MlTSUBlSHl SELFJECTOR SERIES MD 4-1-17
MlTSUBlSHl SELFJECTOR SERIES MD 4-1-17
Though the setting time of Timer will differ depending on the flow rate of operating water. The standard
setting time at each operation mode is shown in the following Table:
Perform start-up by reference to Fig. 5.1 1 and in accordance with the procedures given in Table 5.21.
Stop
Perform stopping by reference to Fig. 5.11 and in accordance with the procedures given in Table 5.22
Adjusting operation
The adjusting operation is performed for adjustment of the quantity of sludge discharge. After
confirming that purifying operation has commenced, adjust the quantity of discharge in accordance with
the following procedures.
NOTE:
1. Before conducting "Discharge Test", push manually the Solenoid Valve SV6 for about ten (10) seconds
and lift up the cylinder valve and keep the LD tank completely empty, thereby the amount of sludge
accumulated in the leakage Detector can be accurately measured.
2.Sludge discharge quantity varies depending on small difference in pressure and so on and therefore,
measure discharge quantity per each equipment.