Professional Documents
Culture Documents
Augus
t,2019
Table of Contents
A: Cost Summary
I: Cost of Package 7 (No. 1: Natun Bazar SLS, No. 2: Banasree SLS, No. 4: Bijoy Sarani SLS)
J: Cost of Package 8 (Gulshan and Banani including Gulshan SLS & Tejgaon SLS, designed by IWM)
Employer’s Cost Estimates2
A: Cost Summary
Regarding the rate analyses the following explanations are to be kept in mind in order to assess the whole process of cost
estimation;
1. As it is a preliminary design for a design-build-operation procurement package, composite items of works have
been considered for cost estimation.
2. The full requirement of a particular item of works/services considered consists of a number of basic work items and
as such the breakdown of the rate analyses in terms of materials, labour and equipment were required and worked
out.
3. The rates and prices covered the full scope of works including Contractor’s equipment, overheads, profit, road
cutting permit fees where applicable, VAT & income tax as admissible, but exclusive of Custom Duties (CD, VAT).
4. For the rates of basic work items the widely used PWD schedule of rates and updated DWASA schedule of rates
have been used extensively.
5. A clear understanding of the process would require one to get through the step by step procedures of the rate
analyses and cost calculations.
6. The soft copies of the rate analyses are provided for easy reference and checking of the basic considerations and
the calculations.
Employer’s Cost Estimates4
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 37,776.80
1.1.2 ø250 mm m 1,493.80
1.1.3 ø300 mm m 866.30
1.1.4 ø350 mm m 380.90
1.1.5 ø400 mm m 390.50
1.1.6 ø450 mm m
1.1.7 ø500 mm m 935.20
1.1.8 ø600 mm m 587.90
1.1.9 ø700 mm m 380.30
1.1.10 ø800 mm m 257.60
1.1.11 ø900 mm m
1.1.12 ø1000 mm m
1.1.13 ø1100 mm m
1.1.14 ø1300 mm m
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 76
1.2.2 ø250 mm nos. 3
1.2.3 ø300 mm nos. 2
1.2.4 ø350 mm nos. 1
1.2.5 ø400 mm nos. 1
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 2
1.2.8 ø600 mm nos. 1
1.2.9 ø700 mm nos. 1
1.2.10 ø800 mm nos. 1
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 1 of 70
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.11 ø900 mm nos.
1.2.12 ø1000 mm nos.
1.2.13 ø1100 mm nos.
1.2.14 ø1300 mm nos.
1.3 Equal and Un Equal Tee of different sizes
1.3.1 200mm x200mm nos. 76
1.3.2 250mm x250mm nos. 3
1.3.3 300mm X 300mm nos. 2
1.3.4 350mm X 350mm nos. 1
1.3.5 400mm X 400mm nos. 1
1.3.6 450mm X 450mm nos.
1.3.7 500mm X 500mm nos. 2
1.3.8 600 mm X 600mm nos. 1
1.3.9 700mm X 700mm nos. 1
1.3.10 800mm x 800mm nos. 1
1.3.11 900mm X 900mm nos.
1.3.12 1000mm X 1000mm nos.
1.3.13 250mm X250mm X 200mm nos. 3
1.3.14 300mm X 300mm X 200mm nos. 2
1.3.15 300mm X 300mm X 250mm nos. 1
1.3.16 400mm X 400mm X 200mm nos. 1
1.3.17 400mm X 400mm X 250mm nos.
1.3.18 400mm X 400mm X 300mm nos. 2
1.3.19 500mm X 500mm X 200mm nos. 1
1.3.20 500mm X 500mm X 300mm nos. 1
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos. 152
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 2 of 70
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4.2 ø250 mm nos. 6
1.4.3 ø300 mm nos. 4
1.4.4 ø350 mm nos. 2
1.4.5 ø400 mm nos. 2
1.4.6 ø450 mm nos.
1.4.7 ø500 mm nos. 4
1.4.8 ø600 mm nos. 2
1.4.9 ø700 mm nos. 2
1.4.10 ø800 mm nos. 2
1.4.11 ø900 mm nos.
1.4.12 ø1000 mm nos.
1.4.13 ø1100 mm nos.
1.4.14 ø1300 mm nos.
1.5 Flanged Adapters
1.5.1 ø200 mm nos. 19
1.5.2 ø250 mm nos. 1
1.5.3 ø300 mm nos. 1
1.5.4 ø350 mm nos.
1.5.5 ø400 mm nos. 1
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos. 1
1.5.8 ø600 mm nos.
1.5.9 ø700 mm nos.
1.5.10 ø800 mm nos. 1
1.5.11 ø900 mm nos. 1
1.5.12 ø1000 mm nos. 1
1.5.13 ø1100 mm nos.
1.5.14 ø1300 mm nos. 1
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 3 of 70
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 4 of 70
Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 5 of 70
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 6 of 70
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.5.2 LS 1 18,489,087 18,489,087.45
Report
3.2.5.3 Design Control Services including documentation LS 1 5,042,478 5,042,478.40
Sub-total B: 134,173,873.70
Total A+B: Sub-total 3:
146,752,674.36
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary
Name of Bidder:
Signature of Bidder:
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 7 of 70
Schedule No. 4 - Installation / Construction and Other works
a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 4,192,933.55 4,192,933.55
4.1.1.2 Advance Payment Guarantee LS 1 4,192,933.55 4,192,933.55
Subtotal 4.1.1 8,385,867.11
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.2 Installation All Risks Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.3 Third Party Liability Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.4 Automobile Liability Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.5 Workers' Compensation LS 1 6,289,400.33 6,289,400.33
4.1.2.6 Employer's Liability LS 1 6,289,400.33 6,289,400.33
4.1.2.7 Contractor's Equipment Insurance LS 1 6,289,400.33 6,289,400.33
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 6,289,400.33 6,289,400.33
Subtotal 4.1.2 50,315,202.64
4.1.3 Site establishment, operation and removal
Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 4,791,924.06 4,791,924.06
workshops, site access and miscellaneous services etc.
Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 4,791,924.06 4,791,924.06
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 4,791,924.06 4,791,924.06
4.1.3.4 Survey instruments LS 1 4,791,924.06 4,791,924.06
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 4,791,924.06 4,791,924.06
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 4,791,924.06 4,791,924.06
Subtotal 4.1.3 28,751,544.36
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 87,452,614.11
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 8 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified below,
including fitting, fixing of all items, road cutting permission fee, temporary road
4.2.3 -
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 9 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 10 of 70
Schedule No. 4 - Installation and Other Services
4.2.3.B.1.1 ø200 mm m -
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -
4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 11 of 70
Schedule No. 4 - Installation and Other Services
4.2.3.B.2.11 ø900 mm m -
4.2.3.B.2.12 ø1000 mm m -
4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -
4.2.3.B.3.11 ø900 mm m -
4.2.3.B.3.12 ø1000 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 12 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 13 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 14 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 15 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 16 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of service connections with GRP pipes including fitting, fixing
of all items, road cutting permission fee, temporary road reinstatement, dismantling
4.2.5 of existing structures, site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 17 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 18 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 19 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.3.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 20 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 21 of 70
Schedule No. 4 - Installation and Other Services
4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -
4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 22 of 70
Schedule No. 4 - Installation and Other Services
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -
4.3.3.B.2.11 ø900 mm m -
4.3.3.B.2.12 ø1000 mm m -
4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -
4.3.3.B.3.11 ø900 mm m -
4.3.3.B.3.12 ø1000 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 23 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 24 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 25 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 26 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 27 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.3.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 28 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 29 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 30 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 31 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 32 of 70
Schedule No. 4 - Installation and Other Services
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 33 of 70
Schedule No. 4 - Installation and Other Services
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 34 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 35 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 36 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 37 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 38 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 39 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 40 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 41 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 42 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 43 of 70
Schedule No. 4 - Installation and Other Services
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 44 of 70
Schedule No. 4 - Installation and Other Services
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 45 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 46 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 47 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 48 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 49 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 50 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 51 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 52 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 53 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 54 of 70
Schedule No. 4 - Installation and Other Services
4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -
4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 55 of 70
Schedule No. 4 - Installation and Other Services
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -
4.5.3.B.2.11 ø900 mm m -
4.5.3.B.2.12 ø1000 mm m -
4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -
4.5.3.B.3.11 ø900 mm m -
4.5.3.B.3.12 ø1000 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 56 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 57 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 58 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 59 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 60 of 70
Schedule No. 4 - Installation and Other Services
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 61 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 62 of 70
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 63 of 70
Schedule No. 5 - Grand Summary
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 64 of 70
Schedule No. 6 - Recommended Spare Parts
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 66 of 70
Schedule No. 7 - Day Work
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 67 of 70
Schedule No. 7 - Day Work
7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 20 675.00 675.00 13,500.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 20 607.50 607.50 12,150.00
clinker): 50kg bag
7.2.3 White Cement kg 50 54.00 54.00 2,700.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 0.50 86,400.00 86,400.00 43,200.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 0.50 87,750.00 87,750.00 43,875.00
7.2.6 MS Sheet M Ton 0.50 114,750.00 114,750.00 57,375.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 1,110 10,800.00 10,800.00 11,988.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 1,110 12,150.00 12,150.00 13,486.50
7.2.9 Imported Earth m3 20 572.50 572.50 11,450.00
7.2.10 Sand (F.M. 0.8) m3 20 525.00 525.00 10,500.00
7.2.11 Sand (F.M. 1.2) m3 10 810.50 810.50 8,105.00
7.2.12 Sand (F.M. 2.5) m3 10 2,384.00 2,384.00 23,840.00
7.2.13 Viti/Filling Sand m3 20 524.50 524.50 10,490.00
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 68 of 70
Schedule No. 7 - Day Work
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 3,466,234.50
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 69 of 70
Schedule No. 8 - O&M Services
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 1 70 of 70
Employer’s Cost Estimates5
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 57,080.60
1.1.2 ø250 mm m 2,797.70
1.1.3 ø300 mm m 1,720.90
1.1.4 ø350 mm m 1,672.30
1.1.5 ø400 mm m 960.10
1.1.6 ø450 mm m 415.10
1.1.7 ø500 mm m 219.20
1.1.8 ø600 mm m 261.30
1.1.9 ø700 mm m 80.60
1.1.10 ø800 mm m
1.1.11 ø900 mm m
1.1.12 ø1000 mm m
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 114
1.2.2 ø250 mm nos. 6
1.2.3 ø300 mm nos. 3
1.2.4 ø350 mm nos. 3
1.2.5 ø400 mm nos. 2
1.2.6 ø450 mm nos. 1
1.2.7 ø500 mm nos. 1
1.2.8 ø600 mm nos. 1
1.2.9 ø700 mm nos. 1
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 1 of 176
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.10 ø800 mm nos.
1.2.11 ø900 mm nos.
1.2.12 ø1000 mm nos.
Equal and Un Equal Tee
1.3
of different sizes
1.3.1 200mm x200mm nos. 114
1.3.2 250mm x250mm nos. 6
1.3.3 300mm X 300mm nos. 3
1.3.4 350mm X 350mm nos. 3
1.3.5 400mm X 400mm nos. 2
1.3.6 450mm X 450mm nos. 1
1.3.7 500mm X 500mm nos. 1
1.3.8 600 mm X 600mm nos. 1
1.3.9 700mm X 700mm nos. 1
1.3.10 800mm x 800mm nos.
1.3.11 900mm X 900mm nos.
1.3.12 1000mm X 1000mm nos.
1.3.13 250mm X250mm X 200mm nos. 6
1.3.14 300mm X 300mm X 200mm nos. 3
1.3.15 300mm X 300mm X 250mm nos. 3
1.3.16 400mm X 400mm X 200mm nos. 2
1.3.17 400mm X 400mm X 250mm nos. 2
1.3.18 400mm X 400mm X 300mm nos. 2
1.3.19 500mm X 500mm X 200mm nos. 1
1.3.20 500mm X 500mm X 300mm nos. 1
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 2 of 176
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos. 228
1.4.2 ø250 mm nos. 12
1.4.3 ø300 mm nos. 6
1.4.4 ø350 mm nos. 6
1.4.5 ø400 mm nos. 4
1.4.6 ø450 mm nos. 2
1.4.7 ø500 mm nos. 2
1.4.8 ø600 mm nos. 2
1.4.9 ø700 mm nos. 2
1.4.10 ø800 mm nos.
1.4.11 ø900 mm nos.
1.4.12 ø1000 mm nos.
1.5 Flanged Adapters
1.5.1 ø200 mm nos. 29
1.5.2 ø250 mm nos. 2
1.5.3 ø300 mm nos. 1
1.5.4 ø350 mm nos. 1
1.5.5 ø400 mm nos. 1
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos. 1
1.5.8 ø600 mm nos. 1
1.5.9 ø700 mm nos. 1
1.5.10 ø800 mm nos.
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 3 of 176
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.5.11 ø900 mm nos.
1.5.12 ø1000 mm nos.
Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 4 of 176
Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 5 of 176
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 6 of 176
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 7 of 176
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 8 of 176
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
Sub-total B: 195,124,936.04
Total A+B: Sub-total 3:
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 213,417,898.79
Grand Summary
Name of Bidder:
Signature of Bidder:
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 9 of 176
Schedule No. 4 - Installation / Construction and Other works
a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 6,097,654.25 6,097,654.25
4.1.1.2 Advance Payment Guarantee LS 1 6,097,654.25 6,097,654.25
Subtotal 4.1.1 12,195,308.50
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.2 Installation All Risks Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.3 Third Party Liability Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.4 Automobile Liability Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.5 Workers' Compensation LS 1 9,146,481.38 9,146,481.38
4.1.2.6 Employer's Liability LS 1 9,146,481.38 9,146,481.38
4.1.2.7 Contractor's Equipment Insurance LS 1 9,146,481.38 9,146,481.38
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 9,146,481.38 9,146,481.38
Subtotal 4.1.2 73,171,851.01
4.1.3 Site establishment, operation and removal
Supply and erect signboard, establish Contractor´s main site offices, welfare
4.1.3.1 LS 1 6,968,747.72 6,968,747.72
facilities, workshops, site access and miscellaneous services etc.
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 10 of 176
Schedule No. 4 - Installation / Construction and Other works
a b c d e f g h=e+f+g i=dxh
Manage generally the site and the above facilities during the implementation
4.1.3.2 LS 1 6,968,747.72 6,968,747.72
period including health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 6,968,747.72 6,968,747.72
4.1.3.4 Survey instruments LS 1 6,968,747.72 6,968,747.72
The Project Manager's / Engineers Office with all operational facilities, operation
4.1.3.5 LS 1 6,968,747.72 6,968,747.72
and maintenance
Removal at the completion of the works of all the established facilities and site
4.1.3.6 LS 1 6,968,747.72 6,968,747.72
restoration
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 11 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 12 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 13 of 176
Schedule No. 4 - Installation and Other Services
4.2.3.B.1.1 ø200 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 14 of 176
Schedule No. 4 - Installation and Other Services
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -
4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 15 of 176
Schedule No. 4 - Installation and Other Services
4.2.3.B.2.11 ø900 mm m -
4.2.3.B.2.12 ø1000 mm m -
4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -
4.2.3.B.3.11 ø900 mm m -
4.2.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 16 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 17 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 18 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 19 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 20 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 21 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 22 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 24 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 25 of 176
Schedule No. 4 - Installation and Other Services
4.3.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.3.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.3.2.5 Development and submission of GIS based As-built drawings LS 1.00 51,400.00 51,400.00
4.3.2.6 Post Construction modelling LS 1.00 6,168.00 6,168.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 26 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 27 of 176
Schedule No. 4 - Installation and Other Services
4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 28 of 176
Schedule No. 4 - Installation and Other Services
4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -
4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -
4.3.3.B.2.11 ø900 mm m -
4.3.3.B.2.12 ø1000 mm m -
4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 29 of 176
Schedule No. 4 - Installation and Other Services
4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -
4.3.3.B.3.11 ø900 mm m -
4.3.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 31 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 32 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 33 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 34 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 35 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 36 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 37 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 38 of 176
Schedule No. 4 - Installation and Other Services
4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 33,187.50 33,187.50
4.4.2.6 Post Construction modelling LS 1.00 3,982.50 3,982.50
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 40 of 176
Schedule No. 4 - Installation and Other Services
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 41 of 176
Schedule No. 4 - Installation and Other Services
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 42 of 176
Schedule No. 4 - Installation and Other Services
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 43 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 44 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 45 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 46 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 47 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 48 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 49 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 50 of 176
Schedule No. 4 - Installation and Other Services
4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 69,175.00 69,175.00
4.4.2.6 Post Construction modelling LS 1.00 8,301.00 8,301.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 51 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 52 of 176
Schedule No. 4 - Installation and Other Services
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 53 of 176
Schedule No. 4 - Installation and Other Services
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 54 of 176
Schedule No. 4 - Installation and Other Services
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 55 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 57 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 59 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 60 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 61 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 62 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 63 of 176
Schedule No. 4 - Installation and Other Services
4.5.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.5.2.5 Development and submission of GIS based As-built drawings LS 1.00 98,887.50 98,887.50
4.5.2.6 Post Construction modelling LS 1.00 11,866.50 11,866.50
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 64 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 65 of 176
Schedule No. 4 - Installation and Other Services
4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 66 of 176
Schedule No. 4 - Installation and Other Services
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -
4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -
4.5.3.B.2.11 ø900 mm m -
4.5.3.B.2.12 ø1000 mm m -
4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 67 of 176
Schedule No. 4 - Installation and Other Services
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -
4.5.3.B.3.11 ø900 mm m -
4.5.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 68 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 70 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 72 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 73 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 74 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 76 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.6 INSTALLATION of LOOP 205
4.6.1 Miscellaneous works during implementation
4.6.1.1 Setting-out LS 1.00 81,650.00 81,650.00
4.6.1.2 General works and site tests LS 1.00 163,300.00 163,300.00
4.6.2 Commissioning and final inspection /Tests
4.6.2.5 Development and submission of GIS based As-built drawings LS 1.00 102,062.50 102,062.50
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 77 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 78 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.6.3.B.1.1 ø200 mm m -
4.6.3.B.1.2 ø250 mm m -
4.6.3.B.1.3 ø300 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 79 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.6.3.B.1.4 ø350 mm m -
4.6.3.B.1.5 ø400 mm m -
4.6.3.B.1.6 ø450 mm m -
4.6.3.B.1.7 ø500 mm m -
4.6.3.B.1.8 ø600 mm m -
4.6.3.B.1.9 ø700 mm m -
4.6.3.B.1.10 ø800 mm m -
4.6.3.B.1.11 ø900 mm m -
4.6.3.B.1.12 ø1000 mm m -
4.6.3.B.2.1 ø200 mm m -
4.6.3.B.2.2 ø250 mm m -
4.6.3.B.2.3 ø300 mm m -
4.6.3.B.2.4 ø350 mm m -
4.6.3.B.2.5 ø400 mm m -
4.6.3.B.2.6 ø450 mm m -
4.6.3.B.2.7 ø500 mm m -
4.6.3.B.2.8 ø600 mm m -
4.6.3.B.2.9 ø700 mm m -
4.6.3.B.2.10 ø800 mm m -
4.6.3.B.2.11 ø900 mm m -
4.6.3.B.2.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 80 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.6.3.B.3.1 ø200 mm m -
4.6.3.B.3.2 ø250 mm m -
4.6.3.B.3.3 ø300 mm m -
4.6.3.B.3.4 ø350 mm m -
4.6.3.B.3.5 ø400 mm m -
4.6.3.B.3.6 ø450 mm m -
4.6.3.B.3.7 ø500 mm m -
4.6.3.B.3.8 ø600 mm m -
4.6.3.B.3.9 ø700 mm m -
4.6.3.B.3.10 ø800 mm m -
4.6.3.B.3.11 ø900 mm m -
4.6.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 81 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 82 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 84 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 85 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 87 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 88 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 89 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 90 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 91 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 92 of 176
Schedule No. 4 - Installation and Other Services
4.7.3.B.1.1 ø200 mm m -
4.7.3.B.1.2 ø250 mm m -
4.7.3.B.1.3 ø300 mm m -
4.7.3.B.1.4 ø350 mm m -
4.7.3.B.1.5 ø400 mm m -
4.7.3.B.1.6 ø450 mm m -
4.7.3.B.1.7 ø500 mm m -
4.7.3.B.1.8 ø600 mm m -
4.7.3.B.1.9 ø700 mm m -
4.7.3.B.1.10 ø800 mm m -
4.7.3.B.1.11 ø900 mm m -
4.7.3.B.1.12 ø1000 mm m -
4.7.3.B.2.1 ø200 mm m -
4.7.3.B.2.2 ø250 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 93 of 176
Schedule No. 4 - Installation and Other Services
4.7.3.B.2.3 ø300 mm m -
4.7.3.B.2.4 ø350 mm m -
4.7.3.B.2.5 ø400 mm m -
4.7.3.B.2.6 ø450 mm m -
4.7.3.B.2.7 ø500 mm m -
4.7.3.B.2.8 ø600 mm m -
4.7.3.B.2.9 ø700 mm m -
4.7.3.B.2.10 ø800 mm m -
4.7.3.B.2.11 ø900 mm m -
4.7.3.B.2.12 ø1000 mm m -
4.7.3.B.3.1 ø200 mm m -
4.7.3.B.3.2 ø250 mm m -
4.7.3.B.3.3 ø300 mm m -
4.7.3.B.3.4 ø350 mm m -
4.7.3.B.3.5 ø400 mm m -
4.7.3.B.3.6 ø450 mm m -
4.7.3.B.3.7 ø500 mm m -
4.7.3.B.3.8 ø600 mm m -
4.7.3.B.3.9 ø700 mm m -
4.7.3.B.3.10 ø800 mm m -
4.7.3.B.3.11 ø900 mm m -
4.7.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 94 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 95 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 96 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 97 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 98 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 99 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 100 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 101 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 102 of 176
Schedule No. 4 - Installation and Other Services
4.8.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 103 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 104 of 176
Schedule No. 4 - Installation and Other Services
4.8.3.B.1.1 ø200 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 105 of 176
Schedule No. 4 - Installation and Other Services
4.8.3.B.1.2 ø250 mm m -
4.8.3.B.1.3 ø300 mm m -
4.8.3.B.1.4 ø350 mm m -
4.8.3.B.1.5 ø400 mm m -
4.8.3.B.1.6 ø450 mm m -
4.8.3.B.1.7 ø500 mm m -
4.8.3.B.1.8 ø600 mm m -
4.8.3.B.1.9 ø700 mm m -
4.8.3.B.1.10 ø800 mm m -
4.8.3.B.1.11 ø900 mm m -
4.8.3.B.1.12 ø1000 mm m -
4.8.3.B.2.1 ø200 mm m -
4.8.3.B.2.2 ø250 mm m -
4.8.3.B.2.3 ø300 mm m -
4.8.3.B.2.4 ø350 mm m -
4.8.3.B.2.5 ø400 mm m -
4.8.3.B.2.6 ø450 mm m -
4.8.3.B.2.7 ø500 mm m -
4.8.3.B.2.8 ø600 mm m -
4.8.3.B.2.9 ø700 mm m -
4.8.3.B.2.10 ø800 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 106 of 176
Schedule No. 4 - Installation and Other Services
4.8.3.B.2.11 ø900 mm m -
4.8.3.B.2.12 ø1000 mm m -
4.8.3.B.3.1 ø200 mm m -
4.8.3.B.3.2 ø250 mm m -
4.8.3.B.3.3 ø300 mm m -
4.8.3.B.3.4 ø350 mm m -
4.8.3.B.3.5 ø400 mm m -
4.8.3.B.3.6 ø450 mm m -
4.8.3.B.3.7 ø500 mm m -
4.8.3.B.3.8 ø600 mm m -
4.8.3.B.3.9 ø700 mm m -
4.8.3.B.3.10 ø800 mm m -
4.8.3.B.3.11 ø900 mm m -
4.8.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 107 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 108 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 109 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 110 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 111 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 112 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 113 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 115 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 116 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.9 INSTALLATION of LOOP 208
4.9.1 Miscellaneous works during implementation
4.9.1.1 Setting-out LS 1.00 283,304.00 283,304.00
4.9.1.2 General works and site tests LS 1.00 566,608.00 566,608.00
4.9.2 Commissioning and final inspection /Tests
4.9.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.9.2.5 Development and submission of GIS based As-built drawings LS 1.00 354,130.00 354,130.00
4.9.2.6 Post Construction modelling LS 1.00 42,495.60 42,495.60
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 117 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 118 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.9.3.B.1.1 ø200 mm m -
4.9.3.B.1.2 ø250 mm m -
4.9.3.B.1.3 ø300 mm m -
4.9.3.B.1.4 ø350 mm m -
4.9.3.B.1.5 ø400 mm m -
4.9.3.B.1.6 ø450 mm m -
4.9.3.B.1.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 119 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.9.3.B.1.8 ø600 mm m -
4.9.3.B.1.9 ø700 mm m -
4.9.3.B.1.10 ø800 mm m -
4.9.3.B.1.11 ø900 mm m -
4.9.3.B.1.12 ø1000 mm m -
4.9.3.B.2.1 ø200 mm m -
4.9.3.B.2.2 ø250 mm m -
4.9.3.B.2.3 ø300 mm m -
4.9.3.B.2.4 ø350 mm m -
4.9.3.B.2.5 ø400 mm m -
4.9.3.B.2.6 ø450 mm m -
4.9.3.B.2.7 ø500 mm m -
4.9.3.B.2.8 ø600 mm m -
4.9.3.B.2.9 ø700 mm m -
4.9.3.B.2.10 ø800 mm m -
4.9.3.B.2.11 ø900 mm m -
4.9.3.B.2.12 ø1000 mm m -
4.9.3.B.3.1 ø200 mm m -
4.9.3.B.3.2 ø250 mm m -
4.9.3.B.3.3 ø300 mm m -
4.9.3.B.3.4 ø350 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 120 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.9.3.B.3.5 ø400 mm m -
4.9.3.B.3.6 ø450 mm m -
4.9.3.B.3.7 ø500 mm m -
4.9.3.B.3.8 ø600 mm m -
4.9.3.B.3.9 ø700 mm m -
4.9.3.B.3.10 ø800 mm m -
4.9.3.B.3.11 ø900 mm m -
4.9.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 121 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 123 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 125 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 126 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 128 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 129 of 176
Schedule No. 4 - Installation and Other Services
4.10.2.5 Development and submission of GIS based As-built drawings LS 1.00 132,470.00 132,470.00
4.10.2.6 Post Construction modelling LS 1.00 15,896.40 15,896.40
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 130 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 131 of 176
Schedule No. 4 - Installation and Other Services
4.10.3.B.1.1 ø200 mm m -
4.10.3.B.1.2 ø250 mm m -
4.10.3.B.1.3 ø300 mm m -
4.10.3.B.1.4 ø350 mm m -
4.10.3.B.1.5 ø400 mm m -
4.10.3.B.1.6 ø450 mm m -
4.10.3.B.1.7 ø500 mm m -
4.10.3.B.1.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 132 of 176
Schedule No. 4 - Installation and Other Services
4.10.3.B.1.9 ø700 mm m -
4.10.3.B.1.10 ø800 mm m -
4.10.3.B.1.11 ø900 mm m -
4.10.3.B.1.12 ø1000 mm m -
4.10.3.B.2.1 ø200 mm m -
4.10.3.B.2.2 ø250 mm m -
4.10.3.B.2.3 ø300 mm m -
4.10.3.B.2.4 ø350 mm m -
4.10.3.B.2.5 ø400 mm m -
4.10.3.B.2.6 ø450 mm m -
4.10.3.B.2.7 ø500 mm m -
4.10.3.B.2.8 ø600 mm m -
4.10.3.B.2.9 ø700 mm m -
4.10.3.B.2.10 ø800 mm m -
4.10.3.B.2.11 ø900 mm m -
4.10.3.B.2.12 ø1000 mm m -
4.10.3.B.3.1 ø200 mm m -
4.10.3.B.3.2 ø250 mm m -
4.10.3.B.3.3 ø300 mm m -
4.10.3.B.3.4 ø350 mm m -
4.10.3.B.3.5 ø400 mm m -
4.10.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 133 of 176
Schedule No. 4 - Installation and Other Services
4.10.3.B.3.7 ø500 mm m -
4.10.3.B.3.8 ø600 mm m -
4.10.3.B.3.9 ø700 mm m -
4.10.3.B.3.10 ø800 mm m -
4.10.3.B.3.11 ø900 mm m -
4.10.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 135 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 136 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 137 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 138 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 139 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 141 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 142 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 143 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 144 of 176
Schedule No. 4 - Installation and Other Services
4.11.3.B.1.1 ø200 mm m -
4.11.3.B.1.2 ø250 mm m -
4.11.3.B.1.3 ø300 mm m -
4.11.3.B.1.4 ø350 mm m -
4.11.3.B.1.5 ø400 mm m -
4.11.3.B.1.6 ø450 mm m -
4.11.3.B.1.7 ø500 mm m -
4.11.3.B.1.8 ø600 mm m -
4.11.3.B.1.9 ø700 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 145 of 176
Schedule No. 4 - Installation and Other Services
4.11.3.B.1.10 ø800 mm m -
4.11.3.B.1.11 ø900 mm m -
4.11.3.B.1.12 ø1000 mm m -
4.11.3.B.2.1 ø200 mm m -
4.11.3.B.2.2 ø250 mm m -
4.11.3.B.2.3 ø300 mm m -
4.11.3.B.2.4 ø350 mm m -
4.11.3.B.2.5 ø400 mm m -
4.11.3.B.2.6 ø450 mm m -
4.11.3.B.2.7 ø500 mm m -
4.11.3.B.2.8 ø600 mm m -
4.11.3.B.2.9 ø700 mm m -
4.11.3.B.2.10 ø800 mm m -
4.11.3.B.2.11 ø900 mm m -
4.11.3.B.2.12 ø1000 mm m -
4.11.3.B.3.1 ø200 mm m -
4.11.3.B.3.2 ø250 mm m -
4.11.3.B.3.3 ø300 mm m -
4.11.3.B.3.4 ø350 mm m -
4.11.3.B.3.5 ø400 mm m -
4.11.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 146 of 176
Schedule No. 4 - Installation and Other Services
4.11.3.B.3.7 ø500 mm m -
4.11.3.B.3.8 ø600 mm m -
4.11.3.B.3.9 ø700 mm m -
4.11.3.B.3.10 ø800 mm m -
4.11.3.B.3.11 ø900 mm m -
4.11.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 147 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 148 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 149 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 150 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 151 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 152 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 153 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 154 of 176
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 155 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.12 INSTALLATION of LOOP 211
4.12.1 Miscellaneous works during implementation
4.12.1.1 Setting-out LS 1.00 171,126.00 171,126.00
4.12.1.2 General works and site tests LS 1.00 342,252.00 342,252.00
4.12.2 Commissioning and final inspection /Tests
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 156 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 157 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.12.3.B.1.1 ø200 mm m -
4.12.3.B.1.2 ø250 mm m -
4.12.3.B.1.3 ø300 mm m -
4.12.3.B.1.4 ø350 mm m -
4.12.3.B.1.5 ø400 mm m -
4.12.3.B.1.6 ø450 mm m -
4.12.3.B.1.7 ø500 mm m -
4.12.3.B.1.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 158 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.12.3.B.1.9 ø700 mm m -
4.12.3.B.1.10 ø800 mm m -
4.12.3.B.1.11 ø900 mm m -
4.12.3.B.1.12 ø1000 mm m -
4.12.3.B.2.1 ø200 mm m -
4.12.3.B.2.2 ø250 mm m -
4.12.3.B.2.3 ø300 mm m -
4.12.3.B.2.4 ø350 mm m -
4.12.3.B.2.5 ø400 mm m -
4.12.3.B.2.6 ø450 mm m -
4.12.3.B.2.7 ø500 mm m -
4.12.3.B.2.8 ø600 mm m -
4.12.3.B.2.9 ø700 mm m -
4.12.3.B.2.10 ø800 mm m -
4.12.3.B.2.11 ø900 mm m -
4.12.3.B.2.12 ø1000 mm m -
4.12.3.B.3.1 ø200 mm m -
4.12.3.B.3.2 ø250 mm m -
4.12.3.B.3.3 ø300 mm m -
4.12.3.B.3.4 ø350 mm m -
4.12.3.B.3.5 ø400 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 159 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.12.3.B.3.6 ø450 mm m -
4.12.3.B.3.7 ø500 mm m -
4.12.3.B.3.8 ø600 mm m -
4.12.3.B.3.9 ø700 mm m -
4.12.3.B.3.10 ø800 mm m -
4.12.3.B.3.11 ø900 mm m -
4.12.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 160 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 161 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 162 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 163 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 165 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 166 of 176
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 168 of 176
Schedule No. 5 - Grand Summary
Name of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 169 of 176
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 170 of 176
Schedule No. 6 - Recommended Spare Parts
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 172 of 176
Schedule No. 7 - Day Work
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 173 of 176
Schedule No. 7 - Day Work
7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 100 675.00 675.00 67,500.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 100 607.50 607.50 60,750.00
clinker): 50kg bag
7.2.3 White Cement kg 250 54.00 54.00 13,500.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 1 86,400.00 86,400.00 86,400.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 1 87,750.00 87,750.00 87,750.00
7.2.6 MS Sheet M Ton 1 114,750.00 114,750.00 57,375.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 5,000 10,800.00 10,800.00 54,000.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 5,000 12,150.00 12,150.00 60,750.00
7.2.9 Imported Earth m3 100 572.50 572.50 57,250.00
7.2.10 Sand (F.M. 0.8) m3 100 525.00 525.00 52,500.00
7.2.11 Sand (F.M. 1.2) m3 50 810.50 810.50 40,525.00
7.2.12 Sand (F.M. 2.5) m3 50 2,384.00 2,384.00 119,200.00
7.2.13 Viti/Filling Sand m3 100 524.50 524.50 52,450.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 174 of 176
Schedule No. 7 - Day Work
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 14,046,204.00
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 175 of 176
Schedule No. 8 - O&M Services
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 2 176 of 176
Employer’s Cost Estimates6
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 140,169.40
1.1.2 ø250 mm m 7,564.20
1.1.3 ø300 mm m 4,851.90
1.1.4 ø350 mm m 4,182.20
1.1.5 ø400 mm m 3,142.20
1.1.6 ø450 mm m 173.90
1.1.7 ø500 mm m 3,882.10
1.1.8 ø600 mm m 4,263.80
1.1.9 ø700 mm m 3,847.20
1.1.10 ø800 mm m 742.30
1.1.11 ø900 mm m 580.20
1.1.12 ø1000 mm m 451.20
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 280
1.2.2 ø250 mm nos. 15
1.2.3 ø300 mm nos. 10
1.2.4 ø350 mm nos. 8
1.2.5 ø400 mm nos. 6
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 9
1.2.8 ø600 mm nos. 9
1.2.9 ø700 mm nos. 9
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 1 of 199
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.10 ø800 mm nos. 1
1.2.11 ø900 mm nos. 1
1.2.12 ø1000 mm nos. 1
1.3 Equal and Un Equal Tee of different sizes
1.3.1 200mm x200mm nos. 280
1.3.2 250mm x250mm nos. 15
1.3.3 300mm X 300mm nos. 10
1.3.4 350mm X 350mm nos. 8
1.3.5 400mm X 400mm nos. 6
1.3.6 450mm X 450mm nos.
1.3.7 500mm X 500mm nos. 9
1.3.8 600 mm X 600mm nos. 9
1.3.9 700mm X 700mm nos. 9
1.3.10 800mm x 800mm nos. 1
1.3.11 900mm X 900mm nos. 1
1.3.12 1000mm X 1000mm nos. 1
1.3.13 250mm X250mm X 200mm nos. 15
1.3.14 300mm X 300mm X 200mm nos. 10
1.3.15 300mm X 300mm X 250mm nos. 10
1.3.16 400mm X 400mm X 200mm nos. 6
1.3.17 400mm X 400mm X 250mm nos. 6
1.3.18 400mm X 400mm X 300mm nos. 6
1.3.19 500mm X 500mm X 200mm nos. 9
1.3.20 500mm X 500mm X 300mm nos. 9
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 2 of 199
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos. 560
1.4.2 ø250 mm nos. 30
1.4.3 ø300 mm nos. 20
1.4.4 ø350 mm nos. 16
1.4.5 ø400 mm nos. 12
1.4.6 ø450 mm nos.
1.4.7 ø500 mm nos. 18
1.4.8 ø600 mm nos. 18
1.4.9 ø700 mm nos. 18
1.4.10 ø800 mm nos. 2
1.4.11 ø900 mm nos. 2
1.4.12 ø1000 mm nos. 2
1.5 Flanged Adapters
1.5.1 ø200 mm nos. 70
1.5.2 ø250 mm nos. 4
1.5.3 ø300 mm nos. 3
1.5.4 ø350 mm nos. 2
1.5.5 ø400 mm nos. 2
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos. 3
1.5.8 ø600 mm nos. 3
1.5.9 ø700 mm nos. 3
1.5.10 ø800 mm nos.
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 3 of 199
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.5.11 ø900 mm nos.
1.5.12 ø1000 mm nos.
Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 4 of 199
Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 5 of 199
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 6 of 199
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 7 of 199
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 8 of 199
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
Sub-total B: 586,583,863.61
Total A+B: Sub-total 3:
641,576,100.82
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary
Name of Bidder:
Signature of Bidder:
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 9 of 199
Schedule No. 4 - Installation / Construction and Other works
a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 18,330,745.74 18,330,745.74
4.1.1.2 Advance Payment Guarantee LS 1 18,330,745.74 18,330,745.74
Subtotal 4.1.1 36,661,491.48
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.2 Installation All Risks Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.3 Third Party Liability Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.4 Automobile Liability Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.5 Workers' Compensation LS 1 27,496,118.61 27,496,118.61
4.1.2.6 Employer's Liability LS 1 27,496,118.61 27,496,118.61
4.1.2.7 Contractor's Equipment Insurance LS 1 27,496,118.61 27,496,118.61
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 27,496,118.61 27,496,118.61
Subtotal 4.1.2 219,968,948.86
4.1.3 Site establishment, operation and removal
Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 20,949,423.70 20,949,423.70
workshops, site access and miscellaneous services etc.
Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 20,949,423.70 20,949,423.70
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 20,949,423.70 20,949,423.70
4.1.3.4 Survey instruments LS 1 20,949,423.70 20,949,423.70
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 20,949,423.70 20,949,423.70
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 10 of 199
Schedule No. 4 - Installation / Construction and Other works
a b c d e f g h=e+f+g i=dxh
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 20,949,423.70 20,949,423.70
Subtotal 4.1.3 125,696,542.20
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 382,326,982.54
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 11 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.2 INSTALLATION of LOOP 301
4.2.1 Miscellaneous works during implementation
4.2.1.1 Setting-out LS 1.00 181,494.00 181,494.00
4.2.1.2 General works and site tests LS 1.00 362,988.00 362,988.00
4.2.2 Commissioning and final inspection /Tests
4.2.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.2.2.5 Development and submission of GIS based As-built drawings LS 1.00 226,867.50 226,867.50
4.2.2.6 Post Construction modelling LS 1.00 27,224.10 27,224.10
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 12 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 13 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.2.3.B.1.1 ø200 mm m -
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 14 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -
4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -
4.2.3.B.2.11 ø900 mm m -
4.2.3.B.2.12 ø1000 mm m -
4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 15 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -
4.2.3.B.3.11 ø900 mm m -
4.2.3.B.3.12 ø1000 mm m -
Supply and Installation of RCC Manholes chambers in accordance
with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.2.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.
4.2.4.A Normal Manhole Rectangular or circular
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 16 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 17 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 18 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 19 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 20 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 21 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 22 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 23 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 24 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.3 INSTALLATION of LOOP 302
4.3.1 Miscellaneous works during implementation
4.3.1.1 Setting-out LS 1.00 126,930.00 126,930.00
4.3.1.2 General works and site tests LS 1.00 253,860.00 253,860.00
4.3.2 Commissioning and final inspection /Tests
4.3.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.3.2.5 Development and submission of GIS based As-built drawings LS 1.00 158,662.50 158,662.50
4.3.2.6 Post Construction modelling LS 1.00 19,039.50 19,039.50
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 25 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 26 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 27 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -
4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -
4.3.3.B.2.11 ø900 mm m -
4.3.3.B.2.12 ø1000 mm m -
4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 28 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -
4.3.3.B.3.11 ø900 mm m -
4.3.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 29 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 30 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 31 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 32 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 33 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 34 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 35 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 36 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 37 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.4 INSTALLATION of LOOP 303
4.4.1 Miscellaneous works during implementation
4.4.1.1 Setting-out LS 1.00 171,278.00 171,278.00
4.4.1.2 General works and site tests LS 1.00 342,556.00 342,556.00
4.4.2 Commissioning and final inspection /Tests
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.4.2.5 Development and submission of GIS based As-built drawings LS 1.00 214,097.50 214,097.50
4.4.2.6 Post Construction modelling LS 1.00 25,691.70 25,691.70
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 38 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 39 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 40 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 41 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 42 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 43 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 44 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 45 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 47 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 48 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 49 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 50 of 199
Schedule No. 4 - Installation and Other Services
4.4.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 51 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 52 of 199
Schedule No. 4 - Installation and Other Services
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 53 of 199
Schedule No. 4 - Installation and Other Services
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 54 of 199
Schedule No. 4 - Installation and Other Services
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 55 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 56 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 57 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 60 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 61 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 62 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 63 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.5 INSTALLATION of LOOP 305
4.5.1 Miscellaneous works during implementation
4.5.1.1 Setting-out LS 1.00 131,044.00 131,044.00
4.5.1.2 General works and site tests LS 1.00 262,088.00 262,088.00
4.5.2 Commissioning and final inspection /Tests
4.5.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
Development and submission of Operation and Maintenance
4.5.2.4 LS 1.00 7,500.00 7,500.00
manuals
4.5.2.5 Development and submission of GIS based As-built drawings LS 1.00 163,805.00 163,805.00
4.5.2.6 Post Construction modelling LS 1.00 19,656.60 19,656.60
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 64 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 65 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 66 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -
4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -
4.5.3.B.2.11 ø900 mm m -
4.5.3.B.2.12 ø1000 mm m -
4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 67 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -
4.5.3.B.3.11 ø900 mm m -
4.5.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 68 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 69 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 71 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 72 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 73 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 74 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 75 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 76 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 77 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 78 of 199
Schedule No. 4 - Installation and Other Services
4.6.3.B.1.1 ø200 mm m -
4.6.3.B.1.2 ø250 mm m -
4.6.3.B.1.3 ø300 mm m -
4.6.3.B.1.4 ø350 mm m -
4.6.3.B.1.5 ø400 mm m -
4.6.3.B.1.6 ø450 mm m -
4.6.3.B.1.7 ø500 mm m -
4.6.3.B.1.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 79 of 199
Schedule No. 4 - Installation and Other Services
4.6.3.B.1.9 ø700 mm m -
4.6.3.B.1.10 ø800 mm m -
4.6.3.B.1.11 ø900 mm m -
4.6.3.B.1.12 ø1000 mm m -
4.6.3.B.2.1 ø200 mm m -
4.6.3.B.2.2 ø250 mm m -
4.6.3.B.2.3 ø300 mm m -
4.6.3.B.2.4 ø350 mm m -
4.6.3.B.2.5 ø400 mm m -
4.6.3.B.2.6 ø450 mm m -
4.6.3.B.2.7 ø500 mm m -
4.6.3.B.2.8 ø600 mm m -
4.6.3.B.2.9 ø700 mm m -
4.6.3.B.2.10 ø800 mm m -
4.6.3.B.2.11 ø900 mm m -
4.6.3.B.2.12 ø1000 mm m -
4.6.3.B.3.1 ø200 mm m -
4.6.3.B.3.2 ø250 mm m -
4.6.3.B.3.3 ø300 mm m -
4.6.3.B.3.4 ø350 mm m -
4.6.3.B.3.5 ø400 mm m -
4.6.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 80 of 199
Schedule No. 4 - Installation and Other Services
4.6.3.B.3.7 ø500 mm m -
4.6.3.B.3.8 ø600 mm m -
4.6.3.B.3.9 ø700 mm m -
4.6.3.B.3.10 ø800 mm m -
4.6.3.B.3.11 ø900 mm m -
4.6.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 82 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 83 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 84 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 85 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 86 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 88 of 199
Schedule No. 4 - Installation and Other Services
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 89 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.7 INSTALLATION of LOOP 307
4.7.1 Miscellaneous works during implementation
4.7.1.1 Setting-out LS 1.00 388,136.00 388,136.00
4.7.1.2 General works and site tests LS 1.00 776,272.00 776,272.00
4.7.2 Commissioning and final inspection /Tests
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 91 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.7.3.B.1.1 ø200 mm m -
4.7.3.B.1.2 ø250 mm m -
4.7.3.B.1.3 ø300 mm m -
4.7.3.B.1.4 ø350 mm m -
4.7.3.B.1.5 ø400 mm m -
4.7.3.B.1.6 ø450 mm m -
4.7.3.B.1.7 ø500 mm m -
4.7.3.B.1.8 ø600 mm m -
4.7.3.B.1.9 ø700 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 92 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.7.3.B.1.10 ø800 mm m -
4.7.3.B.1.11 ø900 mm m -
4.7.3.B.1.12 ø1000 mm m -
4.7.3.B.2.1 ø200 mm m -
4.7.3.B.2.2 ø250 mm m -
4.7.3.B.2.3 ø300 mm m -
4.7.3.B.2.4 ø350 mm m -
4.7.3.B.2.5 ø400 mm m -
4.7.3.B.2.6 ø450 mm m -
4.7.3.B.2.7 ø500 mm m -
4.7.3.B.2.8 ø600 mm m -
4.7.3.B.2.9 ø700 mm m -
4.7.3.B.2.10 ø800 mm m -
4.7.3.B.2.11 ø900 mm m -
4.7.3.B.2.12 ø1000 mm m -
4.7.3.B.3.1 ø200 mm m -
4.7.3.B.3.2 ø250 mm m -
4.7.3.B.3.3 ø300 mm m -
4.7.3.B.3.4 ø350 mm m -
4.7.3.B.3.5 ø400 mm m -
4.7.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 93 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.7.3.B.3.7 ø500 mm m -
4.7.3.B.3.8 ø600 mm m -
4.7.3.B.3.9 ø700 mm m -
4.7.3.B.3.10 ø800 mm m -
4.7.3.B.3.11 ø900 mm m -
4.7.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 94 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 97 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 99 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 102 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.8 INSTALLATION of LOOP 308
4.8.1 Miscellaneous works during implementation
4.8.1.1 Setting-out LS 1.00 67,626.00 67,626.00
4.8.1.2 General works and site tests LS 1.00 135,252.00 135,252.00
4.8.2 Commissioning and final inspection /Tests
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 103 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 104 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.8.3.B.1.1 ø200 mm m -
4.8.3.B.1.2 ø250 mm m -
4.8.3.B.1.3 ø300 mm m -
4.8.3.B.1.4 ø350 mm m -
4.8.3.B.1.5 ø400 mm m -
4.8.3.B.1.6 ø450 mm m -
4.8.3.B.1.7 ø500 mm m -
4.8.3.B.1.8 ø600 mm m -
4.8.3.B.1.9 ø700 mm m -
4.8.3.B.1.10 ø800 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 105 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.8.3.B.1.11 ø900 mm m -
4.8.3.B.1.12 ø1000 mm m -
4.8.3.B.2.1 ø200 mm m -
4.8.3.B.2.2 ø250 mm m -
4.8.3.B.2.3 ø300 mm m -
4.8.3.B.2.4 ø350 mm m -
4.8.3.B.2.5 ø400 mm m -
4.8.3.B.2.6 ø450 mm m -
4.8.3.B.2.7 ø500 mm m -
4.8.3.B.2.8 ø600 mm m -
4.8.3.B.2.9 ø700 mm m -
4.8.3.B.2.10 ø800 mm m -
4.8.3.B.2.11 ø900 mm m -
4.8.3.B.2.12 ø1000 mm m -
4.8.3.B.3.1 ø200 mm m -
4.8.3.B.3.2 ø250 mm m -
4.8.3.B.3.3 ø300 mm m -
4.8.3.B.3.4 ø350 mm m -
4.8.3.B.3.5 ø400 mm m -
4.8.3.B.3.6 ø450 mm m -
4.8.3.B.3.7 ø500 mm m -
4.8.3.B.3.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 106 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.8.3.B.3.9 ø700 mm m -
4.8.3.B.3.10 ø800 mm m -
4.8.3.B.3.11 ø900 mm m -
4.8.3.B.3.12 ø1000 mm m -
Supply and Installation of RCC Manholes chambers in accordance with
the technical specification and the standard detailed drawings, of any
diameter/ size and to the depths specified below, including fitting,
fixing of all items, road cutting permission fee, temporary road
4.8.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.
4.8.4.A Normal Manhole Rectangular or circular
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 107 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 108 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 109 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 110 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 111 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 112 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 113 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 114 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.9 INSTALLATION of LOOP 309
4.9.1 Miscellaneous works during implementation
4.9.1.1 Setting-out LS 1.00 200,400.00 200,400.00
4.9.1.2 General works and site tests LS 1.00 400,800.00 400,800.00
4.9.2 Commissioning and final inspection /Tests
4.9.2.3 Training of Employer's staff on operation and maintenance LS 1.00 15,000.00 15,000.00
4.9.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.9.2.5 Development and submission of GIS based As-built drawings LS 1.00 250,500.00 250,500.00
4.9.2.6 Post Construction modelling LS 1.00 30,060.00 30,060.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 115 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 116 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.9.3.B.1.1 ø200 mm m -
4.9.3.B.1.2 ø250 mm m -
4.9.3.B.1.3 ø300 mm m -
4.9.3.B.1.4 ø350 mm m -
4.9.3.B.1.5 ø400 mm m -
4.9.3.B.1.6 ø450 mm m -
4.9.3.B.1.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 117 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.9.3.B.1.8 ø600 mm m -
4.9.3.B.1.9 ø700 mm m -
4.9.3.B.1.10 ø800 mm m -
4.9.3.B.1.11 ø900 mm m -
4.9.3.B.1.12 ø1000 mm m -
4.9.3.B.2.1 ø200 mm m -
4.9.3.B.2.2 ø250 mm m -
4.9.3.B.2.3 ø300 mm m -
4.9.3.B.2.4 ø350 mm m -
4.9.3.B.2.5 ø400 mm m -
4.9.3.B.2.6 ø450 mm m -
4.9.3.B.2.7 ø500 mm m -
4.9.3.B.2.8 ø600 mm m -
4.9.3.B.2.9 ø700 mm m -
4.9.3.B.2.10 ø800 mm m -
4.9.3.B.2.11 ø900 mm m -
4.9.3.B.2.12 ø1000 mm m -
4.9.3.B.3.1 ø200 mm m -
4.9.3.B.3.2 ø250 mm m -
4.9.3.B.3.3 ø300 mm m -
4.9.3.B.3.4 ø350 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 118 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.9.3.B.3.5 ø400 mm m -
4.9.3.B.3.6 ø450 mm m -
4.9.3.B.3.7 ø500 mm m -
4.9.3.B.3.8 ø600 mm m -
4.9.3.B.3.9 ø700 mm m -
4.9.3.B.3.10 ø800 mm m -
4.9.3.B.3.11 ø900 mm m -
4.9.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 119 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 121 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 123 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 124 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 127 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.10 INSTALLATION of LOOP 310
4.10.1 Miscellaneous works during implementation
4.10.1.1 Setting-out LS 1.00 332,354.00 332,354.00
4.10.1.2 General works and site tests LS 1.00 664,708.00 664,708.00
4.10.2 Commissioning and final inspection /Tests
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 128 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 129 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.10.3.B.1.1 ø200 mm m -
4.10.3.B.1.2 ø250 mm m -
4.10.3.B.1.3 ø300 mm m -
4.10.3.B.1.4 ø350 mm m -
4.10.3.B.1.5 ø400 mm m -
4.10.3.B.1.6 ø450 mm m -
4.10.3.B.1.7 ø500 mm m -
4.10.3.B.1.8 ø600 mm m -
4.10.3.B.1.9 ø700 mm m -
4.10.3.B.1.10 ø800 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 130 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.10.3.B.1.11 ø900 mm m -
4.10.3.B.1.12 ø1000 mm m -
4.10.3.B.2.1 ø200 mm m -
4.10.3.B.2.2 ø250 mm m -
4.10.3.B.2.3 ø300 mm m -
4.10.3.B.2.4 ø350 mm m -
4.10.3.B.2.5 ø400 mm m -
4.10.3.B.2.6 ø450 mm m -
4.10.3.B.2.7 ø500 mm m -
4.10.3.B.2.8 ø600 mm m -
4.10.3.B.2.9 ø700 mm m -
4.10.3.B.2.10 ø800 mm m -
4.10.3.B.2.11 ø900 mm m -
4.10.3.B.2.12 ø1000 mm m -
4.10.3.B.3.1 ø200 mm m -
4.10.3.B.3.2 ø250 mm m -
4.10.3.B.3.3 ø300 mm m -
4.10.3.B.3.4 ø350 mm m -
4.10.3.B.3.5 ø400 mm m -
4.10.3.B.3.6 ø450 mm m -
4.10.3.B.3.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 131 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.10.3.B.3.8 ø600 mm m -
4.10.3.B.3.9 ø700 mm m -
4.10.3.B.3.10 ø800 mm m -
4.10.3.B.3.11 ø900 mm m -
4.10.3.B.3.12 ø1000 mm m -
Supply and Installation of RCC Manholes chambers in accordance
with the technical specification and the standard detailed drawings, of
any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary road
4.10.4
reinstatement, dismantling of existing structures, site cleaning, earth
cutting, sand filling, earth refilling , coarse materials/ khoa filling,
concreting, Approved brand CI Manhole cover, as per approved
drawing and specification.
4.10.4.A Normal Manhole Rectangular or circular
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 132 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 133 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 134 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 136 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 137 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 138 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 139 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.11 INSTALLATION of LOOP 311
4.11.1 Miscellaneous works during implementation
4.11.1.1 Setting-out LS 1.00 335,690.00 335,690.00
4.11.1.2 General works and site tests LS 1.00 671,380.00 671,380.00
4.11.2 Commissioning and final inspection /Tests
4.11.2.4 Development and submission of Operation and Maintenance manuals LS 1.00 7,500.00 7,500.00
4.11.2.5 Development and submission of GIS based As-built drawings LS 1.00 419,612.50 419,612.50
4.11.2.6 Post Construction modelling LS 1.00 50,353.50 50,353.50
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 141 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.11.3.B.1.1 ø200 mm m -
4.11.3.B.1.2 ø250 mm m -
4.11.3.B.1.3 ø300 mm m -
4.11.3.B.1.4 ø350 mm m -
4.11.3.B.1.5 ø400 mm m -
4.11.3.B.1.6 ø450 mm m -
4.11.3.B.1.7 ø500 mm m -
4.11.3.B.1.8 ø600 mm m -
4.11.3.B.1.9 ø700 mm m -
4.11.3.B.1.10 ø800 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 142 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.11.3.B.1.11 ø900 mm m -
4.11.3.B.1.12 ø1000 mm m -
4.11.3.B.2.1 ø200 mm m -
4.11.3.B.2.2 ø250 mm m -
4.11.3.B.2.3 ø300 mm m -
4.11.3.B.2.4 ø350 mm m -
4.11.3.B.2.5 ø400 mm m -
4.11.3.B.2.6 ø450 mm m -
4.11.3.B.2.7 ø500 mm m -
4.11.3.B.2.8 ø600 mm m -
4.11.3.B.2.9 ø700 mm m -
4.11.3.B.2.10 ø800 mm m -
4.11.3.B.2.11 ø900 mm m -
4.11.3.B.2.12 ø1000 mm m -
4.11.3.B.3.1 ø200 mm m -
4.11.3.B.3.2 ø250 mm m -
4.11.3.B.3.3 ø300 mm m -
4.11.3.B.3.4 ø350 mm m -
4.11.3.B.3.5 ø400 mm m -
4.11.3.B.3.6 ø450 mm m -
4.11.3.B.3.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 143 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.11.3.B.3.8 ø600 mm m -
4.11.3.B.3.9 ø700 mm m -
4.11.3.B.3.10 ø800 mm m -
4.11.3.B.3.11 ø900 mm m -
4.11.3.B.3.12 ø1000 mm m -
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 145 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 146 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 147 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 148 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 149 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 150 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 151 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 152 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.12 INSTALLATION of LOOP 312
4.12.1 Miscellaneous works during implementation
4.12.1.1 Setting-out LS 1.00 428,014.00 428,014.00
4.12.1.2 General works and site tests LS 1.00 856,028.00 856,028.00
4.12.2 Commissioning and final inspection /Tests
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 153 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 154 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.12.3.B.1.1 ø200 mm m -
4.12.3.B.1.2 ø250 mm m -
4.12.3.B.1.3 ø300 mm m -
4.12.3.B.1.4 ø350 mm m -
4.12.3.B.1.5 ø400 mm m -
4.12.3.B.1.6 ø450 mm m -
4.12.3.B.1.7 ø500 mm m -
4.12.3.B.1.8 ø600 mm m -
4.12.3.B.1.9 ø700 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 155 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.12.3.B.1.10 ø800 mm m -
4.12.3.B.1.11 ø900 mm m -
4.12.3.B.1.12 ø1000 mm m -
4.12.3.B.2.1 ø200 mm m -
4.12.3.B.2.2 ø250 mm m -
4.12.3.B.2.3 ø300 mm m -
4.12.3.B.2.4 ø350 mm m -
4.12.3.B.2.5 ø400 mm m -
4.12.3.B.2.6 ø450 mm m -
4.12.3.B.2.7 ø500 mm m -
4.12.3.B.2.8 ø600 mm m -
4.12.3.B.2.9 ø700 mm m -
4.12.3.B.2.10 ø800 mm m -
4.12.3.B.2.11 ø900 mm m -
4.12.3.B.2.12 ø1000 mm m -
4.12.3.B.3.1 ø200 mm m -
4.12.3.B.3.2 ø250 mm m -
4.12.3.B.3.3 ø300 mm m -
4.12.3.B.3.4 ø350 mm m -
4.12.3.B.3.5 ø400 mm m -
4.12.3.B.3.6 ø450 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 156 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.12.3.B.3.7 ø500 mm m -
4.12.3.B.3.8 ø600 mm m -
4.12.3.B.3.9 ø700 mm m -
4.12.3.B.3.10 ø800 mm m -
4.12.3.B.3.11 ø900 mm m -
4.12.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 157 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 160 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 162 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 163 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 165 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.13 INSTALLATION of LOOP 313
4.13.1 Miscellaneous works during implementation
4.13.1.1 Setting-out LS 1.00 694,340.00 694,340.00
4.13.1.2 General works and site tests LS 1.00 1,388,680.00 1,388,680.00
4.13.2 Commissioning and final inspection /Tests
4.13.2.5 Development and submission of GIS based As-built drawings LS 1.00 867,925.00 867,925.00
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 167 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.13.3.B.1.1 ø200 mm m -
4.13.3.B.1.2 ø250 mm m -
4.13.3.B.1.3 ø300 mm m -
4.13.3.B.1.4 ø350 mm m -
4.13.3.B.1.5 ø400 mm m -
4.13.3.B.1.6 ø450 mm m -
4.13.3.B.1.7 ø500 mm m -
4.13.3.B.1.8 ø600 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 168 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.13.3.B.1.9 ø700 mm m -
4.13.3.B.1.10 ø800 mm m -
4.13.3.B.1.11 ø900 mm m -
4.13.3.B.1.12 ø1000 mm m -
4.13.3.B.2.1 ø200 mm m -
4.13.3.B.2.2 ø250 mm m -
4.13.3.B.2.3 ø300 mm m -
4.13.3.B.2.4 ø350 mm m -
4.13.3.B.2.5 ø400 mm m -
4.13.3.B.2.6 ø450 mm m -
4.13.3.B.2.7 ø500 mm m -
4.13.3.B.2.8 ø600 mm m -
4.13.3.B.2.9 ø700 mm m -
4.13.3.B.2.10 ø800 mm m -
4.13.3.B.2.11 ø900 mm m -
4.13.3.B.2.12 ø1000 mm m -
4.13.3.B.3.1 ø200 mm m -
4.13.3.B.3.2 ø250 mm m -
4.13.3.B.3.3 ø300 mm m -
4.13.3.B.3.4 ø350 mm m -
4.13.3.B.3.5 ø400 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 169 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.13.3.B.3.6 ø450 mm m -
4.13.3.B.3.7 ø500 mm m -
4.13.3.B.3.8 ø600 mm m -
4.13.3.B.3.9 ø700 mm m -
4.13.3.B.3.10 ø800 mm m -
4.13.3.B.3.11 ø900 mm m -
4.13.3.B.3.12 ø1000 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 170 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 171 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 172 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 173 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 174 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 175 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 176 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 177 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 178 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.14 INSTALLATION of LOOP 314
4.14.1 Miscellaneous works during implementation
4.14.1.1 Setting-out LS 1.00 228,062.00 228,062.00
4.14.1.2 General works and site tests LS 1.00 456,124.00 456,124.00
4.14.2 Commissioning and final inspection /Tests
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 179 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 180 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.14.3.B.1.1 ø200 mm m -
4.14.3.B.1.2 ø250 mm m -
4.14.3.B.1.3 ø300 mm m -
4.14.3.B.1.4 ø350 mm m -
4.14.3.B.1.5 ø400 mm m -
4.14.3.B.1.6 ø450 mm m -
4.14.3.B.1.7 ø500 mm m -
4.14.3.B.1.8 ø600 mm m -
4.14.3.B.1.9 ø700 mm m -
4.14.3.B.1.10 ø800 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 181 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.14.3.B.1.11 ø900 mm m -
4.14.3.B.1.12 ø1000 mm m -
4.14.3.B.2.1 ø200 mm m -
4.14.3.B.2.2 ø250 mm m -
4.14.3.B.2.3 ø300 mm m -
4.14.3.B.2.4 ø350 mm m -
4.14.3.B.2.5 ø400 mm m -
4.14.3.B.2.6 ø450 mm m -
4.14.3.B.2.7 ø500 mm m -
4.14.3.B.2.8 ø600 mm m -
4.14.3.B.2.9 ø700 mm m -
4.14.3.B.2.10 ø800 mm m -
4.14.3.B.2.11 ø900 mm m -
4.14.3.B.2.12 ø1000 mm m -
4.14.3.B.3.1 ø200 mm m -
4.14.3.B.3.2 ø250 mm m -
4.14.3.B.3.3 ø300 mm m -
4.14.3.B.3.4 ø350 mm m -
4.14.3.B.3.5 ø400 mm m -
4.14.3.B.3.6 ø450 mm m -
4.14.3.B.3.7 ø500 mm m -
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 182 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
4.14.3.B.3.8 ø600 mm m -
4.14.3.B.3.9 ø700 mm m -
4.14.3.B.3.10 ø800 mm m -
4.14.3.B.3.11 ø900 mm m -
4.14.3.B.3.12 ø1000 mm m -
Supply and Installation of RCC Manholes chambers in accordance
with the technical specification and the standard detailed drawings,
of any diameter/ size and to the depths specified below, including
fitting, fixing of all items, road cutting permission fee, temporary
4.14.4
road reinstatement, dismantling of existing structures, site cleaning,
earth cutting, sand filling, earth refilling , coarse materials/ khoa
filling, concreting, Approved brand CI Manhole cover, as per
approved drawing and specification.
4.14.4.A Normal Manhole Rectangular or circular
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 183 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 184 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 185 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 187 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 188 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 189 of 199
Schedule No. 4 - Installation and Other Services
a b c d e f g h i = e+f+g+h j=dxi
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 190 of 199
Schedule No. 5 - Grand Summary
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 191 of 199
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 192 of 199
Schedule No. 6 - Recommended Spare Parts
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 193 of 199
Schedule No. 6 - Recommended Spare Parts
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 194 of 199
Schedule No. 6 - Recommended Spare Parts
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 195 of 199
Schedule No. 7 - Day Work
7.1.1 Micro Tunneling Machine with complete set hrs. 240 6,000.00 6,000.00 1,440,000.00
7.1.2 Hydraulic HDD Unit hrs. 144 4,000.00 4,000.00 576,000.00
7.1.3 Excavator, face shovel, or dragline:
7.1.3.1 Up to and including 1 m3 hrs. 144 2,000.00 2,000.00 288,000.00
7.1.3.2 Over 1 m3 to 2 m3 hrs. 180 3,000.00 3,000.00 540,000.00
7.1.3.3 Over 2 m3 hrs. 120 3,510.00 3,510.00 421,200.00
7.1.4 Tractor, including bull or angle dozer:
7.1.4.1 Up to and including 150 kW hrs. 200 1,000.00 1,000.00 200,000.00
7.1.4.2 Over 150 kW to 200 kW hrs. 200 1,500.00 1,500.00 300,000.00
7.1.4.3 Over 200 kW to 250 kW hrs. 200 2,000.00 2,000.00 400,000.00
7.1.5 Tractor with ripper:
7.1.5.1 Up to and including 200 kW hrs. 200 1,500.00 1,500.00 300,000.00
7.1.5.2 Over 200 kW to 250 kW hrs. 200 2,000.00 2,000.00 400,000.00
7.1.6 Portable concrete mixer - 0.4m3 hrs. 300 500.00 500.00 150,000.00
7.1.7 Hydraulic Excavator – 1 m3 hrs. 200 3,000.00 3,000.00 600,000.00
7.1.8 4-tool compressor including tools and hoses hrs. 200 2,000.00 2,000.00 400,000.00
7.1.9 10 tonne lorry-mounted crane hrs. 200 5,000.00 5,000.00 1,000,000.00
7.1.10 750 Kg crane hrs. 200 2,000.00 2,000.00 400,000.00
7.1.11 0.5 m3 dumper hrs. 200 1,000.00 1,000.00 200,000.00
7.1.12 1 m3 dumper hrs. 200 1,500.00 1,500.00 300,000.00
7.1.13 7 m3 tipper lorry hrs. 200 2,000.00 2,000.00 400,000.00
7.1.14 15 m3 lorry hrs. 200 2,000.00 2,000.00 400,000.00
7.1.15 4 wheel drive pick-up or van hrs. 200 500.00 500.00 100,000.00
7.1.16 Vibrating plate compactor hrs. 200 500.00 500.00 100,000.00
7.1.17 8-10 tonne roller hrs. 200 2,000.00 2,000.00 400,000.00
7.1.18 Scaffolding, 10 sqm day 36 2,025.00 2,025.00 72,900.00
7.1.19 5-Ton capacity truck-fare in Dhaka city i/c loading, unloading hrs. 300 456.50 456.50 136,950.00
7.1.20 Concrete mixer machine -1 bag capacity hrs. 168 537.50 537.50 90,300.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 196 of 199
Schedule No. 7 - Day Work
7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1 (32.5-
7.2.1 bag 100 675.00 675.00 67,500.00
42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 100 607.50 607.50 60,750.00
clinker): 50kg bag
7.2.3 White Cement kg 250 54.00 54.00 13,500.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 1 86,400.00 86,400.00 86,400.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 1 87,750.00 87,750.00 87,750.00
7.2.6 MS Sheet M Ton 1 114,750.00 114,750.00 57,375.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 5,000 10,800.00 10,800.00 54,000.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 5,000 12,150.00 12,150.00 60,750.00
7.2.9 Imported Earth m3 100 572.50 572.50 57,250.00
7.2.10 Sand (F.M. 0.8) m3 100 525.00 525.00 52,500.00
7.2.11 Sand (F.M. 1.2) m3 50 810.50 810.50 40,525.00
7.2.12 Sand (F.M. 2.5) m3 50 2,384.00 2,384.00 119,200.00
7.2.13 Viti/Filling Sand m3 100 524.50 524.50 52,450.00
7.3 Labor
-
7.3.1 Contract Manager day 36 15,000.00 15,000.00 540,000.00
7.3.2 Office Assistant day 72 500.00 500.00 36,000.00
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 197 of 199
Schedule No. 7 - Day Work
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 14,046,204.00
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 198 of 199
Schedule No. 8 - O&M Services
Name of Bidder
Signature of Bidder
2019
Dasherkandi Sewerage Project, Cost Estimate for Package 3 199 of 199
Employer’s Cost Estimates7
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 53,518.80
1.1.2 ø250 mm m 1,751.70
1.1.3 ø300 mm m 1,978.50
1.1.4 ø350 mm m 1,391.90
1.1.5 ø400 mm m 1,824.40
1.1.6 ø450 mm m
1.1.7 ø500 mm m 1,932.00
1.1.8 ø600 mm m 1,234.30
1.1.9 ø700 mm m 232.70
1.1.10 ø800 mm m 28.90
1.1.11 ø900 mm m
1.1.12 ø1000 mm m
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 107
1.2.2 ø250 mm nos. 4
1.2.3 ø300 mm nos. 4
1.2.4 ø350 mm nos. 3
1.2.5 ø400 mm nos. 4
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 5
1.2.8 ø600 mm nos. 2
1.2.9 ø700 mm nos. 1
1.2.10 ø800 mm nos.
Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
a b c d e f g h=e+f+g i=dxh
a b c d e f g h=e+f+g i=dxh
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.5.2 LS 1 15,833,953 15,833,952.82
Report
3.2.5.3 Design Control Services including documentation LS 1 4,318,351 4,318,350.77
Sub-total B: 209,061,599.75
Total A+B: Sub-total 3:
228,661,124.73
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary
Name of Bidder:
Signature of Bidder:
a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 6,533,174.99 6,533,174.99
4.1.1.2 Advance Payment Guarantee LS 1 6,533,174.99 6,533,174.99
Subtotal 4.1.1 13,066,349.98
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.2 Installation All Risks Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.3 Third Party Liability Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.4 Automobile Liability Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.5 Workers' Compensation LS 1 9,799,762.49 9,799,762.49
4.1.2.6 Employer's Liability LS 1 9,799,762.49 9,799,762.49
4.1.2.7 Contractor's Equipment Insurance LS 1 9,799,762.49 9,799,762.49
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 9,799,762.49 9,799,762.49
Subtotal 4.1.2 78,398,099.90
4.1.3 Site establishment, operation and removal
Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 7,466,485.71 7,466,485.71
workshops, site access and miscellaneous services etc.
Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 7,466,485.71 7,466,485.71
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 7,466,485.71 7,466,485.71
4.1.3.4 Survey instruments LS 1 7,466,485.71 7,466,485.71
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 7,466,485.71 7,466,485.71
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 7,466,485.71 7,466,485.71
Subtotal 4.1.3 44,798,914.23
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 136,263,364.11
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified below,
including fitting, fixing of all items, road cutting permission fee, temporary road
4.2.3 -
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.
4.2.3.B.1.1 ø200 mm m -
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -
4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -
4.2.3.B.2.11 ø900 mm m -
4.2.3.B.2.12 ø1000 mm m -
4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -
4.2.3.B.3.11 ø900 mm m -
4.2.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting, fixing
of all items, road cutting permission fee, temporary road reinstatement, dismantling
4.2.5 of existing structures, site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.3.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -
4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -
4.3.3.B.2.11 ø900 mm m -
4.3.3.B.2.12 ø1000 mm m -
4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -
4.3.3.B.3.11 ø900 mm m -
4.3.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.3.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -
4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -
4.5.3.B.2.11 ø900 mm m -
4.5.3.B.2.12 ø1000 mm m -
4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -
4.5.3.B.3.11 ø900 mm m -
4.5.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Name of Bidder
Signature of Bidder
Name of Bidder
Signature of Bidder
7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 30 675.00 675.00 20,250.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 30 607.50 607.50 18,225.00
clinker): 50kg bag
7.2.3 White Cement kg 80 54.00 54.00 4,320.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 0.50 86,400.00 86,400.00 43,200.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 0.50 87,750.00 87,750.00 43,875.00
7.2.6 MS Sheet M Ton 0.50 114,750.00 114,750.00 57,375.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 1,670 10,800.00 10,800.00 18,036.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 1,670 12,150.00 12,150.00 20,290.50
7.2.9 Imported Earth m3 30 572.50 572.50 17,175.00
7.2.10 Sand (F.M. 0.8) m3 30 525.00 525.00 15,750.00
7.2.11 Sand (F.M. 1.2) m3 20 810.50 810.50 16,210.00
7.2.12 Sand (F.M. 2.5) m3 20 2,384.00 2,384.00 47,680.00
7.2.13 Viti/Filling Sand m3 30 524.50 524.50 15,735.00
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 4,832,631.50
Name of Bidder
Signature of Bidder
Name of Bidder
Signature of Bidder
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m 121,902.50
1.1.2 ø250 mm m 1,310.60
1.1.3 ø300 mm m 1,768.60
1.1.4 ø350 mm m 1,528.50
1.1.5 ø400 mm m 555.30
1.1.6 ø450 mm m
1.1.7 ø500 mm m 826.70
1.1.8 ø600 mm m 1,392.90
1.1.9 ø700 mm m 1,569.50
1.1.10 ø800 mm m 176.60
1.1.11 ø900 mm m
1.1.12 ø1000 mm m 554.30
1.1.13 ø1100 mm m 1,823.80
1.1.14 ø1300 mm m 188.10
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos. 244
1.2.2 ø250 mm nos. 3
1.2.3 ø300 mm nos. 4
1.2.4 ø350 mm nos. 3
1.2.5 ø400 mm nos. 1
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 2
1.2.8 ø600 mm nos. 3
1.2.9 ø700 mm nos. 3
Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
a b c d e f g h=e+f+g i=dxh
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.3.2 LS 1 21,518,967 21,518,967.05
Report
3.2.3.3 Design Control Services including documentation LS 1 5,868,809 5,868,809.19
a b c d e f g h=e+f+g i=dxh
Detailed designs, Specifications and documentation, including Quality Assurance and Design
3.2.5.2 LS 1 34,907,686 34,907,686.35
Report
3.2.5.3 Design Control Services including documentation LS 1 9,520,278 9,520,278.10
Sub-total B: 443,006,696.48
Total A+B: Sub-total 3:
484,538,574.27
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary
Name of Bidder:
Signature of Bidder:
a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 13,843,959.26 13,843,959.26
4.1.1.2 Advance Payment Guarantee LS 1 13,843,959.26 13,843,959.26
Subtotal 4.1.1 27,687,918.53
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.2 Installation All Risks Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.3 Third Party Liability Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.4 Automobile Liability Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.5 Workers' Compensation LS 1 20,765,938.90 20,765,938.90
4.1.2.6 Employer's Liability LS 1 20,765,938.90 20,765,938.90
4.1.2.7 Contractor's Equipment Insurance LS 1 20,765,938.90 20,765,938.90
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 20,765,938.90 20,765,938.90
Subtotal 4.1.2 166,127,511.18
4.1.3 Site establishment, operation and removal
Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 15,821,667.73 15,821,667.73
workshops, site access and miscellaneous services etc.
Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 15,821,667.73 15,821,667.73
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 15,821,667.73 15,821,667.73
4.1.3.4 Survey instruments LS 1 15,821,667.73 15,821,667.73
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 15,821,667.73 15,821,667.73
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 15,821,667.73 15,821,667.73
Subtotal 4.1.3 94,930,006.39
a b c d e f g h=e+f+g i=dxh
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 288,745,436.10
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified below,
including fitting, fixing of all items, road cutting permission fee, temporary road
4.2.3 -
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.
4.2.3.B.1.1 ø200 mm m -
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -
4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -
4.2.3.B.2.11 ø900 mm m -
4.2.3.B.2.12 ø1000 mm m -
4.2.3.B.3.1 ø200 mm m -
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -
4.2.3.B.3.11 ø900 mm m -
4.2.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting, fixing
of all items, road cutting permission fee, temporary road reinstatement, dismantling
4.2.5 of existing structures, site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.3.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -
4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -
4.3.3.B.2.11 ø900 mm m -
4.3.3.B.2.12 ø1000 mm m -
4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -
4.3.3.B.3.11 ø900 mm m -
4.3.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.3.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.4.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.4.3.B.1.1 ø200 mm m -
4.4.3.B.1.2 ø250 mm m -
4.4.3.B.1.3 ø300 mm m -
4.4.3.B.1.4 ø350 mm m -
4.4.3.B.1.5 ø400 mm m -
4.4.3.B.1.6 ø450 mm m -
4.4.3.B.1.7 ø500 mm m -
4.4.3.B.1.8 ø600 mm m -
4.4.3.B.1.9 ø700 mm m -
4.4.3.B.1.10 ø800 mm m -
4.4.3.B.1.11 ø900 mm m -
4.4.3.B.1.12 ø1000 mm m -
4.4.3.B.2.1 ø200 mm m -
4.4.3.B.2.2 ø250 mm m -
4.4.3.B.2.3 ø300 mm m -
4.4.3.B.2.4 ø350 mm m -
4.4.3.B.2.5 ø400 mm m -
4.4.3.B.2.6 ø450 mm m -
4.4.3.B.2.7 ø500 mm m -
4.4.3.B.2.8 ø600 mm m -
4.4.3.B.2.9 ø700 mm m -
4.4.3.B.2.10 ø800 mm m -
4.4.3.B.2.11 ø900 mm m -
4.4.3.B.2.12 ø1000 mm m -
4.4.3.B.3.1 ø200 mm m -
4.4.3.B.3.2 ø250 mm m -
4.4.3.B.3.3 ø300 mm m -
4.4.3.B.3.4 ø350 mm m -
4.4.3.B.3.5 ø400 mm m -
4.4.3.B.3.6 ø450 mm m -
4.4.3.B.3.7 ø500 mm m -
4.4.3.B.3.8 ø600 mm m -
4.4.3.B.3.9 ø700 mm m -
4.4.3.B.3.10 ø800 mm m -
4.4.3.B.3.11 ø900 mm m -
4.4.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.4.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -
4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -
4.5.3.B.2.11 ø900 mm m -
4.5.3.B.2.12 ø1000 mm m -
4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -
4.5.3.B.3.11 ø900 mm m -
4.5.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -
4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -
4.5.3.B.2.11 ø900 mm m -
4.5.3.B.2.12 ø1000 mm m -
4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -
4.5.3.B.3.11 ø900 mm m -
4.5.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.5.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
4.5.3.B.1.1 ø200 mm m -
4.5.3.B.1.2 ø250 mm m -
4.5.3.B.1.3 ø300 mm m -
4.5.3.B.1.4 ø350 mm m -
4.5.3.B.1.5 ø400 mm m -
4.5.3.B.1.6 ø450 mm m -
4.5.3.B.1.7 ø500 mm m -
4.5.3.B.1.8 ø600 mm m -
4.5.3.B.1.9 ø700 mm m -
4.5.3.B.1.10 ø800 mm m -
4.5.3.B.1.11 ø900 mm m -
4.5.3.B.1.12 ø1000 mm m -
4.5.3.B.2.1 ø200 mm m -
4.5.3.B.2.2 ø250 mm m -
4.5.3.B.2.3 ø300 mm m -
4.5.3.B.2.4 ø350 mm m -
4.5.3.B.2.5 ø400 mm m -
4.5.3.B.2.6 ø450 mm m -
4.5.3.B.2.7 ø500 mm m -
4.5.3.B.2.8 ø600 mm m -
4.5.3.B.2.9 ø700 mm m -
4.5.3.B.2.10 ø800 mm m -
4.5.3.B.2.11 ø900 mm m -
4.5.3.B.2.12 ø1000 mm m -
4.5.3.B.3.1 ø200 mm m -
4.5.3.B.3.2 ø250 mm m -
4.5.3.B.3.3 ø300 mm m -
4.5.3.B.3.4 ø350 mm m -
4.5.3.B.3.5 ø400 mm m -
4.5.3.B.3.6 ø450 mm m -
4.5.3.B.3.7 ø500 mm m -
4.5.3.B.3.8 ø600 mm m -
4.5.3.B.3.9 ø700 mm m -
4.5.3.B.3.10 ø800 mm m -
4.5.3.B.3.11 ø900 mm m -
4.5.3.B.3.12 ø1000 mm m -
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.2.6 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
Name of Bidder
Signature of Bidder
Name of Bidder
7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 60 675.00 675.00 40,500.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 60 607.50 607.50 36,450.00
clinker): 50kg bag
7.2.3 White Cement kg 160 54.00 54.00 8,640.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 1.00 86,400.00 86,400.00 86,400.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 1.00 87,750.00 87,750.00 87,750.00
7.2.6 MS Sheet M Ton 1.00 114,750.00 114,750.00 114,750.00
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 3,340 10,800.00 10,800.00 36,072.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 3,340 12,150.00 12,150.00 40,581.00
7.2.9 Imported Earth m3 60 572.50 572.50 34,350.00
7.2.10 Sand (F.M. 0.8) m3 60 525.00 525.00 31,500.00
7.2.11 Sand (F.M. 1.2) m3 40 810.50 810.50 32,420.00
7.2.12 Sand (F.M. 2.5) m3 40 2,384.00 2,384.00 95,360.00
7.2.13 Viti/Filling Sand m3 60 524.50 524.50 31,470.00
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 9,665,263.00
Name of Bidder
Signature of Bidder
Name of Bidder
Signature of Bidder
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
a b c d e f g h i=f+g+h j=exi k
1.1 GRP Pipes
1.1.1 ø200 mm m
1.1.2 ø250 mm m
1.1.3 ø300 mm m
1.1.4 ø350 mm m
1.1.5 ø400 mm m
1.1.6 ø450 mm m
1.1.7 ø500 mm m 608.30
1.1.8 ø600 mm m 403.50
1.1.9 ø700 mm m
1.1.10 ø800 mm m 254.50
1.1.11 ø900 mm m
1.1.12 ø1000 mm m 259.90
1.1.13 ø1100 mm m
1.1.14 ø1200 mm m 175.00
1.1.15 ø1300 mm m 1,254.20
1.1.16 ø1400 mm m 96.40
1.1.17 ø1500 mm m
1.1.18 ø1600 mm m 1,102.90
1.1.19 ø1700 mm m 506.70
1.1.20 ø1800 mm m 719.10
1.1.21 ø1900 mm m 733.20
1.1.22 ø2000 mm m 117.00
o
1.2 GRP Elbow / 90 bend
1.2.1 ø200 mm nos.
1.2.2 ø250 mm nos.
1.2.3 ø300 mm nos.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 1 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.4 ø350 mm nos.
1.2.5 ø400 mm nos.
1.2.6 ø450 mm nos.
1.2.7 ø500 mm nos. 1
1.2.8 ø600 mm nos. 1
1.2.9 ø700 mm nos.
1.2.10 ø800 mm nos. 1
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 2 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.2.11 ø900 mm nos.
1.2.12 ø1000 mm nos. 1
1.2.13 ø1100 mm nos.
1.2.14 ø1200 mm nos.
1.2.15 ø1300 mm nos. 3
1.2.16 ø1400 mm nos.
1.2.17 ø1500 mm nos.
1.2.18 ø1600 mm nos. 2
1.2.19 ø1700 mm nos. 1
1.2.20 ø1800 mm nos. 1
1.2.21 ø1900 mm nos. 1
1.2.22 ø2000 mm nos.
1.3 Equal and Un Equal Tee of different sizes
1.3.1 200mm x200mm nos.
1.3.2 250mm x250mm nos.
1.3.3 300mm X 300mm nos.
1.3.4 350mm X 350mm nos.
1.3.5 400mm X 400mm nos.
1.3.6 450mm X 450mm nos.
1.3.7 500mm X 500mm nos. 1
1.3.8 600 mm X 600mm nos. 1
1.3.9 700mm X 700mm nos.
1.3.10 800mm x 800mm nos. 1
1.3.11 900mm X 900mm nos.
1.3.12 1000mm X 1000mm nos. 1
1.3.13 250mm X250mm X 200mm nos.
1.3.14 300mm X 300mm X 200mm nos.
1.3.15 300mm X 300mm X 250mm nos.
1.3.16 400mm X 400mm X 200mm nos.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 3 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.3.17 400mm X 400mm X 250mm nos.
1.3.18 400mm X 400mm X 300mm nos.
1.3.19 500mm X 500mm X 200mm nos. 1
1.3.20 500mm X 500mm X 300mm nos. 1
1.4 GRP Coupler/Sleeves
1.4.1 ø200 mm nos.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 4 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.4.2 ø250 mm nos.
1.4.3 ø300 mm nos.
1.4.4 ø350 mm nos.
1.4.5 ø400 mm nos.
1.4.6 ø450 mm nos.
1.4.7 ø500 mm nos. 2
1.4.8 ø600 mm nos. 2
1.4.9 ø700 mm nos.
1.4.10 ø800 mm nos. 2
1.4.11 ø900 mm nos.
1.4.12 ø1000 mm nos. 2
1.4.13 ø1100 mm nos.
1.4.14 ø1200 mm nos.
1.4.15 ø1300 mm nos. 6
1.4.16 ø1400 mm nos.
1.4.17 ø1500 mm nos.
1.4.18 ø1600 mm nos. 4
1.4.19 ø1700 mm nos. 2
1.4.20 ø1800 mm nos. 2
1.4.21 ø1900 mm nos. 2
1.4.22 ø2000 mm nos.
1.5 Flanged Adapters
1.5.1 ø200 mm nos.
1.5.2 ø250 mm nos.
1.5.3 ø300 mm nos.
1.5.4 ø350 mm nos.
1.5.5 ø400 mm nos. 1
1.5.6 ø450 mm nos. 1
1.5.7 ø500 mm nos.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 5 of 42
Custom Duties
Unit Price (BDT) Total Price
Country of (CD, VAT)
Item Description Unit Qty.
Origin Total Unit Local Currency Local Currency
Material Labour Equipment
Price (CIP) (BDT) (BDT)
1.5.8 ø600 mm nos.
1.5.9 ø700 mm nos.
1.5.10 ø800 mm nos. 1
1.5.11 ø900 mm nos. 1
1.5.12 ø1000 mm nos. 1
1.5.13 ø1100 mm nos.
1.5.14 ø1200 mm nos. 1
1.5.15 ø1300 mm nos. 2
1.5.16 ø1400 mm nos. 1
1.5.17 ø1500 mm nos. 1
1.5.18 ø1600 mm nos. 2
1.5.19 ø1700 mm nos. 1
1.5.20 ø1800 mm nos. 1
1.5.21 ø1900 mm nos. 1
1.5.22 ø2000 mm nos. 1
Sub-total 1: Total Column 'j' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 6 of 42
Schedule No. 2 - Pipe and Fittings Supplied from within the Employer´s Country
Total 2: Total Column 'i' to be carried forward to Schedule No. 5. Grand Summary
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 7 of 42
Schedule No. 3 - Design Services
a b c d e f g h=e+f+g i=dxh
Sub-total B: 40,806,119.80
Total A+B: Sub-total 3:
44,631,693.53
Sub-total 3: Column 'i' to be carried forward to Schedule No. 5 Grand Summary
Name of Bidder:
Signature of Bidder:
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 8 of 42
Schedule No. 4 - Installation / Construction and Other works
a b c d e f g h=e+f+g i=dxh
4.1 Implementation Provisions and Preliminaries for all Loops
4.1.1 Guarantees
4.1.1.1 Performance Security LS 1 1,275,191.24 1,275,191.24
4.1.1.2 Advance Payment Guarantee LS 1 1,275,191.24 1,275,191.24
Subtotal 4.1.1 2,550,382.49
4.1.2 Insurances
4.1.2.1 Cargo Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.2 Installation All Risks Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.3 Third Party Liability Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.4 Automobile Liability Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.5 Workers' Compensation LS 1 1,912,786.87 1,912,786.87
4.1.2.6 Employer's Liability LS 1 1,912,786.87 1,912,786.87
4.1.2.7 Contractor's Equipment Insurance LS 1 1,912,786.87 1,912,786.87
4.1.2.8 Other Insurances (to be specified by the Tenderer) LS 1 1,912,786.87 1,912,786.87
Subtotal 4.1.2 15,302,294.93
4.1.3 Site establishment, operation and removal
Supply and erect signboard, establish Contractor´s main site offices, welfare facilities,
4.1.3.1 LS 1 1,457,361.42 1,457,361.42
workshops, site access and miscellaneous services etc.
Manage generally the site and the above facilities during the implementation period including
4.1.3.2 LS 1 1,457,361.42 1,457,361.42
health, safety and security measures
4.1.3.3 Site materials laboratory establishment, operation and maintenance LS 1 1,457,361.42 1,457,361.42
4.1.3.4 Survey instruments LS 1 1,457,361.42 1,457,361.42
4.1.3.5 The Project Manager's / Engineers Office with all operational facilities, operation and maintenance LS 1 1,457,361.42 1,457,361.42
4.1.3.6 Removal at the completion of the works of all the established facilities and site restoration LS 1 1,457,361.42 1,457,361.42
Subtotal 4.1.3 8,744,168.53
Sub-total 4.1: Column 'i' to be carried forward to Schedule No. 5 Grand Summary 26,596,845.95
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 9 of 42
Schedule No. 4 - Installation and Other Services
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified below,
including fitting, fixing of all items, road cutting permission fee, temporary road
4.2.3 -
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse material s/ khoa filling, concreting as per approved
drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 10 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 11 of 42
Schedule No. 4 - Installation and Other Services
4.2.3.B.1.1 ø200 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 12 of 42
Schedule No. 4 - Installation and Other Services
4.2.3.B.1.2 ø250 mm m -
4.2.3.B.1.3 ø300 mm m -
4.2.3.B.1.4 ø350 mm m -
4.2.3.B.1.5 ø400 mm m -
4.2.3.B.1.6 ø450 mm m -
4.2.3.B.1.7 ø500 mm m -
4.2.3.B.1.8 ø600 mm m -
4.2.3.B.1.9 ø700 mm m -
4.2.3.B.1.10 ø800 mm m -
4.2.3.B.1.11 ø900 mm m -
4.2.3.B.1.12 ø1000 mm m -
4.2.3.B.2.1 ø200 mm m -
4.2.3.B.2.2 ø250 mm m -
4.2.3.B.2.3 ø300 mm m -
4.2.3.B.2.4 ø350 mm m -
4.2.3.B.2.5 ø400 mm m -
4.2.3.B.2.6 ø450 mm m -
4.2.3.B.2.7 ø500 mm m -
4.2.3.B.2.8 ø600 mm m -
4.2.3.B.2.9 ø700 mm m -
4.2.3.B.2.10 ø800 mm m -
4.2.3.B.2.11 ø900 mm m -
4.2.3.B.2.12 ø1000 mm m -
4.2.3.B.3.1 ø200 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 13 of 42
Schedule No. 4 - Installation and Other Services
4.2.3.B.3.2 ø250 mm m -
4.2.3.B.3.3 ø300 mm m -
4.2.3.B.3.4 ø350 mm m -
4.2.3.B.3.5 ø400 mm m -
4.2.3.B.3.6 ø450 mm m -
4.2.3.B.3.7 ø500 mm m -
4.2.3.B.3.8 ø600 mm m -
4.2.3.B.3.9 ø700 mm m -
4.2.3.B.3.10 ø800 mm m -
4.2.3.B.3.11 ø900 mm m -
4.2.3.B.3.12 ø1000 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 14 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 15 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 16 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 17 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 18 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 19 of 42
Schedule No. 4 - Installation and Other Services
Supply and Installation of service connections with GRP pipes including fitting, fixing
of all items, road cutting permission fee, temporary road reinstatement, dismantling
4.2.5 of existing structures, site cleaning, earth cutting, sand filling, earth refilling , coarse
material s/ khoa filling, concreting, individual house hold inspection pit, average
length of 10m as per approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 20 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 21 of 42
Schedule No. 4 - Installation and Other Services
Supply and Installation of sewerline in canal crossing through pipe jacking using
hydraulic jacks in accordance with the technical specification and the standard
detail drawing, of any diameter and to the depths in any kind of soils, including
construction of thrust and reception pits at manhole positions incorporating headwall
4.2.7 and seal assembly, construction of thrust wall/structural framework and piling if
necessary, fitting, fixing of all items, road cutting permission fee, temporary road
reinstatement, dismantling of existing structures, site cleaning, earth cutting, sand
filling, earth refilling , coarse materials/ khoa filling, concreting as per approved
drawing and specification.
4.2.7.1 Diameter and depth as specified in the drawing m 74.00 1,148,648.65 85,000,000.00
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 22 of 42
Schedule No. 4 - Installation and Other Services
Supply and Installation of GRP pipes in accordance with the technical specification
and the standard detail drawing, of any diameter and to the depths specified
below, including fitting, fixing of all items, road cutting permission fee, temporary
4.3.3 -
road reinstatement, dismantling of existing structures, site cleaning, earth cutting,
sand filling, earth refilling , coarse material s/ khoa filling, concreting as per
approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 23 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 24 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 25 of 42
Schedule No. 4 - Installation and Other Services
4.3.3.B.1.1 ø200 mm m -
4.3.3.B.1.2 ø250 mm m -
4.3.3.B.1.3 ø300 mm m -
4.3.3.B.1.4 ø350 mm m -
4.3.3.B.1.5 ø400 mm m -
4.3.3.B.1.6 ø450 mm m -
4.3.3.B.1.7 ø500 mm m -
4.3.3.B.1.8 ø600 mm m -
4.3.3.B.1.9 ø700 mm m -
4.3.3.B.1.10 ø800 mm m -
4.3.3.B.1.11 ø900 mm m -
4.3.3.B.1.12 ø1000 mm m -
4.3.3.B.2.1 ø200 mm m -
4.3.3.B.2.2 ø250 mm m -
4.3.3.B.2.3 ø300 mm m -
4.3.3.B.2.4 ø350 mm m -
4.3.3.B.2.5 ø400 mm m -
4.3.3.B.2.6 ø450 mm m -
4.3.3.B.2.7 ø500 mm m -
4.3.3.B.2.8 ø600 mm m -
4.3.3.B.2.9 ø700 mm m -
4.3.3.B.2.10 ø800 mm m -
4.3.3.B.2.11 ø900 mm m -
4.3.3.B.2.12 ø1000 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 26 of 42
Schedule No. 4 - Installation and Other Services
4.3.3.B.3.1 ø200 mm m -
4.3.3.B.3.2 ø250 mm m -
4.3.3.B.3.3 ø300 mm m -
4.3.3.B.3.4 ø350 mm m -
4.3.3.B.3.5 ø400 mm m -
4.3.3.B.3.6 ø450 mm m -
4.3.3.B.3.7 ø500 mm m -
4.3.3.B.3.8 ø600 mm m -
4.3.3.B.3.9 ø700 mm m -
4.3.3.B.3.10 ø800 mm m -
4.3.3.B.3.11 ø900 mm m -
4.3.3.B.3.12 ø1000 mm m -
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 27 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 28 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 29 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 30 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 31 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 32 of 42
Schedule No. 4 - Installation and Other Services
Supply and Installation of service connections with GRP pipes including fitting,
fixing of all items, road cutting permission fee, temporary road reinstatement,
4.3.5 dismantling of existing structures, site cleaning, earth cutting, sand filling, earth
refilling , coarse material s/ khoa filling, concreting, individual house hold
inspection pit, average length of 10m as per approved drawing and specification.
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 33 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 34 of 42
Schedule No. 4 - Installation and Other Services
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 35 of 42
Schedule No. 5 - Grand Summary
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 36 of 42
Schedule No. 6 - Recommended Spare Parts
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 38 of 42
Schedule No. 7 - Day Work
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 39 of 42
Schedule No. 7 - Day Work
7.2 Materials
Ordinary Portland Cement, ASTM C-150, Type-1,/ BDS-EN-197-1-CEM-1
7.2.1 bag 3 675.00 675.00 2,025.00
(32.5-42.5): 50kg bag
Portland Composite Cement CEM-II/A-M(6-20% constituents other than
7.2.2 bag 3 607.50 607.50 1,822.50
clinker): 50kg bag
7.2.3 White Cement kg 8 54.00 54.00 432.00
7.2.4 M. S. plain bars with min Fy-276 MPa (Billet) 40 gr. M Ton 0.05 86,400.00 86,400.00 4,320.00
7.2.5 M. S. deformed bars with min Fy-415 MPa (Billet) 60 gr M Ton 0.05 87,750.00 87,750.00 4,387.50
7.2.6 MS Sheet M Ton 0.05 114,750.00 114,750.00 5,737.50
7.2.7 1st Class Picked/Jhama Bricks %0 Nos. 1,000 10,800.00 10,800.00 10,800.00
7.2.8 Machine Made 1st Class Brick %0 Nos. 1,000 12,150.00 12,150.00 12,150.00
7.2.9 Imported Earth m3 3 572.50 572.50 1,717.50
7.2.10 Sand (F.M. 0.8) m3 3 525.00 525.00 1,575.00
7.2.11 Sand (F.M. 1.2) m3 2 810.50 810.50 1,621.00
7.2.12 Sand (F.M. 2.5) m3 2 2,384.00 2,384.00 4,768.00
7.2.13 Viti/Filling Sand m3 3 524.50 524.50 1,573.50
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 40 of 42
Schedule No. 7 - Day Work
Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 502,380.50
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 41 of 42
Schedule No. 8 - O&M Services
8.1
One year O&M (2 Loops in Segments 1-5 and in 7-16)
8.1.1 O&M Services in Loop 601 km 0.25 934,330.00 233,582.50
8.1.2 O&M Services in Loop 602 km 5.98 934,330.00 5,587,293.40
6.23
Sub-total 8.1: Total Column 'i' to be carried forward to Schedule No. 5 Grand Summary 5,820,875.90
Name of Bidder
Signature of Bidder
2018
Dasherkandi Sewerage Project, Cost Estimate for Package 6 42 of 42
Employer’s Cost Estimates10
I: Cost of Package 7
Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit Rates Amount
LxBxH=1500x700x800,
3 Slag bucket Set 1 420,000 420,000
Material: SS304
DN1500, H=7.7m
4 Electrical sluice gate Set 1 1,680,000 1,680,000
N=1.5kW
BxH=1.2x1.2,H=7.85m
5 Electrical sluice gate Set 2 1,680,000 3,360,000
N=3kW
BxH=1.2x1.2,H=8.15m
6 Electrical sluice gate Set 2 1,680,000 3,360,000
N=3kW
DN1500,H=5.05m
7 Electrical sluice gate Set 1 1,680,000 1,680,000
N=2kW
BxH=2.5x2.5, H=9.89m
8 Electrical sluice gate Set 1 1,680,000 1,680,000
N=3kW
DN1000,H= 4.65m,
9 Electrical sluice gate Set 2 1,680,000 3,360,000
N=2kW
duty-2, Standby-2,
10 Submersible sewage pump Q=0.926m3/s, H=7.04m,N=90kW Set 4 8,400,000 33,600,000
VFD Control
1 Frequency Converter (VFD) 90kW Pump motor matching frequency Set 4 630,000 2,520,000
Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit Rates Amount
I Monitoring Equipment - -
Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit Rates Amount
8
Part-A Server
: Mechanical cabinet and KVM
Equipment Height 2.2m Set 1 1,680,000 1,680,000
II Software system - -
IV Instrumentation - -
Total BDT
S.No Items Main Specification Unit Remarks
Quantity Unit Rates Amount
3
Part-A : Mechanical
Line-by-line
Equipment HD monitor LED Set 6 42,000 252,000
a) Transformers
b) Diesel Generators
d) HV Circuit Breaker
Note:
0.163×1×55.56×7
Pump Output Power= ×1.15=90kW
0.81
90
Motor Rated Power= =95.75kW~110kW
0.94
Submersible sewage
1 4 2 110.00 440.00 220.00 0.83 0.95 209.00 140.45 251.81
pump
2 Coarse screen machine 2 2 1.50 3.00 3.00 0.80 0.75 2.25 1.69 2.81
3 Screw conveyor 1 1 3.00 3.00 3.00 0.80 0.75 2.25 1.69 2.81
4 Electric crane 2 2 16.20 32.40 32.40 0.82 0.10 3.24 2.26 3.95
Electrical Sluice
5 2 2 3.00 6.00 6.00 0.80 0.10 0.60 0.45 0.75
gate(rectangle)
Electrical Sluice
6 2 2 3.00 6.00 6.00 0.80 0.10 0.60 0.45 0.75
gate(rectangle)
Electrical Sluice
7 1 1 3.00 3.00 3.00 0.80 0.10 0.30 0.23 0.38
gate(rectangle)
Electrical Sluice
8 1 1 1.50 1.50 1.50 0.80 0.10 0.15 0.11 0.19
gate(circular)
Electrical Sluice
9 1 1 2.00 2.00 2.00 0.80 0.10 0.20 0.15 0.25
gate(circular)
Electrical Sluice
10 2 2 2.00 4.00 4.00 0.80 0.10 0.40 0.30 0.50
gate(circular)
Submersible sewage
11 2 2 4.20 8.40 8.40 0.80 0.20 1.68 1.26 2.10
pump
12 Axial flow fan 2 2 0.75 1.50 1.50 0.80 0.20 0.30 0.23 0.38
14 Maintenance power box 3 1 5.00 15.00 5.00 0.80 0.10 0.50 0.38 0.63
17 Consent Power 1 1 5.00 5.00 5.00 0.80 0.50 2.50 1.88 3.13
Total
Sum 565.80 335.80 252.97 166.88 303.34
(kW)
Note:
■For lighting-15W/m2
■For HVAC-100W/m2
LxBxH=1500x700x800,
3 Slag bucket Set 1 420,000.00 420,000.00
Material: SS304
DN800, H=7.905m
4 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=1.5kW
BxH=1x1,H=7.9m
5 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=3kW
BxH=1x1,H=7.6m
6 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=3kW
DN800,H=4.458m
7 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=2kW
DN500,H= 4.65m,
8 Electrical sluice gate Set 2 1,680,000.00 3,360,000.00
N=2kW
duty-2, Standby-1,
9 Submersible sewage pump Q=0.202m3/s, H=5.5m,N=22kW Set 3 3,360,000.00 10,080,000.00
VFD Control
1 Frequency Converter (VFD) 22kW Pump motor matching frequency Set 3 336,000 1,008,000
I Monitoring Equipment
Intel core i5, 3G, memory 8G DDR4 2400 MHz, Hard
1 Industrial Personal Computer Set 3 168,000 504,000
disk 1T
2 Workstation According to Intel corei5 processor Set 1 420,000 420,000
Rack server; CPU: Intel Xeon, E5 2600 V4 series;
3 Communication Server Set 1 336,000 336,000
core:16, 3G
4 Exchange 100M/24 interfaces Set 1 84,000 84,000
II Software system - -
IV Instrumentation - -
a) Transformers
b) Diesel Generators
d) HV Circuit Breaker
Submersible sewage
1 3 2 90.00 270.00 180.00 0.83 0.95 171.00 114.91 206.02
pump
2 Coarse screen machine 1 2 1.50 1.50 3.00 0.80 0.75 2.25 1.69 2.81
3 Screw conveyor 1 1 3.00 3.00 3.00 0.80 0.75 2.25 1.69 2.81
4 Electric crane 2 2 16.20 32.40 32.40 0.82 0.10 3.24 2.26 3.95
Electrical Sluice
5 2 2 3.00 6.00 6.00 0.80 0.10 0.60 0.45 0.75
gate(rectangle)
Electrical Sluice
6 2 2 3.00 6.00 6.00 0.80 0.10 0.60 0.45 0.75
gate(rectangle)
Electrical Sluice
7 1 1 3.00 3.00 3.00 0.80 0.10 0.30 0.23 0.38
gate(rectangle)
Electrical Sluice
8 1 1 1.50 1.50 1.50 0.80 0.10 0.15 0.11 0.19
gate(circular)
Electrical Sluice
9 1 1 2.00 2.00 2.00 0.80 0.10 0.20 0.15 0.25
gate(circular)
Electrical Sluice
10 2 2 2.00 4.00 4.00 0.80 0.10 0.40 0.30 0.50
gate(circular)
Submersible sewage
11 2 2 4.20 8.40 8.40 0.80 0.20 1.68 1.26 2.10
pump
14 Maintenance power box 3 1 5.00 15.00 5.00 0.80 0.10 0.50 0.38 0.63
15 Power of PLC 1 1 5.00 5.00 5.00 0.80 1.00 5.00 3.75 6.25
18 Potable Water Pump 1 1 3.00 3.00 3.00 0.80 0.80 2.40 1.80 3.00
Total
Sum 397.30 298.80 217.37 143.15 260.55
(kW)
Note:
2
■For lighting-15W/m
2
■For HVAC-100W/m
2
■For Electric Room, Transformer & Generator HVAC-120W/m
1 Rotary coarse screen Grate interval 25mm,mounting angle 75o Set 1 12,600,000.00 12,600,000.00
H=8.540m,N=1.5kW
3
2 Screw conveyor Q=5m /h, L=2m, N=1.5kW Set 1 4,200,000.00 4,200,000.00
LxBxH=1500x700x800,
3 Slag bucket Set 1 420,000.00 420,000.00
Material: SS304
DN600, H=7.940m
4 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=1.5kW
BxH=1x1,H=7.74m
5 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=3kW
BxH=1x1,H=8.54m
6 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=3kW
DN600,H=6m
7 Electrical sluice gate Set 1 1,680,000.00 1,680,000.00
N=2kW
1 Frequency Converter (VFD) 11kW Pump motor matching frequency Set 2 252,000 504,000
including incoming and
2 HV incoming and outgoing lines cabinet KYN28-12, (H2200xW800xD1000) Set 2 1,092,000 2,184,000
outgoing wire cabinet
I Monitoring Equipment
Intel core i5, 3G, memory 8G DDR4 2400 MHz, Hard
1 Industrial Personal Computer Set 3 168,000 504,000
disk 1T
2 Workstation According to Intel corei5 processor Set 1 420,000 420,000
Rack server; CPU: Intel Xeon, E5 2600 V4 series;
3 Communication Server Set 1 336,000 336,000
core:16, 3G
4 Exchange 100M/24 interfaces Set 1 84,000 84,000
II Software system - -
IV Instrumentation - -
a) Transformers
b) Diesel Generators
d) HV Circuit Breaker
Submersible sewage
1 2 1 11.00 22.00 11.00 0.83 0.95 10.45 7.02 12.59
pump
2 Coarse screen machine 1 1 1.50 1.50 1.50 0.80 0.75 1.13 0.84 1.41
3 Screw conveyor 1 1 1.50 1.50 1.50 0.80 0.75 1.13 0.84 1.41
4 Electric crane 2 2 7.85 15.70 15.70 0.82 0.10 1.57 1.10 1.91
Electrical Sluice
5 1 1 3.00 3.00 3.00 0.80 0.10 0.30 0.23 0.38
gate(rectangle)
Electrical Sluice
6 1 1 3.00 3.00 3.00 0.80 0.10 0.30 0.23 0.38
gate(rectangle)
Electrical Sluice
7 1 1 1.50 1.50 1.50 0.80 0.10 0.15 0.11 0.19
gate(circular)
Electrical Sluice
8 1 1 2.00 2.00 2.00 0.80 0.10 0.20 0.15 0.25
gate(circular)
Submersible sewage
9 2 2 4.20 8.40 8.40 0.80 0.20 1.68 1.26 2.10
pump
10 Axial flow fan 2 2 0.75 1.50 1.50 0.80 0.20 0.30 0.23 0.38
11 Maintenance power box 3 1 5.00 15.00 5.00 0.80 0.10 0.50 0.38 0.63
15 Potable Water Pump 1 1 3.00 3.00 3.00 0.80 0.80 2.40 1.80 3.00
Total
Sum 118.10 97.10 51.60 31.43 60.65
(kW)
Note:
2
■For lighting-15W/m
2
■For HVAC-100W/m
2
■For Electric Room, Transformer & Generator HVAC-120W/m
J: Cost of Package 8
(Gulshan and Banani including Gulshan SLS & Tejgaon SLS, designed
by IWM)
Package - 08 (1)
Gulshan
Grand Summary
Bill No. 3: Gravity Sewer Manholes, Air valve Chamber; Wash out
135,089,276
valve Chamber and Discharge Chamber
Service Connection:
(a) Construction of 100mm/150 mm diameter service connection
including service pit with the supply of all necessary construction
materials, CI manhole cover, pipe materials and fittings as per
No.
specifications and drawings. This item shall also include
excavation and refilling of trenches.
(i) 100 mm Service connection line with service pit No. 75 21,273 1,595,475
(ii) 150 mm Service connection line with service pit No. 175 21,623 3,784,025
209
Unit
Item Nominal
Description Unit Price Total Price (BDT) Remarks
no. quantity
(BDT)
a b c d e f g
Include the sum of 3,000,000 for materials as
certified for works executed by Dayworks. The
cost shall be the net invoiced cost of the
materials including cash discounts plus the
D201 3,000,000
net cost of transport to the site.
Subtotal 3,000,000
D122 Allow 8 percent of Subtotal for Contractor’s 240,000
Total for Daywork: Materials
3,240,000
(carried forward to Daywork Summary)
Nominal
Item Unit Price Total Price
Description quantity Remarks
no. (BDT) (BDT)
(hours)
a b c d e f
D301 Excavator, face shovel, or dragline:
0.1 Up to and including 1 m3 500 2,000 1,000,000
0.2 Over 1 m3 to 2 m3 400 3,000 1,200,000
0.3 Over 2 m3 100 3,510 351,000
D302 Tractor, including bull or angle dozer:
0.1 Up to and including 150 kW 500 1,000 500,000
0.2 Over 150 kW to 200 kW 400 1,500 600,000
0.3 Over 200 kW to 250 kW 200 2,000 400,000
D303 Tractor with ripper:
0.1 Up to and including 200 kW 400 1,500 600,000
0.2 Over 200 kW to 250 kW 200 2,000 400,000
D304 Portable concrete mixer - 0.4m3 400 500 200,000
D305 Hydraulic Excavator – 1 m3 500 3,000 1,500,000
D306 4-tool compressor including tools and hoses 500 2,000 1,000,000
D307 10 tonne lorry-mounted crane 500 5,000 2,500,000
D308 750 Kg crane 500 2,000 1,000,000
D309 0.5 m3 dumper 500 1,000 500,000
D310 1 m3 dumper 500 1,500 750,000
D311 7 m3 tipper lorry 500 2,000 1,000,000
D312 15 m3 lorry 500 2,000 1,000,000
D313 4 wheel drive pick-up or van 500 500 250,000
D314 Vibrating plate compactor 500 500 250,000
D315 8-10 tonne roller 500 2,000 1,000,000
Total for Daywork: Contractor’s Equipment
16,001,000
(carried forward to Daywork Summary)
Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
General Items
Mobilisation Establish, maintain and
1 remove Contractor's site office, 1 sum 335,020 335,020
workshops, welfare and other facilities.
Provision and removal of the Engineer's
2 accommodation, equipment and site 1 sum 335,020 335,020
facilities
Operation and maintenance of the
3 Engineer's accommodation, equipment 1 yr 335,020 335,020
and site facilities
4 Approval of the Authorities 1 sum 850,000 850,000
Insurances
For Design 1 sum 586,285 586,285
For Third Party Liability 1 sum 439,714 439,714
5
For Contractor's Equipment 1 sum 439,714 439,714
For Site against Fire 1 sum 439,714 439,714
For Workers 1 sum 439,714 439,714
6 Maintenance of Site, Storage, Guarding 1 yr 335,020 335,020
7 Maintenance of Flow During Construction 1 sum 335,020 335,020
8 Temporary pipelines and facilities 1 sum 335,020 335,020
9 Necessary Testing and Quality Control 1 sum 335,020 335,020
10 Consumables 1 sum 850,000 850,000
Heating -
Electricity -
Telecommunication -
11 Provide and Maintain and bonds and guarantees1 sum 293,143 293,143
12 Test on Taking Over 1 sum 293,143 293,143
13 Test During Guarantee Period 1 sum 100,000 100,000
Grand Summary
Amount
General Summary Page Remarks
(BDT)
a b c d
Bill No. 1: General Items 16,405,480
Bill No. 2: Procurement and Construction of Sewers 1,229,715,075
Service Connection:
(a) Construction of 100mm/150 mm diameter service connection
including service pit with the supply of all necessary construction
materials, CI manhole cover, pipe materials and fittings as per
No.
specifications and drawings. This item shall also include
excavation and refilling of trenches.
(i) 100 mm Service connection line with service pit No. 50 21,273 1,063,650
(ii) 150 mm Service connection line with service pit No. 150 21,623 3,243,450
209
(b) Construction of 100mm/150 mm diameter sewer line (including
T connection with main pipe) and connection of the lines with the
existing service pit where possible including supply of all
necessary construction materials, pipe materials and fittings as per
specifications and drawings. This item shall also include
excavation and refilling of trenches.
Unit
Item Nominal
Description Unit Price Total Price (BDT) Remarks
no. quantity
(BDT)
a b c d e f g
Include the sum of 3,000,000 for materials as
certified for works executed by Dayworks. The
cost shall be the net invoiced cost of the
materials including cash discounts plus the net
D201 3,000,000
cost of transport to the site.
Subtotal 3,000,000
D122 Allow 8 percent of Subtotal for Contractor’s 240,000
Total for Daywork: Materials
3,240,000
(carried forward to Daywork Summary)
Nominal
Item Unit Price
Description quantity Total Price (BDT) Remarks
no. (BDT)
(hours)
a b c d e f
D301 Excavator, face shovel, or dragline:
0.1 Up to and including 1 m3 500 2,000 1,000,000
0.2 Over 1 m3 to 2 m3 400 3,000 1,200,000
0.3 Over 2 m3 100 3,510 351,000
D302 Tractor, including bull or angle dozer:
0.1 Up to and including 150 kW 500 1,000 500,000
0.2 Over 150 kW to 200 kW 400 1,500 600,000
0.3 Over 200 kW to 250 kW 200 2,000 400,000
D303 Tractor with ripper:
0.1 Up to and including 200 kW 400 1,500 600,000
0.2 Over 200 kW to 250 kW 200 2,000 400,000
D304 Portable concrete mixer - 0.4m3 400 500 200,000
D305 Hydraulic Excavator – 1 m3 500 3,000 1,500,000
D306 4-tool compressor including tools and hoses 500 2,000 1,000,000
D307 10 tonne lorry-mounted crane 500 5,000 2,500,000
D308 750 Kg crane 500 2,000 1,000,000
D309 0.5 m3 dumper 500 1,000 500,000
D310 1 m3 dumper 500 1,500 750,000
D311 7 m3 tipper lorry 500 2,000 1,000,000
D312 15 m3 lorry 500 2,000 1,000,000
D313 4 wheel drive pick-up or van 500 500 250,000
D314 Vibrating plate compactor 500 500 250,000
D315 8-10 tonne roller 500 2,000 1,000,000
Total for Daywork: Contractor’s Equipment
16,001,000
(carried forward to Daywork Summary)
Quantity Unit of
SL No. Description of Items Rate (Tk) Amount (Bd. TK) Remarks
of Works Works
a b c d e f g
General Items
Mobilisation Establish, maintain and
1 remove Contractor's site office, 1 sum 258,741 258,741
workshops, welfare and other facilities.
Provision and removal of the Engineer's
2 accommodation, equipment and site 1 sum 258,741 258,741
facilities
Operation and maintenance of the
3 Engineer's accommodation, equipment 1 yr 258,741 258,741
and site facilities
4 Approval of the Authorities 1 sum 850,000 850,000
Insurances
For Design 1 sum 452,797 452,797
For Third Party Liability 1 sum 339,597 339,597
5
For Contractor's Equipment 1 sum 339,597 339,597
For Site against Fire 1 sum 339,597 339,597
For Workers 1 sum 339,597 339,597
6 Maintenance of Site, Storage, Guarding 1 yr 258,741 258,741
7 Maintenance of Flow During Construction 1 sum 258,741 258,741
8 Temporary pipelines and facilities 1 sum 258,741 258,741
9 Necessary Testing and Quality Control 1 sum 258,741 258,741
10 Consumables 1 sum 850,000 850,000
Heating -
Electricity -
Telecommunication -
11 Provide and Maintain and bonds and guarantees1 sum 226,398 226,398
12 Test on Taking Over 1 sum 226,398 226,398
13 Test During Guarantee Period 1 sum 100,000 100,000