Professional Documents
Culture Documents
A PROJECT REPORT
Submitted by
VIKASH A (312316203303)
of
BACHELOR OF TECHNOLOGY
in
CHEMICAL ENGINEERING
SEPTEMBER 2020
i
ANNA UNIVERSITY : CHENNAI 600 025
BONAFIDE CERTIFICATE
my supervision.
SIGNATURE SIGNATURE
ii
ACKNOWLEDGMENT
iii
CERTIFICATE OF EVALUTION
1 RAKESHRAJ G.R
(312316203301) DESIGN AND EFFICIENCY Ms.R.SIVARANJANEE
OF HEAT M.TECH
EXCHANGERS FOR ASSISTANT
2 VIKASH A CHLORINATION UNIT PROFESSOR
(312316203303)
The report of the project work submitted by the above students in partial
fulfillment for the award of Bachelor of Technology degree in chemical
engineering of Anna University was evaluated and confirmed to be
reports of the work done by the above student and then evaluated.
iv
ABSTRACT
This project work is for kerala minerals and metals Ltd (KMML) at
chavara. They produce very pure rutile grade TiO2 pigment. One of their
unit namely U-200 is designed for the production of titanium tetra
chloride (TiCl4) which is important raw material of TiO2 . After various
chemical processes the product TiCl4 is obtained, which ranges about
150oC in temperature (vapour form). To store the product its temperature
should be reduced to 40oC . In this stage a shell and tube heat exchanger
is used (184 tubes). As the plant undergoes capacity expansion process,
consequently the production of TiCl4 will increase by 65%. This
necessitates a heat exchanger of enhanced capacity. The aim of this
project is to design a shell and tube heat exchangers and spiral heat
exchanger according to various theoretical design available for improving
the capacity and select ones that are suitable for current system at Kerala
Minerals and Metals Ltd (KMML), chavara.
v
TABLE OF CONTENT
Chapter Title Page
No. No.
ABSTRACT v
LIST OF FIGURES x
LIST OF TABLES xi
1 INTRODUCTION
1.1 About the company 1
1.1.1 Milestone of company 2
1.1.2 Products 3
1.1.2.1 Titanium dioxide pigment 3
1.1.2.2 Magnesium chloride 4
1.1.2.3 Titanium tetra chloride 6
1.1.2.4 Ilmenite 6
1.1.2.5 Zircon 7
1.2 Properties of TiO2 9
1.3 Classification of heat exchanger 10
1.4 Types of heat exchanger 10
1.4.1 Shell and tube heat exchanger 11
1.4.1.1 Tube diameter 12
1.4.1.2 Tube thickness 12
1.4.1.3 Tube length 12
1.4.1.4 Tube layout 13
1.4.1.5 Baffle design 13
1.4.2 Plate heat exchanger 14
1.4.3 Plate fin heat exchanger 15
vi
1.4.3.1 Advantages of plate and fin 16
1.4.3.2 Disadvantages of plate and fin 16
1.4.4 Sprial heat exchanger 16
1.5 Advantages of TiO2 17
1.6 Disadvantages of TiO2 18
2 MANUFACTURING PROCESS
2.1 Ilmenite benification plant 19
2.1.1 Roasting 19
2.1.2 Leaching in digesters 20
2.1.3 Tank farm 20
2.1.4 Calcinatoin 20
2.2 Acid regeneration plant 21
2.3 Chlorination plant 22
2.4 Oxidation plant 24
2.5 Sand mill and classification 25
2.5.1 Treatments 26
2.5.2 Filtration and drying 26
2.5.3 Larox 27
2.5.4 Micronisation and condensate cooling 28
2.6 Utilities department 28
2.6.1 Boiler plant 29
2.6.1.1 Water tube boiler 29
2.6.1.2 Fire tube boiler 30
2.6.2 Water treatment plant 31
2.6.3 Air compressor station 32
2.6.4 Effluent compressor station 32
vii
2.6.5 Furnace oil recipt storage 33
3 MATERIAL BALANCE
3.1 Material balance 34
3.2 Over all material balance in heat exchanger 35
4 ENERGY BALANCE
4.1 Heat loss 36
4.2 Heat gain 37
4.3 Total energy balance 37
5 DESIGN OF EQUIPMENT
5.1 Design of shell and tube Heat exchanger 39
5.1.1 To Increase Efficiency 40
5.1.1.1 Case I 41
5.1.1.2 Case II 42
5.1.1.3 Case III 43
5.1.2 Mechanical Design 45
5.1.2.1 Shell Diameter Design 45
5.1.2.2 Material selected for the Shell 46
5.1.3 Design of shell and tube 47
5.2 Spiral heat exchanger 48
5.2.1 Spiral heat exchanger Data 48
5.2.2 Calcination 48
5.2.3 Design of sprial tube heat exchanger 51
6 EXCISTING HEAT EXCHANGER
6.1 Dimensional parameter 52
viii
6.2 Company Requirments 52
6.3 Comparitive study 52
6.3.1 Find hi 55
6.3.2 Finf ho 56
7 PROCESS ECONAMICS
7.1 Cost of Estimation 59
7.2 Maintance Cost 60
CONCLUSION 61
REFERENCE 62
ix
LIST OF FIGURES
x
LIST OF TABLES
xi
xii
xiii
CHAPTER 1
INTRODUCTION
In this project we are going study the design of shell and tube
heat ex-changer and spiral heat ex-changer which has been used in the
kerala minerals and metals ltd at chavara. The aim of this project is to
design a shell and tube heat ex-changers and spiral heat ex-changer
according to various theoretical design available for improving the
capacity
1
the initiatives taken by KMML have made a significant change to the area
and its people.
KMML is now in the aerospace industry & Defence applications with the
commissioning of the titanium sponge plant. The TSP is a joint venture of
KMML, Vikram Sarabhai Space Centre (VSSC) and the Defence
Metallurgical. Research Laboratory (DMRL). The VSSC has
fully funded the Rs.143crore TSP pr-object. With the inauguration of TS
P, India becomes the7th country in the world having the technology for pr
oducing titanium sponge,Which is the raw material for titanium metal.
Titanium sponge is known for its high strength but low weight, making it
an-ideal-material for aircraft manufacture, including fighter aircraft.The m
aterialist,also used In-nuclear plants, Engine parts, Ocean platforms, Re-a
ctors,Heat Ex-changers and to make dental implants and artificial bones.
1992 - Won the First National Award for in-house R&D efforts in
Industry for Technology Absorption under TAAS programme by
DSIR
2
1999 - Erected and commissioned one more Chlorinator in
Chlorination section.
2005 - World class quality management systems like ISO 14001 and
OSHAS-1800 implemented.
1.1.2 Products
Magnesium chloride
Ilmenite
Zircon
3
sourced from ilmenite ore. This is the most widespread form of titanium
dioxide-bearing ore around the world. Rutile is the next most abundant
and contains around 98% titanium dioxide in the ore. The metastable
anatase and brookite phases convert irreversibly to the equilibrium rutile
phase upon heating above temperatures in the range 600–800 °C
(1,110–1,470 °F). Titanium dioxide has eight modifications – in addition
to rutile, anatase, akaogiite, and brookite, three metastable phases can be
produced synthetically (monoclinic, tetragonal, and orthorombic), and
five high-pressure forms (α-PbO2-like, baddeleyite-like, cotunnite-like,
orthorhombic OI, and cubic phases).
4
the Jordan Valley. Magnesium chloride, as the natural mineral bischofite,
is also extracted (by solution mining) out of ancient seabeds, for example,
the Zechstein seabed in northwest Europe. Some magnesium chloride is
made from solar evaporation of seawater. Anhydrous magnesium
chloride is the principal precursor to magnesium metal, which is
produced on a large scale. Hydrated magnesium chloride is the form most
readily available.
5
1.1.2.3 Titanium tetra chloride
1.1.2.4 Ilmenite
6
which is used in paints, printing inks, fabrics, plastics, paper, sunscreen,
food and cosmetics.
1.1.2.5 Zircon
7
The name derives from the Persian zargun, meaning "gold-hued". This
word is corrupted into "jargoon", a term applied to light-colored zircons.
The English word "zircon" is derived from Zirkon, which is the German
adaptation of this word. Yellow, orange and red zircon is also known as
"hyacinth", from the flower hyacinthus, whose name is of Ancient
Greek origin.
8
1.2 Properties of Tio2 :
Formal Charge 0
Complexity 18.3
9
1.3 Classification of heat ex-changer
For efficiency, heat exchangers are designed to maximize the surface area
of the wall between the two fluids, while minimizing resistance to fluid
flow through the exchanger. The exchanger's performance can also be
affected by the addition of fins or corrugations in one or both directions,
which increase surface area and may channel fluid flow or induce
turbulence.
The driving temperature across the heat transfer surface varies with
position, but an appropriate mean temperature can be defined. In most
simple systems this is the "log mean temperature difference" (LMTD).
Sometimes direct knowledge of the LMTD is not available and the NTU
method is used.
10
Double pipe heat exchangers are the simplest exchangers used in
industries. On one hand, these heat exchangers are cheap for both design
and maintenance, making them a good choice for small industries. On the
other hand, their low efficiency coupled with the high space occupied in
large scales, has led modern industries to use more efficient heat
exchangers like shell and tube or plate. However, since double pipe heat
exchangers are simple, they are used to teach heat exchanger design
basics to students as the fundamental rules for all heat exchangers are the
same.
Shell and tube heat exchangers consist of a series of tubes which contain
fluid that must be either heated or cooled. A second fluid runs over the
tubes that are being heated or cooled so that it can either provide the heat
or absorb the heat required. A set of tubes is called the tube bundle and
can be made up of several types of tubes: plain, longitudinally finned, etc.
Shell and tube heat exchangers are typically used for high-pressure
applications (with pressures greater than 30 bar and temperatures greater
than 260 °C). This is because the shell and tube heat exchangers are
robust due to their shape.
Several thermal design features must be considered when designing the
tubes in the shell and tube heat exchangers: There can be many variations
on the shell and tube design. Typically, the ends of each tube are
connected to plenums (sometimes called water boxes) through holes in
tubesheets. The tubes may be straight or bent in the shape of a U, called
U-tubes.
11
Fig 1.2 shell and tube heat ex-changer
Using a small tube diameter makes the heat exchanger both economical
and compact. However, it is more likely for the heat exchanger to foul up
faster and the small size makes mechanical cleaning of the fouling
difficult. To prevail over the fouling and cleaning problems, larger tube
diameters can be used. Thus to determine the tube diameter, the available
space, cost and fouling nature of the fluids must be considered.
12
heat exchangers are usually cheaper when they have a smaller shell
diameter and a long tube length. Thus, typically there is an aim to make
the heat exchanger as long as physically possible whilst not exceeding
production capabilities. However, there are many limitations for this,
including space available at the installation site and the need to ensure
tubes are available in lengths that are twice the required length (so they
can be withdrawn and replaced). Also, long, thin tubes are difficult to
take out and replace.
refers to how tubes are positioned within the shell. There are four main
types of tube layout, which are, triangular (30°), rotated triangular (60°),
square (90°) and rotated square (45°). The triangular patterns are
employed to give greater heat transfer as they force the fluid to flow in a
more turbulent fashion around the piping. Square patterns are employed
where high fouling is experienced and cleaning is more regular.
baffles are used in shell and tube heat exchangers to direct fluid across
the tube bundle. They run perpendicularly to the shell and hold the
bundle, preventing the tubes from sagging over a long length. They can
also prevent the tubes from vibrating. The most common type of baffle is
the segmental baffle. The semicircular segmental baffles are oriented at
180 degrees to the adjacent baffles forcing the fluid to flow upward and
downwards between the tube bundle. Baffle spacing is of large
thermodynamic concern when designing shell and tube heat exchangers.
Baffles must be spaced with consideration for the conversion of pressure
drop and heat transfer. For thermo economic optimization it is suggested
13
that the baffles be spaced no closer than 20% of the shell's inner diameter.
Having baffles spaced too closely causes a greater pressure drop because
of flow redirection. Consequently, having the baffles spaced too far apart
means that there may be cooler spots in the corners between baffles. It is
also important to ensure the baffles are spaced close enough that the
tubes do not sag. The other main type of baffle is the disc and doughnut
baffle, which consists of two concentric baffles. An outer, wider baffle
looks like a doughnut, whilst the inner baffle is shaped like a disk. This
type of baffle forces the fluid to pass around each side of the disk then
through the doughnut baffle generating a different type of fluid flow.
14
between the two is that plate exchangers typically serve low to medium
pressure fluids, compared to medium and high pressures of shell and tube.
A third and important difference is that plate exchangers employ more
countercurrent flow rather than cross current flow, which allows lower
approach temperature differences, high temperature changes, and
increased efficiencies.
Plate and fin heat ex-changers are usually made of aluminium alloys,
which provide high heat transfer efficiency. The material enables the
system to operate at a lower temperature difference and reduce the weight
of the equipment. Plate and fin heat ex-changers are mostly used for low
temperature services such as natural gas, helium and oxygen liquefaction
15
plants, air separation plants and transport industries such as motor
and aircraft engines.
The main advantage of the SHE is its highly efficient use of space. This
attribute is often leveraged and partially reallocated to gain other
16
improvements in performance, according to well known trade offs in heat
ex-changer design. (A notable trade off is capital cost vs operating cost.)
A compact SHE may be used to have a smaller footprint and thus lower
all-around capital costs, or an oversized SHE may be used to have
less pressure drop, less pumping energy, higher thermal efficiency, and
lower energy costs.
17
1.6 DISADVANTAGES OF TiO2 :
There are also some potential disadvantages to titanium, one of which is
the difficulty of casting. Unlike iron and aluminium, titanium can not be
easily cast. If you are looking for cast metals, it’s best to choose a
different metal instead of titanium. So, why can’t titanium be cast? Again,
this has to do with its strength. Because it’s so strong, titanium can not be
easily cast like aluminium or iron.
It’s also worth mentioning that titanium is generally more expensive than
other types of metals. When compared to steel, iron, aluminium, etc., you
can expect to pay more for titanium. This is due largely to its rarity.
While not necessarily considered “rare,” titanium is rarer than other
metals, resulting in a higher selling price.
The bottom line is that titanium has both advantages and disadvantages.
It’s strong, durable and naturally resistant to rust and corrosion. At the
same time, however, it cannot be cast like aluminium or iron, and it tends
to cost more than other metals.
18
CHAPTER 2
MANUFACTURING PROCESS
2.1.1 Roasting
Raw limonite is fed at the rate of 65.9 Ton/Hr with 100C petroleum
coke into a rotating kiln called roaster. The ferric oxide in raw ilmenite is
first subjected to high temperature reduction to ferric oxide in presence of
petroleum coke at a temperature of 900 to 950OC. The reduced limonite is
discharged through a rotary cooler having cooling water tubes and
collected in a hopper.
19
Reaction
Fe2O3 + C → 2FeO + CO
Fe2O3 + CO → 2FeO + CO2
2.1.4 Calcination
Leaching ilmenite is fed into calciner at the rate of 4 to 6 T/Hr through
screw feeder where it is calcined at 500 – 550oC to remove moisture and
20
volatile matter. The material is cooled by draft in the cooler. The cooled
beneficiated ilmenite is screened and stored in the BI go down through
bucket elevator and belt conveyor.
21
water is continuously added in a scrubber and continuously Blunt to a
liquid storage tank.
22
charged to the chlorinators through the side nozzles above the chlorinator
bed.
During initial start up, when air ( 1200Nm3/hr) is fed through the bed
nozzles the material above the bed will be in a fluidized condition and the
temperature will rise gradually. When the temperature reaches 200oC Pet.
Coke will be fed continuously to build up the level up to 40%. BI is fed to
the chlorinator when the temperature reaches 600oC and the level is build
up to 80%. Before feeding Cl2 gas the composition of bed to be ensured
between 45 to 55%. When the chlorinator exits gas temperature reaches
700 to 950oC chlorine can be fed to chlorinators through the dished end.
The temperature of Cl2 from vaporizer must be a minimum of 50oC. The
reaction will take place and TiCl4 vapor produced will come out through
the cross over pipe and then to the cyclone. The temperature of TiCl4 at
cross over pipe is reduced to 180 to 2000C by spraying cooled TiCl4
inside the crossover pipe. The cooled gas will then pass through the
condensation section and the unreacted ore plus other metallic chlorides
are collected at the cyclone bottom and then pumped to ENP.
The gas from the cyclone enters the condensing column bottom and
crude TiCl4 cooled in water cooled heat exchangers ( E204 A/B) enters
from the top and condensed the upward flowing gas. The crude TiCl4 then
flows by gravity to quench surge tank (F.204) and from that to crude
TiCl4 surge tank (F.205).
23
exigency. The vent gas from scrubbing system connected with a blower
and dilution air fan draws the gas to atmosphere.
24
Pure tickle from tickle storage tank is pumped using transfer pumps
(G-235, G-236) through a heater (E-323) at a temperature of 120oc to
1350c. Aluminum chloride dissolving tank (D-303) from which the feed
material for the further process is drawn. Quantity of AlCl3 to be added
varies for different grades of raw pigment produced. Aluminum chloride
is added for enhancing nucleation reaction.
Tickle and AlCl3 solution from D-304 is taken to tickle feed vaporizer
E301, E302) where it is vaporized using steam in nickel tube bundle and
vapor is send to the tickle pre-heater at a temperature of 145oC to 195oC
through glass lined pipe in the tickle pre-heater this vapour is preheated to
330oC to 370oC using burners Oxygen from oxygen plant is preheated to
940oc to 980oc in the oxygen pre-heater and send to the oxidizer where
LPG is injected and this LPG in presence of heated oxygen forms a flame.
Then the pre-heater tickle vapor is admitted into the oxidizer
where the TiCl3 + AlCl3 vapor reacts to produce TiO2 pigment particles
and chlorine silica sand also fed into the oxidizer to craze the pigment
from downstream cooling tube side. Potassium chloride is injected
downstream.
25
tank from there slurry is pumped to product classifier S41 A/B/C. product
classifier separates 5 microns particles as overflow for treatment and
slurry is stored in treatment feed tank F414
2.5.1 Treatment:
In treatment various chemicals such as sodium silicate, sodium
aluminate etc. are added which when neutralized with caustic soda
or sulphuric acid from hydrous oxides. Hydrous oxide particles are very
small compared to titanium dioxide particles and trend to coat individual
pigment particles.
Treatment is done in F415 A or B tank on basis. This tank is provided
with steam spurger and agitator having two seeds (20 rpm & 30 rpm).
UsingG417 A&B pumps required quantity of raw slurry is pumped to
treatment tank. Required quantity of filtrate is taken in the tank using G42
pump. The treatment chemicals from U500 are connected to F415 A/B
tank. After batch treatment is connected the whole contents are
transferred to F418.
26
the tunnel drier conveyor. Macroni is carried into the drying chambers by
the conveyor. As the pigment passes through the drier, it loses the
moisture and pigment is discharged to the vibrating conveyor C417. At
this stage moisture content will be less than 1% and organic addition is
sprayed at the discharge of the conveyor. The macroni is stored in F425
through bucket elevator C418 and screw conveyor C428.
2.5.3 Larox:
The slurry from the filter feed tank (F418) is pumped to the slurry tank
(F418) in the laroxsection, using the pump G423B. The pressure
filtration process is done on the basis. In a single batch, 4.5 m3of slurry is
fed into the filter press (PF706). The slurry from the slurry tank (F1418)
is pumped to filter press using the slurry feed pump (G1423). In the
pressure filter the slurry is introduced in the cavity region of the filter
press and air is introduced into the diaphragm above, which creates a
pressure inside removing water content along the pigment particles. The
cake thus formed from the filter press is the feed vat (F1404) using the
belt conveyor C1402. The cake from feed vat is conveyed to the drying
chamber with screw conveyor. In the drying chamber the containing 30%
moisture is reduced to less than 1% moisture content using the heated air
from the burner chamber (500-600oc) and equally distributed to the
pigment particles using the agitator inside the drying chamber
(G1403A). Trimet (600 cc/min) is sprayed into the drying chamber for
the better dispersion of pigment particles. From the drying chamber the
pigment particles are carried to the cyclone. In the cyclone the particles
having higher density will be settle on the bottom of the cyclone (S1410)
and passes on the screw conveyor (S1417A). The escaping fine particles
is collected from the bag filter is passed on the screw conveyor and
forwarded to the screw conveyor D1417 and S1417B. The pigment from
27
the screw conveyor C1417A, C1417 and C1417B is fed to the bucket
elevator (C1418) which carries it to the screw conveyor (C428) and
ultimately to micronized feed tank F425. The flue gas is blown out
through the exhaust to atmosphere.
1. Boiler plant
2. Water treatment plant
3. Air compressor station
4. Effluent compressor station
28
5. Furnace oil reception storage
2.6.1.Boiler plant
Our boiler house equipped with 2 Nos. of water tubes boilers and one no.
fire tube boiler for supplying steam to production plant
The boiler was originally designed for coal/oil fired with spreader stoker
and feeder with an economiser. This is steel cased, thin wall two-drum
integral type water tube boiler with natural circulation and balanced draft.
The exit fuel gas passes through the economiser and outlet gases into
atmosphere through chimney by means of ID fans. After dearation the
feed water is supplied in stream drum through economizer using
multistage pump.
The economizer water flows through integral bare type parallel tubes for
picks up the heat from the fuel gas. Water in the steam drum is circulated
to the mud drum via main bank tubes, from the mud drum is distributed
to evaporator main bank tubes and rest to the combustion chamber wall
via down comer pipes and manifold.
29
A steam/water mixture is returned by natural circulation to the steam
drum. This is fitted with internal baffles and cyclone separator for
separating steam water mixture then the steam is purified by passing
through the scrubber box mounted on the top of the cyclone. From the
steam drum, saturated steam is conveyed to saturated collecting header
and distributed to the production plants via common distributed header .
Part of the steam from the drum goes to super heater. The superheated
coils are suspended in the horizontal draught between combustion
chamber and the heat recovery surfaces. There are 15 Nos. of coils and
finally collected in super heated steam collecting header and distributed
to U-400 via common distribution header.
30
Max working pressure :- 20 kg/cm2
Our source water is tube wells; we have 13 Nos of tubes well with a draw
capacity of 40 M3 /hr each. The plant has been designed to produce
560M3/hr filtered water. Process of treatment is aeration, flocculation,
clarification and filtration.
Filtered water is drawn from the filtered water storage tank with the help
of centrifugal pump and supplying to different plants overhead tanks and
DM unit. 5 Nos cooling water pumps are used to circulate the cooling
water and 2 Nos of cooling towers are provided for cooling the hot water.
31
The hot water coming from various plants sent through the induced
vertical cross flow cooling tower cells and cooled water is collected in the
cold sump. We have a demineralization plant to produce DM water; it is
used in U400 U300 and boiler plant. The DM water plant consist of 3
Nos. strong acid and alkali storage tanks with connected pipe lines.
A fire and drinking water supply network in the factory. The whole plant
is connected with fire and drinking water meet the sanitary requirements
as well as drinking purpose and fire fighting. The fire and drinking water
supply and emergency water to U300& boiler provide by the over headed
tanks and welfare activities
32
if PH value is in the range 5 to 9. All statutory rules and regulations are
applicable while doing the operation.
33
CHAPTER - 3
MATERIAL BALANCE
34
TiCl4 + O2 TiO2 + 2Cl2
From stoichiometry
1 mole of TiCl4 + 1 mole of O2 1 mole of TiO2 + 2 mole of Cl4
= (1000×189.88)/79.88
= 2.377 tons
Oxygen required for production of 1 Ton of TiO2= (1000 × mol.wt of
O2 )/
( mol. wt of TiO2 )
= (1000 × 32)/79.88
= 0.4006 tons
35
CHAPTER - 4
ENERGY BALANCE
Hot fluid
Cold fluid
36
4.2 HEAT GAIN
= 91712.998 W
= 1.691 × 1.798 × ( 60 - 30 )
=91487.634 W
Hence Q = Qh = Qc
37
91712.998 = 91487.634
38
CHAPTER 5
DESING OF EQUIPMENTS
In this chapter we are going to see about the design of shell and tube
heat ex-changer and spiral heat ex-changer which has been used to
increase the efficiency of the product that has been produced in the
industry for long period of time.
cold
water IN
31oC
Tickle IN (Th1)
85 – 90oC
39
Mass flow rate of hot fluid = 290
Mass flow rate of cold fluid = 100
Specific heat of hot fluid = 0.795
Specific heat of cold fluid = 4.18
Ch => mn Cph => 290 × 0.795 = 230.55 [ Cmin]
Cc => mn Cpc => 100 × 4.186 = 418.6 [ Cmax]
Efficiency
Tickle OUT ?
Water cold water
30 – 32oc 90C
Water OUT
31oC
Tank-1 SHE
85 – 90oC
Tickle IN
40
5.1.1.1 CASE : 1
Flow rate of H2o = 100 m3 (m2w)
Temperature of H2o out from tank 1 = [ Tc1 ] ?
Temperature of cold H2o = 9oC [ Tc2]
Temperature of water in = 31 [ Tf1 ]
Specific heat of water Cp = 4.18 joule/gram oC
Let us assume that flow rate of cold H2O is ( mc ) = 5 m3 ( mc T )
Mh cph ( Tc1 – Tf1 ) = mc cpc ( Tf1 – Tc2 )
100 ( Tc1 – 31 ) = 5 ( 31 – 9 )
100 ( Tc1 – 31 ) = 110
Tc1 – 31 = 1.1
Tc1 = 32.1
Tc1 = 320 C
To find outlet temperature of Tickle
Flow rate of tickle ( mht ) = 290 m3
Specific heat of tickle ( Cpn T ) = 0.795 joule/ gmo C
Inlet temperature of tickle ( Th1 ) = 900C
Outlet temperature of tickle ( Th2 ) = ?
Flow rate of H2O ( mc w) = 100
Specific heat of H2O ( Cpc w ) = 4.18 joule/gmoc
Inlet temperature of H2O ( Tf1 ) = 310 C
Outlet temperature of H2O ( Tf2 ) = 45o C
Mht Cpht ( Th1 – Th2 ) = Mc w Cpc w ( Tf2 – Tf1 )
290 × 0.795 ( 90 – Th2) = 100 × 4.18 ( 45 – 31 )
230.55 ( 90 – Th2 ) = 418 × 14
90 – Th2 = 5852 / 230.55
90 – Th2 = 25.38
41
Th2 = 640C
Efficiency :
E = C max ( Th1 – Th2 ) / C min ( Th1 – Tf1 )
E = 418 ( 90 – 64 ) / 230 ( 90 – 31 ) = 10,868 / 13,570
E = 80.08 %
5.1.1.2 CASE 2 :
Flow rate of H2O = 100 m3 ( mL w )
Temperature of H2O from Tank 1 = [ Tc1 ]
Temperature of cold H2O = 9o C [ Tc2 ]
Temperature of water IN = 30 [ Tf1 ]
Specific heat of water Cp = 4.18 joule / gram oC
Let us assume flow rate of H2O is ( mc ) = 5 m3 ( mct )
mh cph ( Tc1 – Tf1 ) = mc Cpc ( Tf2 – Tc2 )
100 ( Tc1 – 30 ) = 105
Tc1 – 30 = 105/100
Tc1 = 31oC
42
mh T Cph T ( Th1 – Th2 ) = mc w Cpc w ( Tf2 – Tf1 )
290 × 0.795 ( 90 – Th2 ) = 100 × 4.18 ( 45 – 30 )
230.55 ( 90 -Th2 ) = 4.8 ( 45 – 30 )
90 – Th2 = 6270 / 230.55
Th2 = 630C
Efficiency :
E = Cmax ( Th1 – Th2 ) / Cmin ( Th1 – Tf2 )
= 418 ( 90 – 65 ) / 230.55 ( 90 – 30 )
= 11286 / 13800
E = 81.78 %
5.1.1.3 CASE : 3
Flow rate of H2O = 100 m3
Temperature of H2O from tank 1 = [ Tc1 ] ?
Temperature of cold H2O = 9oC [ Th2 ]
Temperature of water inlet = 27 [ Tf2 ]
Specific heat of H2O Cp = 4.18 joule/ gmoC
Let us assume flow rate of H2O is ( wc T )= 5 m3
Mh Cph ( Tc1 – Tf1 ) = mc Cpc ( Tf1 – Tc2 )
100 ( Tc1 – 27 ) = 5 ( 27 – 9 )
100 ( Tc1 – 27 ) = 90
Tc1 – 27 = 0.9
Tc1 = 28
To find outlet temperature of Tickle
Flow rate of Tickle ( cm h T ) = 290 m3
Specific heat of tickle (Cp h T) = 0.795 joule/gmoC
Tickle inlet ( Th1 ) = 90oC
43
Tickle outlet ( Th2 ) = ?
Flow rate of water ( mc w ) = 100 m3
Specific heat of water ( mc w) = 4.18 joule/ gmoC
H2O inlet ( Tf1 ) = 27o C
H2O outlet ( Tf2 ) = 45oC
mnT Cpn T (Th1 – Th2 ) = mc w Cpn W ( Tf2 – Tf1 )
290 × 0.795 ( 90 – Th2 ) = 100 × 4.18 ( 45 – 27 )
230.55 ( 90 – Th2 ) = 418 ( 45 – 27 )
90 – Th2 = 7524 / 230.55
Th2 = 57oC
Efficiency :
E = Cmax ( Th1 – Th2 ) / Cmin ( Th1 – Tf2 )
= 418 ( 90 – 57 ) / 230 ( 90 – 27 )
= 13794 / 14490
E = 95 %
Since case 3 yields the maximum efficiency, now calculating the flow
rate of cold water inlet in tank 1
At Temp 30oC
mh T Cp T ( Tc1 – Tf2 ) = mc w Cpn w ( Tf1 – Tc2)
mh T = 100 cm3 ; Cph T = 100 ; Tc1 = 30 ; Tc2 = 27 ;
mcw = ? ; Cp n T = 100 ; Tf2 = 30 ; Tf1 = 9 .
AT temperature 300C
TC1 = 300
100 ( 30 – 27 ) = mc ( 30 – 9 )
300 = mc × 21
mc = 14.28 m3
AT temperature 31oC
44
Tc1 = 31
100 ( 31 – 27 ) = mc ( 31 – 9 )
400 = mc × 22
mc = 18.18 m3
AT temperature 320C
TC1 = 32
100 ( 32 – 27 ) = mc ( 32 – 9 )
500 = mc × 23
mc = 21.73 m3
45
5.1.2.2 MATERIAL SELECTED FOR THE SHELL
SA516 GR 70 is a material standard accepted all over the
global for steel plates.
It is primarily intended for use in welded pressure vessels where notch
toughness is important. The grade covers a range of tensile strength from
50 – 90Mpa
Carbon = 0.27 – 0.31%
Manganese = 0.79 – 1.3%
Phosphorous = 0.035%
Sulphur = 0.035%
Silicon = 0.13-0.45%
The ASME equivalent of P355NH grade is SA 516 GR 70
Tensile strength (N/mm2) = 510/650
Yield stress/min (N/mm2)= 355
E= 34.2 Gpa
No. of TUBES :
Q=U A LMTD
1541.54 × 10-3 = 200.73 × × D × L × N × LMTD
N = 1541.54 × 103 / (200.73 × × 0.0254 × 4.94 × 72.305)
= 269.43 tubes
= 270 tubes
IS2062
Density – 7850 kg/m3
Mild steel with carbon 0.20% to 0.23% and alloying element. It is used
in fabrication.
46
5.1.3 Design of shell and tube
47
5.2 SPIRAL HEAT EXCHANGER
5.2.1 SPIRAL HEAT EXCHANGER DATA :
Heat transfer on the hot side can be calculated as
Q = mh ch (Thi – Tho)
Heat transfer rate on cold side can be calculated as
Q = mc cc (Tco – Tci)
The over all heat transfer coefficient is obtained from
U = Q / ( A × LMTD )
Table 5.2 input data for hot and cold fluids of spiral plate heat
ex-changer
Fluid Flow rate Specific heat Inlet temperature
(kg/s) (KJ/kg) (oC)
Tickle 3.475 185.22 90
Water 3.475 0.795 31
5.2.2 CALCULATION
Q = mh ch (Thi – Tho)
m= mass flow rate = 12500 kg/hr 3.472 kg/sec
Specific heat of vaporization of TiCl4 = 8.4Kcal/mole
Qh = 3.472 × 8.4 × ( 90 – 70 )
= 583.8 KJ/hr
Q = mc cc (Tco – Tci)
m=mass flow rate = 12500kg/hr 3.472kg/sec
Cp= specific heat of liquid = 37.53cal/oC mol=0.795kJ/kg K
Qc = 3.472 × 0.795 × ( 45 – 31 )
= 38.67 KJ/hr
Q = Qh + Qc
48
= 583.8 + 38.67
Q = 622.47 KJ/hr
U = Q / ( A × LMTD )
49
A = 622.47 / 35.9 × 41.923
= 0.413 m2
50
5.2.3 Design of spiral tube heat ex-changer
51
CHAPTER 6
EXCISTING HEAT EXCHANGER
52
The dimensional parameter of the existing heat exchanger
were gathered from the plant (U-200). Theoretical design was done for
existing heat exchanger using correlation & formulas obtained from
machine design book.
Objective of comparative study.
1. By conducting comparative study, its necessitates the design of a
new heat exchanger.
2. In order to compare the dimensional values of existing heat
exchanger to the values obtained after calculations.
3. In order to check the reliability of the equation, formulas, constants
values used.
Heat Transfer in a Shell and Tube Heat Exchanger
Hot side fluid (tube) : TiCl4 at 150oC to 40oC
Cold side fluid (shell) : Water at 36oC
Mass flow rate of TiCl4 : 12500 Kg/hr
Boiling point of TiCl4is 136oC. Therefore the heat transfer process inside
tube can be explained by dividing it into three zones.
Zone 1: Heat Transfer at vapour state i.e. from 150oC to 136oC
Zone 2: Heat Transfer at boiling point i.e. at 136oC
Zone 3: Heat Transfer at liquid state i.e. from 150oC to 40oC
Lets Q1, Q2, Q3 be the heat transfer at zone 1, 2 and 3
Then total heat transfer Q=Q1 + Q2+ Q3
Q1=m Cp ∆T
m= mass flow rate = 12500 kg/hr 3.472 kg/sec
Cp= specific heat of vapour = 24.3 cal/oC mol
=0.5364 J/oCg
=0.535 KJ/Kg K
53
150oC
136oC
40oC
40oc
36oC
300c
Therefore, Q1=3.472×0.535×14=26.033 kJ
Q2= m× latent heat of vaporization of TiCl4 at 136oC
Latent heat of vaporization = 8.4Kcal/mole = 185.22KJ/kg
Therefore, Q2 = 3.4728×185.22
= 643.084kJ
Q3=m×Cp×∆T
m=mass flow rate = 12500kg/hr 3.472kg/sec
Cp= specific heat of liquid = 37.53cal/oC mol=0.795kJ/kg K
∆T= temperature difference = 136 - 40 = 96oC
Therefore, Q3=3.472×96×0.795=265Kj
Thermal Duty Q=Q1 + Q2 + Q3 = 26.033+643.084+265
= 934.1kJ/hr
54
6.3.1 To find hi
Reynolds number:- Re=ρvd/μ
=4m/ Dμ
=8720214.114
Assuming that all the heat from hot fluid is transferred to cold fluid
Qh(TiCl4) = Qc (water)
Qh=934.12 kJ/sec
Qc=mc × CP × ∆T
55
∆T=40-31=90C
Cp=4.186kJ/kg K
Qh=Qc=mC × 4.186 × 9=934.12
mC=934.12/ (4.186×9)
=24.794kg/sec
Therefore according triangular to effectiveness, the mass flow rate of cold
fluid should be greater than 25kg/sec
6.3.2 To find ho
For 60o equilateral triangle arrangement
De=8[0.43p2-0.5 (d102)/4]/ d10/2
Here P, pitch = 31.5mm=1.25inch,d10, diameter of tube=1 inch
De =8[0.43(1.25)2-0.5 (12/4)]/
=2.233 inch =0.056m
Clearance, c=P-d10=1.25-1=0.25 in=6.25cm
Flow area of tube bundle as,
as=(DS × c × B)/ (P× 144 × 1000)
B-Distance between baffles=L/no: of baffles
=4940/18=274.4mm
Ds=485mm(from sheet)
as=(485× 6.25 × 274.44)/ (31.5 × 144 × 1000)
=0.1834m2
Gs=mass flow rate of cold fluid
=mc/as
mc=25kg/sec
Gs=25/0.1834
=136.3kg/m2 sec
Reynolds No: Re= DeGs/μ
56
=(0.056 × 136.3)/ (233.415 × 10-6)
=32703.93
57
Substituting all the values
3362821.2 × 1000/3600= 78.87 × × 72.305 × 0.0254 × L × 184
L=4.92m
The present length of tube is 4.94m which is approximately equal to the
value obtained (4.92m).
On comparing the dimension of existing heat exchanger with values
obtained using calculation, it is inferred that:
1. Both the values are similar
2. The formulas and constant values are reliable for further designs.
58
CHAPTER 7
PROCESS ECONOMICS
7.1 Cost of Estimation
Cost of Alfa Lava heat exchanger = Rs.52500
Cost of one shell of Alfa Lava = Rs.4200
Cost of GEO Eco flux = Rs.556000
Cost of one shell used in Alfa Lava heat exchanger = Rs.4150
Number of Tubes used in Alfa Lava heat exchanger = Rs.270
So Total cost of Alfa Lava heat exchanger = 270 × 4200 = Rs.11,34,000
59
7.2 MAINTENANCE COST
Per hour loss = Rs.35,000
Total time = 8 hrs for cleaning
Labor = 5 people Rs.150/hr
Considering two heat exchangers, there would be four maintenance
schedules, two for each heat exchanger.
So downtime loss would be = 8 × 4 = 32 hrs
Per hour loss is assumed by Rs. 50,000
So for 8 hrs Rs.35000 × 32 = Rs.11,20,000
Considering new heat exchanger, there would be an average of 3
maintenance schedules.
So down time loss would be 8 × 3 = 24hrs
Per hour loss is assumed to be Rs.35000 × 24 = Rs.840000
60
CONCLUSION
As the conclusion, the objective of this experiment is to increase
the rate of efficiency of heat exchanger which as been using on the plant.
our aim is to increase the efficiency of shell and tube heat exchangers
without change in the no. of tubes and not by increasing their tube
diameters and another equipment named spiral heat exchanger, so that it
would be helpful to the industry. We have increased the efficiency of the
shell and tube heat exchanger by decreasing the standard temperature of
the inlet water. We have decided to decrease the ambient temperature by
placing a cooler on the inlet of water and that rises the rate of efficiency
of shell and tube heat exchanger. Then we have designed a spiral heat
exchanger which is very useful and the cost of the product is low. The
spiral heat exchanger has a backwash which makes the cleaning process
simple and the way of operation is easy, this is less complicated than shell
and tube heat exchanger. The objectives of the experiments are achieved.
61
REFERENCE :
62
9. Hewitt G, Shires G, Bott T (1994), Process Heat Transfer, CRC
Press Inc, Florida.
10. Table: Various Types of Gas – Liquid Direct Contact Heat
Exchangers (Hewitt G, Shires G & Bott T, 1994)
11. Kee Robert J.; et al. (2011). "The design, fabrication, and
evaluation of a ceramic counter-flow microchannel heat
exchanger". Applied Thermal Engineering. 31 (11):
2004–2012. doi:10.1016/j.applthermaleng.2011.03.009.
12. Northcutt B.; Mudawar I. (2012). "Enhanced design of cross-flow
microchannel heat exchanger module for high-performance aircraft
gas turbine engines". Journal of Heat Transfer. 134 (6):
061801. doi:10.1115/1.4006037.
13. Moallem E.; Padhmanabhan S.; Cremaschi L.; Fisher D. E. (2012).
"Experimental investigation of the surface temperature and water
retention effects on the frosting performance of a compact
microchannel heat exchanger for heat pump
systems". 171–186. doi:10.1016/j.ijrefrig.2011.08.010.
14. Xu, B., Shi, J., Wang, Y., Chen, J., Li, F., & Li, D. (2014).
Experimental Study of Fouling Performance of Air Conditioning
System with Microchannel Heat Exchanger.
15. "MICROCHANNEL TECHNOLOGY" (PDF). Archived from the
original (PDF) on June 4, 2013.
16. Patent 2,046,968 John C Raisley issued July 7, 1936; filed Jan. 8,
1934 [1]
63
64