Professional Documents
Culture Documents
Conventional Exergetic and Exergoeconomi PDF
Conventional Exergetic and Exergoeconomi PDF
77-86, 2010
ISSN 1301-9724 www.icatweb.org/ijot
Abstract
Exergy-based methods can be used as a tool for examining, comparing and assessing thermodynamic systems. In
this paper, an exergoeconomic analysis is used to evaluate a power plant with chemical looping combustion (CLC)
for CO2 capture. This oxy-fuel plant is compared, from an exergetic and an economic perspective, to a conventional,
reference power plant without CO2 capture. The exergetic analysis shows decreased exergy destruction in the CLC
reactors, compared to the exergy destruction in the conventional combustion chamber of the reference case; thus, the
irreversibilities caused by combustion in the CLC are reduced. However, due to the addition of the CO2 compression
unit, the overall exergetic efficiency of the plant with CLC is lower than that of the reference plant by approximately
5 percentage points. The economic analysis confirms a significant increase in the investment cost of the CO2 capture
plant, due to the addition of the units for CO2 compression and CLC. Thus, the cost of electricity is 24% higher for
this plant in comparison to that of the reference case. Nevertheless, when compared to the reference plant with CO2
capture with monoethanolamine, the plant with CLC was found to be a more economical option. Since CO2
abatement must be realized in the future, given expected environmental or tax measures, CLC provides relatively
low cost carbon dioxide capture and it, therefore, appears to be a promising option for reducing greenhouse gases
emitted by power plants using fossil fuels.
Keywords: CO2 capture, chemical looping combustion, exergetic analysis, exergoeconomic analysis.
*This paper is an updated version of a paper published in the ECOS’09 proceedings. It is printed here with permission of the authors and
organizers.
**Corresponding Author Vol. 13 (No. 3) / 77
product can be defined as the exergy of the desired output estimate the total capital investment (TCI) of a project, the
resulting from the operation of a component, while the total expenses of the construction and the overall operation
exergy of the fuel is the expense in exergetic resources for of the plant must be assessed. The economic life of the
the generation of this desired output. The exergy plant is assumed to be 20 years, while its life for tax
destruction within a component is then calculated as the purposes is 15 years. The date of commercial operation of
difference between the exergy of the fuel and the exergy of the plant is set to 01.01.2012 with a two year period of
the product ( E D , k = E F , k − E P , k ). design and construction preceding. The average capacity
factor of the plant is assumed to be 85%, resulting in an
In dissipative components, such as condensers,
annual operation of 7446 hours. The total capital
intercoolers and throttling valves, exergy is destroyed
requirement (TCR) of the plant comes from equity and debt
without any useful product in the component itself; thus, no
financing with a 10% average annual rate of the cost of
exergetic purpose for these components can be defined
money. Lastly, all costs, except that of the fuel, increase
(Bejan et al., 1996; Lazzaretto and Tsatsaronis, 2006). The
annually with an inflation rate of 3%; the cost of natural gas
essential role of these components is to serve other
is assumed to be 7€ per GJ of lower heating value (LHV:
components, or the overall system.
50.015 MJ/kg) and its average annual increase amounts to
For the component-level analysis, all streams exiting a
4%.
component are considered either as part of the product, or
With these assumptions the levelized TRR is calculated
they are used in the definition of the component’s fuel.
for a levelization period of 10 years. After completion of
Thereafter, exergy loss ( E L,tot ) is defined only for the the economic analysis, the exergy costing procedure and an
overall system. exergoeconomic evaluation follow.
The exergetic efficiencies of the kth component and of
the overall system consisting of NC-components are 2.3 Exergoeconomic Analysis
defined by Eqs. (1a) and (1b), respectively: In an exergoeconomic analysis a specific cost c is
assigned to each exergy stream of the plant. The specific
E E cost of stream i, ci , multiplied by the exergy of the same
ε k = P,k = 1 − D,k (1a)
EF , k EF , k
stream, E , calculated in the preceding exergetic analysis,
i
NC
provides the cost rate Ci , associated with the ith exergy
E ∑ E D,k + E L ,tot
stream:
ε tot = P ,tot = 1 − k =1
(1b)
EF ,tot E F ,tot
Ci = ci E i (3)
Here the system’s exergy of the product ( E P ,tot ) is the
The cost balance for the kth component is
net power produced, whereas the system’s exergy of the
fuel ( E F ,tot ) is the sum of the fuel and the air exergy i =n j=m
This ratio is a measure of the contribution of the exergy streams leaving component k , and
destruction within each component to the reduction of the Zk is the cost rate associated with the investment cost and
overall exergetic efficiency.
With the aid of an exergetic analysis, the main sources the operating and maintenance costs of component k. Z is k
of irreversibilities within a plant are identified and are then known from the preceding economic analysis.
linked to costs in the exergoeconomic evaluation. An important variable of the exergoeconomic evaluation
is the relative cost difference. For a given component k, the
2.2 Economic Analysis difference between the specific cost of the product, cP , k ,
For the economic analysis, the total revenue
and the specific cost of the fuel, cF , k , depends on the cost
requirement (TRR) method has been implemented (Bejan et
al., 1996). The first step of the analysis is to calculate the of exergy destruction, C D , k , and the investment-based cost
fixed capital investment (FCI) of the plant (Tsatsaronis and
Winhold, 1984; Tsatsaronis et al., 1990; U.S. Department Zk . The relative cost difference, rk is defined by
of Energy, 2000; Gas Turbine World Handbook, 2006).
Costs are then escalated to the reference year 2008 using ⎛c −c ⎞
the chemical engineering plant cost index (CEPCI) as rk = ⎜ P , k F , k ⎟⎟ (5)
⎜ c
published in Chemical Engineering Magazine. ⎝ F ,k ⎠
The next step that allows the implementation of the
TRR method is to meet assumptions concerning market The contribution of the capital cost to the total sum of
conditions, plant operation and plant construction. To costs associated with capital investment and exergy
Reactors CO2/H2O
64 3 4 Expander
63 Chemical 57 53
G
NG NG PH Looping M
31
2 Combustion 5 Steam Turbine Pump
Compressor GT
G 45
46 G
6 9
1 Gas Turbine 67
7 48
: Air HP HRSG LPS T49
HPST IPS T Mixer 5
: Flue gas RH 43 44 68
: Water/ Steam 30 8 10 HPS H 32 47 Cooling
56 Condenser
: CO2/H2O stream 52 65 66 Tower
11 Mixer 4
: Shaft 29 Mixer 3 M
Me x
+ Oy
Air Fuel
reactor, reactor,
AR FR
Me x
+O y-1
Air CH 4
3
2
Figure 3. Configuration of Chemical Looping Combustion (the numbering of the streams agrees with Figure 2).
Table 1. Calculated variables for selected streams of the reference case without CO2 capture.
Table 2. Calculated variables for selected streams of the plant with CLC.
Table 3. Results of the exergetic and exergoeconomic analyses at the component-level for the reference case.
E F ,k E P ,k E D ,k εk yk cF ,k cP ,k C D ,k Z k fk rk
Component, k
[MW] [MW] [MW] [%] [%] [€/GJ] [€/GJ] [€/h] [€/h] [%] [%]
Compressor 242.68 231.30 11.38 95.3 1.56 16.67 19.05 682.8 1297.0 65.5 14.3
CC 729.62 508.76 220.87 69.7 30.23 9.15 13.63 7276.3 926.5 11.3 48.9
GT 551.15 530.67 20.47 96.3 2.80 15.30 16.67 1127.9 1482.3 56.8 8.9
Reheater 26.47 23.89 2.58 90.3 0.35 15.30 19.13 141.9 105.4 42.6 25.0
HPSH 35.07 31.72 3.35 90.5 0.46 15.30 19.16 184.5 149.5 44.8 25.2
HPEVAP 43.64 39.91 3.73 91.5 0.51 15.30 18.83 205.3 183.6 47.2 23.1
HPECON 28.92 24.91 4.00 86.2 0.55 15.30 20.16 220.5 88.6 28.7 31.8
IPSH 0.18 0.12 0.06 69.0 0.01 15.30 34.61 3.1 3.8 55.2 126.1
IPEVAP 6.10 5.67 0.43 92.9 0.06 15.30 20.32 23.8 65.0 73.2 32.8
IPECON 1.06 0.87 0.19 82.5 0.03 15.30 22.06 10.2 5.2 33.5 44.2
LPSH 1.43 1.04 0.38 73.3 0.05 15.30 28.97 21.0 18.3 46.6 89.3
LPEVAP 19.03 15.48 3.55 81.4 0.49 15.30 23.93 195.4 172.8 46.9 56.4
LPECON 11.49 7.71 3.78 67.1 0.52 15.30 30.48 208.5 92.7 30.8 99.2
HPST 31.29 29.18 2.11 93.2 0.29 20.10 23.77 152.9 165.6 52.0 18.3
IPST 37.39 35.21 2.18 94.2 0.30 20.03 24.19 157.4 299.7 65.6 20.7
LPST 70.99 61.35 9.64 86.4 1.32 21.15 29.01 734.3 696.3 48.7 37.2
Condensate Pump 0.04 0.04 0.01 78.8 0.00 19.64 80.52 0.7 6.7 91.0 310.0
HP Pump 1.12 0.96 0.17 85.3 0.02 19.64 35.63 11.7 38.2 76.6 81.4
IP Pump 0.03 0.02 0.01 65.3 0.00 19.64 140.35 0.7 7.3 91.0 614.6
LP Pump 0.00 0.00 0.00 67.2 0.00 19.64 384.64 0.1 2.4 97.3 1858.4
De-aerator 0.56 0.53 0.03 95.4 0.00 24.79 40.05 2.3 26.1 92.0 61.6
Mixer 1 1.81 1.63 0.18 90.1 0.02 20.03 22.49 12.9 0.0 − 12.2
Mixer 2 0.63 0.58 0.04 92.9 0.01 20.10 24.35 3.2 0.0 − 21.2
Mixer 3 0.18 0.18 0.00 99.9 0.00 15.30 15.32 0.0 0.0 − 0.1
Condenser 12.43 − 7.53 − 1.70 21.15 − 946.4 85.7 8.3 −
Total (EL=14 MW) 730.58 411.40 305.15 56.3 41.77 9.15 20.53 10053.1 6459.9 39.1 124.4
E F ,k E P ,k E D ,k εk yk cF ,k cP ,k C D ,k Z k fk rk
Component, k
[MW] [MW] [MW] [%] [%] [€/GJ] [€/GJ] [€/h] [€/h] [%] [%]
Compressor 281.78 268.57 13.21 95.3 1.81 18.32 20.16 871.4 903.7 50.9 10.0
Reactors 694.73 500.67 194.06 72.1 26.56 9.06 15.25 6,332.4 4,823.1 43.2 68.3
GT 540.99 521.34 19.65 96.4 2.69 17.13 18.32 1,211.7 1,032.8 46.0 7.0
CO2/H2O Expander 54.16 51.35 2.81 94.8 0.38 14.61 16.51 147.6 202.2 57.8 12.9
NG PH 6.32 1.12 5.20 17.7 0.71 14.61 84.49 273.8 7.4 2.6 478.1
Reheater 16.60 14.36 2.24 86.5 0.31 17.13 22.20 138.2 52.3 27.4 29.6
HPSH 22.43 20.43 1.99 91.1 0.27 17.13 21.06 123.0 102.5 45.5 23.0
HPEVAP 35.74 32.97 2.77 92.2 0.38 17.13 20.52 170.8 142.6 45.5 19.8
HPECON 24.25 20.58 3.67 84.9 0.50 17.13 22.54 226.1 57.5 20.3 31.6
IPSH 0.63 0.49 0.14 78.1 0.02 17.13 28.74 8.5 7.6 47.2 67.8
IPEVAP 11.97 11.00 0.97 91.9 0.13 17.13 21.77 60.0 92.5 60.7 27.1
IPECON 2.03 1.70 0.33 83.6 0.05 17.13 23.65 20.5 8.7 29.8 38.1
LPSH 1.12 0.81 0.32 71.9 0.04 17.13 31.82 19.4 13.1 40.3 85.8
LPEVAP 17.03 13.99 3.03 82.2 0.42 17.13 25.51 187.1 137.9 42.4 48.9
LPECON 11.28 7.52 3.76 66.6 0.51 17.13 32.90 232.0 74.0 24.2 92.1
SH II 0.48 0.42 0.05 88.6 0.01 14.61 20.04 2.9 3.7 56.2 37.1
EVAP II 2.03 1.93 0.10 95.2 0.01 14.61 17.36 5.1 10.8 67.7 18.8
ECON II 1.47 1.20 0.27 81.8 0.04 14.61 20.42 14.1 2.6 15.4 39.7
HPST 24.14 22.41 1.73 92.8 0.24 22.01 25.59 137.0 95.9 41.2 16.2
IPST 22.98 21.57 1.41 93.9 0.19 22.27 26.08 112.8 138.4 55.1 17.1
LPST 48.80 42.17 6.63 86.4 0.91 23.55 31.02 561.8 360.8 39.1 31.8
ST for CO2 supply 20.73 15.66 5.06 75.6 0.69 22.29 34.96 406.3 146.0 26.4 56.9
Condensate Pump 0.04 0.03 0.01 78.6 0.00 20.37 72.99 0.7 5.4 89.0 258.3
HP Pump 0.98 0.84 0.14 85.3 0.02 20.37 34.75 10.6 28.0 72.6 70.6
IP Pump 0.05 0.04 0.02 70.1 0.00 20.37 95.73 1.1 8.2 87.9 369.9
LP Pump 0.00 0.00 0.00 66.5 0.00 20.37 348.84 0.1 1.9 96.8 1612.4
CO2 Compressor 1 3.85 3.24 0.61 84.1 0.08 34.96 182.09 76.9 294.1 79.3 420.8
CO2 Compressor 2 3.96 3.32 0.64 83.8 0.09 34.96 73.28 81.0 302.4 78.9 109.6
CO2 Compressor 3 3.91 3.27 0.64 83.5 0.09 34.96 75.71 81.0 298.4 78.7 116.6
CO2 Compressor 4 3.93 3.26 0.67 83.0 0.09 34.96 76.53 84.0 299.8 78.1 118.9
De-aerator 0.44 0.42 0.02 95.6 0.00 26.45 41.59 1.8 20.7 91.8 57.3
Mixer 1 0.85 0.79 0.06 92.5 0.01 22.27 24.80 5.1 0.0 0.0 11.4
Mixer 2 0.08 0.08 0.00 99.4 0.00 22.01 22.22 0.0 0.0 0.0 0.9
Mixer 3 1.99 1.97 0.02 99.1 0.00 17.13 17.37 1.1 0.0 0.0 1.4
Mixer 4 0.77 0.73 0.05 93.9 0.01 22.10 24.10 3.7 0.0 0.0 9.1
Mixer 5 0.12 0.12 0.00 100.0 0.00 23.55 23.55 0.0 0.0 0.0 0.0
Flue gas condenser 22.36 - 18.65 - 2.55 14.70 - 1,183.0 70.6 5.6 -
Cooler 1 0.77 - 0.62 - 0.08 33.04 - 91.8 8.7 8.7 -
Cooler 2 0.91 - 0.74 - 0.10 37.19 - 122.0 8.7 6.6 -
Cooler 3 0.85 - 0.70 - 0.10 40.80 - 124.4 7.9 5.9 -
Cooler 4 0.86 - 0.71 - 0.10 43.94 - 136.7 10.2 6.9 -
Condenser 11.52 - 6.99 - 0.96 23.25 - 964.5 66.2 6.4 -
Total (EL=43 MW) 730.73 374.82 312.89 51.29 42.82 9.15 25.46 10,308.1 10,422.8 50.3 178.2
plant increases by about 30%. The cost of the avoided CO2 100% CO2 capture, has been compared to a simple
in the case with MEA would then be 78.3 €/t, a price 47% combined cycle plant without CO2 capture and briefly to a
higher, than that of the plant with CLC. The difference in plant with CO2 capture through chemical absorption using
cost is caused by the high energy consumption during monoethanolamine.
regeneration and the lower CO2 capture percentage (85%) An exergetic analysis showed lower irreversibilities for
assumed for the plant with MEA. the chemical looping reactors in comparison to the
conventional combustion chamber of the reference case.
5. Conclusions Moreover, the process resulted in a decrease of the
In this paper, a three-pressure-level combined cycle exergetic efficiency by about 5 percentage points with
plant using chemical looping combustion for approximately respect to the case without CO2 capture; yet it achieves an