storage Building 7.00 4.00 35.20 0.53 0.53
10 Corridor 10.24 2.00 20.48 0.31 0.31
11 Street 1.00 1.00
Total 7.18 17.84 25.02

Note:
2
■For lighting-15W/m
2
■For HVAC-100W/m
2
■For Electric Room, Transformer & Generator HVAC-120W/m

Dasherkandi Sewerage Project, Cost Estimate for Package 7 12/12


Employer’s Cost Estimates11

J: Cost of Package 8

(Gulshan and Banani including Gulshan SLS & Tejgaon SLS, designed

by IWM)
Package - 08 (1)
Gulshan

Grand Summary

General Summary Page Amount (BDT) Remarks


a b c d
Bill No. 1: General Items 45,397,678
Bill No. 2: Procurement and Construction of Sewers 2,088,259,003

Bill No. 3: Gravity Sewer Manholes, Air valve Chamber; Wash out
135,089,276
valve Chamber and Discharge Chamber

Bill No. 4: Site Cleaning & Temporary Road Reinstatement 47,043,853


Bill No. 5: Tejgaon SLS – Civil Works 143,782,809
Bill No. 6: Tejgaon SLS – Mechanical, Electrical and Generator
160,000,000
Works
—etc.—
Subtotal of Bills (A) 2,619,572,618
Total for Daywork (B) 19,471,388
Specified Provisional Sums included in subtotal of bills (C) 136,063,533
Total of Bills Plus Provisional Sums (A + B + C) (D) 2,775,107,538
Add Provisional Sum for Contingency Allowance (10% of D) (E) 277,510,754

Bid Price (D + E) (Carried forward to Form of Bid) (F) 3,052,618,292

USD (million) 35.91

Dasherkandi Sewerage Project, Cost Estimate for Package 8 1 of 25


Bill No. 1: General Items

Item Unit Price Total Price


Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
Performance Security and Advance Payment
101 L.S. 1 1,259,921 1,259,921
Guarantee.

Road restoration charges payable to road owning


102 L.S. 1 1,439,909 1,439,909
agencies

103 Insurances and Bonds L.S. 1 15,119,048 15,119,048

Preparation of Construction Health and Safety


104 L.S. 1 1,439,909 1,439,909
Plan
Preparation of Contractor’s Quality Assurance
105 L.S. 1 3,779,762 3,779,762
and Control Plan
106 Preparation of Environmental Management Plan L.S. 1 1,439,909 1,439,909

107 Preparation of Traffic Management Plan L.S. 1 1,439,909 1,439,909

Provision for erection, operation, maintenance


and removal of Contractor’s accommodation,
108 equipment and site facilities such as providing L.S. 1 3,779,762 3,779,762
furniture, first aid box, safety helmet,
consumables, stationary etc

Provision for erection, operation, maintenance


and removal of the Engineer's accommodation,
109 equipment and site facilities such as providing L.S. 1 1,439,909 1,439,909
furniture, first aid box, safety helmet,
consumables, stationary etc.
Provision, operation and maintenance of the
110 L.S. 1 1,439,909 1,439,909
Engineer’s transportation

Dasherkandi Sewerage Project, Cost Estimate for Package 8 2 of 25


Item Unit Price Total Price
Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
Provision, erection and removal of Contractor’s
111 L.S. 1 1,439,909 1,439,909
Signboards

112 CCTV inspection of the completed works L.S. 1 8,500,000 8,500,000

Additional testing of materials as instructed by


113 p.s. 1 1,439,909 1,439,909
the Engineer

Additional Record photographs as instructed by


114 p.s. 1 1,439,909 1,439,909
the Engineer
Total for Bill No. 1
45,397,678
(carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 3 of 25


Bill No. 2: Procurement and Construction of Sewers

Item Unit Price Total Price


Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
Earth work in excavation in in/c. Pucca road cutting with
dismetting hard rock, Bituminous pavement, solling, herring bone
bond, etc. lead & lift from trenches of through all kinds of soil and
road pavements to the required depth, width & proper gradient
from the preparation of foundation bed for placing of foundation
concrete or sand cushion as the case may be for pipe drain, brick
sewer, manholes & catchpits, etc., including taking all appropriate
precaution on easy measure against side collapsing any
201 underground utility serving and removing the excavated earth and
other debris from the site within 24 hours by the truck to safe
distance or nearest DCC dumping yard as per drawing
specification and direction of the Engineer-in-charge.

(a) depth up to 3m cum 41900 224 9,385,600


(b) depth 3 to 5m cum 22430 293 6,571,990
(c) depth 5 to 7m cum 43005 307 13,202,535
The excavation of Trial Holes and the completion of backfill with
202 approved fill material, all in accordance with the Technical P/cum 1538 241 370,658
Specification.
Supplying, pipes and fittings of different diameter as per terms,
conditions and specifications including transportation to Dhaka
WASA store.
A. Gravity Main
(i) UPVC pipe 200 mm diameter m 32845 1,278 41,979,195
(ii) UPVC pipe 250 mm diameter m 1794 1,804 3,237,094
(iii) UPVC pipe 300 mm diameter m 367 3,609 1,324,393
(iv) UPVC pipe 350 mm diameter m 94 3,989 374,975
203
(v) UPVC pipe 400 mm diameter m 632 5,714 3,611,122
(vi) UPVC pipe 500 mm diameter m 741 12,473 9,242,419

Dasherkandi Sewerage Project, Cost Estimate for Package 8 4 of 25


Bill No. 2: Procurement and Construction of Sewers

Item Unit Price Total Price


203 Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
(vii) GRP pipe SN 10000 PN 1 600 mm m 931 17,051 15,874,667
(viii) GRP pipe SN 10000 PN 1 700 mm m 750 22,988 17,240,625
(ix) GRP pipe SN 10000 PN 1 800 mm m 1434 33,080 47,436,577
(x) GRP pipe SN 10000 PN 1 1000 mm m 868 56,620 49,146,160
B. Force Main
(i) GRP pipe SN 10000 PN 6 800 mm m 300 54,375 16,312,500
Carrying, Laying, jointing of the following sizes of uPVC and GRP
pipes with collar of the standards as mentioned in specification in
trenches as per technical specification and standard drawings and
accepted by the Engineer
A. Gravity Main
(i) UPVC pipe 200 mm diameter m 18106 1,116 20,206,296
(ii) UPVC pipe 250 mm diameter m 739 1,125 831,375
(iii) UPVC pipe 300 mm diameter m 1111 1,134 1,259,874
204 (iv) UPVC pipe 350 mm diameter m 1211 1,210 1,465,310
(v) UPVC pipe 400 mm diameter m 348 1,233 429,084
(vi) UPVC pipe 500 mm diameter m 744 1,383 1,028,952
(vii) GRP pipe SN 10000 PN 1 600 mm m 1176 1,413 1,661,688
(viii) GRP pipe SN 10000 PN 1 700 mm m 147 1,459 214,473
(ix) GRP pipe SN 10000 PN 1 800 mm m 601 1,504 903,904
(x) GRP pipe SN 10000 PN 1 1000 mm m 868 1,459 1,266,412
B. Force Main
(i) GRP pipe SN 10000 PN 6 900 mm m 300 1,459 437,700
Thrust block for force main at different junction points as specified
205 cum 15.43 6,481 100,001
in drawings and technical specification.

Dasherkandi Sewerage Project, Cost Estimate for Package 8 5 of 25


Bill No. 2: Procurement and Construction of Sewers

Item Unit Price Total Price


Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
Demolishing of Existing RCC / CC / Brick Sewer/ Deckslab /
Foundation / Wall / railing / abutment / beam / Manholes etc. with
206 soling under RCC/CC in bed, without disturbing the foundation soil cum 840 1,881 1,580,040
and dumping the materials to a safe place as per direction of the
Engineer.
Supplying and placing bedding materials in trenches and
compacted to specified density as per technical specification and
standard drawings for all sewer pipes and accepted by the
Engineer`
207
(a)coarse sand(F.M.2.5 to 3.5) bedding & surrounding the sewer
cum 20233 1,618 32,736,994
(b).Mass concrete (1:3:6) bedding & surrounding and 1m top of
cum 443 2,944,621
the sewer at road crossings 6,647
Supplying and Back filling the excavated trenches after laying
208 sewer & sorrounding by saturated river sand(. at any depth) P/Cum 87102 635 55,309,770

Service Connection:
(a) Construction of 100mm/150 mm diameter service connection
including service pit with the supply of all necessary construction
materials, CI manhole cover, pipe materials and fittings as per
No.
specifications and drawings. This item shall also include
excavation and refilling of trenches.

(i) 100 mm Service connection line with service pit No. 75 21,273 1,595,475
(ii) 150 mm Service connection line with service pit No. 175 21,623 3,784,025
209

Dasherkandi Sewerage Project, Cost Estimate for Package 8 6 of 25


Bill No. 2: Procurement and Construction of Sewers

Item Unit Price Total Price


Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
209
(b) Construction of 100mm/150 mm diameter sewer line (including
T connection with main pipe) and connection of the lines with the
existing service pit where possible including supply of all
necessary construction materials, pipe materials and fittings as per
specifications and drawings. This item shall also include
excavation and refilling of trenches.

(i) 100 mm dia service connection line m 1500 1,075 1,612,500


(ii) 150 mm dia service connection line m 3500 1,200 4,200,000
Extra-over item 203 for the Testing of the Sewer Pipes in
accordance with the Technical Specification. The rate to include
210 P/m 40456 42,500 1,719,380,000
for the supply of all necessary equipment, materials and testing
Water.
Total for Bill No. 2
2,088,259,003
(carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 7 of 25


Bill No. 3: Gravity Sewer Manholes, Air valve Chamber; Wash out valve Chamber and
Discharge Chamber

Item Unit Price Total Price


Description Unit Quantity Remarks
no.
(BDT) (BDT)
a b c d e f g
A. Construction of R.C.C sewer manhole with R.C.C. cover
slab with embedded half flexible GRP joint to the
dimension required by the specification at various depths
in accordance with technical specification and standard
drawings.The rates include C.I.manhole cover and all
necessary ancillary works etc.

(a) manholes for pipe dia 400 mm no 8 138,592 1,108,739


(b) manholes for pipe dia 500 mm no 11 139,852 1,538,371
(c) manholes for pipe dia 600 mm no 22 141,178 3,105,920
301 (d) manholes for pipe dia 700 mm no 13 142,428 1,851,563
(e) manholes for pipe dia 800 mm no 25 143,754 3,593,854
(f) manholes for pipe dia 1000 mm no 18 145,014 2,610,247
B. Construction of Brick sewer manhole at various depths
in accordance with technical specification and standard
drawings.The rates include C.I.manhole cover and all
necessary ancillary works etc
(a) manholes for pipe dia 200 mm no 535 136,016 72,768,753
(b) manholes for pipe dia 250 mm no 31 136,679 4,237,064
(c) manholes for pipe dia 300 mm no 9 137,266 1,235,395
(d) manholes for pipe dia 350 mm no 2 137,929 275,859

Dasherkandi Sewerage Project, Cost Estimate for Package 8 8 of 25


Item Unit Price Total Price
Description Unit Quantity Remarks
no.
(BDT) (BDT)
a b c d e f g
Construction of Intermediate Brick sewer manhole at
various depths in accordance with technical specification
and standard drawings and as per decision & direction of
the Engineer incharge.The rates include C.I.manhole cover
302 and all necessary ancillary works

(a) manholes for pipe dia 200 mm no 287 136,016 39,036,695


(b) manholes for pipe dia 250 mm no 14 136,679 1,913,513

Supplying, carrying, fitting, fixing of air release valve


including supply of isolating gate valve with the supply of
all necessary materials and Construction of RCC Air valve
chamber including supply of all construction materials for
303 pipe dia 1000 & 1100mm as per specifications and no 2 139,852 279,704
drawings. The rate includes earth work excavation,
removal of excavated soil to safe distance, and backfilling
the trenches with saturated river sand and make he road
level acceptable for traffic movement etc.

Supplying, carrying, fitting, fixing of wash out valves


including supply of flap valve with the supply of all
necessary materials and Construction of RCC Wash out
valve chamber for diameter 1000 & 1100 mm as per
specifications and drawings. The rate includes earth work
304 no 2 139,852 279,704
excavation, removal of excavated soil to safe distance, and
backfilling the trenches with saturated river sand and make
the road level acceptable for traffic movement etc.

Dasherkandi Sewerage Project, Cost Estimate for Package 8 9 of 25


Item Unit Price Total Price
Description Unit Quantity Remarks
no.
(BDT) (BDT)
a b c d e f g
Construction of discharge chamber by supplying all
necessary construction materials in the junction point of
pipe dia-1000 & 1100 mm force main and 1800 mm gravity
main as per specifications and drawings. The rate includes
305 no 1 139,852 139,852
earth work excavation, removal of excavated soil to safe
distance, and backfilling the trenches with saturated river
sand and make the road level acceptable for traffic
movement etc.

Connection of the sewer, to existing manholes in


accordance with the Technical specification and Standard
Detail Drawings. The rate to include for dismantling and
306 making good the existing manhole; necessary plugging, de- No. 8 139,255 1,114,044
watering, cleaning and unplugging of the exiting sewer line
and completion of correct benching in Class A Mass
Concrete and back-drop arrangement as required.

Total for Bill No. 3


135,089,276
(carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 10 of 25


Bill No. 4: Site Cleaning & Temporary Road Reinstatement

Item Unit Price Total Price


Description Unit Quantity Remarks
no.
(BDT) (BDT)
a b c d e f g
Mobilization, demobilization and clearing of the work
site, removal of debris and other materials from
401 L.S. 1 5,039,683 5,039,683
inside the site and restoration of finished
groundsurface to the satisfaction of the Engineer.

Providing temporary restroation of roads surface to


their original conditions placing salvaged bricks,brick
khoa over backfilled surface as requirement and
accepted by the Engineer
402
a. Brick flat soling sq.m 17334 420 7,280,280
b. Base/ sub base layer cum 2600 4,455 11,583,000
c. Asphalt road surface sq.m 17334 1,335 23,140,890
Total for Bill No. 4
47,043,853
(carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 11 of 25


Bill No. 5: Gulshan SLS – Civil Works

Item Description Amount (BDT) Remark

501 General items 26,525,740


502 Earthworks 11,325,550
503 Brickworks 880,170
504 Concrete Works 9,724,765
505 Building Works 88,452,108
506 External Works 6,874,476
Total for Bill No. 5
143,782,809
(carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 12 of 25


Bill No. 6:Gulshan SLS –Mechanical, Electrical and Generator Works

Item Description Amount (BDT) Remark

601 Electrical Works 80,000,000

602 Mechanical works 80,000,000

603 Generator Works Included in the Electrical works


Total for Bill No. 6
160,000,000
(carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 13 of 25


Schedule of Daywork Rates: 1. Labour

Nominal Nominal Unit


Item
Description Unit quantity quantity Price Total Price (BDT) Remarks
no.
(hour) (day) (BDT)
a b c d e f g h
D100 Ganger day 500 21 1,100 22,917
D101 Labourer day 5000 208 464 96,663
D102 Bricklayer day 500 21 464 9,666
D103 Mason day 500 21 696 14,499
D104 Carpenter day 500 21 696 14,499
D105 Steelwork Erector day 500 21 696 14,499
D106 Driver for vehicle up to 10 tons day 1000 42 440 18,333
Operator for excavator, dragline,
D107 day 500 21 696 14,499
shovel, or crane
Operator for tractor with dozer blade
D108 day 500 21 696 14,499
or ripper
D109 Survey Crew day 500 21 495 10,313
Total for Daywork: Labour
230,388
(carried forward to Daywork Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 14 of 25


Schedule of Daywork Rates: 2. Materials

Unit
Item Nominal
Description Unit Price Total Price (BDT) Remarks
no. quantity
(BDT)
a b c d e f g
Include the sum of 3,000,000 for materials as
certified for works executed by Dayworks. The
cost shall be the net invoiced cost of the
materials including cash discounts plus the
D201 3,000,000
net cost of transport to the site.

Subtotal 3,000,000
D122 Allow 8 percent of Subtotal for Contractor’s 240,000
Total for Daywork: Materials
3,240,000
(carried forward to Daywork Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 15 of 25


Schedule of Daywork Rates: 3. Contractor’s Equipment

Nominal
Item Unit Price Total Price
Description quantity Remarks
no. (BDT) (BDT)
(hours)
a b c d e f
D301 Excavator, face shovel, or dragline:
0.1 Up to and including 1 m3 500 2,000 1,000,000
0.2 Over 1 m3 to 2 m3 400 3,000 1,200,000
0.3 Over 2 m3 100 3,510 351,000
D302 Tractor, including bull or angle dozer:
0.1 Up to and including 150 kW 500 1,000 500,000
0.2 Over 150 kW to 200 kW 400 1,500 600,000
0.3 Over 200 kW to 250 kW 200 2,000 400,000
D303 Tractor with ripper:
0.1 Up to and including 200 kW 400 1,500 600,000
0.2 Over 200 kW to 250 kW 200 2,000 400,000
D304 Portable concrete mixer - 0.4m3 400 500 200,000
D305 Hydraulic Excavator – 1 m3 500 3,000 1,500,000
D306 4-tool compressor including tools and hoses 500 2,000 1,000,000
D307 10 tonne lorry-mounted crane 500 5,000 2,500,000
D308 750 Kg crane 500 2,000 1,000,000
D309 0.5 m3 dumper 500 1,000 500,000
D310 1 m3 dumper 500 1,500 750,000
D311 7 m3 tipper lorry 500 2,000 1,000,000
D312 15 m3 lorry 500 2,000 1,000,000
D313 4 wheel drive pick-up or van 500 500 250,000
D314 Vibrating plate compactor 500 500 250,000
D315 8-10 tonne roller 500 2,000 1,000,000
Total for Daywork: Contractor’s Equipment
16,001,000
(carried forward to Daywork Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 16 of 25


Daywork Summary

Description Amount (BDT) Remark

1. Total for Daywork: Labour 230,388

2. Total for Daywork: Materials 3,240,000

3. Total for Daywork: Contractor’s Equipment 16,001,000

Total for Daywork 19,471,388

(Carried forward to Bid Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 17 of 25


Detailed Price schedule for Gulshan SLS

Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
General Items
Mobilisation Establish, maintain and
1 remove Contractor's site office, 1 sum 335,020 335,020
workshops, welfare and other facilities.
Provision and removal of the Engineer's
2 accommodation, equipment and site 1 sum 335,020 335,020
facilities
Operation and maintenance of the
3 Engineer's accommodation, equipment 1 yr 335,020 335,020
and site facilities
4 Approval of the Authorities 1 sum 850,000 850,000
Insurances
For Design 1 sum 586,285 586,285
For Third Party Liability 1 sum 439,714 439,714
5
For Contractor's Equipment 1 sum 439,714 439,714
For Site against Fire 1 sum 439,714 439,714
For Workers 1 sum 439,714 439,714
6 Maintenance of Site, Storage, Guarding 1 yr 335,020 335,020
7 Maintenance of Flow During Construction 1 sum 335,020 335,020
8 Temporary pipelines and facilities 1 sum 335,020 335,020
9 Necessary Testing and Quality Control 1 sum 335,020 335,020
10 Consumables 1 sum 850,000 850,000
Heating -
Electricity -
Telecommunication -
11 Provide and Maintain and bonds and guarantees1 sum 293,143 293,143
12 Test on Taking Over 1 sum 293,143 293,143
13 Test During Guarantee Period 1 sum 100,000 100,000

Dasherkandi Sewerage Project, Cost Estimate for Package 8 18 of 25


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
14 Other Costs of Guarantee Period 1 sum 3,000 3,000
15 As-Built Drawing 1 sum 3,224,569 3,224,569
Training and Manuals 1 sum 15,000 15,000
Documentation and Operation and
1 sum 3,224,569 3,224,569
Maintenance Manual
16 Documentation and Operation and
1 sum 3,224,569 3,224,569
Maintenance Staff
Supervision of operation staff during
1 sum 335,020 335,020
testing period
17 Costs of Temporary Measures 1 sum 879,428 879,428
18 Greenery and other Landscaping Works 1 sum 335,020 335,020
Performance security and advance
19 1 sum 293,143 293,143
payment Bank Guarantee
20 Preparation of Health and Safety Plan 1 sum 293,143 293,143
Preparation of Quality Assurance and
21 1 sum 335,020 335,020
Quality Control Plan
Preparation of the Environmental
22 1 sum 335,020 335,020
Management Plan
23 Preparation of Traffic Management Plan 1 sum 335,020 335,020
Provision of erection and removal of
24 1 sum 335,020 335,020
Contract Signboard
Provisional sum for Additional Testing of
25 1 sum 335,020 335,020
Materials as instructed by the Engineer
Provisional sum for Additional Special
26 Record, Photographs as instructed by 1 sum 335,020 335,020
the Engineer
Provisional sum for Permanent Diversion
27 1 sum 335,020 335,020
of Existing Utility Authorities
28 Other items Entered by Tenderer 1 sum 5,276,568 5,276,568

Dasherkandi Sewerage Project, Cost Estimate for Package 8 19 of 25


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
Earthworks
1 Site preparation 1,000.00 sqm 5,918 5,918,000
2 Construction of Bench Mark pillar(s) 1 No. 10,000 10,000
Earth work in excavation of foundation
3 trenches in Pump Station and Control 3000 cum 346 1,038,000
Building.
Extra rate for every additional lift
3 1200 cum 426 511,200
Lift 6 Nos for 1200.00 cum earth work
Sand filling foundation in Pump House.
3 700 cum 913 639,100
Sand of FM>=1.00
Back filling in Pump House and Control
6 Building.
Sand of FM>=0.80.
(a) Pump House 270 cum 913 246,510
(b) Control Room- Between Pile Caps 1530 cum 913 1,396,890
Bailing out of water from foundation pit.
7 2500 cum 500 1,250,000
By pump
Pilling Works
Construction of R.C.C. cast in situ bored
1 280 meter 980 274,400
piles 500 mm dia
Labour for breaking of head of cast in
2 5 cum 464 2,320
situ bored pile
Providing and making joint of welding of
3 at the lapping portion of main 45 meter 236 10,630
reinforcements of cast in situ bored pile
Providing and making point welding at
4 7500 No. 3 22,500
contact points of the spiral binders
Carrying out pilled load test Design load
5 1 No. 6,000 6,000
upto 70.00 tonne
Brickworks

Dasherkandi Sewerage Project, Cost Estimate for Package 8 20 of 25


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
Damp proof coarse (D.P.C) in Brickwork
1 (proportion 1:2:4) in Control Building 25 sqm 8 200
Minimum 40mm thick
250 mm brick work in Control Building.
2 40 cum 6,769 270,760
Proportion : 1:4
125mm thick brick work in Control
3 Building. 90 sqm 6,769 609,210
Proportion: 1: 4
Concrete Works
Blinding Concrete in Pump Station and
Control Building.
1 30 cum 7,517 225,510
With 25mm down graded stone chips as
per specification
Formwork in Pump Station, Control
Building & Transformer Base.
Vertical and inclined walls, columns 1,450 sqm 700 1,015,000
2
Slab 300 sqm 700 210,000
Beams 350 sqm 700 245,000
Footing, grade beams, foundation slab 200 sqm 700 140,000
M.S. work for RCC in Pump Station,
Control Building & Transformer Base
3 47,500.00 kg 82 3,895,000
8mm dia to 30mm dia as per drawing
and technical specification.
M.S work for 3 Nos. I-Beams as per
4 1500 kg 82 123,000
drawing and technical specification.
Reinforced Cement Concrete(RCC) in
Pump Station and Control Building.
5 480 cum 7,517 3,608,160
With stone chips as per drawing and
technical specification.
Reinforced Cement Concrete(RCC) for
benching in Pump Station.
6 35 cum 7,517 263,095
Dasherkandi Sewerage Project, Cost Estimate for Package 8 21 of 25
Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
6 35 cum 7,517 263,095
With stone chips as per drawing and
technical specification.
Building Works
1 Setting out of building layouts 1000 sqm 87,000 87,000,000
Wood work in door and window frames in
2 2 cum 130,410 260,820
Control Building.
Wood work in Door Shutter (40 mm
3 25 sqm 914 22,841
thickness) in Control Building.
Glass shutter window ( Grills of any
4 design made with 25X6 mm F.I bar and 5 1.02 sqm 3,720 3,794
mm thick glass) all complete
Silver gray cast in situ mosaic in Control
5 125 sqm 1,655 206,875
Building.
GIazed tiles in Control Room Toilet.
6 Various size (in walls) 12 sqm 1,571 18,852
Various size (in walls) 3 sqm 1,571 4,713
Plastic emulsion painting to walls and
7 ceiling in Pump Station and Control 250 sqm 450 112,500
Room. 3 coats
White washing in Pump Station and
8 Control Building. 2 coats over a priming 1,000.00 sqm 70 70,000
coat
French polishing in door shutters in
9 Control Building. 2 coats over a priming 25 sqm 1,584 39,600
coat
Minimum 12mm thick sand cement
10 plaster, in Pump Station and Control 1250 sqm 193 240,625
Building. Proportion 1:4

Artificial Patent stone flooring in Control


11 125 sqm 450 56,250
Building. Minimum 25 mm thick

Dasherkandi Sewerage Project, Cost Estimate for Package 8 22 of 25


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
Artificial Patent stone flooring in Control
a
11 b c
125 d
sqm e 450 f 56,250 g
Building. Minimum 25 mm thick

Neat cement finishing in Control Building.


12 30 sqm 6,336 190,080
Minimum 25 mm thick
Galvanised Iron pipes in Control
13 Building. 25 meter 171 4,264
13 mm dia G.I. pipe line
uPVC Rain water drainage pipes in
14 Pump Station and Control Building. 150 25 meter 548 13,694
mm dia PVC pipe
Connection to water supply for Control
15 1 No. 85,000 85,000
Building
C.P. Bib cock in Control Building (13 mm
16 2 No. 780 1,560
dia)
C.P pillar cock In Control Building (13
17 2 No. 950 1,900
mm dia)
Brass bib cock in Control Building (13
18 2 No. 950 1,900
mm dia)
Check valve in Control Building (13 mm
19 2 No. 200 400
dia)
Gate valve in Control Building (13 mm
20 2 No. 300 600
dia)
21 Ball cock in Control Building (13 mm dia) 2 No. 200 400

"BISF STANDARD" white glazed vitreous


22 Wash Hand Basin (685mm x 460mm X 1 No. 3,500 3,500
235mm size) wgite

Dasherkandi Sewerage Project, Cost Estimate for Package 8 23 of 25


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
European type glased porcelin comode
'P' or 'S' type "BISF STANDARD'
(580mmx345mmx410 mm) with low
23 1 set 6,000 6,000
down white vitreous china cistern
including all external fittings
complete:White
Bath room mirror with C.P. screws and
24 hard board backing in Control Building 1 No. 886 886
0.45m X 0.60m size
C.P. towel rail, with all necessary
25 accessories in Control Building 1 No. 750 750
.75m long and 25mm square/round
26 C.P. Soap dish in Control Building 1 No. 240 240
Construction of masonry inspection pits
27 2 No. 84,000
in Control Building.
Galvanised Iron/Food grade PVC tank of
1.20m x 1.20m x 1.20m size or
28 equivalent to 1800 litres capacity in 1 No. 20,064 20,064
Control Building.
16 BWG, over head tank.
External Works
Demolition of Existing Boundary Walls (2
1 150 sqm 840,000
m height, 85 m long)
RCC Bollards 200mm dia, 1200mm in
2 length with 300mm embedment in earth 25 No. 7,000 175,000
with 0.60 m3 base
3 6.00m wide sliding entrance gate 1 No. 30,000 30,000
2.00 m high Security Fence for
4 13 meter 1,500 19,500
Transformer
5 New Boundary Wall 120 meter 4,000 480,000

Dasherkandi Sewerage Project, Cost Estimate for Package 8 24 of 25


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
External 150 mm uPVC Sewer
6 12 meter 1,075 12,900
Connection pipe from WC
7 GRP Open Mesh Flooring & Supports 80 meter 20,000 1,600,000
Stainless Steel Access Stairs(0.8 m
8 10 meter 7,500 75,000
wide)
9 GMS Hand Railing 65 meter 4,500 292,500
10 Screening Skip (0.2 m3 capacity) 1 No. 84,000 84,000
Manual Bar Screen (2.3m long x 2.4m
11 20 m2 21,000 420,000
wide)
Steel Collection Trough for Screenings
12 1 No. 400,000 400,000
(300mm wide, 250mm deep, 2.5 m long)
3 Nos Concrete Ramp to Control Room
13 2.55 long @ 1V:3 H (1.5m, 2.00m & 8 cum 7,517 60,136
2.50m width)
Concrete site access turning area
(Including access road), 510.00 m2
300 mm thick concrete 155 cum 7,643 1,184,665
14
200 mm thick cement bond granular sub-
105 cum 6,647 697,935
base
600 mm thick selected granular fill 305 cum 149 45,445
15 150mm dia uPVC Site Drainage 455 meter 548 249,231
16 150mm dia uPVC Electrical Ducts 150 meter 548 82,164
17 600mm x 600mm Drainage Gullys 11 No. 8,400 92,400
Water Connection Hydrants for
18 2 No. 16,800 33,600
screening chamber and wet well
Total (A)= 143,782,809

Dasherkandi Sewerage Project, Cost Estimate for Package 8 25 of 25


Package - 08 (2)
Banani

Grand Summary

Amount
General Summary Page Remarks
(BDT)
a b c d
Bill No. 1: General Items 16,405,480
Bill No. 2: Procurement and Construction of Sewers 1,229,715,075

Bill No. 3: Gravity Sewer Manholes, Air valve Chamber; Wash


79,416,835
out valve Chamber and Discharge Chamber

Bill No. 4: Site Cleaning & Temporary Road Reinstatement 43,083,943


Bill No. 5: Tejgaon SLS – Civil Works 111,459,455
Bill No. 6: Tejgaon SLS – Mechanical, Electrical and Generator
160,000,000
Works
—etc.—
Subtotal of Bills (A) 1,640,080,788
Total for Daywork (B) 19,471,388
Specified Provisional Sums included in subtotal of bills (C) 85,822,838
Total of Bills Plus Provisional Sums (A + B + C) (D) 1,745,375,014
Add Provisional Sum for Contingency Allowance (10% of
(E) 174,537,501
D)

Bid Price (D + E) (Carried forward to Form of Bid) (F) 1,919,912,516

USD (million) 22.59

Dasherkandi Sewerage Project, Cost Estimate for Package 8 1 of 26


Bill No. 1: General Items

Item Unit Price Total Price


Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
Performance Security and Advance Payment
101 L.S. 1 269,943 269,943
Guarantee.

Road restoration charges payable to road owning


102 L.S. 1 308,507 308,507
agencies

103 Insurances and Bonds L.S. 1 3,239,319 3,239,319

Preparation of Construction Health and Safety


104 L.S. 1 308,507 308,507
Plan
Preparation of Contractor’s Quality Assurance
105 L.S. 1 809,830 809,830
and Control Plan
106 Preparation of Environmental Management Plan L.S. 1 308,507 308,507

107 Preparation of Traffic Management Plan L.S. 1 308,507 308,507

Provision for erection, operation, maintenance


and removal of Contractor’s accommodation,
108 equipment and site facilities such as providing L.S. 1 809,830 809,830
furniture, first aid box, safety helmet,
consumables, stationary etc

Provision for erection, operation, maintenance


and removal of the Engineer's accommodation,
109 equipment and site facilities such as providing L.S. 1 308,507 308,507
furniture, first aid box, safety helmet,
consumables, stationary etc.
Provision, operation and maintenance of the
110 L.S. 1 308,507 308,507
Engineer’s transportation

Dasherkandi Sewerage Project, Cost Estimate for Package 8 2 of 26


Item Unit Price Total Price
Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
Provision, erection and removal of Contractor’s
111 L.S. 1 308,507 308,507
Signboards

112 CCTV inspection of the completed works L.S. 1 8,500,000 8,500,000

Additional testing of materials as instructed by


113 p.s. 1 308,507 308,507
the Engineer

Additional Record photographs as instructed by


114 p.s. 1 308,507 308,507
the Engineer
Total for Bill No. 1
16,405,480
(carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 3 of 26


Bill No. 2: Procurement and Construction of Sewers

Item Unit Price Total Price


Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
Earth work in excavation in in/c. Pucca road cutting with
dismetting hard rock, Bituminous pavement, solling, herring bone
bond, etc. lead & lift from trenches of through all kinds of soil and
road pavements to the required depth, width & proper gradient
from the preparation of foundation bed for placing of foundation
concrete or sand cushion as the case may be for pipe drain, brick
sewer, manholes & catchpits, etc., including taking all appropriate
precaution on easy measure against side collapsing any
201 underground utility serving and removing the excavated earth and
other debris from the site within 24 hours by the truck to safe
distance or nearest DCC dumping yard as per drawing
specification and direction of the Engineer-in-charge.

(a) depth up to 3m cum 26,710 224 5,983,040


(b) depth 3 to 5m cum 12,873 293 3,771,789
(c) depth 5 to 7m cum 17,211 307 5,283,777
The excavation of Trial Holes and the completion of backfill with
202 approved fill material, all in accordance with the Technical P/cum 938 241 226,058
Specification.
Supplying, pipes and fittings of different diameter as per terms,
conditions and specifications including transportation to Dhaka
WASA store.
A. Gravity Main
(i) UPVC pipe 200 mm diameter m 18,106 1,278 23,141,279
(ii) UPVC pipe 250 mm diameter m 739 1,804 1,333,452
(iii) UPVC pipe 300 mm diameter m 1,111 3,609 4,009,266
203 (iv) UPVC pipe 350 mm diameter m 1,211 3,989 4,830,800
(v) UPVC pipe 400 mm diameter m 348 5,714 1,988,402
(vi) UPVC pipe 500 mm diameter m 744 12,473 9,279,838

Dasherkandi Sewerage Project, Cost Estimate for Package 8 4 of 26


Item
203 Unit Price Total Price
Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
(vii) GRP pipe SN 10000 PN 1 600 mm m 1,176 17,051 20,052,211
(viii) GRP pipe SN 10000 PN 1 700 mm m 147 22,988 3,379,163
(ix) GRP pipe SN 10000 PN 1 800 mm m 601 33,080 19,881,020
B. Force Main
(i) GRP pipe SN 10000 PN 16 900 mm m 300 39,529 11,858,760
Carrying, Laying, jointing of the following sizes of uPVC and GRP
pipes with collar of the standards as mentioned in specification in
trenches as per technical specification and standard drawings and
accepted by the Engineer
A. Gravity Main
(i) UPVC pipe 200 mm diameter m 18,106 1,116 20,206,296
(ii) UPVC pipe 250 mm diameter m 739 1,125 831,375
(iii) UPVC pipe 300 mm diameter m 1,111 1,134 1,259,874
204
(iv) UPVC pipe 350 mm diameter m 1,211 1,210 1,465,310
(v) UPVC pipe 400 mm diameter m 348 1,233 429,084
(vi) UPVC pipe 500 mm diameter m 744 1,383 1,028,952
(vii) GRP pipe SN 10000 PN 1 600 mm m 1,176 1,413 1,661,688
(viii) GRP pipe SN 10000 PN 1 700 mm m 147 1,459 214,473
(ix) GRP pipe SN 10000 PN 1 800 mm m 601 1,504 903,904
B. Force Main
(i) GRP pipe SN 10000 PN 6 900 mm m 300 1,865 559,500
Thrust block for force main at different junction points as specified
205 cum 12 6,481 74,985
in drawings and technical specification.
Demolishing of Existing RCC / CC / Brick Sewer/ Deckslab /
Foundation / Wall / railing / abutment / beam / Manholes etc. with
206 soling under RCC/CC in bed, without disturbing the foundation soil cum 720 1,881 1,354,320
and dumping the materials to a safe place as per direction of the
Engineer.

Dasherkandi Sewerage Project, Cost Estimate for Package 8 5 of 26


Item Unit Price Total Price
Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
Supplying and placing bedding materials in trenches and
compacted to specified density as per technical specification and
standard drawings for all sewer pipes and accepted by the
Engineer`
207
(a)coarse sand(F.M.2.5 to 3.5) bedding & surrounding the sewer
cum 11,574 1,618 18,726,732
(b).Mass concrete (1:3:6) bedding & surrounding and 1m top of
cum 492 3,270,324
the sewer at road crossings 6,647
Supplying and Back filling the excavated trenches after laying
208 sewer & sorrounding by saturated river sand(. at any depth) P/Cum 43,543 635 27,649,805

Service Connection:
(a) Construction of 100mm/150 mm diameter service connection
including service pit with the supply of all necessary construction
materials, CI manhole cover, pipe materials and fittings as per
No.
specifications and drawings. This item shall also include
excavation and refilling of trenches.

(i) 100 mm Service connection line with service pit No. 50 21,273 1,063,650
(ii) 150 mm Service connection line with service pit No. 150 21,623 3,243,450
209
(b) Construction of 100mm/150 mm diameter sewer line (including
T connection with main pipe) and connection of the lines with the
existing service pit where possible including supply of all
necessary construction materials, pipe materials and fittings as per
specifications and drawings. This item shall also include
excavation and refilling of trenches.

(i) 100 mm dia service connection line m 1,000 1,075 1,075,000


(ii) 150 mm dia service connection line m 3,000 1,200 3,600,000

Dasherkandi Sewerage Project, Cost Estimate for Package 8 6 of 26


Item Unit Price Total Price
Description Unit Qty. Remarks
no. (BDT) (BDT)
a b c d e f g
Extra-over item 203 for the Testing of the Sewer Pipes in
accordance with the Technical Specification. The rate to include
210 P/m 24,143 42,500 1,026,077,500
for the supply of all necessary equipment, materials and testing
Water.
Total for Bill No. 2
1,229,715,075
(carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 7 of 26


Bill No. 3: Gravity Sewer Manholes, Air valve Chamber; Wash out valve Chamber and
Discharge Chamber

Item Unit Price Total Price


Description Unit Quantity Remarks
no.
(BDT) (BDT)
a b c d e f g
A. Construction of R.C.C sewer manhole with R.C.C.
cover slab with embedded half flexible GRP joint to
the dimension required by the specification at various
depths in accordance with technical specification and
standard drawings.The rates include C.I.manhole
cover and all necessary ancillary works etc.

(a) manholes for pipe dia 400 mm no 10 138,592 1,385,924


(b) manholes for pipe dia 500 mm no 12 139,852 1,678,223
(c) manholes for pipe dia 600 mm no 23 141,178 3,247,098
301 (d) manholes for pipe dia 700 mm no 2 142,428 284,856
(e) manholes for pipe dia 800 mm no 9 143,754 1,293,788
B. Construction of Brick sewer manhole at various
depths in accordance with technical specification and
standard drawings.The rates include C.I.manhole
cover and all necessary ancillary works etc

(a) manholes for pipe dia 200 mm no 290 136,016 39,444,744


(b) manholes for pipe dia 250 mm no 12 136,679 1,640,154
(c) manholes for pipe dia 300 mm no 21 137,266 2,882,589
(d) manholes for pipe dia 350 mm no 20 137,929 2,758,585
Construction of Intermediate Brick sewer manhole at
various depths in accordance with technical
specification and standard drawings and as per
decision & direction of the Engineer incharge.The
302 rates include C.I.manhole cover and all necessary
ancillary works

Dasherkandi Sewerage Project, Cost Estimate for Package 8 8 of 26


Item Unit Price Total Price
Description Unit Quantity Remarks
no.
302
(BDT) (BDT)
a b c d e f g
(a) manholes for pipe dia 200 mm no 163 136,016 22,170,667
(b) manholes for pipe dia 250 mm no 7 136,679 956,756

Supplying, carrying, fitting, fixing of air release valve


including supply of isolating gate valve with the
supply of all necessary materials and Construction of
RCC Air valve chamber including supply of all
construction materials for pipe dia 1000 & 1100mm
303 no 1 139,852 139,852
as per specifications and drawings. The rate includes
earth work excavation, removal of excavated soil to
safe distance, and backfilling the trenches with
saturated river sand and make he road level
acceptable for traffic movement etc.

Supplying, carrying, fitting, fixing of wash out valves


including supply of flap valve with the supply of all
necessary materials and Construction of RCC Wash
out valve chamber for diameter 1000 & 1100 mm as
304 per specifications and drawings. The rate includes no 2 139,852 279,704
earth work excavation, removal of excavated soil to
safe distance, and backfilling the trenches with
saturated river sand and make the road level
acceptable for traffic movement etc.

Construction of discharge chamber by supplying all


necessary construction materials in the junction point
of pipe dia-1000 & 1100 mm force main and 1800
mm gravity main as per specifications and drawings.
305 no 1 139,852 139,852
The rate includes earth work excavation, removal of
excavated soil to safe distance, and backfilling the
trenches with saturated river sand and make the road
level acceptable for traffic movement etc.

Dasherkandi Sewerage Project, Cost Estimate for Package 8 9 of 26


Item Unit Price Total Price
Description Unit Quantity Remarks
no.
(BDT) (BDT)
a b c d e f g
Connection of the sewer, to existing manholes in
accordance with the Technical specification and
Standard Detail Drawings. The rate to include for
dismantling and making good the existing manhole;
306 No. 8 139,255 1,114,044
necessary plugging, de-watering, cleaning and
unplugging of the exiting sewer line and completion
of correct benching in Class A Mass Concrete and
back-drop arrangement as required.
Total for Bill No. 3
79,416,835
(carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 10 of 26


Bill No. 4: Site Cleaning & Temporary Road Reinstatement

Item Unit Price Total Price


Description Unit Quantity Remarks
no.
(BDT) (BDT)
a b c d e f g

Mobilization, demobilization and clearing of the work


site, removal of debris and other materials from inside
401 L.S. 1 1,079,773 1,079,773
the site and restoration of finished groundsurface to
the satisfaction of the Engineer.

Providing temporary restroation of roads surface to


their original conditions placing salvaged bricks,brick
khoa over backfilled surface as requirement and
accepted by the Engineer
402
a. Brick flat soling sq.m 17334 420 7,280,280

b. Base/ sub base layer cum 2600 4,455 11,583,000

c. Asphalt road surface sq.m 17334 1,335 23,140,890


Total for Bill No. 4
43,083,943
(carried forward to Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 11 of 26


Bill No. 5: Tejgaon SLS – Civil Works

Item Description Amount (BDT) Remarks

501 General items 20,900,141


502 Earthworks 10,904,550
503 Brickworks 880,170
504 Concrete Works 9,712,010
505 Building Works 62,352,108
506 External Works 6,710,476

Total for Bill No. 5


111,459,455
(carried forward to Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 12 of 26


Bill No. 6: Tejgaon SLS –Mechanical, Electrical and Generator Works

Item Description Amount (BDT) Remarks

601 Electrical Works 80,000,000

602 Mechanical works 80,000,000

Included in the Electrical


603 Generator Works
works
Total for Bill No. 6
160,000,000
(carried forward to Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 13 of 26


Schedule of Daywork Rates: 1. Labour

Nominal Nominal Unit


Item Total Price
Description Unit quantity quantity Price Remarks
no. (BDT)
(hour) (day) (BDT)
a b c d e f g h
D100 Ganger day 500 21 1,100 22,917
D101 Labourer day 5000 208 464 96,663
D102 Bricklayer day 500 21 464 9,666
D103 Mason day 500 21 696 14,499
D104 Carpenter day 500 21 696 14,499
D105 Steelwork Erector day 500 21 696 14,499
D106 Driver for vehicle up to 10 tons day 1000 42 440 18,333
Operator for excavator, dragline,
D107 day 500 21 696 14,499
shovel, or crane
Operator for tractor with dozer blade
D108 day 500 21 696 14,499
or ripper
D109 Survey Crew day 500 21 495 10,313
Total for Daywork: Labour
230,388
(carried forward to Daywork Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 14 of 26


Schedule of Daywork Rates: 2. Materials

Unit
Item Nominal
Description Unit Price Total Price (BDT) Remarks
no. quantity
(BDT)
a b c d e f g
Include the sum of 3,000,000 for materials as
certified for works executed by Dayworks. The
cost shall be the net invoiced cost of the
materials including cash discounts plus the net
D201 3,000,000
cost of transport to the site.

Subtotal 3,000,000
D122 Allow 8 percent of Subtotal for Contractor’s 240,000
Total for Daywork: Materials
3,240,000
(carried forward to Daywork Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 15 of 26


Schedule of Daywork Rates: 3. Contractor’s Equipment

Nominal
Item Unit Price
Description quantity Total Price (BDT) Remarks
no. (BDT)
(hours)
a b c d e f
D301 Excavator, face shovel, or dragline:
0.1 Up to and including 1 m3 500 2,000 1,000,000
0.2 Over 1 m3 to 2 m3 400 3,000 1,200,000
0.3 Over 2 m3 100 3,510 351,000
D302 Tractor, including bull or angle dozer:
0.1 Up to and including 150 kW 500 1,000 500,000
0.2 Over 150 kW to 200 kW 400 1,500 600,000
0.3 Over 200 kW to 250 kW 200 2,000 400,000
D303 Tractor with ripper:
0.1 Up to and including 200 kW 400 1,500 600,000
0.2 Over 200 kW to 250 kW 200 2,000 400,000
D304 Portable concrete mixer - 0.4m3 400 500 200,000
D305 Hydraulic Excavator – 1 m3 500 3,000 1,500,000
D306 4-tool compressor including tools and hoses 500 2,000 1,000,000
D307 10 tonne lorry-mounted crane 500 5,000 2,500,000
D308 750 Kg crane 500 2,000 1,000,000
D309 0.5 m3 dumper 500 1,000 500,000
D310 1 m3 dumper 500 1,500 750,000
D311 7 m3 tipper lorry 500 2,000 1,000,000
D312 15 m3 lorry 500 2,000 1,000,000
D313 4 wheel drive pick-up or van 500 500 250,000
D314 Vibrating plate compactor 500 500 250,000
D315 8-10 tonne roller 500 2,000 1,000,000
Total for Daywork: Contractor’s Equipment
16,001,000
(carried forward to Daywork Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 16 of 26


Daywork Summary

Description Amount (BDT) Remark

1. Total for Daywork: Labour 230,388

2. Total for Daywork: Materials 3,240,000

3. Total for Daywork: Contractor’s Equipment 16,001,000

Total for Daywork


19,471,388
(Carried forward to Grand Summary)

Dasherkandi Sewerage Project, Cost Estimate for Package 8 17 of 26


Detailed Price schedule for Tejgaon SLS

Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
General Items
Mobilisation Establish, maintain and
1 remove Contractor's site office, 1 sum 258,741 258,741
workshops, welfare and other facilities.
Provision and removal of the Engineer's
2 accommodation, equipment and site 1 sum 258,741 258,741
facilities
Operation and maintenance of the
3 Engineer's accommodation, equipment 1 yr 258,741 258,741
and site facilities
4 Approval of the Authorities 1 sum 850,000 850,000
Insurances
For Design 1 sum 452,797 452,797
For Third Party Liability 1 sum 339,597 339,597
5
For Contractor's Equipment 1 sum 339,597 339,597
For Site against Fire 1 sum 339,597 339,597
For Workers 1 sum 339,597 339,597
6 Maintenance of Site, Storage, Guarding 1 yr 258,741 258,741
7 Maintenance of Flow During Construction 1 sum 258,741 258,741
8 Temporary pipelines and facilities 1 sum 258,741 258,741
9 Necessary Testing and Quality Control 1 sum 258,741 258,741
10 Consumables 1 sum 850,000 850,000
Heating -
Electricity -
Telecommunication -
11 Provide and Maintain and bonds and guarantees1 sum 226,398 226,398
12 Test on Taking Over 1 sum 226,398 226,398
13 Test During Guarantee Period 1 sum 100,000 100,000

Dasherkandi Sewerage Project, Cost Estimate for Package 8 18 of 26


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
14 Other Costs of Guarantee Period 1 sum 3,000 3,000
15 As-Built Drawing 1 sum 2,490,381 2,490,381
Training and Manuals 1 sum 15,000 15,000
Documentation and Operation and
1 sum 2,490,381 2,490,381
Maintenance Manual
16 Documentation and Operation and
1 sum 2,490,381 2,490,381
Maintenance Staff
Supervision of operation staff during
1 sum 258,741 258,741
testing period
17 Costs of Temporary Measures 1 sum 679,195 679,195
18 Greenery and other Landscaping Works 1 sum 258,741 258,741
Performance security and advance
19 1 sum 226,398 226,398
payment Bank Guarantee
20 Preparation of Health and Safety Plan 1 sum 226,398 226,398
Preparation of Quality Assurance and
21 1 sum 258,741 258,741
Quality Control Plan
Preparation of the Environmental
22 1 sum 258,741 258,741
Management Plan
23 Preparation of Traffic Management Plan 1 sum 258,741 258,741
Provision of erection and removal of
24 1 sum 258,741 258,741
Contract Signboard
Provisional sum for Additional Testing of
25 1 sum 258,741 258,741
Materials as instructed by the Engineer
Provisional sum for Additional Special
26 Record, Photographs as instructed by 1 sum 258,741 258,741
the Engineer
Provisional sum for Permanent Diversion
27 1 sum 258,741 258,741
of Existing Utility Authorities
28 Other items Entered by Tenderer 1 sum 4,075,169 4,075,169

Dasherkandi Sewerage Project, Cost Estimate for Package 8 19 of 26


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
Earthworks
1 Site preparation 1,000.00 sqm 5,918 5,918,000
2 Construction of Bench Mark pillar(s) 1 No. 10,000 10,000
Earth work in excavation of foundation
3 trenches in Pump Station and Control 2600 cum 346 899,600
Building.
Extra rate for every additional lift
3 1200 cum 426 511,200
Lift 6 Nos for 1200.00 cum earth work
Sand filling foundation in Pump House.
3 700 cum 913 639,100
Sand of FM>=1.00
Back filling in Pump House and Control
6 Building.
Sand of FM>=0.80.
(a) Pump House 150 cum 913 136,950
(b) Control Room- Between Pile Caps 1450 cum 913 1,323,850
Bailing out of water from foundation pit.
7 2300 cum 500 1,150,000
By pump
Pilling Works
Construction of R.C.C. cast in situ bored
1 280 meter 980 274,400
piles 500 mm dia
Labour for breaking of head of cast in
2 5 cum 464 2,320
situ bored pile
Providing and making joint of welding of
3 at the lapping portion of main 45 meter 236 10,630
reinforcements of cast in situ bored pile
Providing and making point welding at
4 7500 No. 3 22,500
contact points of the spiral binders
Carrying out pilled load test Design load
5 1 No. 6,000 6,000
upto 70.00 tonne
Brickworks

Dasherkandi Sewerage Project, Cost Estimate for Package 8 20 of 26


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
Damp proof coarse (D.P.C) in Brickwork
1 (proportion 1:2:4) in Control Building 25 sqm 8 200
Minimum 40mm thick
250 mm brick work in Control Building.
2 40 cum 6,769 270,760
Proportion : 1:4
125mm thick brick work in Control
3 Building. 90 sqm 6,769 609,210
Proportion: 1: 4
Concrete Works
Blinding Concrete in Pump Station and
Control Building.
1 20 cum 7,517 150,340
With 25mm down graded stone chips as
per specification
Formwork in Pump Station, Control
Building & Transformer Base.
Vertical and inclined walls, columns 1,300.00 sqm 700 910,000
2
Slab 300 sqm 700 210,000
Beams 350 sqm 700 245,000
Footing, grade beams, foundation slab 200 sqm 700 140,000
M.S. work for RCC in Pump Station,
Control Building & Transformer Base
3 50,000.00 kg 82 4,100,000
8mm dia to 30mm dia as per drawing
and technical specification.
M.S work for 3 Nos. I-Beams as per
4 1500 kg 82 123,000
drawing and technical specification.
Reinforced Cement Concrete(RCC) in
Pump Station and Control Building.
5 475 cum 7,517 3,570,575
With stone chips as per drawing and
technical specification.
Reinforced Cement Concrete(RCC) for
benching in Pump Station.
6 35 cum 7,517 263,095
Dasherkandi Sewerage Project, Cost Estimate for Package 8 21 of 26
Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
6 35 cum 7,517 263,095
With stone chips as per drawing and
technical specification.
Building Works
1 Setting out of building layouts 700 sqm 87,000 60,900,000
Wood work in door and window frames in
2 2 cum 130,410 260,820
Control Building.
Wood work in Door Shutter (40 mm
3 25 sqm 914 22,841
thickness) in Control Building.
Glass shutter window ( Grills of any
4 design made with 25X6 mm F.I bar and 5 1.02 sqm 3,720 3,794
mm thick glass) all complete
Silver gray cast in situ mosaic in Control
5 125 sqm 1,655 206,875
Building.
GIazed tiles in Control Room Toilet.
6 Various size (in walls) 12 sqm 1,571 18,852
Various size (in walls) 3 sqm 1,571 4,713
Plastic emulsion painting to walls and
7 ceiling in Pump Station and Control 250 sqm 450 112,500
Room. 3 coats
White washing in Pump Station and
8 Control Building. 2 coats over a priming 1,000.00 sqm 70 70,000
coat
French polishing in door shutters in
9 Control Building. 2 coats over a priming 25 sqm 1,584 39,600
coat
Minimum 12mm thick sand cement
10 plaster, in Pump Station and Control 1250 sqm 193 240,625
Building. Proportion 1:4

Artificial Patent stone flooring in Control


11 125 sqm 450 56,250
Building. Minimum 25 mm thick

Dasherkandi Sewerage Project, Cost Estimate for Package 8 22 of 26


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
Artificial Patent stone flooring in Control
a
11 b c
125 d
sqm e 450 f 56,250 g
Building. Minimum 25 mm thick

Neat cement finishing in Control Building.


12 30 sqm 6,336 190,080
Minimum 25 mm thick
Galvanised Iron pipes in Control
13 Building. 25 meter 171 4,264
13 mm dia G.I. pipe line
uPVC Rain water drainage pipes in
14 Pump Station and Control Building. 150 25 meter 548 13,694
mm dia PVC pipe
Connection to water supply for Control
15 1 No. 85,000 85,000
Building
C.P. Bib cock in Control Building (13 mm
16 2 No. 780 1,560
dia)
C.P pillar cock In Control Building (13
17 2 No. 950 1,900
mm dia)
Brass bib cock in Control Building (13
18 2 No. 950 1,900
mm dia)
Check valve in Control Building (13 mm
19 2 No. 200 400
dia)
Gate valve in Control Building (13 mm
20 2 No. 300 600
dia)
21 Ball cock in Control Building (13 mm dia) 2 No. 200 400

"BISF STANDARD" white glazed vitreous


22 Wash Hand Basin (685mm x 460mm X 1 No. 3,500 3,500
235mm size) wgite

Dasherkandi Sewerage Project, Cost Estimate for Package 8 23 of 26


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
European type glased porcelin comode
'P' or 'S' type "BISF STANDARD'
(580mmx345mmx410 mm) with low
23 1 set 6,000 6,000
down white vitreous china cistern
including all external fittings
complete:White
Bath room mirror with C.P. screws and
24 hard board backing in Control Building 1 No. 886 886
0.45m X 0.60m size
C.P. towel rail, with all necessary
25 accessories in Control Building 1 No. 750 750
.75m long and 25mm square/round
26 C.P. Soap dish in Control Building 1 No. 240 240
Construction of masonry inspection pits
27 2 No. 84,000
in Control Building.
Galvanised Iron/Food grade PVC tank of
1.20m x 1.20m x 1.20m size or
28 equivalent to 1800 litres capacity in 1 No. 20,064 20,064
Control Building.
16 BWG, over head tank.
External Works
Demolition of existing Sewerage Pump
1 1 No.
Generator
Demolition of existing Sewerage Pump
2 1 No.
Transformer
Demolition of existing Sewage Pump
3 1 No.
House
840,000
Demolition of existing Inlet Screen
5 1 No.
Chambers 1 and 2
6 Demolition of existing Splash Box 1 No.
Demolition of existing manholes 5 No.

Dasherkandi Sewerage Project, Cost Estimate for Package 8 24 of 26


840,000
Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
Demolition of Existing Boundary Walls (2
7 120 sqm
m height, 85 m long)
RCC Bollards 200mm dia, 1200mm in
8 length with 300mm embedment in earth 25 No. 7,000 175,000
3
with 0.60 m base
9 6.00m wide sliding entrance gate 1 No. 30,000 30,000
2.00 m high Security Fence for
10 13 meter 1,500 19,500
Transformer
11 New Boundary Wall 100 meter 4,000 400,000
External 150 mm uPVC Sewer
12 12 meter 1,075 12,900
Connection pipe from WC
14 GRP Open Mesh Flooring & Supports 80 meter 20,000 1,600,000
Stainless Steel Access Stairs(0.8 m
15 10 meter 7,500 75,000
wide)
16 GMS Hand Railing 65 meter 4,500 292,500
17 Screening Skip (0.2 m3 capacity) 1.00 No. 84,000
Manual Bar Screen (2.3m long x 2.4m
18 20 m2 21,000 420,000
wide)
Steel Collection Trough for Screenings
19 1 No. 400,000 400,000
(300mm wide, 250mm deep, 2.5 m long)
3 Nos Concrete Ramp to Control Room
20 2.55 long @ 1V:3 H (1.5m, 2.00m & 8 cum 7,517 60,136
2.50m width)
Concrete site access turning area
(Including access road), 510.00 m2
300 mm thick concrete 155 cum 7,643 1,184,665
21
200 mm thick cement bond granular sub-
105 cum 6,647 697,935
base
600 mm thick selected granular fill 305 cum 149 45,445
22 150mm dia uPVC Site Drainage 455 meter 548 249,231
23 150mm dia uPVC Electrical Ducts 150 meter 548 82,164

Dasherkandi Sewerage Project, Cost Estimate for Package 8 25 of 26


Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
24 600mm x 600mm Drainage Gullys 11 No. 8,400 92,400
Water Connection Hydrants for
25 2 No. 16,800 33,600
screening chamber and wet well
Total (A)= 111,459,455

Dasherkandi Sewerage Project, Cost Estimate for Package 8 26 of 26

You might also like