Alteration work comprises demolition of
existing buildings, alterations to them and
often items of new works.
The main work section in SMM covering this
class of work is Section C: Demolition
Description Clause
The demolition section starts with the usual descriptive
item giving a general description of the work. Any
limitations on the method of execution of work also to
be stated.
Example of description
Remove 1800mm x 1200mm high timber
casement window including frame and setting
aside and storing old materials for property
of the Employer.
Description Clause
Example of description
Remove 1800mm x 1200mm high timber
casement window including frame from Site
to Contractor's own storage to be re-used.
Description Clause
Example of description
Remove the soil and waste piping from sanitary
fittings to gully trap and inspection chamber
including connection to the compound manhole for
female and male toilet.
Description Clause
Example of description
Remove the 0.48mm Thick Fina Blue B2 'Ajiya' or
approved equal and approved metal roof decking
lapped and fix to purlin with and including
requisite connectors and screws, all as per
manufacturer's instructions (measured nett-no
allowance made for laps)
Description Clause
Shoring C.4