Professional Documents
Culture Documents
Abstract—The paper is devoted to the identification of trans- method is widely used for power system state and parameter
mission lines from synchronized measurements of current and estimation, where weights are commonly set to be the inverse
voltage phasors provided by the phasor measurement units of the measurement error variances [3]. Each time, the line
(PMUs). The series and shunt line parameters are recursively
estimated using the extended Kalman filter (EKF). Actual line parameters are estimated based on a redundant number of
temperature and reference resistance are estimated instead of current and voltage measurements taken at different time
actual series resistance, which is then computed from these instants. The number of measurements used is limited by nu-
estimates. This approach can accommodate more information merical stabilityand must be sufficiently large to yield reliable
and, therefore, produce better estimates of the line resistance than instantaneous estimates of time varying parameters [1], [4].
the traditional approaches based on the weighted least squares
method. Two case studies based on data from South Moravia and Therefore, new approach that uses a nonlinear filtering method
East Bohemia are presented to demonstrate the effectiveness of for parameter estimation is proposed in this paper. Instead of
the proposed approach. directly estimating actual series resistances of the line, series
resistances corresponding to some reference average tempera-
I. I NTRODUCTION ture and actual average line temperature will be estimated.
As the demand for electricity transmission capacity in- The paper is organized such that Section II describes
creases the knowledge of transmission line parameters in- the proposed model of the transmission line and introduces
volving series impedance and shunt admitance is crucial to the EKF based parameter estimation method. The proposed
determine the line ampacity. While construction parameters approach is illustrated in two case studies from South Moravia
are commonly valid when the line is designed, actual values and East Bohemia in Section III. The results are summarized
differ due to line age, ambient conditions and the load of line. in Section IV.
It is therefore necessary to compute the actual parameters to
II. T RANSMISSION LINE PARAMETER ESTIMATION BY EKF
ensure effective and safe operation of the transmission line.
Several approaches for estimating the line parameters from Average conductor temperature T at time t can be computed
measured data were discussed in the past. The accuracy of the using the following non-steady-state heat balance formula
estimated values is significantly influenced by measurement given in the standard IEEE Std 738T M − 2006 [5]:
errors and errors in synchronization of data acquisition. Firstly, dT 1
τ = R(T )I 2 (t) − qc − qr , (1)
there was an effort to use measurements from the Supervisory dt l
Control and Data Acquisition (SCADA) system. However, it R(T ) = R20 (1 + α (T − 20)), (2)
was not possible to reach a satisfactory solution due to con-
where
siderable synchronization inaccuracy of measured data, mainly
caused by the δ–criterion used for data transfer [1]. A more τ total heat capacity of conductor,
promissing way to acquire data utilizes synchronized current l length of conductor,
and voltage phasor PMU measurements, which utilize GPS I(t) absolute value of current through the series
signals to guarantee high precision of mutual synchronization impedance at time t,
of measurements from both ends of the line. A number of qc convected heat loss rate per unit length,
papers deal with the utilization of synchronized phasors in qr radiated heat loss rate per unit length,
wide area measurement systems, e.g. [2] and other references R(T ) AC resistance of conductor at temperature T,
mentioned therein. R20 AC resistance of conductor at reference
Contrary to the synchronization errors, which are solved temperature 20o C,
on the hardware side using PMUs, impact of measurement α temperature coefficient of resistance.
errors should be minimized by using an apropriate model Averaged conductor temperature is understood as the average
and estimation method. The weighted least squares (WLS) between conductor core and surface temperature.
where
∆t
f1 (sk ) = Tk + R20,k (1 + α (Tk − 20)) Ik2 −
τl
∆t
− (qr,k + qc,k ) , (7)
τ
f2 (sk ) = R20,k , (8)
Fig. 1. Model of the transmission line. f3 (sk ) = Xk , (9)
f4 (sk ) = Gk , (10)
f5 (sk ) = Bk . (11)
Let us consider a three-phase transmission line, where
PMUs are installed at both ends of each phase. PMUs Noise wk makes it possible to represent uncertainty in the
measure, at discrete time instants k and with period ∆t, development of parameter values and possible time variability.
voltage phasors, U ~ k = URe,k + jUIm,k , and current phasors,
As all parameters, with the exception of temperature, are
~
Ik = IRe,k + jIIm,k . Phasors measured at one end will assumed to be constant, wk is set wk = 0 for all k.
be marked with superscript A and at the other end with Measurement equations are considered in the form
superscript B. Moreover,suppose that the ambient temperature
and wind speed along the line are measured. The objective is ∆URe,k
to estimate line average temperature Tk , reference resistance ∆UIm,k
zk =
∆IRe,k = hk (sk ) + ek ,
(12)
R20,k , reactance Xk , shunt conductance Gk and susceptance
Bk based on measurements up to time k. Instead of inde- ∆IIm,k
pendent estimating the line parameters from measurements of
each of the three phases, the symmetrical component for the
Rk K1,k − Xk K2,k
measured voltage and current phasors will be computed [6]. e1,k
Let us define a vector sk of the parameters, which represents Rk K2,k + Xk K1,k e2,k
zk = URe,k
A B A B
+ (13)
+URe,k UIm,k +UIm,k
the estimated state G
k − B k e3,k
2 2
U A +U B U A +U B
Tk G Im,k Im,k + B Re,k Re,k e4,k
k 2 k 2
R20,k
sk = Xk .
(3) where
Gk "
A B
1 A URe,k − URe,k
Bk K1,k = B
IRe,k + IRe,k − Gk +
2 2
In order to use recursive estimation, equation (1) will #
A B
be discretized with period ∆t. Then, the discrete relation UIm,k − UIm,k
describing the development of the average temperature is as +Bk , (14)
2
follows: "
A B
1 A UIm,k − UIm,k
∆t ∆t K2,k = B
IIm,k + IIm,k − Gk −
Tk+1 = Tk + R20,k (1 + α (Tk − 20)) Ik2 − (qr,k + qc,k ) . 2 2
τl τ
(4) A B
#
Since the phasor values are not measured accurately, but URe,k − URe,k
−Bk , (15)
they are affected by measurement errors, absolute value of 2
the current Ik through series impedance is computed as the Rk = R20,k (1 + α (Tk − 20)) , (16)
average of the values determined from measurements at both
ends of the line, which model is depicted in Fig. 1. Thus ek denotes measurement errors of measurement instruments
R20 [Ω]
R20 [Ω] 7.36 8.58
4
X[Ω] 19.08 19.31
2
G[µS] — 22.45
B[µS] 137.08 163.34 0
12:00 18:00 0:00 6:00 12:00 18:00 0:00 6:00 12:00
time [h]
Development of average line resistance according to estimated conductor temperature
10
following relations:
Rk [Ω]
5
sk|k = sk|k−1 + KF,k zk − hk (sk|k−1 ) , (18)
−1
= Pk|k−1 HTk Hk Pk|k−1 HTk + R
KF,k , (19)
0
Pk|k = Pk|k−1 − KF,k Hk Pk|k−1 , (20) 12:00 18:00 0:00 6:00 12:00 18:00 0:00 6:00 12:00
time [h]
sk+1|k = f (sk|k ), (21)
Estimated value Designed value
Pk+1|k = Fk Pk|k FTk , (22)
Fig. 2. Development of estimated reference resistance and computed
where sk|k is the state estimate at time k based on measure- actual resistance of the conductors according to the increasing number of
ment history up to time k, sk+1|k is the one-step prediction measurements from the line in South Moravia.
of the state at time k + 1 based on measurement history up to
Development of the estimated average line temperature
time k, 22
16
∂h2,k T
14
∂hk
∂s
Hk = = k T ,
12
∂sk sk =sk|k−1
∂h3,k 10
∂sk
T 8
∂h4,k 12:00 18:00 0:00 6:00 12:00 18:00 0:00 6:00 12:00
time [h]
∂sk
Development of absolute value of the line current synchronous component
160
T 140
∂f1 120
∂sk 100
I [A]
∂f 0 1 0 0 0 80
Fk = = .
∂sk sk =sk|k
0 0 1 0 0 60
0 0 0 1 0 40
0 0 0 0 1 20
12:00 18:00 0:00 6:00 12:00 18:00 0:00 6:00 12:00
time [h]
19.5
5
T [oC]
k
19 0
12:00 18:00 0:00 6:00 12:00 18:00 0:00 6:00 12:00
time [h]
−5
Development of estimated line conductance
40 Estimated line temperature Ambient temperature
−10
12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00
G [µS]
20 time [h]
I [A]
200
150
100 150
12:00 18:00 0:00 6:00 12:00 18:00 0:00 6:00 12:00
time [h]
100
Estimated value Designed value 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00
time [h]
Fig. 4. Development of estimated reactance X, conductance G and Fig. 6. Development of estimated average temperature Tk of conductor
susceptance B of the line in South Moravia. with respect to the ambient temperature and actual load I of the line in East
Bohemia.
X [Ω]
7
1
6
0 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00
12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 time [h]
time [h]
Development of average line resistance according to estimated conductor temperature Development of estimated line conductance
3 10
G [µS]
2 0
Rk [Ω]
1
−10
12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00
0 time [h]
12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00
time [h]
Development of estimated line susceptance
70
Estimated value Designed value
B [µS]
60
50
Fig. 5. Development of estimated actual resistance and computed actual 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00 0:00 12:00
resistance of conductors according to the ambient temperature and actual load time [h]
of the line in East Bohemia.
Estimated value Designed value
is no need to compute matrix inversion at each time instant. Fig. 7. Development of estimated reactance X, conductance G and
The estimation of reference resistance and actual conductor susceptance B of the line in East Bohemia.
temperature instead of actual resistance allows for the entire
data history to be utilized and, thereby, improves the estimate
[3] A. Abur and A. Expósito, Power System State Estimation, Theory and
of the actual line resistance. Implementation. Marcel Dekker INC., New York, 2004.
[4] Y. Liao and M. Kezunovic, “Online optimal transmission line parameter
ACKNOWLEDGMENT estimation for relying applications,” IEEE Transactions on Power Deliv-
The work was supported by Ministry of Industry and Trade ery, vol. 24, no. 1, 2009.
[5] “IEEE standard for calculating the current–temperature of bare overhead
of the Czech Republic under project FR-TI1/462. conductors, IEEE std 738T M − 2006,” 2007.
[6] J. Blackburn, Symmetrical components for power systems engineering.
R EFERENCES Marcel Dekker INC., New York, 1993.
[1] F. Vávra, “Computation of powerline resistance and reactance,” ZCE,
Tech. Rep., 1998.
[2] A. Phadke and B. Kasztenny, “Synchronize phasor and frequency mea-
surement under transient conditions,” IEEE Transactions on Power De-
livery, vol. 24, no. 1, 2009.