Construction of Combined Warehouse for HIV, TB, Malaria at NIH, Islamabad

Activity Sequence For Plinth Beams


Sr. Joint-4 Joint-3 Joint-2 Joint-1
Description Remarks
No Start Finish Start Finish Start Finish Start Finish

1 PCC 14/05/20 21/05/20 22/05/20 7/6/2020 8/6/2020 15/6/2020 16/6/2020 23/6/2020

2 Steel 1/6/2020 12/6/2020 13/6/2020 25/06/2020 26/6/2020 8/7/2020 9/7/2020 21/7/2020

3 Formwork 13/6/2020 25/06/2020 26/06/2020 7/7/2020 9/7/2020 21/7/2020 22/7/2020 3/8/2020

4 Concreting 26/06/2020 27/06/2020 8/7/2020 9/7/2020 22/7/2020 23/07/2020 4/8/2020 5/8/2020

Actual Date of
Pouring of Concrete 19/06/2020 20/06/2020